TUGAS KULIAH

MANAJEMEN DAN TEKNOLOGI PRODUKSI KAPAL

Disusun oleh:
Philipus Valentino
21090117130062
Kelas C

DEPARTEMEN TEKNIK PERKAPALAN


FAKULTAS TEKNIK
UNIVERSITAS DIPONEGORO
2020
⚫ Tentukan:
1. Estimation cost and schedule dengan membuat earn value
analysis pada 50% duration project dengan
mengasumsikan sendiri incure cost pada field report end
of date?
2. Lakukan project crashing bila project saving/ day 600
sam?

Jawab:

1. Earn value analysis


Report Date

A
B
C
D
E
F
G
H
I
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Field Report
Field Report at End of Day
Act Actual 100% Complete Incurred Cost
A 100 2550
B 100 1100
C 100 2400
D 25 350
E 50 200
F 50 1550
G 0 0
H 0 0
I 0 0

Act ACWP BCWP BCWS CPI CV SPI SV


A 2550 2500 2500
B 1100 1250 1250
C 2400 2400 2400
D 350 400 800
E 200 150 300
F 1550 1600 2400
G 0 0
H 0 0
I 0 0
Total to 8150 8300 9640 8300/8150 = 8300-8150 = 8300/9640 = 8300-9640 =
date 1.018 150 0.860 -1340
Under budget under budget Behind of Behind of
schedule schedule
2. Project crashing (project saving 60/day)

Normal Normal Crash Crash Max


Act Pred. Slope
time cost Time cost Crash
(575-500)/(5-2)
A - 5 500 2 575 3
= 25
(550-250)/(5-2)
B A 5 250 2 550 3
= 100
(600-600)/(4-4)
C A 4 600 4 600 0
=0
(400-400)/(4-4)
D B 4 400 4 400 0
=0
(250-150)/(2-1)
E B 2 150 1 250 1
=100
(850-800)/(4-3)
F C 4 800 3 850 1
= 50
(900-500)/(6-2)
G D 6 500 2 900 4
= 100
(600-600)/(3-3)
H E, F 3 600 3 600 0
=0
(300-300)/(3-3)
I G, H 3 300 3 300 0
=0
Initial AON A-1 Run 1
Activity Nt Ct Slope TF Activity D.S Dur TF
A 5 2 25 0 A 1 4 0
B 5 2 100 0 B 5 0
C 4 4 0 4 C 4 4
D 4 4 0 0 D 4 0
E 2 1 100 5 E 2 5
F 4 3 50 4 F 4 4
G 6 2 100 0 G 6 0
H 3 3 0 4 H 3 4
I 3 3 0 0 I 3 0
Cost - Cost 25
Saving - Saving 60
Project Cost 4100 Project Cost 4065
Project Duration 23 Project Duration 22

AON A-2 Run 2 AON A-3 Run 3


Activity D.S Dur TF Activity D.S Dur TF
A 1 3 0 A 1 2 0
B 5 0 B 5 0
C 4 4 C 4 4
D 4 0 D 4 0
E 2 5 E 2 5
F 4 4 F 4 4
G 6 0 G 6 0
H 3 4 H 3 4
I 3 0 I 3 0
Cost 25 Cost 25
Saving 60 Saving 60
Project Cost 4030 Project Cost 3995
Project Duration 21 Project Duration 20
AON B-1 Run 4 AON B-2 Run 5 AON B-3 Run 6
Activity D.S Dur TF Activity D.S Dur TF Activity D.S Dur TF
A 2 0 A 2 0 A 2 0
B 1 4 0 B 1 3 0 B 1 2 0
C 4 3 C 4 2 C 4 1
D 4 0 D 4 0 D 4 0
E 2 5 E 2 5 E 2 5
F 4 3 F 4 4 F 4 1
G 6 0 G 6 0 G 6 0
H 3 3 H 3 2 H 3 1
I 3 0 I 3 0 I 3 0
Cost 100 Cost 100 Cost 100
Saving 60 Saving 60 Saving 60
Project Cost 4035 Project Cost 4075 Project Cost 4115
Project Duration 19 Project Duration 18 Project Duration 17

AON G-1 Run 7


Activity D.S Dur TF
A 2 0
B 2 0
C 4 0
D 4 0
E 2 4
F 4 0
G 1 5 0
H 3 0
I 3 0
Cost 100
Saving 60
Project Cost 4155
Project Duration 16
AON G-2 Run 8 AON G-3 Run 9 AON G-4 Run 10
Activity D.S Dur TF Activity D.S Dur TF Activity D.S Dur TF
A 2 0 A 2 0 A 2 0
B 2 1 B 2 2 B 2 3
C 4 0 C 4 0 C 4 0
D 4 1 D 4 2 D 4 3
E 2 4 E 2 4 E 2 4
F 4 0 F 4 0 F 4 0
G 1 4 1 G 1 3 2 G 1 2 3
H 3 0 H 3 0 H 3 0
I 3 0 I 3 0 I 3 0
Cost 100 Cost 100 Cost 100
Saving 60 Saving 60 Saving 60
Project Cost 4195 Project Cost 4235 Project Cost 4275
Project Duration 16 Project Duration 16 Project Duration 16

Activity on Node Diagram and Critical Path


Initial

Run 1 on Activity A (Day Saving = 1)


Run 2 on Activity A (Day Saving = 1)

Run 3 on Activity A (Day Saving = 1)


Run 4 on Activity B (Day Saving = 1)

Run 5 on Activity B (Day Saving = 1)


Run 6 on Activity B (Day Saving = 1)

Run 7 on Activity G (Day Saving = 1)


Run 8 on Activity G (Day Saving = 1)

Run 9 on Activity G (Day Saving = 1)


Run 10 on Activity G (Day Saving = 1)