3 Mengamati perancah keseluruhan. Apakah layak untuk digunakan sesuaI dengan pekerjaan?
10 Jika tidak ada sistem pagar pembatas, pekerja terlindung dengan alat pelindung jatuh?
13 Jika tidak ada ikatan, adalah tinggi untuk rasio dasar kurang dari 4 to1? Titik ikatan/tie off
30 Inspect the ties. Can they resist both tension and compression loads?
31 Is the scaffold tied to the structure at proper intervals?
32 How do the platforms look?
33 Are all platforms at least 18 inches wide?
Is the space between the platform and the work surface less than 14 inches? (18
34
inches for plastering and lathing)
35 If the space is more than 14 inches (18 inches), is fall protection provided?
What is the maximum spacing between plank? (It should be less than 1” unless
36
you can show otherwise.)
Is the maximum space between the platform and the guardrail system less than
37
9-1/2”?
38 Are the spans of the plank consistent with the strength of the plank?
39 Is there proper support for the plank?
40 Is the plank overhang sufficient? (6”min, 12” or 18” max)
41 Is the overlap of the plank sufficient? (12” minimum)
42
If the overhang or overlap is insufficient, are the plank secure from movement?
43 Are the plank secured from uplift?
44 Are cantilevers minimized and within the regulations?
45 Is the scaffold tagged in any way that would limit the use?
46
Are there any electrical lines that might energize the scaffold? (and the workers!)
47 If side brackets are used, are they properly installed?
48 Are the side brackets used only to support workers, not materials?
49 Are all scaffold components in good condition?
50 Are the materials loaded on the scaffold safely supported?
51 Is the scaffold overloaded?
Are the users of the scaffold trained in the recognition of electrical, fall, and falling
52
object hazards?
53
7 Apakah sistem pagar pembatas diinstal (handrail)pada semua ujung & platform terbuka?