DAFTAR HARGA SATUAN BAHAN DAN UPAH PEKERJAAN

Instansi : Dinas Pendapatan Daerah Prov. Sul-Sel


Pekerjaan : Pekerjaan Instalasi Listrik LCD di Bandara Sultan Hasanuddin
Tahun Anggaran : APBD PERUBAHAN 2012

A. UPAH Harga Sat


1 Mandor Rp. 100,000.00 /Oh
2 Kepala Tukang Rp. 85,000.00 /Oh
3 Tukang Rp. 75,000.00 /Oh
4 Pekerja Rp. 50,000.00 /Oh
B BAHAN Harga Sat
1 Panel SDP Rp. 17,500,000.00 BH
2 Panel 40 / 60 Rp. 8,500,000.00 BH
3 Panel P / LP - 4 Rp. 5,700,000.00 BH
4 Panel box KWH Rp. 270,000.00 BH
5 Kabel NYY 4 x 120mm + Nya 16mm Rp. 550,000.00 M
6 Kabel NYY 4 x 35mm + Nya 16mm Rp. 250,000.00 M
7 Kabel NYY 4 x 35mm Rp. 185,000.00 M
8 Kabel NYY 4 x 25 mm Rp. 125,000.00 M
9 Kabel LTVC 3X 35+50mm Rp. 75,000.00 M
10 Lampu RM ACR TL 2 x 18 Watt Rp. 75,000.00 BH
11 Down Light SL 18 Watt Rp. 315,000.00 BH
12 Stop Kontak 10 A 1P Rp. 75,000.00 BH
13 Saklar tunggal Rp. 19,300.00 BH
14 Saklar Seri Rp. 25,300.00 BH
15 Radar Otomatis Rp. 1,250,000.00 BH
15 Pipa PVC 3/4" Rp. 28,000.00 Btg
16 Pipa PVC 1" Rp. 30,000.00 Btg
17 Pipa PVC 1.5" Rp. 32,000.00 Btg
18 ARDE/Pentanahan 4mm Rp. 135,000.00 Set
19 OKI (LMK) Rp. 150,000.00 Bh
20 Terminal Legrand Rp. 120,000.00 Btg
21 Suspension/Small Angel Assembly Rp. 50,000.00 Set
22 Isolasi Unibel Rp. 15,000.00 Rol
23 Fixed Dead End Assembly Rp. 65,000.00 Set
24 Pasir Rp. 350,000.00 M3
25 Batu Merah Rp. 450.00 Bj
24 Conector Rp. 25,000.00 BH

Makassar 25 Oktober 2012


CV. Nur Fadilla

Zaldy Syahruddin
Direktur

Anda mungkin juga menyukai