Job Title : Installasi Pipe Spool dan Orifice Flange Well Test
Department : Project
Ref Doc :
Standard
EMP Bentu Ltd. MAG
Protective Equipment and system required to perform this job JSA NO : MAG/JSA-HWP/003/2020
Hard Hat Work Gloves X Safety shoes X Safety glasses X Work Gloves X Analized By : JSA Team Rev : 0
Work vest / life jacket Face Shield Leather Gloves X Safety Harness X Face Shield X Reviewed By : SHE Date : 24-Aug-20
Lock Out tag X Googles X Fire extinguiser X Approved by : Area MGR Rev : 0
1 Pre job safety meeting Miss Komunikasi Kesalahan dalam pekerjaan karena kesalahan L L L2 Pastikan pekerja benar-benar mengerti sebelum L L L2 SHE Officer / 24-Aug-20
pemahaman pekerja closing pre job meeting Supervisor
Spool Terlepas dari belt Cedera/ Kaki terhimpit Kuatkan penguncian bolt flange dan pastikan belting Mechanic / Supv 24-Aug-20
dan terjatuh layak untuk digunakan
3 Pemasangan Spool
Terkena pukulan palu Jari memar Pakai sarung tangan Mechanic / Supv 24-Aug-20
Kebisingan Telinga mendengung,Turunnya daya dengar - Gunakan Welding machine sound proof. Welder / 24-Aug-20
( AKUT ) - Beri safety sign : wajib menggunakan ear plug. Mechanic