Ee Mep Rs Upt Kupang
Ee Mep Rs Upt Kupang
NO URAIAN JUMLAH
TOTAL 137,904,869,997
LAIN - LAIN
1 Sambungan Baru PLN Tegangan Menengah 2,847,080,000
Ditetapkan pada sambungan awal 2.180.000 VA dari 3.465.000 VA
- Biaya Penyambungan Daya PLN VA 2,180,000.00 631 1,375,580,000
- Uang Jaminan Langganan (UJL) VA 2,180,000.00 250 545,000,000
- SLO termasuk Jasa Pemasangan SKTM & Instalasi VA 2,180,000.00 425 926,500,000
Lengkap dengan biaya materai
TOTAL 8,630,153,205
Page 2 of 285
ENGINEERING ESTIMATE (EE)
PEKERJAAN MEKANIKAL & ELEKTRIKAL
PROYEK : PAKET PEKERJAAN JASA KONSULTANSI KONSTRUKSI PENGADAAN JASA KONSULTAN LANJUTAN RUMAH SAKIT KUPANG NTT
BANGUNAN : GEDUNG A (FARMASI)
LOKASI : NUSA TENGGARA TIMUR
A.2 Lantai 2
1 PP.2A unit 1.00 8,779,000 8,779,000
2 P.AC-2A unit 1.00 10,923,000 10,923,000
A.3 Lantai 3
1 PP.3A unit 1.00 8,735,000 8,735,000
2 P.AC-3A unit 1.00 10,923,000 10,923,000
2 Dari SDP.A
NYY 4 x 16 mm2 ke PP.1A mtr 10.00 134,033 1,340,330
NYY 4 x 16 mm2 ke PP.2A mtr 15.00 134,033 2,010,495
NYY 4 x 16 mm2 ke PP.3A mtr 19.00 134,033 2,546,627
NYY 4 x 35 mm2 ke P.LIFT.A mtr 55.00 278,933 15,341,315
NYY 4 x 16 mm2 ke P. SUMPIT A mtr 12.00 134,033 1,608,396
3 Dari SDP.AC-A
NYY 4 x 25 mm2 ke P.AC-1A mtr 10.00 205,275 2,052,750
NYY 4 x 25 mm2 ke P.AC-2A mtr 15.00 205,275 3,079,125
NYY 4 x 25 mm2 ke P.AC-3A mtr 19.00 205,275 3,900,225
4 Dari P.LIFT-A
NYY 4 x 10 mm2 ke PC. LIFT-A1 mtr 11.00 80,903 889,933
NYY 4 x 10 mm2 ke PC. LIFT-A2 mtr 11.00 80,903 889,933
5 Dari P. SUMPIT A
NYY 4 x 4 mm2 PC. SUMPIT A-01 mtr 32.00 36,225 1,159,200
NYY 4 x 4 mm2 PC. SUMPIT A-02 mtr 77.00 36,225 2,789,325
NYY 4 x 4 mm2 PC. SUMPIT KIMIA A-01 mtr 45.00 36,225 1,630,125
NYY 4 x 4 mm2 PC. SUMPIT KIMIA A-02 mtr 77.00 36,225 2,789,325
NYY 3 x 4 mm2 PC. POND A-01 mtr 44.00 27,773 1,222,012
NYY 3 x 4 mm2 PC. POND A-02 mtr 34.00 27,773 944,282
6 Dari SDP.PF-C
FRC 4 x 1 x 4 mm2 P PF.A mtr 107.00 95,440 10,212,080
2 Lantai 2
Kabel Tray Listrik
- uk. 600 mm x 50 mm m 34.00 353,000 12,002,000
Page 3 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- uk. 300 mm x 50 mm m 22.00 211,600 4,655,200
3 Lantai 3
Kabel Tray Listrik
- uk. 600 mm x 50 mm m 34.00 353,000 12,002,000
- uk. 300 mm x 50 mm m 22.00 211,600 4,655,200
E.2 Lantai 2
1 RM TLED 3 x 8 Watt + Cover bh - 1,360,594 -
2 RM TLED 3 x 8 Watt + Cover c/w Nicad Battery bh 2.00 2,403,118 4,806,236
3 RM TLED 2 x 14 Watt + Cover bh 17.00 1,205,715 20,497,155
4 RM TLED 2 x 14 Watt + Cover c/w Nicad Battery bh 15.00 2,248,239 33,723,585
5 RM TLED 2 x 8 Watt + Cover bh - 805,111 -
6 RM TLED 2 x 8 Watt + Cover c/w Nicad Battery bh - 1,847,635 -
7 TLED 2x14 Watt (Balk) bh - 881,139 -
8 TLED 2x14 Watt (Balk) c/w Nicad Battery bh 1.00 1,923,663 1,923,663
9 TLED 1x14 Watt (Balk) bh 1.00 483,571 483,571
10 TLED 1x14 Watt (Balk) c/w Nicad Battery bh - 1,526,007 -
11 Lampu Wastafel LED 1 x 8 watt bh 10.00 540,015 5,400,150
12 Lampu Bed TLED 8 Watt bh - 354,799 -
13 Down Light LED E27 13 Watt Bulb + Cover bh 53.00 372,527 19,743,952
14 Down Light LED E27 13 Watt Bulb + Cover c/w Nicad Battery bh 15.00 1,481,731 22,225,959
15 Down Light LED E27 6 Watt Bulb + Cover bh 7.00 284,327 1,990,292
16 Down Light LED E27 6 Watt Bulb + Cover + Nicad Battery bh 3.00 1,393,531 4,180,592
17 Lampu Baret LED E27 10,5 Watt Bulb bh 2.00 229,996 459,992
18 Lampu Baret LED E27 10,5 Watt Bulb c/w Nicad Battery bh 2.00 1,339,288 2,678,575
19 Exit Lamp LED 8 Watt bh 2.00 1,349,254 2,698,508
20 Stop Kontak 1 Ph 200 Watt bh 92.00 52,763 4,854,150
21 Stop Kontak Ceiling TV 1Ph 200 Watt bh 6.00 52,763 316,575
22 Stop Kontak Hand Dryer 1000 Watt bh 2.00 78,750 157,500
23 Saklar Tunggal bh 12.00 44,163 529,956
24 Saklar Ganda bh 24.00 48,794 1,171,044
25 Saklar Hotel bh - 46,242 -
26 Grid Switch 4 Gang bh 1.00 227,462 227,462
27 Titik nyala lampu dengan kabel NYM 3 x 2,5 mm² di dalam conduit PVC HI 20 mmtitik 130.00 321,800 41,834,000
28 Titik nyala Stop kontak NYM 3 x 2,5 mm² didalam conduit PVC HI 20 mm titik 98.00 400,900 39,288,200
E.3 Lantai 3
1 RM TLED 3 x 8 Watt + Cover bh - 1,360,594 -
2 RM TLED 3 x 8 Watt + Cover c/w Nicad Battery bh 2.00 2,403,118 4,806,236
Page 4 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
3 RM TLED 2 x 14 Watt + Cover bh 17.00 1,205,715 20,497,155
4 RM TLED 2 x 14 Watt + Cover c/w Nicad Battery bh 15.00 2,248,239 33,723,585
5 RM TLED 2 x 8 Watt + Cover bh - 805,111 -
6 RM TLED 2 x 8 Watt + Cover c/w Nicad Battery bh 1,847,635 -
7 TLED 2x14 Watt (Balk) bh 1.00 881,139 881,139
8 TLED 2x14 Watt (Balk) c/w Nicad Battery bh 1,923,663 -
9 TLED 1x14 Watt (Balk) bh 1.00 483,571 483,571
10 TLED 1x14 Watt (Balk) c/w Nicad Battery bh 1,526,007 -
11 Lampu Wastafel LED 1 x 8 watt bh 10.00 540,015 5,400,150
12 Lampu Bed TLED 8 Watt bh 354,799 -
13 Down Light LED E27 13 Watt Bulb + Cover bh 49.00 372,527 18,253,843
14 Down Light LED E27 13 Watt Bulb + Cover c/w Nicad Battery bh 16.00 1,481,731 23,707,690
15 Down Light LED E27 6 Watt Bulb + Cover bh 13.00 284,327 3,696,256
16 Down Light LED E27 6 Watt Bulb + Cover + Nicad Battery bh 3.00 1,393,531 4,180,592
17 Lampu Baret LED E27 10,5 Watt Bulb bh 2.00 229,996 459,992
18 Lampu Baret LED E27 10,5 Watt Bulb c/w Nicad Battery bh 2.00 1,339,288 2,678,575
19 Exit Lamp LED 8 Watt bh 1.00 1,349,254 1,349,254
20 Stop Kontak 1 Ph 200 Watt bh 84.00 52,763 4,432,050
21 Stop Kontak Ceiling TV 1Ph 200 Watt bh 6.00 52,763 316,575
22 Stop Kontak Hand Dryer 1000 Watt bh 2.00 78,750 157,500
23 Saklar Tunggal bh 12.00 44,163 529,956
24 Saklar Ganda bh 24.00 48,794 1,171,044
25 Saklar Hotel bh - 46,242 -
26 Grid Switch 4 Gang bh 1.00 227,462 227,462
27 Titik nyala lampu dengan kabel NYM 3 x 2,5 mm² di dalam conduit PVC HI 20 mmtitik 132.00 321,800 42,477,600
28 Titik nyala Stop kontak NYM 3 x 2,5 mm² didalam conduit PVC HI 20 mm titik 92.00 400,900 36,882,800
Page 5 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
IV.C Pekerjaan Instalasi Fire Alarm dalam Bangunan
C.1 Lantai 1
1 Terminal Box (TB. FA - 1A) unit 1.00 630,525 630,525
2 Horn & Strobe bh 2.00 795,769 1,591,538
3 Manual Break Glass bh 2.00 289,013 578,025
4 Addresable Rate of Rise Detector bh 4.00 1,092,315 4,369,260
5 Addresable Fixed Heat Detector bh - 1,092,315 -
6 Addressable Smoke Detector bh 11.00 1,373,846 15,112,309
7 Smoke Detector Photoelectric bh - 581,805 -
8 Rate of Rise Detector bh 11.00 491,715 5,408,865
9 Fixed Heat Detector bh - 491,715 -
10 Telephone Jack bh 2.00 487,961 975,923
11 End off line bh 8.00 6,379 51,030
12 P.AC.1A bh 1.00 by Others
13 Flow Switch bh 1.00 by Others
C.2 Lantai 2
1 Terminal Box (TB. FA - 2A) unit 1.00 630,525 630,525
2 Horn & Strobe bh 2.00 795,769 1,591,538
3 Manual Break Glass bh 2.00 289,013 578,025
4 Addresable Rate of Rise Detector bh 4.00 1,092,315 4,369,260
5 Addresable Fixed Heat Detector bh 1.00 1,092,315 1,092,315
6 Addressable Smoke Detector bh 29.00 1,373,846 39,841,541
7 Rate of Rise Detector bh - 581,805 -
8 Smoke Detector Photoelectric bh 7.00 491,715 3,442,005
9 Fixed Heat Detector bh - 491,715 -
10 Telephone Jack bh 2.00 487,961 975,923
11 End off line bh 8.00 6,379 51,030
12 P.AC.2A bh 1.00 by Others
13 Flow Switch bh 1.00 by Others
Page 6 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Pengadaan dan pemasangan sistem sesuai dengan
Gambar & Spesifikasi Teknis
C.2 Lantai 2
1 Terminal Box Sound System Lt. 2 (TB. TS. 2C) bh 1.00 800,100 800,100
2 Ceiling Speaker 3 Watt + Matching Transformer bh 49.00 196,035 9,605,715
3 Volume Control bh 18.00 451,920 8,134,560
4 Emergency Speaker 6 Watt bh - 322,382 -
5 Instalasi untuk Speaker dengan kabel NYMHY 2 x 1.5 mm2 ttk 49.00 297,900 14,597,100
dalam conduit PVC HI dia. 20 mm
6 Instalasi untuk Volume Control dengan kabel NYMHY 3 x 1.5 mm2 ttk 18.00 492,500 8,865,000
dalam conduit PVC HI dia. 20 mm
7 Instalasi untuk Speaker dengan kabel FRC 2 x 1,5 mm2 ttk - 597,400 -
dalam conduit PVC HI dia. 20 mm
C.3 Lantai 3
1 Terminal Box Sound System Lt. 3 (TB. TS. 3C) bh 1.00 800,100 800,100
2 Ceiling Speaker 3 Watt + Matching Transformer bh 50.00 196,035 9,801,750
3 Volume Control bh 16.00 451,920 7,230,720
4 Emergency Speaker 6 Watt bh 1.00 322,382 322,382
5 Instalasi untuk Speaker dengan kabel NYMHY 2 x 1.5 mm2 ttk 50.00 297,900 14,895,000
dalam conduit PVC HI dia. 20 mm
6 Instalasi untuk Volume Control dengan kabel NYMHY 3 x 1.5 mm2 ttk 16.00 492,500 7,880,000
dalam conduit PVC HI dia. 20 mm
7 Instalasi untuk Speaker dengan kabel FRC 2 x 1,5 mm2 ttk 1.00 597,400 597,400
dalam conduit PVC HI dia. 20 mm
2 Outlet :
- Outlet Access Point RJ 45 bh 2.00 135,000 270,000
- Outlet Data RJ 45 bh 30.00 135,000 4,050,000
- Outlet Telepon RJ 45 bh 20.00 135,000 2,700,000
3 Fixture Unit
Page 7 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- Access Point bh 2.00 1,390,000 2,780,000
- Pesawat Telepon IP Extention bh 18.00 1,135,000 20,430,000
- Pesawat Telepon IP Direct bh 1.00 1,135,000 1,135,000
- Pesawat Telepon IP Faximile bh 1.00 6,775,000 6,775,000
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point titik 2.00 936,100 1,872,200
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 30.00 936,100 28,083,000
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 20.00 936,100 18,722,000
B.2 Lantai 2
1 Peralatan Distribusi
- Wall Mounted Rack 19", 15U c/w Accessories unit 1.00 2,200,000 2,200,000
- Wiring Management 1U bh 2.00 148,000 296,000
- Patch Panel FO 12 port bh 1.00 1,634,400 1,634,400
- FO Connector bh 1.00 160,800 160,800
- UTP Cat 6 Patch Panel 24 Port Loaded bh 2.00 1,380,000 2,760,000
- UTP Cat 6 Patch Cord, 1m bh 48.00 45,000 2,160,000
- Switch Hub 24 port bh 2.00 4,508,000 9,016,000
2 Outlet :
- Outlet Access Point RJ 45 bh 2.00 135,000 270,000
- Outlet Data RJ 45 bh 23.00 135,000 3,105,000
- Outlet Telepon RJ 45 bh 22.00 135,000 2,970,000
3 Fixture Unit
- Access Point bh 2.00 1,390,000 2,780,000
- Pesawat Telepon IP Extention bh 22.00 1,135,000 24,970,000
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point titik 2.00 936,100 1,872,200
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 23.00 936,100 21,530,300
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 22.00 936,100 20,594,200
B.3 Lantai 3
1 Peralatan Distribusi
- Wall Mounted Rack 19", 15U c/w Accessories unit 1.00 2,200,000 2,200,000
- Wiring Management 1U bh 2.00 148,000 296,000
- Patch Panel FO 12 port bh 1.00 1,634,400 1,634,400
- FO Connector bh 1.00 160,800 160,800
- UTP Cat 6 Patch Panel 24 Port Loaded bh 2.00 1,380,000 2,760,000
- UTP Cat 6 Patch Cord, 1m bh 48.00 45,000 2,160,000
- Switch Hub 24 port bh 2.00 4,508,000 9,016,000
2 Outlet :
- Outlet Access Point RJ 45 bh 2.00 135,000 270,000
- Outlet Data RJ 45 bh 21.00 135,000 2,835,000
- Outlet Telepon RJ 45 bh 20.00 135,000 2,700,000
3 Fixture Unit
- Access Point bh 2.00 1,390,000 2,780,000
- Pesawat Telepon IP Extention bh 20.00 1,135,000 22,700,000
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point titik 2.00 936,100 1,872,200
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 21.00 936,100 19,658,100
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 20.00 936,100 18,722,000
2 Lantai 2
Kabel Tray 300 mm x 100 mm m 35.00 253,000 8,855,000
Kabel Tray 200 mm x 100 mm m 33.00 199,900 6,596,700
3 Lantai 3
Kabel Tray 300 mm x 100 mm m 35.00 253,000 8,855,000
Kabel Tray 200 mm x 100 mm m 33.00 199,900 6,596,700
Page 8 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Gambar & Spesifikasi Teknis
B.2 Lantai 2
1 Splitter 6 Way Unit 1.00 533,108 533,108
2 Outlet TV Unit 6.00 80,325 481,950
3 Instalasi kabel Outlet TV, coaxial RG6 (5C/2 volt) dakan konduit PVC HI dia. 20 mm
titik 6.00 533,800 3,202,800
4 Instalasi kabel Splitter, Coaxial RG-11 (7C) dalam konduit PVC HI dia. 20 mm m 12.00 26,775 321,300
B.3 Lantai 3
1 Splitter 6 Way Unit 1.00 533,108 533,108
2 Splitter 4 Way Unit 1.00 366,892 366,892
3 Booster Unit 1.00 1,658,475 1,658,475
4 Outlet TV Unit 6.00 80,325 481,950
5 Instalasi kabel Outlet TV, coaxial RG6 (5C/2 volt) dakan konduit PVC HI dia. 20 mm
titik 6.00 533,800 3,202,800
6 Instalasi kabel Splitter, Coaxial RG-11 (7C) dalam konduit PVC HI dia. 20 mm m 160.00 26,775 4,284,000
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 4.00 5,901,300 23,605,200
- Indoor Fixed Dome IP Camera + thermal detector bh 3.00 139,500,000 418,500,000
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 7.00 936,100 6,552,700
B.2 Lantai 2
1 Peralatan Distribusi
- Wall Mounted Rack 19", 8U c/w Accessories bh 1.00 1,940,000 1,940,000
- Wiring Management 1U bh 1.00 148,000 148,000
- Patch Panel FO 12 port bh 1.00 1,634,400 1,634,400
- FO Connector bh 1.00 160,800 160,800
- UTP Cat 6 Patch Panel 24 Port Loaded bh 1.00 1,380,000 1,380,000
- UTP Cat 6 Patch Cord, 1m bh 24.00 45,000 1,080,000
- Switch Hub PoE 24 port bh 1.00 4,508,000 4,508,000
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 3.00 5,901,300 17,703,900
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 3.00 936,100 2,808,300
Page 9 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- Patch Panel FO 12 port bh 1.00 1,634,400 1,634,400
- FO Connector bh 1.00 160,800 160,800
- UTP Cat 6 Patch Panel 24 Port Loaded bh 1.00 1,380,000 1,380,000
- UTP Cat 6 Patch Cord, 1m bh 24.00 45,000 1,080,000
- Switch Hub PoE 24 port bh 1.00 4,508,000 4,508,000
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 5.00 5,901,300 29,506,500
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 5.00 936,100 4,680,500
2 Kabel Data dari MCU di Ruang BAS ke: mtr 406.00 51,424 20,878,217
DDC Lt. D ~ 3 STP AWG #18 dalam Conduit PVC 20 mm
1 LANTAI 1
PANEL SDP.A
PANEL SDP.AC.A
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
Power Monitoring HLI Titik 2.00 1,677,000 3,354,000
PANEL PP.1A
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
On - Off Digital Output Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
PANEL PP.AC.1A
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
POMPA PON
Status Digital Input Titik 4.00 928,000 3,712,000
Trip Alarm Digital Input Titik 4.00 928,000 3,712,000
Level alarm Digital Input Titik 8.00 928,000 7,424,000
2 LANTAI 2
PANEL PP, PAC
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
On - Off Digital Output Titik 2.00 928,000 1,856,000
Page 10 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Power Monitoring HLI Titik 2.00 1,677,000 3,354,000
3 LANTAI 3
PANEL PP, PAC
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
On - Off Digital Output Titik 2.00 928,000 1,856,000
Power Monitoring HLI Titik 2.00 1,677,000 3,354,000
4 LANTAI ATAP
PANEL LIFT, PC. FA
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
XI PEKERJAAN ANTRIAN
Pengadaan dan pemasangan sistem lengkap sesuai
gambar & spesifikasi teknis
XII.A Lantai 1
1 Controller Mesin Antrian unit 1.00 94,000,000 94,000,000
2 Tombol Panggil unit 11.00 1,450,000 15,950,000
3 Counter Display unit 11.00 3,200,000 35,200,000
4 Main Counter Display unit 5.00 8,500,000 42,500,000
5 Mini Speaker System unit 3.00 1,250,000 3,750,000
6 Instalasi Sistem Antrian titik 30.00 725,000 21,750,000
XI.B Lantai 2
1 Controller Mesin Antrian unit - 94,000,000 -
2 Tombol Panggil unit 13.00 1,450,000 18,850,000
3 Counter Display unit 13.00 3,200,000 41,600,000
4 Main Counter Display unit 5.00 8,500,000 42,500,000
5 Mini Speaker System unit - 1,250,000 -
6 Instalasi Sistem Antrian titik 31.00 725,000 22,475,000
XI.C Lantai 3
1 Controller Mesin Antrian unit - 94,000,000 -
2 Tombol Panggil unit 1.00 1,450,000 1,450,000
3 Counter Display unit 1.00 3,200,000 3,200,000
4 Main Counter Display unit 5.00 8,500,000 42,500,000
5 Mini Speaker System unit - 1,250,000 -
6 Instalasi Sistem Antrian titik 7.00 725,000 5,075,000
Page 11 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- dia. 32 mm bh 1.00 380,783 380,783
- dia. 25 mm bh 2.00 288,330 576,660
- dia. 20 mm bh 1.00 211,523 211,523
- dia. 15 mm bh 1.00 163,380 163,380
5 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
A.2.2 Lantai 2
1 Instalasi pipa air bersih dengan PPR80 - PN10
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 65 mm m' 10.00 177,620 1,776,200
- dia. 50 mm m' 32.00 132,320 4,234,240
- dia. 40 mm m' 19.00 89,540 1,701,260
- dia. 32 mm m' 58.00 64,860 3,761,880
- dia. 25 mm m' 25.00 46,250 1,156,250
- dia. 20 mm m' 34.00 28,830 980,220
- dia. 15 mm m' 200.00 22,590 4,518,000
3 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
A.2.3 Lantai 3
1 Instalasi pipa air bersih dari Booster Packaged ke Lantai 3 dengan PPR80 - PN10
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 65 mm m' 106.00 177,620 18,827,720
- dia. 50 mm m' 19.00 132,320 2,514,080
- dia. 40 mm m' 33.00 89,540 2,954,820
4 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
2 Ball Valve :
- dia. 15 mm bh 1.00 163,380 163,380
3 Kran Botol
- dia. 15 mm bh 2.00 75,000 150,000
Page 12 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Bak Submersible Cutter Pump + QDC (Sewage.AB-01) unit 1.00 skope sipil
Kapasitas : 5 m³
Ukuran : 2500 x 2000 x (1000+500)mm
Bak Submersible Cutter Pump + QDC (Sewage.AB-02) unit 1.00 skope sipil
Kapasitas : 3 m³
Ukuran : 1500 x 1500 x (1400+500)mm
Bak Submersible Cutter Pump + QDC (Chemical.AB-01) unit 1.00 skope sipil
Kapasitas : 3 m³
Ukuran : 3000 x 1000 x (1000+500)mm
Bak Submersible Cutter Pump + QDC (Chemical.AB-02) unit 1.00 skope sipil
Kapasitas : 3 m³
Ukuran : 3000 x 1000 x (1000+500)mm
5 Submersible Pump (Kolam Pond-2) / Drainage Pit-A-01 set 1.00 70,200,000 70,200,000
Kapasitas : 2 x @4.5 m3/ jam
Type : Submersible Pump
Head : 7 meter
Power : sesuai seleksi unit
Jumah Pompa : 2 unit
Bekerja secara parallel
lengkap dengan katup2, panel kontrol otomatis dan Level Control
Bak Submersible Pump (Kolam Pond-2) / Drainage Pit-A-01 unit 1.00 skope sipil
Kapasitas : 2 m³
Ukuran : 2200 x 1000 x (800+500)mm
6 Submersible Pump (Kolam Pond-2) / Drainage Pit-A-02 set 1.00 70,200,000 70,200,000
Kapasitas : 2 x @4.5 m3/ jam
Type : Submersible Pump
Head : 7 meter
Power : sesuai seleksi unit
Jumah Pompa : 2 unit
Bekerja secara parallel
lengkap dengan katup2, panel kontrol otomatis dan Level Control
Bak Submersible Pump (Kolam Pond-2) / Drainage Pit-A-02 unit 1.00 skope sipil
Kapasitas : 2 m³
Ukuran : 2200 x 1000 x (800+500)mm
Page 13 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
B.3 Pekerjaan Instalasi Pipa Air Kotor, Kotor & Vent dalam bangunan
B.3.1 Lantai 1
1 Instalasi Air Kotoran Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 150 mm m' 21.00 288,460 6,057,660
- dia. 100 mm m' 41.00 153,900 6,309,900
- dia. 50 mm m' 8.00 63,440 507,520
Shaft
- dia. 100 mm m' 10.00 153,900 1,539,000
2 Instalasi Air Kotor Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 150 mm m' 29.00 288,460 8,365,340
- dia. 100 mm m 6.00 153,900 923,400
- dia. 80 mm m 20.00 105,190 2,103,800
- dia. 50 mm m 54.00 63,440 3,425,760
- dia. 40 mm m 4.00 48,250 193,000
Shaft
- dia. 100 mm m' 10.00 153,900 1,539,000
Shaft
- dia. 50 mm m' 10.00 63,440 634,400
B.3.2 Lantai 2
1 Instalasi Air Kotoran Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 41.00 153,900 6,309,900
- dia. 80 mm m 3.00 105,190 315,570
- dia. 50 mm m 8.00 63,440 507,520
Shaft
- dia. 100 mm m' 10.00 153,900 1,539,000
2 Instalasi Air Kotor cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 10.00 153,900 1,539,000
- dia. 80 mm m 24.00 105,190 2,524,560
- dia. 50 mm m 39.00 63,440 2,474,160
- dia. 40 mm m 13.00 48,250 627,250
Shaft
- dia. 100 mm m' 10.00 153,900 1,539,000
Shaft
- dia. 100 mm m 10.00 425,060 4,250,600
Shaft
- dia. 50 mm m' 10.00 63,440 634,400
6 Grease Trap :
- Kap. 30 liter bh 1.00 3,850,000 3,850,000
Page 14 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
1 Instalasi Air Kotoran Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 47.00 153,900 7,233,300
- dia. 80 mm m 3.00 105,190 315,570
- dia. 50 mm m 8.00 63,440 507,520
Shaft
- dia. 100 mm m' 10.00 153,900 1,539,000
2 Instalasi Air Kotor cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 10.00 153,900 1,539,000
- dia. 80 mm m 24.00 105,190 2,524,560
- dia. 50 mm m 47.00 63,440 2,981,680
- dia. 40 mm m 14.00 48,250 675,500
Shaft
- dia. 100 mm m' 10.00 153,900 1,539,000
Shaft
- dia. 100 mm m 10.00 425,060 4,250,600
Shaft
- dia. 50 mm m' 10.00 63,440 634,400
6 Grease Trap :
- Kap. 30 liter bh 1.00 3,850,000 3,850,000
7 Vent Cup :
- dia. 80 mm bh 2.00 341,250 682,500
Sub Total Pekerjaan Instalasi Pipa Air Kotor, Kotor & Vent dalam bangunan 241,496,738
2 Instalasi Pipa Tegak Air Hujan dengan Pipa PVC kelas AW 10 kg/cm2 termasuk
gantungan/hanger, support, fitting dan aksesories :
- dia .150 mm m' 19.00 220,820 4,195,580
- dia .100 mm m' 301.00 153,900 46,323,900
- dia . 80 mm m' 7.00 105,190 736,330
Page 15 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
XV PEKERJAAN PEMADAM KEBAKARAN
Pengadaan dan pemasangan lengkap
sesuai gambar & spesifikasi teknis
A.2 Sprinkler
1 Instalasi pipa utama dengan pipa Black steel Sch. 40
termasuk fitting dan aksesoriesnya :
- dia. 150 mm Tegak (Shaft) m' 52.00 800,660 41,634,320
- dia. 80 mm Pipa tegak Shaft test drain m' 30.00 328,950 9,868,500
- dia. 25 mm m' 3.00 85,310 255,930
4 Gate Valve :
- dia. 65 mm bh 2.00 4,884,868 9,769,736
B.2 Lantai 2
1 Hydrant Box Type Indoor lengkap terpasang unit 2.00 4,773,510 9,547,020
ukuran : 125 x 75 x 18 cm, Cat Bakar
- 1 pc Hose Nozzle dia. 40 mm
- 1 pc Hydrant valve dia. 40 mm
- 1 pc Hose rack 600 mm COMB
- 1 roll fire hose with Machino Coupling dia. 40 mm x 30 m
4 Gate Valve :
- dia. 65 mm bh 2.00 4,884,868 9,769,736
B.3 Lantai 3
1 Hydrant Box Type Indoor lengkap terpasang unit 2.00 4,773,510 9,547,020
ukuran : 125 x 75 x 18 cm, Cat Bakar
- 1 pc Hose Nozzle dia. 40 mm
- 1 pc Hydrant valve dia. 40 mm
- 1 pc Hose rack 600 mm COMB
- 1 roll fire hose with Machino Coupling dia. 40 mm x 30 m
Page 16 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- dia. 65 mm bh 2.00 1,548,708 3,097,416
4 Gate Valve :
- dia. 65 mm bh 2.00 4,884,868 9,769,736
3 Branch Control Valve dia. 150 mm terdiri dari : set 1.00 14,023,800 14,023,800
- Butterfly Valve with Tamper Switch dia. 100 bh = 1 bh
- Flow Switch dia. 100 mm = 1 bh
- Sight Glass = 1 bh
- Test Drain Valve = 2 bh
C.2 Lantai 2
1 Instalasi sprinkler dengan Pipa Black Steel Sch. 40 termasuk
fitting, gantungan/hanger/support dan aksesories :
- dia. 80 mm m' 30.00 328,950 9,868,500
- dia. 65 mm m' 17.00 259,530 4,412,010
- dia. 50 mm m' 23.00 178,730 4,110,790
- dia. 40 mm m' 14.00 133,880 1,874,320
- dia. 32 mm m' 13.00 112,210 1,458,730
- dia. 25 mm m' 202.00 85,310 17,232,620
- dia. 25 mm Drooper m' 37.00 85,310 3,156,470
3 Branch Control Valve dia. 80 mm terdiri dari : set 1.00 10,168,200 10,168,200
- Butterfly Valve with Tamper Switch dia. 80 bh = 1 bh
- Flow Switch dia. 80 mm = 1 bh
- Sight Glass = 1 bh
- Test Drain Valve = 2 bh
C.3 Lantai 3
1 Instalasi sprinkler dengan Pipa Black Steel Sch. 40 termasuk
fitting, gantungan/hanger/support dan aksesories :
- dia. 100 mm m' 13.00 457,940 5,953,220
- dia. 80 mm m' 24.00 328,950 7,894,800
- dia. 65 mm m' 17.00 259,530 4,412,010
- dia. 50 mm m' 18.00 178,730 3,217,140
- dia. 40 mm m' 5.00 133,880 669,400
- dia. 32 mm m' 13.00 112,210 1,458,730
- dia. 25 mm m' 218.00 85,310 18,597,580
- dia. 25 mm Drooper m' 34.00 85,310 2,900,540
3 Branch Control Valve dia. 100 mm terdiri dari : set 1.00 11,025,000 11,025,000
- Butterfly Valve with Tamper Switch dia. 100 bh = 1 bh
- Flow Switch dia. 100 mm = 1 bh
- Sight Glass = 1 bh
- Test Drain Valve = 2 bh
Page 17 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
A.1 Lantai 1
1 a IU-OU-GD.A.1.1 unit 1.00 31,386,272 31,386,272
- Type : Split Duct c/w Pre Filter
- Kapasitas : 48.000 BTUH
- Power : sesuai seleksi unit
- Air Flow Rate : 1.400 cfm
- Lokasi : R. Administrasi IRNA
Page 18 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Euro Vent Standard
Everage Arrestance : 90 - 95%
Material Resistance (Pa) : 150
Face Felocity. MpM : 150
Size Frame : menyesuaikan ukuran unit
A.2 Lantai 2
1 a IU-OU-GD.A.2.1 s/d GD.A.2.4 unit 4.00 17,158,910 68,635,638
- Type : Split Duct c/w Pre Filter
- Kapasitas : 30.000 BTUH
- Power : sesuai seleksi unit
- Air Flow Rate : 900 cfm
- Lokasi : Poli Umum, R. Tunggu Dokter, Poli Jantung/ Poli Paru/ Poli Penyakit Dalam
Poli Tumbuh Kebang/ Poli Gizi / Poli Anak
A.2 Lantai 3
1 a IU-OU-GD.A.3.1 s/d GD.A.3.2 unit 2.00 17,158,910 34,317,819
- Type : Split Duct c/w Pre Filter
- Kapasitas : 30.000 BTUH
- Power : sesuai seleksi unit
- Air Flow Rate : 900 cfm
- Lokasi : Poli THT, R. Tunggu Dokter
Page 19 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
A.3 Lantai Atap
1 IU-OU-GD.A.LA.1 s/d GD.A.LA.1A unit 2.00 5,940,000 11,880,000
- Type : Wall Mounted Inverter
- Kapasitas : 12.000 BTUH
- Power : sesuai seleksi unit
- Air Flow Rate : 350 cfm
- Lokasi : R. Lift
B.1 Lantai 1
1 EF-GD.A.1.1 unit 1.00 7,350,000 7,350,000
- Type : In Line
- Kapasitas : 550 CFM
- Ext. Static Pressure : 1,0 In Wg
- Putaran : 1.440 RPM
- Power : sesuai seleksi unit
- Lokasi : Toilet
B.2 Lantai 2
1 EF-GD.A.2.1 unit 1.00 7,350,000 7,350,000
- Type : In Line
- Kapasitas : 550 CFM
- Ext. Static Pressure : 1,0 In Wg
- Putaran : 1.440 RPM
- Power : sesuai seleksi unit
- Lokasi : Toilet
B.3 Lantai 3
1 EF-GD.A.3.1 unit 1.00 7,350,000 7,350,000
- Type : In Line
- Kapasitas : 550 CFM
- Ext. Static Pressure : 1,0 In Wg
- Putaran : 1.440 RPM
- Power : sesuai seleksi unit
- Lokasi : Toilet
Page 20 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- Type : Axial
- Kapasitas : 4.000 CFM
- Static Pressure : 2,5 In Wg
- Putaran : 1.440 RPM
- Power : sesuai seleksi unit
- Lokasi : Area R. Tunggu
C.2 Lantai 2
1 Pengadaan dan pemasangan pipa refrigerant ASTM B280 + isolasi lengkap dengan hanger
dan aksesories pendukung lainnya sesuai dengan spesifikasi dan gambar detail
C.3 Lantai 3
1 Pengadaan dan pemasangan pipa refrigerant ASTM B280 + isolasi lengkap dengan hanger
dan aksesories pendukung lainnya sesuai dengan spesifikasi dan gambar detail
Page 21 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
2 Unit AC
a Ducting Bahan BJLS + isolasi elestomeric nitrille rubber class 0 lengkap dengan
