R A B Rumah Type 30

Ukuran KEBUTUHAN MATERIAL

NO Pekerjaan Jumlah Volume sat harga satuan jumlah HEBEL Rangka Triplek Kayu
Usuk Galvalum Reng Galvalum Gypsum Calsiboard Cat Kozen dim-10 Triplek 8mm Kayu Usuk
Lebar Tinggi Panjang PC PASIR KORAL BATU KALI Bata Ringan genteng / bjij plafond hollow dim-8 lonjor dim-6 lonjor 12mm Reng
Lonjor -4m Lonjor -4m Lembar Lembar Liter m' lonjor Lbr m'
m3 2/4 (ljr) Lbr m'

A PEKERJAAN PONDASI
1 Pas.Bouwplank T.1,00M/m' 6 + 6 + 8 + 8 1 28 m' 15,000 420,000
2 Galian Tanah Pondasi 0.60 0.6 33.8 1 12.17 m3 35,000 425,880
3 Bor Strous diameter 30 cm 2 x 11 22 0 20,000 440,000
4 Cor beton strouss diameter 300cm
Beton PHI 3.14 R 0.1 2 11 0.0314 0.6908 m3 650,000 449,020 4.706 0.38 0.565
Pembesian besi 10 0.62 x 2 x 4 x 11 54.25 kg 8,500 461,142 7.33
besi 6 0.22 x 0.6 x ############# x 11 21.98 kg 8,500 186,790 8.25
7 Pasangan Batu Kali ##### ##### x 0.8 34 1 10.82 m3 600,000 6,489,600 32 6.07 13
6 kolom 12/12 -
Beton 0.12 x 0.12 x 3.7 11 0.59 m3 650,000 380,952 3.992 0.32 0.479
Pembesian besi 8 0.39 x 3.7 x 4 x 14 81.75 kg 8,500 694,899 17.27
besi 6 0.22 x 0.37 x x 345 28.36 kg 8,500 241,043 10.65
begesting 0.12 x 4 x 14 6.72 m2 10,000 67,200
6 kolom 10/10 -
Beton 0.10 x 0.1 x 3.7 2 0.07 m3 650,000 48,100 0.504 0.04 0.060
Pembesian besi 8 0.39 x 3.7 x 4 x 11 64.23 kg 8,500 545,992 13.57
besi 6 0.22 x 0.29 x x 271 17.46 kg 8,500 148,442 6.56
begesting 0.20 x 4 x 11 8.8 m2 10,000 88,000
6 kolom 15/30 -
Beton 0.15 x 0.3 x 3 1 0.14 m3 650,000 87,750 0.920 0.07 0.110
Pembesian besi 8 0.39 x 3 x 4 x 1 4.73 kg 8,500 40,245 1.00
besi 6 0.22 x 0.79 x x 20 3.51 kg 8,500 29,807 1.32
begesting 0.20 x 4 x 1 0.8 m2 10,000 8,000
8 Urugan Tanah kembali 9.73 m3 27,000 262,829
SUB TOTAL BIAYA PEKERJAAN PONDASI 11,515,691

B PEKERJAAN STRUKTUR -
1 Beton sloff 12/25 -
Beton 0.12 x 0.25 x 36.80 1.104 m3 650,000 717,600 7.520 0.60 0.902
Pembesian besi 8 0.39 x 1 x 4 x 37 58.08 kg 8,500 493,673 12.27
besi 6 0.22 x 0.63 x x 245 34.30 kg 8,500 291,576 12.88
begesting 0.25 x 2 x 37 18.4 m2 10,000 184,000
6 Beton balok Ring 10/15 -
Beton 0.10 x 0.15 x 35.00 0.525 m3 650,000 341,250 3.576 0.29 0.429
Pembesian besi 8 0.39 x 1 x 4 x 35 55.24 kg 8,500 469,526 11.67
besi 6 0.22 x 0.39 x x 233 20.20 kg 8,500 171,671 7.58
begesting 0.15 x 2 x 35 10.5 m2 10,000 105,000
7 kolom gevel 12/12 -
Beton 0.12 x 0.12 x 10 1 0.14 m3 650,000 93,600 0.981 0.08 0.118
Pembesian besi 8 0.39 x 10 x 4 x 1 15.78 kg 8,500 134,150 3.33
besi 6 0.22 x 0.37 x x 67 5.47 kg 8,500 46,533 2.06
begesting 0.20 x 4 x 1 0.8 m2 10,000 8,000
8 Beton balok gevel 10/15 -
Beton 0.10 x 0.15 x 30 0.45 m3 650,000 292,500 3.065 0.25 0.368
Pembesian besi 8 0.39 x 1 x 4 x 30 47.35 kg 8,500 402,451 10.00
besi 6 0.22 x 0.39 x x 200 17.31 kg 8,500 147,146 6.50
begesting 0.15 x 2 x 30 9 m2 10,000 90,000
9 Beton plat teras depan tebal 10 cm -
Beton 1.00 x 0.1 x 2.5 0.25 m3 650,000 162,500 1.703 0.14 0.204
Pembesian besi 8 0.39 x 1 x 1.95 x 25 19.23 kg 8,500 163,496 4.06
besi 8 0.39 x 1 x 3.45 x 10 13.61 kg 8,500 115,705 2.88
begesting 1.00 x 1 x 3 2.5 m2 100,000 250,000
10 Beton plat kamar mandi 10 cm -
Beton 1.50 x 0.1 x 1.3 0.195 m3 650,000 126,750 1.328 0.11 0.159
Pembesian besi 8 0.39 x 1 x 1.45 x 13 7.44 kg 8,500 63,218 1.57
besi 6 0.22 x 1 x 1.25 x 15 4.16 kg 8,500 35,372 1.56
begesting 1.50 x 1 x 1 1.95 m2 100,000 195,000
10 Beton plat kitchen -
Beton 0.60 x 0.1 x 1.5 0.09 m3 650,000 58,500 0.613 0.05 0.074
Pembesian besi 8 0.39 x 1 x 0.55 x 15 3.26 kg 8,500 27,669 0.69
besi 8 0.39 x 1 x 1.45 x 6 3.43 kg 8,500 29,178 0.73
begesting 0.60 x 1 x 2 0.9 m2 100,000 90,000

