NO URAIAN PEKERJAAN ANALISA HARGA SATUAN HALAMAN

A PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan 1 M Bouwplank AHSP PU A.2.2.1.4 90,501.70 1
2 Pembersihan 1 M2 Lapangan dan Perataan AHSP PU A.2.2.1.9 21,018.00 1

B PEKERJAAN TANAH
1 Galian Tanah Biasa Sedalam 1 Meter AHSP PU A.2.3.1.1 69,500.00 1
2 Galian Tanah Biasa Sedalam 2 Meter AHSP PU A.2.3.1.2 97,632.00 2
3 Galian Tanah Biasa Sedalam 3 Meter AHSP PU A.2.3.1.3 117,181.00 2
4 Mengurug Kembali Galian AHSP PU A.2.3.1.9 43,120.80 2
5 Memadatkan tanah (per 20 cm) AHSP PU A.2.3.1.10 59,890.00 3
6 Timbunan Tanah didatangkan Termasuk Perataan dan Pemadatan AHSP PU - T.14 E 251,990.00 3
7 Urugan Pasir AHSP PU A.2.3.1.11 241,594.00 3
8 Timbunan Tanah AHSP PU A.2.3.1.11.a 189,800.00 4
9 Pengurugan 1 M3 Sirtu AHSP PU A.2.3.1.14 282,161.00 4

C PEKERJAAN PASANGAN
1 Pondasi Batu Belah / Kali Campuran 1 : 4 AHSP PU A.3.2.1.2 952,925.00 4
2 Pasangan Batu Kosong ( Anstamping ) AHSP PU A.3.2.1.9 530,185.83 5
3 Pasangan 1 M3 Pondasi Cyclopen 60% Camp 1Pc:2PB:3Kr 40% Batu Belah AHSP PU A.3.2.1.10 1,266,179.69 5
4 Membuat Beton Mutu F'c = 7,4 Mpa (K 100), Slump (12 ± 2) cm, W/c = 0,87 AHSP PU A.4.1.1.1 1,172,838.95 6
5 Membuat Beton Mutu F'c = 9,8 Mpa (K 125), Slump (12 ± 2) cm, W/c = 0,78 AHSP PU A.4.1.1.2 1,223,657.20 6
6 Beton Mutu F'c = 14,5 Mpa (K 175), Slump (12 ± 2) cm, W/c = 0,66 AHSP PU A.4.1.1.5 1,159,826.29 7
7 Beton Mutu F'c = 16,9 Mpa (K 200), Slump (12 ± 2) cm, W/c = 0,61 AHSP PU A.4.1.1.6 1,310,603.70 7
8 Beton Mutu F'c = 19,3 Mpa (K 225), Slump (12 ± 2) cm, W/c = 0,58 AHSP PU A.4.1.1.7 1,389,317.89 8
9 Beton Mutu F'c = 21,7 Mpa (K 250), Slump (12 ± 2) cm, W/c = 0,56 AHSP PU A.4.1.1.8 1,411,682.74 8
10 Beton Mutu F'c = 24,0 Mpa (K 275), Slump (12 ± 2) cm, W/c = 0,53 AHSP PU A.4.1.1.8 1,450,168.39 9
11 Beton Mutu F'c = 26,4 Mpa (K 300), Slump (12 ± 2) cm, W/c = 0,52 AHSP PU A.4.1.1.8 1,462,098.50 9

D PEKERJAAN PEMBESIAN
1 Pembesian 1 Kg Dengan Besi Polos AHSP PU A.4.1.1.17 15,288.30 10
2 Pembesian 1 Kg Dengan Besi Ulir AHSP PU A.4.1.1.17.a 29,378.08 10
3 Memasang 1 Kg Jaring Kawat Baja / Wire Mesh AHSP PU A.4.1.1.19 21,518.59 11

E PEKERJAAN BEKISTING
1 Memasang Bekisting Untuk Pondasi AHSP PU A.4.1.1.20 72,340.34 11
2 Memasang Bekisting Untuk Sloof AHSP PU A.4.1.1.21 136,216.33 12
3 Memasang Bekisting Untuk Kolom AHSP PU A.4.1.1.22 170,723.67 12
4 Memasang Bekisting Untuk Balok AHSP PU A.4.1.1.23 170,723.67 13
5 Memasang Bekisting Untuk Plat Lantai AHSP PU A.4.1.1.24 264,872.00 13
6 Memasang Bekisting Untuk Dinding AHSP PU A.4.1.1.25 263,742.00 14
7 Memasang Bekisting Untuk Tangga AHSP PU A.4.1.1.26 145,996.00 14
8 Memasang Bekisting Untuk Jembatan Pengecoran AHSP PU A.4.1.1.27 109,610.00 15

F PEKERJAAN BAJA BERAT


1 Pemasangan Baja Profil AHSP PU A.4.2.1.1 43,351.32 15
2 Pemasangan Rangka Kuda-Kuda Baja IWF AHSP PU A.4.2.1.2 30,356.32 16

