Anda di halaman 1dari 9

BILL OF QUANTITY (BOQ)

PAKET/ PEKERJAAN : PENGAWASAN JALAN PULAU SULABESI DAN PULAU MANGOLI


LOKASI KEGIATAN : KABUPATEN KEPULAUAN SULA
JANGKA WAKTU : 300 (TIGA RATUS) HARI KALENDER
TAHUN ANGGARAN : 2017

A. BIAYA LANGSUNG PERSONIL (REMUNIRATION/ BILLING RATE)

NO URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

I. Tenaga Profesional
Site Engineer (1 Orang x 10 Bln) OB 10 16,500,000.00 165,000,000.00
Chief Inspector (1 Orang x 10 Bln) OB 10 10,500,000.00 105,000,000.00

II. Tenaga Subprofesional


Inspector (1 Orang x 10 Bln) OB 10 4,000,000.00 40,000,000.00
Surveyor (2 Orang x 10 Bln) OB 20 3,000,000.00 60,000,000.00
Material & Lab. Technician (1 Orang x 10 Bln) OB 10 3,000,000.00 30,000,000.00

III. Supporting Staf


Administrasi (1 Orang x 10 Bln) OB 10 2,000,000.00 20,000,000.00
Draftman/CAD Operator (1 Orang x 10 Bln) OB 10 3,000,000.00 30,000,000.00
Office Boy (1 Orang x 10 Bln) OB 10 1,000,000.00 10,000,000.00

SUB TOTAL I 460,000,000.00

B. BIAYA LANGSUNG NON PERSONIL (DIRECT COST)


OE/ HPS
NO URAIAN SATUAN VOLUME
HARGA SATUAN JUMLAH HARGA

I Mobilisasi / Demobilisasi
1 Site Engineer Return 2 2,500,000.00 5,000,000.00
3 Chief Inspector Return 2 2,500,000.00 5,000,000.00
4 Inspector Return 2 1,000,000.00 2,000,000.00
5 Surveyor Return 4 1,000,000.00 4,000,000.00
6 Material Technician Return 2 1,000,000.00 2,000,000.00

II Biaya Perjalanan Dinas dan Hotel


1 Biaya Perjalanan Tiket/Ongkos Jalan OT 15 750,000.00 11,250,000.00
2 Biaya Sewa Hotel/Penginapan OT 15 350,000.00 5,250,000.00
II Sewa Kantor Profesional Staff Bln 10 2,000,000.00 20,000,000.00
III Sewa Rumah Profesional Staff Bln 10 2,000,000.00 20,000,000.00
IV Sewa Kamar Sub Profesional Staff (4 Kamar x 10 Bln) UB 40 700,000.00 28,000,000.00
V Sewa Motor (7 Unit x 10 Bln), Termasuk Biaya Operasional UB 70 650,000.00 45,500,000.00

VI Bahan Operasional Kantor


Sewa Komputer & Printer (3 Unit x 10 Bln) UB 30 1,000,000.00 30,000,000.00
Peralatan dan Bahan Operasional Kantor Bln 10 3,477,000.00 34,770,000.00
Komunikasi Kantor Bln 10 2,500,000.00 25,000,000.00

V Laporan
Laporan Pendahuluan + foto (1 x 5 ) Buku 5 400,000.00 2,000,000.00
Laporan Bulanan ( 10 x 5 ) Buku 50 500,000.00 25,000,000.00
Laporan Akhir ( 1 x 5 ) Buku 5 500,000.00 2,500,000.00

SUB TOTAL II 267,270,000.00


REKAPITULASI
PAKET/ PEKERJAAN : PENGAWASAN JALAN PULAU SULABESI DAN PULAU MANGOLI
LOKASI KEGIATAN : KABUPATEN KEPULAUAN SULA
JANGKA WAKTU : 300 (TIGA RATUS) HARI KALENDER
TAHUN ANGGARAN : 2017

NO. URAIAN TOTAL BIAYA (Rp.)

A. BIAYA LANGSUNG PERSONIL 460,000,000.00

B. BIAYA LANGSUNG NON-PERSONIL 267,270,000.00

JUMLAH A + B 727,270,000.00
PPN 10 % 72,727,000.00
JUMLAH TOTAL ( Termasuk PPN ) 799,997,000.00
DIBULATKAN 800,000,000.00

Terbilang : Delapan Ratus Juta Rupiah.

