Max.

Crash
Predecess Normal Crash Normal Crash Crash cost per Days to
Activity ors Time Time Cost Cost Time day crash Y ES
A 8 6 100 200 2 50 0
B 4 2 150 350 2 100 0
C A 2 1 50 90 1 40 8
D A 10 5 100 400 5 60 8
E B 5 1 100 200 4 25 4
F C, E 3 1 80 100 2 10 10

VAR.
Realized Critical
EF LF LS SLACK Time Path
8 8 0 0 8 A
4 10 6 6 4
10 15 13 5 2
18 18 8 0 10 D
9 15 10 6 5
13 18 15 5 3
Max. Crash
Normal Normal Crash Crash cost per Days to
Activity Pendahulu Time Crash Time Cost Cost Time week crash Y
A 16 8 2000 4400 8 300 6
B 14 9 1000 1800 5 160 2
C A 8 6 500 700 2 100 0
D A 5 4 600 1300 1 700 0
E B 4 2 1500 3000 2 750 0
F B 6 4 800 1600 2 400 0
G C 10 7 3000 4500 3 500 0
H D, E 15 10 5000 8000 5 600 3

VARIABEL
Total Costs 18320
Min. Total crash costs 3920
Umur proyek yang diinginkan 28
AKTIVITAS TANPA P
Realized Critical
ES EF LF LS SLACK Time Path
0 10 10 0 0 10 A
0 12 12 0 0 12 B
10 18 18 10 0 8 C
10 15 16 11 1 5
12 16 16 12 0 4 E
12 18 28 22 10 6
18 28 28 18 0 10 G
16 28 28 16 0 12 H

AKTIVITAS TANPA PENGIKUT : LF=MAX(EF)

AKTIVITAS TANPA PENDAHULU : ES = 0


Max. Crash
Normal Crash Normal Crash Crash cost per Days to
Activity Predecessors Time Time Cost Cost Time day crash Y ES
A 12 7 3000 5000 5 400 0
B A 8 5 2000 3500 3 500 12
C A 4 3 4000 7000 1 3000 12
D B, C 12 9 50000 71000 3 7000 20
E B, C 4 1 500 1100 3 200 20
F E 4 1 500 1100 3 200 24
G D, F 4 3 15000 22000 1 7000 32

VAR.

UPDP = 23
Realized Critical
EF LF LS SLACK Time Path
12 12 0 0 12 A
20 20 12 0 8 B
16 20 16 4 4
32 32 20 0 12 D
24 28 24 4 4
28 32 28 4 4
36 36 32 0 4 G
Max. Days to
Normal Normal Crash Crash Crash cost crash
Activity Predecessors Time Crash Time Cost Cost Time per day Y ES
A 12 7 3000 5000 5 400 0
B A 8 5 2000 3500 3 500 12
C A 4 3 4000 7000 1 3000 12
D B, C 12 9 50000 71000 3 7000 20
E B, C 4 1 500 1100 3 200 20
F E 4 1 500 1100 3 200 24
G D, F 4 3 15000 22000 1 7000 32

VAR.
Total Costs 75000
Min. Total crash costs 0
Umur proyek yang diinginkan
Realized Critical
EF LF LS SLACK Time Path
12 12 0 0 12 A
20 20 12 0 8 B
16 20 16 4 4
32 32 20 0 12 D
24 28 24 4 4
28 32 28 4 4
36 36 32 0 4 G

Jika terdapat satu aktivitas yang tidak mempunyai aktivitas pengikut, maka :
LF = EF
Jika terdapat lebih dari satu aktivitas yang tidak mempunyai aktivitas pengikut,
maka :
LF = max( EF dari seluruh aktivitas yang tidak mempunyai aktivitas pengikut)
Max. Crash
Activity Predecessors Normal Time Crash Time Normal Cost Crash Cost Time
A 9 7 4800 6300 2
B 11 9 9100 15500 2
C A 7 5 3000 4000 2
D A 10 8 3600 5000 2
E B, C 1 1 0 0 0
F B, C 5 3 1500 2000 2
G D, E 6 5 1800 2000 1
H D, E 3 3 0 0 0
I H 1 1 0 0 0
J F, G 2 2 0 0 0
K G, I 8 6 5000 7000 2

Penyelesaian proyek maksimum dapat dipercepat =


Crash cost per Days to crash
day Y ES EF LF LS SLACK
750 2 0 7 7 0 0
3200 0 0 11 14 3 3
500 0 7 14 14 7 0
700 2 7 15 15 7 0
0 0 14 15 15 14 0
250 0 14 19 24 19 5
200 1 15 20 20 15 0
0 0 15 18 19 16 1
0 0 18 19 20 19 1
0 0 20 22 26 24 4
1000 2 20 26 26 20 0

7 minggu
Realized Time Critical Path
7 A
11
7 C
8 D
1 E
5
5 G
3
1
2
6 K
Max. Crash
Normal Crash Normal Crash Crash cost per Days to
Activity Predecessors Time Time Cost Cost Time day crash Y ES
A 9 7 4800 6300 2 750 2 0
B 11 9 9100 15500 2 3200 0 0
C A 7 5 3000 4000 2 500 0 7
D A 10 8 3600 5000 2 700 2 7
E B, C 1 1 0 0 0 0 0 14
F B, C 5 3 1500 2000 2 250 0 14
G D, E 6 5 1800 2000 1 200 1 15
H D, E 3 3 0 0 0 0 0 15
I H 1 1 0 0 0 0 0 18
J F, G 2 2 0 0 0 0 0 20
K G, I 8 6 5000 7000 2 1000 2 20