G PEKERJAAN ALUMINIUM
1 Pemasangan Kusen Pintu Aluminum AHSP PU A.4.2.1.11 61,038.87 16
2 Pemasangan Rangka besi Hollow 40 x 40 x 2 mm AHSP PU A.4.2.1.20 101,361.00 17
H PEKERJAAN BATU BATA DAN PLASTERAN
1 Pasangan Dinding Bata ( 5 x 11 x 22 ) cm Tebal 1 Bata Camp. 1Pc : 2 PP. AHSP PU A.4.4.1.1 328,496.65 17
2 Pasangan Dinding Bata ( 4 x 10 x 20 ) cm Tebal 1 Bata Camp. 1Pc : 2 PP. AHSP PU A.4.4.1.1.a 354,260.65 18
3 Pasangan Dinding Bata Tebal 1 Bata Camp. 1Pc : 3 PP AHSP PU A.4.4.1.2 311,114.43 18
4 Pasangan Dinding Bata ( 5x11x22) cm Tebal 1 Bata Camp. 1Pc : 4 PP AHSP PU A.4.4.1.3 299,091.23 19
5 Pasangan Dinding Bata ( 4x10x20) cm Tebal 1 Bata Camp. 1Pc : 4 PP AHSP PU A.4.4.1.3.a 324,855.23 19
6 Pasangan Dinding Bata Tebal 1 Bata Camp. 1Pc : 5 PP AHSP PU A.4.4.1.4 293,336.70 20
7 Pasangan Dinding Bata ( 5x11x22) cm Tebal 1/2 Bata Camp. 1Pc : 2 PP AHSP PU A.4.4.1.7 158,078.53 20
8 Pasangan Dinding Bata ( 4x10x20) cm Tebal 1/2 Bata Camp. 1Pc : 2 PP AHSP PU A.4.4.1.7.a 170,960.53 21
9 Pasangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 3 PP AHSP PU A.4.4.1.8 149,654.38 21
10 Pasangan Dinding Bata ( 5 x 11 x 22 ) cmTebal 1/2 Bata Camp. 1Pc : 4 PP AHSP PU A.4.4.1.9 144,928.15 22
11 Pasangan Dinding Bata ( 4 x 10 x 20 ) cm Tebal 1/2 Bata Camp. 1Pc : 4 PP AHSP PU A.4.4.1.9.a 139,655.00 22
12 Pasangan Dinding Bata Tebal 1/2 Bata Camp. 1Pc : 5 PP AHSP PU A.4.4.1.10 141,961.90 23
13 Pasangan Dinding Kerawang (Roster) Camp. 1 PC : 3 PP AHSP PU A.4.4.1.22 342,322.20 23
14 Pasangan Dinding Kerawang (Roster) Camp. 1 PC : 4 PP AHSP PU A.4.4.1.23 342,322.20 24
15 Plesteran 1 PC : 1 PP Tebal 15 mm AHSP PU A.4.4.2.1 92,148.11 24
16 Plesteran 1 PC : 2 PP Tebal 15 mm AHSP PU A.4.4.2.2 82,972.51 25
17 Plesteran 1 PC : 3 PP Tebal 15 mm AHSP PU A.4.4.2.3 79,080.79 25
18 Plesteran 1 PC : 4 PP Tebal 15 mm AHSP PU A.4.4.2.4 67,575.00 26
19 Plesteran 1 PC : 5 PP Tebal 15 mm AHSP PU A.4.4.2.5 74,904.31 26
20 Acian AHSP PU A.4.4.2.27 44,044.58 27

I PEKERJAAN LANTAI
1 Memasang Lantai Keramik Uk 40 x 40 cm AHSP PU A.4.4.3.34 259,103.92 27
2 Memasang Lantai Keramik Uk 20 x 20 cm AHSP PU A.4.4.3.36 246,388.59 28
3 Pasangan Keramik Lantai Uk. 33 x 33 cm AHSP PU A.4.4.3.34. 243,600.32 28
4 Pasangan Keramik Lantai Uk. 30 x 30 cm Pholished AHSP PU A.4.4.3.35. 301,898.71 29
5 Pasangan Keramik Lantai Uk. 30 x 30 cm UnPholished AHSP PU A.4.4.3.35.a 254,952.86 29
6 Pasangan Keramik Lantai Uk. 40 x 40 cm Pholished AHSP PU A.4.4.3.35.b 263,645.95 30
7 Pasangan Keramik Lantai Uk. 40 x 40 cm Pholished AHSP PU A.4.4.3.35.c 248,801.00 30
8 Pasangan Lantai Granit Tile Uk. 60 x 60 cm Pholished AHSP PU A.4.4.3.35.d 310,115.00 31
9 Pasangan Lantai Granit Tile Uk. 60 x 60 cm UnPholished AHSP PU A.4.4.3.35.e 310,115.00 31
10 Pasangan Keramik Lantai Uk. 20 x 20 cm UnPholished AHSP PU A.4.4.3.36 261,361.09 32
11 Pasangan Keramik Lantai Uk. 25 x 25 cm UnPholished AHSP PU A.4.4.3.36.a 264,567.47 32
12 Pasangan Plint Keramik Uk. 10 x 20 cm AHSP PU A.4.4.3.39 40,600.90 33
13 Pasangan Plint Keramik Uk. 8 x 25 cm AHSP PU A.4.4.3.39.a 99,485.20 33
14 Pasangan Dinding Keramik Uk. 20 x 25 cm AHSP PU A.4.4.3.54 298,835.28 34
15 Pasangan Dinding Keramik Uk. 20 x 45 cm AHSP PU A.4.4.3.54.a 304,824.28 34
16 Pasangan Dinding Keramik Uk. 20 x 40 cm AHSP PU A.4.4.3.54.b 372,511.28 35
17 Pasangan Dinding Batu tempel Hitam AHSP PU A.4.4.3.58 507,796.58 35
18 Pasangan Dinding Batu Alam AHSP PU A.4.4.3.58.a 507,796.58 36
19 Memasang Dinding Keramik Uk 20 x 20 cm AHSP PU A.4.4.3.54 274,879.28 39
20 Memasang Dinding Keramik Uk 20 x 40 cm AHSP PU A.4.4.3.54a 334,893.58 40

J PEKERJAAN PLAFOND DAN ATAP


1 Memasang Langit-Langit Tripleks Ukuran (120 x 240) cm, tebal 6 mm AHSP PU A.4.5.1.5 71,627.88 36
2 Memasang Langit-Langit Lambesering Kayu, tebal 9 mm AHSP PU A.4.5.1.6 261,809.70 37
3 Memasang Langit-Langit Gypsum Board Tebal 9 mm AHSP PU A.4.5.1.7 45,535.00 37
4 Memasang List Profil Kayu AHSP PU A.4.5.1.9 31,487.45 38
5 Memasang List Profil Gypsum AHSP PU A.4.5.1.9a 28,679.40 38
6 Memasang Atap Asbes Gelombang 92 x 200 cm AHSP PU A.4.5.2.10 36,434.59 39
7 Memasang Langit - Langit Triplek Uk 120 x 240 cm AHSP PU A.4.5.1.5 54,042.25 40
8 Memasang Rangka Langit - Langit Kayu Kls II AHSP PU A.4.5.1.5a 284,409.70 41
9 Memasang Atap Bitumen Selulosa 95 x 200 cm AHSP PU A.4.5.2.10.a 157,118.59 41
10 Memasang Rabung Asbes Gelombang 92 x 200 cm AHSP PU A.4.5.2.25 40,573.78 42
11 Memasang Rabung Bitumen Selulosa 95 x 200 cm AHSP PU A.4.5.2.25.a 149,957.78 42
12 Rangka Kuda-kuda Aluzing Aluminium untuk Metal AHSP PU A.4.5.2.32 230,485.00 43
13 Memasang Atap Seng Genteng Metal AHSP PU A.4.5.2.33 101,855.94 43
14 Memasang Rabung Seng AHSP PU A.4.5.2.36 86,145.55 44
15 Memasang Atap 1 M2 Atap Seng Zincalume AHSP PU A.4.5.2.32 75,048.50 48
16 Memasang Rabung Genteng Metal AHSP PU A.4.5.2.36 84,707.63 49
17 Pemasangan 1 M2 Genteng Aspal AHSP PU A.4.5.2.31 65,220.21 62

