A PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan 1 M Bouwplank AHSP PU A.2.2.1.4 90,501.70 1
2 Pembersihan 1 M2 Lapangan dan Perataan AHSP PU A.2.2.1.9 21,018.00 1
B PEKERJAAN TANAH
1 Galian Tanah Biasa Sedalam 1 Meter AHSP PU A.2.3.1.1 69,500.00 1
2 Galian Tanah Biasa Sedalam 2 Meter AHSP PU A.2.3.1.2 97,632.00 2
3 Galian Tanah Biasa Sedalam 3 Meter AHSP PU A.2.3.1.3 117,181.00 2
4 Mengurug Kembali Galian AHSP PU A.2.3.1.9 43,120.80 2
5 Memadatkan tanah (per 20 cm) AHSP PU A.2.3.1.10 59,890.00 3
6 Timbunan Tanah didatangkan Termasuk Perataan dan Pemadatan AHSP PU - T.14 E 251,990.00 3
7 Urugan Pasir AHSP PU A.2.3.1.11 241,594.00 3
8 Timbunan Tanah AHSP PU A.2.3.1.11.a 189,800.00 4
9 Pengurugan 1 M3 Sirtu AHSP PU A.2.3.1.14 282,161.00 4
C PEKERJAAN PASANGAN
1 Pondasi Batu Belah / Kali Campuran 1 : 4 AHSP PU A.3.2.1.2 952,925.00 4
2 Pasangan Batu Kosong ( Anstamping ) AHSP PU A.3.2.1.9 530,185.83 5
3 Pasangan 1 M3 Pondasi Cyclopen 60% Camp 1Pc:2PB:3Kr 40% Batu Belah AHSP PU A.3.2.1.10 1,266,179.69 5
4 Membuat Beton Mutu F'c = 7,4 Mpa (K 100), Slump (12 ± 2) cm, W/c = 0,87 AHSP PU A.4.1.1.1 1,172,838.95 6
5 Membuat Beton Mutu F'c = 9,8 Mpa (K 125), Slump (12 ± 2) cm, W/c = 0,78 AHSP PU A.4.1.1.2 1,223,657.20 6
6 Beton Mutu F'c = 14,5 Mpa (K 175), Slump (12 ± 2) cm, W/c = 0,66 AHSP PU A.4.1.1.5 1,159,826.29 7
7 Beton Mutu F'c = 16,9 Mpa (K 200), Slump (12 ± 2) cm, W/c = 0,61 AHSP PU A.4.1.1.6 1,310,603.70 7
8 Beton Mutu F'c = 19,3 Mpa (K 225), Slump (12 ± 2) cm, W/c = 0,58 AHSP PU A.4.1.1.7 1,389,317.89 8
9 Beton Mutu F'c = 21,7 Mpa (K 250), Slump (12 ± 2) cm, W/c = 0,56 AHSP PU A.4.1.1.8 1,411,682.74 8
10 Beton Mutu F'c = 24,0 Mpa (K 275), Slump (12 ± 2) cm, W/c = 0,53 AHSP PU A.4.1.1.8 1,450,168.39 9
11 Beton Mutu F'c = 26,4 Mpa (K 300), Slump (12 ± 2) cm, W/c = 0,52 AHSP PU A.4.1.1.8 1,462,098.50 9
D PEKERJAAN PEMBESIAN
1 Pembesian 1 Kg Dengan Besi Polos AHSP PU A.4.1.1.17 15,288.30 10
2 Pembesian 1 Kg Dengan Besi Ulir AHSP PU A.4.1.1.17.a 29,378.08 10
3 Memasang 1 Kg Jaring Kawat Baja / Wire Mesh AHSP PU A.4.1.1.19 21,518.59 11
E PEKERJAAN BEKISTING
1 Memasang Bekisting Untuk Pondasi AHSP PU A.4.1.1.20 72,340.34 11
2 Memasang Bekisting Untuk Sloof AHSP PU A.4.1.1.21 136,216.33 12
3 Memasang Bekisting Untuk Kolom AHSP PU A.4.1.1.22 170,723.67 12
4 Memasang Bekisting Untuk Balok AHSP PU A.4.1.1.23 170,723.67 13
