PEMERINTAH KABUPATEN BREBES

DINAS PEKERJAAN UMUM


Jalan Jend. Sudirman No. 129 Telp ( 0283 ) 671721 Brebes

DAFTAR HARGA SATUAN PEKERJAAN


PROPINSI : JAWA TENGAH TAHUN ANGGARAN : ----
KABUPATEN : BREBES

NO. URAIAN PEKERJAAN KODE SATUAN JUMLAH HARGA (RP)

1 PENYEDIAAN KERIKIL SUNGAI (TIDAK DISARING) K.013 m3 151,851.41


2 PRODUKSI KERIKIL SUNGAI (TERSARING) K.016 m3 198,800.88
3 PRODUKSI KERIKIL PECAH TERSARING (ALAT) K.017 m3 209,334.22
4 PRODUKSI BATU PECAH TERSARING (ALAT) K.018 m3 291,371.45
5 MEMPRODUKSI CAMPURAN LATASIR K.020 ton 1,016,273.00
6 MEMPRODUKSI CAMPURAN ASPAL BETON UNTUK LAPIS PONDASI ATAS K.026 ton 706,203.88
7 (LASTA ATAS) Menggunakan Buruh K.026.A ton 792,997.61
8 MEMBUAT PARIT GALIAN TANAH K.110 m3 22,333.33
9 MEMBUAT PASANGAN BATU PADA PARIT GALIAN TANAH K.112 m` 253,240.82
10 MENGUPAS DAN MEMBERSIHKAN SEMAK PADA DAMIJA K.210 m2 1,340.00
11 MENGGANGKUT TANAH UNTUK GALIAN DIPADATKAN K.220 m3 168,083.70
12 PENIMBUNAN DAN PEMADATAN (tanah urug pilihan) K.225.A m3 152,449.69
13 PENIMBUNAN DAN PEMADATAN(Kerikil Berpasir Alami) K.225 m3 184,449.69
14 MEMBENTUK BADAN JALAN/SUB GRADE DNG TIMBUNAN K.310 m3 168,778.48
15 MEMBENTUK BADAN JLN (GALIAN TANAH, MENGANGKUT DAN MEMBUANG HASIL GALIAN) K.320 m3 84,025.91
16 MEMBENTUK BADAN JLN/SUBGRADE DNG TIMBUNAN K.341 m2 88,164.91
17 MEMBERSIHKAN PARIT SAMPING K.424 m2 5,344.66
18 KONTRUKSI LAPIS PONDASI BAWAH (LPB)KLAS``A`` K.511 m3 227,870.66
19 KONTRUKSI LAPIS PONDASI BAWAH (LPB)KLAS``B`` K.515 m3 149,354.62
20 KONTRUKSI LAPIS BAWAH (LPB TELPOORD) K.516 m3 210,047.21
21 KONSTRUKSI LPB TELFORD (tanpa pasir) K.516.A m3 169,172.21
22 LEVELING LAPIS PONDASI ATAS (LPA) KLAS ``A'' K.521.A m3 263,787.52
23 LAPIS PONDASI ATAS (LPA) KLAS ``A'' K.521 m3 298,763.82
24 LEVELING KONTRUKSI LAPIS PONDASI ATAS (LPA) KLAS B K.523.A m3 253,837.95
25 KONTRUKSI LAPIS PONDASI ATAS (LPA) KLAS " B " K.523 m3 266,678.99
26 LAPIS PENETRASI MAKADAM 4 CM (LAPEN) K.618.B m2 37,127.24
27 LAPIS PENETRASI MAKADAM 4CM ( LAPEN) K.618.A m2 46,356.39
28 LAPIS PENETRASI MAKADAM 5CM ( LAPEN) K.618 m2 59,787.95
29 MENGHAMPAR DAN MEMADATKAN LATASIR TEBAL 1 cm K.638 m2 24,252.01
30 PENGHAMPARAN DAN PEMADATAN LATASTON TEBAL 3 cm K.636 m2 57,535.22
31 LAPIS PENETRASI PONDASI ATAS MAKADAM 7 CM (LAPEN) K.637 m3 1,017,136.21
32 MENGHAMPAR LAPIS PERMUKAAN LAPIS ASPAL BETON K.641 m3 1,959,495.64
33 Mengerjakan 1 m² pengukuran dan pemasangan bouwplank A.004 m2 205,184.50
34 Membersihkan 1 m² lapangan dan perataan A.008 m2 5,375.00
35 Membuat 1 m² steger dari bambu, ukuran (40 x 60 x 20) cm A.011 m2 25,595.00
36 Membongkar 1 m³ beton bertulang A.013 m3 227,829.50
37 Mengerjakan1 m² pengukuran kembali (site) A.015 m2 1,630.00
38 Membongkar 1 m³ dinding bata/ pas. batu kali (bongkaran dipakai kembali) A.016 m3 99,915.00
39 Membongkar 1 m³ jembatan kayu (bongkaran dipakai kembali) A.018 m3 407,000.00
40 Membongkar 1 m³ jembatan kayu (bongkaran tidak dipakai kembali) A.019 m3 286,050.00
41 Menggali 1 m³ tanah biasa sedalam 1 meter B.001 m3 25,087.50
42 Menggali 1 m³ tanah biasa sedalam 2 meter B.002 m3 30,757.50
43 Menggali 1 m³ tanah biasa sedalam 3 meter B.003 m3 36,514.50
44 Menggali 1 m³ tanah keras sedalam 1 meter B.004 m3 33,392.00
45 Menggali 1 m³ tanah cadas sedalam 1 meter B.005 m3 50,610.00
46 Menggali 1 m³ tanah lumpur sedalam 1 meter B.006 m3 40,357.50
47 Membuang 1 m³ tanah sejauh 30 meter B.008 m3 10,995.00
48 Membuang 1 m³ tanah sejauh 150 meter B.009 m3 18,687.00
49 Mengurug kembali 1 m³ galian B.010 m3 8,362.50
50 Memadatkan 1 m³ tanah (per 20 cm) B.011 m3 18,175.00
51 Mengurug 1 m³ pasir urug B.012 m3 127,375.00
52 Mengurug 1 m³ tanah urug B.012.A m3 97,375.00
53 Memasang 1 m² lapisan ijuk tebal 10 cm B.015 m2 114,652.50
54 Membuang 1 m³ tanah sejauh 2 kilometer B.017 m3 28,545.00
55 Mengurug 1 m³ tanah dengan tanah urug pilihan menggunakan alat berat B.018 m3 137,775.20
56 Memasang 1 m³ pondasi batu belah; campuran 1 PC : 4 PP C.005 m3 523,568.50
57 Memasang 1 m³ pondasi siklop; 60% beton campuran 1 PC : 2 PB : 3 KR dan 40 % batu belah C. 013 m3 603,565.50
NO. URAIAN PEKERJAAN KODE SATUAN JUMLAH HARGA (RP)

58 Memasang 1 m³ pondasi sumuran; diameter 100 cm C.014 m3 551,613.00


59 Memasang 1 m' tiang pancang (40x40) cm, beton bertulang C.015 m' 747,746.50
60 Memasang 1 m' tiang pancang (35x35) cm, beton bertulang C.016 m' 592,872.00
61 Memasang 1 m³ batu bronjong C.017 m3 641,970.00
62 Memasang 1 m² plesteran 1 PC : 3 PP; tebal 15 mm E.003 m2 27,095.65
63 Memasang 1 m² finishing siar pasangan batu kali adukan 1 PC : 2 PP E.032 m2 26,691.18
64 Memasang 1 m² acian E.033 m2 14,047.00
65 Membuat 1 m³ beton tumbuk 1 PC : 3 PB : 5 KR G.001 m3 599,528.50
66 Membuat 1 m² lantai kerja beton tumbuk 1 PC : 3 PB : 5 KR; tebal 5 cm G.004 m2 63,442.00
67 Membuat 1 m³ beton mutu f'c=7,4 Mpa (K 100); slump (12 ± 2) cm; w/c = 0,87 G.011 m3 633,133.86
68 Membuat 1 m³ beton mutu f'c=9,8 Mpa (K 125); slump (12 ± 2) cm; w/c = 0,78 G.012 m3 670,412.49
69 Membuat 1 m³ beton mutu f'c=12,2 Mpa (K 150); slump (12 ± 2) cm; w/c = 0,78 G.013 m3 670,412.49
70 Membuat 1 m³ beton mutu f'c=7,4 Mpa (K 100); slump (3-6) cm; w/c = 0,87 G.014 m3 600,647.37
71 Membuat 1 m³ beton mutu f'c=14,5 Mpa (K 175); slump (12 ± 2) cm; w/c = 0,66 G.015 m3 734,153.76
72 Membuat 1 m³ beton mutu f'c=16,9 Mpa (K 200); slump (12 ± 2) cm; w/c = 0,61 G.016 m3 766,901.79
73 Membuat 1 m³ beton mutu f'c=19,3 Mpa (K 225); slump (12 ± 2) cm; w/c = 0,58 G.017 m3 791,836.62
74 Membuat 1 m³ beton mutu f'c=21,7 Mpa (K 250); slump (12 ± 2) cm; w/c = 0,56 G.018 m3 807,699.92
75 Membuat 1 m³ beton mutu f'c=24 Mpa (K 275); slump (12 ± 2) cm; w/c = 0,53 G.019 m3 834,823.29
76 Membuat 1 m³ beton mutu f'c=26,4 Mpa (K 300); slump (12 ± 2) cm; w/c = 0,52 G.020 m3 843,286.49
77 Membuat 1 m³ beton mutu f'c=28,8 Mpa (K 325); slump (12 ± 2) cm; w/c = 0,49 G.021 m3 875,250.40
78 Membuat 1 m³ beton mutu f'c=31,2 Mpa (K 350); slump (12 ± 2) cm; w/c = 0,48 G.022 m3 886,273.16
79 Memasang 10 kg jaring kawat baja /wiremesh G.024 kg 394,596.00
80 Memasang 1 m² bekisting untuk pondasi G.025 m2 117,754.00
81 Memasang 1 m² bekisting untuk dinding G.030 m2 281,717.00
82 Memasang 1 m² jembatan untuk pengecoran beton G.032 m2 102,872.50
83 Memasang 1 m³ pondasi beton bertulang (150 kg besi + bekisting) G.033 m3 2,820,218.00
84 Menghamparkan 1 m³ beton mutu K-125 (ready mix) G.042 m3 900,110.00
85 Menghamparkan 1 m³ beton mutu K-175 (ready mix) G.043 m3 914,110.00
86 Menghamparkan 1 m³ beton mutu K-225 (ready mix) G.044 m3 972,610.00
87 Menghamparkan 1 m³ beton mutu K-250 (ready mix) G.045 m3 1,005,110.00
88 Menghamparkan 1 m³ beton mutu K-275 (ready mix) G.046 m3 1,035,010.00
89 Menghamparkan 1 m³ beton mutu K-300 (ready mix) G.047 m3 1,113,010.00
90 Menghamparkan 1 m³ beton mutu K-350 (ready mix) G.048 m3 1,167,610.00
91 Memasang 1 m² plat beton "bondex" G.049 m2 220,196.00
92 Pembesian 1 kg dengan besi beton G.050 kg 12,232.75
93 1 KG PEK. BAJA PROFIL, IWF G.051 kg 18,226.25
94 1 KG PEK. BONGKAR PASANG KEMBALI BAJA PROFIL, IWF G.051.A kg 4,996.25
95 Mengerjakan 1cm' Pengelasan dengan las listrik K.004 cm 2,953.90
96 Mengecat 1 m² bidang tembok baru (1 lps plamir, 1 lps cat dsr, 2 lps cat penutup) N.008 m2 12,374.90
97 Mengecat 1 m² permukaan baja dengan meni besi N.010 m2 12,737.00
98 Mengecat 1 m² permukaan baja dengan meni besi dan perancah N.011 m2 31,007.50
PEMERINTAH KABUPATEN BREBES
DINAS PEKERJAAN UMUM
Jalan Jend. Sudirman No. 129 Telp ( 0283 ) 671721 Brebes

DAFTAR HARGA SATUAN PERALATAN


PROPINSI : JAWA TENGAH TAHUN ANGGARAN : ----
KABUPATEN : BREBES

NO. URAIAN PEKERJAAN KODE SATUAN JUMLAH HARGA (RP)


1 BULDOZER E.001 Jam 351,790.48
2 MOTOR GRADER E.010 Jam 455,793.66
3 CRUSHER 30 T/hr E.031 Jam 542,928.50
4 SCREENING PLANT E.040 Jam 199,108.50
5 LOADER WHEELED E.052 Jam 281,834.30
6 TRACTOR WHEELED E.053 Jam 106,706.72
7 ROLLER THREE WHEEL 8 - ton E.080 Jam 137,655.42
8 TANDEM ROLLER 6 - 10 ton E.081 Jam 136,871.93
9 TOWED VIBRATOR ROLLER 2 - 3 ton E.083 Jam 61,151.50
10 PNEUMATIC ROLLER 8 - 15 ton E.084 Jam 233,948.69
11 MESIN GILAS BERGETAR 1 ton E.087 Jam 41,535.08
12 PLATE VIBRATOR TAMPER E.088 Jam 12,939.46
13 CONCRETE VIBRATOR E.089 Jam 11,619.95
14 CHIP SPREADER E.130 Jam 25,636.05
15 SPRAYE SELPROPELLED (pemanas aspal) E.152 Jam 222,793.49
16 ASPHLAT SPRAYER TOWED 350 L E.153 Jam 91,266.98
17 ASPHLAT MIXING PLAN 30t/h E.155 Jam 2,303,215.39
18 ASPHLAT FINISHER E.157 Jam 369,985.00
19 TRUCK AIR (WATER TANK TRUCK) E.182 Jam 171,115.60
20 DUMP TRUCK 3,5 ton E.211 Jam 168,066.58
21 DUMP TRUCK 5,00 ton E.212 Jam 224,269.48
22 FLAT BED TRUCK 4 TON E.221 Jam 139,682.90
23 SPRAYER TOWED 400 L E.154 Jam 23,763.97
24 CONCRETE MIXER (Beton Molen) 0,125 m3 E.251 Jam 11,222.10
25 CONCRETE MIXER (Beton Molen) 0,25 m3 E.252 Jam 28,732.39
26 CONCRETE MIXER (Beton Molen) 0,50m3 E.253 Jam 57,449.97
27 COMPRESOR AIR 150 m3 E.301 Jam 103,720.16
28 WATER PUMP E.341 Jam 14,508.27
29 TRACTOR EQUIPMENT,ETC E.401 Jam 73,513.77
30 GEROBAK DORONG (WHEEL BARROW) E.402 Jam 119.78
PEMERINTAH KABUPATEN BREBES
DINAS PEKERJAAN UMUM
Jalan Jend. Sudirman No. 129 Telp ( 0283 ) 671721 Brebes

DAFTAR HARGA SATUAN UPAH


PROPINSI : JAWA TENGAH TAHUN ANGGARAN : ----
KABUPATEN : BREBES

NO. URAIAN PEKERJAAN KODE SATUAN JUMLAH HARGA (RP)

1 Mandor Lapangan L.061 Hari 43,500.00


2 Mekanik L.071 Hari 45,500.00
3 Mekanik Pembantu L.072 Hari 43,500.00
4 Kepala Tukang L.073 Hari 45,500.00
5 Tukang L.079 Hari 40,500.00
6 Operator terlatih L.081 Hari 55,000.00
7 Operator Kurang terlatih L.082 Hari 50,000.00
8 Pembantu Operator L.083 Hari 45,000.00
9 Sopir Material / Truck L.091 Hari 43,000.00
10 Sopir Personil L.092 Hari 40,000.00
11 Pembantu Sopir / Kenek L.099 Hari 31,000.00
12 Buruh Lapangan tak terlatih L.101 Hari 30,000.00
13 Buruh Lapangan Agak terlatih L.103 Hari 31,000.00
14 Buruh lapangan terlatih L.106 Hari 40,000.00
15 Pekerja - hari 32,000.00
16 Tukang Gali - hari 32,000.00
17 Tukang cat / plitur / batu - hari 40,500.00
18 Kepala tukang cat / plitur / batu - hari 45,500.00
19 Tukang kayu - hari 40,500.00
20 Kepala tukang kayu - hari 45,500.00
21 Tukang Besi - hari 40,500.00
22 Kepala Tukang besi - hari 45,500.00
23 Tukang Besi Profil - hari 40,500.00
24 Kepala Tukang Besi Profil - hari 45,500.00
25 Tukang Instalasi - hari 45,500.00
26 Tukang masak aspal - hari 44,000.00
27 Penjaga malam - hari 37,500.00
28 Sewa Dump Truck 3/4 + Bahan bakar - hari 440,000.00
29 Sewa Mesin Gilas ( Wals ) + Bahan bakar - hari 684,359.65
30 Sewa Mesin Gilas ( Wals ) + Bahan bakar 1 bulan ( 25 hari ) - Bulan 17,108,991.20
PEMERINTAH KABUPATEN BREBES
DINAS PEKERJAAN UMUM
Jalan Jend. Sudirman No. 129 Telp ( 0283 ) 671721 Brebes

DAFTAR HARGA SATUAN BAHAN / MATERIAL


PROPINSI : JAWA TENGAH TAHUN ANGGARAN : ----
KABUPATEN : BREBES
NO. URAIAN PEKERJAAN KODE SATUAN JUMLAH HARGA (RP)
1 Batu Belah Besar M.010 m3 143,000.00
2 Kerikil Sirtu *) M.011 m3 30,000.00
3 Kerikil Sungai ( tidak disaring ) *) M.012 m3 30,000.00
4 Batu Kali ( besar ) *) M.013 m3 21,000.00
5 Batu Kali ( Kecil disaring ) *) M.014 m3 15,000.00
6 Batu Belah 10 - 15 cm M.020 m3 143,000.00
7 Batu Pecah 5 - 7 cm Pecah Tangan M.022 m3 143,000.00
8 Batu Pecah 3 - 5 cm Pecah Tangan M.023 m3 143,000.00
9 Batu Pecah 3 - 4 cm Pecah Tangan M.023.A m3 160,000.00
10 Batu Pecah 2 - 3 cm Pecah Tangan M.024 m3 195,000.00
11 Batu Pecah 3 - 4 cm Pecah Mesin M.024.B m3 230,000.00
12 Batu Pecah 2 - 3 cm Pecah Mesin M.024.A m3 235,000.00
13 Batu Pecah 1 - 2 cm Pecah Mesin M.025 m3 235,000.00
14 Batu Pecah 0,5 - 1cm Pecah Mesin M.026 m3 247,000.00
15 Abu Batu M.027 m3 230,000.00
16 Batu Bata M.025 Buah 550.00
17 Gorong-gorong Beton Diameter 60 cm M.031 m' 166,400.00
18 Gorong-gorong Beton Diameter 80 cm M.033 m' 206,700.00
19 Gorong-gorong Beton Diameter 100 cm M.035 m' 260,000.00
20 Pasir Urug ( Bahan Timbunan Pilihan ) M.040 m3 91,000.00
21 Pasir Bersih ( Agregat Halus ) M.041 m3 130,000.00
22 Kerikil berpasir alami M.042 m3 90,000.00
23 Tanah urug ( timbunan ) M.042.A m3 66,000.00
24 Tanah urug ( timbunan pilihan ) M.050 m3 78,000.00
25 Aspal bitumen M.061 kg 7,720.00
26 Aspal curah M.062 kg 5,590.00
27 Karosine M.064 liter 8,500.00
28 Minyak tanah M.065 liter 4,550.00
29 Kayu bakar M.070 m3 149,500.00
30 Asbuton B-20 M.061.A ton 450,000.00
31 Modifieer M.064.A liter 7,800.00
32 Portland cement M.080 kg 1,352.00
33 Portland cement 50kg M.080.A Zak 67,600.00
34 Kapur M.081 m3 390,000.00
35 Batu kapur bongkahan M.082 ton 747,500.00
36 Cat jembatan ( besi ) M.090 kg 46,800.00
37 Cat tembok M.090.A kg 20,800.00
38 Pipa PVC 2 " M.100 m' 23,100.00
39 Pipa PVC 2,5 " M.101 m' 29,100.00
40 Pipa PVC 3 " M.102 m' 51,700.00
41 Ijuk M.103 ikat 18,200.00
42 Bambu M.104 Btng 11,700.00
43 Baja gulungan ukuran ringan M.161 kg 24,700.00
44 Baja anyaman bronjong 0,4 mm M.162 kg 24,700.00
45 Baja baud - baud M.163 kg 15,100.00
46 Baud lawa - lawa M.163.A buah 4,450.00
47 Baja galvanis M.164 m' 17,550.00
48 Pipa galvanis 2,5 " M.164.A m' 82,400.00
49 Pipa galvanis 3 " M.164.B m' 109,950.00
50 Baja struktur M.165 kg 12,700.00
51 Baja plat M.165.A kg 12,600.00
52 paku M.166 kg 15,600.00
53 Baja tulangan beton ( besi beton ) M.167 kg 8,650.00
54 Alat - alat bantu ( @ 3 alat ) M.170 set 55,000.00
55 Kayu untuk perancah ( kayu pinus / rawa ) M.180 m3 2,080,000.00
56 Kayu Struktural ( jati klas 2 ) M.181 m3 15,860,000.00
57 Kayu tahun M.182 m3 1,495,000.00
58 Solar M.183 liter 5,850.00
59 Solar industri M.183.A liter 5,900.00
60 Bensin premium M.184 liter 5,850.00
61 Minyak pelumas M.185 liter 33,150.00
62 Batu quary royalty *) MR.11 m3 21,000.00
63 Kerikil sungai royalty *) MR.12 m3 30,000.00
64 Sirtu royalty *) MR.42 m3 30,000.00
65 Elastomer MR.43 buah 512,000.00
NO. URAIAN PEKERJAAN KODE SATUAN JUMLAH HARGA (RP)
66 Kayu Kalimantan ( Meranti Batu ) 5/7 & 4/6 (ikat) - m3 4,680,000.00
67 Kayu Punak Ukuran 5/7 & 4/6 (ikat) m3 4,946,500.00
68 Kayu Bengkirai 5/7 (ikat) M3 8,450,000.00
69 Papan bangkirai ( 2 x 30 x 400 ) M3 13,650,000.00
70 Papan Meranti Batu ( 2 x 25 x 400 ) - m3 6,500,000.00
71 Batu blonos - m3 117,000.00
72 Beton K 125 (ready mix) m³ 805,000.00
73 Beton K 175 (ready mix) - m³ 819,000.00
74 Beton K 225 (ready mix) - m³ 877,500.00
75 Beton K 250 (ready mix) m³ 910,000.00
76 Beton K 275 (ready mix) m³ 939,900.00
77 Beton K 300 (ready mix) - m³ 1,017,900.00
78 Beton K 350 (ready mix) m³ 1,072,500.00
79 Kawat beton (bindrad) - kg 15,600.00
80 Minyak Bekisting ( olie bekas ) - ltr 3,900.00
81 Multipleks 9 mm - lbr 162,500.00
82 Multipleks 12 mm - lbr 188,500.00
83 Dolken kayu galam Φ - 8 - 10/4 m - btng 15,600.00
84 Meni besi - Kg 26,000.00
85 Amplas besi - Lbr 4,000.00
86 Minyak cat thiner B - Ltr 13,000.00
87 Kuas 3" - bh 5,200.00
88 Besi kanal C 50 - Kg 12,600.00
89 Besi siku L 50.50.4 - Kg 12,600.00
90 Besi IWF - Kg 12,600.00
91 Kawat las listrik - Kg 28,600.00
92 Bondex - m2 193,600.00
93 Shear Connector - Ls 18,550.00
94 Cat Dasar - Kg 20,800.00
95 Plamir - Kg 13,000.00
96 Formite / penjaga jarak bekisting / spacer Bh 2,200.00

