INSTRUKSI KERJA

PENGGANTIAN RELE AVR


GI 150 KV MANYAR BAY TRAFO 2

PT SURYA PRIMA ELTRINDO

PT SURYA PRIMA ELTRINDO


Head Office :
Taman Palem Lestari, Komplek Ruko Galaxy Blok Q 1-2
Jl. Kamal Raya Outer Ring Road, Cengkareng – Jakarta 11730
Telp : (62-21) 5595 7594 (Hunting) Fax : (62-21) 5596 0038

Unrestricted
PT SURYA PRIMA ELTRINDO
Head Office : PT PLN (Persero)
Taman Palem Lestari, Komplek Ruko Galaxy Blok Q 1-2 UNIT INDUK TRANSMISI JAWA
Jl. Kamal Raya Outer Ring Road, Cengkareng – Jakarta BAGIAN TIMUR DAN BALI
Telp : (62-21) 5595 7594 (Hunting) Fax : (62-21) 5596 0038
INSTRUKSI KERJA PENGGANTIAN RELE AVR GI 150 KV MANYAR No. Kontrak 003.PJ/DAN.01.03/C36060000/2022
BAY TRAFO 2
Tanggal 29 Juni 2022

I. Lembar Pengesahan

NAMA UNIT TANDA TANGAN TANGGAL

NUR AZIZ

DIBUAT
OLEH SAEPUL ROHIM

M RIZAL

DIPERIKSA
OLEH

DISAHKAN
OLEH

Unrestricted 1
PT SURYA PRIMA ELTRINDO
Head Office : PT PLN (Persero)
Taman Palem Lestari, Komplek Ruko Galaxy Blok Q 1-2 UNIT INDUK TRANSMISI JAWA
Jl. Kamal Raya Outer Ring Road, Cengkareng – Jakarta BAGIAN TIMUR DAN BALI
Telp : (62-21) 5595 7594 (Hunting) Fax : (62-21) 5596 0038
INSTRUKSI KERJA PENGGANTIAN RELE AVR GI 150 KV MANYAR No. Kontrak 003.PJ/DAN.01.03/C36060000/2022
BAY TRAFO 2
Tanggal 29 Juni 2022

II. Daftar Isi

Contents
I. Lembar Pengesahan ....................................................................................................................... 1
II. Daftar Isi ........................................................................................................................................... 2
III. Instruksi Kerja Penggantian Rele AVR GI MANYAR Bay Trafo 2 ..................................................... 3
1. Tujuan ............................................................................................................................................................... 3
2. Analisa resiko .................................................................................................................................................... 3
3. Antisipasi resiko ................................................................................................................................................ 3
4. Ruang Lingkup .................................................................................................................................................. 4
5. Referensi ........................................................................................................................................................... 4
6. Definisi dan Istilah ............................................................................................................................................ 4
7. Informasi Umum ............................................................................................................................................... 5
8. Peralatan Kerja dan Perlengkapan K3 ............................................................................................................... 5
8.1. Alat Kerja...................................................................................................................................................... 5
8.2. Perlengkapan K3 ........................................................................................................................................... 6
9. Persiapan Pekerjaan........................................................................................................................................... 6
10. Langkah-Langkah Pengamanan ........................................................................................................................ 6
11. Pelaksanaan Pekerjaan ...................................................................................................................................... 7
11.1. Pengukuran Tegangan DC sebelum memulai pekerjaan ................................................................................... 7
11.2. Dismantling AVR eksisting merk Alstom tipe MVGC01 ................................................................................. 7
11.3. Instalasi AVR baru ABB tipe REU615 ............................................................................................................. 7
12. PENORMALAN ............................................................................................................................................... 8
13. DOKUMENTASI ............................................................................................................................................. 8
14. CATATAN KHUSUS (JIKA ADA) ................................................................................................................. 8
15. LAMPIRAN ...................................................................................................................................................... 9

