FLOWCHART PENGAWASAN KONSTRUKSI

SPECIAL FACILITY SUTT KALBAR-1 (2X100MW) 150kV SINGKAWANG


SUBSTATION EXTENSION PROJECT
PLN UIP PLN UPP KBB 3
SINGKAWANG GCL INDO TENAGA SEPCO
KALBAGBAR

ENGINEERING DESIGN
MULAI
SPECIAL FACILITIS

MEMBUAT SURAT
REVIEW DRAWING OLEH
PERMOHONAN REVIEW
BAGIAN PERENCANAAN PLN SUBMIT DRAWING DESIGN DRAWING KE PLN
UIP KALBAGBAR
UIP KALBAGBAR

DRAWING

Approve Drawing TIDAK OK

OK

MENERIMA
MENERIMA APPROVAL MENERIMA APPROVAL
APPROVAL KONFIRMASI DRAWING DRAWING
DRAWING

REVIEW DAN PERSETUJUAN


REVIEW DOKUMEN INTERNAL KONTRAKTOR PENG AJUAN DOKUMEN
UNTUK DI SUBMIT KE PLN

1. WP GARDU INDUK
2. WP PEKERJAAN TOWER
3. REQUEST FOR INSPECTION

APPROVAL
DOKUMEN
TIDAK OK

MENERIMA APPROVAL
OK DOKUMEN PERINTAH KERJA KONSTRUKSI

REVIEW DAN PERSETUJUAN


REVIEW RFI RFI INTERNAL KONTRAKTOR REQUEST FOR INSPECTION
UNTUK DISUBMIT KE PLN

1.FORM RFI
2.FORM CHECK LIST INSPECTION

APPROVE RFI TIDAK OK

OK

JOINT INSPECTION

APPROVAL JOINT
INSPECTION REPAIR

OK

SELESAI