Keterangan :
*) Harga BBM Mengikuti Harga Pemerintah
*) Harga Material Dilokasi material
Semua harga tersebut sudah termasuk PPN
PEMERINTAH KABUPATEN BREBES
DINAS PEKERJAAN UMUM
Jalan Jend. Sudirman No. 129 Telp ( 0283 ) 671721 Brebes

DAFTAR HARGA PERALATAN


PROPINSI : JAWA TENGAH
KABUPATEN : BREBES

NO. JENIS ALAT HARGA


1 BULDOZER E.001 880,000,000.00
2 MOTOR GRADER E.010 1,501,500,000.00
3 CRUSHER 30 T/hr E.031 1,980,000,000.00
4 SCREENING PLANT E.040 499,991,250.00
5 LOADER WHEELED E.052 698,500,000.00
6 TRACTOR WHEELED E.053 199,657,050.00
7 ROLLER THREE WHEEL 8 - ton E.080 412,500,000.00
8 TANDEM ROLLER 6 - 10 ton E.081 473,000,000.00
9 TOWED VIBRATOR ROLLER 2 - 3 ton E.083 250,844,250.00
10 PNEUMATIC ROLLER 8 - 15 ton E.084 652,204,350.00
11 MESIN GILAS BERGETAR 1 ton E.087 104,638,950.00
12 PLATE VIBRATOR TAMPER E.088 16,354,050.00
13 CONCRETE VIBRATOR E.089 9,778,950.00
14 CHIP SPREADER E.130 39,929,550.00
15 SPRAYE SELPROPELLED (pemanas aspal) E.152 559,683,300.00
16 ASPHLAT SPRAYER TOWED 350 L E.153 162,224,550.00
17 ASPHLAT MIXING PLAN 30t/h E.155 2,893,000,000.00
18 ASPHLAT FINISHER E.157 1,150,000,000.00
19 TRUCK AIR (WATER TANK TRUCK) E.182 158,100,000.00
20 DUMP TRUCK 3,5 ton E.211 186,000,000.00
21 DUMP TRUCK 5,00 ton E.212 232,500,000.00
22 FLAT BED TRUCK 4 TON E.221 190,375,650.00
23 SPRAYER TOWED 400 L E.154 30,800,000.00
24 CONCRETE MIXER (Beton Molen) 0,125 m3 E.251 13,001,400.00
25 CONCRETE MIXER (Beton Molen) 0,25 m3 E.252 60,022,200.00
26 CONCRETE MIXER (Beton Molen) 0,50m3 E.253 119,993,250.00
27 COMPRESOR AIR 150 m3 E.301 187,000,000.00
28 WATER PUMP E.341 7,998,000.00
29 TRACTOR EQUIPMENT,ETC E.401 101,532,750.00
30 GEROBAK DORONG (WHEEL BARROW) E.402 1,000,000.00
DINAS PEKERJAAN UMUM
KABUPATEN BREBES