SUB TOTAL BIAYA PEKERJAAN STRUKTUR 5,306,064

C PEKERJAAN PASANGAN DINDING


1 Pas.Dinding 142.69 m2
datar 3.7 x 34 1 125.06 m2
gevel 1 2.3 x 6.2 1.5 10.695 m2
gevel 2 1.85 x 5.0 1.5 6.9375 m2
Pengurang Pasangan dinding m2
Kosen beton Cat/m'
P1 0.9 x 2.1 4 7.56 m2
P2 0.7 X 2.1 1 1.47 m2
` w1 0.5 x 1.5 1 0.75 m2
w2 1 x 1.5 2 3 m2
Beton balok Ring 10/15 0.15 x 35.00 1 5.25 m2
Beton gevel 10/15 0.15 x 30 1 4.5 m2
kolom praktis 0.10 x 7.4 1 0.74 m2
kolom 0.12 x 40.7 1 4.884 m2
kolom gevel 0.12 x 10 1 1.2 m2
Ukuran KEBUTUHAN MATERIAL

NO Pekerjaan Jumlah Volume sat harga satuan jumlah HEBEL Rangka Triplek Kayu
Usuk Galvalum Reng Galvalum Gypsum Calsiboard Cat Kozen dim-10 Triplek 8mm Kayu Usuk
Lebar Tinggi Panjang PC PASIR KORAL BATU KALI Bata Ringan genteng / bjij plafond hollow dim-8 lonjor dim-6 lonjor 12mm Reng
Lonjor -4m Lonjor -4m Lembar Lembar Liter m' lonjor Lbr m'
m3 2/4 (ljr) Lbr m'

pasang roaster beton 0.15 x 0.3 22 0.99 m2 20,000 440,000


30.344

Pas. Dinding 112.35 m2 115,000 12,920,078 11

2 volume Kosen beton Cat/m' 29


P1 0.9 + 2.1 x 2 4 17.7 m'
W2 1.5 x 2 + 1 x 2 2 7 m'
W1 0.5 x 2 + 1.5 x 2 1 4 m'
28.7 m' 75,000 2,152,500

SUB TOTAL BIAYA PEKERJAAN PASANGAN DINDING 15,512,578


-
D PEKERJAAN RANGKA & PENUTUP ATAP -
1 Rangka Atap Galvalum 45.00 m2 110,000 4,950,000 30 36
2 Pas.Genteng semi mantili (biji) 45.00 x 25.00 1125 bji 1,400 1,575,000 1,125
3 Pas.Genteng Nok semi mantili /m' 5 x 4 20 bji 7,500 150,000
4 Pas.kalsi plang 10 m' 20,000 200,000
B TOTAL BIAYA PEKERJAAN RANGKA & PENUTUP ATAP 6,875,000

E PEKERJAAN PELAPIS DINDING -


1 Acian Plesteran Tebal 23mm/m2 112.35 x 2 202.2 m2 17,500 3,538,978 26 5.46
2 Plesteran Beton 1:3/m2 T.1,52cm -
Beton plat teras depan tebal 10 cm 1.00 x 5 x 1 5 m2 17,500 87,500 1 0.14
-
3 Sekonengan Sudut Dinding/m' 3.7 x 25 92.5 m' 15,000 1,387,500 12 2.50
4 Tali Air Keliling Kosen/m' 28.7 m' 10,000 287,000 4 0.77
5 keramik dinding m2 -
Pas.Keramik Dinding Lokal 20X25/m2 Mulia -Toilet 4.50 x 1.5 6.75 m2 125,000 843,750 3 0.34
Pas.Keramik Dinding Lokal 20X25/m2 Mulia - Meja Dapur 2.5 m2 125,000 312,500 1 0.13
SUB TOTAL BIAYA PEKERJAAN PELAPIS DINDING 6,457,228