gantungan/hanger/support dan aksesories lainya
- BjLS 80 m2 - 476,100 -
- BjLS 60 m2 121.00 400,880 48,506,480
- BjLS 50 m2 93.00 372,650 34,656,450
E.2 Lantai 2
1 Unit Fan
a Ducting tanpa isolasi finish cat zinkromat lengkap dgn
gantungan/hanger/support dan aksesories lainnya :
- BjLS 80 m2 48.00 267,020 12,816,960
- BjLS 60 m2 89.00 204,930 18,238,770
- BjLS 50 m2 49.00 184,580 9,044,420
2 Unit AC
a Ducting Bahan BJLS + isolasi elestomeric nitrille rubber class 0 lengkap dengan
gantungan/hanger/support dan aksesories lainya
- BjLS 80 m2 - 476,100 -
- BjLS 60 m2 226.00 400,880 90,598,880
- BjLS 50 m2 106.00 372,650 39,500,900
Page 22 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Sub Total Lantai 2 194,361,730
E.3 Lantai 3
1 Unit Fan
a Ducting tanpa isolasi finish cat zinkromat lengkap dgn
gantungan/hanger/support dan aksesories lainnya :
- BjLS 80 m2 47.00 267,020 12,549,940
- BjLS 60 m2 139.00 204,930 28,485,270
- BjLS 50 m2 104.00 184,580 19,196,320
2 Unit AC
a Ducting Bahan BJLS + isolasi elestomeric nitrille rubber class 0 lengkap dengan -
gantungan/hanger/support dan aksesories lainya
- BjLS 80 m2 - 476,100 -
- BjLS 60 m2 222.00 400,880 88,995,360
- BjLS 50 m2 134.00 372,650 49,935,100
2 Pengkabelan unit Fan dari P.AC-1A ke masing-masing unit titik 4.00 600,000 2,400,000
3 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 171.00 15,698 2,684,358
F.2 Lantai 2
1 Pengkabelan unit AC dari P.AC-2A ke masing-masing unit titik 6.00 850,000 5,100,000
2 Pengkabelan unit Fan dari P.AC-2A ke masing-masing unit titik 3.00 600,000 1,800,000
3 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 153.00 15,698 2,401,794
F.3 Lantai 3
1 Pengkabelan unit AC dari P.AC-3A ke masing-masing unit titik 6.00 850,000 5,100,000
2 Pengkabelan unit Fan dari P.AC-3A ke masing-masing unit titik 3.00 600,000 1,800,000
3 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 121.00 15,698 1,899,458
dalam konduit PVC HI dia. 20 mm
2 Pengkabelan unit Fan dari P.LIFT.A ke masing-masing unit titik 1.00 600,000 600,000
3 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 8.00 15,698 125,584
dalam konduit PVC HI dia. 20 mm
Page 23 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
TOTAL PEKERJAAN TATA UDARA 1,371,858,549
1 LIFT BED / PASSENGER (L.B/P-1 & L.B/P-2) unit 2.00 640,000,000 1,280,000,000
Spesifikasi :
- Type : Machine Room Elevator
- Kapasitas : 1600 kg
- Kecepatan : 60 Mpm
- Travel : 9.180 mm
- Travel Height : 15.180 mm
- Jumlah pemberhentian : 3 bh
- Jumlah Pintu : 3 bh
- Hoistway Size ( W x D ) : 2.400 x 3.000 mm
- Car Size ( W x D x H ) : 1.400 x 2.400 x 2.400 mm
- Type Pintu : 2 - Side Opening Door
- Lebar Pintu : 1.300 mm
- Tinggi Pintu : 2.100 mm
- Overhead : 4.500 mm
- Pit : 1.500 mm
- Kontrol : AC Gearred (OHT) VVVF Control
- Cara Operasi : Duplex Operation
- Penggerak : Traction Drive AC - Gearless
- Car Wall Finishing : Hairline Stainless Steel
- Power : Sesuai Seleksi Unit
termasuk interfacing dengan General Fire Alarm
1 Lantai 1
A STATIONS & DIVERTERS AND ACCESSORIES
1 Diverter 3-Way Unit 1.00 29,454,660 29,454,660
2 Bottom Loading Station Unit 1.00 39,637,440 39,637,440
All Stations incl.: Basket, Cushion and Carrier Rack
B.6.2 Lantai 2
A STATIONS & DIVERTERS AND ACCESSORIES
1 Bottom Loading Station Unit 1.00 39,637,440 39,637,440
All Stations incl.: Basket, Cushion and Carrier Rack
Page 24 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
B.6.3 Lantai 3
A STATIONS & DIVERTERS AND ACCESSORIES
1 Bottom Loading Station Unit 1.00 39,637,440 39,637,440
All Stations incl.: Basket, Cushion and Carrier Rack
Page 25 of 285
ENGINEERING ESTIMATE (EE)
PEKERJAAN MEKANIKAL & ELEKTRIKAL
PROYEK : PAKET PEKERJAAN JASA KONSULTANSI KONSTRUKSI PENGADAAN JASA KONSULTAN LANJUTAN RUMAH SAKIT KUPANG NTT
BANGUNAN : GEDUNG B (LABORATORIUM)
LOKASI : NUSA TENGGARA TIMUR
TOTAL 9,085,428,570
Page 26 of 285
ENGINEERING ESTIMATE (EE)
PEKERJAAN MEKANIKAL & ELEKTRIKAL
PROYEK : PAKET PEKERJAAN JASA KONSULTANSI KONSTRUKSI PENGADAAN JASA KONSULTAN LANJUTAN RUMAH SAKIT KUPANG NTT
BANGUNAN : GEDUNG B (LABORATORIUM)
LOKASI : NUSA TENGGARA TIMUR
A.2 Lantai 2
1 PP.2B unit 1.00 6,949,000 6,949,000
2 P.AC-2B unit 1.00 12,005,000 12,005,000
A.3 Lantai 3
1 PP.3B unit 1.00 6,796,000 6,796,000
2 P.AC-3B unit 1.00 11,172,000 11,172,000
2 Dari SDP.B
NYY 4 x 6 mm2 ke PP.1B mtr 11.00 50,715 557,865
NYY 4 x 16 mm2 ke PP.2B mtr 16.00 134,033 2,144,528
NYY 4 x 10 mm2 ke PP.3B mtr 21.00 80,903 1,698,963
NYY 4(2 x 1 x 95 mm2) ke P. LAB mtr 13.00 1,458,664 18,962,632
NYY 3 x 6 mm2 ke PC. VK mtr 27.00 38,640 1,043,280
NYY 4 x 25 mm2 ke P. SUMPIT B mtr 13.00 205,275 2,668,575
3 Dari SDP.AC-B
NYY 4 x 70 mm2 ke P.AC-1B mtr 11.00 536,130 5,897,430
NYY 4 x 35 mm2 ke P.AC-2B mtr 16.00 278,933 4,462,928
NYY 4 x 35 mm2 ke P.AC-3B mtr 21.00 278,933 5,857,593
4 Dari P. SUMPIT B
NYY 4 x 4 mm2 PC. SUMPIT B-01 mtr 38.00 36,225 1,376,550
NYY 4 x 4 mm2 PC. SUMPIT B-02 mtr 39.00 36,225 1,412,775
NYY 4 x 4 mm2 PC. SUMPIT B-03 mtr 35.00 36,225 1,267,875
NYY 4 x 4 mm2 PC. SUMPIT KIMIA B-02 mtr 34.00 36,225 1,231,650
NYY 4 x 4 mm2 PC. SUMPIT KIMIA B-03 mtr 36.00 36,225 1,304,100
NYY 4 x 4 mm2 PC. SUMPIT KIMIA B-04 mtr 19.00 36,225 688,275
5 Dari SDP.PF-C
FRC 4 x 1 x 4 mm2 P PF.B mtr 136.00 95,440 12,979,840
Page 27 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- Surge Arrester tipe 1/1P+N 8kA 1 pcs
- MCB 1P/6A/4,5ka for Protection Unit 1 pcs
- Wiring and ALL Acc.Components Panel 1 lot
2 Lantai 2
Kabel Tray Listrik
- uk. 600 mm x 50 mm m 30.00 353,000 10,590,000
- uk. 300 mm x 50 mm m 19.00 211,600 4,020,400
3 Lantai 3
Kabel Tray Listrik
- uk. 600 mm x 50 mm m 30.00 353,000 10,590,000
- uk. 300 mm x 50 mm m 19.00 211,600 4,020,400
F.2 Lantai 2
1 RM TLED 3 x 8 Watt + Cover bh 3.00 1,360,594 4,081,783
2 RM TLED 3 x 8 Watt + Cover c/w Nicad Battery bh 8.00 2,403,118 19,224,946
3 RM TLED 2 x 14 Watt + Cover bh 12.00 1,205,715 14,468,580
Page 28 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
4 RM TLED 2 x 14 Watt + Cover c/w Nicad Battery bh 6.00 2,248,239 13,489,434
5 TLED 2x14 Watt (Balk) bh - 881,139 -
6 TLED 2x14 Watt (Balk) c/w Nicad Battery bh 1.00 1,923,663 1,923,663
7 Down Light LED E27 13 Watt Bulb + Cover bh 29.00 372,527 10,803,295
8 Down Light LED E27 13 Watt Bulb + Cover c/w Nicad Battery bh 9.00 1,481,731 13,335,575
9 Down Light LED E27 6 Watt Bulb + Cover bh 8.00 284,327 2,274,619
10 Spot Light LED 10W bh 2.00 298,704 597,408
11 Lampu Baret LED E27 10,5 Watt Bulb bh 2.00 229,996 459,992
12 Lampu Baret LED E27 10,5 Watt Bulb + Nicad Battery bh 1.00 1,339,288 1,339,288
13 Lampu Bed LED 29 Watt bh 12.00 930,304 11,163,650
14 Lampu Bed Head LED 8 watt bh 12.00 354,799 4,257,590
15 Exit Lamp LED 8 Watt bh 2.00 1,349,254 2,698,508
16 Stop Kontak 1 Ph 200 Watt bh 54.00 52,763 2,849,175
17 Stop Kontak 1 Ph 200 Watt Backup Trafo Isolasi + UPS bh 27.00 52,763 1,424,588
18 Stop Kontak Ceiling TV 1Ph 200 Watt bh 5.00 52,763 263,813
19 Saklar Tunggal bh 21.00 44,163 927,423
20 Saklar Ganda bh 26.00 48,794 1,268,631
21 Saklar Hotel bh - 46,242 -
22 Grid Switch 6 Gang bh - 329,007 -
23 Titik nyala lampu dengan kabel NYM 3 x 2,5 mm² di dalam conduit PVC HI 20 mm titik 107.00 321,800 34,432,600
24 Titik nyala Stop kontak NYM 3 x 2,5 mm² didalam conduit PVC HI 20 mm titik 86.00 400,900 34,477,400
F.3 Lantai 3
1 RM TLED 3 x 8 Watt + Cover bh 4.00 1,360,594 5,442,377
2 RM TLED 3 x 8 Watt + Cover c/w Nicad Battery bh 4.00 2,403,118 9,612,473
3 RM TLED 2 x 14 Watt + Cover bh 38.00 1,205,715 45,817,170
4 RM TLED 2 x 14 Watt + Cover c/w Nicad Battery bh 14.00 2,248,239 31,475,346
5 TLED 2x14 Watt (Balk) bh - 881,139 -
6 TLED 2x14 Watt (Balk) c/w Nicad Battery bh 1.00 1,923,663 1,923,663
7 Down Light LED E27 13 Watt Bulb + Cover bh 4.00 372,527 1,490,110
8 Down Light LED E27 13 Watt Bulb + Cover c/w Nicad Battery bh 1.00 1,481,731 1,481,731
9 Down Light LED E27 6 Watt Bulb + Cover bh 6.00 284,327 1,705,964
10 Spot Light LED 10W bh 4.00 298,704 1,194,816
11 Lampu Baret LED E27 10,5 Watt Bulb bh 2.00 229,996 459,992
12 Lampu Baret LED E27 10,5 Watt Bulb + Nicad Battery bh 1.00 1,339,288 1,339,288
13 Lampu Bed LED 29 Watt bh 4.00 930,304 3,721,217
14 Lampu Bed Head LED 8 watt bh 4.00 354,799 1,419,197
15 Exit Lamp LED 8 Watt bh 1.00 1,349,254 1,349,254
16 Stop Kontak 1 Ph 200 Watt bh 50.00 52,763 2,638,125
17 Stop Kontak Ceiling TV 1Ph 200 Watt bh 5.00 52,763 263,813
18 Saklar Tunggal bh 16.00 44,163 706,608
19 Saklar Ganda bh 12.00 48,794 585,522
20 Saklar Hotel bh - 46,242 -
21 Grid Switch 6 Gang bh 1.00 329,007 329,007
22 Titik nyala lampu dengan kabel NYM 3 x 2,5 mm² di dalam conduit PVC HI 20 mm titik 88.00 321,800 28,318,400
23 Titik nyala Stop kontak NYM 3 x 2,5 mm² didalam conduit PVC HI 20 mm titik 55.00 400,900 22,049,500
Page 29 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Addressable Relay Module P. AC unit 3.00 1,328,670.00 3,986,010
Addressable Relay Module Pressurized Fan unit 1.00 1,328,670.00 1,328,670
C.1 Lantai 1
1 Terminal Box (TB. FA - 1B) unit 1.00 630,525 630,525
2 Horn & Strobe bh 2.00 795,769 1,591,538
3 Manual Break Glass bh 2.00 289,013 578,025
4 Addresable Rate of Rise Detector bh 7.00 1,092,315 7,646,205
5 Addresable Fixed Heat Detector bh 1.00 1,092,315 1,092,315
6 Addressable Smoke Detector bh 22.00 1,373,846 30,224,618
7 Smoke Detector Photoelectric bh 3.00 581,805 1,745,415
8 Rate of Rise Detector bh - 491,715 -
9 Fixed Heat Detector bh - 491,715 -
10 Telephone Jack bh 2.00 487,961 975,923
11 End off line bh 7.00 6,379 44,651
12 P.AC.1 bh 1.00 by Others
13 Flow Switch bh 1.00 by Others
C.2 Lantai 2
1 Terminal Box (TB. FA - 2B) unit 1.00 630,525 630,525
2 Horn & Strobe bh 2.00 795,769 1,591,538
3 Manual Break Glass bh 2.00 289,013 578,025
4 Addresable Rate of Rise Detector bh 5.00 1,092,315 5,461,575
5 Addresable Fixed Heat Detector bh 1.00 1,092,315 1,092,315
6 Addressable Smoke Detector bh 19.00 1,373,846 26,103,079
7 Smoke Detector Photoelectric bh 5.00 581,805 2,909,025
8 Rate of Rise Detector bh - 491,715 -
9 Fixed Heat Detector bh 491,715 -
10 Telephone Jack bh 2.00 487,961 975,923
11 End off line bh 7.00 6,379 44,651
12 P.AC.2 bh 1.00 by Others
13 Flow Switch bh 1.00 by Others
Page 30 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Instalasi Manual Break Glass NYA 2 x 1,5 mm2 titik 2.00 231,500 463,000
Instalasi Telephone Jack ITC 2 x d 0,6 mm titik 2.00 497,000 994,000
Instalasi PAC NYA 3 x 1,5 mm2 titik 1.00 517,700 517,700
Instalasi Flow Switch NYA 3 x 1,5 mm2 titik 1.00 773,200 773,200
Instalasi Pressurized Fan NYA 3 x 1,5 mm2 titik 1.00 773,200 773,200
C.2 Lantai 2
1 Terminal Box Sound System Lt. 2 (TB. TS. 2B) bh 1.00 800,100 800,100
2 Ceiling Speaker 3 Watt + Matching Transformer bh 33.00 196,035 6,469,155
3 Volume Control bh 12.00 451,920 5,423,040
4 Emergency Speaker 6 Watt bh - 322,382 -
5 Instalasi untuk Speaker dengan kabel NYMHY 2 x 1.5 mm2 ttk 33.00 297,900 9,830,700
dalam conduit PVC HI dia. 20 mm
6 Instalasi untuk Volume Control dengan kabel NYMHY 3 x 1.5 mm2 ttk 12.00 492,500 5,910,000
dalam conduit PVC HI dia. 20 mm
7 Instalasi untuk Speaker dengan kabel FRC 2 x 1,5 mm2 ttk - 597,400 -
dalam conduit PVC HI dia. 20 mm
Page 31 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
2 Outlet :
- Outlet Access Point RJ 45 bh 2.00 135,000 270,000
- Outlet Data RJ 45 bh 13.00 135,000 1,755,000
- Outlet Telepon RJ 45 bh 11.00 135,000 1,485,000
3 Fixture Unit
- Access Point bh 2.00 1,390,000 2,780,000
- Pesawat Telepon IP Extention bh 9.00 1,135,000 10,215,000
- Pesawat Telepon IP Direct bh 1.00 1,135,000 1,135,000
- Pesawat Telepon IP Faximile bh 1.00 6,775,000 6,775,000
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point titik 2.00 936,100 1,872,200
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 13.00 936,100 12,169,300
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 11.00 936,100 10,297,100
B.2 Lantai 2
1 Peralatan Distribusi
- Wall Mounted Rack 19", 15U c/w Accessories unit 1.00 2,200,000 2,200,000
- Wiring Management 1U bh 2.00 148,000 296,000
- Patch Panel FO 12 port bh 1.00 1,634,400 1,634,400
- FO Connector bh 1.00 160,800 160,800
- UTP Cat 6 Patch Panel 24 Port Loaded bh 1.00 1,380,000 1,380,000
- UTP Cat 6 Patch Cord, 1m bh 24.00 45,000 1,080,000
- Switch Hub 24 port bh 1.00 4,508,000 4,508,000
2 Outlet :
- Outlet Access Point RJ 45 bh 2.00 135,000 270,000
- Outlet Data RJ 45 bh 8.00 135,000 1,080,000
- Outlet Telepon RJ 45 bh 7.00 135,000 945,000
3 Fixture Unit
- Access Point bh 2.00 1,390,000 2,780,000
- Pesawat Telepon IP Extention bh 7.00 1,135,000 7,945,000
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point titik 2.00 936,100 1,872,200
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 8.00 936,100 7,488,800
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 7.00 936,100 6,552,700
B.3 Lantai 3
1 Peralatan Distribusi
- Wall Mounted Rack 19", 15U c/w Accessories unit 1.00 2,200,000 2,200,000
- Wiring Management 1U bh 2.00 148,000 296,000
- Patch Panel FO 12 port bh 1.00 1,634,400 1,634,400
- FO Connector bh 1.00 160,800 160,800
- UTP Cat 6 Patch Panel 24 Port Loaded bh 2.00 1,380,000 2,760,000
- UTP Cat 6 Patch Cord, 1m bh 48.00 45,000 2,160,000
- Switch Hub 24 port bh 2.00 4,508,000 9,016,000
2 Outlet :
- Outlet Access Point RJ 45 bh 2.00 135,000 270,000
- Outlet Data RJ 45 bh 13.00 135,000 1,755,000
- Outlet Telepon RJ 45 bh 14.00 135,000 1,890,000
3 Fixture Unit
- Access Point bh 2.00 1,390,000 2,780,000
- Pesawat Telepon IP Extention bh 14.00 1,135,000 15,890,000
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point titik 2.00 936,100 1,872,200
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 13.00 936,100 12,169,300
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 14.00 936,100 13,105,400
2 Lantai 2
Kabel Tray 200 mm x 100 mm m 50.00 199,900 9,995,000
Page 32 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
3 Lantai 3
Kabel Tray 200 mm x 100 mm m 51.00 199,900 10,194,900
B.2 Lantai 2
1 Splitter 6 Way Unit 1.00 533,108 533,108
2 Outlet TV Unit 5.00 80,325 401,625
3 Instalasi kabel Outlet TV, coaxial RG6 (5C/2 volt) dakan konduit PVC HI dia. 20 mmtitik 5.00 533,800 2,669,000
4 Instalasi kabel Splitter, Coaxial RG-11 (7C) dalam konduit PVC HI dia. 20 mm m 27.00 26,775 722,925
B.3 Lantai 3
1 Splitter 6 Way Unit 1.00 533,108 533,108
2 Splitter 4 Way Unit 1.00 366,892 366,892
3 Booster Unit 1.00 1,658,475 1,658,475
4 Outlet TV Unit 5.00 80,325 401,625
5 Instalasi kabel Outlet TV, coaxial RG6 (5C/2 volt) dakan konduit PVC HI dia. 20 mmtitik 5.00 533,800 2,669,000
6 Instalasi kabel Splitter, Coaxial RG-11 (7C) dalam konduit PVC HI dia. 20 mm m 132.00 26,775 3,534,300
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 2.00 5,901,300 11,802,600
- Indoor Fixed Dome IP Camera + thermal detector bh 1.00 139,500,000 139,500,000
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 3.00 936,100 2,808,300
C.2 Lantai 2
1 Peralatan Distribusi
- Wall Mounted Rack 19", 8U c/w Accessories bh 1.00 1,940,000 1,940,000
Page 33 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- Wiring Management 1U bh 1.00 148,000 148,000
- Patch Panel FO 12 port bh 1.00 1,634,400 1,634,400
- FO Connector bh 1.00 160,800 160,800
- UTP Cat 6 Patch Panel 24 Port Loaded bh 1.00 1,380,000 1,380,000
- UTP Cat 6 Patch Cord, 1m bh 24.00 45,000 1,080,000
- Switch Hub PoE 24 port bh 1.00 4,508,000 4,508,000
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 5.00 5,901,300 29,506,500
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 5.00 936,100 4,680,500
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 5.00 5,901,300 29,506,500
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 5.00 936,100 4,680,500
2 Kabel Data dari MCU di Ruang BAS ke: mtr 368.00 51,424 18,924,098
DDC Lt. D ~ 3 STP AWG #18 dalam Conduit PVC 20 mm
1 LANTAI 1
PANEL SDP.B
PANEL SDP.AC.B
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
Power Monitoring HLI Titik 2.00 1,677,000 3,354,000
PANEL PP.1B
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
On - Off Digital Output Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
PANEL PP.AC.1B
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
Page 34 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
POMPA PON
Status Digital Input Titik 4.00 928,000 3,712,000
Trip Alarm Digital Input Titik 4.00 928,000 3,712,000
Level alarm Digital Input Titik 8.00 928,000 7,424,000
2 LANTAI 2
PANEL PP, PAC
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
On - Off Digital Output Titik 2.00 928,000 1,856,000
Power Monitoring HLI Titik 2.00 1,677,000 3,354,000
3 LANTAI 3
PANEL PP, PAC
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
On - Off Digital Output Titik 2.00 928,000 1,856,000
Power Monitoring HLI Titik 2.00 1,677,000 3,354,000
4 LANTAI ATAP
PANEL PRESSURE FAN
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
XI PEKERJAAN ANTRIAN
Pengadaan dan pemasangan sistem lengkap sesuai
gambar & spesifikasi teknis
XI.A Lantai 1
1 Controller Mesin Antrian unit 1.00 94,000,000 94,000,000
2 Tombol Panggil unit 7.00 1,450,000 10,150,000
3 Counter Display unit 7.00 3,200,000 22,400,000
4 Main Counter Display unit 3.00 8,500,000 25,500,000
5 Mini Speaker System unit 1.00 1,250,000 1,250,000
6 Instalasi Sistem Antrian titik 18.00 725,000 13,050,000
XI.B Lantai 2
1 Controller Mesin Antrian unit - 94,000,000 -
2 Tombol Panggil unit 1.00 1,450,000 1,450,000
3 Counter Display unit 1.00 3,200,000 3,200,000
4 Main Counter Display unit 1.00 8,500,000 8,500,000
5 Mini Speaker System unit - 1,250,000 -
6 Instalasi Sistem Antrian titik 3.00 725,000 2,175,000
XI.C Lantai 3
1 Controller Mesin Antrian unit - 94,000,000 -
2 Tombol Panggil unit 7.00 1,450,000 10,150,000
3 Counter Display unit 7.00 3,200,000 22,400,000
4 Main Counter Display unit 3.00 8,500,000 25,500,000
5 Mini Speaker System unit 1.00 1,250,000 1,250,000
6 Instalasi Sistem Antrian titik 17.00 725,000 12,325,000
Page 35 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
a Main Components:
RO Membrane: Optional 2.5”x40”
Membrane Housing: SS304 body+ABS end caps-2054 x 1pc
Pump: Italian Rotary Vane Pump 400LPH 12Bar + 1/2HP
Frame: Electro-Plated SS304
Pre-Filter: (20” KF Housing + PP Cartridge 5um) x 2 sets
Solenoid Valve x 2
Low Pressure Switch x 1
Concentrate Recycling Valve x 1
Product Storage Tank SUS 304 500 L
7 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
A.2.2 Lantai 2
1 Instalasi pipa air bersih dengan PPR80 - PN10
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 50 mm m' 18.00 132,320 2,381,760
- dia. 40 mm m' 17.00 89,540 1,522,180
- dia. 32 mm m' 30.00 64,860 1,945,800
- dia. 25 mm m' 187.00 46,250 8,648,750
- dia. 20 mm m' 66.00 28,830 1,902,780
- dia. 15 mm m' 52.00 22,590 1,174,680
Page 36 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- dia. 25 mm bh 1.00 288,330 288,330
- dia. 20 mm bh 14.00 211,523 2,961,315
- dia. 15 mm bh 1.00 163,380 163,380
5 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
A.2.3 Lantai 3
1 Instalasi pipa air bersih dari Booster Packaged ke Lantai 2 & 3 dengan PPR80 - PN10
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 65 mm m' 121.00 177,620 21,492,020
6 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
2 Ball Valve :
- dia. 15 mm bh 1.00 163,380 163,380
Bak Submersible Cutter Pump + QDC (Sewage.AB-01) unit 1.00 skope sipil
Kapasitas : 5 m³
Ukuran : 2500 x 2000 x (1000+500)mm
Bak Submersible Cutter Pump + QDC (Sewage.B-02) unit 1.00 skope sipil
Kapasitas : 5 m³
Ukuran : 2500 x 2000 x (1000+500)mm
Page 37 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Type : Submersible Sewage Pump with Cutter
Head : 20 meter
Power : sesuai seleksi unit
Jumah Pompa : 2 unit
Bekerja secara parallel
lengkap dengan katup2, panel kontrol otomatis dan Level Control
Bak Submersible Cutter Pump + QDC (Sewage.B-03) unit 1.00 skope sipil
Kapasitas : 1 m³
Ukuran : 1000 x 1000 x (1000+500)mm
Bak Submersible Cutter Pump + QDC (Chemical.B-02) unit 1.00 skope sipil
Kapasitas : 3 m³
Ukuran : 2000 x 1000 x (1000+500)mm
Bak Submersible Cutter Pump + QDC (Chemical.B-03) unit 1.00 skope sipil
Kapasitas : 2 m³
Ukuran : 2000 x 1000 x (1000+500)mm
Bak Submersible Cutter Pump + QDC (Chemical.B-04) unit 1.00 skope sipil
Kapasitas : 2 m³
Ukuran : 2000 x 1000 x (1000+500)mm
Shaft
- dia. 100 mm m' 27.00 153,900 4,155,300
2 Instalasi Pipa Utama Air Kotor dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
Dari Shaft ke Bak Sumpit
- dia. 150 mm m' 16.00 288,460 4,615,360
Shaft
- dia. 100 mm m' 27.00 153,900 4,155,300
3 Instalasi Pipa Utama Air Kotor Kimia dengan Pipa Cast Iron
termasuk gantungan/hanger, support, fitting dan aksesories :
Dari Shaft ke Bak Sumpit
- dia. 150 mm m' 10.00 692,030 6,920,300
Shaft
- dia. 100 mm m' 14.00 425,060 5,950,840
6 Vent Cup
- dia. 80 mm bh 2.00 341,250 682,500
B.3 Pekerjaan Instalasi Pipa Air Kotor, Kotor & Vent dalam bangunan
B.3.1 Lantai 1
1 Instalasi Air Kotoran Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 23.00 153,900 3,539,700
Page 38 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
2 Instalasi Air Kotor Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 11.00 153,900 1,692,900
- dia. 80 mm m 16.00 105,190 1,683,040
- dia. 50 mm m 16.00 63,440 1,015,040
- dia. 40 mm m 2.00 48,250 96,500
- Gater 200x100mm m 4.00 sipil
B.3.2 Lantai 2
1 Instalasi Air Kotoran Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 57.00 153,900 8,772,300
2 Instalasi Air Kotor Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 19.00 153,900 2,924,100
- dia. 80 mm m 44.00 105,190 4,628,360
- dia. 50 mm m 17.00 63,440 1,078,480
- dia. 40 mm m 18.00 48,250 868,500
2 Instalasi Air Kotor Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 3.00 153,900 461,700
- dia. 80 mm m 27.00 105,190 2,840,130
- dia. 50 mm m 9.00 63,440 570,960
- dia. 40 mm m 12.00 48,250 579,000
SUB TOTAL AIR KOTORAN, KOTOR DAN VENT DALAM BANGUNAN 117,567,980
Page 39 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
XII.C Instalasi Air Hujan
1 Roof Drain :
- dia. 100 mm bh 11.00 296,888 3,265,763
- dia. 80 mm bh 1.00 279,825 279,825
2 Instalasi Pipa Tegak Air Hujan dengan Pipa PVC kelas AW 10 kg/cm2 termasuk
gantungan/hanger, support, fitting dan aksesories :
- dia .100 mm m' 217.00 153,900 33,396,300
- dia . 80 mm m' 4.00 105,190 420,760
INSTALASI UTAMA -
3 Zona Valve 3 Gas (O, A,V) + Alarm Set 1.00 37,298,640 37,298,640
Page 40 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Air Release Vent (ARV) dia. 25 mm bh 2.00 2,613,517 5,227,034
4
Pressure Gauge + gate valve bh 2.00 479,145 958,291
A.2 Sprinkler
Instalasi pipa utama dengan pipa Black steel Sch. 40
termasuk fitting dan aksesoriesnya :
- dia. 150 mm Tegak (Shaft) m' 37.00 800,660 29,624,420
- dia. 80 mm Pipa tegak Shaft test drain m' 40.00 328,950 13,158,000
- dia. 25 mm m' 14.00 85,310 1,194,340
4 Gate Valve :
- dia. 65 mm bh 2.00 4,884,868 9,769,736
B.2 Lantai 2
1 Hydrant Box Type Indoor lengkap terpasang unit 2.00 4,773,510 9,547,020
ukuran : 125 x 75 x 18 cm, Cat Bakar
- 1 pc Hose Nozzle dia. 40 mm
- 1 pc Hydrant valve dia. 40 mm
- 1 pc Hose rack 600 mm COMB
- 1 roll fire hose with Machino Coupling dia. 40 mm x 30 m
3 Gate Valve :
- dia. 65 mm bh 2.00 4,884,868 9,769,736
B.3 Lantai 3
1 Hydrant Box Type Indoor lengkap terpasang unit 2.00 4,773,510 9,547,020
ukuran : 125 x 75 x 18 cm, Cat Bakar
- 1 pc Hose Nozzle dia. 40 mm
- 1 pc Hydrant valve dia. 40 mm
- 1 pc Hose rack 600 mm COMB
- 1 roll fire hose with Machino Coupling dia. 40 mm x 30 m
3 Gate Valve :
- dia. 65 mm bh 2.00 4,884,868 9,769,736
Page 41 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
XV.C Instalasi Sprinkler pada Bangunan
C.1 Lantai 1
1 Instalasi sprinkler dengan Pipa Black Steel Sch. 40 termasuk
fitting, gantungan/hanger/support dan aksesories :
- dia. 80 mm m' 22.00 328,950 7,236,900
- dia. 65 mm m' 13.00 259,530 3,373,890
- dia. 50 mm m' 10.00 178,730 1,787,300
- dia. 40 mm m' 16.00 133,880 2,142,080
- dia. 32 mm m' 24.00 112,210 2,693,040
- dia. 25 mm m' 142.00 85,310 12,114,020
- dia. 25 mm Drooper m' 30.00 85,310 2,559,300
3 Branch Control Valve dia. 80 mm terdiri dari : set 1.00 10,168,200 10,168,200
- Butterfly Valve with Tamper Switch dia. 80 bh = 1 bh
- Flow Switch dia. 80 mm = 1 bh
- Sight Glass = 1 bh
- Test Drain Valve = 2 bh
C.2 Lantai 2
1 Instalasi sprinkler dengan Pipa Black Steel Sch. 40 termasuk
fitting, gantungan/hanger/support dan aksesories :
- dia. 80 mm m' 15.00 328,950 4,934,250
- dia. 65 mm m' 15.00 259,530 3,892,950
- dia. 50 mm m' 8.00 178,730 1,429,840
- dia. 40 mm m' 12.00 133,880 1,606,560
- dia. 32 mm m' 19.00 112,210 2,131,990
- dia. 25 mm m' 131.00 85,310 11,175,610
- dia. 25 mm Drooper m' 25.00 85,310 2,132,750
3 Branch Control Valve dia. 80 mm terdiri dari : set 1.00 10,168,200 10,168,200
- Butterfly Valve with Tamper Switch dia. 80 bh = 1 bh
- Flow Switch dia. 80 mm = 1 bh
- Sight Glass = 1 bh
- Test Drain Valve = 2 bh
C.3 Lantai 3
1 Instalasi sprinkler dengan Pipa Black Steel Sch. 40 termasuk
fitting, gantungan/hanger/support dan aksesories :
- dia. 80 mm m' 17.00 328,950 5,592,150
- dia. 65 mm m' 19.00 259,530 4,931,070
- dia. 50 mm m' 10.00 178,730 1,787,300
- dia. 40 mm m' - 133,880 -
- dia. 32 mm m' 17.00 112,210 1,907,570
- dia. 25 mm m' 127.00 85,310 10,834,370
- dia. 25 mm Drooper m' 24.00 85,310 2,047,440
3 Branch Control Valve dia. 80 mm terdiri dari : set 1.00 10,168,200 10,168,200
- Butterfly Valve with Tamper Switch dia. 80 bh = 1 bh
- Flow Switch dia. 80 mm = 1 bh
- Sight Glass = 1 bh
- Test Drain Valve = 2 bh
Page 42 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
XV.E Testing Commissioning
1 Testing & Commissioning Instalasi dan Peralatan Fire Hydrant & Sprinkler, lot 1.00 1,500,000 1,500,000
Extinguisher termasuk pengurusan ijin dari dinas terkait
A.1 Lantai 1
1 IU-OU-GD.B.1.1 s/d GD.B.1.2 unit 2.00 3,708,000 7,416,000
- Type : Wall Mounted Inverter
- Kapasitas : 7.000 BTUH
- Power : sesuai seleksi unit
- Air Flow Rate : 210 cfm