ANALISA HARGA SATUAN PEKERJAAN


TAHUN ANGGARAN ----

HARGA SAT JUMLAH


NO KOEF SAT
Rp. Rp.
1 2 3 4 5 6=(3x5)
A. PEKERJAAN PERSIAPAN SNI 03-2835-2002
A.004 Mengerjakan 1 m² pengukuran dan pemasangan bouwplank
Bahan
Kayu Bengkirai 5/7 (ikat) 0.0120 m³ 8,450,000.00 101,400.00
Paku Biasa 2" - 5" 0.0200 kg 15,600.00 312.00
Kayu Papan Bangkirai 2x30x400 0.0070 m³ 13,650,000.00 95,550.00
Jumlah (1) 197,262.00
Tenaga
Pekerja 0.1000 OH 32,000.00 3,200.00
Tukang Kayu 0.1000 OH 40,500.00 4,050.00
Kepala Tukang 0.0100 OH 45,500.00 455.00
Mandor 0.0050 OH 43,500.00 217.50
Jumlah (2) 7,922.50
Jumlah (1) + (2) 205,184.50
A.008 Membersihkan 1 m² lapangan dan perataan
Pekerja 0.1000 OH 32,000.00 3,200.00
Mandor 0.0500 OH 43,500.00 2,175.00
Jumlah (1) 5,375.00
A.011 Membuat 1 m² steger dari bambu, ukuran (40 x 60 x 20) cm
Bahan
Bambu 1.0000 btg 11,700.00 11,700.00
Tali Ijuk 0.2500 kg 18,200.00 4,550.00
Jumlah (1) 16,250.00
Tenaga
Pekerja 0.2500 OH 32,000.00 8,000.00
Tukang Kayu 0.0170 OH 40,500.00 688.50
Kepala Tukang 0.0020 OH 45,500.00 91.00
Mandor 0.0130 OH 43,500.00 565.50
Jumlah (2) 9,345.00
Jumlah (1) + (2) 25,595.00
A.013 Membongkar 1 m³ beton bertulang
Pekerja 6.6670 OH 32,000.00 213,344.00
Mandor 0.3330 OH 43,500.00 14,485.50
Jumlah 227,829.50
A.015 Mengerjakan1 m² pengukuran kembali (site)
Pekerja 0.0100 OH 32,000.00 320.00
Tukang Kayu 0.0200 OH 40,500.00 810.00
Peralatan 0.5000 OH 1,000.00 500.00
Jumlah 1,630.00
A.016 Membongkar 1 m³ dinding bata/ pas. batu kali (bongkaran dipakai kembali)
Pekerja 3.0000 OH 32,000.00 96,000.00
Mandor 0.0900 OH 43,500.00 3,915.00
Jumlah 99,915.00
A.018 Membongkar 1 m³ jembatan kayu (bongkaran dipakai kembali)
Pekerja 4.0000 OH 32,000.00 128,000.00
Tukang Kayu 6.0000 OH 40,500.00 243,000.00
Kepala Tukang 0.6000 OH 45,500.00 27,300.00
Mandor 0.2000 OH 43,500.00 8,700.00
Jumlah 407,000.00
A.019 Membongkar 1 m³ jembatan kayu (bongkaran tidak dipakai kembali)
Pekerja 6.0000 OH 32,000.00 192,000.00
Tukang Kayu 2.0000 OH 40,500.00 81,000.00
Mandor 0.3000 OH 43,500.00 13,050.00
Jumlah 286,050.00
HARGA SAT JUMLAH
NO KOEF SAT
Rp. Rp.
1 2 3 4 5 6=(3x5)
B. PEKERJAAN TANAH SNI
B.001 Menggali 1 m³ tanah biasa sedalam 1 meter
Tenaga
Pekerja 0.7500 OH 32,000.00 24,000.00
Mandor 0.0250 OH 43,500.00 1,087.50
Jumlah 25,087.50
B.002 Menggali 1 m³ tanah biasa sedalam 2 meter
Tenaga
Pekerja 0.9000 OH 32,000.00 28,800.00
Mandor 0.0450 OH 43,500.00 1,957.50
Jumlah 30,757.50
B.003 Menggali 1 m³ tanah biasa sedalam 3 meter
Tenaga
Pekerja 1.0500 OH 32,000.00 33,600.00
Mandor 0.0670 OH 43,500.00 2,914.50
Jumlah 36,514.50
B.004 Menggali 1 m³ tanah keras sedalam 1 meter
Tenaga
Pekerja 1.0000 OH 32,000.00 32,000.00
Mandor 0.0320 OH 43,500.00 1,392.00
Jumlah 33,392.00
B.005 Menggali 1 m³ tanah cadas sedalam 1 meter
Tenaga
Pekerja 1.5000 OH 32,000.00 48,000.00
Mandor 0.0600 OH 43,500.00 2,610.00
Jumlah 50,610.00
B.006 Menggali 1 m³ tanah lumpur sedalam 1 meter
Tenaga
Pekerja 1.2000 OH 32,000.00 38,400.00
Mandor 0.0450 OH 43,500.00 1,957.50
Jumlah 40,357.50
B.007 Mengerjakan 1 m² stripping tebing setinggi 1 meter
Tenaga
Pekerja 0.0500 OH 32,000.00 1,600.00
Mandor 0.0050 OH 43,500.00 217.50
Jumlah 1,817.50
B.008 Membuang 1 m³ tanah sejauh 30 meter
Tenaga
Pekerja 0.3300 OH 32,000.00 10,560.00
Mandor 0.0100 OH 43,500.00 435.00
Jumlah 10,995.00
B.009 Membuang 1 m³ tanah sejauh 150 meter
Tenaga
Pekerja 0.5160 OH 32,000.00 16,512.00
Mandor 0.0500 OH 43,500.00 2,175.00
Jumlah 18,687.00
B.010 Mengurug kembali 1 m³ galian
Tenaga
Pekerja 0.2500 OH 32,000.00 8,000.00
Mandor 0.0083 OH 43,500.00 362.50
Jumlah 8,362.50
B.011 Memadatkan 1 m³ tanah (per 20 cm)
Tenaga
Pekerja 0.5000 OH 32,000.00 16,000.00
Mandor 0.0500 OH 43,500.00 2,175.00
Jumlah 18,175.00
HARGA SAT JUMLAH
NO KOEF SAT
Rp. Rp.
1 2 3 4 5 6=(3x5)
B.012 Mengurug 1 m³ pasir urug
Bahan
Pasir Urug 1.2000 m³ 91,000.00 109,200.00
Jumlah (1) 109,200.00
Tenaga
Pekerja 0.5000 OH 32,000.00 16,000.00
Mandor 0.0500 OH 43,500.00 2,175.00
Jumlah (2) 18,175.00
Jumlah (1) + (2) 127,375.00
B.012.A Mengurug 1 m³ tanah urug
Bahan
Tanah Urug ( Timbunan ) 1.2000 m³ 66,000.00 79,200.00
Jumlah (1) 79,200.00
Tenaga
Pekerja 0.5000 OH 32,000.00 16,000.00
Mandor 0.0500 OH 43,500.00 2,175.00
Jumlah (2) 18,175.00
Jumlah (1) + (2) 97,375.00
B.013 Memasang 1 m³ lapisan pudel campuran 1 KP : 3 PP : 7 TL
Bahan
Kapur Pasang (KP) 0.1350 m³ 390,000.00 52,650.00
Pasir Pasang (PP) 0.4000 m³ 130,000.00 52,000.00
Tanah Lempung (TL) 0.9480 m³ 78,000.00 73,944.00
Jumlah (1) 178,594.00
Tenaga
Pekerja 0.8000 OH 32,000.00 25,600.00
Tukang Batu 0.4000 OH 40,500.00 16,200.00
Kepala Tukang 0.0400 OH 45,500.00 1,820.00
Mandor 0.0800 OH 43,500.00 3,480.00
Jumlah (2) 47,100.00
Jumlah (1) + (2) 225,694.00
B.014 Memasang 1 m³ lapisan pudel campuran 1 KP : 5 TL
Bahan
Kapur Pasang (KP) 0.2480 m³ 390,000.00 96,720.00
Tanah Lempung (TL) 1.2400 m³ 78,000.00 96,720.00
Jumlah (1) 193,440.00
Tenaga
Pekerja 0.8000 OH 32,000.00 25,600.00
Tukang Batu 0.4000 OH 40,500.00 16,200.00
Kepala Tukang 0.0400 OH 45,500.00 1,820.00
Mandor 0.0800 OH 43,500.00 3,480.00
Jumlah (2) 47,100.00
Jumlah (1) + (2) 240,540.00
B.015 Memasang 1 m² lapisan ijuk tebal 10 cm
Bahan
Ijuk 6.0000 kg 18,200.00 109,200.00
Jumlah (1) 109,200.00
Tenaga
Pekerja 0.1500 OH 32,000.00 4,800.00
Mandor 0.0150 OH 43,500.00 652.50
Jumlah (2) 5,452.50
Jumlah (1) + (2) 114,652.50
B.017 Membuang 1 m³ tanah sejauh 2 kilometer
Tenaga
Sopir Truck 0.0500 OH 43,000.00 2,150.00
Biaya Angkat Tanah ke Dump Truck (B.008) 1.0000 m³ 10,995.00 10,995.00
Sewa Dump Truck + BBM 0.0350 hari 440,000.00 15,400.00
Jumlah 28,545.00
B.018 Mengurug 1 m³ tanah dengan tanah urug pilihan menggunakan alat berat
Tenaga
Pek. Galian (10 org) 50% - B.001 0.6000 m³ 25,087.50 15,052.50
Pek. Galian Tanah Keras(10 org) 50% - B.004 0.6000 m³ 33,392.00 20,035.20
Pek. Striping (10 org) 50% - B.007 5.0000 m³ 1,817.50 9,087.50
Beli Tanah + Angkut; Max. 10 km (tanah urug pilihan) 1.2000 m³ 78,000.00 93,600.00
Jumlah 137,775.20
HARGA SAT JUMLAH
NO KOEF SAT
Rp. Rp.
1 2 3 4 5 6=(3x5)
C. PEKERJAAN PONDASI SNI 03-2836-2002
C.005 Memasang 1 m³ pondasi batu belah; campuran 1 PC : 4 PP
Bahan
Batu Belah 15/20 1.1000 m³ 143,000.00 157,300.00
Portland Cement (PC) 163.0000 kg 1,352.00 220,376.00
Pasir Pasang (PP) 0.5200 m³ 130,000.00 67,600.00
Jumlah (1) 445,276.00
Tenaga
Pekerja 1.5000 OH 32,000.00 48,000.00
Tukang Batu 0.6000 OH 40,500.00 24,300.00
Kepala Tukang 0.0600 OH 45,500.00 2,730.00
Mandor 0.0750 OH 43,500.00 3,262.50
Jumlah (2) 78,292.50
Jumlah (1) + (2) 523,568.50
C. 013 Memasang 1 m³ pondasi siklop; 60% beton campuran 1 PC : 2 PB : 3 KR dan 40 % batu belah
Bahan
Batu Belah 15/20 0.4800 m³ 143,000.00 68,640.00
Portland Cement (PC) 194.0000 kg 1,352.00 262,288.00
Pasir Beton (PB) 0.3120 m³ 130,000.00 40,560.00
Koral (Batu pecah tangan ukuran 5 mm - 40 mm) 0.4680 m³ 195,000.00 91,260.00
Jumlah (1) 462,748.00
Tenaga
Pekerja 3.0000 OH 32,000.00 96,000.00
Tukang Batu 0.8500 OH 40,500.00 34,425.00
Kepala Tukang 0.0850 OH 45,500.00 3,867.50
Mandor 0.1500 OH 43,500.00 6,525.00
Jumlah (2) 140,817.50
Jumlah (1) + (2) 603,565.50
C.014 Memasang 1 m³ pondasi sumuran; diameter 100 cm
Bahan
Batu Belah 15/20 0.4500 m³ 143,000.00 64,350.00
Portland Cement (PC) 194.0000 kg 1,352.00 262,288.00
Pasir Beton (PB) 0.3120 m³ 130,000.00 40,560.00
Koral (Batu pecah tangan ukuran 5 mm - 40 mm) 0.4680 m³ 195,000.00 91,260.00
Jumlah (1) 458,458.00
Tenaga
Pekerja 2.3800 OH 32,000.00 76,160.00
Tukang Batu 0.3000 OH 40,500.00 12,150.00
Kepala Tukang 0.0300 OH 45,500.00 1,365.00
Mandor 0.0800 OH 43,500.00 3,480.00
Jumlah (2) 93,155.00
Jumlah (1) + (2) 551,613.00
C.015 Memasang 1 m' tiang pancang (40x40) cm, beton bertulang
Bahan
Pasir Urug 0.0190 m³ 91,000.00 1,729.00
Pasir Beton (PB) 0.0940 m³ 130,000.00 12,220.00
Koral (Batu pecah tangan ukuran 5 mm - 40 mm) 0.1500 m³ 195,000.00 29,250.00
Portland Cement (PC) 60.5000 kg 1,352.00 81,796.00
Besi Beton 45.0000 kg 8,650.00 389,250.00
Kawat Beton 0.9000 kg 15,600.00 14,040.00
Kayu Kaso 5/7 0.0320 m³ 4,680,000.00 149,760.00
Paku 0.1200 kg 15,600.00 1,872.00
Minyak Bekisting 0.0900 lt 3,900.00 351.00
Plamuur Tembok 0.2400 kg 13,000.00 3,120.00
Jumlah (1) 683,388.00
Tenaga
Pekerja 1.0000 OH 32,000.00 32,000.00
Tukang Batu 0.6700 OH 40,500.00 27,135.00
Kepala Tukang 0.0670 OH 45,500.00 3,048.50
Mandor 0.0500 OH 43,500.00 2,175.00
Jumlah (2) 64,358.50
Jumlah (1) + (2) 747,746.50
HARGA SAT JUMLAH
NO KOEF SAT
Rp. Rp.
1 2 3 4 5 6=(3x5)
C.016 Memasang 1 m' tiang pancang (35x35) cm, beton bertulang
Bahan
Pasir Urug 0.0160 m³ 91,000.00 1,456.00
Pasir Beton (PB) 0.0800 m³ 130,000.00 10,400.00
Koral (Batu pecah tangan ukuran 5 mm - 40 mm) 0.1250 m³ 195,000.00 24,375.00
Portland Cement (PC) 49.0000 kg 1,352.00 66,248.00
Besi Beton 34.5000 kg 8,650.00 298,425.00
Kawat Beton 0.7000 kg 15,600.00 10,920.00
Kayu Kaso 5/7 0.0270 m³ 4,680,000.00 126,360.00
Paku 0.1200 kg 15,600.00 1,872.00
Minyak Bekisting 0.0900 lt 3,900.00 351.00
Plamuur Tembok 0.2000 kg 13,000.00 2,600.00
Jumlah (1) 543,007.00
Tenaga
Pekerja 0.8000 OH 32,000.00 25,600.00
Tukang Batu 0.5000 OH 40,500.00 20,250.00
Kepala Tukang 0.0500 OH 45,500.00 2,275.00
Mandor 0.0400 OH 43,500.00 1,740.00
Jumlah (2) 49,865.00
Jumlah (1) + (2) 592,872.00
C.017 Memasang 1 m³ batu bronjong
Bahan
Batu Kali Bulat (Blonos) 1.2000 m³ 117,000.00 140,400.00
Kawat Bronjong 18.0000 kg 24,700.00 444,600.00
Jumlah (1) 585,000.00
Tenaga
Pekerja 1.5000 OH 32,000.00 48,000.00
Tukang Batu 0.2000 OH 40,500.00 8,100.00
Mandor 0.0200 OH 43,500.00 870.00
Jumlah (2) 56,970.00
Jumlah (1) + (2) 641,970.00
E. PEKERJAAN PLESTERAN SNI 03-2837-2002
Memasang 1 m² plesteran 1 PC : 3 PP; tebal 15
E.003
mm
Bahan
Portland Cement (PC) 7.7760 kg 1,352.00 10,513.15
Pasir Pasang (PP) 0.0230 m³ 130,000.00 2,990.00
Jumlah (1) 13,503.15
Tenaga
Pekerja 0.2000 OH 32,000.00 6,400.00
Tukang Batu 0.1500 OH 40,500.00 6,075.00
Kepala Tukang 0.0150 OH 45,500.00 682.50
Mandor 0.0100 OH 43,500.00 435.00
Jumlah (2) 13,592.50
Jumlah (1) + (2) 27,095.65
E.032 Memasang 1 m² finishing siar pasangan batu kali adukan 1 PC : 2 PP
Bahan
Portland Cement (PC) 6.3400 kg 1,352.00 8,571.68
Pasir Pasang (PP) 0.0120 m³ 130,000.00 1,560.00
Jumlah (1) 10,131.68
Tenaga
Pekerja 0.3000 OH 32,000.00 9,600.00
Tukang Batu 0.1400 OH 40,500.00 5,670.00
Kepala Tukang 0.0140 OH 45,500.00 637.00
Mandor 0.0150 OH 43,500.00 652.50
Jumlah (2) 16,559.50
Jumlah (1) + (2) 26,691.18
E.033 Memasang 1 m² acian
Bahan
Portland Cement (PC) 3.2500 kg 1,352.00 4,394.00
Jumlah (1) 4,394.00
Tenaga
Pekerja 0.1500 OH 32,000.00 4,800.00
Tukang Batu 0.1000 OH 40,500.00 4,050.00
Kepala Tukang 0.0100 OH 45,500.00 455.00
Mandor 0.0080 OH 43,500.00 348.00
Jumlah (2) 9,653.00
Jumlah (1) + (2) 14,047.00
HARGA SAT JUMLAH
NO KOEF SAT
Rp. Rp.
1 2 3 4 5 6=(3x5)
G. PEKERJAAN BETON RSNI-T-13-2002
G.001 Membuat 1 m³ beton tumbuk 1 PC : 3 PB : 5 KR
Bahan
Portland Cement (PC) 218.0000 kg 1,352.00 294,736.00
Pasir Beton (PB) 0.5200 m³ 130,000.00 67,600.00
Koral (Batu pecah tangan 2-3) 0.8700 m³ 195,000.00 169,650.00
Jumlah (1) 531,986.00
Tenaga
Pekerja 1.6500 OH 32,000.00 52,800.00
Tukang Batu 0.2500 OH 40,500.00 10,125.00
Kepala Tukang 0.0250 OH 45,500.00 1,137.50
Mandor 0.0800 OH 43,500.00 3,480.00
Jumlah (2) 67,542.50
Jumlah (1) + (2) 599,528.50
G.004 Membuat 1 m² lantai kerja beton tumbuk 1 PC : 3 PB : 5 KR; tebal 5 cm
Bahan
Portland Cement (PC) 10.0000 kg 1,352.00 13,520.00
Pasir Beton (PB) 0.0260 m³ 130,000.00 3,380.00
Koral (Batu pecah tangan 2-3) 0.0440 m³ 195,000.00 8,580.00
Jumlah (1) 25,480.00
Tenaga
Pekerja 1.1500 OH 32,000.00 36,800.00
Tukang Batu 0.0200 OH 40,500.00 810.00
Kepala Tukang 0.0020 OH 45,500.00 91.00
Mandor 0.0060 OH 43,500.00 261.00
Jumlah (2) 37,962.00
Jumlah (1) + (2) 63,442.00
G.011 Membuat 1 m³ beton mutu f'c=7,4 Mpa (K 100); slump (12 ± 2) cm; w/c = 0,87
Bahan
Portland Cement (PC) 247.0000 kg 1,352.00 333,944.00
Pasir Beton (PB) 0.6207 m³ 130,000.00 80,692.86
Koral (Batu pecah tangan 2-3) 0.7400 m³ 195,000.00 144,300.00
Air 215.0000 liter 25.00 5,375.00
Jumlah (1) 564,311.86
Tenaga
Pekerja 1.6500 OH 32,000.00 52,800.00
Tukang Batu 0.2750 OH 40,500.00 11,137.50
Kepala Tukang 0.0280 OH 45,500.00 1,274.00
Mandor 0.0830 OH 43,500.00 3,610.50
Jumlah (2) 68,822.00
Jumlah (1) + (2) 633,133.86
G.012 Membuat 1 m³ beton mutu f'c=9,8 Mpa (K 125); slump (12 ± 2) cm; w/c = 0,78
Bahan
Portland Cement (PC) 276.0000 kg 1,352.00 373,152.00
Pasir Beton (PB) 0.5914 m³ 130,000.00 76,885.71
Koral (Batu pecah tangan 2-3) 0.7496 m³ 195,000.00 146,177.78
Air 215.0000 liter 25.00 5,375.00
Jumlah (1) 601,590.49
Tenaga
Pekerja 1.6500 OH 32,000.00 52,800.00
Tukang Batu 0.2750 OH 40,500.00 11,137.50
Kepala Tukang 0.0280 OH 45,500.00 1,274.00
Mandor 0.0830 OH 43,500.00 3,610.50
Jumlah (2) 68,822.00
Jumlah (1) + (2) 670,412.49
HARGA SAT JUMLAH
NO KOEF SAT
Rp. Rp.
1 2 3 4 5 6=(3x5)
G.013 Membuat 1 m³ beton mutu f'c=12,2 Mpa (K 150); slump (12 ± 2) cm; w/c = 0,78
Bahan
Portland Cement (PC) 276.0000 kg 1,352.00 373,152.00
Pasir Beton (PB) 0.5914 m³ 130,000.00 76,885.71
Koral (Batu pecah tangan 2-3) 0.7496 m³ 195,000.00 146,177.78
Air 215.0000 liter 25.00 5,375.00
Jumlah (1) 601,590.49
Tenaga
Pekerja 1.6500 OH 32,000.00 52,800.00
Tukang Batu 0.2750 OH 40,500.00 11,137.50
Kepala Tukang 0.0280 OH 45,500.00 1,274.00
Mandor 0.0830 OH 43,500.00 3,610.50
Jumlah (2) 68,822.00
Jumlah (1) + (2) 670,412.49
G.014 Membuat 1 m³ beton mutu f'c=7,4 Mpa (K 100); slump (3-6) cm; w/c = 0,87
Bahan
Portland Cement (PC) 230.0000 kg 1,352.00 310,960.00
Pasir Beton (PB) 0.6379 m³ 130,000.00 82,921.43
Koral (Batu pecah tangan 2-3) 0.7607 m³ 195,000.00 148,344.44
Air 200.0000 liter 25.00 5,000.00
Jumlah (1) 547,225.87
Tenaga
Pekerja 1.2000 OH 32,000.00 38,400.00
Tukang Batu 0.2750 OH 40,500.00 11,137.50
Kepala Tukang 0.0280 OH 45,500.00 1,274.00
Mandor 0.0600 OH 43,500.00 2,610.00
Jumlah (2) 53,421.50
Jumlah (1) + (2) 600,647.37
G.015 Membuat 1 m³ beton mutu f'c=14,5 Mpa (K 175); slump (12 ± 2) cm; w/c = 0,66
Bahan
Portland Cement (PC) 326.0000 kg 1,352.00 440,752.00
Pasir Beton (PB) 0.5429 m³ 130,000.00 70,571.43
Koral (Batu pecah tangan 2-3) 0.7622 m³ 195,000.00 148,633.33
Air 215.0000 liter 25.00 5,375.00
Jumlah (1) 665,331.76
Tenaga
Pekerja 1.6500 OH 32,000.00 52,800.00
Tukang Batu 0.2750 OH 40,500.00 11,137.50
Kepala Tukang 0.0280 OH 45,500.00 1,274.00
Mandor 0.0830 OH 43,500.00 3,610.50
Jumlah (2) 68,822.00
Jumlah (1) + (2) 734,153.76
G.016 Membuat 1 m³ beton mutu f'c=16,9 Mpa (K 200); slump (12 ± 2) cm; w/c = 0,61
Bahan
Portland Cement (PC) 352.0000 kg 1,352.00 475,904.00
Pasir Beton (PB) 0.5221 m³ 130,000.00 67,878.57
Koral (Batu pecah tangan 2-3) 0.7637 m³ 195,000.00 148,922.22
Air 215.0000 liter 25.00 5,375.00
Jumlah (1) 698,079.79
Tenaga
Pekerja 1.6500 OH 32,000.00 52,800.00
Tukang Batu 0.2750 OH 40,500.00 11,137.50
Kepala Tukang 0.0280 OH 45,500.00 1,274.00
Mandor 0.0830 OH 43,500.00 3,610.50
Jumlah (2) 68,822.00
Jumlah (1) + (2) 766,901.79
G.017 Membuat 1 m³ beton mutu f'c=19,3 Mpa (K 225); slump (12 ± 2) cm; w/c = 0,58
Bahan
Portland Cement (PC) 371.0000 kg 1,352.00 501,592.00
Pasir Beton (PB) 0.4986 m³ 130,000.00 64,814.29
Koral (Batu pecah tangan 2-3) 0.7756 m³ 195,000.00 151,233.33
Air 215.0000 liter 25.00 5,375.00
Jumlah (1) 723,014.62
Tenaga
Pekerja 1.6500 OH 32,000.00 52,800.00
Tukang Batu 0.2750 OH 40,500.00 11,137.50
Kepala Tukang 0.0280 OH 45,500.00 1,274.00
Mandor 0.0830 OH 43,500.00 3,610.50
Jumlah (2) 68,822.00
Jumlah (1) + (2) 791,836.62
HARGA SAT JUMLAH
NO KOEF SAT
Rp. Rp.
1 2 3 4 5 6=(3x5)
G.018 Membuat 1 m³ beton mutu f'c=21,7 Mpa (K 250); slump (12 ± 2) cm; w/c = 0,56
Bahan
Portland Cement (PC) 384.0000 kg 1,352.00 519,168.00
Pasir Beton (PB) 0.4943 m³ 130,000.00 64,257.14
Koral (Batu pecah tangan 2-3) 0.7696 m³ 195,000.00 150,077.78
Air 215.0000 liter 25.00 5,375.00
Jumlah (1) 738,877.92
Tenaga
Pekerja 1.6500 OH 32,000.00 52,800.00
Tukang Batu 0.2750 OH 40,500.00 11,137.50
Kepala Tukang 0.0280 OH 45,500.00 1,274.00
Mandor 0.0830 OH 43,500.00 3,610.50
Jumlah (2) 68,822.00
Jumlah (1) + (2) 807,699.92
G.019 Membuat 1 m³ beton mutu f'c=24 Mpa (K 275); slump (12 ± 2) cm; w/c = 0,53
Bahan
Portland Cement (PC) 406.0000 kg 1,352.00 548,912.00
Pasir Beton (PB) 0.4886 m³ 130,000.00 63,514.29
Koral (Batu pecah tangan 2-3) 0.7600 m³ 195,000.00 148,200.00
Air 215.0000 liter 25.00 5,375.00
Jumlah (1) 766,001.29
Tenaga
Pekerja 1.6500 OH 32,000.00 52,800.00
Tukang Batu 0.2750 OH 40,500.00 11,137.50
Kepala Tukang 0.0280 OH 45,500.00 1,274.00
Mandor 0.0830 OH 43,500.00 3,610.50
Jumlah (2) 68,822.00
Jumlah (1) + (2) 834,823.29
G.020 Membuat 1 m³ beton mutu f'c=26,4 Mpa (K 300); slump (12 ± 2) cm; w/c = 0,52
Bahan
Portland Cement (PC) 413.0000 kg 1,352.00 558,376.00
Pasir Beton (PB) 0.4864 m³ 130,000.00 63,235.71
Koral (Batu pecah tangan 2-3) 0.7563 m³ 195,000.00 147,477.78
Air 215.0000 liter 25.00 5,375.00
Jumlah (1) 774,464.49
Tenaga
Pekerja 1.6500 OH 32,000.00 52,800.00
Tukang Batu 0.2750 OH 40,500.00 11,137.50
Kepala Tukang 0.0280 OH 45,500.00 1,274.00
Mandor 0.0830 OH 43,500.00 3,610.50
Jumlah (2) 68,822.00
Jumlah (1) + (2) 843,286.49
G.021 Membuat 1 m³ beton mutu f'c=28,8 Mpa (K 325); slump (12 ± 2) cm; w/c = 0,49
Bahan
Portland Cement (PC) 439.0000 kg 1,352.00 593,528.00
Pasir Beton (PB) 0.4786 m³ 130,000.00 62,214.29
Koral (Batu pecah tangan 2-3) 0.7452 m³ 195,000.00 145,311.11
Air 215.0000 liter 25.00 5,375.00
Jumlah (1) 806,428.40
Tenaga
Pekerja 1.6500 OH 32,000.00 52,800.00
Tukang Batu 0.2750 OH 40,500.00 11,137.50
Kepala Tukang 0.0280 OH 45,500.00 1,274.00
Mandor 0.0830 OH 43,500.00 3,610.50
Jumlah (2) 68,822.00
Jumlah (1) + (2) 875,250.40
G.022 Membuat 1 m³ beton mutu f'c=31,2 Mpa (K 350); slump (12 ± 2) cm; w/c = 0,48
Bahan
Portland Cement (PC) 448.0000 kg 1,352.00 605,696.00
Pasir Beton (PB) 0.4764 m³ 130,000.00 61,935.71
Koral (Batu pecah tangan 2-3) 0.7407 m³ 195,000.00 144,444.44
Air 215.0000 liter 25.00 5,375.00
Jumlah (1) 817,451.16
Tenaga
Pekerja 1.6500 OH 32,000.00 52,800.00
Tukang Batu 0.2750 OH 40,500.00 11,137.50
Kepala Tukang 0.0280 OH 45,500.00 1,274.00
Mandor 0.0830 OH 43,500.00 3,610.50
Jumlah (2) 68,822.00
Jumlah (1) + (2) 886,273.16
HARGA SAT JUMLAH
NO KOEF SAT
Rp. Rp.
1 2 3 4 5 6=(3x5)
G.024 Memasang 10 kg jaring kawat baja /wiremesh
Bahan
Jaring Kawat Baja dilas/wiremesh 10.5000 kg 37,000.00 388,500.00
Kawat Beton 0.1000 kg 15,600.00 1,560.00
Jumlah (1) 390,060.00
Tenaga
Pekerja 0.0800 OH 32,000.00 2,560.00
Tukang Besi 0.0400 OH 40,500.00 1,620.00
Kepala Tukang 0.0040 OH 45,500.00 182.00
Mandor 0.0040 OH 43,500.00 174.00
Jumlah (2) 4,536.00
Jumlah (1) + (2) 394,596.00
G.025 Memasang 1 m² bekisting untuk pondasi
Bahan
Kayu Pinus/Kayu Rawa 0.0400 m³ 2,080,000.00 83,200.00
Paku 5 cm - 10 cm 0.3000 kg 15,600.00 4,680.00
Minyak Bekisting 0.1000 liter 3,900.00 390.00
Jumlah (1) 88,270.00
Tenaga
Pekerja 0.5200 OH 32,000.00 16,640.00
Tukang Kayu 0.2600 OH 40,500.00 10,530.00
Kepala Tukang 0.0260 OH 45,500.00 1,183.00
Mandor 0.0260 OH 43,500.00 1,131.00
Jumlah (2) 29,484.00
Jumlah (1) + (2) 117,754.00
G.030 Memasang 1 m² bekisting untuk dinding
Bahan
Kayu Pinus/Kayu Rawa 0.0300 m³ 2,080,000.00 62,400.00
Paku 5 cm - 12 cm 0.4000 kg 15,600.00 6,240.00
Minyak Bekisting 0.2000 liter 3,900.00 780.00
Balok Kayu Meranti Batu 5/7 0.0200 m³ 4,680,000.00 93,600.00
Plywood tebal 9 mm 0.3500 lembar 162,500.00 56,875.00
Dolken Ø (8-10) cm 12.0000 m' 1,300.00 15,600.00
Formite/Penjaga jarak Bekisting/spacer 4.0000 buah 2,200.00 8,800.00
Jumlah (1) 244,295.00
Tenaga
Pekerja 0.6600 OH 32,000.00 21,120.00
Tukang Kayu 0.3300 OH 40,500.00 13,365.00
Kepala Tukang 0.0330 OH 45,500.00 1,501.50
Mandor 0.0330 OH 43,500.00 1,435.50
Jumlah (2) 37,422.00
Jumlah (1) + (2) 281,717.00
G.032 Memasang 1 m² jembatan untuk pengecoran beton
Bahan
Kayu Pinus/Kayu Rawa 0.0264 m³ 2,080,000.00 54,912.00
Paku 5 cm - 12 cm 0.6000 kg 15,600.00 9,360.00
Dolken Ø 12 cm 2.0000 m' 15,600.00 31,200.00
Jumlah (1) 95,472.00
Tenaga
Pekerja 0.1500 OH 32,000.00 4,800.00
Tukang Kayu 0.0500 OH 40,500.00 2,025.00
Kepala Tukang 0.0050 OH 45,500.00 227.50
Mandor 0.0080 OH 43,500.00 348.00
Jumlah (2) 7,400.50
Jumlah (1) + (2) 102,872.50
HARGA SAT JUMLAH
NO KOEF SAT
Rp. Rp.
1 2 3 4 5 6=(3x5)
G.033 Memasang 1 m³ pondasi beton bertulang (150 kg besi + bekisting)
Bahan
Kayu Pinus/Kayu Rawa 0.2000 m³ 2,080,000.00 416,000.00
Paku 5 cm - 12 cm 1.5000 kg 15,600.00 23,400.00
Minyak Bekisting 0.4000 liter 3,900.00 1,560.00
Besi Beton (polos/ulir) 157.5000 kg 8,650.00 1,362,375.00
Kawat Beton 2.2500 kg 15,600.00 35,100.00
Portland Cement (PC) 336.0000 kg 1,352.00 454,272.00
Pasir Beton (PB) 0.5400 m³ 130,000.00 70,200.00
Koral (Batu pecah tangan 2-3) 0.8100 m³ 195,000.00 157,950.00
Jumlah (1) 2,520,857.00
Tenaga
Pekerja 5.3000 OH 32,000.00 169,600.00
Tukang Batu 0.2750 OH 40,500.00 11,137.50
Tukang Kayu 1.3000 OH 40,500.00 52,650.00
Tukang Besi 1.0500 OH 40,500.00 42,525.00
Kepala Tukang 0.2620 OH 45,500.00 11,921.00
Mandor 0.2650 OH 43,500.00 11,527.50
Jumlah (2) 299,361.00
Jumlah (1) + (2) 2,820,218.00
G.042 Menghamparkan 1 m³ beton mutu K-125 (ready mix)
Bahan
Beton Ready Mix (K-125) 1.0000 m³ 805,000.00 805,000.00
Jumlah (1) 805,000.00
Tenaga
Pekerja 2.5000 OH 32,000.00 80,000.00
Tukang Batu 0.2500 OH 40,500.00 10,125.00
Kepala Tukang 0.1000 OH 45,500.00 4,550.00
Mandor 0.0100 OH 43,500.00 435.00
Alat Bantu (slang + tes lab.) 0.0450 lot 56,870.00 2,559.15
Jumlah (2) 95,110.00
Jumlah (1) + (2) 900,110.00
G.043 Menghamparkan 1 m³ beton mutu K-175 (ready mix)
Bahan
Beton Ready Mix (K-175) 1.0000 m³ 819,000.00 819,000.00
Jumlah (1) 819,000.00
Tenaga
Pekerja 2.5000 OH 32,000.00 80,000.00
Tukang Batu 0.2500 OH 40,500.00 10,125.00
Kepala Tukang 0.1000 OH 45,500.00 4,550.00
Mandor 0.0100 OH 43,500.00 435.00
Alat Bantu (slang + tes lab.) 0.0450 lot 56,870.00 2,559.15
Jumlah (2) 95,110.00
Jumlah (1) + (2) 914,110.00
G.044 Menghamparkan 1 m³ beton mutu K-225 (ready mix)
Bahan
Beton Ready Mix (K-225) 1.0000 m³ 877,500.00 877,500.00
Jumlah (1) 877,500.00
Tenaga
Pekerja 2.5000 OH 32,000.00 80,000.00
Tukang Batu 0.2500 OH 40,500.00 10,125.00
Kepala Tukang 0.1000 OH 45,500.00 4,550.00
Mandor 0.0100 OH 43,500.00 435.00
Alat Bantu (slang + tes lab.) 0.0450 lot 56,870.00 2,559.15
Jumlah (2) 95,110.00
Jumlah (1) + (2) 972,610.00
G.045 Menghamparkan 1 m³ beton mutu K-250 (ready mix)
Bahan
Beton Ready Mix (K-250) 1.0000 m³ 910,000.00 910,000.00
Jumlah (1) 910,000.00
Tenaga
Pekerja 2.5000 OH 32,000.00 80,000.00
Tukang Batu 0.2500 OH 40,500.00 10,125.00
Kepala Tukang 0.1000 OH 45,500.00 4,550.00
Mandor 0.0100 OH 43,500.00 435.00
Alat Bantu (slang + tes lab.) 0.0450 lot 56,870.00 2,559.15
Jumlah (2) 95,110.00
Jumlah (1) + (2) 1,005,110.00
HARGA SAT JUMLAH
NO KOEF SAT
Rp. Rp.
1 2 3 4 5 6=(3x5)
G.046 Menghamparkan 1 m³ beton mutu K-275 (ready mix)
Bahan
Beton Ready Mix (K-275) 1.0000 m³ 939,900.00 939,900.00
Jumlah (1) 939,900.00
Tenaga
Pekerja 2.5000 OH 32,000.00 80,000.00
Tukang Batu 0.2500 OH 40,500.00 10,125.00
Kepala Tukang 0.1000 OH 45,500.00 4,550.00
Mandor 0.0100 OH 43,500.00 435.00
Alat Bantu (slang + tes lab.) 0.0450 lot 56,870.00 2,559.15
Jumlah (2) 95,110.00
Jumlah (1) + (2) 1,035,010.00
G.047 Menghamparkan 1 m³ beton mutu K-300 (ready mix)
Bahan
Beton Ready Mix (K-300) 1.0000 m³ 1,017,900.00 1,017,900.00
Jumlah (1) 1,017,900.00
Tenaga
Pekerja 2.5000 OH 32,000.00 80,000.00
Tukang Batu 0.2500 OH 40,500.00 10,125.00
Kepala Tukang 0.1000 OH 45,500.00 4,550.00
Mandor 0.0100 OH 43,500.00 435.00
Alat Bantu (slang + tes lab.) 0.0450 lot 56,870.00 2,559.15
Jumlah (2) 95,110.00
Jumlah (1) + (2) 1,113,010.00
G.048 Menghamparkan 1 m³ beton mutu K-350 (ready mix)
Bahan
Beton Ready Mix (K-350) 1.0000 m³ 1,072,500.00 1,072,500.00
Jumlah (1) 1,072,500.00
Tenaga
Pekerja 2.5000 OH 32,000.00 80,000.00
Tukang Batu 0.2500 OH 40,500.00 10,125.00
Kepala Tukang 0.1000 OH 45,500.00 4,550.00
Mandor 0.0100 OH 43,500.00 435.00
Alat Bantu (slang + tes lab.) 0.0450 lot 56,870.00 2,559.15
Jumlah (2) 95,110.00
Jumlah (1) + (2) 1,167,610.00
G.049 Memasang 1 m² plat beton "bondex"
Bahan
Bondex 1.0100 kg 193,600.00 195,536.00
Kawat Las Rb 26 0.1000 kg 28,600.00 2,860.00
Jumlah (1) 198,396.00
Tenaga
Pekerja 0.0500 OH 32,000.00 1,600.00
Tukang Besi 0.0300 OH 40,500.00 1,215.00
Mandor 0.0100 OH 43,500.00 435.00
Shear Connector 1.0000 ls 18,550.00 18,550.00
Jumlah (2) 21,800.00
Jumlah (1) + (2) 220,196.00
G.050 Pembesian 1 kg dengan besi beton
Bahan
Besi Beton 1.0500 kg 8,650.00 9,082.50
Kawat Beton 0.0150 kg 15,600.00 234.00
Jumlah (1) 9,316.50
Tenaga
Pekerja 0.0400 OH 32,000.00 1,280.00
Tukang Besi 0.0150 OH 40,500.00 607.50
Kepala Tukang 0.0150 OH 45,500.00 682.50
Mandor 0.0075 OH 43,500.00 326.25
Peralatan, Spancer 0.0200 lot 1,000.00 20.00
Jumlah (2) 2,916.25
Jumlah (1) + (2) 12,232.75
HARGA SAT JUMLAH
NO KOEF SAT
Rp. Rp.
1 2 3 4 5 6=(3x5)
G.051 1 KG PEK. BAJA PROFIL, IWF
Bahan
Besi IWF 1.0500 kg 12,600.00 13,230.00
Meni Besi 0.0800 kg 26,000.00 2,080.00
Jumlah (1) 15,310.00
Tenaga
Pekerja 0.0400 OH 32,000.00 1,280.00
Tukang Besi 0.0150 OH 40,500.00 607.50
Kepala Tukang 0.0150 OH 45,500.00 682.50
Mandor 0.0075 OH 43,500.00 326.25
Peralatan, Spancer 0.0200 lot 1,000.00 20.00
Jumlah (2) 2,916.25
Jumlah (1) + (2) 18,226.25
G.051.A 1 KG PEK. BONGKAR PASANG KEMBALI BAJA PROFIL, IWF
Bahan
Meni Besi 0.0800 kg 26,000.00 2,080.00
Jumlah (1) 2,080.00
Tenaga
Pekerja 0.0400 OH 32,000.00 1,280.00
Tukang Besi 0.0150 OH 40,500.00 607.50
Kepala Tukang 0.0150 OH 45,500.00 682.50
Mandor 0.0075 OH 43,500.00 326.25
Peralatan, Spancer 0.0200 lot 1,000.00 20.00
Jumlah (2) 2,916.25
Jumlah (1) + (2) 4,996.25
K.004 Mengerjakan 1cm' Pengelasan dengan las listrik
Bahan
Kawat las Listrik 0.0400 kg 28,600.00 1,144.00
Solar 0.0300 Ltr 5,850.00 175.50
Minyak Pelumas 0.0040 Ltr 33,150.00 132.60
Jumlah (1) 1,452.10
Tenaga
Pekerja 0.0040 OH 32,000.00 128.00
Tukang Besi 0.0020 OH 40,500.00 81.00
Kepala Tukang 0.0002 OH 45,500.00 9.10
Mandor 0.0002 OH 43,500.00 8.70
Sewa Alat 0.0170 Jam 75,000.00 1,275.00
Jumlah (2) 1,501.80
Jumlah (1) + (2) 2,953.90

