METODE PELAKSANAAN

PENGECORAN LANTAI GEDUNG EL.4000


ANCILLIARY BUILDING
No. Doc : EKKN/AB/ Sunshine / IV-2022 / 001
Rev No : 0.00
Page 1

ANCILLIARY BUILDING

PT.UNILEVER OLEO CHEMICAL INDONESIA SEI MANGKE

KONTRAKTOR : PT.ERA KARYA KONSTRUKSI NUSANTARA

NOMOR : EKKN / WM / Sun Shine / IV-2022 / 001

Revisi No. : 0.0

TANGGAL PENGAJUAN : 26 April 2022

TANGGAL PELAKSANAAN : 5 Mei 2022

ESTIMASI WAKTU KERJA : 28 Hari

AREA KERJA : Ancilarry Building – Betaine Plant 9-ha

Pembuat Dokumen, Reviewer SHE


Site Manager SHE Officer Engineer PT. Safety PT. UOI Departement
PT.EKKN PT. EKKN UOI Head

Tanda tangan

Nama
Tanggal

1. Survey & Assesment Area Kerja

PT. ERAKARYA KONTRUKSI NUSANTARA


METODE PELAKSANAAN
PENGECORAN LANTAI GEDUNG EL.4000
ANCILLIARY BUILDING
No. Doc : EKKN/AB/ Sunshine / IV-2022 / 001
Rev No : 0.00
Page 2 a.

L
ay Out Area Kerja
Gambar 1 (Kondisi Lapangan )

Gambar 2 (Lay Out Area Kerja)

Gambar 3 (Design Scafolding Tampak Atas)

PT. ERAKARYA KONTRUKSI NUSANTARA


METODE PELAKSANAAN
PENGECORAN LANTAI GEDUNG EL.4000
ANCILLIARY BUILDING
No. Doc : EKKN/AB/ Sunshine / IV-2022 / 001
Rev No : 0.00
Page 3

Gambar 4 (Design Scafolding Tampak Samping)

PT. ERAKARYA KONTRUKSI NUSANTARA


METODE PELAKSANAAN
PENGECORAN LANTAI GEDUNG EL.4000
ANCILLIARY BUILDING
No. Doc : EKKN/AB/ Sunshine / IV-2022 / 001
Rev No : 0.00
Page 4

b. Assesment Area Kerja


 Area kerja merupakan gedung ancilary yang digunakan untuk operasional Betaine Plant 9-ha
 Akan dilakukan pengecoran lantai 1,2, dan 3 Roof Top

PT. ERAKARYA KONTRUKSI NUSANTARA


METODE PELAKSANAAN
PENGECORAN LANTAI GEDUNG EL.4000
ANCILLIARY BUILDING
No. Doc : EKKN/AB/ Sunshine / IV-2022 / 001
Rev No : 0.00
Page 5

 Setiap lantai memiliki bobot + 200 Ton


 Dilakukan perhitunagan dan design scafolding penyokong lantai pada saat pengecoran.

Assesment area kerja dilakukan oleh :

 Eng. PT.EKKN : _______________________ _________

 SHE PT.EKKN : _______________________ _________

 SHE PT.UOI : _______________________ _________

 Eng.PT.UOI : _______________________ _________

 Dep. Head SHE PT.UOI : _______________________ _________

Catatan :
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________

2. Informasi Beban
a. Balok / Beam
Dimensi = 0,38 m x 0,25 m x 147,9

PT. ERAKARYA KONTRUKSI NUSANTARA


METODE PELAKSANAAN
PENGECORAN LANTAI GEDUNG EL.4000
ANCILLIARY BUILDING
No. Doc : EKKN/AB/ Sunshine / IV-2022 / 001
Rev No : 0.00
Page 6

Volume = 14,05 m3
Bobot / Meter = 2,4 Ton / m3
Total Beban = 33,72 Ton

b. Lantai
Dimensi = 0,12 m x 12 m x 25,32 m
Volume = 36,46 m3
Bobot = 2,4 Ton / m3
Total Beban = 87,5 Ton

c. Mal / Bekisting
Volume = 5 m3
Bobot = + 300 Kg / m3
Total Beban = 1,5 Ton

d. Beban Hidup ( Pekerja dan Alat )


Pekerja 10 Orang = 600 Kg
Vibrator 2 Unit = 60 Kg
Hand Tools = 50 Kg
Total Beban = 0,71 Ton

3. Informasi Penopang Beban


a. Kolom Gedung
Dimensi = 50 cm x 25 cm x 400 cm
Jumlah = 20 Kolom
Daya Dukung = 90 Ton / Kolom Tiang Pancang ( Dari Hasil PDA Test )
Total Daya Dukung = 1800 Ton

b. Scafolding
Dimensi = 3,5 m x 13 m x 26 m
Luasan = 338 m2

PT. ERAKARYA KONTRUKSI NUSANTARA


METODE PELAKSANAAN
PENGECORAN LANTAI GEDUNG EL.4000
ANCILLIARY BUILDING
No. Doc : EKKN/AB/ Sunshine / IV-2022 / 001
Rev No : 0.00
Page 7

Jumlah = 237 Set


Daya Dukung = 500 Kg / Set
Total Daya Dukung = 118 Ton

4. Perhitungan Safety Factor Penopang Lantai


a. Beban
Beam = 33,72 Ton
Lantai = 87,5 Ton
Mal = 1,5 Ton
Pekerja = 0,71 Ton
Total 123,43 Ton

b. Daya Penopang Lantai


Kolom = 1800 Ton
Scafolding = 118 Ton
Total 1.918 Ton

c. Persentase Safety Factor Penopang Lantai


SF % = Beban x 100
Daya

SF % = 123, 43 Ton x 100


1,918 Ton

SF = 6,43 % dari kapasitas daya penopang lantai

5. Tahapan Pekerjaan
 Melakukan pre job analisa mengenai perhitungan beban dan kapasitas daya penopang
lantai.
 Membuat design scafolding dan mengajukan ke konsultan dan PT. UOI.

PT. ERAKARYA KONTRUKSI NUSANTARA


METODE PELAKSANAAN
PENGECORAN LANTAI GEDUNG EL.4000
ANCILLIARY BUILDING
No. Doc : EKKN/AB/ Sunshine / IV-2022 / 001
Rev No : 0.00
Page 8

 Melakukan inspeksi scaffolding frame yang akan di gunakan.


 Melakukan instalasi scaffolding.
 Melakukan pemeriksaan hasil instal sacaffolding.
 Melakukan leveling jack base dan U head sesuai kebutuhan di lapangan.
 Melakukan pemasangan lifeline untuk pekerja.
 Pemasangan bakisting beam / balok.
 Melakukan pemasangan besi beton yang telah di fabrikasi di workshop.
 Melakukan perkuatan bakesting.
 Melakukan pemeriksaan bakesting dan besi beton.
 Melakukan pengecoran manual dengan menggunakan timba.
 Setelah 24 jam bongkar satu sisi bakisting bagian dalam.
 Melakukan pemasangan gelagar sebagai dudukan bakisting lantai.
 Pemasangan bakisting lantai.
 Melakukan perkuatan bakisting lantai.
 Instal besi beton.
 Melakukan pemeriksaan bersama.
 Melakukan pengecoran menggunakan concrete pump.