Unrestricted 2
PT SURYA PRIMA ELTRINDO
Head Office : PT PLN (Persero)
Taman Palem Lestari, Komplek Ruko Galaxy Blok Q 1-2 UNIT INDUK TRANSMISI JAWA
Jl. Kamal Raya Outer Ring Road, Cengkareng – Jakarta BAGIAN TIMUR DAN BALI
Telp : (62-21) 5595 7594 (Hunting) Fax : (62-21) 5596 0038
INSTRUKSI KERJA PENGGANTIAN RELE AVR GI 150 KV MANYAR No. Kontrak 003.PJ/DAN.01.03/C36060000/2022
BAY TRAFO 2
Tanggal 29 Juni 2022

III. Instruksi Kerja Penggantian Rele AVR GI MANYAR Bay Trafo 2

1. Tujuan

Instruksi Kerja ini dibuat sebagai petunjuk pelaksanaan pekerjaan penggantian rela AVR
GI 150 kV MANYAR bay Trafo 2. Pekerjaan dilaksanakan dalam kondisi bebas tegangan
(Padam).

2. Analisa resiko

Resiko yang dimungkinkan timbul akibat aktifitas tersebut, adalah :


a. Pekerjaan ini berpotensi menimbulkan padam meluas pada subsistem GI MANYAR
saat melaksanakan proses pekerjaan.
b. Pekerjaan ini berpotensi menimbulkan kerusakan pada peralatan di sisi sekunder
saat melakukan pengujian.
c. Pekerjaan ini berpotensi menimbulkan kecelakaan pekerja pada saat kelalaian
menggunakan APD.

No AKTIVITAS RESIKO DAMPAK MITIGASI

1 Mengukur Trip pada Hilang Supply Melakukan


Polaritas DC MCB DC tegangan DC isolasi pada
Supply ujung ujung
AVO Meter

2 Dismaintling Short Trip pada bay Selalu


relay existing circuit yang melakukan
bertegangan isolasi pada
kabel yang
dilepas

3 Terminasi pada Kesalahan AVR tidak Mencocokan


AVR ABB terminasi berfungsi gambar
REU615 sebagaimana existing
mestinya dengan
terminasi
yang baru

3. Antisipasi resiko

a. Berkoordinasi dengan team jalur terkait pekerjaan dengan kondisi padam.


b. Pembuatan cable schedule sesuai dengan schematic eksisting.
c. Pemasangan tagging di bay yang dikerjakan untuk memisahkan area aman dan
area berbahaya.
d. Melaksanakan pekerjaan sesuai dengan Instruksi Kerja yang telah disepakati.
e. Memastikan bahwa pekerjaan sudah dalam keadaan aman dengan berkoordinasi
dengan Pengawas Pekerjaan dan Pengawas K3.
f. Pada saat pelaksanaan pekerjaan selalu menggunakan APD lengkap.

Unrestricted 3
PT SURYA PRIMA ELTRINDO
Head Office : PT PLN (Persero)
Taman Palem Lestari, Komplek Ruko Galaxy Blok Q 1-2 UNIT INDUK TRANSMISI JAWA
Jl. Kamal Raya Outer Ring Road, Cengkareng – Jakarta BAGIAN TIMUR DAN BALI
Telp : (62-21) 5595 7594 (Hunting) Fax : (62-21) 5596 0038
INSTRUKSI KERJA PENGGANTIAN RELE AVR GI 150 KV MANYAR No. Kontrak 003.PJ/DAN.01.03/C36060000/2022
BAY TRAFO 2
Tanggal 29 Juni 2022

4. Ruang Lingkup

Instruksi kerja ini meliputi aktivitas pelaksanakan pekerjaan :

1. Pembongkaran rele AVR eksisting (F90) merk Alstom tipe MVGC beserta Test Block
(x40.1), posisi di panel meter eksisting Trafo 2.

Tampak depan Tampak belakang

2. Penambahan plat besi ukuran 200x240 mm untuk dudukan relay AVR baru.
3. Pemasangan rele baru merk ABB tipe REU615 di panel meter eksisting Trafo 2.
4. Pemasangan test block merk Alstom tipe MMLG01 di panel meter eksisting Trafo 2.
5. Wiring koneksi AVR baru ke terminal eksisting.
6. Pengujian individu sesuai dengan setting dari PT PLN (Persero) dilakukan sebelum
proses pemadaman.
7. Uji fungsi rele AVR.