- Lokasi : Ruang Konsul, Ruang Adm
Page 43 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
b Pre Filter lengkap dengan housing set 1.00 2,700,000 2,700,000
type High Efficiency Catridge Filter Back Loading Methode
Euro Vent Standard
Everage Arrestance : 80 - 85%
Material Resistance (Pa) : 75
Face Felocity. MpM : 150
Size Frame : menyesuaikan ukuran unit
A.2 Lantai 2
1 IU-OU-GD.B.2.1 s/d GD.B.2.2 unit 2.00 18,421,364 36,842,728
- Type : Cassette Inverter
- Kapasitas : 25.000 BTUH
- Power : sesuai seleksi unit
- Air Flow Rate : 750 cfm
- Lokasi : R. Tunggu
Page 44 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- Lokasi : R. Bayi Sehat
A.3 Lantai 3
1 IU-OU-GD.B.3.1 unit 1.00 3,708,000 3,708,000
- Type : Wall Mounted Inverter
- Kapasitas : 7.000 BTUH
- Power : sesuai seleksi unit
- Air Flow Rate : 210 cfm
- Lokasi : Terapi 2
Page 45 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- Air Flow Rate : 600 cfm
- Lokasi : Terapi Okupasi,& Terapi Vokasional
B.1 Lantai 1
1 a EF-GD.B.1.1 unit 1.00 7,350,000 7,350,000
- Type : Inline - Plenum Box c/w PF & MF
- Kapasitas : 700 CFM
- Static Pressure : 3,5 In Wg
- Putaran : 1.440 RPM
- Power : sesuai seleksi unit
- Lokasi : Lab. VK
Page 46 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Euro Vent Standard
Everage Arrestance : 90 - 95%
Material Resistance (Pa) : 150
Face Felocity. MpM : 150
Size Frame : 700 x 650 x 500 mm
B.2 Lantai 2
1 EF-GD.B.2.1 s/d GD.B.2.2 unit 2.00 776,160 1,552,320
- Type : Ceiling Fan
- Kapasitas : 50 CFM
- Static Pressure : 0,35 In Wg
- Putaran : 950 RPM
- Power : sesuai seleksi unit
- Lokasi : Toilet R. Persiapan
Page 47 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
B.3 Lantai 3
1 EF-GD.B.3.1 unit 1.00 2,352,000 2,352,000
- Type : Inline
- Kapasitas : 200 CFM
- Static Pressure : 1,0 In Wg
- Putaran : 1.440 RPM
- Power : sesuai seleksi unit
- Lokasi : Toilet, R. Ganti
Page 48 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Bahan :
Pipa Refrigerant : Cooper Tube ASTM B 280
Pipa Drain : PVC kelas AW 10 kg/cm2
Isolasi Pipa : Elestomeric Nitrile Rubber Class 0
C.1 Lantai 1
1 Pipa AC Split + Isolasi
- dia. 6,4 mm & 9,5 mm IU-OU-GD.B.1.1 mtr 6.05 248,800.00 1,505,240
- dia. 6,4 mm & 9,5 mm IU-OU-GD.B.1.2 mtr 6.05 248,800.00 1,505,240
- dia. 6,4 mm & 12,7 mm IU-OU-GD.B.1.3 mtr 6.05 273,470.00 1,654,494
- dia. 6,4 mm & 9,5 mm IU-OU-GD.B.1.4 mtr 6.05 248,800.00 1,505,240
- dia. 6,4 mm & 9,5 mm IU-OU-GD.B.1.5 mtr 11.00 248,800.00 2,736,800
- dia. 9,52 mm & 19,05 mm IU-OU-GD.B.1.6 mtr 29.70 419,780.00 12,467,466
- dia. 12,7 mm & 25,4 mm IU-OU-GD.B.1.7 mtr 33.00 569,800.00 18,803,400
- dia. 9,52 mm & 19,05 mm IU-OU-GD.B.1.8 mtr 27.50 419,780.00 11,543,950
- dia. 9,52 mm & 19,05 mm IU-OU-GD.B.1.9 mtr 31.90 419,780.00 13,390,982
- dia. 9,52 mm & 19,05 mm IU-OU-GD.B.1.10 mtr 16.50 419,780.00 6,926,370
- dia. 9,52 mm & 19,05 mm IU-OU-GD.B.1.11 mtr 16.50 419,780.00 6,926,370
- dia. 6,4 mm & 9,5 mm IU-OU-GD.B.1.12 mtr 11.00 248,800.00 2,736,800
- dia. 6,4 mm & 9,5 mm IU-OU-GD.B.1.12A mtr 11.00 248,800.00 2,736,800
- dia. 6,4 mm & 12,7 mm IU-OU-GD.B.1.13 mtr 15.95 273,470.00 4,361,847
- dia. 6,4 mm & 9,5 mm IU-OU-GD.B.1.14 mtr 14.85 248,800.00 3,694,680
C.2 Lantai 2
1 Pipa AC Split + Isolasi
- dia. 9,52 mm & 15,9 mm IU-OU-GD.B.2.1 mtr 11.55 395,210 4,564,676
- dia. 9,52 mm & 15,9 mm IU-OU-GD.B.2.2 mtr 9.35 395,210 3,695,214
- dia. 6,4 mm & 12,7 mm IU-OU-GD.B.2.3 mtr 6.60 273,470 1,804,902
- dia. 6,4 mm & 9,5 mm IU-OU-GD.B.2.4 mtr 12.10 248,800 3,010,480
- dia. 9,52 mm & 19 mm IU-OU-GD.B.2.5 mtr 19.25 419,780 8,080,765
- dia. 9,52 mm & 15,9 mm IU-OU-GD.B.2.6 mtr 17.05 395,210 6,738,331
- dia. 9,52 mm & 15,9 mm IU-OU-GD.B.2.7 mtr 11.00 395,210 4,347,310
- dia. 9,52 mm & 15,9 mm IU-OU-GD.B.2.8 mtr 16.50 395,210 6,520,965
- dia. 9,52 mm & 15,9 mm IU-OU-GD.B.2.9 mtr 17.05 395,210 6,738,331
- dia. 9,52 mm & 15,9 mm IU-OU-GD.B.2.10 mtr 18.15 395,210 7,173,062
- dia. 6,4 mm & 12,7 mm IU-OU-GD.B.2.11 mtr 12.10 273,470 3,308,987
- dia. 6,4 mm & 12,7 mm IU-OU-GD.B.2.12 mtr 11.00 273,470 3,008,170
- dia. 6,4 mm & 12,7 mm IU-OU-GD.B.2.13 mtr 14.30 273,470 3,910,621
- dia. 6,4 mm & 12,7 mm IU-OU-GD.B.2.14 mtr 16.50 273,470 4,512,255
- dia. 6,4 mm & 12,7 mm IU-OU-GD.B.2.15 mtr 14.30 273,470 3,910,621
- dia. 6,4 mm & 9,5 mm IU-OU-GD.B.2.16 mtr 7.70 248,800 1,915,760
- dia. 6,4 mm & 9,5 mm IU-OU-GD.B.2.17 mtr 11.00 248,800 2,736,800
- dia. 6,4 mm & 9,5 mm IU-OU-GD.B.2.18 mtr 8.80 248,800 2,189,440
- dia. 6,4 mm & 9,5 mm IU-OU-GD.B.2.19 mtr 13.75 248,800 3,421,000
- dia. 6,4 mm & 9,5 mm IU-OU-GD.B.2.20 mtr 12.65 248,800 3,147,320
- dia. 6,4 mm & 15,9 mm IU-OU-GD.B.2.21 mtr 11.00 339,210 3,731,310
C.3 Lantai 3
1 Pipa AC Split + Isolasi
- dia. 6,4 mm & 9,5 mm IU-OU-GD.B.3.1 mtr 7.70 248,800 1,915,760
- dia. 6,4 mm & 15,9 mm IU-OU-GD.B.3.2 mtr 14.30 339,210 4,850,703
- dia. 9,52 mm & 15,9 mm IU-OU-GD.B.3.3 mtr 12.65 395,210 4,999,407
- dia. 9,52 mm & 15,9 mm IU-OU-GD.B.3.4 mtr 14.30 395,210 5,651,503
- dia. 9,52 mm & 15,9 mm IU-OU-GD.B.3.5 mtr 11.55 395,210 4,564,676
- dia. 9,52 mm & 15,9 mm IU-OU-GD.B.3.6 mtr 19.25 395,210 7,607,793
- dia. 9,52 mm & 15,9 mm IU-OU-GD.B.3.7 mtr 18.70 395,210 7,390,427
- dia. 9,52 mm & 15,9 mm IU-OU-GD.B.3.8 mtr 21.45 395,210 8,477,255
- dia. 9,52 mm & 15,9 mm IU-OU-GD.B.3.9 mtr 15.40 395,210 6,086,234
- dia. 6,4 mm & 9,5 mm IU-OU-GD.B.3.10 mtr 10.45 248,800 2,599,960
- dia. 6,4 mm & 9,5 mm IU-OU-GD.B.3.11 mtr 7.15 248,800 1,778,920
- dia. 6,4 mm & 12,7 mm IU-OU-GD.B.3.12 mtr 8.25 273,470 2,256,128
- dia. 9,52 mm & 15,9 mm IU-OU-GD.B.3.13 mtr 15.95 395,210 6,303,600
- dia. 9,52 mm & 15,9 mm IU-OU-GD.B.3.14 mtr 11.55 395,210 4,564,676
- dia. 9,52 mm & 15,9 mm IU-OU-GD.B.3.15 mtr 9.90 395,210 3,912,579
- dia. 9,52 mm & 15,9 mm IU-OU-GD.B.3.16 mtr 11.55 395,210 4,564,676
- dia. 6,4 mm & 15,9 mm IU-OU-GD.B.3.17 mtr 10.45 339,210 3,544,745
D.1 Lantai 1
1 Unit Fan
a Ducting tanpa isolasi finish cat zinkromat lengkap dgn
Page 49 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
gantungan/hanger/support dan aksesories lainnya :
- BjLS 80 m2 96.00 267,020 25,633,920
- BjLS 60 m2 71.00 204,930 14,550,030
- BjLS 50 m2 105.00 184,580 19,380,900
2 Unit AC
a Ducting Bahan BJLS + isolasi elestomeric nitrille rubber class 0 lengkap dengan
gantungan/hanger/support dan aksesories lainya
- BjLS 80 m2 - 476,100 -
- BjLS 60 m2 84.00 400,880 33,673,920
- BjLS 50 m2 60.00 372,650 22,359,000
D.2 Lantai 2
1 Unit Fan
a Ducting tanpa isolasi finish cat zinkromat lengkap dgn
gantungan/hanger/support dan aksesories lainnya :
- BjLS 50 m2 152.00 184,580 28,056,160
2 Unit AC
a Ducting Bahan BJLS + isolasi elestomeric nitrille rubber class 0 lengkap dengan
gantungan/hanger/support dan aksesories lainya
- BjLS 60 m2 8.00 400,880 3,207,040
- BjLS 50 m2 66.00 372,650 24,594,900
D.3 Lantai 3
1 Unit Fan
a Ducting tanpa isolasi finish cat zinkromat lengkap dgn
Page 50 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
gantungan/hanger/support dan aksesories lainnya :
- BjLS 50 m2 23.00 184,580 4,245,340
2 Pengkabelan unit Fan dari P.AC masing-masing unit titik 5.00 600,000 3,000,000
3 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 243.10 15,698 3,816,184
E.2 Lantai 2
1 Pengkabelan unit AC dari P.AC ke masing-masing unit titik 21.00 850,000 17,850,000
2 Pengkabelan unit Fan dari P.AC- ke masing-masing unit titik 8.00 600,000 4,800,000
3 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 271.70 15,698 4,265,147
E.3 Lantai 3
1 Pengkabelan unit AC dari P.AC ke masing-masing unit titik 17.00 850,000 14,450,000
2 Pengkabelan unit Fan dari P.AC ke masing-masing unit titik 3.00 600,000 1,800,000
3 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 220.55 15,698 3,462,194
A Lantai 1
A. STATIONS & DIVERTERS AND ACCESSORIES
1 MultiLab Station with 2 fully automatic sending dispatchs Unit 2.00 82,882,800 165,765,600
All Stations incl.: Basket, Cushion and Carrier Rack
B Lantai 2
Page 51 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
A. STATIONS & DIVERTERS AND ACCESSORIES
1 Bottom Loading Station Unit 2.00 39,637,440 79,274,880
All Stations incl.: Basket, Cushion and Carrier Rack
Page 52 of 285
ENGINEERING ESTIMATE (EE)
PEKERJAAN MEKANIKAL & ELEKTRIKAL
PROYEK : PAKET PEKERJAAN JASA KONSULTANSI KONSTRUKSI PENGADAAN JASA KONSULTAN LANJUTAN RUMAH SAKIT KUPANG NTT
BANGUNAN : GEDUNG C (IRNA)
LOKASI : NUSA TENGGARA TIMUR
TOTAL 15,941,862,745
Page 53 of 285
ENGINEERING ESTIMATE (EE)
PEKERJAAN MEKANIKAL & ELEKTRIKAL
PROYEK : PAKET PEKERJAAN JASA KONSULTANSI KONSTRUKSI PENGADAAN JASA KONSULTAN LANJUTAN RUMAH SAKIT KUPANG NTT
BANGUNAN : GEDUNG C (IRNA)
LOKASI : NUSA TENGGARA TIMUR
A.2 Lantai 2
1 PP.2C unit 1.00 22,231,000 22,231,000
2 P.AC-2C unit 1.00 17,535,000 17,535,000
3 MB. BOX unit 12.00 1,828,000 21,936,000
A.3 Lantai 3
1 PP.3C unit 1.00 22,965,000 22,965,000
2 P.AC-3C unit 1.00 17,725,000 17,725,000
3 MB. BOX unit 15.00 1,828,000 27,420,000
A.4 Lantai 4
1 PP.4C unit 1.00 23,899,000 23,899,000
2 P.AC-4C unit 1.00 13,820,000 13,820,000
3 MB. BOX unit 17.00 1,828,000 31,076,000
2 Dari SDP.C
NYY 4 x 70 mm2 ke PP.1C mtr 10.00 536,130 5,361,300
NYY 4 x 70 mm2 ke PP.2C mtr 17.00 536,130 9,114,210
NYY 4 x 70 mm2 ke PP.3C mtr 22.00 536,130 11,794,860
NYY 4 x 35 mm2 ke PP.4C mtr 27.00 278,933 7,531,191
NYY 4 x 25 mm2 ke P. LIFT.C mtr 36.00 205,275 7,389,900
NYY 4 x 10 mm2 ke P. SUMPIT C mtr 12.00 80,903 970,836
3 Dari SDP.AC-C
NYY 4 x 70 mm2 ke P.AC-1C mtr 10.00 536,130 5,361,300
NYY 4 x 70 mm2 ke P.AC-2C mtr 17.00 536,130 9,114,210
NYY 4 x 70 mm2 ke P.AC-3C mtr 22.00 536,130 11,794,860
NYY 4 x 50 mm2 ke P.AC-4C mtr 27.00 379,155 10,237,185
4 Dari PP.1C
NYY 3 x 4 mm2 MB. BOX.1.1 mtr 31.00 27,773 860,963
NYY 3 x 4 mm2 MB. BOX.1.2 mtr 39.00 27,773 1,083,147
NYY 3 x 4 mm2 MB. BOX.1.3 mtr 44.00 27,773 1,222,012
NYY 3 x 4 mm2 MB. BOX.1.4 mtr 54.00 27,773 1,499,742
NYY 3 x 4 mm2 MB. BOX.1.5 mtr 59.00 27,773 1,638,607
NYY 3 x 4 mm2 MB. BOX.1.6 mtr 69.00 27,773 1,916,337
NYY 3 x 4 mm2 MB. BOX.1.7 mtr 33.00 27,773 916,509
NYY 3 x 4 mm2 MB. BOX.1.8 mtr 33.00 27,773 916,509
NYY 3 x 4 mm2 MB. BOX.1.9 mtr 41.00 27,773 1,138,693
NYY 3 x 4 mm2 MB. BOX.1.10 mtr 47.00 27,773 1,305,331
NYY 3 x 4 mm2 MB. BOX.1.11 mtr 52.00 27,773 1,444,196
NYY 3 x 4 mm2 MB. BOX.1.12 mtr 62.00 27,773 1,721,926
5 Dari PP.2C
NYY 3 x 4 mm2 MB. BOX.2.1 mtr 31.00 27,773 860,963
Page 54 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
NYY 3 x 4 mm2 MB. BOX.2.2 mtr 39.00 27,773 1,083,147
NYY 3 x 4 mm2 MB. BOX.2.3 mtr 44.00 27,773 1,222,012
NYY 3 x 4 mm2 MB. BOX.2.4 mtr 54.00 27,773 1,499,742
NYY 3 x 4 mm2 MB. BOX.2.5 mtr 59.00 27,773 1,638,607
NYY 3 x 4 mm2 MB. BOX.2.6 mtr 69.00 27,773 1,916,337
NYY 3 x 4 mm2 MB. BOX.2.7 mtr 33.00 27,773 916,509
NYY 3 x 4 mm2 MB. BOX.2.8 mtr 33.00 27,773 916,509
NYY 3 x 4 mm2 MB. BOX.2.9 mtr 41.00 27,773 1,138,693
NYY 3 x 4 mm2 MB. BOX.2.10 mtr 47.00 27,773 1,305,331
NYY 3 x 4 mm2 MB. BOX.2.11 mtr 52.00 27,773 1,444,196
NYY 3 x 4 mm2 MB. BOX.2.12 mtr 62.00 27,773 1,721,926
6 Dari PP.3C
NYY 3 x 4 mm2 MB. BOX.3.1 mtr 31.00 27,773 860,963
NYY 3 x 4 mm2 MB. BOX.3.2 mtr 40.00 27,773 1,110,920
NYY 3 x 4 mm2 MB. BOX.3.3 mtr 40.00 27,773 1,110,920
NYY 3 x 4 mm2 MB. BOX.3.4 mtr 44.00 27,773 1,222,012
NYY 3 x 4 mm2 MB. BOX.3.5 mtr 54.00 27,773 1,499,742
NYY 3 x 4 mm2 MB. BOX.3.6 mtr 59.00 27,773 1,638,607
NYY 3 x 4 mm2 MB. BOX.3.7 mtr 70.00 27,773 1,944,110
NYY 3 x 4 mm2 MB. BOX.3.8 mtr 33.00 27,773 916,509
NYY 3 x 4 mm2 MB. BOX.3.9 mtr 33.00 27,773 916,509
NYY 3 x 4 mm2 MB. BOX.3.10 mtr 41.00 27,773 1,138,693
NYY 3 x 4 mm2 MB. BOX.3.11 mtr 41.00 27,773 1,138,693
NYY 3 x 4 mm2 MB. BOX.3.12 mtr 48.00 27,773 1,333,104
NYY 3 x 4 mm2 MB. BOX.3.13 mtr 48.00 27,773 1,333,104
NYY 3 x 4 mm2 MB. BOX.3.14 mtr 56.00 27,773 1,555,288
NYY 3 x 4 mm2 MB. BOX.3.15 mtr 62.00 27,773 1,721,926
7 Dari PP.4C
NYY 3 x 4 mm2 MB. BOX.4.1 mtr 31.00 27,773 860,963
NYY 3 x 4 mm2 MB. BOX.4.2 mtr 40.00 27,773 1,110,920
NYY 3 x 4 mm2 MB. BOX.4.3 mtr 40.00 27,773 1,110,920
NYY 3 x 4 mm2 MB. BOX.4.4 mtr 48.00 27,773 1,333,104
NYY 3 x 4 mm2 MB. BOX.4.5 mtr 48.00 27,773 1,333,104
NYY 3 x 4 mm2 MB. BOX.4.6 mtr 55.00 27,773 1,527,515
NYY 3 x 4 mm2 MB. BOX.4.7 mtr 55.00 27,773 1,527,515
NYY 3 x 4 mm2 MB. BOX.4.8 mtr 63.00 27,773 1,749,699
NYY 3 x 4 mm2 MB. BOX.4.9 mtr 63.00 27,773 1,749,699
NYY 3 x 4 mm2 MB. BOX.4.10 mtr 71.00 27,773 1,971,883
NYY 3 x 4 mm2 MB. BOX.4.11 mtr 71.00 27,773 1,971,883
NYY 3 x 4 mm2 MB. BOX.4.12 mtr 33.00 27,773 916,509
NYY 3 x 4 mm2 MB. BOX.4.13 mtr 40.00 27,773 1,110,920
NYY 3 x 4 mm2 MB. BOX.4.14 mtr 49.00 27,773 1,360,877
NYY 3 x 4 mm2 MB. BOX.4.15 mtr 55.00 27,773 1,527,515
NYY 3 x 4 mm2 MB. BOX.4.16 mtr 63.00 27,773 1,749,699
NYY 3 x 4 mm2 MB. BOX.4.17 mtr 63.00 27,773 1,749,699
8 Dari P.LIFT-C
NYY 4 x 10 mm2 PC. LIFT 1 mtr 31.00 80,903 2,507,993
NYY 4 x 10 mm2 PC. LIFT 2 mtr 39.00 80,903 3,155,217
NYY 4 x 4 mm2 ke PC. BOOSTER mtr 29.00 36,225 1,050,525
9 Dari P. SUMPIT C
NYY 4 x 4 mm2 PC. SUMPIT C-01 mtr 38.00 36,225 1,376,550
NYY 4 x 4 mm2 PC. SUMPIT C-02 mtr 66.00 36,225 2,390,850
10 Dari SDP.PF-C
FRC 4 x 1 x 10 mm2 P PF.C mtr 36.00 197,064 7,094,304
11 Dari P.PF-C
FRC 4 x 1 x 4 mm2 PC. PF.1 mtr 15.00 95,440 1,431,600
FRC 4 x 1 x 4 mm2 PC. PF.2 mtr 39.00 95,440 3,722,160
2 Lantai 2
Kabel Tray Listrik
- uk. 600 mm x 50 mm m 40.00 353,000 14,120,000
- uk. 300 mm x 50 mm m 24.00 211,600 5,078,400
3 Lantai 3
Kabel Tray Listrik
Page 55 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- uk. 600 mm x 50 mm m 40.00 353,000 14,120,000
- uk. 300 mm x 50 mm m 24.00 211,600 5,078,400
4 Lantai 4
Kabel Tray Listrik
- uk. 600 mm x 50 mm m 40.00 353,000 14,120,000
- uk. 300 mm x 50 mm m 24.00 211,600 5,078,400
E.2 Lantai 2
1 RM TLED 3 x 8 Watt + Cover bh 3.00 1,360,594 4,081,783
2 RM TLED 3 x 8 Watt + Cover c/w Nicad Battery bh 5.00 2,403,118 12,015,591
3 RM TLED 2 x 14 Watt + Cover bh 12.00 1,205,715 14,468,580
4 RM TLED 2 x 14 Watt + Cover c/w Nicad Battery bh 4.00 2,248,239 8,992,956
5 TLED 2x14 Watt (Balk) bh - 881,139 -
6 TLED 2x14 Watt (Balk) c/w Nicad Battery bh 2.00 1,923,663 3,847,326
7 Lampu Bed / Periksa LED 29 Watt bh 50.00 930,304 46,515,210
8 Down Light LED E27 13 Watt Bulb + Cover bh 20.00 372,527 7,450,548
9 Down Light LED E27 13 Watt Bulb + Cover c/w Nicad Battery bh 18.00 1,481,731 26,671,151
10 Down Light LED E27 6 Watt Bulb + Cover bh 20.00 284,327 5,686,548
11 Spot Light LED 10W bh 3.00 298,704 896,112
12 Lampu Baret LED E27 10,5 Watt Bulb c/w Nicad Battery bh 4.00 1,339,288 5,357,150
13 Lampu Bed Head LED 8 watt bh 50.00 354,799 17,739,960
14 Exit Lamp LED 8 Watt bh 3.00 1,349,254 4,047,763
15 Stop Kontak 1 Ph 200 Watt bh 177.00 52,763 9,338,963
16 Stop Kontak Bed 1 Ph 200 Watt bh 49.00 52,763 2,585,363
17 Stop Kontak Ceiling TV 1Ph 200 Watt bh 14.00 52,763 738,675
18 Saklar Tunggal bh 33.00 44,163 1,457,379
19 Saklar Ganda bh 67.00 48,794 3,269,165
20 Saklar Hotel bh 2.00 46,242 92,484
21 Grid Switch 4 Gang bh 1.00 227,462 227,462
22 Titik nyala lampu dengan kabel NYM 3 x 2,5 mm² di dalam conduit PVC HItitik
20 mm 194.00 321,800 62,429,200
23 Titik nyala Stop kontak NYM 3 x 2,5 mm² didalam conduit PVC HI 20 mm titik 240.00 400,900 96,216,000
E.3 Lantai 3
1 RM TLED 3 x 8 Watt + Cover bh 3.00 1,360,594 4,081,783
2 RM TLED 3 x 8 Watt + Cover c/w Nicad Battery bh 5.00 2,403,118 12,015,591
3 RM TLED 2 x 14 Watt + Cover bh 12.00 1,205,715 14,468,580
4 RM TLED 2 x 14 Watt + Cover c/w Nicad Battery bh 4.00 2,248,239 8,992,956
5 TLED 2x14 Watt (Balk) bh - 881,139 -
6 TLED 2x14 Watt (Balk) c/w Nicad Battery bh 2.00 1,923,663 3,847,326
Page 56 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
7 Lampu Bed / Periksa LED 29 Watt bh 47.00 930,304 43,724,297
8 Down Light LED E27 13 Watt Bulb + Cover bh 24.00 372,527 8,940,658
9 Down Light LED E27 13 Watt Bulb + Cover c/w Nicad Battery bh 21.00 1,481,731 31,116,343
10 Down Light LED E27 6 Watt Bulb + Cover bh 23.00 284,327 6,539,530
11 Spot Light LED 10W bh 3.00 298,704 896,112
12 Lampu Baret LED E27 10,5 Watt Bulb c/w Nicad Battery bh 4.00 1,339,288 5,357,150
13 Lampu Bed Head LED 8 watt bh 47.00 354,799 16,675,562
14 Exit Lamp LED 8 Watt bh 3.00 1,349,254 4,047,763
15 Stop Kontak 1 Ph 200 Watt bh 174.00 52,763 9,180,675
16 Stop Kontak Bed 1 Ph 200 Watt bh 47.00 52,763 2,479,838
17 Stop Kontak Ceiling TV 1Ph 200 Watt bh 17.00 52,763 896,963
18 Saklar Tunggal bh 33.00 44,163 1,457,379
19 Saklar Ganda bh 67.00 48,794 3,269,165
20 Saklar Hotel bh - 46,242 -
21 Grid Switch 4 Gang bh - 227,462 -
22 Titik nyala lampu dengan kabel NYM 3 x 2,5 mm² di dalam conduit PVC HItitik
20 mm 198.00 321,800 63,716,400
23 Titik nyala Stop kontak NYM 3 x 2,5 mm² didalam conduit PVC HI 20 mm titik 238.00 400,900 95,414,200
E.4 Lantai 4
1 RM TLED 3 x 8 Watt + Cover bh 3.00 1,360,594 4,081,783
2 RM TLED 3 x 8 Watt + Cover c/w Nicad Battery bh 5.00 2,403,118 12,015,591
3 RM TLED 2 x 14 Watt + Cover bh 16.00 1,205,715 19,291,440
4 RM TLED 2 x 14 Watt + Cover c/w Nicad Battery bh 4.00 2,248,239 8,992,956
5 TLED 2x14 Watt (Balk) bh - 881,139 -
6 TLED 2x14 Watt (Balk) c/w Nicad Battery bh 2.00 1,923,663 3,847,326
7 Lampu Bed / Periksa LED 29 Watt bh 24.00 930,304 22,327,301
8 Down Light LED E27 13 Watt Bulb + Cover bh 28.00 372,527 10,430,767
9 Down Light LED E27 13 Watt Bulb + Cover c/w Nicad Battery bh 23.00 1,481,731 34,079,804
10 Down Light LED E27 6 Watt Bulb + Cover bh 27.00 284,327 7,676,840
11 Spot Light LED 10W bh 3.00 298,704 896,112
12 Lampu Baret LED E27 10,5 Watt Bulb bh 2.00 229,996 459,992
13 Lampu Baret LED E27 10,5 Watt Bulb c/w Nicad Battery bh 4.00 1,339,288 5,357,150
14 Lampu Bed Head LED 8 watt bh 24.00 354,799 8,515,181
15 Exit Lamp LED 8 Watt bh 3.00 1,349,254 4,047,763
16 Stop Kontak 1 Ph 200 Watt bh 118.00 52,763 6,225,975
17 Stop Kontak Bed 1 Ph 200 Watt bh 24.00 52,763 1,266,300
18 Stop Kontak Ceiling TV 1Ph 200 Watt bh 18.00 52,763 949,725
19 Saklar Tunggal bh 27.00 44,163 1,192,401
20 Saklar Ganda bh 43.00 48,794 2,098,121
21 Saklar Hotel bh - 46,242 -
22 Grid Switch 4 Gang bh - 227,462 -
23 Titik nyala lampu dengan kabel NYM 3 x 2,5 mm² di dalam conduit PVC HItitik
20 mm 168.00 321,800 54,062,400
24 Titik nyala Stop kontak NYM 3 x 2,5 mm² didalam conduit PVC HI 20 mm titik 160.00 400,900 64,144,000
1 Air Terminal jenis Non radioaktif Radius Perlindungan 100 meter unit 1.00 21,600,000 21,600,000
2 FRP Mast set 1.00 4,800,000 4,800,000
3 Termination Kit set 1.00 5,360,000 5,360,000
4 Pengadaan dan pemasangan Lightning Event Strike Counter (penghitung unit 1.00 4,800,000 4,800,000
sambaran petir)
5 Obstruction Light 300 Watt lengkap dengan Photo Electric Switch set 1.00 4,000,000 4,000,000
6 Batang Penyangga tinggi 12 meter, bahan GIP Medium Class unit 1.00 6,800,000 6,800,000
lengkap dengan angur dan tali pengikat
7 Down Conductor Coaxial Cable 50 mm lengkap dengan klem mtr 64.00 708,000 45,312,000
8 Grounding system unit 1.00 14,700,000 14,700,000
9 Testing Commissioning ls 1.00 15,000,000 15,000,000
10 Biaya Perijinan Depnaker ls 1.00 25,000,000 25,000,000
Page 57 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
III PEKERJAAN GENSET
Pengadaan dan pemasangan sistim sesuai dengan
gambar & Spesifikasi Teknis
C.2 Lantai 2
1 Terminal Box (TB. FA - 2C) unit 1.00 630,525 630,525
2 Horn & Strobe bh 2.00 795,769 1,591,538
3 Manual Break Glass bh 2.00 289,013 578,025
4 Addresable Rate of Rise Detector bh 8.00 1,092,315 8,738,520
5 Addresable Fixed Heat Detector bh 2.00 1,092,315 2,184,630
6 Addressable Smoke Detector bh 21.00 1,373,846 28,850,771
7 Smoke Detector Photoelectric bh 5.00 581,805 2,909,025
8 Rate of Rise Detector bh - 491,715 -
9 Fixed Heat Detector bh - 491,715 -
10 Telephone Jack bh 2.00 487,961 975,923
11 End off line bh 7.00 6,379 44,651
12 P.AC.2 bh 1.00 by Others
13 Flow Switch bh 1.00 by Others
C.3 Lantai 3
Page 58 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
1 Terminal Box (TB. FA - 3C) unit 1.00 630,525 630,525
2 Horn & Strobe bh 2.00 795,769 1,591,538
3 Manual Break Glass bh 2.00 289,013 578,025
4 Addresable Rate of Rise Detector bh 9.00 1,092,315 9,830,835
5 Addresable Fixed Heat Detector bh 1.00 1,092,315 1,092,315
6 Addressable Smoke Detector bh 24.00 1,373,846 32,972,310
7 Smoke Detector Photoelectric bh 5.00 581,805 2,909,025
8 Rate of Rise Detector bh - 491,715 -
9 Fixed Heat Detector bh - 491,715 -
10 Telephone Jack bh 2.00 487,961 975,923
11 End off line bh 7.00 6,379 44,651
12 P.AC.3 bh 1.00 by Others
13 Flow Switch bh 1.00 by Others
Page 59 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
dalam conduit PVC HI dia. 20 mm
6 Instalasi untuk Volume Control dengan kabel NYMHY 3 x 1.5 mm2 ttk 17.00 492,500 8,372,500
dalam conduit PVC HI dia. 20 mm
7 Instalasi untuk Speaker dengan kabel FRC 2 x 1,5 mm2 ttk 2.00 597,400 1,194,800
dalam conduit PVC HI dia. 20 mm
C.2 Lantai 2
1 Terminal Box Sound System Lt. 2 (TB. TS. 2C) bh 1.00 800,100 800,100
2 Ceiling Speaker 3 Watt + Matching Transformer bh 40.00 196,035 7,841,400
3 Volume Control bh 20.00 451,920 9,038,400
4 Emergency Speaker 6 Watt bh - 322,382 -
5 Instalasi untuk Speaker dengan kabel NYMHY 2 x 1.5 mm2 ttk 40.00 297,900 11,916,000
dalam conduit PVC HI dia. 20 mm
6 Instalasi untuk Volume Control dengan kabel NYMHY 3 x 1.5 mm2 ttk 20.00 492,500 9,850,000
dalam conduit PVC HI dia. 20 mm
7 Instalasi untuk Speaker dengan kabel FRC 2 x 1,5 mm2 ttk - 597,400 -
dalam conduit PVC HI dia. 20 mm
C.3 Lantai 3
1 Terminal Box Sound System Lt. 3 (TB. TS. 3C) bh 1.00 800,100 800,100
2 Ceiling Speaker 3 Watt + Matching Transformer bh 42.00 196,035 8,233,470
3 Volume Control bh 20.00 451,920 9,038,400
4 Emergency Speaker 6 Watt bh 2.00 322,382 644,763
5 Instalasi untuk Speaker dengan kabel NYMHY 2 x 1.5 mm2 ttk 42.00 297,900 12,511,800
dalam conduit PVC HI dia. 20 mm
6 Instalasi untuk Volume Control dengan kabel NYMHY 3 x 1.5 mm2 ttk 20.00 492,500 9,850,000
dalam conduit PVC HI dia. 20 mm
7 Instalasi untuk Speaker dengan kabel FRC 2 x 1,5 mm2 ttk 2.00 597,400 1,194,800
dalam conduit PVC HI dia. 20 mm
C.4 Lantai 4
1 Terminal Box Sound System Lt. 3 (TB. TS. 3C) bh 1.00 800,100 800,100
2 Ceiling Speaker 3 Watt + Matching Transformer bh 46.00 196,035 9,017,610
3 Volume Control bh 22.00 451,920 9,942,240
4 Emergency Speaker 6 Watt bh - 322,382 -
5 Instalasi untuk Speaker dengan kabel NYMHY 2 x 1.5 mm2 ttk 46.00 297,900 13,703,400
dalam conduit PVC HI dia. 20 mm
6 Instalasi untuk Volume Control dengan kabel NYMHY 3 x 1.5 mm2 ttk 22.00 492,500 10,835,000
dalam conduit PVC HI dia. 20 mm
7 Instalasi untuk Speaker dengan kabel FRC 2 x 1,5 mm2 ttk - 597,400 -
dalam conduit PVC HI dia. 20 mm
2 Outlet :
- Outlet Access Point RJ 45 bh 2.00 135,000 270,000
- Outlet Data RJ 45 bh 3.00 135,000 405,000
- Outlet Telepon RJ 45 bh 4.00 135,000 540,000
3 Fixture Unit
- Access Point bh 2.00 1,390,000 2,780,000
- Pesawat Telepon IP Extention bh 4.00 1,135,000 4,540,000
Page 60 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point
titik 2.00 936,100 1,872,200
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 3.00 936,100 2,808,300
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 4.00 936,100 3,744,400
B.2 Lantai 2
1 Peralatan Distribusi
- Wall Mounted Rack 19", 15U c/w Accessories unit 1.00 2,200,000 2,200,000
- Wiring Management 1U bh 2.00 148,000 296,000
- Patch Panel FO 12 port bh 1.00 1,634,400 1,634,400
- FO Connector bh 1.00 160,800 160,800
- UTP Cat 6 Patch Panel 24 Port Loaded bh 1.00 1,380,000 1,380,000
- UTP Cat 6 Patch Cord, 1m bh 24.00 45,000 1,080,000
- Switch Hub 24 port bh 1.00 4,508,000 4,508,000
2 Outlet :
- Outlet Access Point RJ 45 bh 2.00 135,000 270,000
- Outlet Data RJ 45 bh 3.00 135,000 405,000
- Outlet Telepon RJ 45 bh 4.00 135,000 540,000
3 Fixture Unit
- Access Point bh 2.00 1,390,000 2,780,000
- Pesawat Telepon IP Extention bh 4.00 1,135,000 4,540,000
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point
titik 2.00 936,100 1,872,200
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 3.00 936,100 2,808,300
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 4.00 936,100 3,744,400
B.3 Lantai 3
1 Peralatan Distribusi
- Wall Mounted Rack 19", 15U c/w Accessories unit 1.00 2,200,000 2,200,000
- Wiring Management 1U bh 1.00 148,000 148,000
- Patch Panel FO 12 port bh 1.00 1,634,400 1,634,400
- FO Connector bh 1.00 160,800 160,800
- UTP Cat 6 Patch Panel 24 Port Loaded bh 1.00 1,380,000 1,380,000
- UTP Cat 6 Patch Cord, 1m bh 24.00 45,000 1,080,000
- Switch Hub 24 port bh 1.00 4,508,000 4,508,000
2 Outlet :
- Outlet Access Point RJ 45 bh 2.00 135,000 270,000
- Outlet Data RJ 45 bh 3.00 135,000 405,000
- Outlet Telepon RJ 45 bh 4.00 135,000 540,000
3 Fixture Unit
- Access Point bh 2.00 1,390,000 2,780,000
- Pesawat Telepon IP Extention bh 4.00 1,135,000 4,540,000
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point
titik 2.00 936,100 1,872,200
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 3.00 936,100 2,808,300
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 4.00 936,100 3,744,400
B.4 Lantai 4
1 Peralatan Distribusi
- Wall Mounted Rack 19", 15U c/w Accessories unit 1.00 2,200,000 2,200,000
- Wiring Management 1U bh 1.00 148,000 148,000
- Patch Panel FO 12 port bh 1.00 1,634,400 1,634,400
- FO Connector bh 1.00 160,800 160,800
- UTP Cat 6 Patch Panel 24 Port Loaded bh 1.00 1,380,000 1,380,000
- UTP Cat 6 Patch Cord, 1m bh 24.00 45,000 1,080,000
- Switch Hub 24 port bh 1.00 4,508,000 4,508,000
2 Outlet :
- Outlet Access Point RJ 45 bh 2.00 135,000 270,000
- Outlet Data RJ 45 bh 3.00 135,000 405,000
- Outlet Telepon RJ 45 bh 4.00 135,000 540,000
3 Fixture Unit
- Access Point bh 2.00 1,390,000 2,780,000
- Pesawat Telepon IP Extention bh 4.00 1,135,000 4,540,000
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point
titik 2.00 936,100 1,872,200
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 3.00 936,100 2,808,300
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 4.00 936,100 3,744,400
Page 61 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Kabel Tray 200 mm x 100 mm m 76.00 199,900 15,192,400