5 Memasang Bekisting Untuk Plat Lantai AHSP PU A.4.1.1.24 264,872.00 13
6 Memasang Bekisting Untuk Dinding AHSP PU A.4.1.1.25 263,742.00 14
7 Memasang Bekisting Untuk Tangga AHSP PU A.4.1.1.26 145,996.00 14
8 Memasang Bekisting Untuk Jembatan Pengecoran AHSP PU A.4.1.1.27 109,610.00 15
G PEKERJAAN ALUMINIUM
1 Pemasangan Kusen Pintu Aluminum AHSP PU A.4.2.1.11 61,038.87 16
2 Pemasangan Rangka besi Hollow 40 x 40 x 2 mm AHSP PU A.4.2.1.20 101,361.00 17
H PEKERJAAN BATU BATA DAN PLASTERAN
1 Pasangan Dinding Bata ( 5 x 11 x 22 ) cm Tebal 1 Bata Camp. 1Pc : 2 PP. AHSP PU A.4.4.1.1 328,496.65 17
2 Pasangan Dinding Bata ( 4 x 10 x 20 ) cm Tebal 1 Bata Camp. 1Pc : 2 PP. AHSP PU A.4.4.1.1.a 354,260.65 18
3 Pasangan Dinding Bata Tebal 1 Bata Camp. 1Pc : 3 PP AHSP PU A.4.4.1.2 311,114.43 18
4 Pasangan Dinding Bata ( 5x11x22) cm Tebal 1 Bata Camp. 1Pc : 4 PP AHSP PU A.4.4.1.3 299,091.23 19
5 Pasangan Dinding Bata ( 4x10x20) cm Tebal 1 Bata Camp. 1Pc : 4 PP AHSP PU A.4.4.1.3.a 324,855.23 19
6 Pasangan Dinding Bata Tebal 1 Bata Camp. 1Pc : 5 PP AHSP PU A.4.4.1.4 293,336.70 20
7 Pasangan Dinding Bata ( 5x11x22) cm Tebal 1/2 Bata Camp. 1Pc : 2 PP AHSP PU A.4.4.1.7 158,078.53 20
8 Pasangan Dinding Bata ( 4x10x20) cm Tebal 1/2 Bata Camp. 1Pc : 2 PP AHSP PU A.4.4.1.7.a 170,960.53 21
9 Pasangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 3 PP AHSP PU A.4.4.1.8 149,654.38 21
10 Pasangan Dinding Bata ( 5 x 11 x 22 ) cmTebal 1/2 Bata Camp. 1Pc : 4 PP AHSP PU A.4.4.1.9 144,928.15 22
11 Pasangan Dinding Bata ( 4 x 10 x 20 ) cm Tebal 1/2 Bata Camp. 1Pc : 4 PP AHSP PU A.4.4.1.9.a 139,655.00 22
12 Pasangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 5 PP AHSP PU A.4.4.1.10 141,961.90 23
13 Pasangan Dinding Kerawang (Roster) Camp. 1 PC : 3 PP AHSP PU A.4.4.1.22 342,322.20 23
14 Pasangan Dinding Kerawang (Roster) Camp. 1 PC : 4 PP AHSP PU A.4.4.1.23 342,322.20 24
15 Plesteran 1 PC : 1 PP Tebal 15 mm AHSP PU A.4.4.2.1 92,148.11 24
16 Plesteran 1 PC : 2 PP Tebal 15 mm AHSP PU A.4.4.2.2 82,972.51 25
17 Plesteran 1 PC : 3 PP Tebal 15 mm AHSP PU A.4.4.2.3 79,080.79 25
18 Plesteran 1 PC : 4 PP Tebal 15 mm AHSP PU A.4.4.2.4 67,575.00 26
19 Plesteran 1 PC : 5 PP Tebal 15 mm AHSP PU A.4.4.2.5 74,904.31 26
20 Acian AHSP PU A.4.4.2.27 44,044.58 27
I PEKERJAAN LANTAI