N. PEKERJAAN PENGECATAN SNI


N.008 Mengecat 1 m² bidang tembok baru (1 lps plamir, 1 lps cat dsr, 2 lps cat penutup)
Bahan
Plamir 0.1000 kg 13,000.00 1,300.00
Cat Dasar 0.1000 kg 20,800.00 2,080.00
Cat Penutup 0.2600 kg 20,800.00 5,408.00
Jumlah (1) 8,788.00
Tenaga
Pekerja 0.0200 OH 32,000.00 640.00
Tukang Cat 0.0630 OH 40,500.00 2,551.50
Kepala Tukang 0.0063 OH 45,500.00 286.65
Mandor 0.0025 OH 43,500.00 108.75
Jumlah (2) 3,586.90
Jumlah (1) + (2) 12,374.90
HARGA SAT JUMLAH
NO KOEF SAT
Rp. Rp.
1 2 3 4 5 6=(3x5)
N.010 Mengecat 1 m² permukaan baja dengan meni besi
Bahan
Meni Besi 0.1000 kg 26,000.00 2,600.00
Kuas 0.0100 bh 5,200.00 52.00
Jumlah (1) 2,652.00
Tenaga
Pekerja 0.0200 OH 32,000.00 640.00
Tukang Cat 0.2000 OH 40,500.00 8,100.00
Kepala Tukang 0.0200 OH 45,500.00 910.00
Mandor 0.0100 OH 43,500.00 435.00
Jumlah (2) 10,085.00
Jumlah (1) + (2) 12,737.00
N.011 Mengecat 1 m² permukaan baja dengan meni besi dan perancah
Bahan
Meni Besi 0.1000 kg 26,000.00 2,600.00
Kuas 0.0100 bh 5,200.00 52.00
Perancah Kayu Punak 0.0020 m³ 4,946,500.00 9,893.00
Jumlah (1) 12,545.00
Tenaga
Pekerja 0.2500 OH 32,000.00 8,000.00
Tukang Cat 0.2250 OH 40,500.00 9,112.50
Kepala Tukang 0.0225 OH 45,500.00 1,023.75
Mandor 0.0075 OH 43,500.00 326.25
Jumlah (2) 18,462.50
Jumlah (1) + (2) 31,007.50
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN PENYEDIAAN KERIKIL SUNGAI (TIDAK DISARING)

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (Menggunakan buruh) K.013

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Truck diisi dengan tenaga Manusia di sungai 1. Menggunakan tenaga Manusia (60 m3/hari) dalam dua kelompok
2. Truck mengangkut kerikil sungai kelokasi pekerjaan penimbuanan 2. Muatan Truck perjam (1m3/orang/hari)
3. Muatan dibongkar dengan tenaga Manusia 3. Material dikirim kelokasi pekerajaan penimbunan
4. Pengambilan Material dengan Dipungut pembayaran ganti rugi royalti yang berlaku
5. Volume yang diukur berdasarkan 3 ton/trck (lepas BJ = 1,5)
6. Penggunaan Alat Bantu rata - rata 1 set untuk 1 orang perbulan

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 2.00 1 L.061 2 43,500.00 87,000.00
E Sopir Material / Truck 6.00 1 L.091 6 43,000.00 258,000.00
K Buruh Lapangan tak terlatih 60.00 1 L.101 60 30,000.00 1,800,000.00
E
R
J
A
PEKERJAAN 2,145,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit) ( Rp. ) ( Rp. )
M Sirtu royalti 60.00 m3 MR.42 30,000.00 1,800,000.00
A Alat - alat bantu ( set @ 3 alat ) 2.50 set M.170 55,000.00 137,500.00
T
E
R
I
A
L
MATERIAL 1,937,500.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E FLAT BED TRUCK 4 ton 6.00 1 E.221 36.00 139,682.90 5,028,584.53
R
A
L
A
T
A
N
PERALATAN 5,028,584.53
TOTAL ( Rp ) 9,111,084.53

VOLUME /
QUANTITY : 60 SATUAN m3 HARGA SATUAN 151,851.41 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN PRODUKSI KERIKIL SUNGAI (TERSARING)

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (Menggunakan buruh) K.016

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Buldozer menimbun Stock disungai 1. Menggunakan alar berat (60 m3/hari)
2. Loader mengangakt muatan trck 2. Wheel Loader mengisi 6 truck/jam ( 6jam kerja)
3. Kerikil disaring diintalasi pengaringan sesuai ukuran yang 3. Pengambilan Material dipungut pembayaran ganti rugi yang berlaku
dikehendaki 4. Volume yang diukur berdasarkan 5 ton/truck (lepas BJ = 1,5)
4. Dump truck mengangkut kerikil sungai yang disaring ke lokasi 5. 1,0 trip/jam/truck
penimbunan atau pekerjaan 6. Pengguanaan alat bantu rata - rata 1 set untuk 1 orang per bulan
7. Kapasitas screening rata - rata 18 ton.jam, dengan ditambah bagian
halus 20% dan terjadi oversize 30 %

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Operator terlatih 3.00 1 L.081 3 55,000.00 165,000.00
K Operator semi terlatih 1.00 1 L.082 1 50,000.00 50,000.00
E Sopir Material /Truck 4.00 1 L.091 4 43,000.00 172,000.00
R Buruh Lapangan tak terlatih 4.00 1 L.101 4 30,000.00 120,000.00
J Buruh Lapangan agak terlatih 4.00 1 L.103 4 31,000.00 124,000.00
A
PEKERJAAN 674,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Kerikil Sungai Royalti 67.50 m3 MR.12 30,000.00 2,025,000.00
T Ganti rugi sungai royalti 12.50 m3 MR.42 30,000.00 375,000.00
E Alat - alat bantu ( set @ 3 alat ) 0.20 set M.170 55,000.00 11,000.00
R
I
A
L
MATERIAL 2,411,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E BULDOZER 1.00 1 E.001 3 351,790.48 1,055,371.44
R SCREENING PLANT 1.00 1 E.040 5 199,108.50 995,542.52
A LOADER WHEELED 1.00 1 E.052 5 281,834.30 1,409,171.52
L DUMP TRUCK 5,00 ton 4.00 1 E.212 24 224,269.48 5,382,467.42
A
T
A
N
PERALATAN 8,842,552.91
TOTAL ( Rp ) 11,928,052.91

VOLUME /
QUANTITY : 60 SATUAN m3 HARGA SATUAN 198,800.88 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN PRODUKSI KERIKIL PECAH TERSARING (ALAT)

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN MEMPERGUNAKAN KERIKIL SUNGAI (menggunakan alat) K.017

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Buldozer membuat timbunan dipinggir sungai 1. Menggunakan alat berat(60 m3/hari), materail diolah dua kali
2. Wheel Loader memuat ke truck yang memebongkar batu 2. Batu diambil dari sungai & dianggkut ke pemecah batu
ditempat penyaringan 3. 33,3% batu lolos saringan pada mesin dengan produksi 15 ton/jam
3. Batu Over size dipecah Mesin 4. 70% batu yang sudah dipecah dicampur kembali dengan batu dari sungai yang lolos
4. Hasil pecahan batu dicampur kembali daenga batu saringan
hasil dari sungai yang lolos saringan 5. Volume yang diukur berdasarkan 5 ton/truck (lepas) 1,0 trip/tr BJ = 1,5
6. Rata - rata umur alat bantu 1 bualan/orang/set

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Operator terlatih 3.00 1 L.081 3 55,000.00 165,000.00
K Operator Kurang terlatih 2.00 1 L.082 2 50,000.00 100,000.00
E Sopir Material /Truck 2.00 1 L.091 2 43,000.00 86,000.00
R Buruh Lapangan tak terlatih 4.00 1 L.101 4 30,000.00 120,000.00
J Buruh Lapangan agak terlatih 4.00 1 L.103 4 31,000.00 124,000.00
A
PEKERJAAN 638,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Kerikil Sungai Royalti 72.00 m3 MR.12 30,000.00 2,160,000.00
T Alat - alat bantu ( set @ 3 alat ) 0.20 set M.170 55,000.00 11,000.00
E
R
I
A
L
MATERIAL 2,171,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E BULDOZER 1.00 1 E.001 6 351,790.48 2,110,742.88
R CRUSHER 30t/hr 1.00 1 E.031 6 542,928.50 3,257,570.98
A LOADER WHEELED 1.00 1 E.052 6 281,834.30 1,691,005.83
L DUMP TRUCK 5,00 ton 2.00 1 E.212 12 224,269.48 2,691,233.71
A
T
A
N
PERALATAN 9,750,553.40
TOTAL ( Rp ) 12,560,053.40

VOLUME /
QUANTITY : 60 SATUAN m3 HARGA SATUAN 209,334.22 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN PRODUKSI BATU PECAH TERSARING (ALAT)

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN MEMPERGUNAKAN BATU QUARRY (menggunakan alat) K.018

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Buldozer mengupas lapangan tertutup dan membuat timbunan 1. Menggunakan alat berat(60 m3/hari), materail diolah dua kali
2. Wheel Loader memuat ke truck dan memebongkar ditempat 2. Pemecah dalam dua tahap produksi akhir 18t/jam
penyaringan 3. Pemakai ulang 3 t/jam dan 8% hilang
3. Pemecah batu memecah batu Over size 4. Volume diukur atas dasar 5 t/truck lepas ( BJ = 1,5)
4. Produksi batu pecah disaring 5. 1 rit pp/jam/truck
5. Penimbunan batu pecah tersaring dala timbunan terpisah 6. Rata - rata umur alat bantu 1 bualan/orang/set

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 3.00 1 L.061 3 43,500.00 130,500.00
E Operator terlatih 3.00 1 L.081 3 55,000.00 165,000.00
K Operator Kurang terlatih 2.00 1 L.082 2 50,000.00 100,000.00
E Sopir Material /Truck 4.00 1 L.091 4 43,000.00 172,000.00
R Buruh Lapangan tak terlatih 4.00 1 L.101 4 30,000.00 120,000.00
J Buruh Lapangan agak terlatih 90.00 1 L.103 90 31,000.00 2,790,000.00
A
PEKERJAAN 3,477,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Batu quarry royalti 65.00 m3 MR.11 21,000.00 1,365,000.00
T Alat - alat bantu ( set @ 3 alat ) 3.60 set M.170 55,000.00 198,000.00
E
R
I
A
L
MATERIAL 1,563,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E BULDOZER 1.00 1 E.001 6 351,790.48 2,110,742.88
R CRUSHER 30t/hr 1.00 1 E.031 6 542,928.50 3,257,570.98
A LOADER WHEELED 1.00 1 E.052 6 281,834.30 1,691,005.83
L DUMP TRUCK 5,00 ton 4.00 1 E.212 24 224,269.48 5,382,467.42
A
T
A
N
PERALATAN 12,441,787.11
TOTAL ( Rp ) 17,482,287.11

VOLUME /
QUANTITY : 60 SATUAN m3 HARGA SATUAN 291,371.45 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN MEMPRODUKSI CAMPURAN LATASIR

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ( MENGGUNAKAN BURUH ) K.020

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Semua material dikirim oleh suplier 1. Latasir dihasilkan dilapangan
2. Aspal dipanaskan agar tersedia kpada waktunya
3. Hasil dimuat dan digelar dilapangan
4. Rata - rata umur alat bantu, sebulan/orang/set
5. Sesuai spesifikasi BM no. 12/PT/B/1983

PEKERJA VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 15.00 1 L.061 15 43,500.00 652,500.00
E Buruh Lapangan tak terlatih 17.00 1 L.101 17 30,000.00 510,000.00
K Buruh Lapangan semi terlatih 403.00 1 L.103 403 31,000.00 12,493,000.00
E
R
J
A
PEKERJA 13,655,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M Agregat Halus / Pasir Bersih 56.61 m3 M.041 130,000.00 7,359,300.00
A Aspal bitumen 9,425.00 kg M.061 7,720.00 72,761,000.00
T Alat - alat bantu (set @ 3 alat) 15.00 set M.170 55,000.00 825,000.00
E Kayu bakar 47.00 m3 M.070 149,500.00 7,026,500.00
R
I
A
L
MATERIAL 87,971,800.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R
A
L
A
T
A
N
PERALATAN -
TOTAL ( Rp ) 101,627,300.00

VOLUME /
QUANTITY : 100 SATUAN ton HARGA SATUAN 1,016,273.00 Per ton
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN MEMPRODUKSI CAMPURAN ASPAL BETON UNTUK LAPIS PONDASI ATAS

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (LASTA ATAS) Menggunakan alat K.026

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Semua material dikirim oleh Leveransir 1. ATB dibuat di AMP Produksi 100 ton/hari
2. loader menjaga bin tatap penuh 2. Dipakai Agregat pecah tersaring
3. Produksi mesin 100 ton/hari 3. Aspal dipanaskan terlebih dahulu agar aspal sudah siap pada waktunya
4' Dimuat dengan dump truck ditutup trepal untuk menjaga 4. Rata - rata umur alat bantu 1 bulan (orang) set
temperatur 5. Spek B.M No. 03/PT/B/1983

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 2.00 1 L.061 2.00 43,500.00 87,000.00
E Mekanik 1.00 1 L.071 1.00 45,500.00 45,500.00
K Operator terlatih 4.00 1 L.081 4.00 55,000.00 220,000.00
E Operator kurang terlatih 3.00 1 L.082 3.00 50,000.00 150,000.00
R Sopir Material /Truck 7.00 1 L.091 7.00 43,000.00 301,000.00
J Buruh Lapangan tak terlatih 7.00 1 L.101 7.00 30,000.00 210,000.00
A Buruh lapangan agak terlatih 7.00 1 L.103 7.00 31,000.00 217,000.00
PEKERJA 1,230,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M Agregat Halus 25.00 m3 M.041 130,000.00 3,250,000.00
A Aspal curah 5,900.00 kg M.062 5,590.00 32,981,000.00
T Alat - alat bantu (set @ 3 alat) 0.20 set M.170 55,000.00 11,000.00
E Kerikil sungai Royalti 47.00 m3 K.017 209,334.22 9,838,708.34
R
I
A
L
MATERIAL 46,080,708.34
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P LOADER WHEELED 2.00 1 E.052 9 281,834.30 2,536,508.74
E ASPHALT MIXING PLAN 30t/h 1.00 1 E.155 5 2,303,215.39 11,516,076.96
R DUMP TRUCK 5,00 ton 7.00 1 E.212 35 224,269.48 7,849,431.66
A BULDOZER 1.00 1 E.001 4 351,790.48 1,407,161.92
L -
A
T
A
N
PERALATAN 23,309,179.28
TOTAL ( Rp ) 70,620,387.62

