Lokasi : Desa Lolanan Kecamatan Sangtombolang Tahun : 2022
Rincian Pendanaan :
HARGA SATUAN JUMLAH
NO URAIAN VOLUME Rp. Rp. I Bahan 3 1 Pasir 0.65 m 249.000.00 162.700.00 3 2 Kerikil 0.87 m 302.500.00 264.300.00 3 Semen Portland 50 kg 7.68 Zak 69.300.00 532.300.00 4 Paku Seng 1.96 Lbr 41.250.00 80.800.00 5 Seng Spandek 74.80 Lbr 72.000.00 5.385.600.00 6 Baja Ringan Canai Dingin C75 47.26 Ujg 120.000.00 5.670.700.00 7 Papan Proyek 1.00 Ls 200.000.00 200.000.00 Sub Total 1) 12.296.400.00 II Alat 1 2 Sub Total 2) - III Upah 1 Pekerja 90.46 OH 100.000.00 9.045.600.00 2 Tukang 82.93 OH 150.000.00 12.440.100.00 3 Kepala Tukang 8.25 OH 160.000.00 1.320.300.00 Sub Total 3) 22.806.000.00 Jumlah (Rp.) 35.102.400.00 Operasional TPK 3 % 1.054.000.00 Total Anggaran (Rp.) 36.156.400.00