1 Memasang Lantai Keramik Uk 40 x 40 cm AHSP PU A.4.4.3.34 259,103.92 27
2 Memasang Lantai Keramik Uk 20 x 20 cm AHSP PU A.4.4.3.36 246,388.59 28
3 Pasangan Keramik Lantai Uk. 33 x 33 cm AHSP PU A.4.4.3.34. 243,600.32 28
4 Pasangan Keramik Lantai Uk. 30 x 30 cm Pholished AHSP PU A.4.4.3.35. 301,898.71 29
5 Pasangan Keramik Lantai Uk. 30 x 30 cm UnPholished AHSP PU A.4.4.3.35.a 254,952.86 29
6 Pasangan Keramik Lantai Uk. 40 x 40 cm Pholished AHSP PU A.4.4.3.35.b 263,645.95 30
7 Pasangan Keramik Lantai Uk. 40 x 40 cm Pholished AHSP PU A.4.4.3.35.c 248,801.00 30
8 Pasangan Lantai Granit Tile Uk. 60 x 60 cm Pholished AHSP PU A.4.4.3.35.d 310,115.00 31
9 Pasangan Lantai Granit Tile Uk. 60 x 60 cm UnPholished AHSP PU A.4.4.3.35.e 310,115.00 31
10 Pasangan Keramik Lantai Uk. 20 x 20 cm UnPholished AHSP PU A.4.4.3.36 261,361.09 32
11 Pasangan Keramik Lantai Uk. 25 x 25 cm UnPholished AHSP PU A.4.4.3.36.a 264,567.47 32
12 Pasangan Plint Keramik Uk. 10 x 20 cm AHSP PU A.4.4.3.39 40,600.90 33
13 Pasangan Plint Keramik Uk. 8 x 25 cm AHSP PU A.4.4.3.39.a 99,485.20 33
14 Pasangan Dinding Keramik Uk. 20 x 25 cm AHSP PU A.4.4.3.54 298,835.28 34
15 Pasangan Dinding Keramik Uk. 20 x 45 cm AHSP PU A.4.4.3.54.a 304,824.28 34
16 Pasangan Dinding Keramik Uk. 20 x 40 cm AHSP PU A.4.4.3.54.b 372,511.28 35
17 Pasangan Dinding Batu tempel Hitam AHSP PU A.4.4.3.58 507,796.58 35
18 Pasangan Dinding Batu Alam AHSP PU A.4.4.3.58.a 507,796.58 36
19 Memasang Dinding Keramik Uk 20 x 20 cm AHSP PU A.4.4.3.54 274,879.28 39
20 Memasang Dinding Keramik Uk 20 x 40 cm AHSP PU A.4.4.3.54a 334,893.58 40
K PEKERJAAN KAYU
1 Membuat dan Memasang Kusen pintu dan Kusen Jendela, Kayu Kelas I AHSP PU A.4.6.1.1 10,132,879.50 44
2 Membuat dan Memasang Daun Pintu Panel Kayu Kelas II AHSP PU A.4.6.1.5 732,466.00 45
3 Membuat dan Memasang Daun Jendela Kayu Kelas II AHSP PU A.4.6.1.6 556,705.80 45
4 Memasang Jalusi Kusen, Kayu Kelas I AHSP PU A.4.6.1.10 787,304.90 46
5 Memasang Konstruksi Kuda-Kuda, Kayu Kelas I AHSP PU A.4.6.1.14 11,051,953.70 46
6 Memasang Konstruksi Gordeng, Kayu Kelas II AHSP PU A.4.6.1.15 5,453,244.40 47
7 Memasang Rangka Langit-Langit Kayu Kelas II AHSP PU A.4.6.1.20 125,836.80 47
8 Memasang Listplank Uk. 3 x 20 Cm Kayu Kelas I atau Klas II AHSP PU A.4.6.1.21 78,783.60 48
9 Memasang Kuda - Kuda Kayu Kelas I atau Klas II AHSP PU A.4.6.1.13 6,462,922.00 49