5. Referensi

1. Manual book AVR ABB


2. Single line diagram GI 150 kV MANYAR
3. Schematic diagram eksisting GI MANYAR bay Trafo 2

6. Definisi dan Istilah

DS Disconnecting Switch
ES Earthing Switch
CB Circuit Breaker
CT Current Transformer
CVT Capacitor Voltage Transformer (Outdoor)
LA Lightning Arrester
BB Busbar

Unrestricted 4
PT SURYA PRIMA ELTRINDO
Head Office : PT PLN (Persero)
Taman Palem Lestari, Komplek Ruko Galaxy Blok Q 1-2 UNIT INDUK TRANSMISI JAWA
Jl. Kamal Raya Outer Ring Road, Cengkareng – Jakarta BAGIAN TIMUR DAN BALI
Telp : (62-21) 5595 7594 (Hunting) Fax : (62-21) 5596 0038
INSTRUKSI KERJA PENGGANTIAN RELE AVR GI 150 KV MANYAR No. Kontrak 003.PJ/DAN.01.03/C36060000/2022
BAY TRAFO 2
Tanggal 29 Juni 2022

7. Informasi Umum

GI MANYAR mempunyai 12 bay, diantaranya:


 Bay Trafo 150/20 kV : 4 bay
 Bay Trafo IBT 150/70 kV : 2 bay
 Bay line : 4 bay
 Bay SKTT : - bay
 Bay Kopel : 1 bay
 Bay Kapasitor : 1 bay

8. Peralatan Kerja dan Perlengkapan K3

8.1. Alat Kerja


 Alat uji relay 3 phasa
 Tools Set
 Multimeter
 Ampere clamp
 Gerinda
 Bor tangan
 Kabel Roll
 Printer marker
 Grounding local (bila diperlukan)

Unrestricted 5
PT SURYA PRIMA ELTRINDO
Head Office : PT PLN (Persero)
Taman Palem Lestari, Komplek Ruko Galaxy Blok Q 1-2 UNIT INDUK TRANSMISI JAWA
Jl. Kamal Raya Outer Ring Road, Cengkareng – Jakarta BAGIAN TIMUR DAN BALI
Telp : (62-21) 5595 7594 (Hunting) Fax : (62-21) 5596 0038
INSTRUKSI KERJA PENGGANTIAN RELE AVR GI 150 KV MANYAR No. Kontrak 003.PJ/DAN.01.03/C36060000/2022
BAY TRAFO 2
Tanggal 29 Juni 2022

8.2. Perlengkapan K3
 Pakaian kerja.
 Sepatu safety.
 Safety helmet.
 Rambu-rambu.
 Tagging/Barricade.
 Masker.
 Handsanitizer.

9. Persiapan Pekerjaan

b. Memastikan WP sudah mendapatkan ijin dari PLN (Persero) UPT Gresik.


c. Memasang safety line pada area kerja.
d. Persiapkan personil, alat ukur dan dan accessories lainnya serta yakinkan
semuanya dalam kondisi baik.
e. Memasang tagging (LOTO) di bay yang akan dikerjakan dan juga di bay yang ada
disebelah bay yang tidak dikerjakan.
f. Breafing dilakukan sebelum pekerjaan dimulai.
g. Langkah pengamanan selama pekerjaan berlangsung.
h. Pengawas pekerjaan dan pengawas K3 selalu berada di daerah kerja.
i. Pelaksana pekerjaan agar mematuhi rambu dan IK yang ada.

10. Langkah-Langkah Pengamanan

a. Safety Breafing
b. Pemasangan grounding local (jika diperlukan)
c. Pasang tagging area kerja aman dan area berbahaya.

