II PEMBORAN TEKNIK
2.1 Pemboran Inti 3 titik (3 X SPT 60) Titik 3 25,000,000
2.2 Pengambilan Contoh Tanah (UDS) Tabung 6 250,000
2.3 Pengadaan Corebox Buah 3 250,000
Sub Jumlah II
III PEMERIKSAAN LABORATORIUM
3.1 Test Laboratorium Titik - -
3.2 Laporan Ls - -
Sub Jumlah III
IV Sewa Kendaraan
4.1 Sewa Truk Ls 1 35,000,000
Sub Jumlah IV
Yodi Litha, ST
Pimpinan Teknis
NAWARAN BIAYA PEMBORAN JEMBATAN KALI KILL
JUMLAH HARGA
20,000,000
1,600,000
21,600,000
75,000,000
1,500,000
750,000
77,250,000
-
-
-
35,000,000
35,000,000
133,850,000
Yodi Litha, ST
Pimpinan Teknis
PENAWARAN BIAYA PEMBORAN
II SOIL INVESTIGASI
2.1 Sondir Titik 3 4,500,000 13,500,000
2.2 Laporan Buku 1 1,000,000 1,000,000
Sub Jumlah II 13,500,000
Total Biaya (I + II + III + IV) 20,000,000
Yodi Litha, ST
Pimpinan Teknis