Biaya percepatan proyek = 5100 satuan mata uang


Aktivitas Dipercepat
A 2 minggu
D 2 minggu
G 1 minggu
K 2 minggu
Realized Critical
EF LF LS SLACK Time Path
7 7 0 0 7 A
11 14 3 3 11
14 14 7 0 7 C
15 15 7 0 8 D
15 15 14 0 1 E
19 24 19 5 5
20 20 15 0 5 G
18 19 16 1 3
19 20 19 1 1
22 26 24 4 2
26 26 20 0 6 K
Activity Predecessors a b m t ragam ES EF LF
A 1 3 2 2 0.111 0 2 2
B 2 4 3 3 0.111 0 3 4
C A 1 3 2 2 0.111 2 4 4
D A, B 2 6 4 4 0.444 3 7 8
E C 1 7 4 4 1.000 4 8 8
F C 1 9 2 3 1.778 4 7 13
G D, E 3 11 4 5 1.778 8 13 13
H F, G 1 3 2 2 0.111 13 15 15

ragam proyek = 3.111 minggu2


Peluang proyek dapat selesai paling lambat 16 minggu = 71.462 %
Critical
LS SLACK Path
0 0 1
1 1
2 0 1
4 1
4 0 1
10 6
8 0 1
13 0 1
𝐸𝑆=𝑀𝐴𝑋.(𝐸𝐹 𝐴𝐾𝑇𝐼𝑉𝐼𝑇𝐴𝑆 𝑃𝐸𝑁𝐷𝐴𝐻𝑈𝐿𝑈 𝐿𝐴𝑁𝐺𝑆𝑈𝑁𝐺)
EF = ES + t

LF = MIN.(LS AKTIVITAS PENGIKUT LANGSUNG)


LS = LF - t
Activity Predecessors a b m t ragam ES EF
A 5 17 8 9 4 0 9
B 3 15 12 11 4 0 11
C A 4 10 7 7 1 9 16
D A 5 23 8 10 9 9 19
E B, C 1 1 1 1 0 16 17
F B, C 1 13 4 5 4 16 21
G D, E 3 9 6 6 1 19 25
H D, E 1 7 2.5 3 1 19 22
I H 1 1 1 1 0 22 23
J F, G 2 2 2 2 0 25 27
K G, I 5 11 8 8 1 25 33
FINISH J, K 0 0 0 0 0 33 33

ragam umur proyek = 15


Peluang proyek akan selesai paling lambat 40 minggu = 96.465 %
Critical
LF LS SLACK Path
9 0 0 1
18 7 7
18 11 2
19 9 0 1
19 18 2
31 26 10
25 19 0 1
24 21 2
25 24 2
33 31 6
33 25 0 1
33 33 0 1
Activity Predecessors a b m t ragam ES EF
A 1 3 2 2 0.1111111 0 2
B 2 8 5 5 1 0 5
C 1 5 3 3 0.4444444 0 3
D A 4 25 10 11.5 12.25 2 13.5
E A 3 12 7 7.166666667 2.25 2 9.1666667
F B 10 25 15 15.83333333 6.25 5 20.833333
G C 5 14 9 9.166666667 2.25 3 12.166667
H D, E 2 7 3 3.5 0.6944444 13.5 17
I D, E, F 1 6 4 3.833333333 0.6944444 20.833333 24.666667
J D, E, F, G 2 10 5 5.333333333 1.7777778 20.833333 26.166667
K H, I J 2 2 2 2 0 26.166667 28.166667

ragam umur proyek = 9.028


Peluang proyek akan selesai di atas 35 minggu = 1.147 %
Critical
LF LS SLACK Path
9.3333333 7.3333333 7.3333333
5 0 0 1
11.666667 8.6666667 8.6666667
20.833333 9.3333333 7.3333333
20.833333 13.666667 11.666667
20.833333 5 0 1
20.833333 11.666667 8.6666667
26.166667 22.666667 9.1666667
26.166667 22.333333 1.5
26.166667 20.833333 0 1
28.166667 26.166667 0 1
Activity Predecessors a b m t ragam ES EF
A 1 3 2 2 0.11111111 0 2
B A 2 4 3 3 0.11111111 2 5
C B 1 3 2 2 0.11111111 5 7
D B 10 20 14 14.333333 2.77777778 5 19.333333
E B 4 10 7 7 1 5 12
F B 4 10 7 7 1 5 12
G E 18 32 24 24.333333 5.44444444 12 36.333333
H C 4 10 6 6.3333333 1 7 13.333333
I D, F, G, H 10 16 12 12.333333 1 36.33333333 48.666667
J I 8 20 12 12.666667 4 48.66666667 61.333333
K J 1 3 2 2 0.11111111 61.33333333 63.333333
L K 2 5 4 3.8333333 0.25 63.33333333 67.166667
M L 1 4 2 2.1666667 0.25 67.16666667 69.333333
N M 1 2 2 1.8333333 0.02777778 69.33333333 71.166667

ragam umur proyek = 12.306 minggu2


Peluang proyek selesai dalam 1 tahun (52 minggu) = 0.000 %
Peluang proyek selesai dalam 18 bulan (78 minggu )= 97.429 %
Critical
LF LS SLACK Path
2 0.000 0 1
5 2.000 0 1
30 28.000 23
36.333333 22.000 17
12 5.000 0 1
36.333333 29.333 24
36.333333 12.000 0 1
36.333333 30.000 23
48.667 36.333 0 1
61.333 48.667 0 1
63.333 61.333 0 1
67.167 63.333 0 1
69.333 67.167 0 1
71.166667 69.333 0 1