K PEKERJAAN KAYU
1 Membuat dan Memasang Kusen pintu dan Kusen Jendela, Kayu Kelas I AHSP PU A.4.6.1.1 10,132,879.50 44
2 Membuat dan Memasang Daun Pintu Panel Kayu Kelas II AHSP PU A.4.6.1.5 732,466.00 45
3 Membuat dan Memasang Daun Jendela Kayu Kelas II AHSP PU A.4.6.1.6 556,705.80 45
4 Memasang Jalusi Kusen, Kayu Kelas I AHSP PU A.4.6.1.10 787,304.90 46
5 Memasang Konstruksi Kuda-Kuda, Kayu Kelas I AHSP PU A.4.6.1.14 11,051,953.70 46
6 Memasang Konstruksi Gordeng, Kayu Kelas II AHSP PU A.4.6.1.15 5,453,244.40 47
7 Memasang Rangka Langit-Langit Kayu Kelas II AHSP PU A.4.6.1.20 125,836.80 47
8 Memasang Listplank Uk. 3 x 20 Cm Kayu Kelas I atau Klas II AHSP PU A.4.6.1.21 78,783.60 48
9 Memasang Kuda - Kuda Kayu Kelas I atau Klas II AHSP PU A.4.6.1.13 6,462,922.00 49
10 Memasang Gording Kayu Kelas I atau Klas II AHSP PU A.4.6.1.15 7,710,317.70 50
11 Memasang Listplank Uk. 2 x 20 Cm Kayu Kelas I atau Klas II AHSP PU A.4.6.1.21 69,720.00 50
12 Memasang Listplank Uk. 2 x 30 Cm Kayu Kelas I atau Klas II AHSP PU A.4.6.1.22 78,455.90 51

L PEKERJAAN PENGGANTUNG DAN PENGUNCI


1 Memasang Kunci Silinder AHSP PU A.4.6.2.4 229,932.40 51
2 Memasang Kunci Silinder AHSP PU A.4.6.2.4a 267,222.40 52
3 Memasang Engsel Pintu AHSP PU A.4.6.2.5 49,251.05 52
4 Memasang Engsel Jendela Kupu-Kupu AHSP PU A.4.6.2.6 42,471.05 52
5 Memasang Hak/Kait Angin Jendela AHSP PU A.4.6.2.9 58,291.05 53
6 Memasang Pacok Jendela AHSP PU A.4.6.2.10 50,381.05 53

M PEKERJAAN SANITASI
1 Memasang Kloset Duduk/Monoblock AHSP PU A.5.1.1.1 2,672,325.70 54
2 Memasang Kloset Jongkok Porselen AHSP PU A.5.1.1.2 782,694.50 54
3 Memasang 1 Buah Urinoir AHSP PU A.5.1.1.4 2,192,426.00 55
4 Pemasangan 1 Bh Wastafel AHSP PU A.5.1.1.5 1,705,124.80 55
5 Memasang Floor Drain AHSP PU A.4.5.1.1.14 55,313.50 56
6 Pemasangan 1 Buah Bak Kontrol Bata 30x30 tinggi 35 cm AHSP PU A.5.1.1.15 507,505.60 56
7 Pemasangan 1 Buah Bak Kontrol Bata 45x45 cm tinggi 50 cm AHSP PU A.5.1.1.16 771,429.53 57
8 Pemasangan 1 Buah Bak Kontrol Bata 60x60 cm tinggi 65 cm AHSP PU A.5.1.1.17 921,633.65 57
9 Memasang Kran Air dia. 1/2" atau 3/4" AHSP PU A.4.5.1.19 74,523.50 58

N PEKERJAAN KACA
1 Memasang 1 m2 Kaca tebal 5 mm AHSP PU A.4.6.2.17 199,541.05 58

O PEKERJAAN PENGECATAN
1 Pengecatan Bidang Kayu lama AHSP PU A.4.7.1.4a 15,882.15 59
2 Pengecatan Bidang Kayu Baru (1 x plamir, 1 x cat dasar,2 x cat penutup) AHSP PU A.4.7.1.4 27,048.00 59
3 Pengecatan Tembok Baru (1 x plamir, 1 x cat dasar, 2 x cat penutup) AHSP PU A.4.7.1.10 23,816.70 60
4 Pengecatan Tembok lama (1 x cat dasar, 2 x cat penutup) AHSP PU A.4.7.1.11 34,303.18 60

P PEKERJAAN PEMIPAAN (PLUMBING)


1 Memasang 1 M' pipa Galvanis Dia. 1/2" AHSP PU A.8.4.1.1 20,356.57 61
2 Memasang Pipa PVC dia.3" AHSP PU A.8.4.1.1.a 180,920.16 61
3 Memasang Pipa PVC dia.4" AHSP PU A.8.4.1.1.b 360,025.16 61

Q PEKERJAAN PENATAAN HALAMAN


1 Penanaman Rumput Lempengan AHSP PU A.2.P.12.A 36,838.00 62
2 Memasang Paving Block AHSP PU A.4.1.1.1.P 125,070.32 63
REKAPITULASI RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN MESJID
LOKASI : DUSUN LONRONG
KECAMATAN : PONRE
KABUPATEN : BONE
PROVINSI : SULAWESI SELATAN
TAHUN ANGGARAN : 2020

NO URAIAN JUMLAH HARGA

A PEKERJAAN PERSIAPAN Rp. 5,000,000.00


B PEKERJAAN PEMBANGUNAN MESJID
1 PEKERJAAN TANAH DAN PONDASI Rp. 20,270,499.47
2 PEKERJAAN PASANGAN Rp. 140,610,328.85
3 PEKERJAAN BETON Rp. 124,085,231.60
4 PEKERJAAN LANTAI Rp. 110,433,596.34
5 PEKERJAAN KUSEN, DAUN PINTU DAN VENTILASI Rp. 45,000,000.00
6 PEKERJAAN ATAP Rp. 92,590,829.55
7 PEK. INSTALASI LISTRIK Rp. 13,195,000.00
8 PEKERJAAN PENGECATAN Rp. 17,389,715.63
9 PEKERJAAN LAIN-LAIN Rp. 7,771,870.00