VOLUME /
QUANTITY : 100 SATUAN ton HARGA SATUAN 706,203.88 Per ton
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN MEMPRODUKSI CAMPURAN ASPAL BETON UNTUK LAPIS PONDASI ATAS

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (LASTA ATAS) Menggunakan Buruh K.026.A

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Semua material dikirim oleh Leveransir 1. ATB dibuat di lokasi dengan tenaga buruh
2. loader menjaga bin tatap penuh 2. Dipakai meterial batu pecah 0,5 - 1 cm, 1 - 2 cm, dan abu batu
3. Produksi mesin 100 ton/hari 3. Aspal dipanaskan terlebih dahulu agar aspal sudah siap pada waktunya
4. Rata - rata umur alat bantu 1 bulan (orang) set
5. Spek B.M No. 03/PT/B/1983

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 2.00 1 L.061 2.00 43,500.00 87,000.00
E
K
E
R Sopir Material /Truck 6.00 1 L.091 6.00 43,000.00 258,000.00
J Buruh Lapangan tak terlatih 113.00 1 L.101 113.00 30,000.00 3,390,000.00
A Buruh lapangan agak terlatih 113.00 1 L.103 113.00 31,000.00 3,503,000.00
PEKERJA 7,238,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Aspal Bitumen 5,900.00 kg M.062 7,720.00 45,548,000.00
T Alat - alat bantu (set @ 3 alat) 0.20 set M.170 55,000.00 11,000.00
R Batu Pecah mesin 1 - 2 cm 29.00 m3 M.025 235,000.00 6,815,000.00
I Batu Pecah mesin 0.5 - 1 cm 21.00 m3 M.026 247,000.00 5,187,000.00
A Abu batu 22.00 m3 M.027 230,000.00 5,060,000.00
L Kayu bakar 3.16 m3 M.070 149,500.00 472,778.80
minyak bakar 245.84 lt M.065 4,550.00 1,118,550.62
MATERIAL 64,212,329.42
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R DUMP TRUCK 5,00 ton 7.00 1 E.212 35 224,269.48 7,849,431.66
A
L -
A
T
A
N
PERALATAN 7,849,431.66
TOTAL ( Rp ) 79,299,761.08

VOLUME /
QUANTITY : 100 SATUAN ton HARGA SATUAN 792,997.61 Per ton
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN MEMPRODUKSI DAN MENGGANGKUT ASPAL BETON

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN ALAT/AMT) K.040

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Semua material dikirim oleh Leveransir 1. Memakai alat berat (100t/hari)
2. loader menjaga bin tatap penuh 2. Memakai Agregat pecah tersaring
3. Produksi mesin 20 t/jam - 5 jam/hari 3. AMP didirikan didekat penimbunan material
4. Dump truck memeuat dan membongkar sampai screeder 4. Aspal dipanaskan lebih dulu agar aspal sudah siap saaat dimulai
5. Hasil diangkut dengan truck 5 t dan dikirim sampai spreeder
6. Rata - rata umur alat bantu 1 bulan/orang/set
7. Spek B.M No. 03/PT/B/1983

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 2.00 1 L.061 2 43,500.00 87,000.00
E Mekanik terlatih 1.00 1 L.071 1 45,500.00 45,500.00
K Operator terlatih 3.00 1 L.081 3 55,000.00 165,000.00
E Operator semi terlatih 3.00 1 L.082 3 50,000.00 150,000.00
R Sopir 6.00 1 L.091 6 43,000.00 258,000.00
J Buruh Lapangan tak terlatih 6.00 1 L.101 6 30,000.00 180,000.00
A Buruh lapangan semi terlatih 7.00 1 L.103 7 31,000.00 217,000.00
PEKERJA 1,102,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M Pasir bersih 30.00 m3 M.041 130,000.00 3,900,000.00
A Aspal Bitumen 6,330.00 kg M.061 7,720.00 48,867,600.00
T Semen 100.00 kg M.080 1,352.00 135,200.00
E Kerikil sungai Royalti 33.50 m3 MR.12 30,000.00 1,005,000.00
R Alat - alat Bantu (set @ 3 alat) 0.20 set M.170 55,000.00 11,000.00
I
A
L
MATERIAL 53,918,800.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P LOADER WHEELED 1.00 1 E.052 7 281,834.30 1,972,840.13
E ASPHALT MIXING PLAN 30t/h 1.00 1 E.155 5 2,303,215.39 11,516,076.96
R DUMP TRUCK 5,00 ton 6.00 1 E.212 34 224,269.48 7,625,162.18
A BULDOZER 1.00 1 E.001 2 351,790.48 703,580.96
L CRUSHER 30t/hr 1.00 1 E.031 2 542,928.50 1,085,856.99
A
T
A
N
PERALATAN 22,903,517.23
TOTAL ( Rp ) 77,924,817.23

VOLUME /
QUANTITY : 100 SATUAN ton HARGA SATUAN 779,248.17 Per ton
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN MEMEPRODUKSI LAPIS TIPIS ASPAL BETON

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (LATASTON) (Mengggunakan Alat/Mesin) K.035

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Semua material dikirim oleh Leveransir 1. ATB dibuat di AMP Produksi 100 ton/hari
2. loader menjaga bin tatap penuh 2. Dipakai Agregat pecah tersaring
3. Produksi mesin 100 ton/hari 3. Aspal dipanaskan terlebih dahulu agar aspal sudah siap pada waktunya
4. Dimuat dengan dump truck ditutup trepal untuk menjaga 4. Rata - rata umur alat bantu 1 bulan (orang) set
temperatur 5. Spek B.M No. 03/PT/B/1983

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Mekanik 1.00 1 L.071 1 45,500.00 45,500.00
K Operator terlatih 3.00 1 L.081 3 55,000.00 165,000.00
E Operator kurang terlatih 2.00 1 L.082 2 50,000.00 100,000.00
R Sopir Material /Truck 5.00 1 L.091 5 43,000.00 215,000.00
J Buruh Lapangan tak terlatih 5.00 1 L.101 5 30,000.00 150,000.00
A Buruh lapangan agak terlatih 6.00 1 L.103 6 31,000.00 186,000.00
PEKERJA 905,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M Kerikil sungai Royalti 14.00 m3 MR.12 30,000.00 420,000.00
A Agregat Halus / pasirBersih 38.00 m3 M.041 130,000.00 4,940,000.00
T Aspal Curah 9,000.00 kg M.062 5,590.00 50,310,000.00
E
R Alat - alat Bantu (set @ 3 alat) 0.20 set M.107 55,000.00 11,000.00
I
A
L
MATERIAL 55,681,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P LOADER WHEELED 1.00 1 E.052 6 281,834.30 1,691,005.83
E ASPHALT MIXING PLAN 30t/h 1.00 1 E.155 5 2,303,215.39 11,516,076.96
R DUMP TRUCK 5,00 ton 5.00 1 E.212 28 224,269.48 6,279,545.33
A BULDOZER 1.00 1 E.001 1 351,790.48 351,790.48
L CRUSHER 30t/hr 1.00 1 E.031 1 542,928.50 542,928.50
A
T
A
N
PERALATAN 20,381,347.09
TOTAL ( Rp ) 76,967,347.09

VOLUME /
QUANTITY : 100 SATUAN ton HARGA SATUAN 769,673.47 Per ton
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN MEMBUAT PARIT GALIAN TANAH

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (menggugunakan Buruh) K.110

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Galian Parit 1. Menggunakan tenaga Manusia (100 m/hari)
2. Pembuangan Hasil galian Menggunakan Truck 2. Dimensi parit Lebar bawah = 0.50m
lebar atas = 1.30m
Kedalaman =0.60m (vol. = 0.54 m3/m')
3. 25% hasil galian dibuang setempat
4. Sisa galian dibuang 2,00 km dengan Truck
5. Menggali dan membuang dihitung 1.50 m3/orang/hari
6. Umur alat bantu rata- rata 1bulan/orang/set @ 3 alat

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


P ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
E Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
K
E Buruh Lapangan tak terlatih 36.00 1 L.101 36 30,000.00 1,080,000.00
R
J
A
PEKERJA 1,123,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
A
T
E
R
I Alat - alat Bantu (set @ 3 alat) 1.50 kg M.170 55,000.00 82,500.00
A
L
MATERIAL 82,500.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
P Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
E
R
A
L
A
T
A
N
PERALATAN -
TOTAL ( Rp ) 1,206,000.00

VOLUME /
QUANTITY : 54 SATUAN m3 HARGA SATUAN 22,333.33 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN MENGURAS/MENGGALI,MENGANGKUT & MEMBUANG HASIL KURASAN/GALIAN

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (menggugunakan Buruh) K.110.A

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Galian Parit 1. Menggunakan tenaga Manusia (44 m/hari)
2. Pembuangan Hasil galian Menggunakan Truck 2. Dimensi parit Lebar bawah = 0.50m
lebar atas = 1.30m
Kedalaman =0.60m (vol. = 0.54 m3/m')
3. 25% hasil galian dibuang setempat
4. Sisa galian dibuang 2,00 km dengan Truck
5. Menggali dan membuang dihitung 1.50 m3/orang/hari
6. Umur alat bantu rata- rata 1bulan/orang/set @ 3 alat

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


P ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
E Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
K Sopir Material /Truck 2.00 1 L.091 2 43,000.00 86,000.00
E Buruh Lapangan tak terlatih 16.00 1 L.101 16 30,000.00 480,000.00
R
J
A
PEKERJA 609,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
A
T
E
R
I Alat - alat Bantu (set @ 3 alat) 1.50 kg M.170 55,000.00 82,500.00
A
L
MATERIAL 82,500.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
E
R FLAT BED TRUCK 4 ton 2.00 1 E.221 10.00 139,682.90 1,396,829.04
A
L
A
T
A
N
PERALATAN 1,396,829.04
TOTAL ( Rp ) 2,088,829.04

VOLUME /
QUANTITY : 54 SATUAN m3 HARGA SATUAN 38,682.02 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN MEMBUAT PASANGAN BATU PADA PARIT GALIAN TANAH

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.112

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Galian tambahan (0,55 m3/m) 1. Galian parit Vo. 0.43 m3/meter
2. Pasangan Parit berdekatan dengan dinding Penahan 2. Ukuran parit bagian dalam : tebal = 20cm
tanah bial diperlukan Lebar bawah = 0.5cm ; lebar atas = 0.9 cm ; kedalamn = 0.6 meter
3. tebal pasangan 20cm 3. 40% pembuangan hasil galian dengan truck biasa,sejauh 1,00km
4. 60% dibuang ditempat
5 Bahan - bahan dikrim ditempat pekerajaan oleh leveransir
6. Hasil Produksi 60 m/hari
7. Lihat gambar

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 6 L.061 6 43,500.00 261,000.00
E Tukang 2.00 6 L.079 12 40,500.00 486,000.00
K Sopir Material / truck 1.00 2 L.091 2 43,000.00 86,000.00
E Buruh Lapangan tak terlatih 6.00 6 L.101 36 30,000.00 1,080,000.00
R Buruh Lapangan Agak terlatih 2.00 6 L.103 12 31,000.00 372,000.00
J
A
PEKERJA 2,285,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M Batu quary/batu besar belah 30.00 m3 M.010 143,000.00 4,290,000.00
A Agregat halus / pasir belah 7.50 kg M.041 130,000.00 975,000.00
T Protland Cement (PC) 4,560.00 kg M.080 1,352.00 6,165,120.00
E Alat - alat Bantu (set @ 3 alat) 1.50 Set M.170 55,000.00 82,500.00
R
I
A
L
MATERIAL 11,512,620.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E FLAT BED TTRUCK 4 ton 1.00 2 E.221 10 139,682.90 1,396,829.04
R
A
L
A
T
A
N
PERALATAN 1,396,829.04
TOTAL ( Rp ) 15,194,449.04

VOLUME /
QUANTITY : 60 SATUAN m' HARGA SATUAN 253,240.82 Per m'
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN MENGUPAS DAN MEMBERSIHKAN SEMAK PADA DAMIJA

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.210

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Mengupas dan membersihkan semak dengan tenaga manusia 1. Menggunakan tenaga manusia 99m x 100 m/hari)
pada DAWIJA ( Daerah milik jalan ) 2. Hasil kerja 25 m2/orang - hari
3. Penggunaan alat bantu rata - rata 1 bulan - orang
4. Bakar sampah dilokasi pekerjaan

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Buruh Lapangan tak terlatih 36.00 1 L.101 36 30,000.00 1,080,000.00
K
E
R
J
A
PEKERJA 1,123,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T
E Alat - alat Bantu (set @ 3 alat) 1.50 Set M.170 55,000.00 82,500.00
R
I
A
L
MATERIAL 82,500.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R
A
L
A
T
A
N
PERALATAN -
TOTAL ( Rp ) 1,206,000.00

VOLUME /
QUANTITY : 900 SATUAN m2 HARGA SATUAN 1,340.00 Per m2
KODE

DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN


DIREKTORAT BINA PROGRAM JALAN MENGGANGKUT TANAH UNTUK GALIAN DIPADATKAN

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.220

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Penggalian dan pemauatan Truck dengan tanaga Manusia 1. Menggunakan tenaga manusia (60 m3/hari)
2. Pengiriman ke tempat pekerjaan dengan Truck 2. Dipakai Material dari penggalian didaerah jalan atau tempat lain yang diperbolehkan
3. Membongkar dan Meratakan dengan tenaga Manusia 3. Jarak Angkut PP < 4km (1 Trip/jam/truck)
4. Pemadatan Lapisan - Lapisan 4. Peralatan dengan tenaga Manusia, Perlapis 10cm
5. Pemadatan dengan menggunakan mesin gilas Tandem
6. Tidak termasuk pekerjaan persiapan dilokasi pengambilan
7. Hasil pemadatan 60m3

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 3.00 1 L.061 3 43,500.00 130,500.00
E Operator Terlatih 1.00 1 L.081 1 55,000.00 55,000.00
K Sopir Material /Truck 7.00 1 L.091 7 43,000.00 301,000.00
E Buruh lapangan tak terlatih 90.00 1 L.101 90 30,000.00 2,700,000.00
R
J
A
PEKERJA 3,186,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T
E Alat - alat Bantu (set @ 3 alat) 6.00 Set M.170 55,000.00 330,000.00
R
I
A
L
MATERIAL 330,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E TANDEM ROLLER 6 - 10 TON 1.00 1 E.081 5 136,871.93 684,359.65
R TRUCK AIR ( WATER TANK TRUCK) 1.00 1 E.182 5 171,115.60 855,578.02
A FLAT BED TRUCK 6.00 1 E.221 36 139,682.90 5,028,584.53
L
A
T
A
N
PERALATAN 6,568,522.20
TOTAL ( Rp ) 10,085,022.20

VOLUME /
QUANTITY : 60 SATUAN m3 HARGA SATUAN 168,083.70 Per m3
.
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN GALIAN TANAH KONTRUKSI

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.224

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Penggalian tanah dengan tenaga Manusia (50 m3/hari) 1. Menggunakan tenaga manusia
2. Tanah galian disingkirkan sejauh minimal 30 meter 2. Kapasitas Lerja Kelompok 50m3/hari
dari lubang galian 3. Kedalaman rata - rata galian s/d 3m
4. Untuk jenis tanah berbatu, harga satuan pekerjaan K.224 dikaitkan
dengan faktor 1.5

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Buruh lapangan tak terlatih 30.00 1 L.101 30 30,000.00 900,000.00
K Buruh Lapangan terlatih 2.00 1 L.106 2 40,000.00 80,000.00
E
R
J
A
PEKERJA 1,023,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T
E Alat - alat Bantu (set @ 3 alat) 10.00 Set M.170 55,000.00 550,000.00
R
I
A
L
MATERIAL 550,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R
A
L
A
T
A
N
PERALATAN -
TOTAL ( Rp ) 1,573,500.00

VOLUME /
QUANTITY : 50 SATUAN m3 HARGA SATUAN 31,470.00 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN PENIMBUNAN DAN PEMADATAN

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (Untuk jembatan & Gorong - Gorong)(Menggunakan Buruh) K.225.B

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Struktur dibersihkan dari bahan - bahan Organik 1. Bahan timbunan mengambil dilokasi Pekerjaan
2. Timbunan kembali bagian belakang struktur 2. Timbunan dipadatkan berlapis tebal 20cm
3. Padatkan dengan stemper

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Buruh lapangan tak terlatih 8.00 1 L.101 8 30,000.00 240,000.00
K Buruh Lapangan Agak Terlatih 1.00 1 L.103 1 31,000.00 31,000.00
E
R
J
A
PEKERJA 314,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T
E Alat - alat Bantu (set @ 3 alat) 0.30 Set M.170 55,000.00 16,500.00
R
I
A
L
MATERIAL 16,500.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R
A FLAT VIBRATOR TAMPER 1.00 1 E.088 10.00 12,939.46 129,394.59
L
A
T
A
N
PERALATAN 129,394.59
TOTAL ( Rp ) 460,394.59

VOLUME /
QUANTITY : 15 SATUAN m3 HARGA SATUAN 30,692.97 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN PENIMBUNAN DAN PEMADATAN (tanah urug pilihan)

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (Untuk jembatan & Gorong - Gorong)(Menggunakan Buruh) K.225.A

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Struktur dibersihkan dari bahan - bahan Organik 1. Bahan timbunan mengambil dilokasi Pekerjaan
2. Timbunan kembali bagian belakang struktur 2. Timbunan dipadatkan berlapis tebal 10cm
3. Padatkan dengan stemper dan Mesin gilas bergetar (Vibro)

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Buruh lapangan tak terlatih 10.00 1 L.101 10 30,000.00 300,000.00
K Buruh Lapangan Agak Terlatih 3.00 1 L.103 2 31,000.00 62,000.00
E
R
J
A
PEKERJA 405,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T Tanah Urug (Timbunan) 20.00 m3 M.042.A 66,000.00 1,320,000.00
E Alat - alat Bantu (set @ 3 alat) 0.30 Set M.170 55,000.00 16,500.00
R
I
A
L
MATERIAL 1,336,500.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R MESIN GILAS BERGETAR 1 TON 1.00 1 E.087 10.00 41,535.08 415,350.77
A FLAT VIBRATOR TAMPER 2.00 1 E.088 10.00 12,939.46 129,394.59
L
A
T
A
N
PERALATAN 544,745.36
TOTAL ( Rp ) 2,286,745.36

VOLUME /
QUANTITY : 15 SATUAN m3 HARGA SATUAN 152,449.69 Per m3
KODE

DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN


DIREKTORAT BINA PROGRAM JALAN PENIMBUNAN DAN PEMADATAN(Kerikil Berpasir Alami)

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (Untuk jembatan & Gorong - Gorong)(Menggunakan Buruh) K.225

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Struktur dibersihkan dari bahan - bahan Organik 1. Bahan timbunan mengambil dilokasi Pekerjaan
2. Timbunan kembali bagian belakang struktur 2. Timbunan dipadatkan berlapis tebal 10cm
3. Padatkan dengan stemper dan Mesin gilas bergetar (Vibro)

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Buruh lapangan tak terlatih 10.00 1 L.101 10 30,000.00 300,000.00
K Buruh Lapangan Agak Terlatih 3.00 1 L.103 2 31,000.00 62,000.00
E
R
J
A
PEKERJA 405,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T Kerikil Berpasir alami*) 20.00 m3 M.042 90,000.00 1,800,000.00
E Alat - alat Bantu (set @ 3 alat) 0.30 Set M.170 55,000.00 16,500.00
R
I
A
L
MATERIAL 1,816,500.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R MESIN GILAS BERGETAR 1 TON 1.00 1 E.087 10.00 41,535.08 415,350.77
A FLAT VIBRATOR TAMPER 2.00 1 E.088 10.00 12,939.46 129,394.59
L
A
T
A
N
PERALATAN 544,745.36
TOTAL ( Rp ) 2,766,745.36

VOLUME /
QUANTITY : 15 SATUAN m3 HARGA SATUAN 184,449.69 Per m3
KODE

DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN


DIREKTORAT BINA PROGRAM JALAN MEMBENTUK BADAN JALAN/SUB GRADE DNG TIMBUNAN

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN TENAGA BURUH) K.310

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Material Dihampar (maksimum) setiap lapis 20cm 1. Menggunakan tenaga buruh
2. Setiap Lapis (20cm) Dipadatkan Minimal 4 kali Lintasan 2. Harga meterial berdasarkan harga dilokasi pekerjaan
dengan mesin gilas roda Karet ( Tire Roller )