10 Memasang Gording Kayu Kelas I atau Klas II AHSP PU A.4.6.1.15 7,710,317.70 50
11 Memasang Listplank Uk. 2 x 20 Cm Kayu Kelas I atau Klas II AHSP PU A.4.6.1.21 69,720.00 50
12 Memasang Listplank Uk. 2 x 30 Cm Kayu Kelas I atau Klas II AHSP PU A.4.6.1.22 78,455.90 51
M PEKERJAAN SANITASI
1 Memasang Kloset Duduk/Monoblock AHSP PU A.5.1.1.1 2,672,325.70 54
2 Memasang Kloset Jongkok Porselen AHSP PU A.5.1.1.2 782,694.50 54
3 Memasang 1 Buah Urinoir AHSP PU A.5.1.1.4 2,192,426.00 55
4 Pemasangan 1 Bh Wastafel AHSP PU A.5.1.1.5 1,705,124.80 55
5 Memasang Floor Drain AHSP PU A.4.5.1.1.14 55,313.50 56
6 Pemasangan 1 Buah Bak Kontrol Bata 30x30 tinggi 35 cm AHSP PU A.5.1.1.15 507,505.60 56
7 Pemasangan 1 Buah Bak Kontrol Bata 45x45 cm tinggi 50 cm AHSP PU A.5.1.1.16 771,429.53 57
8 Pemasangan 1 Buah Bak Kontrol Bata 60x60 cm tinggi 65 cm AHSP PU A.5.1.1.17 921,633.65 57
9 Memasang Kran Air dia. 1/2" atau 3/4" AHSP PU A.4.5.1.19 74,523.50 58
N PEKERJAAN KACA
1 Memasang 1 m2 Kaca tebal 5 mm AHSP PU A.4.6.2.17 199,541.05 58
O PEKERJAAN PENGECATAN
1 Pengecatan Bidang Kayu lama AHSP PU A.4.7.1.4a 15,882.15 59
2 Pengecatan Bidang Kayu Baru (1 x plamir, 1 x cat dasar,2 x cat penutup) AHSP PU A.4.7.1.4 27,048.00 59
3 Pengecatan Tembok Baru (1 x plamir, 1 x cat dasar, 2 x cat penutup) AHSP PU A.4.7.1.10 23,816.70 60
4 Pengecatan Tembok lama (1 x cat dasar, 2 x cat penutup) AHSP PU A.4.7.1.11 34,303.18 60
LIMA RATUS TUJUH PULUH ENAM JUTA TIGA RATUS EMPAT PULUH TUJUH RIBU RUPIAH
DISETUJUI, DIKETAHUI,
KEPALA DESA TURUADAE KEPALA DESA PATTIMPA
………………………
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN MESJID
LOKASI : DUSUN LONRONG
KECAMATAN : PONRE
KABUPATEN : BONE
PROVINSI : SULAWESI SELATAN
TAHUN ANGGARAN : 2020
HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SAT ANALISA SATUAN HARGA
(Rp) (Rp)
1 2 3 4 5 6 7
A PEKERJAAN PERSIAPAN
1 Pembongkaran 1.00 Ls Taksir 5,000,000.00 5,000,000.00
Jumlah 5,000,000.00
B PEKERJAAN PEMBANGUNAN MESJID
I PEKERJAAN TANAH DAN PONDASI
1 Galian Tanah Pondasi 78.57 m³ AHSP PU A.2.3.1.1 69,500.00 5,460,281.40
2 Urugan Pasir bawah Lantai 26.13 m³ AHSP PU A.2.3.1.11 241,594.00 6,314,010.87
3 Timbunan Bawah Lantai 44.76 m³ AHSP PU A.2.3.1.11.a 189,800.00 8,496,207.20
Jumlah 20,270,499.47
II PEKERJAAN PASANGAN
1 Pas. Pondasi Batu Kali/batu Gunung 1 : 4 27.06 m³ AHSP PU A.3.2.1.2 952,925.00 25,790,081.32
