1. WBS Jembatan Rangka Baja


PEMBUATAN
JEMBATAN RANGKA
BAJA

TAHAPAN PEKERJAAN PEKERJAAN PEKERJAAN PEKERJAAN PEKERJAAN PEKERJAAN FINISHING


PERSIAPAN TANAH TIANG PANCANG BETON 1 BAJA BETON 2 PERKERASAN

PENYELIDIKAN GALIAN PEMASANGAN DINDING GIRDER DAN PLAT PENGASPALAN CAT (RANGKA
TANAH TIANG PANCANG PENAHAN DIAFRAGMA JEMBATAN DAN
TANAH JEMBATAN TROTOAR TROTOAR)
TIMBUNAN
PEMBERSIHAN
ABUTMENT RANGKA INSTALASI
LOKASI
ANGKUTAN BAJA LAMPU
TANAH OPRIT PENERANGAN
PENGUKURAN JEMBATAN JALAN
INSTALASI
DAN SAMBUNGAN
PEMASANGAN PILECAP RANGKA PEMASANGAN
BLOWPLANK RAMBU LALU
PILAR LINTAS
JEMBATAN
2. Perhitungan Penjadwalan
a. Metode CPM
KEGIATAN SEBELUM SESUDAH DURASI (W)
A - D 10
B - D,E 5
C - E,F 3
D A,B G 12
E B,C H 7
F C I 4
G D J 9
H E J 6
I F J 6
J G,H,I - 2
b. Dari gambar CPM diatas dapat diambil kesimpulan bahwa jalur kritisnya adalah A-D-G-J
c. Tabel Float
Aktivitas Durasi (W) TF FF IF
A 10 0 0 0
B 5 5 0 0
C 3 15 0 0
D 12 0 0 0
E 7 13 0 -13
F 4 18 0 -15
G 9 0 0 0
H 6 13 0 -13
I 6 18 0 -18
J 2 0 0 0
Dari table float diatas dapat diambil kesimpulan bahwa jalur kritisnya adalah A-D-G-J
3. Gantt Chart dan Kurva S dari soal nomor 3 adalah sebagai berikut ( asumsi bobot proyek bernilai bebas )
DURASI (WEEK)
KEGIATAN BOBOT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33
A 3 0,3000 0,3000 0,3000 0,3000 0,3000 0,3000 0,3000 0,3000 0,3000 0,3000
B 4 0,8000 0,8000 0,8000 0,8000 0,8000
C 2 0,6667 0,6667 0,6667
D 28 2,3333 2,3333 2,3333 2,3333 2,3333 2,3333 2,3333 2,3333 2,3333 2,3333 2,3333 2,3333
E 4 0,5714 0,5714 0,5714 0,5714 0,5714 0,5714 0,5714
F 9 2,2500 2,2500 2,2500 2,2500
G 7 0,7778 0,7778 0,7778 0,7778 0,7778 0,7778 0,7778 0,7778 0,7778
H 31 5,1667 5,1667 5,1667 5,1667 5,1667 5,1667
I 8 1,3333 1,3333 1,3333 1,3333 1,3333 1,3333
J 4 2,0000 2,0000
TOTAL 100
PROGRES RENCANA 1,7667 1,7667 1,7667 3,3500 3,3500 3,1214 3,1214 2,2048 2,2048 2,2048 4,2381 4,2381 8,8333 7,5000 7,5000 7,5000 7,5000 7,5000 2,3333 2,3333 2,3333 2,3333 0,7778 0,7778 0,7778 0,7778 0,7778 0,7778 0,7778 0,7778 0,7778 2,0000 2,0000
PROGRES KUMULATIF 1,7667 3,5333 5,3000 8,6500 12,0000 15,1214 18,2429 20,4476 22,6524 24,8571 29,0952 33,3333 42,1667 49,6667 57,1667 64,6667 72,1667 79,6667 82,0000 84,3333 86,6667 89,0000 89,7778 90,5556 91,3333 92,1111 92,8889 93,6667 94,4444 95,2222 96,0000 98,0000 100,0000
4. Diketahui data PDM sebagai berikut:

Perhitungan Maju:
1) Clear & Grade 1 ( duration = 8 )
• ES (1) = 0
• EF (1) = ES (1) + D(A) = 0 + 8 = 8
2) Con. Forms 1 ( duration = 12 )
• ES (2) = EF (1) + FS (1,2) = 8 + 0 = 8
• EF (2) = ES (2) + D (2) = 8 + 12 = 20
3) Sewe Lines 1 ( duration = 16 )
• ES (3) diambil nilai terbesar :
• EF (2) + FF (2,3) – D (3) = 20 + 2 – 16 = 0
• EF (1) + FF (1,3) = 8 + 0 = 8

• EF (3) = ES (3) + D(3) = 8 + 16 = 22


4) Reinforcement 1 ( duration = 9 )
• ES (4) diambil nilai terbesar :
• EF (2) + FF (2,4) – D (4) = 20 + 1 – 9 = 12
• ES (2) + SS (2,4) = 8 + 7 = 15
• ES (3) + SS (3,4) = 8 + 7 = 15
• EF (3) = ES (3) + D (3) = 15 + 9 = 24
5) Pour Concrete 1 ( duration = 4 )
• ES (5) = EF (4) + FS (4,5) = 24 + 2 = 26
• EF (5) = ES (5) + D (5) = 26 + 4 = 30
6) Clear & Grade 2 ( duration = 8 )
• ES (6) = EF (1) + FS (1,6) = 8 + 0 = 8
• EF (6) = ES (6) + D (6) = 8 +6 = 14
7) Con. Forms 2 ( duration = 12 )
• ES (7) diambil nilai terbesar :
• ES (2) + SS (2,7) = 8 + 10 = 18
• EF (6) + FS (6,7) = 16 + 0 = 16

• EF (7) = ES (7) + D (7) = 18 + 12 = 30

Perhitungan Mundur:
1) Con. Forms 2 ( duration = 12 )
• LS (7) = 18
• LF (7) = 30
2) Clear & Grade 2 ( duration = 8 )
• LF (6) = LS (7) – FS (6,7) = 18 – 0 =18
• LS (6) = LF (6) – D (6) = 18 – 8 = 0
3) Pour Concrete 1 ( duration = 4 )
• LS (5) = 26
• LF (5) = 30
4) Reinforcement 1 ( duration = 9 )
• LF (4) = LS (5) – FS (4,5) = 26 – 2 = 24
• LS (4) = LF (4) – D (4) = 24 – 9 = 15
5) Sewe Lines 1 ( duration = 16 )
• LF (3) = LS (4) – SS (3,4) + D (3) = 15 – 7 + 16 = 24
• LS (3) = LF (3) – D (3) = 24 – 16 = 8
6) Con. Forms 1 ( duration = 12 )
• LF (2) diambil nilai terkecil :
• LF (4) – FF (2,4) = 24 – 1 = 23
• LS (4) – SS (2,4) + D(2) = 15 – 7 + 12 = 20
• LS (7) – SS (2,7) + D(2) = 18 – 10 + 12 = 20

• LS (2) = LF(2) - D(2) = 20 - 12 = 8


7) Clear & Grade 1 ( duration = 8 )
• LF (1) diambil nilai terkecil
• LS (2) – FS (1,2) = 8 - 0 = 8
• LS (3) – FS (1,3) = 8 - 0 = 8
• LS (6) – FS (1,6) = 10 - 0 = 10

• LS (1) = LF(1) - D(1) = 8 - 8 = 0