JUMLAH Rp. 576,347,071.45

TOTAL Rp. 576,347,071.45

DIBULATKAN Rp. 576,347,000.00

LIMA RATUS TUJUH PULUH ENAM JUTA TIGA RATUS EMPAT PULUH TUJUH RIBU RUPIAH

PONRE, 19 FEBRUARI 2020

DISETUJUI, DIKETAHUI,
KEPALA DESA TURUADAE KEPALA DESA PATTIMPA

………………………
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN MESJID
LOKASI : DUSUN LONRONG
KECAMATAN : PONRE
KABUPATEN : BONE
PROVINSI : SULAWESI SELATAN
TAHUN ANGGARAN : 2020

HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SAT ANALISA SATUAN HARGA
(Rp) (Rp)
1 2 3 4 5 6 7
A PEKERJAAN PERSIAPAN
1 Pembongkaran 1.00 Ls Taksir 5,000,000.00 5,000,000.00
Jumlah 5,000,000.00
B PEKERJAAN PEMBANGUNAN MESJID
I PEKERJAAN TANAH DAN PONDASI
1 Galian Tanah Pondasi 78.57 m³ AHSP PU A.2.3.1.1 69,500.00 5,460,281.40
2 Urugan Pasir bawah Lantai 26.13 m³ AHSP PU A.2.3.1.11 241,594.00 6,314,010.87
3 Timbunan Bawah Lantai 44.76 m³ AHSP PU A.2.3.1.11.a 189,800.00 8,496,207.20
Jumlah 20,270,499.47
II PEKERJAAN PASANGAN
1 Pas. Pondasi Batu Kali/batu Gunung 1 : 4 27.06 m³ AHSP PU A.3.2.1.2 952,925.00 25,790,081.32
2 Pasangan 1/2 Bata 1: 4 662.01 m² AHSP PU A.4.4.1.9.a 139,655.00 92,452,666.85
3 Plesteran 1 : 4 dan Acian 331.00 m² AHSP PU A.4.4.2.4 67,575.00 22,367,580.69
Jumlah 140,610,328.85
III PEKERJAAN BETON
1 Sloof 20/30
- Beton 3.26 m³ AHSP PU A.4.1.1.5 1,159,826.29 3,777,322.25
- Besi tulangan (Polos) 1,428.99 kg AHSP PU A.4.1.1.17 15,288.30 21,846,812.52
- Bekisting 38.00 m² AHSP PU A.4.1.1.21 136,216.33 5,175,675.80
2 Kolom 20/20
- Beton 3.60 m³ AHSP PU A.4.1.1.5 1,159,826.29 4,175,374.63
- Besi tulangan (Polos) 2,095.11 kg AHSP PU A.4.1.1.17 15,288.30 32,030,725.25
- Bekisting 72.00 m² AHSP PU A.4.1.1.22 170,723.67 12,292,104.00
3 Kolom Praktis 15/15
- Beton 0.18 m³ AHSP PU A.4.1.1.5 1,159,826.29 208,768.73
- Besi tulangan (Polos) 50.76 kg AHSP PU A.4.1.1.17 15,288.30 776,006.15
- Bekisting 2.08 m² AHSP PU A.4.1.1.22 170,723.67 355,105.23
4 Balok Ring Balk 20/20
- Beton 4.34 m³ AHSP PU A.4.1.1.5 1,159,826.29 5,036,429.66
- Besi tulangan (Polos) 1,445.06 kg AHSP PU A.4.1.1.17 15,288.30 22,092,471.90
- Bekisting 56.45 m² AHSP PU A.4.1.1.23 170,723.67 9,637,555.85
5 Cor Atap Plat Beton
- Beton 2.90 m³ AHSP PU A.4.1.1.5 1,159,826.29 3,365,073.59
- Besi tulangan (Polos) 129.76 kg AHSP PU A.4.1.1.17 15,288.30 1,983,758.39
- Bekisting 5.03 m² AHSP PU A.4.1.1.24 264,872.00 1,332,047.64
Jumlah 124,085,231.60
IV PEKERJAAN LANTAI
1 Rabat Beton Lantai, t = 5 cm 4.36 m3 AHSP PU A.4.1.1.5 1,159,826.29 5,051,971.34
2 Lantai Keramik 20 x 20 cm dinding WC 50.00 m2 AHSP PU A.4.4.3.36 261,361.09 13,068,054.50
3 Lantai Keramik 30 x 30 cm WC Kasar 50.00 m2 AHSP PU A.4.4.3.35. 301,898.71 15,094,935.50
4 Lantai Granit 60 x 60 cm 249.00 m2 AHSP PU A.4.4.3.35.d 310,115.00 77,218,635.00
Jumlah 110,433,596.34
V PEKERJAAN KUSEN, DAUN PINTU DAN VENTILASI
1 Kosen + Daun Pintu + Ongkos+ Accesoris Lengkap Terpasang 60.00 m² Taksir 750,000.00 45,000,000.00
Jumlah 45,000,000.00
VII PEKERJAAN ATAP
1 Rangka Kuda - Kuda Baja Ringan 118.00 m² AHSP PU A.4.5.2.32 230,485.00 27,197,230.00
2 Atap Seng spandek + talang luar + talang dalam 118.00 m² AHSP PU A.4.5.2.32 75,048.50 8,855,723.00
2 Alcopan (ACP) pinggiran atap 104.54 m' Taksir 300,000.00 31,362,000.00
Jumlah 92,590,829.55
VIII PEK. INSTALASI LISTRIK
1 Pemasangan Instalasi Listrik 1.00 Pkt Taksir 3,500,000.00 3,500,000.00
2 Instalasi Titik Penerangan, Instalasi termasuk kabel 30.00 Ttk Taksir 165,000.00 4,950,000.00
NYA 2,5 mm dalam Pipa PVC, Fitting dan
Kelengkapan Instalasi Terpasang
3 MCB (Terpasang)+Kabel Arde 1.00 Bh Taksir 140,000.00 140,000.00
4 Down Light + Lampu LED 8 Watt 30.00 Bh Taksir 125,000.00 3,750,000.00
5 Stop Kontak 30.00 Bh Taksir 28,000.00 840,000.00
6 Saklar 1.00 Bh Taksir 15,000.00 15,000.00
Jumlah 13,195,000.00
IX PEKERJAAN PENGECATAN
1 Pekerjaan Cat Dinding 662.01 m² AHSP PU A.4.7.1.10 23,816.70 15,766,835.63
2 Pekerjaan Cat Kayu/Minyak 60.00 m² AHSP PU A.4.7.1.4 27,048.00 1,622,880.00
Jumlah 17,389,715.63
X PEKERJAAN LAIN-LAIN
1 Batu Alam (Terpasang) 18.72 m² Taksir 335,000.00 6,271,870.00
2 Kubah Mesjid GRC Besar 1.00 bh Taksir 1,500,000.00 1,500,000.00
Jumlah 7,771,870.00