2 Pasangan 1/2 Bata 1: 4 662.01 m² AHSP PU A.4.4.1.9.a 139,655.00 92,452,666.85
3 Plesteran 1 : 4 dan Acian 331.00 m² AHSP PU A.4.4.2.4 67,575.00 22,367,580.69
Jumlah 140,610,328.85
III PEKERJAAN BETON
1 Sloof 20/30
- Beton 3.26 m³ AHSP PU A.4.1.1.5 1,159,826.29 3,777,322.25
- Besi tulangan (Polos) 1,428.99 kg AHSP PU A.4.1.1.17 15,288.30 21,846,812.52
- Bekisting 38.00 m² AHSP PU A.4.1.1.21 136,216.33 5,175,675.80
2 Kolom 20/20
- Beton 3.60 m³ AHSP PU A.4.1.1.5 1,159,826.29 4,175,374.63
- Besi tulangan (Polos) 2,095.11 kg AHSP PU A.4.1.1.17 15,288.30 32,030,725.25
- Bekisting 72.00 m² AHSP PU A.4.1.1.22 170,723.67 12,292,104.00
3 Kolom Praktis 15/15
- Beton 0.18 m³ AHSP PU A.4.1.1.5 1,159,826.29 208,768.73
- Besi tulangan (Polos) 50.76 kg AHSP PU A.4.1.1.17 15,288.30 776,006.15
- Bekisting 2.08 m² AHSP PU A.4.1.1.22 170,723.67 355,105.23
4 Balok Ring Balk 20/20
- Beton 4.34 m³ AHSP PU A.4.1.1.5 1,159,826.29 5,036,429.66
- Besi tulangan (Polos) 1,445.06 kg AHSP PU A.4.1.1.17 15,288.30 22,092,471.90
- Bekisting 56.45 m² AHSP PU A.4.1.1.23 170,723.67 9,637,555.85
5 Cor Atap Plat Beton
- Beton 2.90 m³ AHSP PU A.4.1.1.5 1,159,826.29 3,365,073.59
- Besi tulangan (Polos) 129.76 kg AHSP PU A.4.1.1.17 15,288.30 1,983,758.39
- Bekisting 5.03 m² AHSP PU A.4.1.1.24 264,872.00 1,332,047.64
Jumlah 124,085,231.60
IV PEKERJAAN LANTAI
1 Rabat Beton Lantai, t = 5 cm 4.36 m3 AHSP PU A.4.1.1.5 1,159,826.29 5,051,971.34
2 Lantai Keramik 20 x 20 cm dinding WC 50.00 m2 AHSP PU A.4.4.3.36 261,361.09 13,068,054.50
3 Lantai Keramik 30 x 30 cm WC Kasar 50.00 m2 AHSP PU A.4.4.3.35. 301,898.71 15,094,935.50
4 Lantai Granit 60 x 60 cm 249.00 m2 AHSP PU A.4.4.3.35.d 310,115.00 77,218,635.00
Jumlah 110,433,596.34
V PEKERJAAN KUSEN, DAUN PINTU DAN VENTILASI
1 Kosen + Daun Pintu + Ongkos+ Accesoris Lengkap Terpasang 60.00 m² Taksir 750,000.00 45,000,000.00
Jumlah 45,000,000.00
VII PEKERJAAN ATAP
1 Rangka Kuda - Kuda Baja Ringan 118.00 m² AHSP PU A.4.5.2.32 230,485.00 27,197,230.00
2 Atap Seng spandek + talang luar + talang dalam 118.00 m² AHSP PU A.4.5.2.32 75,048.50 8,855,723.00
2 Alcopan (ACP) pinggiran atap 104.54 m' Taksir 300,000.00 31,362,000.00
Jumlah 92,590,829.55
VIII PEK. INSTALASI LISTRIK
1 Pemasangan Instalasi Listrik 1.00 Pkt Taksir 3,500,000.00 3,500,000.00