2 Lantai 2
Kabel Tray 200 mm x 100 mm m 75.00 199,900 14,992,500
3 Lantai 3
Kabel Tray 200 mm x 100 mm m 75.00 199,900 14,992,500
4 Lantai 4
Kabel Tray 200 mm x 100 mm m 75.00 199,900 14,992,500
B.2 Lantai 2
1 Splitter 8 Way Unit 2.00 629,606 1,259,213
2 Splitter 2 Way Unit 1.00 261,548 261,548
3 Outlet TV Unit 14.00 80,325 1,124,550
4 Instalasi kabel Outlet TV, coaxial RG6 (5C/2 volt) dakan konduit PVC HI dia.
titik20 mm 14.00 533,800 7,473,200
5 Instalasi kabel Splitter, Coaxial RG-11 (7C) dalam konduit PVC HI dia. 20 mm
m 178.00 26,775 4,765,950
B.3 Lantai 3
1 Splitter 8 Way Unit 2.00 629,606 1,259,213
2 Splitter 2 Way Unit 1.00 261,548 261,548
3 Splitter 4 Way Unit 1.00 366,892 366,892
4 Booster Unit 1.00 1,658,475 1,658,475
5 Outlet TV Unit 16.00 80,325 1,285,200
6 Instalasi kabel Outlet TV, coaxial RG6 (5C/2 volt) dakan konduit PVC HI dia.
titik20 mm 16.00 533,800 8,540,800
7 Instalasi kabel Splitter, Coaxial RG-11 (7C) dalam konduit PVC HI dia. 20 mm
m 168.00 26,775 4,498,200
B.4 Lantai 4
1 Splitter 6 Way Unit 3.00 533,108 1,599,323
2 Splitter 4 Way Unit 1.00 366,892 366,892
3 Outlet TV Unit 18.00 80,325 1,445,850
4 Instalasi kabel Outlet TV, coaxial RG6 (5C/2 volt) dakan konduit PVC HI dia.
titik20 mm 18.00 533,800 9,608,400
5 Instalasi kabel Splitter, Coaxial RG-11 (7C) dalam konduit PVC HI dia. 20 mm
m 229.00 26,775 6,131,475
Page 62 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Kabel FO Multimode 4 core + konduit, Backbone ke Hub 4C m 119.00 27,276 3,245,844
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 2.00 5,901,300 11,802,600
- Indoor Fixed Dome IP Camera + thermal detector bh 4.00 139,500,000 558,000,000
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 6.00 936,100 5,616,600
C.2 Lantai 2
1 Peralatan Distribusi
- Wall Mounted Rack 19", 8U c/w Accessories bh 1.00 1,940,000 1,940,000
- Wiring Management 1U bh 1.00 148,000 148,000
- Patch Panel FO 12 port bh 1.00 1,634,400 1,634,400
- FO Connector bh 1.00 160,800 160,800
- UTP Cat 6 Patch Panel 24 Port Loaded bh 1.00 1,380,000 1,380,000
- UTP Cat 6 Patch Cord, 1m bh 24.00 45,000 1,080,000
- Switch Hub PoE 24 port bh 1.00 4,508,000 4,508,000
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 3.00 5,901,300 17,703,900
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 3.00 936,100 2,808,300
C.3 Lantai 3
1 Peralatan Distribusi
- Wall Mounted Rack 19", 8U c/w Accessories bh 1.00 1,940,000 1,940,000
- Wiring Management 1U bh 1.00 148,000 148,000
- Patch Panel FO 12 port bh 1.00 1,634,400 1,634,400
- FO Connector bh 1.00 160,800 160,800
- UTP Cat 6 Patch Panel 24 Port Loaded bh 1.00 1,380,000 1,380,000
- UTP Cat 6 Patch Cord, 1m bh 24.00 45,000 1,080,000
- Switch Hub PoE 24 port bh 1.00 4,508,000 4,508,000
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 3.00 5,901,300 17,703,900
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 3.00 936,100 2,808,300
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 6.00 5,901,300 35,407,800
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 6.00 936,100 5,616,600
Page 63 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
X.A Instalasi Dalam Bangunan
A.1 Lantai 1
1 Master Terminal (with call history) Unit 1.00 83,925,680 83,925,680
2 LCD Corridor Display - Double Sided Unit 1.00 37,028,160 37,028,160
3 LED Door Light Buah 14.00 1,166,400 16,329,600
4 Bed Terminal Call Button Buah 48.00 2,721,600 130,636,800
5 Room Terminal Buah 19.00 7,558,720 143,615,680
6 Bathroom Call Button Buah 14.00 1,059,520 14,833,280
7 Instalasi Nurse Call dengan UTP Cat 6 dalam konduit PVC HI 20 mm titik 97.00 480,000 46,560,000
A.2 Lantai 2
1 Master Terminal (with call history) Unit 1.00 83,925,680 83,925,680
2 LCD Corridor Display - Double Sided Unit 1.00 37,028,160 37,028,160
3 LED Door Light Buah 14.00 1,166,400 16,329,600
4 Bed Terminal Call Button Buah 48.00 2,721,600 130,636,800
5 Room Terminal Buah 19.00 7,558,720 143,615,680
6 Bathroom Call Button Buah 14.00 1,059,520 14,833,280
7 Instalasi Nurse Call dengan UTP Cat 6 dalam konduit PVC HI 20 mm titik 97.00 480,000 46,560,000
A.3 Lantai 3
1 Master Terminal (with call history) Unit 1.00 83,925,680 83,925,680
2 LCD Corridor Display - Double Sided Unit 1.00 37,028,160 37,028,160
3 LED Door Light Buah 16.00 1,166,400 18,662,400
4 Bed Terminal Call Button Buah 46.00 2,721,600 125,193,600
5 Room Terminal Buah 20.00 7,558,720 151,174,400
6 Bathroom Call Button Buah 16.00 1,059,520 16,952,320
7 Instalasi Nurse Call dengan UTP Cat 6 dalam konduit PVC HI 20 mm titik 100.00 480,000 48,000,000
A.4 Lantai 4
1 Master Terminal (with call history) Unit 1.00 83,925,680 83,925,680
2 LCD Corridor Display - Double Sided Unit 1.00 37,028,160 37,028,160
3 LED Door Light Buah 18.00 1,166,400 20,995,200
4 Bed Terminal Call Button Buah 22.00 2,721,600 59,875,200
5 Room Terminal Buah 18.00 7,558,720 136,056,960
6 Bathroom Call Button Buah 16.00 1,059,520 16,952,320
7 Instalasi Nurse Call dengan UTP Cat 6 dalam konduit PVC HI 20 mm titik 76.00 480,000 36,480,000
2 Kabel Data dari MCU di Ruang BAS ke: mtr 290.00 51,424 14,913,012
DDC Lt. D ~ 3 STP AWG #18 dalam Conduit PVC 20 mm
Page 64 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
1 LANTAI 1
PANEL SDP.C
PANEL SDP.AC.C
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
Power Monitoring HLI Titik 2.00 1,677,000 3,354,000
PANEL PP.1C
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
On - Off Digital Output Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
PANEL PP.AC.1C
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
2 LANTAI 2
PANEL PP, PAC
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
On - Off Digital Output Titik 2.00 928,000 1,856,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
3 LANTAI 3
PANEL PP, PAC
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
On - Off Digital Output Titik 2.00 928,000 1,856,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
4 LANTAI 4
PANEL PP, PAC
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
On - Off Digital Output Titik 2.00 928,000 1,856,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
5 LANTAI ATAP
PANEL LIFT-C
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
PANEL BOOSTER
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
XI PEKERJAAN ANTRIAN
Pengadaan dan pemasangan sistem lengkap sesuai
gambar & spesifikasi teknis
Page 65 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
6 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
A.2.2 Lantai 2
1 Instalasi pipa air bersih dengan PPR80 - PN10
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 40 mm m' 26.00 89,540 2,328,040
- dia. 32 mm m' 85.00 64,860 5,513,100
- dia. 25 mm m' 24.00 46,250 1,110,000
- dia. 20 mm m' 196.00 28,830 5,650,680
- dia. 15 mm m' 119.00 22,590 2,688,210
5 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
A.2.3 Lantai 3
1 Instalasi pipa air bersih dengan PPR80 - PN10
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 40 mm m' 26.00 89,540 2,328,040
- dia. 32 mm m' 96.00 64,860 6,226,560
- dia. 25 mm m' 28.00 46,250 1,295,000
- dia. 20 mm m' 234.00 28,830 6,746,220
Page 66 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- dia. 15 mm m' 234.00 22,590 5,286,060
5 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
A.2.4 Lantai 4
1 Instalasi pipa air bersih pipa dari booster ke lantai 4 dengan PPR80 - PN10
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 80 mm m' 62.00 241,040 14,944,480
- dia. 65 mm m' 8.00 177,620 1,420,960
- dia. 32 mm m' 13.00 64,860 843,180
2 Instalasi pipa air bersih riser dari lantai 4 ke lantai 2 dengan PPR80 - PN10
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 50 mm m' 85.00 132,320 11,247,200
- dia. 40 mm m' 33.00 89,540 2,954,820
- dia. 32 mm m' 2.00 64,860 129,720
8 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
5 Kran Botol
- dia. 15 mm bh 2.00 skope arsitek
Page 67 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Bak Submersible Cutter Pump + QDC (Sewage.C-01) unit 1.00 skope sipil
Kapasitas : 5 m³
Ukuran : 2500 x 2000 x (1000+500)mm
Bak Submersible Cutter Pump + QDC (Sewage.C-02) unit 1.00 skope sipil
Kapasitas : 5 m³
Ukuran : 2500 x 2000 x (1000+500)mm
3 Bak Submersible Cutter Pump + QDC (Sewage.C-01) unit 1.00 skope sipil
Kapasitas : 5 m³
Ukuran : 2500 x 2000 x (1000+500)mm
4 Bak Submersible Cutter Pump + QDC (Sewage.C-02) unit 1.00 skope sipil
Kapasitas : 5 m³
Ukuran : 2500 x 2000 x (1000+500)mm
5 Bak Submersible Cutter Pump + QDC (Chemical.C-01) unit 1.00 skope sipil
Kapasitas : 3 m³
Ukuran : 3000 x 1000 x (1000+500)mm
Shaft
- dia. 100 mm m' 27.00 153,900 4,155,300
2 Instalasi Pipa Utama Air Kotor dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
Dari Shaft ke Bak Sumpit
- dia. 150 mm m' 16.00 288,460 4,615,360
Shaft
- dia. 100 mm m' 27.00 153,900 4,155,300
3 Instalasi Pipa Utama Air Kotor Kimia dengan Pipa Cast Iron
termasuk gantungan/hanger, support, fitting dan aksesories :
Dari Shaft ke Bak Sumpit
- dia. 150 mm m' 10.00 692,030 6,920,300
Shaft
- dia. 100 mm m' 14.00 425,060 5,950,840
6 Vent Cup
- dia. 80 mm bh 2.00 341,250 682,500
B.3 Pekerjaan Instalasi Pipa Air Kotor, Kotor & Vent dalam bangunan
B.3.1 Lantai 1
1 Instalasi Air Kotoran Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 23.00 153,900 3,539,700
2 Instalasi Air Kotor Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
Page 68 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- dia. 100 mm m 11.00 153,900 1,692,900
- dia. 80 mm m 16.00 105,190 1,683,040
- dia. 50 mm m 16.00 63,440 1,015,040
- dia. 40 mm m 2.00 48,250 96,500
- Gater 200x100mm m 4.00 skope sipil
B.3.2 Lantai 2
1 Instalasi Air Kotoran Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 57.00 153,900 8,772,300
2 Instalasi Air Kotor Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 19.00 153,900 2,924,100
- dia. 80 mm m 44.00 105,190 4,628,360
- dia. 50 mm m 17.00 63,440 1,078,480
- dia. 40 mm m 18.00 48,250 868,500
2 Instalasi Air Kotor Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 3.00 153,900 461,700
- dia. 80 mm m 27.00 105,190 2,840,130
- dia. 50 mm m 9.00 63,440 570,960
- dia. 40 mm m 12.00 48,250 579,000
SUB TOTAL AIR KOTORAN, KOTOR DAN VENT DALAM BANGUNAN 117,567,980
2 Floor Drain 50 mm :
- Lantai 1 bh - 306,075 -
- Lantai 2 bh 14.00 306,075 4,285,050
- Lantai 3 bh 14.00 306,075 4,285,050
Page 69 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- Lantai 4 bh 14.00 306,075 4,285,050
3 Instalasi Pipa Tegak Air Hujan dengan Pipa PVC kelas AW 10 kg/cm2 termasuk
gantungan/hanger, support, fitting dan aksesories :
- dia .100 mm m' 364.00 153,900 56,019,600
- dia . 80 mm m' 42.00 105,190 4,417,980
3 Zona Valve 3 Gas (O, A,V) + Alarm Set 1.00 37,298,640 37,298,640
A.2 Lantai 2
1 Instalasi pipa cooper ASTM B819 termasuk gantungan/hanger/support,
fitting dan aksesories :
Page 70 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- Diameter 15,88 mm Drooper M 147.00 194,080 28,529,760
3 Zona Valve 3 Gas (O, A,V) + Alarm Set 1.00 37,298,640 37,298,640
A.3 Lantai 3
1 Instalasi pipa cooper ASTM B819 termasuk gantungan/hanger/support,
fitting dan aksesories :
3 Zona Valve 3 Gas (O, A,V) + Alarm Set 1.00 37,298,640 37,298,640
A.4 Lantai 4
1 Instalasi pipa cooper ASTM B819 termasuk gantungan/hanger/support,
fitting dan aksesories :
Page 71 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
A.2 Sprinkler
1 Instalasi pipa utama dengan pipa Black steel Sch. 40
termasuk fitting dan aksesoriesnya :
- dia. 150 mm Tegak (Shaft) m' 37.00 800,660 29,624,420
- dia. 80 mm Pipa tegak Shaft test drain m' 51.00 328,950 16,776,450
- dia. 25 mm m' 2.00 85,310 170,620
4 Gate Valve :
- dia. 65 mm bh 2.00 4,884,868 9,769,736
B.2 Lantai 2
1 Hydrant Box Type Indoor lengkap terpasang unit 2.00 4,773,510 9,547,020
ukuran : 125 x 75 x 18 cm, Cat Bakar
- 1 pc Hose Nozzle dia. 40 mm
- 1 pc Hydrant valve dia. 40 mm
- 1 pc Hose rack 600 mm COMB
- 1 roll fire hose with Machino Coupling dia. 40 mm x 30 m
Page 72 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
termasuk fitting, gantungan/hanger/support dan aksesories :
- dia. 65 mm m' 12.00 259,530 3,114,360
- dia. 40 mm m' 9.00 133,880 1,204,920
4 Gate Valve :
- dia. 65 mm bh 2.00 4,884,868 9,769,736
B.3 Lantai 3
1 Hydrant Box Type Indoor lengkap terpasang unit 2.00 4,773,510 9,547,020
ukuran : 125 x 75 x 18 cm, Cat Bakar
- 1 pc Hose Nozzle dia. 40 mm
- 1 pc Hydrant valve dia. 40 mm
- 1 pc Hose rack 600 mm COMB
- 1 roll fire hose with Machino Coupling dia. 40 mm x 30 m
4 Gate Valve :
- dia. 65 mm bh 2.00 4,884,868 9,769,736
B.4 Lantai 4
1 Hydrant Box Type Indoor lengkap terpasang unit 2.00 4,773,510 9,547,020
ukuran : 125 x 75 x 18 cm, Cat Bakar
- 1 pc Hose Nozzle dia. 40 mm
- 1 pc Hydrant valve dia. 40 mm
- 1 pc Hose rack 600 mm COMB
- 1 roll fire hose with Machino Coupling dia. 40 mm x 30 m
4 Gate Valve :
- dia. 65 mm bh 2.00 4,884,868 9,769,736
3 Branch Control Valve dia. 80 mm terdiri dari : set 1.00 10,168,200 10,168,200
- Butterfly Valve with Tamper Switch dia. 80 bh = 1 bh
- Flow Switch dia. 80 mm = 1 bh
- Sight Glass = 1 bh
- Test Drain Valve = 2 bh
C.2 Lantai 2
1 Instalasi sprinkler dengan Pipa Black Steel Sch. 40 termasuk
fitting, gantungan/hanger/support dan aksesories :
- dia. 80 mm m' 26.00 328,950 8,552,700
- dia. 65 mm m' 23.00 259,530 5,969,190
- dia. 50 mm m' 10.00 178,730 1,787,300
- dia. 40 mm m' 12.00 133,880 1,606,560
- dia. 32 mm m' 37.00 112,210 4,151,770
- dia. 25 mm m' 135.00 85,310 11,516,850
Page 73 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- dia. 25 mm Drooper m' 34.00 85,310 2,900,540
3 Branch Control Valve dia. 80 mm terdiri dari : set 1.00 10,168,200 10,168,200
- Butterfly Valve with Tamper Switch dia. 100 bh = 1 bh
- Flow Switch dia. 100 mm = 1 bh
- Sight Glass = 1 bh
- Test Drain Valve = 2 bh
C.3 Lantai 3
1 Instalasi sprinkler dengan Pipa Black Steel Sch. 40 termasuk
fitting, gantungan/hanger/support dan aksesories :
- dia. 80 mm m' 29.00 328,950 9,539,550
- dia. 65 mm m' 23.00 259,530 5,969,190
- dia. 50 mm m' 12.00 178,730 2,144,760
- dia. 40 mm m' 9.00 133,880 1,204,920
- dia. 32 mm m' 28.00 112,210 3,141,880
- dia. 25 mm m' 160.00 85,310 13,649,600
- dia. 25 mm Drooper m' 28.00 85,310 2,388,680
3 Branch Control Valve dia. 80 mm terdiri dari : set 1.00 10,168,200 10,168,200
- Butterfly Valve with Tamper Switch dia. 80 bh = 1 bh
- Flow Switch dia. 80 mm = 1 bh
- Sight Glass = 1 bh
- Test Drain Valve = 2 bh
C.4 Lantai 4
1 Instalasi sprinkler dengan Pipa Black Steel Sch. 40 termasuk
fitting, gantungan/hanger/support dan aksesories :
- dia. 80 mm m' 55.00 328,950 18,092,250
- dia. 65 mm m' 9.00 259,530 2,335,770
- dia. 50 mm m' 7.00 178,730 1,251,110
- dia. 40 mm m' 8.00 133,880 1,071,040
- dia. 32 mm m' 18.00 112,210 2,019,780
- dia. 25 mm m' 182.00 85,310 15,526,420
- dia. 25 mm Drooper m' 30.00 85,310 2,559,300
3 Branch Control Valve dia. 80 mm terdiri dari : set 1.00 10,168,200 10,168,200
- Butterfly Valve with Tamper Switch dia. 80 bh = 1 bh
- Flow Switch dia. 80 mm = 1 bh
- Sight Glass = 1 bh
- Test Drain Valve = 2 bh
Page 74 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
A.1 Lantai 1
1 IU-OU-GD.C.1.1 s/d GD.C.1.2 unit 2.00 5,940,000 11,880,000
- Type : Wall Mounted Inverter
- Kapasitas : 12.000 BTUH
- Power : sesuai seleksi unit
- Air Flow Rate : 350 cfm
- Lokasi : IRNA
A.2 Lantai 2
1 IU-OU-GD.C.2.1 s/d GD.C.2.2 unit 2.00 5,940,000 11,880,000
- Type : Wall Mounted Inverter
- Kapasitas : 12.000 BTUH
- Power : sesuai seleksi unit
- Air Flow Rate : 350 cfm
Page 75 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- Lokasi : IRNA
A.3 Lantai 3
1 IU-OU-GD.C.3.1 s/d GD.C.3.6 unit 6.00 5,940,000 35,640,000
- Type : Wall Mounted Inverter
- Kapasitas : 12.000 BTUH
- Power : sesuai seleksi unit
- Air Flow Rate : 350 cfm
- Lokasi : IRNA
Page 76 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
A.4 Lantai 4
1 IU-OU-GD.C.4.1 s/d GD.C.4.4 unit 4.00 18,421,364 73,685,455
- Type : Cassette Inverter
- Kapasitas : 25.000 BTUH
- Power : sesuai seleksi unit
- Air Flow Rate : 750 cfm
- Lokasi : IRNA
Page 77 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Sub Total Lantai 4 275,226,637
B.1 Lantai 1
1 EF-GD.C.1.1 s/d GD.C.1.13 unit 13.00 776,160 10,090,080
- Type : Ceiling Fan
- Kapasitas : 50 CFM
- Ext. Static Pressure : 0,35 In Wg
- Putaran : 950 RPM
- Power : sesuai seleksi unit
- Lokasi : IRNA, R. Isolasi
B.2 Lantai 2
1 EF-GD.C.2.1 s/d GD.C.2.13 unit 13.00 776,160 10,090,080
- Type : Ceiling Fan
- Kapasitas : 50 CFM
- Ext. Static Pressure : 0,35 In Wg
- Putaran : 950 RPM
- Power : sesuai seleksi unit
- Lokasi : IRNA, R. Isolasi
Page 78 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
3 EF.GD.C.2.16 s/d GD.C.2.19 unit 4.00 970,200 3,880,800
- Type : Ceiling Fan
- Kapasitas : 100 CFM
- Static Pressure : 0,35 In Wg
- Putaran : 1.320 RPM
- Power : sesuai seleksi unit
- Lokasi : Loker, Linen, R. Obat, R. Elektronik
B.3 Lantai 3
1 EF-GD.C.3.1 s/d GD.C.3.16 unit 16.00 776,160 12,418,560
- Type : Ceiling Fan
- Kapasitas : 50 CFM
- Ext. Static Pressure : 0,35 In Wg
- Putaran : 950 RPM
- Power : sesuai seleksi unit
- Lokasi : IRNA, R. Isolasi
Page 79 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- Type : In Line
- Kapasitas : 400 CFM
- Ext. Static Pressure : 1,0 In Wg
- Putaran : 1.440 RPM
- Power : sesuai seleksi unit
- Lokasi : Pantry, Toilet, Janitor
B.4 Lantai 4
1 EF-GD.C.4.1 s/d GD.C.4.18 unit 18.00 776,160 13,970,880
- Type : Ceiling Fan
- Kapasitas : 50 CFM
- Ext. Static Pressure : 0,35 In Wg
- Putaran : 950 RPM
- Power : sesuai seleksi unit
- Lokasi : IRNA, R. Isolasi
Page 80 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
gambar dan spesifikasi teknis
Bahan :
Pipa Refrigerant : Cooper Tube ASTM B 280
Pipa Drain : PVC kelas AW 10 kg/cm2
Isolasi Pipa : Elestomeric Nitrile Rubber Class 0
C.1 Lantai 1
1 Pipa AC Split + Isolasi
- dia. 6,4 mm & 12,7 mm IU-OU-GD.C.1.1 mtr 7.70 273,470 2,105,719
- dia. 6,4 mm & 12,7 mm IU-OU-GD.C.1.2 mtr 6.05 273,470 1,654,494
- dia. 9,52 mm & 19,05 mm IU-OU-GD.C.1.3 mtr 7.70 327,090 2,518,593
- dia. 6,4 mm & 15,9 mm IU-OU-GD.C.1.4 mtr 6.05 339,210 2,052,221
- dia. 6,4 mm & 15,9 mm IU-OU-GD.C.1.5 mtr 7.15 339,210 2,425,352
- dia. 6,4 mm & 15,9 mm IU-OU-GD.C.1.6 mtr 8.25 339,210 2,798,483
- dia. 6,4 mm & 15,9 mm IU-OU-GD.C.1.7 mtr 5.50 339,210 1,865,655
- dia. 6,4 mm & 15,9 mm IU-OU-GD.C.1.8 mtr 6.05 339,210 2,052,221
- dia. 6,4 mm & 15,9 mm IU-OU-GD.C.1.9 mtr 6.05 339,210 2,052,221
- dia. 6,4 mm & 15,9 mm IU-OU-GD.C.1.10 mtr 6.05 339,210 2,052,221
- dia. 6,4 mm & 15,9 mm IU-OU-GD.C.1.11 mtr 6.05 339,210 2,052,221
- dia. 6,4 mm & 9,52 mm IU-OU-GD.C.1.12 mtr 13.20 248,800 3,284,160
- dia. 6,4 mm & 9,52 mm IU-OU-GD.C.1.13 mtr 12.10 248,800 3,010,480
- dia. 6,4 mm & 9,52 mm IU-OU-GD.C.1.14 mtr 7.70 248,800 1,915,760
- dia. 6,4 mm & 9,52 mm IU-OU-GD.C.1.15 mtr 12.10 248,800 3,010,480
- dia. 6,4 mm & 9,52 mm IU-OU-GD.C.1.16 mtr 6.60 248,800 1,642,080
- dia. 6,4 mm & 15,9 mm IU-OU-GD.C.1.17 mtr 7.15 339,210 2,425,352
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.1.18 mtr 11.00 395,210 4,347,310
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.1.19 mtr 14.30 395,210 5,651,503
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.1.20 mtr 14.30 395,210 5,651,503
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.1.21 mtr 16.50 395,210 6,520,965
C.2 Lantai 2
1 Pipa AC Split + Isolasi
- dia. 6,4 mm & 12,7 mm IU-OU-GD.C.2.1 mtr 6.60 273,470 1,804,902
- dia. 6,4 mm & 12,7 mm IU-OU-GD.C.2.2 mtr 7.15 273,470 1,955,311
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.2.3 mtr 7.15 395,210 2,825,752
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.2.4 mtr 7.15 395,210 2,825,752
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.2.5 mtr 7.15 395,210 2,825,752
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.2.6 mtr 7.70 395,210 3,043,117
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.2.7 mtr 7.70 395,210 3,043,117
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.2.8 mtr 6.60 395,210 2,608,386
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.2.9 mtr 6.60 395,210 2,608,386
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.2.10 mtr 6.60 395,210 2,608,386
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.2.11 mtr 6.60 395,210 2,608,386
- dia. 6,4 mm & 15,9 mm IU-OU-GD.C.2.12 mtr 13.20 339,210 4,477,572
- dia. 6,4 mm & 15,9 mm IU-OU-GD.C.2.13 mtr 12.10 339,210 4,104,441
- dia. 6,4 mm & 9,52 mm IU-OU-GD.C.2.14 mtr 7.70 248,800 1,915,760
- dia. 6,4 mm & 9,52 mm IU-OU-GD.C.2.15 mtr 12.10 248,800 3,010,480
- dia. 6,4 mm & 9,52 mm IU-OU-GD.C.2.16 mtr 6.60 248,800 1,642,080
- dia. 6,4 mm & 15,9 mm IU-OU-GD.C.2.17 mtr 7.15 395,210 2,825,752
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.2.18 mtr 11.00 395,210 4,347,310
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.2.19 mtr 14.30 395,210 5,651,503
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.2.20 mtr 14.30 395,210 5,651,503
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.2.21 mtr 16.50 395,210 6,520,965
C.3 Lantai 3
1 Pipa AC Split + Isolasi
- dia. 6,4 mm & 12,7 mm IU-OU-GD.C.3.1 mtr 7.15 273,470 1,955,311
- dia. 6,4 mm & 12,7 mm IU-OU-GD.C.3.2 mtr 6.60 273,470 1,804,902
- dia. 6,4 mm & 12,7 mm IU-OU-GD.C.3.3 mtr 6.60 273,470 1,804,902
- dia. 6,4 mm & 12,7 mm IU-OU-GD.C.3.4 mtr 9.90 273,470 2,707,353
- dia. 6,4 mm & 12,7 mm IU-OU-GD.C.3.5 mtr 7.15 273,470 1,955,311
- dia. 6,4 mm & 12,7 mm IU-OU-GD.C.3.6 mtr 6.60 273,470 1,804,902
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.3.7 mtr 6.60 395,210 2,608,386
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.3.8 mtr 6.60 395,210 2,608,386
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.3.9 mtr 6.05 395,210 2,391,021
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.3.10 mtr 6.05 395,210 2,391,021
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.3.11 mtr 6.05 395,210 2,391,021
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.3.12 mtr 6.05 395,210 2,391,021
- dia. 6,4 mm & 12,7 mm IU-OU-GD.C.3.13 mtr 7.15 273,470 1,955,311
- dia. 6,4 mm & 12,7 mm IU-OU-GD.C.3.14 mtr 7.15 273,470 1,955,311
- dia. 6,4 mm & 15,9 mm IU-OU-GD.C.3.15 mtr 12.65 339,210 4,291,007
- dia. 6,4 mm & 15,9 mm IU-OU-GD.C.3.16 mtr 12.65 339,210 4,291,007
- dia. 6,4 mm & 9,52 mm IU-OU-GD.C.3.17 mtr 7.70 248,800 1,915,760
- dia. 6,4 mm & 9,52 mm IU-OU-GD.C.3.18 mtr 11.55 248,800 2,873,640
- dia. 6,4 mm & 9,52 mm IU-OU-GD.C.3.19 mtr 6.60 248,800 1,642,080
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.3.20 mtr 14.30 395,210 5,651,503
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.3.21 mtr 13.20 395,210 5,216,772
Page 81 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.3.22 mtr 13.75 395,210 5,434,138
- dia. 9,52 mm & 15,9 mm IU-OU-GD.C.3.23 mtr 16.50 395,210 6,520,965
D.1 Lantai 1
1 Unit Fan
a Ducting tanpa isolasi finish cat zinkromat lengkap dgn
gantungan/hanger/support dan aksesories lainnya :
- BjLS 80 m2 96.00 267,020 25,633,920
- BjLS 60 m2 71.00 204,930 14,550,030
- BjLS 50 m2 105.00 184,580 19,380,900
2 Unit AC
a Ducting Bahan BJLS + isolasi elestomeric nitrille rubber class 0 lengkap dengan
gantungan/hanger/support dan aksesories lainya
- BjLS 60 m2 226.00 400,880 90,598,880
- BjLS 50 m2 106.00 372,650 39,500,900
Page 82 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- 300 mm x 300 mm bh 3.00 335,400 1,006,200
- 200 mm x 200 mm bh 3.00 223,600 670,800
D.2 Lantai 2
1 Unit Fan
a Ducting tanpa isolasi finish cat zinkromat lengkap dgn
gantungan/hanger/support dan aksesories lainnya :
- BjLS 80 m2 96.00 267,020 25,633,920
- BjLS 60 m2 71.00 204,930 14,550,030
- BjLS 50 m2 105.00 184,580 19,380,900
2 Unit AC
a Ducting Bahan BJLS + isolasi elestomeric nitrille rubber class 0 lengkap dengan
gantungan/hanger/support dan aksesories lainya
- BjLS 60 m2 226.00 400,880 90,598,880
- BjLS 50 m2 106.00 372,650 39,500,900
D.3 Lantai 3
1 Unit Fan
a Ducting tanpa isolasi finish cat zinkromat lengkap dgn
gantungan/hanger/support dan aksesories lainnya :
- BjLS 80 m2 96.00 267,020 25,633,920
- BjLS 60 m2 71.00 204,930 14,550,030
- BjLS 50 m2 105.00 184,580 19,380,900
2 Unit AC
a Ducting Bahan BJLS + isolasi elestomeric nitrille rubber class 0 lengkap dengan
gantungan/hanger/support dan aksesories lainya
- BjLS 60 m2 226.00 400,880 90,598,880
- BjLS 50 m2 106.00 372,650 39,500,900
Page 83 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- 300 mm x 300 mm bh 3.00 335,400 1,006,200
- 200 mm x 200 mm bh 3.00 223,600 670,800
D.4 Lantai 4
1 Unit Fan
a Ducting tanpa isolasi finish cat zinkromat lengkap dgn
gantungan/hanger/support dan aksesories lainnya :
- BjLS 80 m2 96.00 267,020 25,633,920
- BjLS 60 m2 71.00 204,930 14,550,030
- BjLS 50 m2 105.00 184,580 19,380,900
2 Unit AC
a Ducting Bahan BJLS + isolasi elestomeric nitrille rubber class 0 lengkap dengan
gantungan/hanger/support dan aksesories lainya
- BjLS 60 m2 226.00 400,880 90,598,880
- BjLS 50 m2 106.00 372,650 39,500,900
2 Pengkabelan unit Fan dari P.AC-1A ke masing-masing unit titik 24.00 600,000 14,400,000
3 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 187.55 15,698 2,944,160
E.2 Lantai 2
1 Pengkabelan unit AC dari P.AC-1A ke masing-masing unit titik 21.00 850,000 17,850,000
2 Pengkabelan unit Fan dari P.AC-1A ke masing-masing unit titik 24.00 600,000 14,400,000
3 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 175.45 15,698 2,754,214
E.3 Lantai 3
1 Pengkabelan unit AC dari P.AC-1A ke masing-masing unit titik 23.00 850,000 19,550,000
2 Pengkabelan unit Fan dari P.AC-1A ke masing-masing unit titik 26.00 600,000 15,600,000
3 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 204.60 15,698 3,211,811
E.4 Lantai 4
1 Pengkabelan unit AC dari P.AC-1A ke masing-masing unit titik 25.00 850,000 21,250,000
Page 84 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
2 Pengkabelan unit Fan dari P.AC-1A ke masing-masing unit titik 29.00 600,000 17,400,000
3 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 290.40 15,698 4,558,699
Page 85 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
1 LIFT BED / PASSENGER (L.B/P-3 & L.B/P-4) unit 2.00 664,000,000 1,328,000,000
Spesifikasi :
- Type : Machine Room Bed Elevator
- Kapasitas : 1600 kg
- Kecepatan : 60 Mpm
- Travel : 13.770 mm
- Travel Height : 19.770 mm
- Jumlah pemberhentian : 4 bh
- Jumlah Pintu : 4 bh
- Hoistway Size ( W x D ) : 2.400 x 3.000 mm
- Car Size ( W x D x H ) : 1.400 x 2.400 x 2.400 mm
- Type Pintu : 2 - Side Opening Door
- Lebar Pintu : 1.300 mm
- Tinggi Pintu : 2.100 mm
- Overhead : 4.500 mm
- Pit : 1.500 mm
- Kontrol : AC Gearred (OHT) VVVF Control
- Cara Operasi : Duplex Operation
- Penggerak : Traction Drive AC - Gearless
- Car Wall Finishing : Hairline Stainless Steel
- Power : Sesuai Seleksi Unit
termasuk interfacing dengan General Fire Alarm
A Lantai 1
A. STATIONS & DIVERTERS AND ACCESSORIES
1 Bottom Loading Station Unit 2.00 39,637,440 79,274,880
All Stations incl.: Basket, Cushion and Carrier Rack
B Lantai 2
A. STATIONS & DIVERTERS AND ACCESSORIES
1 Bottom Loading Station Unit 1.00 39,637,440 39,637,440
All Stations incl.: Basket, Cushion and Carrier Rack
3 Lantai 3
A. STATIONS & DIVERTERS AND ACCESSORIES
1 Bottom Loading Station Unit 1.00 39,637,440 39,637,440
All Stations incl.: Basket, Cushion and Carrier Rack
Page 86 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Page 87 of 285
ENGINEERING ESTIMATE (EE)
PEKERJAAN MEKANIKAL & ELEKTRIKAL
PROYEK : PAKET PEKERJAAN JASA KONSULTANSI KONSTRUKSI PENGADAAN JASA KONSULTAN LANJUTAN RUMAH SAKIT KUPANG NTT
BANGUNAN : GEDUNG D (IGD, RUANG OK DAN HEMODIALISA)
LOKASI : NUSA TENGGARA TIMUR
TOTAL 25,514,411,148
Page 88 of 285
ENGINEERING ESTIMATE (EE)
PEKERJAAN MEKANIKAL & ELEKTRIKAL
PROYEK : PAKET PEKERJAAN JASA KONSULTANSI KONSTRUKSI PENGADAAN JASA KONSULTAN LANJUTAN RUMAH SAKIT KUPANG NTT
BANGUNAN : GEDUNG D (IGD, RUANG OK DAN HEMODIALISA)
LOKASI : NUSA TENGGARA TIMUR
A.2 Lantai 2
1 SDP.2D unit 1.00 49,597,000 49,597,000
2 PP.2D unit 1.00 9,319,000 9,319,000
3 P.AC-2D unit 1.00 10,913,000 10,913,000
4 P. CHATLAB unit 1.00 32,197,000 32,197,000
5 P. CSSD unit 1.00 22,876,000 22,876,000
6 PC. OK-1 unit 1.00 Trafo Isolasi
7 PC. OK-2 unit 1.00 Trafo Isolasi
8 PC. OK-3 unit 1.00 Trafo Isolasi
9 PC. OK-4 unit 1.00 Trafo Isolasi
10 PC. OK-5 unit 1.00 Trafo Isolasi
11 PC. CATHLAB unit 1.00 Trafo Isolasi
12 PC. PO unit 1.00 Trafo Isolasi
A.3 Lantai 3
1 PP.3D unit 1.00 8,867,000 8,867,000
2 PP.AC-3D unit 1.00 33,262,000 33,262,000
3 P.HD unit 1.00 8,019,000 8,019,000
4 P.AC.OK unit 1.00 51,929,000 51,929,000
Page 89 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
- MCB 2P/10A/6Ka for Distribution 8 pcs
- Surge Arrester tipe 1/1P+N 8kA 1 pcs
- MCB 1P/6A/4,5ka for Protection Unit 1 pcs
- Wiring and ALL Acc.Components Panel 1 lot
1 Dari PDTR 2 :
NYY 4(3 x 1 x 240 mm2) SDP.D mtr 341.00 5,593,140 1,907,260,740
2 Dari PDTR 1 :
NYY 4(3 x 1 x 240 mm2) SDP.AC-D mtr 343.00 5,593,140 1,918,447,020
2 Dari SDP.D
NYY 4 x 25 mm2 PP. 1D mtr 11.00 205,275 2,258,025
NYY 4 x 95 mm2 P. CSSD mtr 51.00 736,575 37,565,325
NYY 3 x 6 mm2 PC. IGD-1 mtr 76.00 38,640 2,936,640
NYY 4(2 x 1 x 150 mm2) SDP. 2D mtr 18.00 2,241,120 40,340,160
NYY 4 x 16 mm2 P.HD mtr 35.00 134,033 4,691,155
NYY 4 x 16 mm2 PP. 3D mtr 22.00 134,033 2,948,726
NYY 4 x 70 mm2 P. SERVER mtr 83.00 536,130 44,498,790
NYY 4 x 10 mm2 P. LIFT mtr 31.00 80,903 2,507,993
NYY 4 x 16 mm2 P. SUMPIT D mtr 13.00 134,033 1,742,429
3 Dari SDP. 2D
NYY 4 x 16 mm2 PP. 2D mtr 10.00 134,033 1,340,330
NYY 4 x 16 mm2 P. CHATLAB mtr 72.00 134,033 9,650,376
NYY 3 x 6 mm2 PC.OK-1 mtr 84.00 38,640 3,245,760
