Harga Bahan dan Upah Kerja

MENARA SUAR
DISTRIK NAVIGASI KELAS I SURABAYA

I. B A H A N
Transportasi ke
Satuan Harga sampai di
No Material / Barang Harga satuan tempat terpencil / Ket.
Bahan tempat
kg
1 2 3 4 5 6 7
TRANSPORTASI BAHAN KE
Kg Rp 3,937.14
TEMPAT TERPENCIL
1 . Air kerja (tempat terpencil) m3 Rp 80,000.00 Rp 3,937,142.86 Rp 4,017,142.86 4,017
2 . Accu 100 AH bh Rp 5,000,000.00 Rp 204,731.43 Rp 5,204,731.43 52 kg
3 . Bendrat kg Rp 18,500.00 Rp 3,937.14 Rp 22,437.14
4 . Besi Beton Polos kg Rp 12,200.00 Rp 3,937.14 Rp 16,137.14
5 . Besi Beton Ulir kg Rp 12,700.00 Rp 3,937.14 Rp 16,637.14
6 . Besi baja Pipa kg Rp 12,500.00 Rp 7,874.29 Rp 20,374.29 khusus pipa
7 . Besi baja Plat kg Rp 12,500.00 Rp 3,937.14 Rp 16,437.14
8 . Steinless Kg Rp 250,000.00 Rp 3,937.14 Rp 253,937.14
9 . Baut Steinless bh Rp 82,000.00 Rp 984.29 Rp 82,984.29 0,25 kg
10 . Besi / baja Siku / baja INP (profil) kg Rp 12,000.00 Rp 3,937.14 Rp 15,937.14
11 . Box battery unit Rp 875,000.00 Rp 59,057.14 Rp 934,057.14 15 kg
12 . Box solarcell unit Rp 450,000.00 Rp 39,371.43 Rp 489,371.43 10 kg
13 . Cat AC ltr Rp 98,000.00 Rp 3,543.43 Rp 101,543.43 0,9 kg
14 . Cat AF (Anti Fungi/Jamur) ltr Rp 98,000.00 Rp 3,543.43 Rp 101,543.43 0,9 kg
15 . Cat Meni kg Rp 22,500.00 Rp 3,937.14 Rp 26,437.14
16 . Cat Marine kg Rp 110,000.00 Rp 3,937.14 Rp 113,937.14
17 . Cat Minyak untuk Cat Marine ltr Rp 31,500.00 Rp 3,543.43 Rp 35,043.43 0,9 kg
18 . Cat Kayu/Besi kg Rp 52,500.00 Rp 3,937.14 Rp 56,437.14
19 . Minyak Cat Tiner A ltr Rp 26,500.00 Rp 3,543.43 Rp 30,043.43 0,9 kg
20 . Minyak Cat Tiner B ltr Rp 12,500.00 Rp 3,543.43 Rp 16,043.43 0,9 kg
21 . Mortar PC kg Rp 3,375.00 Rp 3,937.14 Rp 7,312.14
22 . Galvanis kg Rp 10,000.00 Rp 3,937.14 Rp 13,937.14
23 . Grease kg Rp 29,700.00 Rp 3,937.14 Rp 33,637.14
24 . Kawat Las (Elektroda baja) kg Rp 29,750.00 Rp 3,937.14 Rp 33,687.14
25 . Kawat Las (Elektroda Steinless) Rp 60,000.00 Rp 3,937.14 Rp 63,937.14
26 . Kayu Meranti MC m3 Rp 4,600,000.00 Rp 3,543,428.57 Rp 8,143,428.57 900 kg
27 . Kayu Meranti Balok/papan m3 Rp 5,250,000.00 Rp 3,543,428.57 Rp 8,793,428.57 900 kg
28 . Kayu Kamper Balok/papan m3 Rp 8,500,000.00 Rp 3,543,428.57 Rp 12,043,428.57 900 kg
29 . Kayu Jati Kwalitas I m3 Rp 45,000,000.00 Rp 3,543,428.57 Rp 48,543,428.57 900 kg
30 . Kayu Jati Kwalitas II m3 Rp 30,000,000.00 Rp 3,543,428.57 Rp 33,543,428.57 900 kg
31 . Kayu Gelam btng Rp 8,500.00 Rp 13,780.00 Rp 22,280.00 3,5 kg
32 . Kertas Gosok / Ampelas lbr Rp 3,500.00 Rp - Rp 3,500.00
33 . Minyak Solar/HSD Industri ltr Rp 9,000.00 Rp 3,543.43 Rp 12,543.43 0,9 kg