2 Instalasi Titik Penerangan, Instalasi termasuk kabel 30.00 Ttk Taksir 165,000.00 4,950,000.00
NYA 2,5 mm dalam Pipa PVC, Fitting dan
Kelengkapan Instalasi Terpasang
3 MCB (Terpasang)+Kabel Arde 1.00 Bh Taksir 140,000.00 140,000.00
4 Down Light + Lampu LED 8 Watt 30.00 Bh Taksir 125,000.00 3,750,000.00
5 Stop Kontak 30.00 Bh Taksir 28,000.00 840,000.00
6 Saklar 1.00 Bh Taksir 15,000.00 15,000.00
Jumlah 13,195,000.00
IX PEKERJAAN PENGECATAN
1 Pekerjaan Cat Dinding 662.01 m² AHSP PU A.4.7.1.10 23,816.70 15,766,835.63
2 Pekerjaan Cat Kayu/Minyak 60.00 m² AHSP PU A.4.7.1.4 27,048.00 1,622,880.00
Jumlah 17,389,715.63
X PEKERJAAN LAIN-LAIN
1 Batu Alam (Terpasang) 18.72 m² Taksir 335,000.00 6,271,870.00
2 Kubah Mesjid GRC Besar 1.00 bh Taksir 1,500,000.00 1,500,000.00
Jumlah 7,771,870.00
B. HARGA BAHAN
1 Air 65.00 / Liter
2 Atap Genteng Metal 0.30 52,400.00 / lbr
3 Bak Air PVC + Penutup Samping 350,000.00 / Unt
4 Batu Alam 335,000.00 / m2
5 Batu bata (Uk. 20 x 10 x 5 cm) 700.00 / bh
6 Batu bata (Uk. 18 x 10 x 3.5 cm) 760.00 / bh
7 Batu gunung/batu kali 227,000.00 / m3
8 Baut Reng 500.00 / bh
9 Baut Truss 500.00 / bh
10 Baja Profil 21,000.00 / kg
11 Besi beton polos 12,000.00 / kg
12 Besi beton ulir 22,200.00 / kg
13 Besi strip 5 mm 30,000.00 / kg
14 Besi Hollow 4 x 40 x 40 6,750.00 / m'
15 Besi Siku 40 x 40 x 4 17,500.00 / m'
16 Besi Baja IWF 11,000.00 / kg
17 Bon bon keramik 18,000.00 / m'
18 Cat dasar 18,000.00 / kg
19 Cat menie 25,000.00 / kg
20 Cat minyak 28,400.00 / kg
21 Cat plafond 22,000.00 / kg
22 Cat tembok 42,000.00 / kg
23 Dempul Kayu 18,000.00 / kg
24 Dolken Kayu ø 8-10/4 m 20,000.00 / btg
25 Downlight lampu 4 inch 68,000.00 / bh
26 Downlight lampu 5 inch 87,000.00 / bh
27 Engsel pintu 21,000.00 / bh
28 Engsel jendela 15,000.00 / bh
29 Floor Penutup Lantai 33,000.00 / bh
30 Furring Plafond 45,000.00 / Btg
31 Gebalan Rumput 20,000.00 / m2
32 Gypsum 9 mm 70,000.00 / lbr
33 Grendel pintu/jendela 27,000.00 / bh
34 Hak angin 29,000.00 / bh
35 Kain Kasa 32,500.00 / Rol
36 Kawat beton 20,000.00 / kg
37 Kayu komea 4,800,000.00 / m3
38 Kayu meuranti (Klas II) 2,800,000.00 / m3
39 Kayu klas III 2,500,000.00 / m3
40 Kaca bening 5 mm 140,000.00 / m2
41 Kaca reyband 5 mm 165,000.00 / m2
42 Kalsiboard 4.5 mm 63,000.00 / lbr
43 Kalsiboard 6 mm 70,000.00 / lbr
44 Kawat duri 4,500.00 / m
45 Kerikil 288,000.00 / m3