Jumlah Total Pekerjaan 576,347,071.45


DAFTAR HARGA BAHAN DAN UPAH

A. HARGA UPAH Hrg Awal


1 Mandor 200,000.00 / Oh
2 Pekerja 86,000.00 / Oh
3 Tukang 127,000.00 / Oh
4 Kepala Tukang 139,000.00 / Oh

B. HARGA BAHAN
1 Air 65.00 / Liter
2 Atap Genteng Metal 0.30 52,400.00 / lbr
3 Bak Air PVC + Penutup Samping 350,000.00 / Unt
4 Batu Alam 335,000.00 / m2
5 Batu bata (Uk. 20 x 10 x 5 cm) 700.00 / bh
6 Batu bata (Uk. 18 x 10 x 3.5 cm) 760.00 / bh
7 Batu gunung/batu kali 227,000.00 / m3
8 Baut Reng 500.00 / bh
9 Baut Truss 500.00 / bh
10 Baja Profil 21,000.00 / kg
11 Besi beton polos 12,000.00 / kg
12 Besi beton ulir 22,200.00 / kg
13 Besi strip 5 mm 30,000.00 / kg
14 Besi Hollow 4 x 40 x 40 6,750.00 / m'
15 Besi Siku 40 x 40 x 4 17,500.00 / m'
16 Besi Baja IWF 11,000.00 / kg
17 Bon bon keramik 18,000.00 / m'
18 Cat dasar 18,000.00 / kg
19 Cat menie 25,000.00 / kg
20 Cat minyak 28,400.00 / kg
21 Cat plafond 22,000.00 / kg
22 Cat tembok 42,000.00 / kg
23 Dempul Kayu 18,000.00 / kg
24 Dolken Kayu ø 8-10/4 m 20,000.00 / btg
25 Downlight lampu 4 inch 68,000.00 / bh
26 Downlight lampu 5 inch 87,000.00 / bh
27 Engsel pintu 21,000.00 / bh
28 Engsel jendela 15,000.00 / bh
29 Floor Penutup Lantai 33,000.00 / bh
30 Furring Plafond 45,000.00 / Btg
31 Gebalan Rumput 20,000.00 / m2
32 Gypsum 9 mm 70,000.00 / lbr
33 Grendel pintu/jendela 27,000.00 / bh
34 Hak angin 29,000.00 / bh
35 Kain Kasa 32,500.00 / Rol
36 Kawat beton 20,000.00 / kg
37 Kayu komea 4,800,000.00 / m3
38 Kayu meuranti (Klas II) 2,800,000.00 / m3
39 Kayu klas III 2,500,000.00 / m3
40 Kaca bening 5 mm 140,000.00 / m2
41 Kaca reyband 5 mm 165,000.00 / m2
42 Kalsiboard 4.5 mm 63,000.00 / lbr
43 Kalsiboard 6 mm 70,000.00 / lbr
44 Kawat duri 4,500.00 / m
45 Kerikil 288,000.00 / m3
46 Kerikil 88.89 / kg
47 Keramik Lantai 60x60cm (polished) 135,000.00 / m2
48 Keramik Lantai 60x60cm (polished) 48,600.00 / bh
49 Keramik Lantai 40x40cm (polished) 75,000.00 / m2
50 Keramik Lantai 40x40cm (polished) 12,000.00 / bh
51 Keramik Lantai 40x40cm (unpolished) 89,500.00 / m2
52 Keramik Lantai 40x40cm (unpolished) 14,320.00 / bh
53 Keramik Lantai 30x30cm (polished) 60,000.00 / m2
54 Keramik Lantai 40x40cm (unpolished) 9,600.00 / bh
55 Keramik Lantai 25x25 (unpolished) 75,000.00 / m2
56 Keramik Lantai 25x25 (unpolished) 4,687.50 / bh
57 Keramik Lantai 20x20 (polished) 60,000.00 / m2
58 Keramik Lantai 20x20 (polished) 2,400.00 / bh
59 Keramik dinding 30x60 cm 26,500.00 / bh
60 Keramik dinding 20x40 cm 120,000.00 / m2
61 Keramik dinding 20x40 cm 12,000.00 / bh
62 Keramik dinding 20x25 cm 80,000.00 / m2
63 Keramik dinding 20x25 cm 4,000.00 / bh
64 Keramik dinding 10x20 cm 1,500.00 / bh
65 Kusen uPVC, t=5 cm + Daun Pintu/Jendela + Aksesories + Terpasang 1,300,000.00 / m2
66 Granit Lantai 60x60 cm 87,000.00 / bh
67 Granit Lantai 80x80 cm 280,000.00 / m2
68 Kloset jongkok keramik (setara KIA) 350,000.00 / bh
69 Kloset duduk keramik (setara KIA) 1,800,000.00 / bh
70 Koral Beton 125,000.00 / m3
71 Kunci tanam 2 slaag 175,000.00 / bh
72 Kran air 3/4" 50,000.00 / bh
73 Kertas Amplas 5,000.00 / lbr
74 Lampu HE 23 Watt 35,000.00 / bh
75 Lampu HE 28 Watt 42,000.00 / bh
76 Lampu HE 32 Watt 55,000.00 / bh
77 Lampu LED 5 Watt 80,000.00 / bh
78 Down Light + Lampu HE 35 Watt 95,000.00 / bh
79 Down Light + Lampu LED 8 Watt 125,000.00 / bh
80 Downlight lampu 4 inch 80,000.00 / bh
81 Downlight lampu 5 inch 100,000.00 / bh
82 List Profil Kayu 15,000.00 / m1
83 List Profil Gypsum 12,500.00 / m1
84 Lem kayu 35,000.00 / kg
85 Minyak Bekesting 4,000.00 / ltr
86 Mangkok Listrik + Penutup 15,000.00 / bh
87 Thiner 21,000.00 / ltr
88 Pacok Jendela 22,000.00 / bh
89 Paku seng 26,000.00 / kg
90 Paku GRC/kalsiboard 33,000.00 / kg
91 Paku kayu 17,000.00 / kg
92 Paku sekrup 31,000.00 / kg
93 Paku Triplek 17,000.00 / kg
94 Pasir urug 155,000.00 / m3
95 Pasir pasang 280,000.00 / m3
96 Pasir pasang 92.86 / kg
97 Pasir beton 292,000.00 / m3
98 Pasir beton 93.86 / kg
99 Papan Meranti 2,800,000.00 / m3
100 Paving Blok 2,225.00 / bh
101 Pegangan jendela 17,000.00 / bh
102 Pegangan Pintu Double 135,000.00 / bh
103 Pipa PVC Dim. 1/2 Inch 25,450.00 / btg
104 Pipa PVC Dim. 3/4 Inch 37,750.00 / btg
105 Pipa PVC Dim. 1 Inch 65,000.00 / btg
106 Pipa PVC Dim. 1.5 Inch 145,500.00 / btg
107 Pipa PVC Dim. 2 Inch 242,100.00 / btg
108 Pipa PVC Dim. 2.5 Inch 350,000.00 / btg
109 Pipa PVC Dim. 3 Inch 878,000.00 / btg
110 Pipa PVC Dim. 4 Inch 1,829,000.00 / btg
111 Plafond PVC + List Profil + Sambungan + Rangka (Terpasang) 275,000.00 / m2
112 Plywood 4 mm (122 x 244) cm 105,000.00 / Lbr
113 Plywood 4 mm (90 x 220) cm 85,000.00 / Lbr
114 Plamir 25,000.00 / kg
115 Profil C.75.75 20,833.33 / m
116 Rabung genteng metal 0.30 27,000.00 / bh
117 Rabung Seng 0.30 110,000.00 / lbr
118 Reng U.45 9,500.00 / m
119 Residu/Minyak bekisting 4,300.00 / ltr
120 Saklar (setara Broco) 18,000.00 / bh
121 Saklar (setara Panasonic) 15,000.00 / bh
122 Saklar lampu 3 Seri (setara Broco) 29,000.00 / bh
123 Screw 550.00 / bh
124 Semen portlant 70,000.00 / zak
125 Semen warna (50 kg) 220,000.00 / zak
126 Seng gelombang BJLS 0.30 75,000.00 / Lbr
127 Seng gelombang Warna 0.30 100,000.00 / Lbr
128 Seng Zincalum Warna 0.30 70,455.00 / Lbr
129 Seng plat BJLS 0.30 130,000.00 / Lbr
130 Stop Kontak (setara Broco) 28,000.00 / bh
131 Stop Kontak (setara Panasonic) 14,000.00 / bh
132 Stop Kontak Tanam (setara Broco) 32,500.00 / bh
133 Timbunan Electrik 135,000.00 / m3
134 Timbunan Sirtu 186,000.00 / m3
135 Tarikan Jendela 23,000.00 / bh
136 Titik Lampu + Instalasi 165,000.00 / Ttk
137 Triplek 2 mm 50,000.00 / Lbr
138 Triplek 3 mm 63,000.00 / Lbr
139 Triplek 4 mm 75,000.00 / Lbr
140 Triplek 5 mm 108,000.00 / Lbr
141 Triplek 9 mm 143,000.00 / Lbr
142 Seal teap 11,000.00 / bh
143 Urinoir keramik 1,300,000.00 / bh
144 Wastafel + Kaca 890,500.00 / bh
145 Wiresmesh 37,500.00 / m2
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Galian Tanah Biasa Sedalam 1 Meter


