1 2 3 4 5
I UPAH
1 Tukang Batu/Kayu/Besi/Aspal/Cat 1 Hr 97,100.00 L.02
2 Kepala Tukang 1 Hr 100,000.00 L.03
3 Pekerja / Buruh tak terampil 1 Hr 80,000.00 L.01
4 Mandor 1 Hr 171,400.00 L.04
PROPINSI JAWA TIMUR
DAFTAR HARGA BAHAN BANGUNAN KABUPATEN TRENGGALEK
KABUPATEN TRENGGALEK TAHUN 2022
HARGA SATUAN
(NON PPN) (Rp)
No URAIAN BAHAN SATUAN KET.
DAT. TINGGI
1 2 3 4 5
II BAHAN
1 Air Liter 136.00 PUPR
2 Batu belah M3 300,000.00 PKPLH
3 Batu pecah 1-2 cm M3 309,444.00 PKPLH
4 Batu pecah 1-2 cm Kg 229.22
5 Pasir ayak beton (Brantas) M3 311,750.00 PKPLH
6 Pasir ayak beton (Brantas) Kg 222.68
7 Pasir urug / pasir lokal M3 168,750.00 PKPLH
8 Sirtu M3 161,300.00 PUPR
9 Paving Stone / Conblok abu-abu tebal 6 cm K.225 Bj 1,751.00 PKPLH
10 Paving Stone / Conblok abu-abu tebal 6 cm K.225 M2 80,546.00 46
11 Stoper / Topi uskup t=6cm (K 225) Bj 3,333.00 PKPLH
12 Kanstin Trap uk. 15.25.40 (me) Bj 19,833.00 PKPLH
13 Semen abu-abu / PC Kg 1,337.50 PKPLH
14 Buis beton Ø 40 cm M1 92,950.00 Dinkes
15 Buis beton U Ø 20 cm M1 - SURVEY LOKAL
16 Besi beton (polos / ulir) Kg 12,500.00 PUPR
17 Kawat beton / bendrat Kg 20,167.00 PUPR
18 Begisting M1 15,270.46 HARGA LAMA
19 Kayu kelas III M3 4,143,450.00 Dinkes
20 Paku 5 cm - 10 cm Kg 20,200.00 Dinkes
21 Minyak bekisting Liter 12,400.00 PUPR
22 Sewa stamper Unit/hari 182,000.00 Dinkes
23 Sewa molen Unit/hari 157,000.00 Dinkes
24 Pipa PVC Type C Ø 1,5" M1 7,887.50 Dinkes
25 Ijuk Kg 27,000.00 PUPR
26 Plamur tembok Kg 9,500.00 PUPR
27 Cat dinding Kg 31,500.00 PUPR
Mengetahui :
Kepala Dinas Perumahan,
Kawasan Permukiman Dan Lingkungan Hidup
Kabupaten Trenggalek
Dataran Tinggi
T.06.a.1. Penggalian 1 m3 tanah biasa sedalam ≤ 1 m
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.5630 80,000.00 45,040.00
Mandor L.04 OH 0.0563 171,400.00 9,649.82
JUMLAH TENAGA KERJA 54,689.82
B BAHAN
A.4.1.1.5. Membuat 1 m3 beton mutu f'c = 14,5 Mpa (K 175), slump (120 ± 20) mm
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang batu L.02 OH 0.275 97,100.00 26,702.50
Kepala tukang L.03 OH 0.028 100,000.00 2,800.00
Mandor L.04 OH 0.083 171,400.00 14,226.20
JUMLAH TENAGA KERJA 175,728.70
B BAHAN
Semen Portland Kg 326.000 1,337.500 436,025.00
Pasir beton Kg 760.000 222.679 169,235.71
Kerikil (maks 30mm) Kg 1,029.000 229.22 235,865.09
Air Liter 215.000 136.00 29,240.00
JUMLAH HARGA BAHAN 870,365.81
C PERALATAN
Molen unit/hari - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1,046,094.51
E Overhead & Profit 12.5% 12.5% x D (maksimum) 130,761.81
F Harga Satuan Pekerjaan (D+E) 1,176,856.32
A.4.1.1.17. Pembesian 10 kg dengan besi polos atau besi ulir.
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.070 80,000.00 5,600.00
Tukang batu L.02 OH 0.070 97,100.00 6,797.00
Kepala tukang L.03 OH 0.007 100,000.00 700.00
Mandor L.04 OH 0.004 171,400.00 685.60
JUMLAH TENAGA KERJA 13,782.60
B BAHAN
Besi beton (polos / ulir) Kg 10.500 12,500.00 131,250.00
Kawat beton Kg 0.150 20,167.00 3,025.05
JUMLAH HARGA BAHAN 134,275.05
C PERALATAN
Mengetahui :
Kepala Dinas Perumahan,
Kawasan Permukiman Dan Lingkungan Hidup
Kabupaten Trenggalek
Ir. MUYONO PIRANATA, M.A P.
NIP. 19671228 199802 1 003