Unrestricted 6
PT SURYA PRIMA ELTRINDO
Head Office : PT PLN (Persero)
Taman Palem Lestari, Komplek Ruko Galaxy Blok Q 1-2 UNIT INDUK TRANSMISI JAWA
Jl. Kamal Raya Outer Ring Road, Cengkareng – Jakarta BAGIAN TIMUR DAN BALI
Telp : (62-21) 5595 7594 (Hunting) Fax : (62-21) 5596 0038
INSTRUKSI KERJA PENGGANTIAN RELE AVR GI 150 KV MANYAR No. Kontrak 003.PJ/DAN.01.03/C36060000/2022
BAY TRAFO 2
Tanggal 29 Juni 2022

11. Pelaksanaan Pekerjaan

11.1. Pengukuran Tegangan DC sebelum memulai pekerjaan

No. Pekerjaan PT PLN PT SPE


1. Sebelum melakukan pembongkaran relay eksisting,
lakukan pengukuran tegangan DC
Positive - Negative X5.11 - X5.13 …. VDC
Positive – Ground X5.11 - G …. VDC
Negative – Ground X5.13 - G …. VDC

11.2. Dismantling AVR eksisting merk Alstom tipe MVGC01


No. Pekerjaan PT PLN PT SPE
1. Matikan sumber DC pada panel proteksi Trafo 2
2. Pelepasan wiring eksisting AVR merk Alstom tipe
MVGC01, sesuai dengan cable schedule. Isolasi kabel
yang dilepas dari terminal.
3. Pembongkaran AVR eksisting merk Alstom pada panel
Meter Trafo 2
4. Cable schedule
TERM AVR TEST AVR
FUNGSI
EKS EKS BLOCK BARU
K4801.12 13 X90.13/14 X100.1 SUPPLY +110 VDC
-C 14 X90.15/16 X100.2 SUPPLY -110 VDC
X28.1 17 X90.21/22 X120.1 VT PH R
X28.2 - X90.23/24 X120.3 VT PH S
X28.3 18 X90.25/26 X120.5 VT PH T
X28.4 - X90.27/28 X120.6 VT PH N
X18.1 - X90.1/2 X120.7 CT PH R
X18.2 27/28 X90.3/4 X120.9 CT PH S
X18.3 - X90.5/6 X120.11 CT PH T
X18.4 - X90.7/8 X120.12 CT PH N
X5.30 3 X90.9/10 X100.6 LOWER COMMAND
K4201.1 5 X90.17/18 X100.7
X5.30 3 X90.9/10 X100.8 RAISE COMMAND
K4202.1 1 X90.19/20 X100.9
X3.163 - - X110.17 OVER VOLTAGE
F100.F6 - - X110.18 OPERATED
X3.164 - - X110.23 UNDER VOLTAGE
F100.F7 - - X110.24 OPERATED

11.3. Instalasi AVR baru ABB tipe REU615


No. Pekerjaan PT PLN PT SPE
1. Pemasangan plat modifikasi untuk dudukan relay AVR

Unrestricted 7
PT SURYA PRIMA ELTRINDO
Head Office : PT PLN (Persero)
Taman Palem Lestari, Komplek Ruko Galaxy Blok Q 1-2 UNIT INDUK TRANSMISI JAWA
Jl. Kamal Raya Outer Ring Road, Cengkareng – Jakarta BAGIAN TIMUR DAN BALI
Telp : (62-21) 5595 7594 (Hunting) Fax : (62-21) 5596 0038
INSTRUKSI KERJA PENGGANTIAN RELE AVR GI 150 KV MANYAR No. Kontrak 003.PJ/DAN.01.03/C36060000/2022
BAY TRAFO 2
Tanggal 29 Juni 2022

baru merk ABB.


2. Pemasangan AVR baru pada plat yang telah terpasang di
panel.
3. Wiring AVR baru sesuai cable schedule yang telah dibuat.
4. Pengecekan koneksi dan continuity rangkaian sesuai
dengan cable schedule.
5. Nyalakan supply DC. Sebelum power On supply DC,
pastikan wiring aman & tidak ada short circuit.
6. Setting & uji individu AVR baru.
7. Uji fungsi AVR baru.

12. PENORMALAN

a. Memastikan kekencangan terminasi.


b. Pengukuran tegangan setelah selesai pekerjaan.

Positive - Negative …. VDC


Positive – Ground …. VDC
Negative – Ground …. VDC

c. Pelepasan grounding local (jika diperlukan)


d. Pelepasan tagging area kerja dan area berbahaya.
e. Koordinasi dengan pengawas pekerjaan bahwa pekerjaan telah selesai dilaksanakan.