46 Kerikil 88.89 / kg
47 Keramik Lantai 60x60cm (polished) 135,000.00 / m2
48 Keramik Lantai 60x60cm (polished) 48,600.00 / bh
49 Keramik Lantai 40x40cm (polished) 75,000.00 / m2
50 Keramik Lantai 40x40cm (polished) 12,000.00 / bh
51 Keramik Lantai 40x40cm (unpolished) 89,500.00 / m2
52 Keramik Lantai 40x40cm (unpolished) 14,320.00 / bh
53 Keramik Lantai 30x30cm (polished) 60,000.00 / m2
54 Keramik Lantai 40x40cm (unpolished) 9,600.00 / bh
55 Keramik Lantai 25x25 (unpolished) 75,000.00 / m2
56 Keramik Lantai 25x25 (unpolished) 4,687.50 / bh
57 Keramik Lantai 20x20 (polished) 60,000.00 / m2
58 Keramik Lantai 20x20 (polished) 2,400.00 / bh
59 Keramik dinding 30x60 cm 26,500.00 / bh
60 Keramik dinding 20x40 cm 120,000.00 / m2
61 Keramik dinding 20x40 cm 12,000.00 / bh
62 Keramik dinding 20x25 cm 80,000.00 / m2
63 Keramik dinding 20x25 cm 4,000.00 / bh
64 Keramik dinding 10x20 cm 1,500.00 / bh
65 Kusen uPVC, t=5 cm + Daun Pintu/Jendela + Aksesories + Terpasang 1,300,000.00 / m2
66 Granit Lantai 60x60 cm 87,000.00 / bh
67 Granit Lantai 80x80 cm 280,000.00 / m2
68 Kloset jongkok keramik (setara KIA) 350,000.00 / bh
69 Kloset duduk keramik (setara KIA) 1,800,000.00 / bh
70 Koral Beton 125,000.00 / m3
71 Kunci tanam 2 slaag 175,000.00 / bh
72 Kran air 3/4" 50,000.00 / bh
73 Kertas Amplas 5,000.00 / lbr
74 Lampu HE 23 Watt 35,000.00 / bh
75 Lampu HE 28 Watt 42,000.00 / bh
76 Lampu HE 32 Watt 55,000.00 / bh
77 Lampu LED 5 Watt 80,000.00 / bh
78 Down Light + Lampu HE 35 Watt 95,000.00 / bh
79 Down Light + Lampu LED 8 Watt 125,000.00 / bh
80 Downlight lampu 4 inch 80,000.00 / bh
81 Downlight lampu 5 inch 100,000.00 / bh
82 List Profil Kayu 15,000.00 / m1
83 List Profil Gypsum 12,500.00 / m1
84 Lem kayu 35,000.00 / kg
85 Minyak Bekesting 4,000.00 / ltr
86 Mangkok Listrik + Penutup 15,000.00 / bh
87 Thiner 21,000.00 / ltr
88 Pacok Jendela 22,000.00 / bh
89 Paku seng 26,000.00 / kg
90 Paku GRC/kalsiboard 33,000.00 / kg
91 Paku kayu 17,000.00 / kg
92 Paku sekrup 31,000.00 / kg
93 Paku Triplek 17,000.00 / kg
94 Pasir urug 155,000.00 / m3
95 Pasir pasang 280,000.00 / m3
96 Pasir pasang 92.86 / kg
97 Pasir beton 292,000.00 / m3
98 Pasir beton 93.86 / kg
99 Papan Meranti 2,800,000.00 / m3
100 Paving Blok 2,225.00 / bh
101 Pegangan jendela 17,000.00 / bh
102 Pegangan Pintu Double 135,000.00 / bh
103 Pipa PVC Dim. 1/2 Inch 25,450.00 / btg