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 2.00 6 L.061 12 43,500.00 522,000.00
E Operator Terlatih 1.00 6 L.081 6 55,000.00 330,000.00
K Sopir Material/Truck 1.00 6 L.091 6 43,000.00 258,000.00
E Buruh lapangan tak terlatih 48.00 6 L.101 288 30,000.00 8,640,000.00
R
J
A
PEKERJA 9,750,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T Pasir Urug 450.00 m3 M.040 91,000.00 40,950,000.00
E Alat - alat Bantu (set @ 3 alat) 8.00 Set M.170 55,000.00 440,000.00
R
I
A
L
MATERIAL 41,390,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R PNEUMATIC ROLLER 8 - 15 TON 1.00 6 E.084 30 233,948.69 7,018,460.72
A TRUCK AIR ( WATER TANK TRUCK) 1.00 6 E.182 30 171,115.60 5,133,468.11
L
A
T
A
N
PERALATAN 12,151,928.83
TOTAL ( Rp ) 63,291,928.83

VOLUME /
QUANTITY : 375 SATUAN m3 HARGA SATUAN 168,778.48 Per m3
KODE

DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN


DIREKTORAT BINA PROGRAM JALAN MEMBENTUK BADAN JLN (GALIAN TANAH, MENGANGKUT DAN MEMBUANG HASIL GALIAN)

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.320

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Digali dengan tenaga Manusia 1. Menggunakan tenaga Manusia (32 m3/hari)
2. Dimuat ke Truck dengan tenaga Manusia 2. 20% dibuang ditempat, selagi truck tidak ada
3. Buang hasil galian tak terpakai menggunakan 3. 80% dibuang dengan 1 truck
truck 4 ton 4. Jarak 1 rit PP < 2 km
5. Penggunaan alat bantu 1 bln/orang
6. Tidak termasuk pemadatan tanah dasar

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Sopir Material/Truck 2.00 1 L.091 2 43,000.00 86,000.00
K Buruh lapangan tak terlatih 36.00 1 L.101 36 30,000.00 1,080,000.00
E
R
J
A
PEKERJA 1,209,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T
E Alat - alat Bantu (set @ 3 alat) 1.50 Set M.170 55,000.00 82,500.00
R
I
A
L
MATERIAL 82,500.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R
A FLAT BED TRUCK 4 ton 2.00 1 E.221 10 139,682.90 1,396,829.04
L
A
T
A
N
PERALATAN 1,396,829.04
TOTAL ( Rp ) 2,688,829.04

VOLUME /
QUANTITY : 32 SATUAN m3 HARGA SATUAN 84,025.91 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN MEMBENTUK BADAN JLN/SUBGRADE DNG TIMBUNAN

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.341

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Pembentukan tanah dasar dengan tenaga Manusia 1. Menggunakan tenaga Orang (8 m x 400 m/hari)
2. Padatkan dengan mesin gilas roda besi 2. 40 m2/hari Orang
3. Penggunaan alat bantu 1 bulan - orang
4. Tenaga dicari Setempat

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 2.00 1 L.061 2 43,500.00 87,000.00
E Operator Terlatih 1.00 1 L.091 1 55,000.00 55,000.00
K Buruh lapangan tak terlatih 66.00 1 L.101 66 30,000.00 1,980,000.00
E
R
J
A
PEKERJA 2,122,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T
E Alat - alat Bantu (set @ 3 alat) 0.20 Set M.170 55,000.00 11,000.00
R
I
A
L
MATERIAL 11,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R
A ROLLER THREE WHEEL 8 - 10 ton 1.00 1 E.080 5.00 137,655.42 688,277.10
L
A
T
A
N
PERALATAN 688,277.10
TOTAL ( Rp ) 2,821,277.10

VOLUME /
QUANTITY : 32 SATUAN m2 HARGA SATUAN 88,164.91 Per m2
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN MEMBENTUK BAHU JALAN

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.410.A

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Bahan timbunan yang baik dihampar dengan tenaga Orang 1. Menggunakan tenaga Orang (96 m3/hari, pemadatan 960 m bahu jalan)
2. Pemadatan bahu jalan dengan Mesin Gilas bergetar 2. Material Pilihan diperoleh di sekitar Proyek
3. 10cm timbunan padat dibutuhkan pada 1m Lebar bahu jalan
4. Pemadatan dengan Mesin gilas getar kecil

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 2.00 1 L.061 2 43,500.00 87,000.00
E Buruh lapangan tak terlatih 66.00 1 L.101 66 30,000.00 1,980,000.00
K Buruh Lapangan agak terlatih 1.00 1 L.103 1 31,000.00 31,000.00
E
R
J
A
PEKERJA 2,098,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T
E Alat - alat Bantu (set @ 3 alat) 2.50 Set M.170 55,000.00 137,500.00
R
I
A
L
MATERIAL 137,500.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R
A MESIN GILAS BERGETAR 1 TON 1.00 1 E.087 5 41,535.08 207,675.39
L
A
T
A
N
PERALATAN 207,675.39
TOTAL ( Rp ) 2,443,175.39

VOLUME /
QUANTITY : 96 SATUAN m3 HARGA SATUAN 25,449.74 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN MEMBENTUK BAHU JALAN KERAS

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.410

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Bahan timbunan yang baik dihampar dengan tenaga Orang 1. Menggunakan tenaga Orang (96 m3/hari, pemadatan 960 m bahu jalan)
2. Pemadatan bahu jalan dengan Mesin Gilas bergetar 2. Material Pilihan diperoleh di sekitar Proyek
3. Leveransir meletakan material timbunan sepanjang bahu jalan
4. 10cm timbunan padat dibutuhkan pada 1m lebar bahu jalan
5. Penghamparan timbunan dengan tenaga manusia
6. Pemadatan dengan mesin gilas getar kecil

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 2.00 1 L.061 2 43,500.00 87,000.00
E Buruh lapangan tak terlatih 66.00 1 L.101 66 30,000.00 1,980,000.00
K Buruh Lapangan agak terlatih 1.00 1 L.103 1 31,000.00 31,000.00
E
R
J
A
PEKERJA 2,098,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T Kerikil sungai tidak disaring 120.00 m3 K.013 151,851.41 18,222,169.20
E Alat - alat Bantu (set @ 3 alat) 2.50 Set M.170 55,000.00 137,500.00
R
I
A
L
MATERIAL 18,359,669.20
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R
A MESIN GILAS BERGETAR 1 TON 1.00 1 E.087 5 41,535.08 207,675.39
L
A
T
A
N
PERALATAN 207,675.39
TOTAL ( Rp ) 20,665,344.59

VOLUME /
QUANTITY : 96 SATUAN m3 HARGA SATUAN 215,264.01 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN MEMBERSIHKAN RUMPUT & TANAMAN DIBAHU JALAN

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.422

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Potong semak belukar yang tumbuh pada bahu jalan 1. Menggunakan tenaga manusia (2 x 1.50 x 500 m/hari)
2. Bersihkan Rumput/semak pada bahu jalan 2. Dengan lebar 1.50 dari tepi jalan, rata - rata luas yanga dibersihkan 3.000 m2/per km
satu sisi
3. Hasil kerja : 60 m2/orang - hari
4. Sampah / reruntuhan dibuang sejauh 1 km
5. Penggunaan alat bantu rata - rata 1 bulan - orang

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Buruh lapangan tak terlatih 25.00 1 L.101 25 30,000.00 750,000.00
K
E
R
J
A
PEKERJA 793,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T
E Alat - alat Bantu (set @ 3 alat) 1.00 Set M.170 55,000.00 55,000.00
R
I
A
L
MATERIAL 55,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R
A
L
A
T
A
N
PERALATAN -
TOTAL ( Rp ) 848,500.00

VOLUME /
QUANTITY : 1500 SATUAN m3 HARGA SATUAN 565.67 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN MEMBERSIHKAN PARIT SAMPING

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.424

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Bersihkan Parit samping dan gorong - gorong dari 1. Menggunakan tenaga manusia
kotoran / sampah atau tumbuhan 2. Membersihkan sampah, kotoran yang menyumbat, tumbuh - tumbuhan
2. Buang sampah ' kotoran tersebut dengan truck tersebut dan gorong - gorong
dengan menggunakan truck dumuat oleh tenaga orang 3. Pembuangan runtuhan sejauh 1 km
4. Penggunaan alat bantu 1 bulan - orang
5. Kapasitas 1.0 rit pp/jam/truk

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Sopir 2.00 1 L.091 2 43,000.00 86,000.00
K Buruh Lapangan tak terlatih 36.00 1 L.101 36 30,000.00 1,080,000.00
E
R
J
A
PEKERJA 1,209,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T
E Alat - alat Bantu (set @ 3 alat) 1.20 Set M.170 55,000.00 66,000.00
R
I
A
L
MATERIAL 66,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R FLAT BED TTRUCK 4 ton 2.00 1 E.221 10.00 139,682.90 1,396,829.04
A
L
A
T
A
N
PERALATAN 1,396,829.04
TOTAL ( Rp ) 2,672,329.04

VOLUME /
QUANTITY : 500 SATUAN m HARGA SATUAN 5,344.66 Per m
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN KONTRUKSI LAPIS PONDASI BAWAH (LPB)KLAS``A``

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.511

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Membentuk atau meratakan kembali permukaan jalan lama 1. Menggunakan buruh (60 m3/hari)
2. Agregat ditempatkan disepanjang jalan 2. Dimulai dengan pekerjaan memperbaiki penurunan
3. Menghampar Agregat 3. Bahan dicampur dan diratakan + 12 cm
4. Jalan disiram dengan gerobak + drum air 4. Harga material berdasarkan harga dilokasi Proyek
5. Pemadatan dilakukan dengan mesin gilas tiap - tiap 10 cm

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Operator Terlatih 1.00 1 L.081 1 55,000.00 55,000.00
K Sopir 1.00 1 L.091 1 43,000.00 43,000.00
E Buruh Lapangan tak terlatih 40.00 1 L.101 40.00 30,000.00 1,200,000.00
R
J
A
PEKERJA 1,341,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Batu Pecah 3 - 5 cm 18.00 m3 M.023 143,000.00 2,574,000.00
T Batu Pecah 2 - 3 cm 9.00 m3 M.024 195,000.00 1,755,000.00
E Batu Pecah 1 - 2 cm 6.00 m3 M.025 235,000.00 1,410,000.00
R Batu tabur 0.5 - 1 cm (klungsun) 10.00 m3 M.026 247,000.00 2,470,000.00
I Bahan Timbunan / Pengikat Pilihan 29.00 m3 M.040 91,000.00 2,639,000.00
A Alat - alat bantu ( set @ 3 alat ) 2.00 set M.170 55,000.00 110,000.00
L
MATERIAL 10,958,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R ROLLER THREEE WHEEL 8 - 10 ton 1.00 1 E.080 5 137,655.42 688,277.10
A TRUCK AIR ( WATER TANK TRUCK) 1.00 1 E.182 4 171,115.60 684,462.41
L
A
T
A
N
PERALATAN 1,372,739.51
TOTAL ( Rp ) 13,672,239.51

VOLUME /
QUANTITY : 60 SATUAN m3 HARGA SATUAN 227,870.66 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN KONTRUKSI LAPIS PONDASI BAWAH (LPB)KLAS``B``

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.515

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Agregat ditempatkan disepanjang jalan oleh leveransir 1. Mengunakan tenaga manusia setempat
2. Menghampar Agregat dengan tenaga orang 2. Kerikil diteimbun sepanjang jalan oleh leveransir
3. Pemadatan dalam memakai truk air dan mesin gilas 3. Kerikil dengan ukuran lebih (Over size) yang tersingkir saat penghamparan
roda baja tiap - tiap 10 cm dengan orang dihitung 6%
4. Perapihan dengan tenaga manusia 4. Penggunaan Alat Bantu + 1 bulan - orang
5. Hasil kerja menghampar dan memadatkan 600 m2/hari (4m x 150 m)
6. Kerikil kali tanpa disaring dikirim leveransir sampai ditempat pekerjaan

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 3.00 1 L.061 3 43,500.00 130,500.00
E Operator Terlatih 1.00 1 L.081 1 55,000.00 55,000.00
K
E Buruh Lapangan tak terlatih 40.00 1 L.101 40.00 30,000.00 1,200,000.00
R
J
A
PEKERJA 1,385,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T
E
R
I Kerikil sungai tanpa disaring 75.00 m3 M.042 90,000.00 6,750,000.00
A Alat - alat bantu ( set @ 3 alat ) 2.50 set M.170 55,000.00 137,500.00
L
MATERIAL 6,887,500.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R ROLLER THREEE WHEEL 8 - 10 ton 1.00 1 E.080 5 137,655.42 688,277.10
A
L
A
T
A
N
PERALATAN 688,277.10
TOTAL ( Rp ) 8,961,277.10

VOLUME /
QUANTITY : 60 SATUAN m3 HARGA SATUAN 149,354.62 Per m3
KODE

DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN


DIREKTORAT BINA PROGRAM JALAN KONTRUKSI LAPIS BAWAH (LPB TELPOORD)

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.516

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Material disiapkan dilokasi pekerjaan 1. Menggunakan tenaga Manusia 400m2/hari
2. Menghampar pasir setebal 5 cm 2. Material dikirim ketempat pekerjaan oleh leveransir
3. Batu pecah berukuran besar (10 - 15 cm) disusun berdiri 3. Batu sudah dipecah
4. Batu Pecah yang lebih kecil mengisi rongga diatasnya 4. Tanah dasar sudah disiaokan
sehingga rata kemudian dipadatkan/digilas dengan mesin gilas 5. Dipadatkan sampai tebal 20cm

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 3.00 1 L.061 3 43,500.00 130,500.00
E Operator Terlatih 1.00 1 L.081 1 55,000.00 55,000.00
K Buruh Lapangan tak terlatih 99.00 1 L.101 99 30,000.00 2,970,000.00
E
R
J
A
PEKERJA 3,155,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T Batu Pecah 10 - 15 cm 50.00 m3 M.020 143,000.00 7,150,000.00
E Batu Pecah 5 - 7 cm 20.00 m3 M.022 143,000.00 2,860,000.00
R Pasir urug 30.00 m3 M.040 91,000.00 2,730,000.00
I Alat - alat bantu ( set @ 3 alat ) 4.00 set M.170 55,000.00 220,000.00
A
L
MATERIAL 12,960,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R ROLLER THREEE WHEEL 8 - 10 ton 1.00 1 E.080 5 137,655.42 688,277.10
A
L
A
T
A
N
PERALATAN 688,277.10
TOTAL ( Rp ) 16,803,777.10

VOLUME /
QUANTITY : 80 SATUAN m3 HARGA SATUAN 210,047.21 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN LEVELING KONSTRUKSI LAPIS PONDASI BAWAH (LPB) TELFOORD
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.516.A

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Material disiapkan dilokasi pekerjaan 1. Menggunakan tenaga Manusia 400m2/hari
2. Menghampar pasir setebal 5 cm 2. Material dikirim ketempat pekerjaan oleh leveransir
3. Batu pecah berukuran besar (10 - 15 cm) disusun berdiri 3. Batu sudah dipecah
4. Batu Pecah yang lebih kecil mengisi rongga diatasnya 4. Tanah dasar sudah disiapkan
sehingga rata kemudian dipadatkan/digilas dengan mesin gilas 5. Dipadatkan sampai tebal 20cm

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 3.00 1 L.061 3 43,500.00 130,500.00
E Operator Terlatih 1.00 1 L.081 1 55,000.00 55,000.00
K Buruh Lapangan tak terlatih 99.00 1 L.101 81 30,000.00 2,430,000.00
E
R
J
A
PEKERJA 2,615,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T Batu Pecah 10 - 15 cm 50.00 m3 M.020 143,000.00 7,150,000.00
E Batu Pecah 5 - 7 cm 20.00 m3 M.022 143,000.00 2,860,000.00
R Alat - alat bantu ( set @ 3 alat ) 4.00 set M.170 55,000.00 220,000.00
I
A
L
MATERIAL 10,230,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R ROLLER THREEE WHEEL 8 - 10 ton 1.00 1 E.080 5 137,655.42 688,277.10
A
L
A
T
A
N
PERALATAN 688,277.10
TOTAL ( Rp ) 13,533,777.10

VOLUME /
QUANTITY : 80 SATUAN m3 HARGA SATUAN 169,172.21 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN LEVELING LAPIS PONDASI ATAS (LPA) KLAS ``A''

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.521.A

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Agregat pecah tersaring ditimbun disepanjang jalan oleh 1. Menggunakan tenaga manusia (60 m3'hari)
Pemasok 2. Pengadaan barang oleh Leveransir
2. Material di hampar dengan tenaga manusia 3. Buruh menghampar batu pecah diatas LPB ( + 15cm)
3. Pemadatan perkerasan dengan mesin gilas roda baja 4. Menggunakan 135m3 batu pecah mesin dengan binder
tiap - tiap 10 cm (pasir urug) 24 m3 atau 140m3 kerikil pecah mesin dengan binder
(pasir urug) 15m3
5. Rongga - rongga ditutup dengan pasri urug dengan tenga manusia
6. Hasil kerja menghampar dan memadatkan 600 m2/hari

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 2 L.061 2.00 43,500.00 87,000.00
E Operator Terlatih 1.00 2 L.081 2.00 55,000.00 110,000.00
K Buruh Lapangan tak terlatih 20.00 2 L.101 40.00 30,000.00 1,200,000.00
E
R
J
A
PEKERJA 1,397,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T Bahan timbunan / Pengikat Pilihan 15.00 m3 M.040 91,000.00 1,365,000.00
E Alat - alat bantu ( set @ 3 alat ) 5.50 set M.170 55,000.00 302,500.00
R Kerikil pecah tersaring 130.00 m3 K.017 209,334.22 27,213,448.60
I
A
L
MATERIAL 28,880,948.60
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R ROLLER THREEE WHEEL 8 - 10 ton 1.00 2 E.080 10 137,655.42 1,376,554.20
A
L
A
T
A
N
PERALATAN 1,376,554.20
TOTAL ( Rp ) 31,654,502.80

VOLUME /
QUANTITY : 120 SATUAN m3 HARGA SATUAN 263,787.52 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN LAPIS PONDASI ATAS (LPA) KLAS ``A''

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.521

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Agregat pecah tersaring ditimbun disepanjang jalan oleh 1. Menggunakan tenaga manusia (60 m3'hari)
Pemasok 2. Pengadaan barang oleh Leveransir
2. Material di hampar dengan tenaga manusia 3. Buruh menghampar batu pecah diatas LPB ( + 15cm)
3. Pemadatan perkerasan dengan mesin gilas roda baja dan tangki 4. Menggunakan 135m3 batu pecah mesin dengan binder
air tiap - tiap 10cm (pasir urug) 24 m3 atau 140m3 kerikil pecah mesin dengan binder
(pasir urug) 15m3
5. Rongga - rongga ditutup dengan pasri urug dengan tenga manusia
6. Hasil kerja menghampar dan memadatkan 600 m2/hari

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 2 L.061 2 43,500.00 87,000.00
E Operator Terlatih 1.00 2 L.081 2 55,000.00 110,000.00
K Sopir 1.00 2 L.091 2 43,000.00 86,000.00
E Buruh Lapangan tak terlatih 60.00 2 L.101 120 30,000.00 3,600,000.00
R
J
A
PEKERJA 3,883,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T Bahan timbunan / Pengikat Pilihan 15.00 m3 M.040 91,000.00 1,365,000.00
E Alat - alat bantu ( set @ 3 alat ) 5.50 set M.170 55,000.00 302,500.00
R Kerikil pecah tersaring 130.00 m3 K.017 209,334.22 27,213,448.60
I
A
L
MATERIAL 28,880,948.60
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R ROLLER THREEE WHEEL 8 - 10 ton 1.00 2 E.080 10 137,655.42 1,376,554.20
A TRUCK AIR (WATER TANK TRUCK) 1.00 2 E.182 10 171,115.60 1,711,156.04
L
A
T
A
N
PERALATAN 3,087,710.24
TOTAL ( Rp ) 35,851,658.84

VOLUME /
QUANTITY : 120 SATUAN m3 HARGA SATUAN 298,763.82 Per m3
KODE

DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN


DIREKTORAT BINA PROGRAM JALAN LEVELING KONTRUKSI LAPIS PONDASI ATAS (LPA) KLAS B

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN KLAS'B" (MENGGUNAKAN BURUH) K.523.A

JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Agregat ditempatkan sepanjang jalan 1. Menggunakan tenaga buruh (60 m3/hari)
2. Menghampar Agregat 2. Bahan dicampur dan diratakan
3. 3. Harga materail berdasarkan harga dilokasi Proyek
4. Pemadatan dilakukan dengan mesin gilas tiap -tiap 10 cm

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 2.00 2 L.061 4.00 43,500.00 174,000.00
E Operator Terlatih 1.00 2 L.081 2.00 55,000.00 110,000.00
K Buruh Lapangan tak terlatih 53.00 2 L.101 106.00 30,000.00 3,180,000.00
E
R
J
A
PEKERJA 3,464,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Batu Pecah 3 - 5 cm 10.00 m3 M.023 143,000.00 1,430,000.00
T Batu Pecah 2 - 3 cm 11.00 m3 M.024 195,000.00 2,145,000.00
E Batu Pecah 1 - 2 cm 7.50 m3 M..025 235,000.00 1,762,500.00
R Batu Pecah 0.5 - 1 cm 11.00 m3 M.026 247,000.00 2,717,000.00
I Pasir Urug 32.50 m3 M.040 91,000.00 2,957,500.00
A Alat Bantu 1.20 set M.170 55,000.00 66,000.00
L
MATERIAL 11,078,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R ROLLER THREEE WHEEL 8 - 10 ton 1.00 2 E.080 5 137,655.42 688,277.10
A
L
A
T
A
N
PERALATAN 688,277.10
TOTAL ( Rp ) 15,230,277.10