34 . Minyak Begesting ltr Rp 9,000.00 Rp 3,543.43 Rp 12,543.43 0,9 kg
35 . Paku kg Rp 14,850.00 Rp 3,937.14 Rp 18,787.14
36 . Paku Seng kg Rp 17,500.00 Rp 3,937.14 Rp 21,437.14
37 . Paku Asbes kg Rp 17,500.00 Rp 3,937.14 Rp 21,437.14
38 . Pasir Cor/Pasang m3 Rp 197,500.00 Rp 5,512,000.00 Rp 5,709,500.00 1.400 kg
39 . Pasir Lokal m3 Rp 197,500.00 Rp - Rp 197,500.00
40 . Sirtu Lokal m3 Rp 165,000.00 Rp - Rp 165,000.00
41 . Plamuer Tembok kg Rp 27,500.00 Rp 3,937.14 Rp 31,437.14
42 . Semen Portland (40 kg) zak Rp 65,000.00 Rp 196,857.14 Rp 261,857.14 Rp 5,237.14
43 . Solarcell 60 wtt unit Rp 7,500,000.00 Rp 39,371.43 Rp 7,539,371.43 10 kg
44 . Kerikil / Steinslah m3 Rp 225,000.00 Rp 7,086,857.14 Rp 7,311,857.14 1.800 kg
45 . Triplek uk. 4 mm lbr Rp 47,850.00 Rp 29,528.57 Rp 77,378.57 7,5 kg
46 . Triplek uk. 9 mm lbr Rp 135,000.00 Rp 66,931.43 Rp 201,931.43 17 kg
II. UPAH
Upah di tempat Upah
No URAIAN - TENAGA Satuan Upah Normal terpencil : hasil di tempat Keterangan
kerja = 30 % Terpencil
1. 2. 3. 4. 5. 6 .= 5./30% 7.
Tenaga Kerja
1. Mandor Orang Rp 120,000.00 35% Rp 342,857.14 per Hari
2. Kepala Tukang Orang Rp 110,000.00 35% Rp 314,285.71 per Hari
3. Kepala Tukang Cat Orang Rp 95,000.00 35% Rp 271,428.57 per Hari
4. Tukang Kayu Orang Rp 85,000.00 35% Rp 242,857.14 per Hari
5. Tukang Batu Orang Rp 80,000.00 35% Rp 228,571.43 per Hari
6. Tukang Cat Orang Rp 80,000.00 35% Rp 228,571.43 per Hari
7. Tukang Besi Orang Rp 80,000.00 35% Rp 228,571.43 per Hari
8. Tukang Las Orang Rp 90,000.00 35% Rp 257,142.86 per Hari
9. Tukang Konstruksi Orang Rp 85,000.00 35% Rp 242,857.14 per Hari
10 . Operator Orang Rp 80,000.00 35% Rp 228,571.43 per Hari
11 . Pembantu Operator Orang Rp 75,000.00 35% Rp 214,285.71 per Hari
12 . Pekerja Orang Rp 70,000.00 35% Rp 200,000.00 per Hari
Analisa Harga Satuan
REPLACEMENT RAMSU PILE BEACON MERAH BAWEAN T.10 M LAUT

SATUAN UPAH BAHAN/ALAT JUMLAH


AN URAIAN PEKERJAAN
(Rp) (Rp) (Rp) (Rp)

TRANSPORTASI BAHAN KE TEMPAT TERPENCIL


1 kg Akomodasi (Angkutan) bahan sd. Lokasi
0.0004 hari Perahu dan Truck Rp 7,500,000 Rp 3,000
0.0004 Org/hr Mandor Rp 342,857 Rp 137
0.0040 Org/hr Pekerja Rp 200,000 Rp 800
Rp 937 Rp 3,000 Rp 3,937
1 m3 Akomodasi (Angkutan) bahan sd. Lokasi
0.4000 hari Perahu dan Truck Rp 7,500,000 Rp 3,000,000
0.4000 Org/hr Mandor Rp 342,857 Rp 137,143
4.0000 Org/hr Pekerja Rp 200,000 Rp 800,000
Rp 937,143 Rp 3,000,000 Rp 3,937,143
NB : Kronologis Pengangkutan bahan material, pasir dan kerikil
- pasir dan kerikil diangkut dari tempat (pulau Jawa) ke pelabuhan di Pulau Jawa.
