Perhitungan OB

LOKASI LUAS AREA (m2) ESTIMASITEBAL OB (m) VOLUME OB (m3) BULK DENSITY OB
LOKASI 1 1361 3 4083 1.6
LOKASI 2 1456 3 4368 1.6
LOKASI 3 2361 4 9444 1.6
LOKASI 4 5461 4 21844 1.6
TOTAL 39739
MASSA OB (ton) RITASE ESTIMASI PER RITASE TOTAL
OB YANG SUDAH DI MUAT
6532.8 2600 10 26000
6988.8
15110.4 ESTIMASI SISA OB 3758.24 10 37582.4
34950.4
63582.4 ESTIMASI MASA KERJA 37 HARI DENGAN CATATAN MINIMAL 100 TON/HARI