NYY 3 x 6 mm2 PC.OK-2 mtr 85.00 38,640 3,284,400
NYY 3 x 6 mm2 PC.OK-3 mtr 87.00 38,640 3,361,680
NYY 3 x 6 mm2 PC.OK-4 mtr 87.00 38,640 3,361,680
NYY 3 x 6 mm2 PC.OK-5 mtr 89.00 38,640 3,438,960
NYY 3 x 6 mm2 PC.CHATLAB mtr 83.00 38,640 3,207,120
NYY 3 x 6 mm2 PC.PO mtr 89.00 38,640 3,438,960
4 Dari SDP.AC-D
NYY 4 x 95 mm2 P. AC-1D mtr 11.00 736,575 8,102,325
NYY 4 x 35 mm2 P. AC-2D mtr 17.00 278,933 4,741,861
NYY 4 x 185 mm2 P. AC-3D mtr 22.00 1,411,568 31,054,496
NYY 4 x 240 mm2 P. AC-OK mtr 30.00 1,847,475 55,424,250
5 Dari P. CSSD
NYM 3 x 2,5 mm2 ULTRASONIC CLEANER mtr 15.00 15,698 235,470
NYM 3 x 2,5 mm2 ULTRASONIC CLEANER mtr 15.00 15,698 235,470
NYM 4 x 4 mm2 WASHER DISINFECTOR mtr 12.00 32,603 391,236
NYM 4 x 4 mm2 WASHER DISINFECTOR mtr 12.00 32,603 391,236
NYM 4 x 2,5 mm2 DRYING CABINET mtr 20.00 15,698 313,960
NYM 4 x 2,5 mm2 DRYING CABINET mtr 20.00 15,698 313,960
NYM 3 x 2,5 mm2 SEALER mtr 20.00 15,698 313,960
NYM 3 x 2,5 mm2 SEALER mtr 20.00 15,698 313,960
NYM 3 x 2,5 mm2 LINEN TABLE mtr 15.00 15,698 235,470
NYM 3 x 2,5 mm2 LINEN TABLE mtr 15.00 15,698 235,470
NYM 4 x 70 mm2 STEAM STERILIZERS mtr 37.00 536,130 19,836,810
NYM 4 x 70 mm2 STEAM STERILIZERS mtr 37.00 536,130 19,836,810
NYM 3 x 6 mm2 STERICOOL SINGLE DOOR mtr 30.00 35,018 1,050,540
6 Dari P. SUMPIT D
NYY 4 x 4 mm2 PC. SUMPIT D-01 mtr 70.00 36,225 2,535,750
NYY 4 x 4 mm2 PC. SUMPIT D-02 mtr 7.00 36,225 253,575
NYY 4 x 4 mm2 PC. SUMPIT KIMIA D-01 mtr 57.00 36,225 2,064,825
NYY 4 x 4 mm2 PC. SUMPIT KIMIA D-02 mtr 58.00 36,225 2,101,050
Page 90 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
NYY 4 x 4 mm2 PC. SUMPIT POND E-1 mtr 45.00 36,225 1,630,125
8 Dari P.PF-D
FRC 4 x 1 x 4 mm2 PC. PF.D.1 mtr 15.00 95,440 1,431,600
FRC 4 x 1 x 4 mm2 PC. PF.D.2 mtr 35.00 95,440 3,340,400
2 Lantai 2
Kabel Tray Listrik
- uk. 700 mm x 100 mm m 75.00 546,400 40,980,000
3 Lantai 3
Kabel Tray Listrik
- uk. 700 mm x 100 mm m 19.00 546,400 10,381,600
- uk. 600 mm x 50 mm m 18.00 353,000 6,354,000
- uk. 300 mm x 50 mm m 14.00 211,600 2,962,400
G.2 Lantai 1
1 RM TLED 3 x 8 Watt + Cover bh 36.00 1,360,594 48,981,391
2 RM TLED 3 x 8 Watt + Cover c/w Nicad Battery bh 17.00 2,403,118 40,853,009
3 RM TLED 2 x 14 Watt + Cover bh 44.00 1,205,715 53,051,460
4 RM TLED 2 x 14 Watt + Cover c/w Nicad Battery bh 23.00 2,248,239 51,709,497
5 TLED 2x14 Watt (Balk) bh - 881,139 -
6 TLED 2x14 Watt (Balk) c/w Nicad Battery bh 3.00 1,923,663 5,770,989
7 TLED 1x14 Watt (Balk) bh - 483,571 -
8 TLED 1x14 Watt (Balk) c/w Nicad Battery bh - 1,526,007 -
9 Lampu Bed / Periksa LED 29 Watt bh 25.00 930,304 23,257,605
10 Down Light LED E27 13 Watt Bulb + Cover bh 18.00 372,527 6,705,493
11 Down Light LED E27 13 Watt Bulb + Cover c/w Nicad Battery bh 6.00 1,481,731 8,890,384
12 Down Light LED E27 6 Watt Bulb + Cover bh 13.00 284,327 3,696,256
13 Spot Light LED 10W bh 3.00 298,704 896,112
14 Lampu Baret LED E27 10,5 Watt Bulb bh 2.00 229,996 459,992
15 Lampu Baret LED E27 10,5 Watt Bulb c/w Nicad Battery bh 2.00 1,339,288 2,678,575
16 Lampu Bed Head LED 8 watt bh 25.00 354,799 8,869,980
17 Exit Lamp LED 8 Watt bh 3.00 1,349,254 4,047,763
18 Stop Kontak 1 Ph 200 Watt bh 139.00 52,763 7,333,988
19 Stop Kontak 1 Ph 200 Watt Backup Trafo Isolasi + UPS bh 17.00 52,763 896,963
20 Stop Kontak Bed 1 Ph 200 Watt bh 17.00 52,763 896,963
21 Stop Kontak Ceiling TV 1Ph 200 Watt bh 2.00 52,763 105,525
22 Saklar Tunggal bh 23.00 44,163 1,015,749
23 Saklar Ganda bh 48.00 48,794 2,342,088
24 Saklar Hotel bh 2.00 46,242 92,484
25 Grid Switch 5 Gang bh 1.00 329,007 329,007
26 titik
Titik nyala lampu dengan kabel NYM 3 x 2,5 mm² di dalam conduit PVC HI 20 mm 220.00 321,800 70,796,000
Page 91 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
27 Titik nyala Stop kontak NYM 3 x 2,5 mm² didalam conduit PVC HI 20 mm titik 175.00 400,900 70,157,500
G.3 Lantai 2
1 RM TLED 3 x 8 Watt + Cover bh 4.00 1,360,594 5,442,377
2 RM TLED 3 x 8 Watt + Cover c/w Nicad Battery bh 2.00 2,403,118 4,806,236
3 RM TLED 2 x 14 Watt + Cover bh 81.00 1,205,715 97,662,915
4 RM TLED 2 x 14 Watt + Cover c/w Nicad Battery bh 24.00 2,248,239 53,957,736
5 TLED 2x14 Watt (Balk) bh 2.00 881,139 1,762,278
6 TLED 2x14 Watt (Balk) c/w Nicad Battery bh 3.00 1,923,663 5,770,989
7 TLED 1x14 Watt (Balk) bh 2.00 483,571 967,142
8 TLED 1x14 Watt (Balk) c/w Nicad Battery bh 1.00 1,526,007 1,526,007
9 Lampu Bed / Periksa LED 29 Watt bh 14.00 930,304 13,024,259
10 Down Light LED E27 13 Watt Bulb + Cover bh 38.00 372,527 14,156,041
11 Down Light LED E27 13 Watt Bulb + Cover c/w Nicad Battery bh 8.00 1,481,731 11,853,845
12 Down Light LED E27 6 Watt Bulb + Cover bh 18.00 284,327 5,117,893
13 Lampu Baret LED E27 10,5 Watt Bulb bh 2.00 229,996 459,992
14 Lampu Baret LED E27 10,5 Watt Bulb c/w Nicad Battery bh 2.00 1,339,288 2,678,575
15 Exit Lamp LED 8 Watt bh 2.00 1,349,254 2,698,508
16 Stop Kontak 1 Ph 200 Watt bh 75.00 52,763 3,957,188
17 Stop Kontak 1 Ph 200 Watt Backup Trafo Isolasi + UPS bh 15.00 52,763 791,438
18 Stop Kontak Pendant 1 Ph 500 Watt Backup Trafo Isolasi + UPS bh 36.00 52,763 1,899,450
19 Stop Kontak Ceiling TV 1 Ph 200 Watt bh 2.00 52,763 105,525
20 Saklar Tunggal bh 35.00 44,163 1,545,705
21 Saklar Ganda bh 20.00 48,794 975,870
22 Grid Switch 8 Gang bh - 361,515 -
23 titik
Titik nyala lampu dengan kabel NYM 3 x 2,5 mm² di dalam conduit PVC HI 20 mm 203.00 321,800 65,325,400
24 Titik nyala Stop kontak NYM 3 x 2,5 mm² didalam conduit PVC HI 20 mm titik 128.00 400,900 51,315,200
G.4 Lantai 3
1 RM TLED 3 x 8 Watt + Cover bh 59.00 1,360,594 80,275,058
2 RM TLED 3 x 8 Watt + Cover c/w Nicad Battery bh 12.00 2,403,118 28,837,418
3 RM TLED 2 x 14 Watt + Cover bh 15.00 1,205,715 18,085,725
4 RM TLED 2 x 14 Watt + Cover c/w Nicad Battery bh 5.00 2,248,239 11,241,195
5 TLED 2x14 Watt (Balk) bh 28.00 881,139 24,671,892
6 TLED 2x14 Watt (Balk) c/w Nicad Battery bh 5.00 1,923,663 9,618,315
7 Lampu Bed LED 29 Watt bh 11.00 930,304 10,233,346
8 Down Light LED E27 13 Watt Bulb + Cover bh 29.00 372,527 10,803,295
9 Down Light LED E27 13 Watt Bulb + Cover c/w Nicad Battery bh 6.00 1,481,731 8,890,384
10 Down Light LED E27 6 Watt Bulb + Cover bh 7.00 284,327 1,990,292
11 Down Light LED E27 6 Watt Bulb + Cover c/w Nicad Battery bh - 1,393,531 -
12 Lampu Baret LED E27 10,5 Watt Bulb bh 2.00 229,996 459,992
13 Lampu Baret LED E27 10,5 Watt Bulb c/w Nicad Battery bh 2.00 1,339,288 2,678,575
14 Exit Lamp LED 8 Watt bh 2.00 1,349,254 2,698,508
15 Stop Kontak 1 Ph 200 Watt bh 84.00 52,763 4,432,050
16 Stop Kontak Bed 1 Ph 200 Watt bh - 52,763 -
17 Stop Kontak Hemodialisa 4 x 500 watt bh 10.00 133,686 1,336,860
18 Stop Kontak Ceiling TV 1 Ph 200 Watt bh 5.00 52,763 263,813
19 Saklar Tunggal bh 23.00 44,163 1,015,749
20 Saklar Ganda bh 16.00 48,794 780,696
21 Saklar Hotel bh - 46,242 -
22 Grid Switch 8 Gang bh - 361,515 -
23 Titik nyala lampu NYM 3 x 2,5 mm² di dalam conduit PVC HI 20 mm titik 183.00 321,800 58,889,400
24 Titik nyala Stop kontak NYM 3 x 2,5 mm² didalam conduit PVC HI 20 mm titik 99.00 400,900 39,689,100
G.5 Lantai 4
1 Lampu Dinding E27 6 Watt Bulb Water Proof bh 14.00 1,967,188 27,540,626
2 Down Light LED E27 13 Watt Bulb + Cover bh 7.00 372,527 2,607,692
3 Down Light LED E27 13 Watt Bulb + Cover c/w Nicad Battery bh 3.00 1,481,731 4,445,192
4 Lampu Baret LED E27 10,5 Watt Bulb bh 3.00 881,139 2,643,417
5 Lampu Baret LED E27 10,5 Watt Bulb c/w Nicad Battery bh 2.00 1,923,663 3,847,326
6 Stop Kontak 1 Ph 200 Watt bh - 52,763 -
7 Saklar Tunggal bh 2.00 44,163 88,326
8 Saklar Ganda bh 1.00 48,794 48,794
9 Saklar Hotel bh 2.00 46,242 92,484
10 Titik nyala lampu NYM 3 x 2,5 mm² di dalam conduit PVC HI 20 mm titik 5.00 321,800 1,609,000
11 Titik nyala Stop kontak NYM 3 x 2,5 mm² didalam conduit PVC HI 20 mm titik - 400,900 -
Page 92 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Page 93 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
2 Module Module :
- Addressable Monitor Module u/ Detektor unit 3.00 1,659,000 4,977,000
- Addressable Control Module for Horn & Stobe unit 3.00 1,602,694 4,808,081
- Addressable Mini Module for Manual call point / Break Glass unit 3.00 1,020,863 3,062,588
- Addressable Relay Module to Pressurized Fan unit 2.00 1,328,670 2,657,340
- Addressable Relay Module to P. Lift unit 1.00 1,328,670 1,328,670
- Addressable Mini Module (2 input) for Flow Switch / BCV unit 3.00 1,621,463 4,864,388
- Addressable Relay Module for P. AC unit 3.00 1,328,670 3,986,010
2 Kabel ITC 2 x 2 x dia. 0,6 mm dari MDF.FA dalam conduit PVC HI dia. 20 mm
- TB. FA.1 s/d TB.FA.3 m 136.00 61,950 8,425,200
2
3 Kabel NYA 3 x 1,5 mm untuk kabel Power Horn & Strobe
dalam conduit PVC HI dia. 20 mm m 136.00 25,305 3,441,480
- TB. FA.1 s/d TB.FA.3
4 Kabel NYA 2 x 1,5 mm2 untuk Power Module dalam conduit PVC HI dia. 20 mm
- TB. FA.1 s/d TB.FA.3 m 136.00 22,995 3,127,320
5 Kabel STP AWG # 18 + NYA 2 x 1,5 mm2 dari MCFA ke Annunciator m 132.00 74,419 9,823,332
dalam conduit PVC HI dia. 20 mm
C.2 Lantai 2
1 Terminal Box (TB. FA - 2) unit 1.00 630,525 630,525
2 Horn & Strobe bh 2.00 795,769 1,591,538
3 Manual Break Glass bh 2.00 289,013 578,025
4 Addressable Fixed Heat Detector bh 4.00 1,092,315 4,369,260
5 Addressable ROR Detector bh 4.00 1,092,315 4,369,260
6 Addressable Smoke Detector bh 24.00 1,373,846 32,972,310
7 Rate of Rise Detector bh - 491,715 -
8 Photoelectric Smoke Detector Konvensional bh 15.00 581,805 8,727,075
9 Telephone Jack bh 2.00 487,961 975,923
10 End off line bh 4.00 6,379 25,515
11 P.AC bh 1.00 by Others
12 Flow Switch bh 1.00 by Others
Page 94 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Sub Total Lantai 2 78,999,030
C.3 Lantai 3
1 Terminal Box (TB. FA - 3) unit 1.00 630,525 630,525
2 Horn & Strobe bh 2.00 795,769 1,591,538
3 Manual Break Glass bh 2.00 289,013 578,025
4 Addressable Fixed Heat Detector bh - 1,092,315 -
5 Addressable ROR Detector bh 5.00 1,092,315 5,461,575
6 Addressable Smoke Detector bh 14.00 1,373,846 19,233,848
7 Photoelectric Smoke Detector Konvensional bh 16.00 581,805 9,308,880
8 Rate of Rise Detector bh 7.00 491,715 3,442,005
9 Telephone Jack bh 2.00 487,961 975,923
10 End off line bh 4.00 6,379 25,515
11 P.AC bh 1.00 by Others
12 Flow Switch bh 1.00 by Others
13 P. Pressurized Fan bh 1.00 by Others
14 P. Lift bh 1.00 by Others
C.2 Lantai 2
1 Terminal Box Sound System (TB. TS.2) bh 1.00 800,100 800,100
2 Ceiling Speaker 3 Watt + Matching Transformer bh 57.00 196,035 11,173,995
3 Box Speaker 6 Watt bh - 455,133
4 Volume Control bh 14.00 451,920 6,326,880
5 Emergency Speaker 6 Watt bh 2.00 322,382 644,763
6 Instalasi untuk Speaker dengan kabel NYMHY 2 x 1.5 mm2 ttk 57.00 297,900 16,980,300
dalam conduit PVC HI dia. 20 mm
7 Instalasi untuk Volume Control dengan kabel NYMHY 3 x 1.5 mm2 ttk 14.00 492,500 6,895,000
dalam conduit PVC HI dia. 20 mm
8 Instalasi untuk Speaker dengan kabel FRC 2 x 1,5 mm2 ttk 2.00 597,400 1,194,800
dalam conduit PVC HI dia. 20 mm
C.3 Lantai 3
1 Terminal Box Sound System (TB. TS.3) bh 1.00 800,100 800,100
2 Ceiling Speaker 3 Watt + Matching Transformer bh 47.00 196,035 9,213,645
3 Box Speaker 6 Watt bh - 455,133 -
4 Volume Control bh 12.00 451,920 5,423,040
5 Emergency Speaker 6 Watt bh 2.00 322,382 644,763
Page 95 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
6 Instalasi untuk Speaker dengan kabel NYMHY 2 x 1.5 mm2 ttk 47.00 297,900 14,001,300
dalam conduit PVC HI dia. 20 mm
7 Instalasi untuk Volume Control dengan kabel NYMHY 3 x 1.5 mm2 ttk 12.00 492,500 5,910,000
dalam conduit PVC HI dia. 20 mm
8 Instalasi untuk Speaker dengan kabel FRC 2 x 1,5 mm2 ttk 2.00 597,400 1,194,800
dalam conduit PVC HI dia. 20 mm
2 Active Equipment
Manageable Switch Unit 1.00 335,000,000 335,000,000
Server Internet Unit 1.00 153,375,000 153,375,000
IP PABX 10 /100 extention Unit 1.00 255,000,000 255,000,000
3 Cabling System
Kabel FO Multimode 4 core + konduit, Backbone ke Hub 1D m 94.00 27,276 2,563,944
Kabel FO Multimode 4 core + konduit, Backbone ke Hub 2D m 96.00 27,276 2,618,496
Kabel FO Multimode 4 core + konduit, Backbone ke Hub 3D m 14.00 27,276 381,864
2 Outlet :
- Outlet Access Point RJ 45 bh 2.00 135,000 270,000
- Outlet Data RJ 45 bh 19.00 135,000 2,565,000
- Outlet Telepon RJ 45 bh 16.00 135,000 2,160,000
3 Fixture Unit
- Access Point bh 2.00 1,390,000 2,780,000
- Pesawat Telepon IP Extention bh 14.00 1,135,000 15,890,000
- Pesawat Telepon IP Direct bh 1.00 1,135,000 1,135,000
- Pesawat Telepon IP Faximile bh 1.00 6,775,000 6,775,000
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point titik 2.00 936,100 1,872,200
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 19.00 936,100 17,785,900
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 16.00 936,100 14,977,600
B.2 Lantai 2
1 Peralatan Distribusi
- Wall Mounted Rack 19", 15U c/w Accessories unit 1.00 2,200,000 2,200,000
- Wiring Management 1U bh 2.00 148,000 296,000
- Patch Panel FO 12 port bh 1.00 1,634,400 1,634,400
- FO Connector bh 1.00 160,800 160,800
- UTP Cat 6 Patch Panel 24 Port Loaded bh 1.00 1,380,000 1,380,000
- UTP Cat 6 Patch Cord, 1m bh 24.00 45,000 1,080,000
- Switch Hub 24 port bh 1.00 4,508,000 4,508,000
2 Outlet :
- Outlet Access Point RJ 45 bh 3.00 135,000 405,000
- Outlet Data RJ 45 bh 12.00 135,000 1,620,000
- Outlet Telepon RJ 45 bh 10.00 135,000 1,350,000
3 Fixture Unit
- Access Point bh 3.00 1,390,000 4,170,000
- Pesawat Telepon IP Extention bh 10.00 1,135,000 11,350,000
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point titik 3.00 936,100 2,808,300
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 12.00 936,100 11,233,200
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 10.00 936,100 9,361,000
Page 96 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
B.3 Lantai 3
1 Peralatan Distribusi
- Wall Mounted Rack 19", 15U c/w Accessories unit 1.00 2,200,000 2,200,000
- Wiring Management 1U bh 2.00 148,000 296,000
- Patch Panel FO 12 port bh 1.00 1,634,400 1,634,400
- FO Connector bh 1.00 160,800 160,800
- UTP Cat 6 Patch Panel 24 Port Loaded bh 1.00 1,380,000 1,380,000
- UTP Cat 6 Patch Cord, 1m bh 24.00 45,000 1,080,000
- Switch Hub 24 port bh 1.00 4,508,000 4,508,000
2 Outlet :
- Outlet Access Point RJ 45 bh 3.00 135,000 405,000
- Outlet Data RJ 45 bh 14.00 135,000 1,890,000
- Outlet Telepon RJ 45 bh 9.00 135,000 1,215,000
3 Fixture Unit
- Access Point bh 3.00 1,390,000 4,170,000
- Pesawat Telepon IP Extention bh 9.00 1,135,000 10,215,000
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point titik 3.00 936,100 2,808,300
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 14.00 936,100 13,105,400
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 9.00 936,100 8,424,900
2 Lantai 2
Kabel Tray 400 mm x 100 mm m 8.00 293,400 2,347,200
Kabel Tray 300 mm x 100 mm m 22.00 253,000 5,566,000
Kabel Tray 200 mm x 100 mm m 132.00 199,900 26,386,800
3 Lantai 3
Kabel Tray 400 mm x 100 mm m 74.00 293,400 21,711,600
Kabel Tray 300 mm x 100 mm m - 253,000 -
Kabel Tray 200 mm x 100 mm m 45.00 199,900 8,995,500
B.2 Lantai 2
1 Splitter 2 Way Unit 1.00 261,548 261,548
2 Outlet TV Unit 2.00 80,325 160,650
3 Instalasi kabel Outlet TV, coaxial RG6 (5C/2 volt) dakan konduit PVC HI dia. 20 mm
titik 2.00 533,800 1,067,600
4 Instalasi kabel Splitter, Coaxial RG-11 (7C) dalam konduit PVC HI dia. 20 mm m 25.00 26,775 669,375
Page 97 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
Page 98 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
B.3 Lantai 3
1 Splitter 10 Way Unit 1.00 629,606 629,606
2 Splitter 6 Way Unit 2.00 533,108 1,066,215
3 Splitter 4 Way Unit 1.00 366,892 366,892
4 Outlet TV Unit 11.00 80,325 883,575
5 Instalasi kabel Outlet TV, coaxial RG6 (5C/2 volt) dakan konduit PVC HI dia. 20 mm
titik 11.00 533,800 5,871,800
6 Instalasi kabel Splitter, Coaxial RG-11 (7C) dalam konduit PVC HI dia. 20 mm m 56.00 26,775 1,499,400
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 3.00 5,901,300 17,703,900
- Indoor Fixed Dome IP Camera + thermal detector bh 4.00 139,500,000 558,000,000
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Camera titik 7.00 936,100 6,552,700
B.2 Lantai 2
1 Peralatan Distribusi
- Wall Mounted Rack 19", 8U c/w Accessories bh 1.00 1,940,000 1,940,000
- Wiring Management 1U bh 1.00 148,000 148,000
- Patch Panel FO 12 port bh 1.00 1,634,400 1,634,400
- FO Connector bh 1.00 160,800 160,800
- UTP Cat 6 Patch Panel 16 Port Loaded bh 1.00 1,380,000 1,380,000
- UTP Cat 6 Patch Cord, 1m bh 24.00 45,000 1,080,000
- Switch Hub PoE 24 port bh 1.00 4,508,000 4,508,000
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 10.00 5,901,300 59,013,000
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Camera titik 10.00 936,100 9,361,000
B.3 Lantai 3
1 Peralatan Distribusi
- Wall Mounted Rack 19", 15U c/w Accessories bh 1.00 1,940,000 1,940,000
- Wiring Management 1U bh 1.00 148,000 148,000
- Patch Panel FO 12 port bh 1.00 1,634,400 1,634,400
- FO Connector bh 1.00 160,800 160,800
- UTP Cat 6 Patch Panel 16 Port Loaded bh 1.00 1,380,000 1,380,000
- UTP Cat 6 Patch Cord, 1m bh 24.00 45,000 1,080,000
- Switch Hub PoE 24 port bh 1.00 4,508,000 4,508,000
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 10.00 5,901,300 59,013,000
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Camera titik 10.00 936,100 9,361,000
Page 99 of 285
NO. JENIS PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH HARGA
5 UPS kap. Minimal 3 KVA ( Back Up Time min 30 menit) + Surge Arrester unit 1.00 54,085,000 54,085,000
2 Kabel Data dari MCU di Ruang BAS ke: mtr 246.00 51,424 12,650,348
DDC Lt. D ~ 3 STP AWG #18 dalam Conduit PVC 20 mm
1 LANTAI 1
PANEL SDP.D
PANEL SDP.AC.D
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
Power Monitoring HLI Titik 2.00 1,677,000 3,354,000
PANEL PP.1D
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
On - Off Digital Output Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
PANEL PP.AC.1D
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
2 LANTAI 2
PANEL SDP.D
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
PANEL PP.2D
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
On - Off Digital Output Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
3 LANTAI 3
PANEL PP 3.D
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
On - Off Digital Output Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
PANEL PP AC,
Status Digital Input Titik 4.00 928,000 3,712,000
Trip Alarm Digital Input Titik 4.00 928,000 3,712,000
4 LANTAI ATAP
PANEL PRESSURIZED FAN
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
Power Monitoring HLI Titik 2.00 1,677,000 3,354,000
XI PEKERJAAN ANTRIAN
Pengadaan dan pemasangan sistem lengkap sesuai
gambar & spesifikasi teknis
b Catridge filter
- Jumlah : 1 set
- Kapasitas : 2 m3/jam
- Assessories : Valve,Fiting, Piping dll
c RO system, meliputi :
- 1 pcs Pompa umpan RO CNP High Pressure, Cap 1 m3/Head 125 m approximax @3,7 KW
Assesries Valve,fitting dan support
- Membrane LG diameter 6"
- Housing Vessel code line FRP 6"
- Rangka skid mounted steel coated
- Panel control dan pengkabelan
- Alat ukur; TDS meter, Fressure gauge,flow meter
- Piping system complete aksesories
- Tangki storage @1 m3 x 3 unit stainles steel
b Catridge filter
- Jumlah : 1 set
- Kapasitas : 3 m3/jam
- Assessories : Valve,Fiting, Piping dll
c RO system, meliputi :
- 1 pcs Pompa umpan RO CNP High Pressure, Cap 1,5 m3/Head 125 m approximax @3,7 KW
Assesries Valve,fitting dan support
- Membrane LG diameter 6"
- Housing Vessel code line FRP 6"
- Rangka skid mounted steel coated
- Panel control dan pengkabelan
- Alat ukur; TDS meter, Fressure gauge,flow meter
- Piping system complete aksesories
- Tangki storage @1 m3 x 3 unit stainles steel
5 Ball Valve
- dia. 32 mm bh 7.00 380,783 2,665,478
- dia. 25 mm bh 3.00 288,330 864,990
- dia. 20 mm bh 19.00 211,523 4,018,928
- dia. 15 mm bh 2.00 163,380 326,760
8 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
A.2.3 Lantai 2
1 Instalasi pipa air bersih dengan PPR80 - PN10
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 65 mm m' 4.00 177,620 710,480
- dia. 50 mm m' 33.00 132,320 4,366,560
- dia. 40 mm m' 5.00 89,540 447,700
- dia. 32 mm m' 57.00 64,860 3,697,020
- dia. 25 mm m' 3.00 46,250 138,750
- dia. 20 mm m' 83.00 28,830 2,392,890
- dia. 15 mm m' 86.00 22,590 1,942,740
7 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
A.2.4 Lantai 3
1 Instalasi pipa air bersih dari booster lantai atap Gd. C ke Lantai 3 Gd. D
dengan PPR80 - PN10 termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 65 mm m' 72.00 177,620 12,788,640
- dia. 50 mm m' 28.00 132,320 3,704,960
- dia. 40 mm m' 76.00 89,540 6,805,040
Return
- dia. 40 mm m' 15.00 89,540 1,343,100
- dia. 32 mm m' 17.00 64,860 1,102,620
- dia. 25 mm m' 7.00 46,250 323,750
- dia. 20 mm m' 7.00 28,830 201,810
- dia. 15 mm m' 82.00 22,590 1,852,380
6 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
2 Ball Valve :
- dia. 15 mm bh 1.00 163,380 163,380
3 Kran Botol
- dia. 15 mm bh 2.00 ARSITEK
Bak Submersible Cutter Pump + QDC (Sewage.D-01) unit 1.00 skope sipil
Kapasitas : 5 m³
Ukuran : 2500 x 2000 x (1000+500)mm
Bak Submersible Cutter Pump + QDC (Sewage.D-02) unit 1.00 skope sipil
Kapasitas : 5 m³
Ukuran : 2500 x 2000 x (1000+500)mm
Bak Submersible Cutter Pump + QDC (Chemical.D-01) unit 1.00 skope sipil
Kapasitas : 3 m³
Ukuran : 3000 x 1000 x (1000+500)mm
Bak Submersible Cutter Pump + QDC (Chemical.D-02) unit 1.00 skope sipil
Kapasitas : 3 m³
Ukuran : 3000 x 1000 x (1000+500)mm
5 Submersible Pump (Kolam Pond-3) / Drainage Pit-D-01 SET 1.00 108,800,000 108,800,000
Kapasitas : 2 x @9 m3/ jam
Type : Submersible Pump
Head : 5 meter
Power : sesuai seleksi unit
Jumah Pompa : 2 unit
Bekerja secara parallel
lengkap dengan katup2, panel kontrol otomatis dan Level Control
Bak Submersible Pump (Kolam Pond-3) / Drainage Pit-D-01 unit 1.00 skope sipil
Kapasitas : 2 m³
Ukuran : 2200 x 1000 x (800+500)mm
Shaft
- dia. 100 mm m' 30.00 153,900 4,617,000
2 Instalasi Pipa Utama Air Kotor dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
Dari Shaft ke Bak Sumpit
- dia. 150 mm m' 18.00 288,460 5,192,280
Shaft
- dia. 100 mm m' 30.00 153,900 4,617,000
3 Instalasi Pipa Utama Air Kotor Kimia dengan Pipa Cast Iron
termasuk gantungan/hanger, support, fitting dan aksesories :
Dari Shaft ke Bak Sumpit
- dia. 150 mm m' 13.00 692,030 8,996,390
Shaft
- dia. 100 mm m' 30.00 425,060 12,751,800
6 Vent Cup
- dia. 80 mm bh 2.00 341,250 682,500
B.3 Pekerjaan Instalasi Pipa Air Kotor, Kotor & Vent dalam bangunan
B.3.1 Lantai 1
1 Instalasi Air Kotoran Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
2 Instalasi Air Kotor Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 39.00 153,900 6,002,100
- dia. 80 mm m 66.00 105,190 6,942,540
- dia. 50 mm m 33.00 63,440 2,093,520
- dia. 40 mm m 29.00 48,250 1,399,250
B.3.2 Lantai 2
1 Instalasi Air Kotoran Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 72.00 153,900 11,080,800
2 Instalasi Air Kotor Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 15.00 153,900 2,308,500
- dia. 80 mm m 55.00 105,190 5,785,450
- dia. 50 mm m 25.00 63,440 1,586,000
- dia. 40 mm m 21.00 48,250 1,013,250
B.3.3 Lantai 3
1 Instalasi Air Kotoran Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 37.00 153,900 5,694,300
2 Instalasi Air Kotor Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 80 mm m 35.00 105,190 3,681,650
- dia. 50 mm m 9.00 63,440 570,960
- dia. 40 mm m 12.00 48,250 579,000
SUB TOTAL AIR KOTORAN, KOTOR DAN VENT DALAM BANGUNAN 196,215,675
2 Instalasi Pipa Tegak Air Hujan dengan Pipa PVC kelas AW 10 kg/cm2 termasuk
gantungan/hanger, support, fitting dan aksesories :
- dia . 100 mm m' 434.00 153,900 66,792,600
3 Instalasi Pipa Air Hujan dengan Pipa PVC kelas AW 10 kg/cm2 termasuk
gantungan/hanger, support, fitting dan aksesories :
- dia . 100 mm ke Saluran m' 65.00 153,900 10,003,500
2 Automatic Medical Gas Carbon Oxide CO2 (C) set 1.00 133,474,500 133,474,500
Type : Full Automatic Change Over Gas Manifold
Kapasitas : Double Row 2 x@ 2 tabung cylinder (tanpa Tabung)
Output Pressure : 0 - 5 Kg/cm2
~ Double Stage Pressure Regulator (Total 3 Regulators)
~ Pressure Gauge for left and right bank
~ Pressure Gauge for Operating Pressure
Header from High Pressure Copper/Brass dia. 3/4"
~ Copper HP Pig Tails
~ Cylinder Valve High Pressure
~ Safety Valve
~ Regulator inlet emergency
~ Support & Consumable
INSTALASI UTAMA -
3 Zone Valve 3 Gas + Alarm Area Gas set 1.00 37,298,640 37,298,640
C.2 Lantai 2
1 Instalasi pipa cooper ASTM B819 termasuk gantungan/hanger/support,
fitting dan aksesories :
3 Zone Valve
- Zone Valve 5 Gas + Alarm Area Gas set 6.00 83,000,000 498,000,000
- Zone Valve 2 Gas + Alarm Area Gas set 1.00 36,010,000 36,010,000
C.3 Lantai 3
1 Instalasi pipa cooper ASTM B819 termasuk gantungan/hanger/support,
fitting dan aksesories :
3 Zone Valve :
- Zone Valve 2 Gas + Alarm Area Gas set 1.00 36,010,000 36,010,000
D.2 Sprinkler
1 Instalasi pipa utama dengan pipa Black steel Sch. 40
termasuk fitting dan aksesoriesnya :
- dia. 150 mm Tegak (Shaft) m' 15.00 800,660 12,009,900
- dia. 80 mm ( Test Drain ) m' 15.00 328,950 4,934,250
3 Main Control Valve dia. 150 mm + Alarm Gong bh 1.00 38,949,826 38,949,826
4 Gate Valve :
- dia. 65 mm bh 2.00 4,884,868 9,769,736
E.2 Lantai 2
1 Hydrant Box Type Indoor lengkap terpasang unit 2.00 4,773,510 9,547,020
ukuran : 125 x 75 x 18 cm, Cat Bakar
- 1 pc Hose Nozzle dia. 40 mm
- 1 pc Hydrant valve dia. 40 mm
- 1 roll fire hose with Machino Coupling dia. 40 mm x 30 m
- 1 pc Hose Rack
E.3 Lantai 3
1 Hydrant Box Type Indoor lengkap terpasang unit 2.00 4,773,510 9,547,020
ukuran : 125 x 75 x 18 cm, Cat Bakar
- 1 pc Hose Nozzle dia. 40 mm
- 1 pc Hydrant valve dia. 40 mm
- 1 roll fire hose with Machino Coupling dia. 40 mm x 30 m
- 1 pc Hose Rack
3 Branch Control Valve dia. 150 mm terdiri dari : set 1.00 14,023,800 14,023,800
- Butterfly Valve with Tamper Switch dia. 150 bh = 1 bh
- Flow Switch dia. 150 mm = 1 bh
- Sight Glass = 1 bh
- Test Drain Valve = 2 bh
- Coupling
F.2 Lantai 2
1 Instalasi sprinkler dengan Pipa Black Steel Sch. 40 Grid A termasuk
fitting, gantungan/hanger/support dan aksesories :
- dia. 150 mm m' 13.00 800,660 10,408,580
- dia. 100 mm m' 8.00 457,940 3,663,520
- dia. 80 mm m' 36.00 328,950 11,842,200
- dia. 65 mm m' 30.00 259,530 7,785,900
- dia. 50 mm m' 63.00 178,730 11,259,990
- dia. 40 mm m' 45.00 133,880 6,024,600
- dia. 32 mm m' 53.00 112,210 5,947,130
- dia. 25 mm m' 190.00 85,310 16,208,900
- dia. 25 mm Drooper m' 50.00 85,310 4,265,500
3 Branch Control Valve dia. 150 mm terdiri dari : set 1.00 14,023,800 14,023,800
- Butterfly Valve with Tamper Switch dia. 150 bh = 1 bh
- Flow Switch dia. 150 mm = 1 bh
- Sight Glass = 1 bh
- Test Drain Valve = 2 bh
- Coupling
F.3 Lantai 3
1 Instalasi sprinkler dengan Pipa Black Steel Sch. 40 Grid A termasuk
fitting, gantungan/hanger/support dan aksesories :
- dia. 100 mm m' 19.00 457,940 8,700,860
- dia. 80 mm m' 16.00 328,950 5,263,200
- dia. 65 mm m' 29.00 259,530 7,526,370
- dia. 50 mm m' 15.00 178,730 2,680,950
- dia. 40 mm m' 7.00 133,880 937,160
- dia. 32 mm m' 35.00 112,210 3,927,350
- dia. 25 mm m' 166.00 85,310 14,161,460
- dia. 25 mm Drooper m' 32.00 85,310 2,729,920
3 Branch Control Valve dia. 100 mm terdiri dari : set 1.00 11,025,000 11,025,000
- Butterfly Valve with Tamper Switch dia. 100 bh = 1 bh
- Flow Switch dia. 100 mm = 1 bh
- Sight Glass = 1 bh
- Test Drain Valve = 2 bh
H.3 Instalasi
1 Pipe ASTM A53/A106 Seamless Sch. 40
- dia. 65 mm m 290.00 249,600 72,384,000
- dia. 80 mm m 132.00 302,400 39,916,800
2 Pengkabelan STP AWG #18 dalam konduit mtr 936.00 51,424 48,133,033
1 AHU-GD.D.3.OK1
Pipa AHU-DX VRF + Isolasi
dia.12,7 mm & 25,4 mm OU-AHU-GD.D.3.OK.1A & OK.1B m 20.00 569,800 11,396,000
Refnet Joint unit 1.00 2,550,000 2,550,000
Pipa Drain + Isolasi :
- dia. 32 mm m 10.00 87,250 872,500
Return
- Stainless Steel 304 tebal 0,6 mm m2 23.81 465,510 11,082,862
- Stainless Steel 304 tebal 0,5 mm m2 32.72 402,800 13,181,227
Exhaust Air
- BjLS 50 m2 21.60 184,580 3,986,928
- Medium Filter lengkap dengan housing unit 1.00 include unit AHU
type High Efficiency Catridge Filter Back Loading Methode
Euro Vent Standard
Air Flow (CFM) : 1.800
Everage Arrestance : 90 - 95% : 90 - 95 %
Material Resistance Initial (Pa) : 150
Face Felocity. MpM : 150
Frame : Stainless Steel 304
Quantity Filter : Menyesuaikan ukuran AHU
- Pre Filter lengkap dengan housing unit 1.00 include unit AHU
type High Efficiency Catridge Filter Back Loading Methode
Euro Vent Standard
Air Flow (CFM) : 1.800
Everage Arrestance : 80 - 85 %
Material Resistance Initial (Pa) : 75
Face Felocity. MpM : 150
Frame : Stainless Steel 304
Quantity Filter : Menyesuaikan ukuran AHU
4 Pressure differential transmitter and sensor installed on the unit 2.00 9,422,000 18,844,000
housing HEPA filters, this pressure sensor is to send the input
signal to the HVAC controller for modulating the Variable
Speed Drive (VSD) of the AHU supply fan in order to
maintain a constant room pressure
5 Pressure differential transmitter and sensor cross the duct works of unit 1.00 9,492,000 9,492,000
Exhaust fan, this sensor send the signal input to the
HVAC controller for modulating the VSD of the exhaust
fan in order to kept constant flow rate of the exhaust fan
6 Room temperature transmitter and sensor at the grid of cooling coil. unit 1.00 9,226,000 9,226,000
This sensor is to send a signal input to the HVAC
controller in order to maintain a constant dew point
temperature of leaving coil air from cooling coil.
