SOAL
Pekerjaan Pekerjaan
Durasi
No. Kegiatan Yang Yang Biaya (Rp.)
(Hari)
mendahului mengikuti
1 A - D 11 200,000.00
2 B - E, F 12 400,000.00
3 C - G 15 900,000.00
4 D A H 5 150,000.00
5 E B H 8 300,000.00
6 F B - 28 950,000.00
7 G C - 14 850,000.00
8 H D, E - 11 700,000.00
NETWORK PLANNING
11 D 20
1 24 5
4 29
A E H
11 8 11 40
0 0 B 2 12 F 5 40
0 12 12 28
C G
15 14
15
3 26
Total Hari ke -
No. Kegiatan Durasi Keterangan
Float 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
1 A 11 13
2 B 12 0
3 C 15 11
4 D 5 13
5 E 8 9
6 F 28 0
7 G 14 11
8 H 11 9
KETERANGAN :
DURASI (Dij)
Free Hari ke -
No. Kegiatan Durasi Keterangan
Float 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
1 A 11 0
2 B 12 0
3 C 15 0
4 D 5 4
5 E 8 0
6 F 28 0
7 G 14 11
8 H 11 9
KETERANGAN :
DURASI (Dij)
KURVA S
Bobot Hari ke -
No. Kegiatan Biaya (Rp.) Keterangan
(%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
1 A 200,000 4.49 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 100%
2 B 400,000 8.99 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7
3 C 900,000 20.22 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3 1.3
4 D 150,000 3.37 0.7 0.7 0.7 0.7 0.7
5 E 300,000 6.74 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 50%
6 F 950,000 21.35 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8
7 G 850,000 19.10 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4
8 H 700,000 15.73 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4 1.4
JUMLAH 4,450,000 100.00 0%
RENCANA PROGRES HARIAN 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.8 3.6 3.6 3.6 3.6 3.0 3.0 3.0 3.0 3.6 3.6 3.6 3.6 3.6 3.6 3.6 3.6 3.6 2.2 2.2 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8