F PEKERJAAN PENUTUP PLAFOND -


2 Plafond Gypsum 9mm/m2 25 m2 90,000 3,901,500 8 31
3 Plafond calsiboard 4mm/m2 0.70 x 10 x 1 10 m2 90,000 819,000 3 13
SUB TOTAL BIAYA PEKERJAAN PENUTUP PLAFOND 4,720,500
-
G PEKERJAAN PELAPIS LANTAI -
Beton tumbuk lantai ` -
1 Rabat Beton T.7,5cm/m2 Tanpa Tulang dgn Koral 27.00 x x 0.05 1 1.4 M3 350,000 472,500 7 1
2 Pas. Granit 60 x 60 standart 25.0 m2 110,000 2,750,000 11.3 3.8
Pas. Granit 60 x 60 kw standart meja dapur 1.6 m2 110,000 171,600 0.7 0.2
3 Pas.Keramik KM lantai Lokal 20X20/m2 Mulia 1.625 m2 125,000 203,125 0.7 0.2
SUB TOTAL BIAYA PEKERJAAN PELAPIS LANTAI 3,597,225
-
H PEKERJAAN PINTU, JENDELA, KACA -
-
1 Daun Pintu Kayu Jati 4 BH 750,000 4,500,000
2 Pintu toilet 1 BH 600,000 600,000
3 Jendela Rangka kayu jati/ Kaca 3 BH 250,000 750,000
UB TOTAL BIAYA PEKERJAAN PINTU, JENDELA, KACA 5,850,000
-
I PEKERJAAN ENGSEL & KUNCI -
1 Kunci Pintu /bh Lainnya 4 bh 125,000 750,000
2 Kunci Pintu K.Mandi Lain/bh 1 bh 65,000 65,000
3 Engsel pintu 4 set 75,000 450,000
4 Engsel jendela 3 set 50,000 200,000
SUB TOTAL BIAYA PEKERJAAN ENGSEL & KUNCI 1,465,000
-
J PEKERJAAN PENGECATAN -
-
1 Cat Tembok Dalam/m2 112.35 m2 15,000 1,685,227.50
2 Cat Tembok Luar/m2 112.3485 m2 25,000 2,808,712.50
3 Cat plafond 35 m2 12,500 437,500.00
4 Cat genteng 45.00 m2 17,000 765,000.00
SUB TOTAL BIAYA PEKERJAAN PENGECATAN 5,696,440
-
K PEKERJAAN INSTALASI SANITASI -
Air Bersih -

2 Pemipaan PVC D dia 3/4"/m' 40 x 1 20 m' 35,000 700,000


3 kran air biasa 3 bj 25,000 75,000
kitchen zink 1 bj 50,000 50,000
4 tandon air 1 bh 1,250,000 1,250,000
5 kitchen zink 1 bh 250,000 250,000
Air Kotor -
1 Pemipaan PVC AW dia 2"/m' (Bawah Lantai) 20 x 1 15 m' 45,000 675,000
2 Pemipaan PVC AW dia 4"/m' (Bawah Lantai) 15 X 1 12 m' 65,000 780,000
3 avour kamar mandi 1.5 m' 50,000 75,000
closet duduk 1 650,000 650,000
4 Septic Tank buis beton 4 bh dim 0.8 m 4 bh 100,000 400,000
5 Resapan Air kotor buis beton dim 0.8 m 4 bh 100,000 400,000
SUB TOTAL BIAYA PEKERJAAN INSTALASI SANITASI 5,305,000
Ukuran KEBUTUHAN MATERIAL

NO Pekerjaan Jumlah Volume sat harga satuan jumlah HEBEL Rangka Triplek Kayu
Usuk Galvalum Reng Galvalum Gypsum Calsiboard Cat Kozen dim-10 Triplek 8mm Kayu Usuk
Lebar Tinggi Panjang PC PASIR KORAL BATU KALI Bata Ringan genteng / bjij plafond hollow dim-8 lonjor dim-6 lonjor 12mm Reng
Lonjor -4m Lonjor -4m Lembar Lembar Liter m' lonjor Lbr m'
m3 2/4 (ljr) Lbr m'

L PEKERJAAN INSTALASI LISTRIK

2 Titik Lampu Dalam/ttk Bawah Plafond 7.00 ttk 125,000 875,000


4 Titik Stop Kontak Biasa/ttk 6.00 ttk 85,000 510,000
5 Saklar 5.00 ttk 75,000 375,000
SUB TOTAL BIAYA PEKERJAAN INSTALASI LISTRIK 1,760,000

M PEKERJAAN LAIN-LAIN
-
SUB TOTAL BIAYA PEKERJAAN LAIN - LAIN

TOTAL BIAYA PEKERJAAN 74,060,725 126 22.77 3 13 11 30 36 8 3 - 29 7 79 57 - - -

harga per m2 2,468,690.84