- di pelabuhan material pasir dan kerikil dimasukkan ke dalam karung-karung (20 kg) kemudian karung-karung tersebut dipindahkan ke perahu.
- dengan perahu karung-karung 'pasir dan kerikil' tersebut dimobilisasi ke lokasi (pantai Pulau lokasi pekerjaan)
- dari perahu di pantai dimobilisasi secara manual (1karung per orang) ke lokasi pekerjaan
- jarak pantai ke lokasi pekerjaan lebih kurang 350 m sd. 400 m

A PEKERJAAN PERSIAPAN
1 kali #NAME?
1.0000 unit Concrete Vibrator
35.0000 kg Akomodasi (Angkutan) bahan sd. Lokasi Rp 3,937 Rp 137,800
Rp 137,800 Rp 137,800
1.0000 unit Mesin Las / Genzet
400.0000 kg Akomodasi (Angkutan) bahan sd. Lokasi Rp 3,937 Rp 1,574,857
Rp 1,574,857 Rp 1,574,857
1.0000 unit Concrete mixer
600.0000 kg Akomodasi (Angkutan) bahan sd. Lokasi Rp 3,937 Rp 2,362,286
Rp 2,362,286 Rp 2,362,286
1.0000 unit Ponton Pancang
3000.0000 kg Akomodasi (Angkutan) bahan sd. Lokasi Rp 3,937 Rp 11,811,429
Rp 11,811,429 Rp 11,811,429
1 kali Pengangkutan = Rp 15,886,371
### 1 pkt #NAME?
2.0000 kali Pengangkutan Rp 15,886,371 Rp 31,772,743
60.0000 hari Akomodasi tenaga kerja Rp 500,000 Rp 30,000,000
Rp 61,772,743 Rp 61,772,743
1 1 unit Direksi Keet
1.0000 hr Sewa Direksi keet terapung Rp 500,000 Rp 500,000
Rp 500,000 Rp 500,000
1 kali Instalasi dan Perakitan / Bongkar Direksi keet (Bongkar/Pasang)
3.6000 Org/hr Tukang Kayu Rp 242,857 Rp 874,286
1.8000 Org/hr Pekerja Rp 200,000 Rp 360,000
Rp 1,234,286 Rp 1,234,286
1 kali Angkutan
1500.0000 kg Akomodasi (Angkutan) bahan sd. Lokasi Rp 3,937 Rp 5,905,714
Rp 5,905,714 Rp 5,905,714
60 hr Direksi Keet
60.0000 hr Sewa Direksi keet terapung Rp 500,000 Rp 30,000,000
2.0000 kali Bongkar/ Pasang Rp 1,234,286 Rp 2,468,571
2.0000 kali Angkutan Rp 5,905,714 Rp 11,811,429
Rp 44,280,000 Rp 44,280,000
1 ton #NAME?