VOLUME /
QUANTITY : 60 SATUAN m3 HARGA SATUAN 253,837.95 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN KONTRUKSI LAPIS PONDASI ATAS (LPA) KLAS " B "

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.523

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Agregat ditempatkan sepanjang jalan 1. Menggunakan tenaga buruh (60 m3/hari)
2. Menghampar Agregat 2. Bahan dicampur dan diratakan
3. Jalan disiram dengan trukair 3. Harga materail berdasarkan harga dilokasi Proyek
4. Pemadatan dilakukan dengan mesin gilas tiap -tiap 10 cm

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 2.00 2 L.061 4.00 43,500.00 174,000.00
E Operator Terlatih 1.00 2 L.081 2.00 55,000.00 110,000.00
K Sopir 1.00 2 L.091 2.00 43,000.00 86,000.00
E Buruh Lapangan tak terlatih 53.00 2 L.101 106.00 30,000.00 3,180,000.00
R
J
A
PEKERJA 3,550,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Batu Pecah 3 - 5 cm 10.00 m3 M.023 143,000.00 1,430,000.00
T Batu Pecah 2 - 3 cm 11.00 m3 M.024 195,000.00 2,145,000.00
E Batu Pecah 1 - 2 cm 7.50 m3 M..025 235,000.00 1,762,500.00
R Batu Pecah 0.5 - 1 cm 11.00 m3 M.026 247,000.00 2,717,000.00
I Pasir Urug 32.50 m3 M.040 91,000.00 2,957,500.00
A Alat Bantu 1.20 set M.170 55,000.00 66,000.00
L
MATERIAL 11,078,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R ROLLER THREEE WHEEL 8 - 10 ton 1.00 1 E.080 5 137,655.42 688,277.10
A TRUCK AIR (WATER TANK TRUCK) 1.00 1 E.182 4 171,115.60 684,462.41
L
A
T
A
N
PERALATAN 1,372,739.51
TOTAL ( Rp ) 16,000,739.51

VOLUME /
QUANTITY : 60 SATUAN m3 HARGA SATUAN 266,678.99 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN PENGHAMPARAN LAPIS PONDASI ATAS ASPAL BETON LASTON ATAS

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN ALAT) K.528

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Permuakaan jalan dibersihkan dan kering 1. Menggunakan alat berat
2. Siram aspal Pengikat pada tar 0.5 l/m2 2. ATB dihampar dan diipadatkan
3. Temperatur ATB 80 C dan tidak kurang dari 60 C 3. Sesuai spesifikasi B.M No. 03/PT/B/1983

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Operator Terlatih 4.00 1 L.081 4 55,000.00 220,000.00
K Buruh Lapangan tak terlatih 12.00 1 L.101 12 30,000.00 360,000.00
E Buruh Lapangan terlatih 8.00 1 L.106 8 40,000.00 320,000.00
R
J
A
PEKERJA 943,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A ATB ( laston atas ) 100.00 ton K.026 706,203.88 70,620,388.00
T Aspal Curah 135.00 kg M.062 5,590.00 754,650.00
R Minyak tanah 90.00 Liter M.065 4,550.00 409,500.00
I Alat - Alat bantu (set @ 3 alat) 0.50 m3 M.170 55,000.00 27,500.00
A
L
MATERIAL 71,812,038.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R ROLLER THREEE WHEEL 8 - 10 ton 1.00 1 E.080 5 137,655.42 688,277.10
A PNEUMATIC ROLLER 8 - 15 TON 1.00 1 E.084 5 233,948.69 1,169,743.45
L ASPHALT SPRAYER TOWED 350 L 1.00 1 E.153 3 91,266.98 273,800.95
A ASPHALT FINISHER 1.00 1 E.157 5 369,985.00 1,849,925.00
T COMPRESOR, AIR 150 m3 1.00 1 E.301 4 103,720.16 414,880.65
A
N
PERALATAN 4,396,627.15
TOTAL ( Rp ) 77,152,165.15

VOLUME /
QUANTITY : 45 SATUAN m3 HARGA SATUAN 1,714,492.56 Per m3
KODE

DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN

DIREKTORAT BINA PROGRAM JALAN LEVELLING LAPIS PONDASI ATAS ASPAL BETON LASTON ATAS

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN ALAT) K.528.A

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Permuakaan jalan dibersihkan dan kering 1. Menggunakan alat berat
2. Siram aspal Pengikat pada tar 0.5 l/m2 2. ATB dihampar dan diipadatkan
3. Temperatur ATB 80 C dan tidak kurang dari 60 C 3. Sesuai spesifikasi B.M No. 03/PT/B/1983

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1 1 L.061 1 43,500.00 43,500.00
E Operator Terlatih 3 1 L.081 3 55,000.00 165,000.00
K Buruh Lapangan tak terlatih 20 1 L.101 20 30,000.00 600,000.00
E Buruh Lapangan terlatih 10 1 L.106 10 40,000.00 400,000.00
R
J
A

PEKERJA 1,208,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A ATB ( laston atas ) 100.00 ton K.026 706,203.88 70,620,388.00
T Aspal Curah 135.00 kg M.062 5,590.00 754,650.00
R Minyak tanah 90.00 Liter M.065 4,550.00 409,500.00
I Alat - Alat bantu (set @ 3 alat) 0.50 m3 M.170 55,000.00 27,500.00
A
L

MATERIAL 71,812,038.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R ROLLER THREEE WHEEL 8 - 10 ton 1.00 1 E.080 5 137,655.42 688,277.10
A PNEUMATIC ROLLER 8 - 15 TON 1.00 1 E.084 5 233,948.69 1,169,743.45
L ASPHALT SPRAYER TOWED 350 L 1.00 1 E.153 3 91,266.98 273,800.95
A
T COMPRESOR, AIR 150 m3 1.00 1 E.301 4 103,720.16 414,880.65
A
N

PERALATAN 2,546,702.15
TOTAL ( Rp ) 75,567,240.15

VOLUME /
QUANTITY : 45 SATUAN m3 HARGA SATUAN 1,679,272.00 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN MENGHAMPAR LAPIS PONDASI ATAS ASPAL BETON LASTON ATAS (Dengan Buruh)

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.528.B

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Permuakaan jalan dibersihkan dan kering 1. Menggunakan Buruh
2. Siram aspal Pengikat pada tar 0.5 l/m2 2. ATB dihampar dan diipadatkan
3. Temperatur ATB 80 C dan tidak kurang dari 60 C 3. Sesuai spesifikasi B.M No. 03/PT/B/1983

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1 1 L.061 1 43,500.00 43,500.00
E Operator Terlatih 3 1 L.081 3 55,000.00 165,000.00
K Buruh Lapangan tak terlatih 60 1 L.101 60 30,000.00 1,800,000.00
E Buruh Lapangan terlatih 35 1 L.106 35 40,000.00 1,400,000.00
R
J
A
PEKERJA 3,408,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A ATB ( laston atas ) 100.00 ton K.026.A 792,997.61 79,299,761.00
T Aspal Bitumen 135.00 kg M.061 7,720.00 1,042,200.00
R Minyak tanah 90.00 Liter M.065 4,550.00 409,500.00
I Alat - Alat bantu (set @ 3 alat) 0.50 m3 M.170 55,000.00 27,500.00
A
L
MATERIAL 80,778,961.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R ROLLER THREEE WHEEL 8 - 10 ton 1.00 1 E.080 5 137,655.42 688,277.10
A
L
A
T COMPRESOR, AIR 150 m3 1.00 1 E.301 4 103,720.16 414,880.65
A
N
PERALATAN 1,103,157.75
TOTAL ( Rp ) 85,290,618.75

VOLUME /
QUANTITY : 45 SATUAN m3 HARGA SATUAN 1,895,347.08 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN LABURAN ASPAL SATU LAPIS (BURTU) ATAU (BURDA 1)

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.615

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Bersihkan permukaan aspal dari material lepas 1. Hasil kerja 600 m2/hari
2. Semprotkan primer aspal cair MC "0" 2. Agregat haluls hasil saringan 20 mm dari mesin pemecah batu
3. Lapisan permukaan aspal dengan bitumen dan taburkan ditimbun dilokasi pekerjaan oleh leveransir
split serta digilas 3. Permukaan yang dilabur telah selesai digilas dan terikat dengan binder
4. Laburan permukaan menggunakn aspl "MC" 1.0 l/m2
5. Menggunakan minyak residu + 1.6 lm2
6. Agregat halus 1.2 cm disebar dari gerobak dorong

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 3 L.061 3 43,500.00 130,500.00
E Operator Terlatih 3.00 3 L.081 9 55,000.00 495,000.00
K Sopir 2.00 3 L.091 6 43,000.00 258,000.00
E Buruh Lapangan tak terlatih 10.00 3 L.101 30 30,000.00 900,000.00
R Buruh Lapangan agak terlatih 2.00 3 L.103 6 31,000.00 186,000.00
J Buruh Lapangan terlatih 2.00 3 L.106 6 40,000.00 240,000.00
A
PEKERJA 2,209,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T Kerikil pecah tersaring 36.00 m3 M.026 247,000.00 8,892,000.00
E Aspal bitumen 3,745.00 kg M.061 7,720.00 28,911,400.00
R Minyak tanah 580.00 lt M.065 4,550.00 2,639,000.00
I Alat - Alat bantu (set @ 3 alat) 1.50 set M.170 55,000.00 82,500.00
A
L
MATERIAL 40,524,900.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R TRACTOR EQUIPMENT .ETC 1.00 3 E.401 15.00 73,513.77 1,102,706.58
A PNEUMATIC ROLLER 8 - 15 TON 1.00 3 E.084 15.00 233,948.69 3,509,230.36
L ASPHALT SPRAYER TOWED 350 L 1.00 3 E.153 15.00 91,266.98 1,369,004.73
A DUMP TRUCK 3.50 ton 2.00 3 E.211 30.00 168,066.58 5,041,997.42
T
A
N
PERALATAN 11,022,939.10
TOTAL ( Rp ) 53,757,339.10

VOLUME /
QUANTITY : 1800 SATUAN m2 HARGA SATUAN 29,865.19 Per m2
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN PELAPISAN ULANG ATAU LABURA ASPAL LAPIS KEDUA

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (BURDA 2) K.616

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Bersihkan perkerasan aspal yang lama 1. Hasil kerja 1800 m2/hari
2. Panaskan dan semprotkan aspal dengan heater / sprayer 2. Agregat haluls hasil saringan 10 mm dari mesin pemecah batu
3. Taburkan pasor kerikil dan digilas dengan mesin Pneumatic 3. Campuran fulx bituman disemprotkan tiap 1.3 liter/m2
4. Egregat halus tersaring 10mm dihampar tiap 100m2/m3
5. Agregat dumuat ke truck dengan tenaga manusia dan dihampar dengan mesin
penghampar agregat

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Operator Terlatih 3.00 1 L.081 3 55,000.00 165,000.00
K Sopir 2.00 1 L.091 2 43,000.00 86,000.00
E Buruh Lapangan tak terlatih 10.00 1 L.101 10 30,000.00 300,000.00
R Buruh Lapangan agak terlatih 2.00 1 L.103 2 31,000.00 62,000.00
J Buruh Lapangan terlatih 2.00 1 L.106 2 40,000.00 80,000.00
A
PEKERJA 736,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T Kerikil pecah tersaring 18.00 m3 K.017 209,334.22 3,768,015.96
E Aspal bitumen 2,340.00 kg M.061 7,720.00 18,064,800.00
R Alat - Alat bantu (set @ 3 alat) 0.50 set M.170 55,000.00 27,500.00
I
A
L
MATERIAL 21,860,315.96
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R TRACTOR EQUIPMENT .ETC 1.00 1 E.401 5.00 73,513.77 367,568.86
A PNEUMATIC ROLLER 8 - 15 TON 1.00 1 E.084 5.00 233,948.69 1,169,743.45
L ASPHALT SPRAYER TOWED 350 L 1.00 1 E.153 5.00 91,266.98 456,334.91
A DUMP TRUCK 3.50 ton 2.00 1 E.211 10.00 168,066.58 1,680,665.81
T TRACTOR WHEELED 1.00 1 E.053 5.00 106,706.72 533,533.58
A CHIP SPREADER 2.00 1 E.130 10.00 25,636.05 256,360.49
N
PERALATAN 4,464,207.10
TOTAL ( Rp ) 27,061,023.06

VOLUME /
QUANTITY : 1800 SATUAN m2 HARGA SATUAN 15,033.90 Per m2
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN LABUARAN ASPAL DUA LAPIS (BURDA)

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN K.617

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Permukaan harus rata kering dan bersih 1. Hasil kerja 450 m2/hari
2. Untk permukaan jalan yang tak beraspal perlu prime coat 0.7 lt/m2 2. Agregat ukuran 1 - 2 cm dan pemecah batu ditimbun dilokasi pekerjaan oleh
3. Menebarkan agregat / batu pecah 1 - 2 cm dengan gradasi leveransir
seragam dua lapis 3. Permukaan yang sudah diaspal harus sudah dipadatkan diadakan binding
4. Pemadaman dengan PTR 4 - 6 disiram primer aspal cair 1 km/m2
4. Bitumen residu yang dipakai lapis 1 sebanyak 1.6 lt/m2 dan lapis 2
sebanyak 1.3 lt/m2
5. Chip dari Dump truck masuk spreader dengan rata -rata 50 m2/m3

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 4 L.061 4 43,500.00 174,000.00
E Operator Terlatih 3.00 4 L.081 12 55,000.00 660,000.00
K Sopir 2.00 4 L.091 8 43,000.00 344,000.00
E Buruh Lapangan tak terlatih 10.00 4 L.101 40 30,000.00 1,200,000.00
R Buruh Lapangan agak terlatih 2.00 4 L.103 8 31,000.00 248,000.00
J Buruh Lapangan terlatih 2.00 4 L.106 8 40,000.00 320,000.00
A
PEKERJA 2,946,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A
T Kerikil pecah tersaring 54.00 m3 K.017 209,334.22 11,304,047.88
E Aspal bitumen 6,085.00 kg M.061 7,720.00 46,976,200.00
R Alat - Alat bantu (set @ 3 alat) 2.50 set M.170 55,000.00 137,500.00
I Minyak bakar 580.00 Liter M.065 4,550.00 2,639,000.00
A
L
MATERIAL 61,056,747.88
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R TRACTOR EQUIPMENT .ETC 1.00 4 E.401 20.00 73,513.77 1,470,275.45
A PNEUMATIC ROLLER 8 - 15 TON 1.00 4 E.084 20.00 233,948.69 4,678,973.81
L ASPHALT SPRAYER TOWED 350 L 1.00 4 E.153 20.00 91,266.98 1,825,339.64
A DUMP TRUCK 3.50 ton 2.00 4 E.211 40.00 168,066.58 6,722,663.27
T TRACTOR WHEELED 1.00 4 E.053 20.00 106,706.72 2,134,134.30
A CHIP SPREADER 2.00 4 E.130 40.00 25,636.05 1,025,441.95
N
PERALATAN 17,856,828.42
TOTAL ( Rp ) 81,859,576.30

VOLUME /
QUANTITY : 1800 SATUAN m2 HARGA SATUAN 45,477.54 Per m2
KODE

DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN


DIREKTORAT BINA PROGRAM JALAN LAPIS PENETRASI MAKADAM 4 CM (LAPEN)

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ASPAL 2 LAPIS (MENGGUNAKAN BURUH) K.618.B

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Lapis aspal tack coat 0.64 lt/m2 1. Menggunakan tenaga buruh
2. Hamparan Agregat poko 3 - 5, 31 m2/m3 dan dipadatkan 2. Harga material (agregat pokok,agregat pengunci,agregat penutup
3. Hamparan split 2 - 3 56 m2/m3 & padatkan aspal) adalah harga dilokasi proyek
4. Hamparan agregat pengunci split 1 - 2; 112 m2/m3 3. Volume untuk aspal cair tack coat/prime coat 0.64 lt/m2
5. Lapisi aspal (2 kg/m2) 4. Tebal lapisan penetrasi + 4 cm
6. Taburkan pasir penutup dan padatkan 5. Agregat dikirim sampai temmpat pekrjaan oleh leveransir

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 2.00 3 L.061 6 43,500.00 261,000.00
E Operator Terlatih 1.00 3 L.081 6 55,000.00 330,000.00
K Sopir 1.00 3 L.091 3 43,000.00 129,000.00
E Buruh Lapangan tak terlatih 70.00 3 L.101 210 30,000.00 6,300,000.00
R Buruh lapangan terlatih 2.00 3 L.106 6 40,000.00 240,000.00
J
A
PEKERJA 7,260,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Batu 3 - 4 cm pecah tangan 56.00 m3 M.023.A 160,000.00 8,960,000.00
T Batu 2 - 3 cm pecah tangan 31.00 m3 M.024 195,000.00 6,045,000.00
E Batu 1 - 2 cm pecah mesin 15.50 m3 M.025 235,000.00 3,642,500.00
R Aspal Butimen 4,170.00 kg M.061 7,720.00 32,192,400.00
I Kayu bakar 3.60 m3 M.070 149,500.00 538,200.00
A Minyak bakar 280.00 ltr M.065 4,550.00 1,274,000.00
L Alat - alat bantu (set @ 3 set) 8.10 set M.170 55,000.00 445,500.00
Pasir bersih ( agregat halus ) 3.50 m3 M.041 130,000.00 455,000.00
MATERIAL 53,552,600.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R ROLLER THREE WHEEL 8 - 10 ton 1.00 3 E.080 15.00 137,655.42 2,064,831.30
A
L FLAT BED TRUCK 4 ton 1.00 3 E.221 15.00 139,682.90 2,095,243.56
A
T
A
N
PERALATAN 4,160,074.86
TOTAL ( Rp ) 64,972,674.86

VOLUME /
QUANTITY : 1750 SATUAN m2 HARGA SATUAN 37,127.24 Per m2
KODE

DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN


DIREKTORAT BINA PROGRAM JALAN LAPIS PENETRASI MAKADAM 4CM ( LAPEN)

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.618.A

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Lapis aspal tack coat lt/m2 1. Menggunakan tenaga buruh
2. Hamparan agregat pokok 3 - 5, 31 m2/m3 dan dipatakan 2. Harga material (agregat pokok,agregat pengunci,agregat penutup
3. Hamparan split 2 - 3, 56 m2/m3 & padatkan aspal) adalah harga dilokasi proyek
4. Lapisi aspal (2 kg/m2) 3. Volume untuk aspal cair tack coat/prime coat 0.64 lt/m2
5. Hamparan agaregat pengunci split 1 - 2; 112 m2/m3 4. Tebal lapisan penetrasi + 4 cm
dan dipadatkan 5. Agregat dikirim sampai temmpat pekrjaan oleh leveransir
6. Lapis aspal 1.2 kg/m2
7. Taburkan pasir rata- rata 400m2/m3

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 2.00 3 L.061 6 43,500.00 261,000.00
E Operator Terlatih 1.00 3 L.081 3 55,000.00 165,000.00
K Sopir 1.00 3 L.091 3 43,000.00 129,000.00
E Buruh Lapangan tak terlatih 70.00 3 L.101 210 30,000.00 6,300,000.00
R Buruh lapangan terlatih 2.00 3 L.106 6 40,000.00 240,000.00
J
A
PEKERJA 7,095,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Batu 3 - 4 cm pecah tangan 56.00 m3 M.023.A 160,000.00 8,960,000.00 0.032
T Batu 2 - 3 cm pecah tangan 31.00 m3 M.024 195,000.00 6,045,000.00 0.018
E Batu 1 - 2 cm pecah mesin 15.50 m3 M.025 235,000.00 3,642,500.00 0.009
R Aspal Butimen 6,270.00 kg M.061 7,720.00 48,404,400.00 3.583
I Kayu bakar 3.60 m3 M.070 149,500.00 538,200.00
A Minyak bakar 280.00 ltr M.065 4,550.00 1,274,000.00
L Alat - alat bantu (set @ 3 set) 8.10 set M.170 55,000.00 445,500.00
Pasir bersih ( agregat halus ) 4.30 m3 M.041 130,000.00 559,000.00 0.002
MATERIAL 69,868,600.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R ROLLER THREE WHEEL 8 - 10 ton 1.00 3 E.080 15.00 137,655.42 2,064,831.30
A
L FLAT BED TRUCK 4 ton 1.00 3 E.221 15.00 139,682.90 2,095,243.56
A
T
A
N
PERALATAN 4,160,074.86
TOTAL ( Rp ) 81,123,674.86