7 Variable speed drive for AHU fan unit 1.00 12,922,000 12,922,000
8 Variable speed drive for Exhaust fan unit 1.00 8,078,000 8,078,000
9 Control panel included relays, switches, field controller unit 1.00 36,400,000 36,400,000
for all necessary AI, AO, DI and DO asper mentioned on
the air schematic diagram.
A.2 Ruang OK 2
A.2.1 Peralatan Utama AC OK
Pengadaan dan Pemasangan unit AHU lengkap dengan
gantungan/hanger/support dan akseories lainnya :
Unit AHU sudah dilengkapi :
- Pre Filter
- Medium Filter
- Return Plenum Box
- Electric Heater
- UV Lamp
- Pressure Differential Monitor
1 AHU-GD.D.3.OK2
Pipa AHU-DX VRF + Isolasi
dia.12,7 mm & 25,4 mm OU-AHU-GD.D.3.OK.2A & OK.2B m 20.00 569,800 11,396,000
Refnet Joint unit 1.00 2,550,000 2,550,000
Pipa Drain + Isolasi :
- dia. 32 mm m 10.00 87,250 872,500
Return
- Stainless Steel 304 tebal 0,6 mm m2 23.81 465,510 11,082,862
- Stainless Steel 304 tebal 0,5 mm m2 32.72 402,800 13,181,227
Exhaust Air
- BjLS 50 m2 21.60 184,580 3,986,928
- Medium Filter lengkap dengan housing unit 1.00 include unit AHU
type High Efficiency Catridge Filter Back Loading Methode
Euro Vent Standard
Air Flow (CFM) : 1.800
Everage Arrestance : 90 - 95% : 90 - 95 %
Material Resistance Initial (Pa) : 150
Face Felocity. MpM : 150
Frame : Stainless Steel 304
Quantity Filter : Menyesuaikan ukuran AHU
- Pre Filter lengkap dengan housing unit 1.00 include unit AHU
type High Efficiency Catridge Filter Back Loading Methode
Euro Vent Standard
Air Flow (CFM) : 1.800
Everage Arrestance : 80 - 85 %
Material Resistance Initial (Pa) : 75
Face Felocity. MpM : 150
Frame : Stainless Steel 304
4 Pressure differential transmitter and sensor installed on the unit 2.00 9,422,000 18,844,000
housing HEPA filters, this pressure sensor is to send the input
signal to the HVAC controller for modulating the Variable
Speed Drive (VSD) of the AHU supply fan in order to
maintain a constant room pressure
5 Pressure differential transmitter and sensor cross the duct works of unit 1.00 9,492,000 9,492,000
Exhaust fan, this sensor send the signal input to the
HVAC controller for modulating the VSD of the exhaust
fan in order to kept constant flow rate of the exhaust fan
6 Room temperature transmitter and sensor at the grid of cooling coil. unit 1.00 9,226,000 9,226,000
This sensor is to send a signal input to the HVAC
controller in order to maintain a constant dew point
temperature of leaving coil air from cooling coil.
7 Variable speed drive for AHU fan unit 1.00 12,922,000 12,922,000
8 Variable speed drive for Exhaust fan unit 1.00 8,078,000 8,078,000
9 Control panel included relays, switches, field controller unit 1.00 36,400,000 36,400,000
for all necessary AI, AO, DI and DO asper mentioned on
the air schematic diagram.
1 AHU-GD.D.3.OK.3
Pipa AHU-DX VRF + Isolasi
dia.12,7 mm & 25,4 mm OU-AHU-GD.D.3.OK.3A & OK.3B m 20.00 569,800 11,396,000
Refnet Joint unit 1.00 2,550,000 2,550,000
Pipa Drain + Isolasi :
- dia. 32 mm m 10.00 87,250 872,500
Return
- Stainless Steel 304 tebal 0,6 mm m2 23.81 465,510 11,082,862
- Stainless Steel 304 tebal 0,5 mm m2 32.72 402,800 13,181,227
Exhaust Air
- BjLS 50 m2 21.60 184,580 3,986,928
- Medium Filter lengkap dengan housing unit 1.00 include unit AHU
type High Efficiency Catridge Filter Back Loading Methode
Euro Vent Standard
Air Flow (CFM) : 1.800
Everage Arrestance : 90 - 95% : 90 - 95 %
Material Resistance Initial (Pa) : 150
Face Felocity. MpM : 150
Frame : Stainless Steel 304
Quantity Filter : Menyesuaikan ukuran AHU
- Pre Filter lengkap dengan housing unit 1.00 include unit AHU
type High Efficiency Catridge Filter Back Loading Methode
Euro Vent Standard
Air Flow (CFM) : 1.800
Everage Arrestance : 80 - 85 %
Material Resistance Initial (Pa) : 75
Face Felocity. MpM : 150
Frame : Stainless Steel 304
Quantity Filter : Menyesuaikan ukuran AHU
4 Pressure differential transmitter and sensor installed on the unit 2.00 9,422,000 18,844,000
housing HEPA filters, this pressure sensor is to send the input
signal to the HVAC controller for modulating the Variable
Speed Drive (VSD) of the AHU supply fan in order to
maintain a constant room pressure
5 Pressure differential transmitter and sensor cross the duct works of unit 1.00 9,492,000 9,492,000
Exhaust fan, this sensor send the signal input to the
HVAC controller for modulating the VSD of the exhaust
fan in order to kept constant flow rate of the exhaust fan
6 Room temperature transmitter and sensor at the grid of cooling coil. unit 1.00 9,226,000 9,226,000
This sensor is to send a signal input to the HVAC
controller in order to maintain a constant dew point
temperature of leaving coil air from cooling coil.
7 Variable speed drive for AHU fan unit 1.00 12,922,000 12,922,000
8 Variable speed drive for Exhaust fan unit 1.00 8,078,000 8,078,000
9 Control panel included relays, switches, field controller unit 1.00 36,400,000 36,400,000
for all necessary AI, AO, DI and DO asper mentioned on
the air schematic diagram.
A.4 Ruang OK 4
A.4.1 Peralatan Utama AC OK
Pengadaan dan Pemasangan unit AHU lengkap dengan
gantungan/hanger/support dan akseories lainnya :
Unit AHU sudah dilengkapi :
- Pre Filter
- Medium Filter
- Return Plenum Box
- Electric Heater
- UV Lamp
- Pressure Differential Monitor
1 AHU-GD.D.3.OK4
Pipa AHU-DX VRF + Isolasi
dia.12,7 mm & 25,4 mm OU-AHU-GD.D.3.OK.4A & OK.4B m 20.00 569,800 11,396,000
Refnet Joint unit 1.00 2,550,000 2,550,000
Pipa Drain + Isolasi :
- dia. 32 mm m 10.00 87,250 872,500
Return
- Stainless Steel 304 tebal 0,6 mm m2 23.81 465,510 11,082,862
- Stainless Steel 304 tebal 0,5 mm m2 32.72 402,800 13,181,227
Exhaust Air
- BjLS 50 m2 21.60 184,580 3,986,928
- Medium Filter lengkap dengan housing unit 1.00 include unit AHU
type High Efficiency Catridge Filter Back Loading Methode
Euro Vent Standard
Air Flow (CFM) : 1.800
Everage Arrestance : 90 - 95% : 90 - 95 %
Material Resistance Initial (Pa) : 150
Face Felocity. MpM : 150
Frame : Stainless Steel 304
Quantity Filter : Menyesuaikan ukuran AHU
- Pre Filter lengkap dengan housing unit 1.00 include unit AHU
type High Efficiency Catridge Filter Back Loading Methode
Euro Vent Standard
Air Flow (CFM) : 1.800
Everage Arrestance : 80 - 85 %
Material Resistance Initial (Pa) : 75
Face Felocity. MpM : 150
Frame : Stainless Steel 304
Quantity Filter : Menyesuaikan ukuran AHU
4 Pressure differential transmitter and sensor installed on the unit 2.00 9,422,000 18,844,000
housing HEPA filters, this pressure sensor is to send the input
signal to the HVAC controller for modulating the Variable
Speed Drive (VSD) of the AHU supply fan in order to
maintain a constant room pressure
5 Pressure differential transmitter and sensor cross the duct works of unit 1.00 9,492,000 9,492,000
Exhaust fan, this sensor send the signal input to the
HVAC controller for modulating the VSD of the exhaust
fan in order to kept constant flow rate of the exhaust fan
6 Room temperature transmitter and sensor at the grid of cooling coil. unit 1.00 9,226,000 9,226,000
This sensor is to send a signal input to the HVAC
controller in order to maintain a constant dew point
temperature of leaving coil air from cooling coil.
7 Variable speed drive for AHU fan unit 1.00 12,922,000 12,922,000
8 Variable speed drive for Exhaust fan unit 1.00 8,078,000 8,078,000
9 Control panel included relays, switches, field controller unit 1.00 36,400,000 36,400,000
for all necessary AI, AO, DI and DO asper mentioned on
the air schematic diagram.
1 AHU-GD.D.3.OK5 (COVID)
Pipa AHU-DX VRF + Isolasi
dia. 12,7 mm & 25,4 mm OU-AHU-GD.D.3.OK.5A & OK.5B m 15.00 569,800 8,547,000
Refnet Joint unit 1.00 2,550,000 2,550,000
Return
- Stainless Steel 304 tebal 0,6 mm m2 35.15 465,510 16,361,745
- Stainless Steel 304 tebal 0,5 mm m2 31.10 402,800 12,528,691
Exhaust Air
- BjLS 50 m2 21.60 184,580 3,986,928
- Medium Filter lengkap dengan housing unit 1.00 include unit AHU
type High Efficiency Catridge Filter Back Loading Methode
Euro Vent Standard
Air Flow (CFM) : 1.800
Everage Arrestance : 90 - 95% : 90 - 95 %
Material Resistance Initial (Pa) : 150
Face Felocity. MpM : 150
Frame : Stainless Steel 304
Quantity Filter : Menyesuaikan ukuran AHU
- Pre Filter lengkap dengan housing unit 1.00 include unit AHU
type High Efficiency Catridge Filter Back Loading Methode
Euro Vent Standard
Air Flow (CFM) : 1.800
Everage Arrestance : 80 - 85 %
Material Resistance Initial (Pa) : 75
Face Felocity. MpM : 150
Frame : Stainless Steel 304
Quantity Filter : Menyesuaikan ukuran AHU
4 Pressure differential transmitter and sensor installed on the unit 2.00 9,422,000 18,844,000
housing HEPA filters, this pressure sensor is to send the input
signal to the HVAC controller for modulating the Variable
Speed Drive (VSD) of the AHU supply fan in order to
maintain a constant room pressure
5 Pressure differential transmitter and sensor cross the duct works of unit 1.00 9,492,000 9,492,000
Exhaust fan, this sensor send the signal input to the
HVAC controller for modulating the VSD of the exhaust
fan in order to kept constant flow rate of the exhaust fan
6 Room temperature transmitter and sensor at the grid of cooling coil. unit 1.00 9,226,000 9,226,000
This sensor is to send a signal input to the HVAC
controller in order to maintain a constant dew point
temperature of leaving coil air from cooling coil.
7 Variable speed drive for AHU fan unit 1.00 12,922,000 12,922,000
8 Variable speed drive for Exhaust fan unit 1.00 8,078,000 8,078,000
9 Control panel included relays, switches, field controller unit 1.00 36,400,000 36,400,000
for all necessary AI, AO, DI and DO asper mentioned on
the air schematic diagram.
1 AHU-GD.D.3.Cathlab
Pipa AHU-DX Inverter + Isolasi
dia. 15,9 mm & 34,9 mm OU-AHU-GD.D.3.Cathlab A & Cathlab B
m 20.00 680,480 13,609,600
Refnet Joint unit 1.00 2,550,000 2,550,000
Pipa Drain + Isolasi :
- dia. 32 mm m 10.00 87,250 872,500
Return
- Stainless Steel 304 tebal 0,6 mm m2 37.37 465,510 17,395,178
- Stainless Steel 304 tebal 0,5 mm m2 32.40 402,800 13,050,720
Exhaust Air
- BjLS 50 m2 11.12 184,580 2,053,268
- Medium Filter lengkap dengan housing unit 1.00 include unit AHU
type High Efficiency Catridge Filter Back Loading Methode
Euro Vent Standard
Air Flow (CFM) : 3.200
Everage Arrestance : 90 - 95% : 90 - 95 %
Material Resistance Initial (Pa) : 150
Face Felocity. MpM : 150
Frame : Stainless Steel 304
Quantity Filter : Menyesuaikan ukuran AHU
- Pre Filter lengkap dengan housing unit 1.00 include unit AHU
type High Efficiency Catridge Filter Back Loading Methode
Euro Vent Standard
Air Flow (CFM) : 3.200
4 Pressure differential transmitter and sensor installed on the unit 2.00 9,422,000 18,844,000
housing HEPA filters, this pressure sensor is to send the input
signal to the HVAC controller for modulating the Variable
Speed Drive (VSD) of the AHU supply fan in order to
maintain a constant room pressure
5 Pressure differential transmitter and sensor cross the duct works of unit 1.00 9,492,000 9,492,000
Exhaust fan, this sensor send the signal input to the
HVAC controller for modulating the VSD of the exhaust
fan in order to kept constant flow rate of the exhaust fan
6 Room temperature transmitter and sensor at the grid of cooling coil. unit 1.00 9,226,000 9,226,000
This sensor is to send a signal input to the HVAC
controller in order to maintain a constant dew point
temperature of leaving coil air from cooling coil.
7 Variable speed drive for AHU fan unit 1.00 12,922,000 12,922,000
8 Variable speed drive for Exhaust fan unit 1.00 8,078,000 8,078,000
9 Control panel included relays, switches, field controller unit 1.00 36,400,000 36,400,000
for all necessary AI, AO, DI and DO asper mentioned on
the air schematic diagram.
1 AHU-GD.D.OK.7
Pipa AHU-DX Inverter + Isolasi
dia. 12,7 mm & 25,4 mm m 30.00 569,800 17,094,000
Refnet Joint unit 1.00 2,550,000 2,550,000
Pipa Drain + Isolasi :
- dia. 32 mm m 10.00 87,250 872,500
- Pre Filter lengkap dengan housing unit 1.00 include unit AHU
type High Efficiency Catridge Filter Back Loading Methode
Euro Vent Standard
Air Flow (CFM) : 1.800
Everage Arrestance : 80 - 85 %
Material Resistance Initial (Pa) : 75
Face Felocity. MpM : 150
Frame : Stainless Steel 304
Quantity Filter : Menyesuaikan ukuran AHU
1 AHU-GD.D.OK.6
Pipa AHU-DX Inverter + Isolasi
dia. 15,9 mm & 34,9 mm m 30.00 680,480 20,414,400
Refnet Joint unit 1.00 2,550,000 2,550,000
Pipa Drain + Isolasi :
- dia. 32 mm m 10.00 87,250 872,500
- Pre Filter lengkap dengan housing unit 1.00 include unit AHU
type High Efficiency Catridge Filter Back Loading Methode
Euro Vent Standard
Air Flow (CFM) : 3.200
Everage Arrestance : 80 - 85 %
Material Resistance Initial (Pa) : 75
Face Felocity. MpM : 150
Frame : Stainless Steel 304
Quantity Filter : Menyesuaikan ukuran AHU
- Hepa Filter type High Efficiency Catridge Filter / Double Seal unit 1.00 11,150,000 11,150,000
Pengadaan dan Pemasangan Ceiling HEPA Filter lengkap dengan Bracket,
material pendukung dan aksesories lainnya
Air Flow (CFM) : 776
Everage Arrestance : 90 - 95 %
Material Resistance Initial (Pa) : 250
Material Resistance Final (Pa) : 700
Face Felocity. MpM : 45-50
Frame : BJLS 100
- Hepa Filter type High Efficiency Catridge Filter / Double Seal unit 1.00 11,150,000 11,150,000
Pengadaan dan Pemasangan Ceiling HEPA Filter lengkap dengan Bracket,
material pendukung dan aksesories lainnya
Air Flow (CFM) : 624
Everage Arrestance : 90 - 95 %
Material Resistance Initial (Pa) : 250
Material Resistance Final (Pa) : 700
Face Felocity. MpM : 45-50
Frame : BJLS 100
2 Material Instalasi termasuk : Pemipaan refrigerant, pemipaan drain, UNIT 2.00 74,891,050 149,782,100
pemipaan humidifier, pekerjaan elektrikal (kabel power, kabel kontrol,
kabel grounding), refrigerant R-410A, Support material & aksesoris.
Bahan :
Pipa Chilled Water : Black Steel Sch 40
Pipa Refrigerant : Cooper TUbe ASTM B 280
Pipa Drain : PVC kelas AW 10 kg/cm2
Isolasi Pipa : Elestomeric Nitrile Rubber Class 0
Jacketing : Alumunium Sheet
Ducting Return
- BjLS 60 m2 8.00 400,880 3,207,040
- BjLS 50 m2 21.00 372,650 7,825,650
Exhaust Air
- BjLS 60 m2 8.00 204,930 1,639,440
- BjLS 50 m2 77.00 184,580 14,212,660
F.2 Lantai 2
1 Ducting Bahan Polyisocyanurate (PIR) lengkap dengan
gantungan/hanger/support dan aksesories lainya
Ducting Supply
- BjLS 60 m2 17.00 400,880 6,814,960
- BjLS 50 m2 67.00 372,650 24,967,550
Ducting Return
- BjLS 60 m2 6.00 400,880 2,405,280
- BjLS 50 m2 67.00 372,650 24,967,550
Exhaust Air
- BjLS 50 m2 83.50 184,580 15,412,430
8 Plenum Box
- uk. 1.100 mm x 600 mm bh 2.00 596,700 1,193,400
- uk. 1.000 mm x 500 mm bh 2.00 526,500 1,053,000
- uk. 900 mm x 500 mm bh 2.00 491,400 982,800
F.3 Lantai 3
1 Ducting Bahan Polyisocyanurate (PIR) lengkap dengan
gantungan/hanger/support dan aksesories lainya
Ducting Supply
- BjLS 60 m2 263.00 400,880 105,431,440
- BjLS 50 m2 - 372,650 -
Ducting Return
- BjLS 60 m2 151.00 400,880 60,532,880
- BjLS 50 m2 - 372,650 -
Exhaust Air
- BjLS 60 m2 34.00 204,930 6,967,620
- BjLS 50 m2 39.00 184,580 7,198,620
2 Pengkabelan unit Fan dari P.AC ke masing-masing unit titik 6.00 600,000 3,600,000
3 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 649.00 15,698 10,188,002
G.2 Lantai 2
1 Pengkabelan unit AC dari P.ACke masing-masing unit titik 11.00 850,000 9,350,000
2 Pengkabelan unit Fan dari P.AC ke masing-masing unit titik 9.00 600,000 5,400,000
3 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 316.25 15,698 4,964,493
G.3 Lantai 3
1 Pengkabelan unit AC dari P.ACke masing-masing unit titik 21.00 850,000 17,850,000
2 Pengkabelan unit Fan dari P.AC ke masing-masing unit titik 5.00 600,000 3,000,000
3 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 756.80 15,698 11,880,246
A Lantai 1
1 STATIONS & DIVERTERS AND ACCESSORIES
Bottom Loading Station Unit 2.00 39,637,440 79,274,880
All Stations incl.: Basket, Cushion and Carrier Rack
B Lantai 2
1 STATIONS & DIVERTERS AND ACCESSORIES
Bottom Loading Station Unit 1.00 39,637,440 39,637,440
All Stations incl.: Basket, Cushion and Carrier Rack
C Lantai 3
1 STATIONS & DIVERTERS AND ACCESSORIES
Bottom Loading Station Unit 1.00 39,637,440 39,637,440
All Stations incl.: Basket, Cushion and Carrier Rack
TOTAL 25,046,581,731
A.2 Lantai 2
1 SDP.2E unit 1.00 50,130,000 50,130,000
2 PP. 2E unit 1.00 8,881,000 8,881,000
3 P.AC-2E unit 1.00 36,047,000 36,047,000
4 P. ICU unit 1.00 11,355,000 11,355,000
5 P. CVCU unit 1.00 9,125,200 9,125,200
6 PC. CVCU unit 2.00 trafo isolasi
7 PC. ICU-1 unit 1.00 trafo isolasi
8 PC. ICU-2 unit 1.00 trafo isolasi
9 PC. ICU-3 unit 1.00 trafo isolasi
10 PC. ICU-4 unit 1.00 trafo isolasi
11 PC. PICU unit 1.00 trafo isolasi
12 PC. NICU unit 1.00 trafo isolasi
B.3 Lantai 3
1 PP.3E unit 1.00 19,978,000 19,978,000
2 P.AC-3E unit 1.00 22,270,000 22,270,000
2 Dari SDP.E
NYY 4 x 25 mm2 ke PP.1E mtr 11.00 205,275 2,258,025
NYY 4 (2 x 1 x 95 mm2) ke SDP.2E mtr 16.00 1,458,664 23,338,624
NYY 4 x 35 mm2 ke PP.3E mtr 22.00 278,933 6,136,526
NYY 4 x 35 mm2 ke P. LIFT.E mtr 26.00 278,933 7,252,258
NYY 4 x 25 mm2 ke P. SUMPIT E mtr 13.00 205,275 2,668,575
3 Dari SDP.AC-E
NYY 4 x 95 mm2 ke P.AC-1E mtr 12.00 736,575 8,838,900
NYY 4 (2 x 1C x 95 mm2) ke P.AC-2E mtr 17.00 1,458,664 24,797,288
NYY 4 x 95 mm2 ke P.AC-3E mtr 22.00 736,575 16,204,650
4 Dari SDP.2E
NYY 4 x 10 mm2 ke PP. 2E mtr 10.00 80,903 809,030
NYY 4 x 35 mm2 ke P. ICU mtr 12.00 278,933 3,347,196
NYY 4 x 25 mm2 ke P. CVCU mtr 12.00 205,275 2,463,300
NYY 3 x 10 mm2 ke PC. CVCU 1 mtr 41.00 62,790 2,574,390
NYY 3 x 6 mm2 ke PC. CVCU 2 mtr 41.00 38,640 1,584,240
NYY 3 x 16 mm2 ke PC. ICU-1 mtr 83.00 101,430 8,418,690
NYY 3 x 16 mm2 ke PC. ICU-2 mtr 83.00 101,430 8,418,690
NYY 3 x 16 mm2 ke PC. ICU-3 mtr 83.00 101,430 8,418,690
NYY 3 x 16 mm2 ke PC. ICU-4 mtr 85.00 101,430 8,621,550
NYY 3 x 10 mm2 ke PC. PICU mtr 42.00 62,790 2,637,180
NYY 3 x 16 mm2 ke PC. NICU mtr 41.00 101,430 4,158,630
5 Dari P.LIFT-E
NYY 4 x 10 mm2 PC. LIFT 1 mtr 17.00 80,903 1,375,351
NYY 4 x 10 mm2 PC. LIFT 2 mtr 17.00 80,903 1,375,351
6 Dari SDP.RADIOLOGI
NYY 4 (2 x 1C x 95 mm2) ke P. MRI mtr 33.00 1,458,664 48,135,912
NYY 4 x 95 mm2 ke P. XRAY-1 mtr 60.00 736,575 44,194,500
NYY 4 x 95 mm2 ke P. XRAY-2 mtr 68.00 736,575 50,087,100
NYY 4 x 185 mm2 ke P. FLUOROSCOPY mtr 54.00 1,411,568 76,224,672
NYY 4 x 185 mm2 ke P. CT-SCAN mtr 50.00 1,411,568 70,578,400
NYY 4 x 6 mm2 ke P. MAMMOGRAPHY mtr 56.00 50,715 2,840,040
NYY 4 x 4 mm2 ke P. USG mtr 40.00 36,225 1,449,000
NYY 4 x 16 mm2 ke P. PANORAMIC mtr 47.00 134,033 6,299,551
NYY 4 x 6 mm2 ke P. DENTAL X-RAY mtr 51.00 50,715 2,586,465
6 Dari P. SUMPIT E
NYY 4 x 4 mm2 PC. SUMPIT E-01 mtr 26.00 36,225 941,850
NYY 4 x 4 mm2 PC. SUMPIT E-02 mtr 31.00 36,225 1,122,975
NYY 4 x 4 mm2 PC. SUMPIT E-03 mtr 91.00 36,225 3,296,475
NYY 4 x 4 mm2 PC. SUMPIT E-04 mtr 127.00 36,225 4,600,575
NYY 4 x 4 mm2 PC. SUMPIT KIMIA E-02 mtr 31.00 36,225 1,122,975
NYY 4 x 4 mm2 PC. SUMPIT KIMIA D-03 mtr 91.00 36,225 3,296,475
NYY 4 x 2,5 mm2 PC. SUMPIT AIR HUJAN mtr 104.00 24,150 2,511,600
NYY 3 x 4 mm2 PC. PNEUMATIC mtr 104.00 27,773 2,888,392
8 Dari P.PF-E
FRC 4 x 1 x 4 mm2 PC. PF.E.1 mtr 15.00 95,440 1,431,600
FRC 4 x 1 x 4 mm2 PC. PF.E.2 mtr 35.00 95,440 3,340,400
2 Kabel Trench :
- Uk. 400 mm x 400 mm m 84.00 Skope Sipil
2 Lantai 2
Kabel Tray Listrik
- uk. 800 mm x 100 mm m 9.00 586,800 5,281,200
- uk. 600 mm x 50 mm m 113.00 353,000 39,889,000
- uk. 400 mm x 50 mm m 14.00 253,000 3,542,000
- uk. 300 mm x 50 mm m 35.00 211,600 7,406,000
3 Lantai 3
Kabel Tray Listrik
- uk. 600 mm x 50 mm m 22.00 353,000 7,766,000
- uk. 400 mm x 50 mm m 36.00 253,000 9,108,000
H.2 Lantai 2
1 RM TLED 3 x 8 Watt + Cover bh 8.00 1,360,594 10,884,754
2 RM TLED 3 x 8 Watt + Cover c/w Nicad Battery bh 5.00 2,403,118 12,015,591
3 RM TLED 2 x 14 Watt + Cover bh 53.00 1,205,715 63,902,895
4 RM TLED 2 x 14 Watt + Cover c/w Nicad Battery bh 22.00 2,248,239 49,461,258
5 TLED 2x14 Watt (Balk) bh 3.00 881,139 2,643,417
6 TLED 2x14 Watt (Balk) c/w Nicad Battery bh 4.00 1,923,663 7,694,652
7 Down Light LED E27 13 Watt Bulb + Cover bh 51.00 372,527 18,998,897
8 Down Light LED E27 13 Watt Bulb + Cover c/w Nicad Battery bh 8.00 1,481,731 11,853,845
9 Down Light LED E27 6 Watt Bulb + Cover bh 7.00 284,327 1,990,292
10 Spot Light LED 10W bh 10.00 298,704 2,987,040
11 Lampu Baret LED E27 10,5 Watt Bulb c/w Nicad Battery bh 2.00 1,339,288 2,678,575
12 Lampu Bed / Periksa LED 29 Watt bh 30.00 930,304 27,909,126
13 Lampu Bed Head LED 8 watt bh 30.00 354,799 10,643,976
14 Exit Lamp LED 8 Watt bh 2.00 1,349,254 2,698,508
15 Stop Kontak 1 Ph 200 Watt bh 123.00 52,763 6,489,788
16 Stop Kontak 1Ph 200 Watt (Backup UPS + Trado Isolasi) bh - 52,763 -
17 Stop Kontak Pendant 1Ph 200 Watt bh 288.00 52,763 15,195,600
18 Stop Kontak Pendant 1Ph 500 Watt (Backup UPS + Trado Isolasi) bh 138.00 52,763 7,281,225
H.3 Lantai 3
1 RM TLED 3 x 8 Watt + Cover bh 79.00 1,360,594 107,486,942
2 RM TLED 3 x 8 Watt + Cover c/w Nicad Battery bh 19.00 2,403,118 45,659,246
3 TLED 2x14 Watt (Balk) bh - 881,139 -
4 TLED 2x14 Watt (Balk) c/w Nicad Battery bh 1.00 1,923,663 1,923,663
5 Lampu Bed TLED 8 Watt bh - 354,799 -
6 Lampu Wastafel 8 watt bh 8.00 540,015 4,320,120
7 Down Light LED E27 13 Watt Bulb + Cover bh 40.00 372,527 14,901,096
8 Down Light LED E27 13 Watt Bulb + Cover c/w Nicad Battery bh 15.00 1,481,731 22,225,959
8 Down Light LED E27 6 Watt Bulb + Cover bh 8.00 284,327 2,274,619
9 Down Light LED E27 6 Watt Bulb + Cover c/w Nicad Battery bh 2.00 1,393,531 2,787,061
9 Lampu Baret LED E27 10,5 Watt Bulb bh 2.00 229,996 459,992
10 Lampu Baret LED E27 10,5 Watt Bulb c/w Nicad Battery bh 2.00 1,339,288 2,678,575
10 Exit Lamp LED 8 Watt bh 2.00 1,349,254 2,698,508
11 Lampu Strip 6W / meter panjang 5 meter + Trafo roll 18.00 299,500 5,391,000
12 Stop Kontak 1 Ph 200 Watt bh 161.00 52,763 8,494,763
13 Stop Kontak Ceiling TV 1Ph 200 Watt bh 6.00 52,763 316,575
14 Stop Kontak Hand Dryer 1000 Watt bh 2.00 78,750 157,500
15 Saklar Tunggal bh 9.00 44,163 397,467
16 Saklar Ganda bh 20.00 48,794 975,870
17 Saklar Hotel bh - 46,242 -
18 Grid Switch 4 Gang bh 1.00 227,462 227,462
19 Grid Switch 5 Gang bh 1.00 329,007 329,007
20 titik
Titik nyala lampu dengan kabel NYM 3 x 2,5 mm² di dalam conduit PVC HI 20 mm 196.00 321,800 63,072,800
21 Titik nyala Stop kontak NYM 3 x 2,5 mm² didalam conduit PVC HI 20 mm titik 169.00 400,900 67,752,100
3 Module Module :
- Addressable Monitor Module u/ Detektor unit 3.00 1,659,000 4,977,000
- Addressable Control Module for Horn & Stobe unit 3.00 1,602,694 4,808,081
- Addressable Mini Module for Manual call point / Break Glass unit 3.00 1,020,863 3,062,588
- Addressable Relay Module to Pressurized Fan unit 2.00 1,328,670 2,657,340
- Addressable Relay Module to P. Lift unit 1.00 1,328,670 1,328,670
- Addressable Mini Module (2 input) for Flow Switch / BCV unit 3.00 1,621,463 4,864,388
- Addressable Relay Module for P. AC unit 3.00 1,328,670 3,986,010
2 Kabel ITC 2 x 2 x dia. 0,6 mm dari MDF.FA dalam conduit PVC HI dia. 20 mm
- TB.FA.1E S/D 3E m 131.00 61,950 8,115,450
2
3 Kabel NYA 3 x 1,5 mm untuk kabel Power Horn & Strobe
dalam conduit PVC HI dia. 20 mm m 131.00 25,305 3,314,955
- TB.FA.1E S/D 3E
4 Kabel NYA 2 x 1,5 mm2 untuk Power Module dalam conduit PVC HI dia. 20 mm
- TB.FA.1E S/D 3E m 131.00 22,995 3,012,345
C.2 Lantai 2
1 Terminal Box (TB. FA - 2E) unit 1.00 630,525 630,525
2 Horn & Strobe bh 2.00 795,769 1,591,538
3 Manual Break Glass bh 2.00 289,013 578,025
4 Addresable Rate of Rise Detector bh 10.00 1,092,315 10,923,150
5 Addresable Fixed Heat Detector bh 2.00 1,092,315 2,184,630
6 Addressable Smoke Detector bh 23.00 1,373,846 31,598,464
7 Rate of Rise Detector bh 15.00 581,805 8,727,075
8 Smoke Detector Photoelectric bh 8.00 491,715 3,933,720
9 Fixed Heat Detector bh - 491,715 -
10 Telephone Jack bh 2.00 487,961 975,923
11 End off line bh 7.00 6,379 44,651
12 P.AC.2 bh 1.00 by Others
13 Flow Switch bh 1.00 by Others
C.2 Lantai 2
1 Terminal Box Sound System Lt.2 (TB. TS. 2E) bh 1.00 800,100 800,100
2 Ceiling Speaker 3 Watt + Matching Transformer bh 64.00 196,035 12,546,240
3 Volume Control bh 14.00 451,920 6,326,880
4 Emergency Speaker 6 Watt bh - 322,382 -
5 Instalasi untuk Speaker dengan kabel NYMHY 2 x 1.5 mm2 ttk 64.00 297,900 19,065,600
C.3 Lantai 3
1 Terminal Box Sound System Lt. 3 (TB. TS. 3C) bh 1.00 800,100 800,100
2 Ceiling Speaker 3 Watt + Matching Transformer bh 41.00 196,035 8,037,435
3 Volume Control bh 15.00 451,920 6,778,800
4 Emergency Speaker 6 Watt bh 2.00 322,382 644,763
5 Instalasi untuk Speaker dengan kabel NYMHY 2 x 1.5 mm2 ttk 41.00 297,900 12,213,900
dalam conduit PVC HI dia. 20 mm
6 Instalasi untuk Volume Control dengan kabel NYMHY 3 x 1.5 mm2 ttk 15.00 492,500 7,387,500
dalam conduit PVC HI dia. 20 mm
7 Instalasi untuk Speaker dengan kabel FRC 2 x 1,5 mm2 ttk 2.00 597,400 1,194,800
dalam conduit PVC HI dia. 20 mm
2 Outlet :
- Outlet Access Point RJ 45 bh 2.00 135,000 270,000
- Outlet Data RJ 45 bh 33.00 135,000 4,455,000
- Outlet Telepon RJ 45 bh 23.00 135,000 3,105,000
3 Fixture Unit
- Access Point bh 2.00 1,390,000 2,780,000
- Pesawat Telepon IP Extention bh 23.00 1,135,000 26,105,000
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point titik 2.00 936,100 1,872,200
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 33.00 936,100 30,891,300
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 23.00 936,100 21,530,300
B.2 Lantai 2
1 Peralatan Distribusi
- Wall Mounted Rack 19", 15U c/w Accessories unit 1.00 2,200,000 2,200,000
- Wiring Management 1U bh 1.00 148,000 148,000
- Patch Panel FO 12 port bh 1.00 1,634,400 1,634,400
- FO Connector bh 1.00 160,800 160,800
- UTP Cat 6 Patch Panel 24 Port Loaded bh 1.00 1,380,000 1,380,000
- UTP Cat 6 Patch Cord, 1m bh 24.00 45,000 1,080,000
- Switch Hub 24 port bh 1.00 4,508,000 4,508,000
2 Outlet :
- Outlet Access Point RJ 45 bh 2.00 135,000 270,000
- Outlet Data RJ 45 bh 11.00 135,000 1,485,000
- Outlet Telepon RJ 45 bh 10.00 135,000 1,350,000
3 Fixture Unit
- Access Point bh 2.00 1,390,000 2,780,000
- Pesawat Telepon IP Extention bh 10.00 1,135,000 11,350,000
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point titik 2.00 936,100 1,872,200
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 11.00 936,100 10,297,100
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 10.00 936,100 9,361,000
2 Outlet :
- Outlet Access Point RJ 45 bh 3.00 135,000 405,000
- Outlet Data RJ 45 bh 18.00 135,000 2,430,000
- Outlet Data Lantai RJ 45 Single bh 6.00 135,000 810,000
- Outlet Data Lantai RJ 45 Double bh 18.00 270,000 4,860,000
- Outlet Telepon RJ 45 bh 14.00 135,000 1,890,000
- Outlet Telepon Lantai RJ 45 Single bh 6.00 135,000 810,000
