Kuda kuda
1.a. Balok 10/10 l1 0.1 m Btg 3m 34.00 bh
l2 0.1 m V 1.02 m3
A 0.01 m2
1 kk 2 bh
n kk 4 bh
8 bh
p 3m
jumlah 24 m
A 0.0072 m2
V 0.1728 m3
p 12 m
n 10 bh
jumlah 120 m
40 btg
A 0.01 m2
V 0.4 m3
p1 3.5 m
n 6 btg
A 0.006 m2
V 0.126 m3
L p1 papan bh
Papan Nok 12 2 6 bh
Papan Lisplank 24 2 12 bh
Jumlah 36 m 18 bh
A 0.006 m2
V 0.216 m3
Sisi 1 5 12 60 m2
Sisi 2 5 12 60 m2
Jumlah 120 m2
l 1.5 m
n 12 bh
V 0.18 m3
3. Pasangan Bata 1m 26 m
p 9 m
l 6 m
A 54 m2
A.028 Rabat beton tebal 2,5 cm m2 65,635
Pekerja oh 0.12 80,000 9,600
Tukang batu oh 0.06 80,000 4,800
Kepala tukang oh 0.01 80,000 960
Mandor oh 0.01 80,000 400
Semen kg 12.00 1,500 18,000
Pasir beton m3 0.03 250,000 6,875
Seplit 1x2 m3 0.04 250,000 10,000
Air ltr 100.00 150 15,000
RENCANA ANGGARAN BIAYA
Project : Villa Pildun
Tahun : 2018
No
1 Galian Pondasi (Bata Rollag) <m3> 30,000
Bahan Upah
Borongan 1 m3
Harsat
Galian Pondasi (Bata Rollag) 26 m 6.5 m3
Bahan + Upah
30,000 30,000 30,000
20,000 64,250
20,000 109,900
5,000 25,375
8,000 98,750
16,000 92,770
Lisplank 3/20 22 m 11,700
Bahan + Upah
4,000 5,000
5,000 16,700
4,000 27,900
4,000 30,000
15,000 29,600
25,000 92,500
Harga Bahan Harga Upah Jumlah Harga