Mengetahui/Menyetujui
PEJABAT PEMBUAT KOMITMEN
DINAS PEKERJAAN UMUM PENATAAN RUANG PERUMAHAN
DAN KAWASAN PEMUKIMAN
KABUPATEN KEPULAUAN SULA

M. ISNAIN MASUKU, ST
NIP. 19730912 199603 1 003
BILL OF QUANTITY (BOQ)

PAKET/ PEKERJAAN : PENGAWASAN JALAN PULAU SULABESI DAN PULAU MANGOLI


LOKASI KEGIATAN : KABUPATEN KEPULAUAN SULA
JANGKA WAKTU : 300 (TIGA RATUS) HARI KALENDER
TAHUN ANGGARAN : 2017

A. BIAYA LANGSUNG PERSONIL (REMUNIRATION/ BILLING RATE)

NO URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

I. Tenaga Profesional
Site Engineer (1 Orang x 10 Bln) OB 10 16,400,000.00 164,000,000.00
Chief Inspector (1 Orang x 10 Bln) OB 10 10,400,000.00 104,000,000.00
II. Tenaga Subprofesional
Inspector (1 Orang x 10 Bln) OB 10 4,000,000.00 40,000,000.00
Surveyor (2 Orang x 10 Bln) OB 20 3,000,000.00 60,000,000.00
Material & Lab. Technician (1 Orang x 10 Bln) OB 10 3,000,000.00 30,000,000.00
III. Supporting Staf
Administrasi (1 Orang x 10 Bln) OB 10 2,000,000.00 20,000,000.00
Draftman/CAD Operator (1 Orang x 10 Bln) OB 10 3,000,000.00 30,000,000.00
Office Boy (1 Orang x 10 Bln) OB 10 1,000,000.00 10,000,000.00
SUB TOTAL I 458,000,000.00
B. BIAYA LANGSUNG NON PERSONIL (DIRECT COST)
OE/ HPS
NO URAIAN SATUAN VOLUME
HARGA SATUAN JUMLAH HARGA

I Mobilisasi / Demobilisasi
1 Site Engineer Return 2 2,400,000.00 4,800,000.00
3 Chief Inspector Return 2 2,400,000.00 4,800,000.00
4 Inspector Return 2 1,000,000.00 2,000,000.00
5 Surveyor Return 4 1,000,000.00 4,000,000.00
6 Material Technician Return 2 1,000,000.00 2,000,000.00
II Biaya Perjalanan Dinas dan Hotel
1 Biaya Perjalanan Tiket/Ongkos Jalan OT 15 750,000.00 11,250,000.00
2 Biaya Sewa Hotel/Penginapan OT 15 350,000.00 5,250,000.00
II Sewa Kantor Profesional Staff Bln 10 2,000,000.00 20,000,000.00
III Sewa Rumah Profesional Staff Bln 10 2,000,000.00 20,000,000.00
IV Sewa Kamar Sub Profesional Staff (4 Kamar x 10 Bln) UB 40 700,000.00 28,000,000.00
V Sewa Motor (7 Unit x 10 Bln), Termasuk Biaya Operasional UB 70 650,000.00 45,500,000.00
VI Bahan Operasional Kantor
Sewa Komputer & Printer (3 Unit x 10 Bln) UB 30 1,000,000.00 30,000,000.00
Peralatan dan Bahan Operasional Kantor Bln 10 3,400,000.00 34,000,000.00
Komunikasi Kantor Bln 10 2,400,000.00 24,000,000.00
V Laporan
Laporan Pendahuluan + foto (1 x 5 ) Buku 5 350,000.00 1,750,000.00
Laporan Bulanan ( 10 x 5 ) Buku 50 500,000.00 25,000,000.00
Laporan Akhir ( 1 x 5 ) Buku 5 500,000.00 2,500,000.00
SUB TOTAL II 264,850,000.00
REKAPITULASI
PAKET/ PEKERJAAN : PENGAWASAN JALAN PULAU SULABESI DAN PULAU MANGOLI
LOKASI KEGIATAN : KABUPATEN KEPULAUAN SULA
JANGKA WAKTU : 300 (TIGA RATUS) HARI KALENDER
TAHUN ANGGARAN : 2017

NO. URAIAN TOTAL BIAYA (Rp.)