Satuan / Unit : M3
Analisa : AHSP PU A.2.3.1.1

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.7500 86,000.00 64,500.00
2 Mandor OH 0.0250 200,000.00 5,000.00
Jumlah Tenaga Kerja 69,500.00
B. BAHAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 69,500.00
E Overhead & Profit 13% X D -
F Harga Satuan Pekerjaan ( D + E ) 69,500.00
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Timbunan Tanah


Satuan / Unit : M3
Analisa : AHSP PU A.2.3.1.11.a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.3000 86,000.00 25,800.00
2 Mandor OH 0.0100 200,000.00 2,000.00
Jumlah Tenaga Kerja 27,800.00
B. BAHAN
1 Tanah Timbun M3 1.200 135,000.00 162,000.00
Jumlah Bahan 162,000.00
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 189,800.00
E Overhead & Profit 13% X D -
F Harga Satuan Pekerjaan ( D + E ) 189,800.00

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pondasi Batu Belah / Kali Campuran 1 : 4


Satuan / Unit : M3
Analisa : AHSP PU A.3.2.1.2

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 1.5000 86,000.00 129,000.00
2 Tukang OH 0.7500 127,000.00 95,250.00
3 Kepala Tukang OH 0.0750 139,000.00 10,425.00
4 Mandor OH 0.0750 200,000.00 15,000.00
Jumlah Tenaga Kerja 249,675.00
B. BAHAN
1 Batu Gunung/ Batu Kali M3 1.200 227,000.00 272,400.00
2 Semen Portland (PC) Kg 163.000 1,750.00 285,250.00
3 Pasir Pasang M3 0.520 280,000.00 145,600.00
Jumlah Bahan 703,250.00
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 952,925.00
E Overhead & Profit 13% X D -
F Harga Satuan Pekerjaan ( D + E ) 952,925.00
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Beton Mutu F'c = 14,5 Mpa (K 175), Slump (12 ± 2) cm, W/c = 0,66
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.5