1000.0000 ltr Pengangkutan Rp 85 Rp 85,000
1,000.0000 kg Akomodasi (Angkutan) bahan sd. Lokasi Rp 3,937 Rp 3,937,143
Rp 4,022,143 Rp 4,022,143

B PEKERJAAN STRUKTUR BAWAH


1 m' Bor Stouss 4 titik x 3 m' 60 x 60 cm
1 M' Tiang Pancang baja Ө 40 cm
115.0000 kg Bor Stouss 4 titik x 3 m' 60 x 60 cm Rp 20,374 Rp 2,343,043
0.6250 Org/hr Pekerja Rp 200,000 Rp 125,000
Rp 125,000 Rp 2,343,043 Rp 2,468,043
1 M' biaya Pemancangan
1 hari Biaya diesel/hammer
4.0000 liter Olie 42,500.00 170,000.00
20.0000 liter Solar (Industri) 7,500.00 150,000.00
2.0000 kg Grease 33,637.14 67,274.29
1.0000 Hari Sewa diesel hamer 2,500,000.00 2,500,000.00
1.0000 Org/hr Operator 228,571.43 228,571.43
2.0000 Org/hr Pembantu Operator 214,285.71 428,571.43
2.0000 Org/hr Pekerja 200,000.00 400,000.00
3,624,417.14 320,000.00 3,944,417.14
1 hari Biaya ponton pancang
4.0000 liter Olie 42,500.00 170,000.00
100.0000 liter Solar (Industri) 7,500.00 750,000.00
2.0000 kg Grease 33,637.14 67,274.29
1.0000 Hari Sewa Ponton Pancang 5,000,000.00 5,000,000.00
1.0000 Org/hr Tukang Konstruksi 242,857.14 242,857.14
1.0000 Org/hr Operator 228,571.43 228,571.43
2.0000 Org/hr Pembantu Operator 214,285.71 428,571.43
2.0000 Org/hr Pekerja 200,000.00 400,000.00
1,300,000.00 5,987,274.29 7,287,274.29
1 hari dapat 16 m' pancang dari dua alat a+b = 11,231,691.43
Biaya Pemancangan 1 m' = (a+b)/16 = 701,980.71
1 1 m' Tiang pancang pipa baja Ø 40 cm
1.0000 m' Tiang pancang baja Ø 40 cm 2,468,042.86 2,468,042.86
1.0000 m' Biaya Pemancangan 701,980.71 701,980.71
3,170,023.57 3,170,023.57
2 1 ttk Cor Beton Bertulang Strouss
1 titik Pengelasan Sambungan Tiang Pancang
10.0000 kg Plat sambung 16,437.14 164,371.43
2.0000 kg Kawat Las 33,687.14 67,374.29
0.2000 Hari Sewa mesin Las 650,000.00 130,000.00
0.2000 Hari Sewa Perahu 5,000,000.00 1,000,000.00
0.4000 Org/hr Tukang Las 257,142.86 102,857.14
0.8000 Org/hr Pekerja 200,000.00 160,000.00
0.2500 Org/hr Mandor 342,857.14 85,714.29
348,571.43 1,361,745.71 1,710,317.14
1 m' Sloof Beton bertulang 30/40
1 m' balok pengaku
49.9000 kg balok H beam 200 15,937.14 795,263.43
795,263.43 795,263.43
1 ttk pengelasan balok pengaku
1.5000 kg Kawat Las 33,687.14 50,530.71
0.2000 Hari Sewa mesin Las 650,000.00 130,000.00
0.2000 Hari Sewa Perahu 5,000,000.00 1,000,000.00
0.3000 Org/hr Tukang Las 257,142.86 77,142.86
0.6000 Org/hr Pekerja 200,000.00 120,000.00
0.2500 Org/hr Mandor 342,857.14 85,714.29
282,857.14 1,180,530.71 1,463,387.86
5 bh balok pengaku = 10 titik pengelasan = 14,633,878.57
5 bh balok pengaku @ 5 m' = 25 m' 14,633,878.57
Pengelasan balok pengaku 1 m ' = 585,355.14
3 1 m' Sloof Beton bertulang 30/40
1.0000 m' balok H beam 200 795,263.43 795,263.43
1.0000 m' Pengelasan balok pengaku 585,355.14 585,355.14
1,380,618.57 1,380,618.57
4 1 kg Lantai Kerja Lantai Block 2,5m x2,5m 10cm
1.0000 kg 1 kg 125,000.00 125,000.00
0.0250 Org/hr Tukang 228,571.43 5,714.29
0.5000 Org/hr Pekerja 200,000.00 100,000.00
105,714.29 125,000.00 230,714.29
1 M³ Membuat beton bertulang, 1Pc : 2Ps : 3Kr
1 m3 Spesi beton 1Pc : 2Ps : 3 Kr
336.0000 kg Semen portland Rp 5,237 Rp 1,759,680
0.5400 m³ Pasir beton Rp 5,709,500 Rp 3,083,130
0.8100 m³ Koral beton Rp 7,311,857 Rp 5,922,604
1.0000 Org/hr Mandor Rp 342,857 Rp 342,857
0.0350 Org/hr Kepala Tukang Rp 314,286 Rp 11,000
0.3500 Org/hr Tukang Batu Rp 228,571 Rp 80,000
2.0000 Org/hr Pekerja Rp 200,000 Rp 400,000
Rp 833,857 Rp 10,765,414 Rp 11,599,271

1 Kg Pembesian dengan besi polos