- Outlet Telepon Lantai RJ 45 Double bh 18.00 270,000 4,860,000
3 Fixture Unit
- Access Point bh 3.00 1,390,000 4,170,000
- Pesawat Telepon IP Extention bh 56.00 1,135,000 63,560,000
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point titik 3.00 936,100 2,808,300
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 60.00 936,100 56,166,000
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 56.00 936,100 52,421,600
2 Lantai 2
Kabel Tray 400 mm x 100 mm m - 293,400 -
Kabel Tray 300 mm x 100 mm m 14.00 253,000 3,542,000
Kabel Tray 200 mm x 100 mm m 70.00 199,900 13,993,000
3 Lantai 3
Kabel Tray 400 mm x 100 mm m 41.00 293,400 12,029,400
Kabel Tray 300 mm x 100 mm m 28.00 253,000 7,084,000
Kabel Tray 200 mm x 100 mm m 33.00 199,900 6,596,700
B.2 Lantai 2
1 Splitter 2 Way Unit 1.00 261,548 261,548
2 Outlet TV Unit 2.00 80,325 160,650
3 Instalasi kabel Outlet TV, coaxial RG6 (5C/2 volt) dakan konduit PVC HI dia. 20 mm
titik 2.00 533,800 1,067,600
4 Instalasi kabel Splitter, Coaxial RG-11 (7C) dalam konduit PVC HI dia. 20 mm m 70.00 26,775 1,874,250
B.3 Lantai 3
1 Splitter 6 Way Unit 1.00 533,108 533,108
2 Splitter 4 Way Unit 1.00 366,892 366,892
3 Booster Unit 1.00 1,658,475 1,658,475
4 Outlet TV Unit 6.00 80,325 481,950
5 Instalasi kabel Outlet TV, coaxial RG6 (5C/2 volt) dakan konduit PVC HI dia. 20 mm
titik 6.00 533,800 3,202,800
6 Instalasi kabel Splitter, Coaxial RG-11 (7C) dalam konduit PVC HI dia. 20 mm m 105.00 26,775 2,811,375
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 3.00 5,901,300 17,703,900
- Indoor Fixed Dome IP Camera + thermal detector bh 1.00 139,500,000 139,500,000
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 4.00 936,100 3,744,400
C.2 Lantai 2
1 Peralatan Distribusi
- Wall Mounted Rack 19", 8U c/w Accessories bh 1.00 1,940,000 1,940,000
- Wiring Management 1U bh 1.00 148,000 148,000
- Patch Panel FO 12 port bh 1.00 1,634,400 1,634,400
- FO Connector bh 1.00 160,800 160,800
- UTP Cat 6 Patch Panel 24 Port Loaded bh 1.00 1,380,000 1,380,000
- UTP Cat 6 Patch Cord, 1m bh 24.00 45,000 1,080,000
- Switch Hub PoE 24 port bh 1.00 4,508,000 4,508,000
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 4.00 5,901,300 23,605,200
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 4.00 936,100 3,744,400
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 5.00 5,901,300 29,506,500
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 5.00 936,100 4,680,500
2 Kabel Data dari MCU di Ruang BAS ke: mtr 246.00 51,424 12,650,348
DDC Lt. D ~ 3 STP AWG #18 dalam Conduit PVC 20 mm
1 LANTAI 1
PANEL SDP.E
PANEL SDP.AC.E
PANEL SDP. RADIOLOGI
Status Digital Input Titik 3.00 928,000 2,784,000
Trip Alarm Digital Input Titik 3.00 928,000 2,784,000
Power Monitoring HLI Titik 3.00 1,677,000 5,031,000
PANEL PP.1E
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
On - Off Digital Output Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
PANEL PP.AC.1E
P PANORAMIC
P. USG
P. MAMMO
P. CT SCAN
P. FLUOROSCOPY
P. XRAY
P. MRI
Status Digital Input Titik 9.00 928,000 8,352,000
Trip Alarm Digital Input Titik 9.00 928,000 8,352,000
2 LANTAI 2
PANEL SDP.E
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
PANEL PP.2E
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
On - Off Digital Output Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
PANEL PP.AC.2E
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
3 LANTAI 3
PANEL PP 3.E
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
On - Off Digital Output Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
PANEL PP AC.3E
Status Digital Input Titik 4.00 928,000 3,712,000
Trip Alarm Digital Input Titik 4.00 928,000 3,712,000
4 LANTAI ATAP
PANEL PRESSURIZED FAN
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
Power Monitoring HLI Titik 2.00 1,677,000 3,354,000
PANEL LIFT
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
XI PEKERJAAN ANTRIAN
Pengadaan dan pemasangan sistem lengkap sesuai
gambar & spesifikasi teknis
XI.A Lantai 1
1 Controller Mesin Antrian unit 1.00 94,000,000 94,000,000
2 Tombol Panggil unit 3.00 1,450,000 4,350,000
3 Counter Display unit 3.00 3,200,000 9,600,000
4 Main Counter Display unit 2.00 8,500,000 17,000,000
5 Mini Speaker System unit 2.00 1,250,000 2,500,000
6 Instalasi Sistem Antrian titik 10.00 725,000 7,250,000
XI.B Lantai 2
1 Controller Mesin Antrian unit - 94,000,000 -
2 Tombol Panggil unit 2.00 1,450,000 2,900,000
3 Counter Display unit 2.00 3,200,000 6,400,000
4 Main Counter Display unit 2.00 8,500,000 17,000,000
5 Mini Speaker System unit 1.00 1,250,000 1,250,000
6 Instalasi Sistem Antrian titik 7.00 725,000 5,075,000
3 Ball Valve :
- dia. 32 mm bh 2.00 380,783 761,565
- dia. 25 mm bh 7.00 288,330 2,018,310
- dia. 20 mm bh 3.00 211,523 634,568
- dia. 15 mm bh 3.00 163,380 490,140
4 Floating Valve :
- dia. 20 mm bh 1.00 204,645 204,645
5 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
A.2.2 Lantai 2
1 Instalasi pipa air bersih dengan PPR80 - PN10
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 40 mm m' 26.00 89,540 2,328,040
- dia. 32 mm m' 67.00 64,860 4,345,620
- dia. 25 mm m' 19.00 46,250 878,750
- dia. 20 mm m' 25.00 28,830 720,750
- dia. 15 mm m' 68.00 22,590 1,536,120
3 Ball Valve :
- dia. 40 mm bh 1.00 504,840 504,840
- dia. 32 mm bh 2.00 380,783 761,565
- dia. 25 mm bh 3.00 288,330 864,990
- dia. 20 mm bh - 211,523 -
- dia. 15 mm bh 9.00 163,380 1,470,420
4 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
A.2.3 Lantai 3
1 Instalasi pipa air bersih dengan PPR80 - PN10
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 65 mm m' 84.00 177,620 14,920,080
- dia. 50 mm m' 87.00 132,320 11,511,840
- dia. 40 mm m' 14.00 89,540 1,253,560
- dia. 32 mm m' 52.00 64,860 3,372,720
- dia. 25 mm m' 2.00 46,250 92,500
- dia. 20 mm m' 55.00 28,830 1,585,650
- dia. 15 mm m' 74.00 22,590 1,671,660
6 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
2 Ball Valve :
- dia. 15 mm bh 1.00 163,380 163,380
3 Kran Botol
- dia. 15 mm bh 2.00 SKOPE ARSITEK
Bak Submersible Cutter Pump + QDC (Sewage.E-01) unit 1.00 skope sipil
Kapasitas : 3 m³
Ukuran : 1500 x 1500 x (1400+500)mm
Bak Submersible Cutter Pump + QDC (Sewage.E-02) unit 1.00 skope sipil
Kapasitas : 3 m³
Ukuran : 1500 x 1500 x (1400+500)mm
Bak Submersible Cutter Pump + QDC (Sewage.E-03) unit 1.00 skope sipil
Kapasitas : 5 m³
Ukuran : 2500 x 2000 x (1000+500)mm
Bak Submersible Cutter Pump + QDC (Sewage.E-04) unit 1.00 skope sipil
Kapasitas : 5 m³
Ukuran : 2500 x 2000 x (1000+500)mm
Bak Submersible Cutter Pump + QDC (Chemical.E-02) unit 1.00 skope sipil
Kapasitas : 2 m³
Ukuran : 2000 x 1000 x (1000+500)mm
Bak Submersible Cutter Pump + QDC (Chemical.D-03) unit 1.00 skope sipil
Kapasitas : 3 m³
Ukuran : 3000 x 1000 x (1000+500)mm
7 Submersible Pump (Kolam Pond-1) / Drainage Pit-E-01 SET 1.00 90,000,000 90,000,000
Kapasitas : 2 x @4.5 m3/ jam
Type : Submersible Pump
Head : 8 meter
Power : sesuai seleksi unit
Jumah Pompa : 2 unit
Bekerja secara parallel
lengkap dengan katup2, panel kontrol otomatis dan Level Control
Bak Submersible Pump (Kolam Pond-1) / Drainage Pit-E-01 unit 1.00 skope sipil
Kapasitas : 1 m³
Ukuran : 1000 x 1000 x (800+500)mm
8 Submersible Pump (Pompa Air Hujan) / Drainage Pit-E-01 unit 1.00 90,000,000 90,000,000
Kapasitas : 2 x @4.5 m3/ jam
Type : Submersible Pump
Head : 10 meter
Power : sesuai seleksi unit
Jumah Pompa : 2 unit
Bekerja secara parallel
lengkap dengan katup2, panel kontrol otomatis dan Level Control
Bak Submersible Pump (Pompa Air Hujan) / Drainage Pit-E-01 unit 1.00 skope sipil
Kapasitas : 1 m³
Ukuran : 1000 x 1000 x (800+500)mm
Shaft
- dia. 100 mm m' 41.00 153,900 6,309,900
2 Instalasi Pipa Utama Air Kotor dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
Dari Shaft ke Bak Sumpit
- dia. 150 mm m' 30.00 288,460 8,653,800
Shaft
- dia. 100 mm m' 23.00 153,900 3,539,700
- dia. 80 mm m' 23.00 105,190 2,419,370
3 Instalasi Pipa Utama Air Kotor Kimia dengan Pipa Cast Iron
termasuk gantungan/hanger, support, fitting dan aksesories :
Dari Shaft ke Bak Sumpit
- dia. 150 mm m' 6.00 692,030 4,152,180
- dia. 100 mm m' 26.00 425,060 11,051,560
Shaft
- dia. 100 mm m' 20.00 425,060 8,501,200
8 Vent Cup
- dia. 80 mm bh 3.00 341,250 1,023,750
B.3 Pekerjaan Instalasi Pipa Air Kotor, Kotor & Vent dalam bangunan
B.3.1 Lantai 1
1 Instalasi Air Kotoran Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 94.00 153,900 14,466,600
5 Vent Cup
- dia. 50 mm bh 1.00 211,575 211,575
B.3.2 Lantai 2
1 Instalasi Air Kotoran Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 45.00 153,900 6,925,500
2 Instalasi Air Kotor Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 80 mm m 39.00 105,190 4,102,410
- dia. 50 mm m 99.00 63,440 6,280,560
- dia. 40 mm m 73.00 48,250 3,522,250
- Gater AHU 200x50 mm m 74.00 SKOPE SIPIL
B.3.3 Lantai 3
1 Instalasi Air Kotoran Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 70.00 153,900 10,773,000
2 Instalasi Air Kotor Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 80 mm m 49.00 105,190 5,154,310
- dia. 50 mm m 31.00 63,440 1,966,640
- dia. 40 mm m 18.00 48,250 868,500
SUB TOTAL AIR KOTORAN, KOTOR DAN VENT DALAM BANGUNAN 164,595,645
2 Instalasi Pipa Tegak Air Hujan dengan Pipa PVC kelas AW 10 kg/cm2 termasuk
gantungan/hanger, support, fitting dan aksesories :
- dia .100 mm m' 431.00 153,900 66,330,900
- dia . 80 mm m' 101.00 105,190 10,624,190
INSTALASI UTAMA -
C.2 Lantai 2
1 Instalasi pipa cooper ASTM B819 termasuk gantungan/hanger/support,
fitting dan aksesories :
4 Zona Valve 3 Gas (O, A,V) + Alarm Set 1.00 37,298,640 37,298,640
A.2 Sprinkler
1 Instalasi pipa utama dengan pipa Black steel Sch. 40
termasuk fitting dan aksesoriesnya :
- dia. 150 mm Tegak (Shaft) + dari site plant m' 75.00 800,660 60,049,500
- dia. 80 mm Pipa tegak Shaft test drain m' 40.00 328,950 13,158,000
- dia. 25 mm m' 2.00 85,310 170,620
4 Gate Valve :
- dia. 65 mm bh 2.00 4,884,868 9,769,736
B.2 Lantai 2
1 Hydrant Box Type Indoor lengkap terpasang unit 2.00 4,773,510 9,547,020
ukuran : 125 x 75 x 18 cm, Cat Bakar
- 1 pc Hose Nozzle dia. 40 mm
- 1 pc Hydrant valve dia. 40 mm
- 1 pc Hose rack 600 mm COMB
- 1 roll fire hose with Machino Coupling dia. 40 mm x 30 m
4 Gate Valve :
- dia. 65 mm bh 2.00 4,884,868 9,769,736
B.3 Lantai 3
1 Hydrant Box Type Indoor lengkap terpasang unit 2.00 4,773,510 9,547,020
ukuran : 125 x 75 x 18 cm, Cat Bakar
- 1 pc Hose Nozzle dia. 40 mm
- 1 pc Hydrant valve dia. 40 mm
- 1 pc Hose rack 600 mm COMB
- 1 roll fire hose with Machino Coupling dia. 40 mm x 30 m
4 Gate Valve :
- dia. 65 mm bh 2.00 4,884,868 9,769,736
3 Branch Control Valve dia. 150 mm terdiri dari : set 1.00 14,023,800 14,023,800
- Butterfly Valve with Tamper Switch dia. 150 mm = 1 bh
- Flow Switch dia. 150 mm = 1 bh
- Sight Glass = 1 bh
- Test Drain Valve = 2 bh
3 Branch Control Valve dia. 100 mm terdiri dari : set 1.00 11,025,000 11,025,000
- Butterfly Valve with Tamper Switch dia. 100 mm = 1 bh
- Flow Switch dia. 100 mm = 1 bh
- Sight Glass = 1 bh
- Test Drain Valve = 2 bh
C.3 Lantai 3
1 Instalasi sprinkler dengan Pipa Black Steel Sch. 40 termasuk
fitting, gantungan/hanger/support dan aksesories :
- dia. 150 mm m' 8.00 800,660 6,405,280
- dia. 100 mm m' 18.00 457,940 8,242,920
- dia. 80 mm m' 22.00 328,950 7,236,900
- dia. 65 mm m' 14.00 259,530 3,633,420
- dia. 50 mm m' 13.00 178,730 2,323,490
- dia. 40 mm m' 18.00 133,880 2,409,840
- dia. 32 mm m' 47.00 112,210 5,273,870
- dia. 25 mm m' 264.00 85,310 22,521,840
- dia. 25 mm Drooper m' 53.00 85,310 4,521,430
3 Branch Control Valve dia. 150 mm terdiri dari : set 1.00 14,023,800 14,023,800
- Butterfly Valve with Tamper Switch dia. 150 mm = 1 bh
- Flow Switch dia. 150 mm = 1 bh
- Sight Glass = 1 bh
- Test Drain Valve = 2 bh
E.3 Instalasi
1 Pipe ASTM A53/A106 Seamless Sch. 40
- dia. 65 mm m 436.00 249,600 108,825,600
- dia. 80 mm m 198.00 302,400 59,875,200
- dia. 100 mm m 259.00 448,000 116,032,000
2 Pengkabelan STP AWG #18 dalam konduit mtr 624.00 51,424 32,088,689
C.1 Lantai 1
1 EF-GD.E.1.1 unit 1.00 7,350,000 7,350,000
- Type : In Line c/w Prefilter & Medium Filter
- Kapasitas : 1.250 CFM
- Static Pressure : 1,5 In Wg
- Putaran : 1.440 RPM
- Power : sesuai seleksi unit
C.2 Lantai 2
1 EF-GD.E.2.1 unit 1.00 20,619,060 20,619,060
- Type : Axial, Fan Box
- Kapasitas : 2.200 CFM
- Static Pressure : 3,5 In Wg
- Putaran : 2.205 RPM
- Power : sesuai seleksi unit
C.3 Lantai 3
1 EF-GD.E.3.1 unit 1.00 776,160 776,160
- Type : Ceiling Fan
- Kapasitas : 50 CFM
- Static Pressure : 0,35 In Wg
- Putaran : 950 RPM
- Power : sesuai seleksi unit
Bahan :
Pipa Refrigerant : Cooper Tube ASTM B 280
Pipa Drain : PVC kelas AW 10 kg/cm2
Isolasi Pipa : Elestomeric Nitrile Rubber Class 0
D.2 Lantai 2
1 Pipa AC Split + Isolasi
Ruang AHU
- dia. 15,9 mm & 35 mm AHU-OU-GD.E.2.1 mtr 16.50 783,000 12,919,500.00
- dia. 15,9 mm & 28,6 mm AHU-OU-GD.E.2.2 mtr 14.85 680,480 10,105,128.00
D.3 Lantai 3
1 Pipa AC Split + Isolasi
- dia. 6,4 mm & 9,5 mm IU-OU-GD.E.3.1 mtr 19.80 248,800 4,926,240
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.2 mtr 14.85 395,210 5,868,869
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.3 mtr 24.20 395,210 9,564,082
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.4 mtr 15.40 395,210 6,086,234
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.5 mtr 12.65 395,210 4,999,407
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.6 mtr 19.25 395,210 7,607,793
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.7 mtr 18.15 395,210 7,173,062
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.8 mtr 17.60 395,210 6,955,696
- dia. 6,4 mm & 9,5 mm IU-OU-GD.E.3.9 mtr 14.30 248,800 3,557,840
- dia. 6,4 mm & 9,5 mm IU-OU-GD.E.3.10 mtr 11.00 248,800 2,736,800
- dia. 6,4 mm & 9,5 mm IU-OU-GD.E.3.11 mtr 8.80 248,800 2,189,440
- dia. 6,4 mm & 9,5 mm IU-OU-GD.E.3.12 mtr 9.35 248,800 2,326,280
- dia. 6,4 mm & 9,5 mm IU-OU-GD.E.3.13 mtr 7.15 248,800 1,778,920
- dia. 6,4 mm & 9,5 mm IU-OU-GD.E.3.14 mtr 11.55 248,800 2,873,640
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.15 mtr 13.20 395,210 5,216,772
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.16 mtr 13.20 395,210 5,216,772
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.17 mtr 12.65 395,210 4,999,407
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.18 mtr 16.50 395,210 6,520,965
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.19 mtr 17.60 395,210 6,955,696
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.20 mtr 17.60 395,210 6,955,696
- dia. 6,4 mm & 15,9 mm IU-OU-GD.E.3.21 mtr 13.75 339,210 4,664,138
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.22 mtr 11.55 395,210 4,564,676
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.23 mtr 20.35 395,210 8,042,524
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.24 mtr 8.25 395,210 3,260,483
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.25 mtr 12.65 395,210 4,999,407
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.26 mtr 30.25 395,210 11,955,103
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.27 mtr 25.30 395,210 9,998,813
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.28 mtr 8.25 395,210 3,260,483
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.29 mtr 13.20 395,210 5,216,772
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.30 mtr 23.65 395,210 9,346,717
- dia. 9,52 mm & 15,9 mm IU-OU-GD.E.3.31 mtr 18.70 395,210 7,390,427
Ducting Return
- BjLS 60 m2 - 400,880 -
- BjLS 50 m2 102.00 372,650 38,010,300.00
Exhaust Air
- BjLS 60 m2 36.00 204,930 7,377,480.00
- BjLS 50 m2 119.00 184,580 21,965,020.00
11 Plenum Box
- uk. 1.000 mm x 500 mm bh 6.00 526,500 3,159,000.00
- uk. 900 mm x 500 mm bh 2.00 491,400 982,800.00
- uk. 550 mm x 300 mm bh 4.00 298,350 1,193,400.00
12 Kitchen Hood
- uk. 1.150 mm x 400 mm bh 1.00 14,300,000 14,300,000.00
Ducting Return
- BjLS 60 m2 264.00 400,880 105,832,320.00
- BjLS 50 m2 197.00 372,650 73,412,050.00
Exhaust Air
- BjLS 60 m2 11.00 204,930 2,254,230.00
- BjLS 50 m2 53.00 184,580 9,782,740.00
11 Plenum Box
- uk. 2.150 mm x 700 mm bh 1.00 1,000,350 1,000,350.00
- uk. 1.350 mm x 700 mm bh 1.00 719,550 719,550.00
- uk. 1.100 mm x 600 mm bh 1.00 596,700 596,700.00
- uk. 1.000 mm x 500 mm bh 2.00 526,500 1,053,000.00
- uk. 900 mm x 500 mm bh 1.00 491,400 491,400.00
Exhaust Air
- BjLS 60 m2 - 204,930 -
- BjLS 50 m2 46.00 184,580 8,490,680.00
2 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 1,087.90 15,698 17,077,854
F.2 Lantai 2
1 Pengkabelan unit AC & Fan dari P.AC-2E ke masing-masing unit
- NYY 4 x 70 mm² ke AHU.GD.E.2.1 m 32.00 536,130 17,156,160
- NYY 4 x 10 mm² ke AHU.GD.E.2.2 m 31.00 80,903 2,507,993
- NYY 4 x 10 mm² ke IU-OU.GD.E.2.1 m 33.00 80,903 2,669,799
- NYM 3 x 2,5 mm² ke IU-OU.GD.E.2.2 m 31.00 15,698 486,638
- NYM 3 x 2,5 mm² ke IU-OU.GD.E.2.2A m 34.00 15,698 533,732
- NYY 4 x 4 mm² ke IU-OU.GD.E.2.3 m 80.00 36,225 2,898,000
- NYY 4 x 4 mm² ke IU-OU.GD.E.2.4 m 81.00 36,225 2,934,225
- NYM 3 x 2,5 mm² ke IU-OU.GD.E.2.5 m 83.00 15,698 1,302,934
- NYM 3 x 2,5 mm² ke IU-OU.GD.E.2.5A m 84.00 15,698 1,318,632
- NYM 3 x 2,5 mm² ke IU-OU.GD.E.2.6 m 79.00 15,698 1,240,142
- NYY 4 x 10 mm² ke IU-OU.GD.E.2.7 m 59.00 76,073 4,488,307
- NYY 4 x 10 mm² ke IU-OU.GD.E.2.8 m 89.00 76,073 6,770,497
- NYM 3 x 2,5 mm² ke IU-OU.GD.E.2.9 m 85.00 15,698 1,334,330
- NYM 3 x 2,5 mm² ke IU-OU.GD.E.2.10 m 87.00 15,698 1,365,726
- NYM 3 x 2,5 mm² ke IU-OU.GD.E.2.11 m 88.00 15,698 1,381,424
- NYM 3 x 2,5 mm² ke IU-OU.GD.E.2.12 m 84.00 15,698 1,318,632
- NYM 3 x 4 mm² ke IU-OU.GD.E.2.13 m 86.00 24,150 2,076,900
- NYM 3 x 4 mm² ke IU-OU.GD.E.2.14 m 90.00 24,150 2,173,500
- NYM 3 x 4 mm² ke IU-OU.GD.E.2.15 m 82.00 24,150 1,980,300
- NYM 3 x 4 mm² ke IU-OU.GD.E.2.16 m 61.00 24,150 1,473,150
- NYM 3 x 4 mm² ke IU-OU.GD.E.2.17 m 60.00 24,150 1,449,000
- NYM 3 x 4 mm² ke IU-OU.GD.E.2.18 m 34.00 24,150 821,100
- NYM 3 x 4 mm² ke IU-OU.GD.E.2.19 m 32.00 24,150 772,800
- NYM 3 x 4 mm² ke IU-OU.GD.E.2.20 m 34.00 24,150 821,100
- NYM 3 x 4 mm² ke IU-OU.GD.E.2.21 m 35.00 24,150 845,250
- NYM 3 x 4 mm² ke IU-OU.GD.E.2.22 m 60.00 24,150 1,449,000
- NYM 3 x 4 mm² ke IU-OU.GD.E.2.23 m 58.00 24,150 1,400,700
- NYY 4 x 4 mm² ke EF-GD.E.2.1 m 28.00 36,225 1,014,300
- NYM 3 x 2,5 mm² ke EF-GD.E.2.2 m 8.00 15,698 125,584
- NYM 3 x 2,5 mm² ke EF-GD.E.2.3 m 13.00 15,698 204,074
- NYM 3 x 2,5 mm² ke EF-GD.E.2.4 m 77.00 15,698 1,208,746
- NYM 3 x 2,5 mm² ke EF-GD.E.2.5 m 79.00 15,698 1,240,142
- NYM 3 x 2,5 mm² ke EF-GD.E.2.6 m 79.00 15,698 1,240,142
- NYM 3 x 2,5 mm² ke EF-GD.E.2.7 m 62.00 15,698 973,276
- NYM 3 x 2,5 mm² ke IF-GD.E.2.1 m 71.00 15,698 1,114,558
2 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 468.60 15,698 7,356,083
F.3 Lantai 3
1 Pengkabelan unit AC & Fan dari P.AC-3E ke masing-masing unit
- NYM 3 x 2,5 mm² ke IU-OU.GD.E.3.1 m 27.00 15,698 423,846
- NYY 4 x 4 mm² ke IU-OU.GD.E.3.2 m 28.00 36,225 1,014,300
- NYM 3 x 4 mm² ke IU-OU.GD.E.3.3 m 29.00 24,150 700,350
- NYM 3 x 4 mm² ke IU-OU.GD.E.3.4 m 35.00 24,150 845,250
- NYM 3 x 4 mm² ke IU-OU.GD.E.3.5 m 33.00 24,150 796,950
- NYY 4 x 4 mm² ke IU-OU.GD.E.3.6 m 52.00 36,225 1,883,700
- NYY 4 x 4 mm² ke IU-OU.GD.E.3.7 m 35.00 36,225 1,267,875
- NYY 4 x 4 mm² ke IU-OU.GD.E.3.8 m 35.00 36,225 1,267,875
- NYM 3 x 2,5 mm² ke IU-OU.GD.E.3.9 m 53.00 15,698 831,994
- NYM 3 x 2,5 mm² ke IU-OU.GD.E.3.10 m 54.00 15,698 847,692
- NYM 3 x 2,5 mm² ke IU-OU.GD.E.3.11 m 55.00 15,698 863,390
- NYM 3 x 2,5 mm² ke IU-OU.GD.E.3.12 m 60.00 15,698 941,880
- NYM 3 x 2,5 mm² ke IU-OU.GD.E.3.13 m 61.00 15,698 957,578
- NYM 3 x 2,5 mm² ke IU-OU.GD.E.3.14 m 60.00 15,698 941,880
- NYY 4 x 4 mm² ke IU-OU.GD.E.3.15 m 52.00 36,225 1,883,700
2 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 480.70 15,698 7,546,029
dalam konduit PVC HI dia. 20 mm
B.2 LANTAI 2
A STATIONS & DIVERTERS AND ACCESSORIES Unit 2.00 39,637,440 79,274,880
Bottom Loading Station
All Stations incl.: Basket, Cushion and Carrier Rack
TOTAL 2,726,184,961
C.2 Lantai 2
1 Ceiling Speaker 3 Watt + Matching Transformer bh 10.00 196,035 1,960,350
2 Volume Control bh - 451,920 -
3 Emergency Speaker 6 Watt bh - 322,382 -
4 Instalasi untuk Speaker dengan kabel NYMHY 2 x 1.5 mm2 ttk 10.00 297,900 2,979,000
dalam conduit PVC HI dia. 20 mm
5 Instalasi untuk Volume Control dengan kabel NYMHY 3 x 1.5 mm2 ttk - 492,500 -
dalam conduit PVC HI dia. 20 mm
6 Instalasi untuk Speaker dengan kabel FRC 2 x 1,5 mm2 ttk - 597,400 -
dalam conduit PVC HI dia. 20 mm
C.3 Lantai 3
1 Ceiling Speaker 3 Watt + Matching Transformer bh 10.00 196,035 1,960,350
2 Volume Control bh - 451,920 -
3 Emergency Speaker 6 Watt bh - 322,382 -
4 Instalasi untuk Speaker dengan kabel NYMHY 2 x 1.5 mm2 ttk 10.00 297,900 2,979,000
dalam conduit PVC HI dia. 20 mm
5 Instalasi untuk Volume Control dengan kabel NYMHY 3 x 1.5 mm2 ttk - 492,500 -
dalam conduit PVC HI dia. 20 mm
6 Instalasi untuk Speaker dengan kabel FRC 2 x 1,5 mm2 ttk - 597,400 -
dalam conduit PVC HI dia. 20 mm
C.4 Lantai 4
1 Ceiling Speaker 3 Watt + Matching Transformer bh 12.00 196,035 2,352,420
2 Volume Control bh - 451,920 -
3 Emergency Speaker 6 Watt bh - 322,382 -
4 Instalasi untuk Speaker dengan kabel NYMHY 2 x 1.5 mm2 ttk 12.00 297,900 3,574,800
dalam conduit PVC HI dia. 20 mm
5 Instalasi untuk Volume Control dengan kabel NYMHY 3 x 1.5 mm2 ttk - 492,500 -
dalam conduit PVC HI dia. 20 mm
6 Instalasi untuk Speaker dengan kabel FRC 2 x 1,5 mm2 ttk - 597,400 -
dalam conduit PVC HI dia. 20 mm
2 Lantai 2
Kabel Tray 400 mm x 100 mm m 46.00 293,400 13,496,400
3 Lantai 3
Kabel Tray 400 mm x 100 mm m 48.00 293,400 14,083,200
4 Lantai 4
Kabel Tray 400 mm x 100 mm m 3.00 293,400 880,200
Kabel Tray 300 mm x 100 mm m - 253,000 -
Kabel Tray 200 mm x 100 mm m 42.00 199,900 8,395,800
2 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 5.00 936,100 4,680,500
B.2 Lantai 2
1 Fixture Unit
- Indoor Fixed Dome IP Camera bh 3.00 5,901,300 17,703,900
2 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 3.00 936,100 2,808,300
B.3 Lantai 3
1 Fixture Unit
- Indoor Fixed Dome IP Camera bh 3.00 5,901,300 17,703,900
2 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 3.00 936,100 2,808,300
2 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 3.00 936,100 2,808,300
XI PEKERJAAN ANTRIAN
Pengadaan dan pemasangan sistem lengkap sesuai
gambar & spesifikasi teknis
2 Instalasi Pipa Tegak Air Hujan dengan Pipa PVC kelas AW 10 kg/cm2 termasuk
gantungan/hanger, support, fitting dan aksesories :
- dia .100 mm m' 187.00 153,900 28,779,300
- dia . 80 mm m' 131.00 105,190 13,779,890
A.2 Lantai 2
1 Instalasi sprinkler dengan Pipa Black Steel Sch. 40 termasuk
fitting, gantungan/hanger/support dan aksesories :
- dia. 80 mm m' 4.00 328,950 1,315,800
- dia. 65 mm m' 28.00 259,530 7,266,840
- dia. 50 mm m' 8.00 178,730 1,429,840
- dia. 40 mm m' 4.00 133,880 535,520
- dia. 32 mm m' 6.00 112,210 673,260
- dia. 25 mm m' 19.00 85,310 1,620,890
- dia. 25 mm Drooper m' 9.00 85,310 767,790
A.3 Lantai 3
1 Instalasi sprinkler dengan Pipa Black Steel Sch. 40 termasuk
fitting, gantungan/hanger/support dan aksesories :
- dia. 65 mm m' 28.00 259,530 7,266,840
- dia. 50 mm m' 19.00 178,730 3,395,870
- dia. 40 mm m' 8.00 133,880 1,071,040
- dia. 32 mm m' 12.00 112,210 1,346,520
- dia. 25 mm m' 35.00 85,310 2,985,850
- dia. 25 mm Drooper m' 12.00 85,310 1,023,720
A.4 Lantai 4
2 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 8.00 15,698 125,584
1 LIFT BED / PASSENGER (L.B/P-5 & L.B/P-6) unit 2.00 640,000,000 1,280,000,000
Spesifikasi :
- Type : Machine Room Bed Elevator
- Kapasitas : 1600 kg
- Kecepatan : 60 Mpm
- Travel : 9.180 mm
- Travel Height : 15.180 mm
- Jumlah pemberhentian : 3 bh
- Jumlah Pintu : 3 bh
- Hoistway Size ( W x D ) : 2.400 x 3.000 mm
- Car Size ( W x D x H ) : 1.400 x 2.400 x 2.400 mm
- Type Pintu : 2 - Side Opening Door
- Lebar Pintu : 1.300 mm
- Tinggi Pintu : 2.100 mm
- Overhead : 4.500 mm
- Pit : 1.500 mm
- Kontrol : AC Gearred (OHT) VVVF Control
- Cara Operasi : Duplex Operation
- Penggerak : Traction Drive AC - Gearless
- Car Wall Finishing : Hairline Stainless Steel
- Power : Sesuai Seleksi Unit
termasuk interfacing dengan General Fire Alarm
TOTAL 362,578,608
C.3 Lantai 3
1 Ceiling Speaker 3 Watt + Matching Transformer bh 5.00 196,035 980,175
2 Volume Control bh - 451,920 -
3 Emergency Speaker 6 Watt bh - 322,382 -
4 Instalasi untuk Speaker dengan kabel NYMHY 2 x 1.5 mm2 ttk 5.00 297,900 1,489,500
dalam conduit PVC HI dia. 20 mm
5 Instalasi untuk Volume Control dengan kabel NYMHY 3 x 1.5 mm2 ttk - 492,500 -
dalam conduit PVC HI dia. 20 mm
6 Instalasi untuk Speaker dengan kabel FRC 2 x 1,5 mm2 ttk - 597,400 -
dalam conduit PVC HI dia. 20 mm
2 Lantai 2
Kabel Tray 400 mm x 100 mm m 31.00 293,400 9,095,400
Kabel Tray 300 mm x 100 mm m 28.00 253,000 7,084,000
3 Lantai 3
Kabel Tray 400 mm x 100 mm m 31.00 293,400 9,095,400
Kabel Tray 300 mm x 100 mm m 28.00 253,000 7,084,000
XI PEKERJAAN ANTRIAN
Pengadaan dan pemasangan sistem lengkap sesuai
gambar & spesifikasi teknis
2 Instalasi Pipa Tegak Air Hujan dengan Pipa PVC kelas AW 10 kg/cm2 termasuk
gantungan/hanger, support, fitting dan aksesories :
- dia . 200 mm m' 88.00 440,670 38,778,960
- dia . 150 mm m' 122.00 288,460 35,192,120
- dia . 100 mm m' 76.00 153,900 11,696,400
- dia . 80 mm m' 216.00 105,190 22,721,040
A.2 Lantai 2
1 Instalasi sprinkler dengan Pipa Black Steel Sch. 40 termasuk
fitting, gantungan/hanger/support dan aksesories :
- dia. 65 mm m' - 259,530 -
- dia. 50 mm m' - 178,730 -
- dia. 40 mm m' - 133,880 -
- dia. 32 mm m' - 112,210 -
- dia. 25 mm m' - 85,310 -
- dia. 25 mm Drooper m' - 85,310 -
A.3 Lantai 3
1 Instalasi sprinkler dengan Pipa Black Steel Sch. 40 termasuk
fitting, gantungan/hanger/support dan aksesories :
- dia. 50 mm m' - 178,730 -
- dia. 40 mm m' - 133,880 -
- dia. 32 mm m' - 112,210 -
TOTAL 4,604,940,479
1 UPS 10 KVA / 1PH UPS PC. COVID UNIT 1.00 120,000,000 120,000,000
2 Dari SDP. J :
NYY 4 x 25 mm2 ke PP-J mtr 11.00 205,275 2,258,025
NYY 4 x 150 mm2 ke P.AC-J mtr 13.00 1,135,050 14,755,650
NYY 3 x 16 mm2 ke PC. COVID mtr 15.00 101,430 1,521,450
2 Kabel ITC 2 x 2 x dia. 0,6 mm dari MDF.FA dalam conduit PVC HI dia. 20 mm
- TB. FA m 104.00 61,950 6,442,800
3 Kabel NYA 3 x 1,5 mm2 untuk kabel Power Horn & Strobe
dalam conduit PVC HI dia. 20 mm m 104.00 25,305 2,631,720
- TB. FA
4 Kabel NYA 2 x 1,5 mm2 untuk Power Module dalam conduit PVC HI dia. 20 mm
- TB. FA m 104.00 22,995 2,391,480
2 Outlet :
- Outlet Access Point RJ 45 bh 2.00 135,000 270,000
- Outlet Data RJ 45 bh 10.00 135,000 1,350,000
- Outlet Telepon RJ 45 bh 10.00 135,000 1,350,000
3 Fixture Unit
- Access Point bh 2.00 1,390,000 2,780,000
- Pesawat Telepon IP Extention bh 10.00 1,135,000 11,350,000