104 Pipa PVC Dim. 3/4 Inch 37,750.00 / btg
105 Pipa PVC Dim. 1 Inch 65,000.00 / btg
106 Pipa PVC Dim. 1.5 Inch 145,500.00 / btg
107 Pipa PVC Dim. 2 Inch 242,100.00 / btg
108 Pipa PVC Dim. 2.5 Inch 350,000.00 / btg
109 Pipa PVC Dim. 3 Inch 878,000.00 / btg
110 Pipa PVC Dim. 4 Inch 1,829,000.00 / btg
111 Plafond PVC + List Profil + Sambungan + Rangka (Terpasang) 275,000.00 / m2
112 Plywood 4 mm (122 x 244) cm 105,000.00 / Lbr
113 Plywood 4 mm (90 x 220) cm 85,000.00 / Lbr
114 Plamir 25,000.00 / kg
115 Profil C.75.75 20,833.33 / m
116 Rabung genteng metal 0.30 27,000.00 / bh
117 Rabung Seng 0.30 110,000.00 / lbr
118 Reng U.45 9,500.00 / m
119 Residu/Minyak bekisting 4,300.00 / ltr
120 Saklar (setara Broco) 18,000.00 / bh
121 Saklar (setara Panasonic) 15,000.00 / bh
122 Saklar lampu 3 Seri (setara Broco) 29,000.00 / bh
123 Screw 550.00 / bh
124 Semen portlant 70,000.00 / zak
125 Semen warna (50 kg) 220,000.00 / zak
126 Seng gelombang BJLS 0.30 75,000.00 / Lbr
127 Seng gelombang Warna 0.30 100,000.00 / Lbr
128 Seng Zincalum Warna 0.30 70,455.00 / Lbr
129 Seng plat BJLS 0.30 130,000.00 / Lbr
130 Stop Kontak (setara Broco) 28,000.00 / bh
131 Stop Kontak (setara Panasonic) 14,000.00 / bh
132 Stop Kontak Tanam (setara Broco) 32,500.00 / bh
133 Timbunan Electrik 135,000.00 / m3
134 Timbunan Sirtu 186,000.00 / m3
135 Tarikan Jendela 23,000.00 / bh
136 Titik Lampu + Instalasi 165,000.00 / Ttk
137 Triplek 2 mm 50,000.00 / Lbr
138 Triplek 3 mm 63,000.00 / Lbr
139 Triplek 4 mm 75,000.00 / Lbr
140 Triplek 5 mm 108,000.00 / Lbr
141 Triplek 9 mm 143,000.00 / Lbr
142 Seal teap 11,000.00 / bh
143 Urinoir keramik 1,300,000.00 / bh
144 Wastafel + Kaca 890,500.00 / bh
145 Wiresmesh 37,500.00 / m2
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Beton Mutu F'c = 14,5 Mpa (K 175), Slump (12 ± 2) cm, W/c = 0,66
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.5
Jenis Pekerjaan : Pasangan Dinding Bata ( 4 x 10 x 20 ) cm Tebal 1/2 Bata Camp. 1Pc : 4 PP
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.9.a
Jenis Pekerjaan : Pengecatan Bidang Kayu Baru (1 x plamir, 1 x cat dasar,2 x cat penutup)
Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.4
Jenis Pekerjaan : Pengecatan Tembok Baru (1 x plamir, 1 x cat dasar, 2 x cat penutup)
Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.10