1.0500 kg Besi beton (polos) Rp 16,137 Rp 16,944
0.0150 kg Kawat beton (Bendrat) Rp 22,437 Rp 337
0.0040 Org/hr Mandor Rp 342,857 Rp 1,371
0.0007 Org/hr Kepala Tukang Besi Rp 314,286 Rp 220
0.0070 Org/hr Tukang Besi Rp 228,571 Rp 1,600
0.00035 Org/hr Pekerja Rp 200,000 Rp 70
Rp 3,261 Rp 17,281 Rp 20,542
5 1 m3 Beton bertulang Block Lantai 2,5m x2,5m 30cm
1 m3 Beton Bertulang
1.2000 m3 Spesi beton 1Pc : 2Ps : 3Kr Rp 11,599,271 Rp 13,919,126
110.0000 kg Pembesian Polos Rp 20,542 Rp 2,259,618
Rp 16,178,744 Rp 16,178,744
### 1 m3 #NAME?
1 m3 Beton Bertulang
1.2000 m3 Spesi beton 1Pc : 2Ps : 3Kr Rp 11,599,271 Rp 13,919,126
110.0000 kg Pembesian Polos Rp 20,542 Rp 2,259,618
Rp 16,178,744 Rp 16,178,744
### 1 m2 #NAME?
1 m² Pasang begesting
0.0800 m³ Kayu Meanti (MC) Rp 8,143,429 Rp 651,474
0.4000 kg Paku biasa 2"-5" Rp 18,787 Rp 7,515
0.2000 ltr Minyak begesting Rp 12,543 Rp 2,509
0.0150 m³ Balok kayu begesting Rp 8,793,429 Rp 131,901
0.3500 lbr Triplek tebal 9 mm Rp 201,931 Rp 70,676
2.0000 btg Dolken kayu galam Ø 8-10 / 4 m Rp 22,280 Rp 44,560
0.3000 Org/hr Mandor Rp 342,857 Rp 102,857
0.3300 Org/hr Kepala Tukang Rp 314,286 Rp 103,714
0.0330 Org/hr Tukang Kayu Rp 242,857 Rp 8,014
0.0060 Org/hr Pekerja Rp 200,000 Rp 1,200
Rp 215,786 Rp 908,635 Rp 1,124,421
### 1 m2 #NAME?
1 m² Pasang begesting
0.0600 m³ Kayu Meanti (MC) Rp 8,143,429 Rp 488,606
0.3000 kg Paku biasa 2"-5" Rp 18,787 Rp 5,636
0.1000 ltr Minyak begesting Rp 12,543 Rp 1,254
0.0050 Org/hr Mandor Rp 342,857 Rp 1,714
0.0260 Org/hr Kepala Tukang Rp 314,286 Rp 8,171
0.2600 Org/hr Tukang Kayu Rp 242,857 Rp 63,143
0.3000 Org/hr Pekerja Rp 200,000 Rp 60,000
Rp 133,029 Rp 495,496 Rp 628,525
### 1 m2 #NAME?
1 m' Tombak pengaman keliling anjungan
13.8000 kg Besi Beton diameter 19 Rp 16,137 Rp 222,693
0.7500 kg Kawat Las Rp 33,687 Rp 25,265
0.2000 Hari Sewa mesin Las Rp 650,000 Rp 130,000
0.1000 Org/hr Tukang Las Rp 257,143 Rp 25,714
0.3000 Org/hr Pekerja Rp 200,000 Rp 60,000
Rp 85,714 Rp 377,958 Rp 463,672
### 1 pkt #NAME?
1.0000 pkt #NAME? Rp 3,000,000 Rp 3,000,000
75.0000 kg Akomodasi (Angkutan) bahan sd. Lokasi Rp 3,937 Rp 295,286
Rp 3,295,286 Rp 3,295,286
6 1 m' Pagar anjungan Cor Beton
0.1000 m3 Spesi beton 1Pc : 2Ps : 3Kr Rp 11,599,271 Rp 1,159,927
1.5000 m3 #NAME? Rp 628,525 Rp 942,787
Rp 2,102,714 Rp 2,102,714
7 1 m2 Plesteran
PLESTERAN DAN ACIAN T= 1 cm
1 m2 Plsteran dan Acian
Plesteran
0.1500 zak Semen Portland (40 kg) Rp 261,857 Rp 39,279