13. DOKUMENTASI

a. Instruksi Kerja ini didokumentasikan dalam bentuk hard copy dan soft copy
b. Foto pelaksanaan pekerjaan

14. CATATAN KHUSUS (JIKA ADA)


a) Pastikan setelah selesai wiring terminal yang sudah dikonek diukur dengan AVO
meter.
b) Untuk nomor kabel agar diberi tanda/marker nomor kabel untuk mempermudah
pada saat ada trouble shooting.

Unrestricted 8
PT SURYA PRIMA ELTRINDO
Head Office : PT PLN (Persero)
Taman Palem Lestari, Komplek Ruko Galaxy Blok Q 1-2 UNIT INDUK TRANSMISI JAWA
Jl. Kamal Raya Outer Ring Road, Cengkareng – Jakarta BAGIAN TIMUR DAN BALI
Telp : (62-21) 5595 7594 (Hunting) Fax : (62-21) 5596 0038
INSTRUKSI KERJA PENGGANTIAN RELE AVR GI 150 KV MANYAR No. Kontrak 003.PJ/DAN.01.03/C36060000/2022
BAY TRAFO 2
Tanggal 29 Juni 2022

15. LAMPIRAN

Unrestricted 9
PT SURYA PRIMA ELTRINDO
Head Office : PT PLN (Persero)
Taman Palem Lestari, Komplek Ruko Galaxy Blok Q 1-2 UNIT INDUK TRANSMISI JAWA
Jl. Kamal Raya Outer Ring Road, Cengkareng – Jakarta BAGIAN TIMUR DAN BALI
Telp : (62-21) 5595 7594 (Hunting) Fax : (62-21) 5596 0038
INSTRUKSI KERJA PENGGANTIAN RELE AVR GI 150 KV MANYAR No. Kontrak 003.PJ/DAN.01.03/C36060000/2022
BAY TRAFO 2
Tanggal 29 Juni 2022

Unrestricted 10
PT SURYA PRIMA ELTRINDO
Head Office : PT PLN (Persero)
Taman Palem Lestari, Komplek Ruko Galaxy Blok Q 1-2 UNIT INDUK TRANSMISI JAWA
Jl. Kamal Raya Outer Ring Road, Cengkareng – Jakarta BAGIAN TIMUR DAN BALI
Telp : (62-21) 5595 7594 (Hunting) Fax : (62-21) 5596 0038
INSTRUKSI KERJA PENGGANTIAN RELE AVR GI 150 KV MANYAR No. Kontrak 003.PJ/DAN.01.03/C36060000/2022
BAY TRAFO 2
Tanggal 29 Juni 2022

Unrestricted 11
PT SURYA PRIMA ELTRINDO
Head Office : PT PLN (Persero)
Taman Palem Lestari, Komplek Ruko Galaxy Blok Q 1-2 UNIT INDUK TRANSMISI JAWA
Jl. Kamal Raya Outer Ring Road, Cengkareng – Jakarta BAGIAN TIMUR DAN BALI
Telp : (62-21) 5595 7594 (Hunting) Fax : (62-21) 5596 0038
INSTRUKSI KERJA PENGGANTIAN RELE AVR GI 150 KV MANYAR No. Kontrak 003.PJ/DAN.01.03/C36060000/2022
BAY TRAFO 2
Tanggal 29 Juni 2022

Unrestricted 12
PT SURYA PRIMA ELTRINDO
Head Office : PT PLN (Persero)
Taman Palem Lestari, Komplek Ruko Galaxy Blok Q 1-2 UNIT INDUK TRANSMISI JAWA
Jl. Kamal Raya Outer Ring Road, Cengkareng – Jakarta BAGIAN TIMUR DAN BALI
Telp : (62-21) 5595 7594 (Hunting) Fax : (62-21) 5596 0038
INSTRUKSI KERJA PENGGANTIAN RELE AVR GI 150 KV MANYAR No. Kontrak 003.PJ/DAN.01.03/C36060000/2022
BAY TRAFO 2
Tanggal 29 Juni 2022

Unrestricted 13