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point titik 2.00 936,100 1,872,200
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 10.00 936,100 9,361,000
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 10.00 936,100 9,361,000
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 2.00 5,901,300 11,802,600
- Indoor Fixed Dome IP Camera + thermal detector bh 2.00 139,500,000 279,000,000
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 4.00 936,100 3,744,400
PANEL PP
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
PANEL PP.AC.KITCHEN
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
XI PEKERJAAN ANTRIAN
Pengadaan dan pemasangan sistem lengkap sesuai
gambar & spesifikasi teknis
b Main Components:
RO Membrane: Optional 2.5”x40”
Membrane Housing: SS304 body+ABS end caps-2054 x 1pc
Pump: Italian Rotary Vane Pump 400LPH 12Bar + 1/2HP
Frame: Electro-Plated SS304
Pre-Filter: (20” KF Housing + PP Cartridge 5um) x 2 sets
Solenoid Valve x 2
Low Pressure Switch x 1
Concentrate Recycling Valve x 1
Product Storage Tank SUS 304 500 L
3 Instalasi pipa gravitasi dari Roof Tank Lantai Atap Gd. C ke Gd. J dengan PPR80 - PN10
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 65 mm m' 201.00 177,620 35,701,620
4 Instalasi pipa air panas cabang dan toilet dengan PPR80 - PN20
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 20 mm m' 97.00 37,020 3,590,940
- dia. 15 mm m' 9.00 26,460 238,140
8 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
- Blower : 2 unit
Model : LP 30
Capacity : 30 Lpm
- Blower : 1 unit
Model : LP 60
Capacity : 60 Lpm
- Cables : 1 Lot
Type : NYY - 0,6/1 KV
B.2 Pekerjaan Instalasi Pipa Air Kotor, Kotor & Vent dalam bangunan
1 Instalasi Air Kotoran Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 134.00 153,900 20,622,600
2 Instalasi Air Kotor Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 37.00 153,900 5,694,300
- dia. 80 mm m 61.00 105,190 6,416,590
- dia. 50 mm m 63.00 63,440 3,996,720
- dia. 40 mm m 16.00 48,250 772,000
1 Instalasi Pipa Utama Air Kotor Kimia dengan Pipa Cast Iron
termasuk gantungan/hanger, support, fitting dan aksesories :
Dari Shaft ke Bak Sumpit
- dia. 80 mm m' 22.00 333,500 7,337,000
- dia. 50 mm m' 19.00 234,680 4,458,920
5 Vent Cup
- dia. 50 mm bh 4.00 211,575 846,300
SUB TOTAL AIR KOTORAN, KOTOR DAN VENT DALAM BANGUNAN 57,002,850
2 Instalasi Pipa Tegak Air Hujan dengan Pipa PVC kelas AW 10 kg/cm2 termasuk
gantungan/hanger, support, fitting dan aksesories :
- dia .100 mm m' 32.00 153,900 4,924,800
3 Zona Valve 3 Gas (O, A,V) + Alarm Set 1.00 37,298,640 37,298,640
A.2 Sprinkler
1 Instalasi pipa utama dengan pipa Black steel Sch. 40
termasuk fitting dan aksesoriesnya : -
- dia. 80 mm Dari Pipa Site Plan ke Shaft m' 12.00 328,950 3,947,400
- dia. 25 mm m' 2.00 85,310 170,620
3 Gate Valve :
- dia. 65 mm bh 2.00 4,884,868 9,769,736
3 Branch Control Valve dia. 80 mm terdiri dari : set 1.00 10,168,200 10,168,200
- Butterfly Valve with Tamper Switch dia. 100 bh = 1 bh
- Flow Switch dia. 100 mm = 1 bh
- Sight Glass = 1 bh
- Test Drain Valve = 2 bh
4 Unit AC (IU-GD.J.1.1)
a Ducting Bahan BJLS + isolasi elestomeric nitrille rubber class 0 lengkap dengan -
gantungan/hanger/support dan aksesories lainya
- BjLS 50 m2 4.00 372,650 1,490,600
2 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 427.35 15,698 6,708,540
TOTAL 1,742,969,440
3 Dari P. KITCHEN
NYM 4 x 6 mm2 REFRIGERATOR mtr 42.00 45,885 1,927,170
NYM 4 x 6 mm2 MESIN CUCI mtr 35.00 45,885 1,605,975
NYM 4 x 4 mm2 AREA PERSIAPAN mtr 38.00 32,603 1,238,914
NYM 4 x 6 mm2 BOILING FAN mtr 32.00 45,885 1,468,320
NYM 4 x 4 mm2 BOILING FAN mtr 38.00 32,603 1,238,914
NYM 3 x 4 mm2 RICE COOKER mtr 32.00 24,150 772,800
NYM 3 x 4 mm2 RICE COOKER mtr 35.00 24,150 845,250
NYM 3 x 4 mm2 RICE COOKER mtr 36.00 24,150 869,400
NYM 3 x 4 mm2 RICE COOKER mtr 39.00 24,150 941,850
NYM 3 x 4 mm2 RICE COOKER mtr 42.00 24,150 1,014,300
NYM 3 x 4 mm2 RICE COOKER mtr 43.00 24,150 1,038,450
NYM 3 x 4 mm2 RICE COOKER mtr 45.00 24,150 1,086,750
NYM 3 x 4 mm2 RICE COOKER mtr 46.00 24,150 1,110,900
NYM 4 x 4 mm2 F. FAN mtr 42.00 32,603 1,369,326
NYM 4 x 4 mm2 F. FAN mtr 35.00 32,603 1,141,105
NYM 4 x 4 mm2 F. FAN mtr 9.00 32,603 293,427
2 Kabel NYA 2 x 1,5 mm2 untuk Power Module dalam conduit PVC HI dia. 20 mm
- TB. FA m 129.00 22,995 2,966,355
2 Outlet :
- Outlet Access Point RJ 45 bh 1.00 135,000 135,000
- Outlet Data RJ 45 bh 3.00 135,000 405,000
- Outlet Telepon RJ 45 bh 5.00 135,000 675,000
3 Fixture Unit
- Access Point bh 1.00 1,390,000 1,390,000
- Pesawat Telepon IP Extention bh 5.00 1,135,000 5,675,000
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point
titik 1.00 936,100 936,100
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 3.00 936,100 2,808,300
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 5.00 936,100 4,680,500
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 2.00 5,901,300 11,802,600
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 2.00 936,100 1,872,200
2 Kabel Data dari MCU di Ruang BAS ke: mtr 396.00 51,424 20,363,975
DDC STP AWG #18 dalam Conduit PVC 20 mm
PANEL PP.AC.KITCHEN
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
XI PEKERJAAN ANTRIAN
Pengadaan dan pemasangan sistem lengkap sesuai
gambar & spesifikasi teknis
2 Instalasi pipa air panas cabang dan toilet dengan PPR80 - PN20
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 20 mm m' 14.00 37,020 518,280
- dia. 15 mm m' 81.00 26,460 2,143,260
5 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
2 Instalasi Air Kotor Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 80 mm m 23.00 105,190 2,419,370
- dia. 50 mm m 6.00 63,440 380,640
6 Vent Cup
- dia. 50 mm bh 4.00 211,575 846,300
1 IU-OU-GD.I.1.1
- Type : Wall Mounted Inverter unit 1.00 9,024,000 9,024,000
- Kapasitas : 15.000 BTUH
- Power : sesuai seleksi unit
- Air Flow Rate : 450 cfm
- Lokasi : Ruang Diskusi
3 IU-OU-GD.I.1.3
- Type : Wall Mounted Inverter unit 1.00 9,024,000 9,024,000
- Kapasitas : 15.000 BTUH
- Power : sesuai seleksi unit
- Air Flow Rate : 450 cfm
- Lokasi : Ruang Diskusi
6 Kitchen Hood
- Material : Stainless Steel 304
- Size (W x D x H) : 5.500 x 750 x 1200 mm bh 3.00 23,000,000 69,000,000
: 1.000 x 750 x 800 mm bh 1.00 14,300,000 14,300,000
- Complete with : Gease Trap
2 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 12.00 15,698 188,376
XVII
PEKERJAAN TRANSPORTASI DALAM GEDUNG
TOTAL 3,436,331,353
3 Dari P. LOUNDRY
NYY 4 x 70 mm2 WASHER EXTRACTOR mtr 43.00 536,130 23,053,590
NYY 4 x 70 mm2 WASHER EXTRACTOR mtr 40.00 536,130 21,445,200
NYY 4 x 70 mm2 BARRIER WASHER EXTRACTOR
mtr 46.00 536,130 24,661,980
NYY 4 x 70 mm2 BARRIER WASHER EXTRACTOR
mtr 46.00 536,130 24,661,980
NYY 4 x 70 mm2 TUMBLE DRYER mtr 37.00 536,130 19,836,810
NYY 4 x 70 mm2 TUMBLE DRYER mtr 37.00 536,130 19,836,810
NYY 4 x 70 mm2 TUMBLE DRYER mtr 39.00 536,130 20,909,070
NYY 4 x 70 mm2 TUMBLE DRYER mtr 39.00 536,130 20,909,070
NYY 4 x 70 mm2 FLATWORK IRONER mtr 39.00 536,130 20,909,070
NYY 4 x 70 mm2 FLATWORK IRONER mtr 36.00 536,130 19,300,680
2 Fixture Unit
- Access Point bh 1.00 1,390,000 1,390,000
- Pesawat Telepon IP Extention bh 1.00 1,135,000 1,135,000
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Pointtitik 1.00 936,100 936,100
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 5.00 936,100 4,680,500
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 1.00 936,100 936,100
2 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 1.00 936,100 936,100
PANEL PP LOUNDRY
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
XI PEKERJAAN ANTRIAN
Pengadaan dan pemasangan sistem lengkap sesuai
gambar & spesifikasi teknis
2 Instalasi pipa air panas cabang dan toilet dengan PPR80 - PN20
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 20 mm m' 13.00 37,020 481,260
5 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
B.2 Pekerjaan Instalasi Pipa Air Kotor, Kotor & Vent dalam bangunan
1 Instalasi Air Kotoran Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 100 mm m 16.00 153,900 2,462,400
2 Instalasi Air Kotor Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia.100 mm m 95.00 153,900 14,620,500
- dia. 80 mm m 14.00 105,190 1,472,660
- dia. 50 mm m 10.00 63,440 634,400
- Gater 200x100 mm m' 8.00 sipil
6 Vent Cup
- dia. 50 mm bh 1.00 211,575 211,575
SUB TOTAL AIR KOTORAN, KOTOR DAN VENT DALAM BANGUNAN 44,535,545
1 Pengadaan dan pemasangan pipa refrigerant ASTM B280 + isolasi lengkap dengan hanger
dan aksesories pendukung lainnya sesuai dengan spesifikasi dan gambar detail
IU-OU-GD.K.1.1 6,4 mm + 9,5 mm m 4.00 248,800 995,200
IU-OU-GD.K.1.2 6,4 mm + 12,7 mm m 9.00 273,470 2,461,230
IU-OU-GD.K.1.3 6,4 mm + 12,7 mm m 5.00 273,470 1,367,350
IU-OU-GD.K.1.4 6,4 mm + 12,7 mm m 4.00 273,470 1,093,880
2 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 22.00 15,698 345,356
TOTAL 3,876,783,123
C.1 Lantai 1
1 Addresable Rate of Rise Detector bh 1.00 1,092,315 1,092,315
2 Addresable Fixed Heat Detector bh - 1,092,315 -
3 Addressable Smoke Detector bh 8.00 1,373,846 10,990,770
4 Smoke Detector Photoelectric bh - 581,805 -
5 Rate of Rise Detector bh 5.00 491,715 2,458,575
6 Fixed Heat Detector bh - 491,715 -
7 End off line bh 1.00 6,379 6,379
2 Fixture Unit
- Access Point bh 1.00 1,390,000 1,390,000
- Pesawat Telepon IP Extention bh 9.00 1,135,000 10,215,000
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point titik 1.00 936,100 936,100
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 10.00 936,100 9,361,000
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 9.00 936,100 8,424,900
2 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 3.00 936,100 2,808,300
PANEL PP IPSRS
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
XI PEKERJAAN ANTRIAN
Pengadaan dan pemasangan sistem lengkap sesuai
gambar & spesifikasi teknis
2 Instalasi pipa air panas cabang dan toilet dengan PPR80 - PN20
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 20 mm m' 17.00 37,020 629,340
5 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
2 Instalasi Air Kotor Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 80 mm m 36.00 105,190 3,786,840
- dia. 50 mm m 5.00 63,440 317,200
- dia. 40 mm m 6.00 48,250 289,500
5 Vent Cup
- dia. 50 mm bh 2.00 211,575 423,150
2 Automatic Medical Gas Manifold Nitrous Oxside (N2O), set 1.00 126,059,250 126,059,250
Type : Full Automatic Change Over Gas Manifold
Kapasitas : Double Row 2 x@ 4 tabung cylinder (tanpa Tabung)
Output Pressure : 0 - 5 Kg/cm2
3 Medical Gas Compressor Air System (A) set 1.00 738,905,000 738,905,000
tediri dari :
- 2 unit Kompressor Oil Free Reciprocating Bare Type @ 11KW
- 1 unit Receiver Tank kapasitas 500 liter
- Automatic Manifold
- After Cooler 1 unit
- Air Dyer 1 unit
- Filter Air
- Regulator
- Panel Kontrol Otomatis
4 Medical Gas Vacuum Pump System (V) set 1.00 447,097,786 447,097,786
- 2 unit Vacuum Pump Oil Sealed type @ 5,5 KW
- 1 unit Receiver Tank kapasitas 400 liter
- Sparator Tank
- Automatic System
- Filter
- Panel Kontrol Otomatis
5 Sentral Alarm Panel 5 gas Lengkap dengan Valve set 1.00 36,851,750 36,851,750
5 IU-OU.GD.L.1.5
- Type : Wall Mounted Inverter unit 1.00 4,818,000 4,818,000
- Kapasitas : 7.000 BTUH
- Power : sesuai seleksi unit
- Air Flow Rate : 210 cfm
- Lokasi : Ruang Kerja
2 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 64.00 15,698 1,004,672
TOTAL 850,470,722
2 Dari PP JENAZAH :
NYY 4 x 35 mm2 ke P.AC JENAZAH mtr 20.00 278,933 5,578,660
2 Outlet :
- Outlet Access Point RJ 45 bh 1.00 135,000 135,000
- Outlet Data RJ 45 bh 10.00 135,000 1,350,000
- Outlet Telepon RJ 45 bh 9.00 135,000 1,215,000
3 Fixture Unit
- Access Point bh 1.00 1,390,000 1,390,000
- Pesawat Telepon IP Extention bh 9.00 1,135,000 10,215,000
4 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm untuk Access Point titik 1.00 936,100 936,100
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Data titik 10.00 936,100 9,361,000
- Intalasi Kabel UTP Cat 6 dalam KOnduit PVC HI 20 mm untuk Telpon titik 9.00 936,100 8,424,900
2 Fixture Unit
- Indoor Fixed Dome IP Camera bh 3.00 5,901,300 17,703,900
3 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 3.00 936,100 2,808,300
XI PEKERJAAN ANTRIAN
Pengadaan dan pemasangan sistem lengkap sesuai
gambar & spesifikasi teknis
2 Instalasi pipa air panas cabang dan toilet dengan PPR80 - PN20
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 20 mm m' 22.00 37,020 814,440
5 Fixture unit (WC, Wastafel, Kitchen Sink, Urinoir, Jet & Scope Arsitek
Hand Shower, Shower, Janitor, Kran taman)
2 Instalasi Air Kotor Cabang dan toilet dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia.100 mm m 15.00 153,900 2,308,500
- dia. 80 mm m 40.00 105,190 4,207,600
6 Vent Cup
- dia. 50 mm bh 4.00 211,575 846,300
3 IU-OU-GD.M.1.3
- Type : Wall Mounted Inverter unit 1.00 9,024,000 9,024,000
- Kapasitas : 18.000 BTUH
- Power : sesuai seleksi unit
- Air Flow Rate : 525 cfm
- Lokasi : Ruang Adm
2 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 80.00 15,698 1,255,840
TOTAL 19,550,817,155
2 Panel Outgoing Tegangan Menengah Load Break switch panel (LBS FUSE) unit 2.00 84,000,000 168,000,000
- Manual and fixed type, c/w
- SF6 Load Break Switch 630A
- 3 fuses solefuse with striker
- LBS operating mechanism
- 3 phase bus bar 630A
- Shunt trip coil 220 VAC + Aux. contact
- 3 neon indicator
- Earthing switch
- Heater 50 W (220 VAC)
- dan kelengkapan lainnya sesuai standard pabrikan
2 Dari TRAFO-2 :
NYY 10 (4 x 1 x 300 mm2) ke ACTS PDTR-2 mtr 24.00 22,797,600 547,142,400
3 Dari PKG :
NYY 10 (4 x 1 x 300 mm2) ke ACTS PDTR-1 mtr 17.00 22,797,600 387,559,200
NYY 10 (4 x 1 x 300 mm2) ke ACTS PDTR-2 mtr 20.00 22,797,600 455,952,000
4 Dari PDTR-1 :
NYY 4 (4 x 1 x 300 mm2) CAPASITOR BANK -1 mtr 28.00 9,119,040 255,333,120
NYY 4 x 10 mm2 ke PP.PH mtr 21.00 80,903 1,698,963
5 Dari PDTR-2 :
NYY 4 (4 x 1 x 300 mm2) CAPASITOR BANK -2 mtr 21.00 9,119,040 191,499,840
NYY 4 x 150 mm2 ke P. ABR mtr 100.00 1,135,050 113,505,000
FRC 4 (3 x 1 x 185 mm2) ke P. HYDRANT mtr 103.00 7,759,392 799,217,376
2 Kabel Trench :
- Uk. 1.000 mm x 600 mm m 7.00 Skope Sipil
- Uk. 600 mm x 600 mm m 52.00 Skope Sipil
- Uk. 400 mm x 400 mm m 4.00 Skope Sipil
2 Dari PKG :
NYY 7(4 x 1C x 300 mm2) ke Genset 1 mtr 21.00 15,958,320 335,124,720
NYM 2(4 x 2,5 mm2) ke Genset 1 mtr 21.00 41,056 862,176
SHIELDED 3(2 x 1,5 mm2) ke Genset 1 mtr 21.00 55,250 1,160,250
NYY 7(4 x 1C x 300 mm2) ke Genset 2 mtr 23.00 15,958,320 367,041,360
NYM 2(4 x 2,5 mm2) ke Genset 2 mtr 23.00 41,056 944,288
SHIELDED 3(2 x 1,5 mm2) ke Genset 2 mtr 23.00 55,250 1,270,750
NYY 7(4 x 1C x 300 mm2) ke Genset 3 mtr - 15,958,320 -
NYM 2(4 x 2,5 mm2) ke Genset 3 mtr - 41,056 -
SHIELDED 3(2 x 1,5 mm2) ke Genset 3 mtr - 55,250 -
3 Tangki penyimpanan bahan bakar mingguan/ weekly tank, dengan unit 1.00 96,000,000 96,000,000
kapasitas 16.000 lt, ketebalan plat minimal 6 mm, lengkap dengan pipa
vent, pipa inlet, pipa drain, manhole, sight glass, level control, rangka besi
penyangga dan seluruh alat bantu dan aksesoris yang diperlukan.
4 Tangki bahan bakar harian/ daily tank dengan kapasitas 3.000 lt, unit 1.00 22,400,000 22,400,000
ketebalan plat min. 5 mm, lengkap dengan pipa vent, pipa inlet, pipa drain,
manhole, sight glass, level control, stair, rangka besi penyangga,
dan seluruh alat bantu dan asesoris yang diperlukan.
5 Pompa elektrik/ transfer pump Kap. 50 LPM untuk bahan bakar solar, tipe sesuai spesifikasi
unit 2.00 22,000,000 44,000,000
lengkap dengan seluruh alat bantu dan aksesoris yang diperlukan.
7 Pompa Tangan (Hand pump) Kap. 10 LPM, operasi single, dengan kapasitas sesuai spesifikasi
unit 1.00 6,000,000 6,000,000
lengkap dengan seluruh alat bantu dan aksesoris yang diperlukan.
8 Pengadaan dan pemasangan pipa solar jenis black steel sch 40 lengkap dengan lot 1.00 49,000,000 49,000,000
valve-valve, fuel oil meter, water sparator, termasuk dengan material sambungan,
penggantung, klem, bracket dan semua aksesoris pemasangan seperti diuraikan
pada spesifikasi teknis dan gambar
9 Sistem pembuangan gas (knalpot genset) menggunakan pipa hitam (black set 2.00 31,200,000 62,400,000
steel) medium class dibungkus dengan rockwool density 80 kg/m3
kemudian dibungkus dengan aluminium jacketing tebal 50 mm di
sepanjang pipa, lengkap dengan vibration isolators, hangers, flanges,
sealant, rain cap dan semua acsesoris pendukung
10 Gas exhaust silencer tipe critical sesuai spesifikasi dan gambar set 2.00 18,000,000 36,000,000
dan semua asesoris pendukung
12 Intake sound attenuator dengan ukuran 5.500 x 1.000 x 1.500 mm unit 1.00 2,800,000 2,800,000
lengkap dengan semua alat bantu yang diperlukan.
13 Exhaust sound attenuator dengan ukuran 2.500 x 1.000 x 1.500 mm unit 2.00 1,750,000 3,500,000
lengkap dengan semua alat bantu yang diperlukan.
14 Ducting radiator flexible / ducting exhaust plenum genset kapasitas 1.250 KVA set 2.00 7,200,000 14,400,000
15 Isolasi peredam suara di ruang genset, menggunakan rockwool m2 344.75 435,500 150,138,625
dengan density 80 Kg/m3 tebal 50 mm, di pasang di dinding, kolom dan plafon,
dilapisi dengan glass cloth, wire mesh dan diperkuat dengan spindle pin
serta semua alat bantu yang diperlukan.
(Luasan dinding, kolom dan plafon sesuai gambar tender)
16 Testing & Commissioning Genset termasuk pengadaan solar selama testing lot 1.00 25,000,000 25,000,000
19 Biaya Sertifikasi Laik Operasi Instalasi Genset lot 1.00 85,000,000 85,000,000
2 Kabel NYA 2 x 1,5 mm2 untuk Power Module dalam conduit PVC HI dia. 20 mm
- TB. FA m 207.00 22,995 4,759,965
2 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 2.00 936,100 1,872,200
2 Kabel Data dari MCU di Ruang BAS ke: mtr 440.00 51,424 22,626,639
DDC AWG #18 dalam Conduit PVC 20 mm
1 PDTM
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
Power Monitoring HLI Titik 2.00 1,677,000 3,354,000
2 TRAFO
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
HI Temp Digital Input Titik 2.00 928,000 1,856,000
3 PDTR
INCOMING
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
Power Monitoring HLI Titik 4.00 1,677,000 6,708,000
COUPLER
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
OUTGOING
Status Digital Input Titik 21.00 928,000 19,488,000
Trip Alarm Digital Input Titik 21.00 928,000 19,488,000
4 PKG
OUTGOING
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
AMF
General Alarm Digital Input Titik 3.00 928,000 2,784,000
Battery Genset Analog Input Titik 3.00 1,677,000 5,031,000
FUEL OIL DAILY TANK
Lo Level Digital Input Titik 3.00 928,000 2,784,000
P POMPA SOLAR
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
XI PEKERJAAN ANTRIAN
Pengadaan dan pemasangan sistem lengkap sesuai
gambar & spesifikasi teknis
2 Instalasi Pipa Tegak Air Hujan dengan Pipa PVC kelas AW 10 kg/cm2 termasuk
gantungan/hanger, support, fitting dan aksesories :
- dia .100 mm m' 66.00 153,900 10,157,400
TOTAL PENGKABELAN -
TOTAL 5,550,344,540
2 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 3.00 936,100 2,808,300
1 GWT
Low Level Alarm Digital Input Titik 2.00 928,000 1,856,000
Deepwell
Status Digital Input Titik 3.00 928,000 2,784,000
Trip Alarm Digital Input Titik 3.00 928,000 2,784,000
WTP PUMP
Status Digital Input Titik 2.00 928,000 1,856,000
Trip Alarm Digital Input Titik 2.00 928,000 1,856,000
2 ROOF TANK
Low Level Alarm Digital Input Titik 2.00 928,000 1,856,000
POMPA BOOSTER
Status Digital Input Titik 3.00 928,000 2,784,000
Trip Alarm Digital Input Titik 3.00 928,000 2,784,000
3 CLEAN GWT
Low Level Alarm Digital Input Titik 2.00 928,000 1,856,000
POMPA TRANSFER
Status Digital Input Titik 4.00 928,000 3,712,000
Trip Alarm Digital Input Titik 4.00 928,000 3,712,000
4 POMPA HYDRANT
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
Battery Diesel Analog Input Titik 1.00 1,677,000 1,677,000
5 P. ABR
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
6 SDP IPAL
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
7 PP IPAL
Status Digital Input Titik 1.00 928,000 928,000
Trip Alarm Digital Input Titik 1.00 928,000 928,000
Power Monitoring HLI Titik 1.00 1,677,000 1,677,000
On off Digital Input Titik 1.00 928,000 928,000
9 FLOW SWITCH
Status Digital Input Titik 17.00 928,000 15,776,000
XI PEKERJAAN ANTRIAN
Pengadaan dan pemasangan sistem lengkap sesuai
gambar & spesifikasi teknis
4 Water Treatment Plant ( Ruang Pompa ) , terdiri dari peralatan : set 1.00 552,832,000 552,832,000
Sistem : Filtration
Kapasitas WTP : 20 m3/ jam
6 Cables 1 lot
Type : NYY - 0,6/1 kV
5 Strainer 10K
- dia. 50 mm bh 6.00 870,450 5,222,700
2 Instalasi Pipa Tegak Air Hujan dengan Pipa PVC kelas AW 10 kg/cm2 termasuk
gantungan/hanger, support, fitting dan aksesories :
- dia .100 mm m' 66.00 153,900 10,157,400
TOTAL 66,389,173
XI PEKERJAAN ANTRIAN
Pengadaan dan pemasangan sistem lengkap sesuai
gambar & spesifikasi teknis
1 Pengadaan dan pemasangan pipa refrigerant ASTM B280 + isolasi lengkap dengan hanger
dan aksesories pendukung lainnya sesuai dengan spesifikasi dan gambar detail
2 Kabel kontrol dari Indoor ke outdoor dengan NYM 3 x 2,5 mm2 m 11.00 15,698 172,678
TOTAL 4,066,539,873
XI PEKERJAAN ANTRIAN
Pengadaan dan pemasangan sistem lengkap sesuai
gambar & spesifikasi teknis
3 Water Treatment Plant , terdiri dari peralatan : set 1.00 146,800,000 146,800,000
a Sand Filter
Type : Pressure Vessel 3 bar
Kapasitas : 6 m³/ jam
Jumlah : 1 unit
lengkap dengan pressure gauge & buterfly valve
b Carbon Filter
Type : Pressure Vessel 3 bar
Kapasitas : 6 m³/ jam
Jumlah : 1 unit
lengkap dengan pressure gauge & buterfly valve
5 Strainer 10K
- dia. 40 mm bh 4.00 668,098 2,672,393
b. Separator
Dimension : P = 420 cm, D = 240 cm
Thickness : 12 mm
Quantity : 1 Unit
Position : Aboveground
Shapes : Silinder Horisontal
Material : FRP
Position : Aboveground
c. Chlorinasi System
Sistem : Dosing Pump
Posisi : Aboveground
Jumlah : 2 Unit
d. Ring Blower
Listrik : 7,5 pk / 3 ph
Jumlah : 2 Unit
e. Input Pump
Listrik : 0,5 pk / 1 ph
Jumlah : 2 Unit
Jenis : Submersible
f. Sludge Pump
Listrik : 0,3 pk / 1 ph
Jumlah : 1 Unit
Jenis : Submersible
g. Flow Meter
Quantity : 1 Unit
Type : Analog
h. Control Panel
2 Waste Water Treatment Plant (WWTP) Laundry set 1.00 269,040,000 269,040,000
Sistem : Chemical Proses
Kapasitas WWTP : 270 Lpm
2 pH Controller 1 unit
Model : RP 1500
Include : ORP Electrode ( Sensor )
7 Cables 1 lot
Type : NYY - 0,6/1 kV
3 Waste Water Treatment Plant (WWTP) Laboratorium set 1.00 445,944,000 445,944,000
Sistem : Kimia Fisika
Kapasitas WWTP : 4 m3/hari
2 pH Controller 1 UNIT
Include : ORP Electrode ( Sensor )
11 Pipes
Class PVC : AW ( 10 kg/cm2 )
12 Cables
Type : NYY - 0,6/1 kV
TOTAL 6,852,083,171
1 Kabel Trench :
- Uk. 1.000 mm x 600 mm m 181.00 Skope Sipil
- Uk. 600 mm x 600 mm m 87.00 Skope Sipil
- Uk. 600 mm x 400 mm m 87.00 Skope Sipil
- Uk. 400 mm x 600 mm m 16.00 Skope Sipil
- Uk. 400 mm x 400 mm m 198.00 Skope Sipil
1 Air Terminal jenis Non radioaktif Radius Perlindungan 100 meter unit 1.00 21,600,000 21,600,000
2 FRP Mast set 1.00 4,800,000 4,800,000
3 Termination Kit set 1.00 5,360,000 5,360,000
4 Pengadaan dan pemasangan Lightning Event Strike Counter (penghitung unit 1.00 4,800,000 4,800,000
sambaran petir)
5 Obstruction Light 300 Watt lengkap dengan Photo Electric Switch set 1.00 4,000,000 4,000,000
6 Batang Penyangga tinggi 20 meter, bahan GIP Medium Class unit 1.00 8,500,000 8,500,000
lengkap dengan angur dan tali pengikat
7 Down Conductor Coaxial Cable 50 mm lengkap dengan klem meter 33.00 708,000 23,364,000
8 Grounding system UNIT 1.00 14,700,000 14,700,000
9 Testing Commissioning ls 1.00 15,000,000 15,000,000
10 Biaya Perijinan Depnaker ls 1.00 25,000,000 25,000,000
2 Instalasi
- Intalasi Kabel UTP Cat 6 dalam Konduit PVC HI 20 mm titik 2.00 936,100 1,872,200
XI PEKERJAAN ANTRIAN
Pengadaan dan pemasangan sistem lengkap sesuai
gambar & spesifikasi teknis
2 Instalasi pipa utama air bersih dari Ruang Pompa ke riser masing-masing gedung
dengan PPR80 - PN10 termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 80 mm m 689.00 241,040 166,076,560
- dia. 65 mm m 142.00 177,620 25,222,040
- dia. 50 mm m 364.00 132,320 48,164,480
3 Instalasi pipa utama air bersih dari Ruang Pompa Hydropur ke riser masing-masing gedung
dengan PPR80 - PN10 termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 50 mm m 1,302.00 132,320 172,280,640
4 Instalasi pipa utama air bersih dari Pompa Hydropur ke dalam bangunan
dengan PPR80 - PN10 termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 65 mm m 79.00 177,620 14,031,980
- dia. 50 mm m 21.00 132,320 2,778,720
5 Instalasi pipa utama air bersih dari PDAM ke GWT masing-masing gedung
dengan PPR80 - PN10 termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 80 mm m 502.00 241,040 121,002,080
8 PRV
- dia. 65 mm bh 4.00 30,141,000 120,564,000
- dia. 50 mm bh 3.00 28,333,000 84,999,000
3 Kran taman bergerigi sesuai gambar lengkap bak kontrol uk. 40 x 40 cm lengkap dengan bh 35.00 Scope Arsitek
tutupnya
Sub Total Pekerjaan instalasi pipa air bersih site plan 97,076,660
5 Strainer 10K
- dia. 50 mm bh 2.00 1,840,650 3,681,300
8 Nozzle
- dia. 32 mm bh 8.00 455,000 3,640,000
- dia. 25 mm bh 3.00 355,000 1,065,000
2 Instalasi Pipa Utama Air Kotor Laundry dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 150 mm m' 141.00 288,460 40,672,860
3 Instalasi Pipa Utama Air Kotor Dapur dengan Pipa PVC kelas AW 10 kg/cm2
termasuk gantungan/hanger, support, fitting dan aksesories :
- dia. 150 mm m' 165.00 288,460 47,595,900
4 Instalasi pipa dari pompa sampai dengan water meterdengan pipa galvanis Medium
5 Gate Valve
- dia 50 mm bh 6.00 1,065,960 6,395,760
6 Bak Kontrol ukuran (60x80) cm dengan tutup chequer plate bh 3.00 3,000,000 9,000,000
7 WLC untuk Sumur dalam + pengkabelan (kabel power dan kabel kontrol) lot 3.00 3,500,000 10,500,000
8 Instalasi pengkabelan pompa deep well dengan kabel NYY 3 x 4 mm2 mtr 300.00 27,773 8,331,900
9 Instalasi kabel kontrol pompa deep well dengan kabel NYYHY 3 x 1,5 mm2 mtr 300.00 15,000 4,500,000
2 Siamese Conection type 2 cabang bahan cast iron lengkap unit 2.00 4,725,000 9,450,000
terpasang
3 Hydrant Box Type Outdoor size ( 95 x 66 x 20) unit 14.00 5,028,555 70,399,770
lengkap dengan ;
- Color : red, oven painted
- 1 PC Hose Nozzle dia. 65 mm
- 1 roll fire house with machino coupling diameter 65 mm x 30 meter
Lengkap terpasang
5 Gate Valve Rising Steam (OS & Y) class 16 K lengkap dengan bak kontrol:
- dia. 100 mm bh 14.00 9,688,697 135,641,751
7 Galian dan urugan untuk pemasangan pipa dalam tanah m3 1,396.08 75,000 104,706,000
1 Testing & Commissioning Instalasi dan Peralatan Fire Hydrant & Sprinkler, lot 1.00 2,500,000 2,500,000
Extinguisher termasuk pengurusan ijin dari dinas terkait