0.0210 m3 Pasir Cor/Pasang Rp 5,709,500 Rp 119,900
0.0200 Org/hr Mandor Rp 342,857 Rp 6,857
0.0200 Org/hr Kepala Tukang Rp 314,286 Rp 6,286
0.2000 Org/hr Tukang Batu Rp 228,571 Rp 45,714
0.4000 Org/hr Pekerja Rp 200,000 Rp 80,000
Rp 138,857 Rp 159,178 Rp 298,035
1 m2 Acian
0.0813 zak Semen Portland (40 kg) Rp 261,857 Rp 21,276
0.0050 Org/hr Mandor Rp 342,857 Rp 1,714
0.0100 Org/hr Kepala Tukang Rp 314,286 Rp 3,143
0.1000 Org/hr Tukang Batu Rp 228,571 Rp 22,857
0.1000 Org/hr Pekerja Rp 200,000 Rp 20,000
Rp 47,714 Rp 21,276 Rp 68,990
Pekerjaan Plesteran dan Acian 1 m2 = Rp 367,025
0 PEKERJAAN STRUKTUR ATAS
1 Konstruksi Menara GRP Ø 150 - Ø 100 - Ø 150
1 Unit Konstruksi Menara GRP Ø 180 - Ø 100
1.0000 Unit Konstruksi Menara GRP Ø 150 - Ø 100 - Ø 150 200,000,000.00 200,000,000.00
112.0000 Kg Plat Strip Seteinless 253,937.14 28,440,960.00
410.0000 bh Mur Baut Steinless 82,984.29 34,023,557.14
900.0000 m3 Akomodasi (Angkutan) bahan sd. Lokasi 3,937.14 3,543,428.57
1.0000 ls Perakitan dan instalasi 5,000,000.00 5,000,000.00
8,543,428.57 262,464,517.14 271,007,945.71
2 Pagar pipa Ø1,5 " menara atas
1 m2 Pagar pipa Ø 1,5 " menara atas
16.0000 kg Pipa besi / baja Ø 1,5" 20,374.29 325,988.57
0.7500 kg Electrode baja (20%) 33,687.14 25,265.36
0.3500 Hari Sewa alat Las 650,000.00 227,500.00
0.4000 Org/hr Tukang Las 257,142.86 102,857.14
0.8000 Org/hr Pekerja 200,000.00 160,000.00
262,857.14 578,753.93 841,611.07
3 Pengecatan Menara
1 m2 Pengecatan menara 0 +30
0.6500 ltr Cat AF (anti Jamur0 Rp 101,543.43 Rp 66,003.23
0.0600 Org/hr Mandor Rp 342,857.14 Rp 20,571.43
0.0300 Org/hr Kepala Tukang Rp 15,937.14 Rp 478.11
0.6000 Org/hr Tukang cat Rp 228,571.43 Rp 137,142.86
0.6000 Org/hr Pekerja Rp 200,000.00 Rp 120,000.00
Rp 278,192.40 Rp 66,003.23 Rp 344,195.63
1 Unit Pengecatan menara GRP Ø160 - Ø150
48.4000 m2 Pengecatan Menara 344,195.63 Rp 16,659,068.42
Rp 16,659,068.42 16,659,068.42
0 PENGADAAN DAN INSTALASI PERALATAN SBNP
1 Sistem lampu suarflasing 10 NM
1 unit lampu suar flashing 10 NM
1.0000 unit Sistem lampu suarflasing 10 NM 85,000,000.00 85,000,000.00
0.7680 m3 Akomodasi (Angkutan) bahan sd. Lokasi 3,937,142.86 3,023,725.71
25.0000 kg Dudukan lampu Steinless (25kg) 253,937.14 6,348,428.57
1.0000 ls Pemasangan 1,605,000.00 1,605,000.00
7,953,428.57 88,023,725.71 95,977,154.29
2 Sistem proteksi petir
1 unit proteksi petir
1.0000 unit Sistem proteksi petir 4,500,000.00 4,500,000.00