A. BIAYA LANGSUNG PERSONIL 458,000,000.00

B. BIAYA LANGSUNG NON-PERSONIL 264,850,000.00

JUMLAH A + B 722,850,000.00
PPN 10 % 72,285,000.00
JUMLAH TOTAL ( Termasuk PPN ) 795,135,000.00
DIBULATKAN 795,140,000.00

Terbilang : Delapan Ratus Juta Rupiah.

Ternate, 27 Februari 2017

PT. HALEYORA PERENCANA JAYA INDOENSIA

……………………………
……………………………………
KEGIATAN : PERENCANAAN PEMBANGUNAN PRASARANA DAN FASILITAS PERHUBUNGAN
PAKET : PERENCANAAN DID PELABUHAN SALAKAN
LOKASI : SALAKAN KECAMATAN TINANGKUNG
TAHUN ANGGARAN : 2018

I. TENAGA AHLI

JUMLAH JUMLAH
NO URAIAN HARGA SATUAN JUMLAH HARGA
ORANG BULAN

1 Ahli Perencanaan Pelabuhan (Team Leader) 1 5 15,500,000.00 77,500,000.00


2 Ahli Konstruksi 1 5 8,500,000.00 42,500,000.00
3 Ahli Geodesi 1 5 8,500,000.00 42,500,000.00
4 Ahli Transportasi Operasional Pelabuhan 1 5 8,500,000.00 42,500,000.00
5 Ahli Laboratorium 1 5 8,500,000.00 42,500,000.00
6 Ahli Arsitektur 1 5 8,500,000.00 42,500,000.00
Jumlah 290,000,000.00

II. TENAGA PENDUKUNG / TEKNIS

JUMLAH JUMLAH
NO URAIAN HARGA SATUAN JUMLAH HARGA
ORANG BULAN

1 Bor Master 1 5 4,000,000.00 20,000,000.00


2 Surveyor 2 5 4,000,000.00 20,000,000.00
3 Assisten Bor Master 1 5 3,000,000.00 15,000,000.00
4 Drafter 1 5 2,500,000.00 12,500,000.00
5 Operator Komputer/Administrasi 1 5 2,500,000.00 12,500,000.00
6 Office Boy 1 5 2,000,000.00 10,000,000.00
Jumlah 90,000,000.00

III. BIAYA PENINJAUAN LAPANGAN

NO URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

A Transportasi
1 Daerah asal- Luwuk (PP) Trip 4 1,300,000.00 5,200,000.00
2 Luwuk - Lokasi (PP) Trip 4 150,000.00 600,000.00
3 akomodasi Trip 4 1,500,000.00 6,000,000.00

B Allowance
1 Ahli Perencanaan Pelabuhan Orang Hari 5 750,000.00 3,750,000.00
2 Ahli Konstruksi Orang Hari 5 750,000.00 3,750,000.00
3 Ahli Estimasi Biaya Orang Hari 5 500,000.00 2,500,000.00
4 akomodasi Orang Hari 15 450,000.00 6,750,000.00
Jumlah 28,550,000.00
IV. MOBILISASI DAN DEMOBILISASI

NO URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

A Peralatan
1 Asal - luwuk (PP) Trip 2 2,800,000.00 5,600,000.00
2 Luwuk - Lokasi (PP) Trip 2 1,800,000.00 3,600,000.00

B Personil
1 Asal - luwuk (PP) Orang Hari 6 1,500,000.00 9,000,000.00
2 Luwuk - Lokasi (PP) Orang Hari 6 150,000.00 900,000.00
Jumlah 19,100,000.00

V. SURVEY LAPANGAN
V 1. Survey Topografi / Bathimetri / Hidro-oseanografi

NO URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

A Personil
Surveyor (2 Orang) Orang Hari 2 x 6 500,000.00 6,000,000.00
Tenaga bantu/buruh lokal (2 Orang) Orang Hari 2 x 6 200,000.00 2,400,000.00
Tenaga Pengamat Pasut (2 Orang) Orang Hari 2 x 15 150,000.00 4,500,000.00
Akomodasi Orang Hari 6 x 27 50,000.00 8,100,000.00