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 1.6500 86,000.00 141,900.00
2 Tukang OH 0.2750 127,000.00 34,925.00
3 Kepala Tukang OH 0.0280 139,000.00 3,892.00
4 Mandor OH 0.0830 200,000.00 16,600.00
Jumlah Tenaga Kerja 197,317.00
B. BAHAN
1 Semen Portland (PC) Kg 326.00 1,750.00 570,500.00
2 Pasir Beton (PB) Kg 760.00 208.57 158,514.29
3 Kerikil (KR) Kg 1,029.00 213.33 219,520.00
4 Air Liter 215.00 65.00 13,975.00
Jumlah Bahan 962,509.29
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,159,826.29
E Overhead & Profit 13% X D -
F Harga Satuan Pekerjaan ( D + E ) 1,159,826.29
Wc Faktor; Pasir; 1.400 Kg, dan Kerikil = 1.350 Kg
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pembesian 1 Kg Dengan Besi Polos


Satuan / Unit : Kg
Analisa : AHSP PU A.4.1.1.17

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.0700 86,000.00 6,020.00
2 Tukang OH 0.0700 127,000.00 8,890.00
3 Kepala Tukang OH 0.0070 139,000.00 973.00
4 Mandor OH 0.0400 200,000.00 8,000.00
Jumlah Tenaga Kerja 23,883.00
B. BAHAN
1 Besi Beton Polos Kg 10.500 12,000.00 126,000.00
2 Kawat Beton Kg 0.150 20,000.00 3,000.00
Jumlah Bahan 129,000.00
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 152,883.00
E Per Kg Pembesian = D / 10 15,288.30
F Overhead & Profit 13% X E -
G Harga Satuan Pekerjaan ( E + F ) 15,288.30
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Memasang Bekisting Untuk Sloof


Satuan / Unit : M2
Analisa : AHSP PU A.4.1.1.21

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.5400 86,000.00 46,440.00
2 Tukang OH 0.2700 127,000.00 34,290.00
3 Kepala Tukang OH 0.0270 139,000.00 3,753.00
4 Mandor OH 0.0540 200,000.00 10,800.00
Jumlah Tenaga Kerja 95,283.00
B. BAHAN
1 Kayu Kelas III M3 0.013 2,500,000.00 33,333.33
2 Paku 5 cm - 10 cm Kg 0.400 17,000.00 6,800.00
3 Minyak Bekisting Liter 0.200 4,000.00 800.00
Jumlah Bahan 40,933.33
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 136,216.33
E Overhead & Profit 13% X D -
F Harga Satuan Pekerjaan ( D + E ) 136,216.33
Catatan : Bahan digunakan lebih 1 (satu) kali

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Memasang Bekisting Untuk Kolom


Satuan / Unit : M2
Analisa : AHSP PU A.4.1.1.22

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.6600 86,000.00 56,760.00
2 Tukang OH 0.3300 127,000.00 41,910.00
3 Kepala Tukang OH 0.0330 139,000.00 4,587.00
4 Mandor OH 0.0660 200,000.00 13,200.00
Jumlah Tenaga Kerja 116,457.00
B. BAHAN
1 Kayu Kelas III M3 0.0133 2,500,000.00 33,333.33
2 Paku 5 cm - 10 cm Kg 0.4000 17,000.00 6,800.00
3 Minyak Bekisting Liter 0.2000 4,000.00 800.00
4 Balok Kayu Kelas II M3 0.0102 - -
5 Mutipleks tebal 9 mm Lbr 0.3500 - -
6 Kayu dolken dia. 8-10 cm, L = 4 M Batang 0.6667 20,000.00 13,333.33
Jumlah Bahan 54,266.67
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 170,723.67
E Overhead & Profit 13% X D -
F Harga Satuan Pekerjaan ( D + E ) 170,723.67
Catatan : Bahan digunakan lebih 1 (satu) kali
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Memasang Bekisting Untuk Balok


Satuan / Unit : M2
Analisa : AHSP PU A.4.1.1.23

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.6600 86,000.00 56,760.00
2 Tukang OH 0.3300 127,000.00 41,910.00
3 Kepala Tukang OH 0.0330 139,000.00 4,587.00
4 Mandor OH 0.0660 200,000.00 13,200.00
Jumlah Tenaga Kerja 116,457.00
B. BAHAN
1 Kayu Kelas III M3 0.0133 2,500,000.00 33,333.33
2 Paku 5 cm - 10 cm Kg 0.4000 17,000.00 6,800.00
3 Minyak Bekisting Liter 0.2000 4,000.00 800.00
4 Balok Kayu Kelas II M3 0.0102 - -
5 Mutipleks tebal 9 mm Lbr 0.3500 - -
6 Kayu dolken dia. 8-10 cm, L = 4 M Batang 0.6667 20,000.00 13,333.33
Jumlah Bahan 54,266.67
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 170,723.67
E Overhead & Profit 13% X D -
F Harga Satuan Pekerjaan ( D + E ) 170,723.67
Catatan : Bahan digunakan lebih 1 (satu) kali
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pasangan Dinding Bata ( 4 x 10 x 20 ) cm Tebal 1/2 Bata Camp. 1Pc : 4 PP
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.9.a

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.3000 86,000.00 25,800.00
2 Tukang OH 0.1000 127,000.00 12,700.00
3 Kepala Tukang OH 0.0100 139,000.00 1,390.00
4 Mandor OH 0.0150 200,000.00 3,000.00
Jumlah Tenaga Kerja 42,890.00
B. BAHAN
1 Batu Bata Bh 85.000 760.00 64,600.00
2 Semen Portland (PC) Kg 11.500 1,750.00 20,125.00
3 Pasir Pasang M3 0.043 280,000.00 12,040.00
Jumlah Bahan 96,765.00
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 139,655.00
E Overhead & Profit 13% X E -
F Harga Satuan Pekerjaan ( E + F ) 139,655.00
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Plesteran 1 PC : 4 PP Tebal 15 mm


Satuan / Unit : M2
Analisa : AHSP PU A.4.4.2.4

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.3000 86,000.00 25,800.00
2 Tukang OH 0.1500 127,000.00 19,050.00
3 Kepala Tukang OH 0.0150 139,000.00 2,085.00
4 Mandor OH 0.0150 200,000.00 3,000.00
Jumlah Tenaga Kerja 49,935.00
B. BAHAN
1 Semen Portland (PC) Kg 6.240 1,750.00 10,920.00
2 Pasir Pasang M3 0.024 280,000.00 6,720.00
Jumlah Bahan 17,640.00
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 67,575.00
E Overhead & Profit 13% X E -
F Harga Satuan Pekerjaan ( E + F ) 67,575.00
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pasangan Lantai Granit Tile Uk. 60 x 60 cm Pholished


