PT TIWANA ELECTRIKAL TEKNIK

INSTALATIR LISTRIK PLN


JL. A. MALLA PERUMNAS TIBOJONG BLOK C NO. 51 HP. 085242496400

RENCANA ANGGARAN BIAYA PENAMBAHAN DAYA DARI P1-82.500 MENJADI P1-131.000 VA


GEDUNG PICU NICU RSUD DATU PANCAITANA
JL. GATOT SUBROTO

NO URAIAN SATUAN HARGA

1 BIAYA PENYAMBUNGAN (BP) 969 X 48.500 46,996,500


2 UANG JAMINAN LANGGANAN (UJL) 165 X 131.000 21,615,000
3 BIAYA SLO 550 X 48.500 26,675,000
4 BIAYA GIL 850 X 48.500 41,275,000
5 JASA PEKERJAAN 25,000,000
JUMLAH 161,561,500
PPN + PPH (12,5%) 16,156,150
JUMLAH TOTAL 177,717,650

LUH ENAM JUTA DUA RATUS DELAPAN PULUH DUA RIBU


TERBILANG : LIMA RATUS RUPIAH

WATAMPONE, 05 FEBRUARI 2023

PT. TIWANA ELECTRIKAL TEKNIK

MUH. SHUBRI DEA


DIREKTUR
PT TIWANA ELECTRIKAL TEKNIK
INSTALATIR LISTRIK PLN
JL. A. MALLA PERUMNAS TIBOJONG BLOK C NO. 51 HP. 085242496400

RENCANA ANGGARAN BIAYA PENAMBAHAN DAYA DARI P1-82.500 MENJADI P1-131.000 VA


GEDUNG PICU NICU RSUD DATU PANCAITANA
JL. GATOT SUBROTO

NO URAIAN SATUAN HARGA

1 BIAYA PENYAMBUNGAN (BP) 969 X 64.500 62,500,000


2 UANG JAMINAN LANGGANAN (UJL) 165 X 147.000 24,000,000
3 BIAYA SLO 500 X 64.500 32,250,000
4 BIAYA GIL 550 X 64.500 35,475,000
5 JASA PEKERJAAN 27,000,000
JUMLAH 181,225,000
PPN + PPH (12,5%) 18,122,500
JUMLAH TOTAL 199,347,500

TERBILANG : SERATUS SEMBILAN PULUH SEMBILAN JUTA TIGA RATUS EMPAT


TERBILANG : PULUH TUJUH RIBU LIMA RATUS RUPIAH

WATAMPONE, 16 FEBRUARI 2023

PT. TIWANA ELECTRIKAL TEKNIK

MUH. SHUBRI DEA


DIREKTUR
40000
26000
500 64500 18000
550 64500 31000
2000
26000
143000