1.0000 ls Pengkabelan dan konektor 3,750,000.00 3,750,000.00
1.0000 ls Pemasangan 1,000,000.00 1,000,000.00
4,750,000.00 4,500,000.00 9,250,000.00
3 Sistem tenaga surya solar cell 80 watt
1 Unit system tenaga surya
1.0000 unit Solarcell 60 wtt 7,539,371.43 7,539,371.43
1.0000 unit Box solarcell 489,371.43 489,371.43
1.0000 ls Pemasangan 750,000.00 750,000.00
750,000.00 8,028,742.86 8,778,742.86
4 Radar Reflektor
1 Unit system tenaga surya
1.0000 unit Radar Reflektor 4,500,000.00 4,500,000.00
1.0000 ls Pemasangan 350,000.00 350,000.00
350,000.00 4,500,000.00 4,850,000.00
6 URLA Absorbent Glass mate ( AGM) batteray 200 AH
1 unit URLA Absorbent Glass mate (AGM) batteray 100 AH
1.0000 unit Accu 100 AH 5,204,731.43 5,204,731.43
1.0000 unit Box battery 934,057.14 934,057.14
1.0000 ls Pemasangan 500,000.00 500,000.00
500,000.00 6,138,788.57 6,638,788.57
RINCIAN ANGGARAN BIAYA
RAMBU SUAR T. 10 M DARAT KONSTRUKSI GRP - FIBER

HARGA
NO URAIAN PEKERJAAN VOLUME
SATUAN JUMLAH
1 2 3 4 5
A PEKERJAAN PERSIAPAN
1 Direksi Keet 1.00 Unit Rp 5,000,000.00 Rp 5,000,000.00
2 Biaya angkut bahan meterial ke lokasi 1.00 Ls Rp 12,500,000.00 Rp 12,500,000.00
B PEKERJAAN STRUKTUR BAWAH
1 Bor Stouss 4 titik x 3 m' 60 x 60 cm 12.00 M' Rp 350,000.00 Rp 4,200,000.00
2 Cor Beton Bertulang Strouss 4.32 M3
Rp 6,500,000.00 Rp 28,080,000.00
3 Sloof Beton bertulang 30/40 1.20 M3
Rp 7,000,000.00 Rp 8,400,000.00
4 Lantai Kerja Lantai Block 2,5m x2,5m 10cm 0.63 M3
Rp 1,250,000.00 Rp 781,250.00
5 Beton bertulang Block Lantai 2,5m x2,5m 30cm 1.88 M3
Rp 6,000,000.00 Rp 11,250,000.00
6 Pagar anjungan Cor Beton 10.00 M' Rp 1,500,000.00 Rp 15,000,000.00
7 Plesteran 16.00 M2 Rp 275,000.00 Rp 4,400,000.00
PEKERJAAN STRUKTUR ATAS
1 Konstruksi Menara GRP Ø 150 - Ø 100 - Ø 150 1.000 Unit Rp 250,000,000.00 Rp 250,000,000.00
2 Pagar pipa Ø1,5 " menara atas 4.500 M2
Rp 900,000.00 Rp 4,050,000.00
3 Pengecatan Menara 1.000 Unit Rp 17,500,000.00 Rp 17,500,000.00
PENGADAAN DAN INSTALASI PERALATAN SBNP
1 Sistem lampu suarflasing 10 NM 1.000 Unit Rp 75,000,000.00 Rp 75,000,000.00
2 Sistem proteksi petir 1.000 Paket Rp 4,500,000.00 Rp 4,500,000.00
3 Sistem tenaga surya solar cell 80 watt 1.000 Paket Rp 3,500,000.00 Rp 3,500,000.00
4 Radar Reflektor 1.000 Unit Rp 2,500,000.00 Rp 2,500,000.00
5 Tanda Puncak 1.000 Unit Rp 2,500,000.00 Rp 2,500,000.00
6 URLA Absorbent Glass mate ( AGM) batteray 200 AH 1.000 Unit Rp 3,500,000.00 Rp 3,500,000.00
Rp 452,661,250.00
DIBULATKAN Rp 452,661,000.00