Satuan / Unit : M2
Analisa : AHSP PU A.4.4.3.35.d

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.7000 86,000.00 60,200.00
2 Tukang OH 0.3500 127,000.00 44,450.00
3 Kepala Tukang OH 0.0350 139,000.00 4,865.00
4 Mandor OH 0.0350 200,000.00 7,000.00
Jumlah Tenaga Kerja 116,515.00
B. BAHAN
1 Granit Tile 60 x 60 cm Pholished Bh 3.000 52,300.00 156,900.00
2 Semen Portland (PC) Kg 10.000 1,750.00 17,500.00
3 Pasir Pasang M3 0.045 280,000.00 12,600.00
4 Semen Warna Kg 1.500 4,400.00 6,600.00
Jumlah Bahan 193,600.00
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 310,115.00
E Overhead & Profit 13% X E -
F Harga Satuan Pekerjaan ( E + F ) 310,115.00
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Memasang Langit-Langit Gypsum Board Tebal 9 mm


Satuan / Unit : M2
Analisa : AHSP PU A.4.5.1.7

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.1000 86,000.00 8,600.00
2 Tukang Kayu OH 0.0500 127,000.00 6,350.00
3 Kepala Tukang OH 0.0050 139,000.00 695.00
4 Mandor OH 0.0050 200,000.00 1,000.00
Jumlah Tenaga Kerja 16,645.00
B. BAHAN
1 Gypsum Board Lbr 0.3640 70,000.00 25,480.00
2 Paku Skrup Kg 0.1100 31,000.00 3,410.00
Jumlah Bahan 28,890.00
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 45,535.00
E Overhead & Profit 13% X D -
F Harga Satuan Pekerjaan ( D + E ) 45,535.00
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Rangka Kuda-kuda Aluzing Aluminium untuk Metal


Satuan / Unit : M2
Analisa : AHSP PU A.4.5.2.32

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.1400 86,000.00 12,040.00
2 Tukang OH 0.4000 127,000.00 50,800.00
3 Kepala Tukang OH 0.0400 139,000.00 5,560.00
4 Mandor OH 0.0700 200,000.00 14,000.00
Jumlah Tenaga Kerja 82,400.00
B. BAHAN
1 Profil C 75.100 M' 4.2600 20,833.33 88,750.00
2 Reng U 0.45 M' 4.9300 9,500.00 46,835.00
3 Baut Truss Buah 14.0000 500.00 7,000.00
4 Baut Reng Buah 11.0000 500.00 5,500.00
Jumlah Bahan 148,085.00
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 230,485.00
E Overhead & Profit 13% X D -
F Harga Satuan Pekerjaan ( D + E ) 230,485.00
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Memasang Atap 1 M2 Atap Seng Zincalume


Satuan / Unit : M2
Analisa : AHSP PU A.4.5.2.32

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.0750 86,000.00 6,450.00
2 Tukang OH 0.1000 127,000.00 12,700.00
3 Kepala Tukang OH 0.0200 139,000.00 2,780.00
4 Mandor OH 0.0025 200,000.00 500.00
Jumlah Tenaga Kerja 22,430.00
B. BAHAN
1 Atap Zincalume 0,3 lbr 0.7000 70,455.00 49,318.50
2 Baut Screw bh 6.0000 550.00 3,300.00
Jumlah Bahan 52,618.50
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 75,048.50
E Overhead & Profit 13% X D -
F Harga Satuan Pekerjaan ( D + E ) 75,048.50
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Memasang Listplank Uk. 2 x 20 Cm Kayu Kelas I atau Klas II


Satuan / Unit : M'
Analisa : AHSP PU A.4.6.1.21

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.1000 86,000.00 8,600.00
2 Tukang Kayu OH 0.2000 127,000.00 25,400.00
3 Kepala Tukang OH 0.0200 139,000.00 2,780.00
4 Mandor OH 0.0050 200,000.00 1,000.00
Jumlah Tenaga Kerja 37,780.00
B. BAHAN
1 Papan Kayu Kelas II M3 0.0108 2,800,000.00 30,240.00
2 Paku Kayu Kg 0.1000 17,000.00 1,700.00
Jumlah Bahan 31,940.00
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 69,720.00
E Overhead & Profit 13% X D -
F Harga Satuan Pekerjaan ( D + E ) 69,720.00
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pengecatan Bidang Kayu Baru (1 x plamir, 1 x cat dasar,2 x cat penutup)
Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.4

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.0700 86,000.00 6,020.00
2 Tukang OH 0.0090 127,000.00 1,143.00
3 Kepala Tukang OH 0.0060 139,000.00 834.00
4 Mandor OH 0.0030 200,000.00 600.00
Jumlah Tenaga Kerja 8,597.00
B. BAHAN
1 Cat Menie Kg 0.2000 25,000.00 5,000.00
2 Plamir Kayu Kg 0.1500 - -
3 Cat dasar kayu Kg 0.1700 25,000.00 4,250.00
4 Cat kayu penutup Kg 0.2600 28,400.00 7,384.00
5 Kuas Uk 2" - 3" Bh 0.0100 18,700.00 187.00
6 Pengencer/ Minyak cat Liter 0.0300 21,000.00 630.00
7 Ampelas Lembar 0.2000 5,000.00 1,000.00
Jumlah Bahan 18,451.00
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 27,048.00
E Overhead & Profit 13% X D -
F Harga Satuan Pekerjaan ( D + E ) 27,048.00
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pengecatan Tembok Baru (1 x plamir, 1 x cat dasar, 2 x cat penutup)
Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.10

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0.0200 86,000.00 1,720.00
2 Tukang OH 0.0630 127,000.00 8,001.00
3 Kepala Tukang OH 0.0063 139,000.00 875.70
4 Mandor OH 0.0025 200,000.00 500.00
Jumlah Tenaga Kerja 11,096.70
B. BAHAN
1 Plamir Kg 0.1000 - -
2 Cat dasar tembok Kg 0.1000 18,000.00 1,800.00
3 Cat tembok/penutup 2x Kg 0.2600 42,000.00 10,920.00
Jumlah Bahan 12,720.00
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 23,816.70
E Overhead & Profit 13% X D -
F Harga Satuan Pekerjaan ( D + E ) 23,816.70