B Peralatan Survey
Handy Talky (2 Unit) Unit/Hari 2 x 12 350,000.00 4,200,000.00
Pembuatan Palem Unit 1 3,500,000.00 3,500,000.00
GPS Unit/Hari 12 400,000.00 4,800,000.00
Echosounder Unit/Hari 12 1,300,000.00 15,600,000.00
Theodolit (2 Unit) Unit/Hari 2 x 12 1,400,000.00 33,600,000.00
Current Meter Unit/Hari 12 300,000.00 3,600,000.00
Survey Boat Hari 10 500,000.00 5,000,000.00
Accu Buah 3 1,000,000.00 3,000,000.00
Jumlah 94,300,000.00

V 2. Penyelidikan Tanah

NO URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

A Personil
Surveyor (2 Orang) Orang Hari 1 x 15 550,000.00 8,250,000.00
Tenaga bantu/buruh lokal (2 Orang) Orang Hari 1 x 15 200,000.00 3,000,000.00
Tenaga Pengamat Pasut (2 Orang) Orang Hari 2 x 12 400,000.00 4,800,000.00
Akomodasi Orang Hari 4 x 42 100,000.00 4,200,000.00

B Pekerjaan Lapangan
Boring Meter 20 500,000.00 10,000,000.00
Sampel Grab Titik 3 1,400,000.00 4,200,000.00
Platform Boring Buah 5 500,000.00 2,500,000.00
Standard Penetration Test Test 20 100,000.00 2,000,000.00
Alat Boring Hari 15 1,000,000.00 15,000,000.00
Survey Boat Hari 20 500,000.00 10,000,000.00
Jumlah 63,950,000.00
V 3. Laboratorium Test

NO URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

Grain Size Analisis Test 15 500,000.00 7,500,000.00


Spesifik Grafity Test 15 500,000.00 7,500,000.00
Suspensi dan Salinity Test 12 500,000.00 6,000,000.00
Kadar Sedimentasi Test 8 300,000.00 2,400,000.00

Jumlah 23,400,000.00

VI 3.SEMINAR DAN PEMBUATAN LAPORAN

NO URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

1 Laporan Pendahuluan Buku 5 150,000.00 750,000.00


2 Seminar Laporan Pendahuluan Buku 1 8,000,000.00 8,000,000.00
3 Laporan Antara Buku 5 200,000.00 1,000,000.00
4 Seminar Laporan Antara Buku 1 9,500,000.00 9,500,000.00
5 Laporan Draft Akhir Buku 5 500,000.00 2,500,000.00
6 Laporan Akhir Buku 5 700,000.00 3,500,000.00
7 Seminar Laporan Antara dan Akhir Buku 1 11,000,000.00 11,000,000.00
8 Ringkasan Eksekutif Buku 5 500,000.00 2,500,000.00
9 Album Peta/Gambar (A3) Buku 5 2,100,000.00 10,500,000.00
10 Soft Copy Laporan (CD) Keping 5 40,000.00 200,000.00
11 Soft Copy Laporan (FD) Buah 2 150,000.00 300,000.00

Jumlah 49,750,000.00
REKAPITULASI

KEGIATAN : PERENCANAAN PEMBANGUNAN PRASARANA DAN FASILITAS PERHUBUNGAN


PAKET : PERENCANAAN DID PELABUHAN SALAKAN
LOKASI : SALAKAN KECAMATAN TINANGKUNG
TAHUN ANGGARAN : 2018

NO URAIAN JUMLAH HARGA

I TENAGA AHLI 290,000,000.00


II TENAGA PENDUKUNG / TEKNIS 90,000,000.00
III BIAYA PENINJAUAN LAPANGAN 28,550,000.00
IV MOBILISASI DAN DEMOBILISASI 19,100,000.00
V SURVEY LAPANGAN
V.1 Survey Topografi / Bathimetri / Hidro-oseanografi 94,300,000.00
V.2 Penyelidikan Tanah 63,950,000.00
V.3 Laboratorium Test 23,400,000.00
VI SEMINAR DAN PEMBUATAN LAPORAN 49,750,000.00
JUMLAH 659,050,000.00
PPN 10% 65,905,000.00
JUMLAH TOTAL 724,955,000.00
PEMBULATAN 724,950,000.00
Terbilang : Tujuh Ratus Dua Puluh Empat Juta Sembilan Ratus Lima Puluh Ribu Rupiah