VOLUME /
QUANTITY : 1750 SATUAN m2 HARGA SATUAN 46,356.39 Per m2
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN LAPIS PENETRASI MAKADAM 5CM ( LAPEN)

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.618

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Lapis aspal tack coat 0.8 lt/m2 1. Menggunakan tenaga buruh
2. Hamparan agregat pokok 3 - 5, 25 m2/m3 dan dipatakan 2. Harga material (agregat pokok,agregat pengunci,agregat penutup
3. Hamparan split 2 - 3, 45 m2/m3 & padatkan aspal) adalah harga dilokasi proyek
4. Lapisi aspal (2.5 kg/m2) 3. Volume untuk aspal cair tack coat/prime coat 0.8 lt/m2
5. Hamparan agaregat pengunci split 1 - 2; 90 m2/m3 4. Tebal lapisan penetrasi + 5 cm
dan dipadatkan 5. Agregat dikirim sampai temmpat pekrjaan oleh leveransir
6. Lapis aspal 1.5 kg/m2
7. Taburkan pasir rata- rata 400m2/m3

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 2.00 3 L.061 6 43,500.00 261,000.00
E Operator Terlatih 1.00 3 L.081 6 55,000.00 330,000.00
K Sopir 1.00 3 L.091 3 43,000.00 129,000.00
E Buruh Lapangan tak terlatih 70.00 3 L.101 198 30,000.00 5,940,000.00
R Buruh lapangan terlatih 2.00 3 L.106 6 40,000.00 240,000.00
J
A
PEKERJA 6,900,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M 2500
A Batu 3 - 5 cm pecah tangan 56.00 m3 M.023 143,000.00 8,008,000.00 0.04
T Batu 2 - 3 cm pecah tangan 31.00 m3 M.024 195,000.00 6,045,000.00 0.02
E Batu 1 - 2 cm pecah mesin 15.50 m3 M.025 235,000.00 3,642,500.00 0.01
R Aspal Butimen 6,720.00 kg M.061 7,720.00 51,878,400.00 4.80
I Kayu bakar 3.60 m3 M.070 149,500.00 538,200.00 0.00
A Minyak bakar 280.00 ltr M.065 4,550.00 1,274,000.00 0.20
L Alat - alat bantu (set @ 3 set) 8.10 set M.170 55,000.00 445,500.00 0.01
Pasir bersih ( agregat halus ) 3.50 m3 M.041 130,000.00 455,000.00 0.00
MATERIAL 72,286,600.00 -
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R ROLLER THREE WHEEL 8 - 10 ton 1.00 3 E.080 15.00 137,655.42 2,064,831.30
A SPRAYER TOWED 400L 1.00 3 E.154 15.00 23,763.97 356,459.53
L FLAT BED TRUCK 4 ton 1.00 3 E.221 15.00 139,682.90 2,095,243.56
A
T
A
N
PERALATAN 4,516,534.38
TOTAL ( Rp ) 83,703,134.38

VOLUME /
QUANTITY : 1400 SATUAN m2 HARGA SATUAN 59,787.95 Per m2
KODE

DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN


DIREKTORAT BINA PROGRAM JALAN MENGHAMPAR DAN MEMADATKAN LATASIR TEBAL 1 cm

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ( MENGGUNAKAN BURUH ) K.638

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Bersihkan perkerasan aspal yang lama 1. Menggunakan tanaga orang ( 1600 m2/hari )
2. Melapisi dengan Tack coat 2. Campuran dikirim ke tempat pekerjaan oleh leveransir
3. Taburkan pasir aspal dengan tangan 3. BJ padat 1.90 ton/m3
4. Gilas dan padatkan 4. Tack Coat 0.6 lt/m2
5. Suhu pemadatan awal min 110 derajat C pemadatan 5. Spec BM no. 02/PT/B/1983
Akhir 60 derajat C

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Operator Terlatih 1.00 1 L.081 1 55,000.00 55,000.00
K Buruh Lapangan tak terlatih 7.00 1 L.101 7 30,000.00 210,000.00
E Buruh lapangan semi terlatih 7.00 1 L103 7 31,000.00 217,000.00
R Sopir 1.00 1 L.091 1 43,000.00 43,000.00
J
A
PEKERJA 568,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Aspal bitumen 480.00 kg M.061 7,720.00 3,705,600.00
T Minyak tanah 480.00 ltr M.065 4,550.00 2,184,000.00
E Campuran latasir 30.00 ton K.020 1,016,273.00 30,488,190.00
R Alat - Alat bantu (set @ 3 alat) 4.00 set M.170 55,000.00 220,000.00
I kayu bakar 1.70 m3 M.070 149,500.00 254,150.00
A
L
MATERIAL 36,851,940.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R TAMDEM ROLLER 6 - 10 ton 1.00 1 E.081 5.00 136,871.93 684,359.65
A FLAT BED TRUCK 4 ton 1.00 1 E.221 5.00 139,682.90 698,414.52
L
A
T
A
N
PERALATAN 1,382,774.17
TOTAL ( Rp ) 38,803,214.17

VOLUME /
QUANTITY : 1600 SATUAN m2 HARGA SATUAN 24,252.01 Per m2 640
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN PENGHAMPARAN DAN PEMADATAN LATASTON TEBAL 3 cm

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN ALAT) K.636

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Pengiriman Material sampai ke bin preader 1. Menggunakan alat baerat 1500 m2/hari
2. Materaial dihampar dengan mesin speader, dipadatkan 2. Asbutton campuran panas dikirim oleh leveransir ke tampat pekerjaan
3. dengan mesin gilas roda baja dan roda ban pneumatic 3. BJ. Asbutton padat 2.2 ton/m3
4. Spec - BM no. 12/DT/B/1983
5. Rata - rata tebal lapisan 3 cm

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Operator Terlatih 4.00 1 L.081 4 55,000.00 220,000.00
K Buruh Lapangan tak terlatih 12.00 1 L.101 12 30,000.00 360,000.00
E Buruh lapangan terlatih 8.00 1 L.106 8 40,000.00 320,000.00
R
J
A
PEKERJA 943,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Aspal Curah 450.00 kg M.062 5,590.00 2,515,500.00
T Minyak tanah 300.00 ltr M.065 4,550.00 1,365,000.00
E Campuran lataston 100.00 ton K.035 769,673.47 76,967,347.00
R Alat - Alat bantu (set @ 3 alat) 0.50 set M.170 55,000.00 27,500.00
I
A
L
MATERIAL 80,875,347.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R TAMDEM ROLLER 6 - 10 ton 1.00 1 E.081 5 136,871.93 684,359.65
A PNEUMATIC ROLLER 8 - 15 Ton 1.00 1 E.084 5 233,948.69 1,169,743.45
L ASPHALT SPRAYER TOWED 350 L 1.00 1 E.153 4 91,266.98 365,067.93
A ASPHLAT FINISHER 1.00 1 E.157 5 369,985.00 1,849,925.00
T COMPRESOR, AIR 150 m3 1.00 1 E.301 4 103,720.16 414,880.65
A
N
PERALATAN 4,483,976.68
TOTAL ( Rp ) 86,302,823.68

VOLUME /
QUANTITY : 1500 SATUAN m2 HARGA SATUAN 57,535.22 Per m2
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN LAPIS PENETRASI PONDASI ATAS MAKADAM 7 CM (LAPEN)

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.637

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Hampar batu pecah 3 - 5 cm 16m2/m3 1. Menggunakan tenaga manusia
2. Hampar batu pecah 2 - 3 cm,60m2/m3 2. Metarial dikirimi ke pekerjaan oleh pemasok
3. Setiap lapis batu dipadatkan 3. Tebal lapisan 7cm
4. Semprot aspal 3.7 l/m2 4. Kapasitas hamparan 2000/minggu (6 hari)
5. Hampar batu pecah 1 -2 cm, 70 m2/m3
6. Semprotkanb aspal 1.5 l/m2
7. Hampar pasir (blilnder) 90 m2/m3

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 2.00 3 L.061 6 43,500.00 261,000.00
E Operator Terlatih 2.00 3 L.081 6 55,000.00 330,000.00
K Sopir Material/truck 1.00 3 L.091 3 43,000.00 129,000.00
E Buruh lapangan tak terlatih 66.00 3 L.101 198 30,000.00 5,940,000.00
R buruh lapangan terlatih 2.00 3 L.106 6 40,000.00 240,000.00
J
A
PEKERJA 6,900,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Batu pecah 3 - 5 cm 62.00 m3 M.023 143,000.00 8,866,000.00
T Batu pecah 2 -3 cm 16.60 m3 M.024 195,000.00 3,237,000.00
E Batu pecah 1 - 2 cm 14.20 m3 M.025 235,000.00 3,337,000.00
R Agregat halus / pasi bersih 11.10 m3 M.041 130,000.00 1,443,000.00
I Aspal bitumen 5,500.00 kg M.061 7,720.00 42,460,000.00
A Alat - Alat bantu (set @ 3 alat) 8.00 set M.170 55,000.00 440,000.00
L
MATERIAL 59,783,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R ROLLER THREE WHEEL 8 - 10 ton 1.00 3 E.080 15.00 137,655.42 2,064,831.30
A SPRAYER TOWED 400L 1.00 3 E.154 15.00 23,763.97 356,459.53
L FLAT BED TRUCK 4 ton 1.00 3 E.221 15.00 139,682.90 2,095,243.56
A
T
A
N
PERALATAN 4,516,534.38
TOTAL ( Rp ) 71,199,534.38

VOLUME /
QUANTITY : 70 SATUAN m3 HARGA SATUAN 1,017,136.21 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN MENGHAMPAR LAPIS PERMUKAAN LAPIS ASPAL BETON

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (LASTON) ( MENGGUNAKAN ALAT) K.641

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Pengiriman matrial sampai ke bin preader 1. Menggunakan peralatan
2. Material dihampar dengan mesin spreader, dipadatkan 2. Hotmix dikirim leveransir sampai spreader
dengan mesin gilas roda baja dan roda ban pneumatiz 3. BJ asbutton padat 2.25 ton/m3
3. Suhu Pemadam awal min 110 derajat C, pedatan akhir 4. Produksi 900 m2 padat
60 derajat C 5. Spec - BM no. B/PT/BM
6. Disemprot tack coat 0.4 ltr/m2

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Operator Terlatih 4.00 1 L.081 4 55,000.00 220,000.00
K Buruh lapangan tak terlatih 12.00 1 L.101 12 30,000.00 360,000.00
E Buruh lapangan terlatih 8.00 1 L.106 8 40,000.00 320,000.00
R
J
A
PEKERJA 943,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Aspal bitumen 350.00 kg M.061 7,720.00 2,702,000.00
T Minyak tanah 300.00 ltr M.065 4,550.00 1,365,000.00
E Pasir beton/bersih 0.90 m3 M.041 130,000.00 117,000.00
R Campuran laston 100.00 ton K..040 779,248.17 77,924,817.00
I Alat - Alat bantu (set @ 3 alat) 0.80 set M.170 55,000.00 44,000.00
A
L
MATERIAL 82,152,817.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R ROLLER THREE WHEEL 8 - 10 ton 1.00 1 E.080 5 137,655.42 688,277.10
A TANDEM ROLLER 6 - 10 ton 1.00 1 E.081 5 136,871.93 684,359.65
L PNEUMATIC ROLLER 8 - 15 TON 1.00 1 E.084 5 233,948.69 1,169,743.45
A ASPHALT SPRAYER TOWED 350 L 1.00 1 E.153 3 91,266.98 273,800.95
T ASPHALT FINISHER 1.00 1 E.157 5 369,985.00 1,849,925.00
A COMPRESOR AIR 150 m3 1.00 1 E.301 4 103,720.16 414,880.65
N
PERALATAN 5,080,986.80
TOTAL ( Rp ) 88,177,303.80

VOLUME /
QUANTITY : 45 SATUAN m3 HARGA SATUAN 1,959,495.64 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN PENULANGAN BETON (MEMOTONG, MEMBENGKOK DAN MEMASANG BESI TULANGAN)

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.715

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Pemotongan dan pembengkokan dan perakitan 1. 200kg tulangan jadi disiapkan dalam 1 hari
tulangan dilakukan ditempat pekerjafan bersama - sama 2. Besi untuk tulangan dikirim ketempat pekrjaan oleh leveransir
persiapan pekerjaan 3. Batang - bantang tulangan dibengkok ditempat pekerjaan
4. Penyusutan tulangan dihitung 10% dan pemakaian kawat baja dihitung 1%

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Kepala Tukang 1.00 1 L.073 1 45,500.00 45,500.00
K Buruh Lapangan tak terlatih 2.00 1 L.101 2 30,000.00 60,000.00
E Buruh Lapangan agak terlatih 2.00 1 L.103 2 31,000.00 62,000.00
R
J
A
PEKERJA 211,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Baja Tulangan dan Kawat Beton 225.00 kg M.167 8,650.00 1,946,250.00
T Alat - Alat bantu (set @ 3 alat) 0.20 set M.170 55,000.00 11,000.00
E
R
I
A
L
MATERIAL 1,957,250.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R
A
L
A
T
A
N
PERALATAN -
TOTAL ( Rp ) 2,168,250.00

VOLUME /
QUANTITY : 200 SATUAN kg HARGA SATUAN 10,841.25 Per kg
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN BETON CYCLOOP

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN K.720 R

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Material dikirim oleh levensir 1. Bahan - bahan dasar dikirim ke lokasi pekerjaan oleh pemasok
2. Pencampuran beton ditempat pekerjaan 2. Dipakai Agregat Pecah dan batu 5/7 30%
3. Hasil kerja 6.0 m3/hari, 6 jam ( 9campuran per jam)
4. Campuran 1 PC : 3 Ps : 5 Kr ( atau 1 : 8)
5. Dalam 1 m3 beton dibutuhkan 6.25 sak (40 kg/zak) PC (250 kg/m3)
6. Setiap pencampuran memerlukan + 30 kg semen
7. Dibutuhkan untuk alas pondasi beton

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Buruh lapangan tak terlatih 12.00 1 L.101 12 30,000.00 360,000.00
K Buruh lapangan Agak terlatih 2.00 1 L.103 2 31,000.00 62,000.00
E
R
J
A
PEKERJA 465,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Pasir bersih 3.00 m3 M.041 130,000.00 390,000.00
T semen 1,500.00 kg M.080 1,352.00 2,028,000.00
E Alat - Alat bantu (set @ 3 alat) 0.60 set M.170 55,000.00 33,000.00
R Batu pecah 2 - 3cm 3.50 m3 M.024 195,000.00 682,500.00
I Batu 5/7 1.50 m3 M.022 143,000.00 214,500.00
A
L
MATERIAL 3,348,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R CONCRETE VIBRATOR 1.00 1 E.089 5 11,619.95 58,099.75
A CONCRETE MIXER (Beton Molen)0.125 M3 1.00 1 E.251 5 11,222.10 56,110.48
L WATER PUMP ( 0.5 CM ) 1.00 1 E.341 5 14,508.27 72,541.34
A
T
A
N
PERALATAN 186,751.57
TOTAL ( Rp ) 4,000,251.57

VOLUME /
QUANTITY : 6 SATUAN m3 HARGA SATUAN 666,708.60 Per m3
KODE

DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN


DIREKTORAT BINA PROGRAM JALAN BETON NON STRUKTUR / RABAT K.125

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN K.720

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Material dikirim oleh levensir 1. Bahan - bahan dasar dikirim ke lokasi pekerjaan oleh pemasok
2. Pencampuran beton ditempat pekerjaan 2. Dipakai Agregat Pecah dan batu 5/7 30%
3. Hasil kerja 6.0 m3/hari, 6 jam ( 9campuran per jam)
4. Campuran 1 PC : 3 Ps : 5 Kr ( atau 1 : 8)
5. Dalam 1 m3 beton dibutuhkan 6.25 sak (40 kg/zak) PC (250 kg/m3)
6. Setiap pencampuran memerlukan + 30 kg semen
7. Dibutuhkan untuk alas pondasi beton

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Buruh lapangan tak terlatih 12.00 1 L.101 12 30,000.00 360,000.00
K Buruh lapangan agak terlatih 2.00 1 L.103 2 31,000.00 62,000.00
E
R
J
A
PEKERJA 465,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Pasir beton 3.00 m3 M.041 130,000.00 390,000.00
T semen 1,500.00 kg M.080 1,352.00 2,028,000.00
E Alat - Alat bantu (set @ 3 alat) 0.60 set M.170 55,000.00 33,000.00
R Batu pecah 2 - 3cm 5.00 m3 M.024 195,000.00 975,000.00
I
A
L
MATERIAL 3,426,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R CONCRETE VIBRATOR 1.00 1 E.089 5 11,619.95 58,099.75
A CONCRETE MIXER (Beton Molen)0.125 M3 1.00 1 E.251 5 11,222.10 56,110.48
L WATER PUMP ( 0.5 CM ) 1.00 1 E.341 5 14,508.27 72,541.34
A
T
A
N
PERALATAN 186,751.57
TOTAL ( Rp ) 4,078,251.57

VOLUME /
QUANTITY : 6 SATUAN m3 HARGA SATUAN 679,708.60 Per m3
KODE

DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN


DIREKTORAT BINA PROGRAM JALAN PERANCAH (BEGISTING) UNTUK BETON BERTULANG

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.710

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Pengadaan bahan oleh Leveransir 1. Kelompok tukang kayu memasang 100m2 dalam 5 hari kerja
2. Tukang kayu memotong dan membuat acuan/ perancah 2. 1/3 material dapat dipakai kembali
3. Tukang kayu membongkar acuan/perancah setelah disetujui 3. Pengadaan bahan oleh leveransir
4. Untuk 1m3 beton digunakan 40 lbr playwood untuk : 120cm x 240cm x 1.7
5. Tukang kayu membongkar perancah

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 5 L.061 5 43,500.00 217,500.00
E Tukang 4.00 5 L.079 20 40,500.00 810,000.00
K Buruh Lapangan tak terlatih 7.00 5 L.101 35 30,000.00 1,050,000.00
E Buruh Lapangan agak terlatih 3.00 5 L.103 15 31,000.00 465,000.00
R
J
A
PEKERJA 2,542,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Paku 20.00 kg M.166 15,600.00 312,000.00
T Kayu 3.00 m3 M.180 2,080,000.00 6,240,000.00
E Alat - Alat bantu (set @ 3 alat) 3.00 set M.170 55,000.00 165,000.00
R
I
A
L
MATERIAL 6,717,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R
A
L
A
T
A
N
PERALATAN -
TOTAL ( Rp ) 9,259,500.00

VOLUME /
QUANTITY : 100 SATUAN m2 HARGA SATUAN 92,595.00 Per m2
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN BETON STRUKTUR K.225

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN ALAT PENGADUK BETON ) K.722

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Pemasok mengirim material 1. Bahan - bahan dasar dikirim ke lokasi pekerjaan oleh pemasok
2. Acuan dan tulangan besi beton dipasang 2. Dipakai agregat pecah 2 - 3 cm
3. Beton di cor dari digetar sampai padat 3. Dicor 6.17 m3/hari dengan 54 adukan/6 jam/hari
4. Adukan 1 PC : 2 Ps 3 Kr ( yaitu 1 : 5) semen 324 kg/m3
air 160 kg/m3; 2487 kg/m3
5. Anggap tiap adukan membutuhkan 1,0 zak ( 27.8 liter lepas) semen
portland; 55,6 ltr pasir, 83,3 ltr kerikil dan 18,3 ltr air
6. Tidak termasuk acuan dan tulangan besi beton yang sudah dipasang
7. Beton bertulang dipakai untuk pilar, gorong- gorong dinding penahan dll
8. Sesuai peraturan beton bertulang Indonesia (PBI 1971 N.I.2)

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 6 L.061 6 43,500.00 261,000.00
E Buruh Lapangan tak terlatih 12.00 6 L.101 72 30,000.00 2,160,000.00
K Buruh Lapangan terlatih 2.00 6 L.106 12 40,000.00 480,000.00
E
R
J
A
PEKERJA 2,901,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
M Satuan (Rp/Unit ( Rp. ) ( Rp. )
A
T Agregat halus / Pasir bersih 18.00 m3 M.041 130,000.00 2,340,000.00
E protland Cement ( PC ) 11,988.00 kg M.080 1,352.00 16,207,776.00
R Alat - Alat bantu (set @ 3 alat) 2.88 set M.170 55,000.00 158,400.00
I Batu pecah 2 - 3 cm 27.00 m3 M.024 195,000.00 5,265,000.00
A
L
MATERIAL 23,971,176.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
P Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
E
R CONCRETE VIBRATOR 1.00 6 E.089 36.00 11,619.95 418,318.23
A CONCRETE MIXER (Beton Molen) 0.50m3 1.00 6 E.253 36.00 57,449.97 2,068,198.74
L WATER PUMP ( 0.5 cm ) 1.00 6 E.341 12.00 14,508.27 174,099.22
A
T
A
N
PERALATAN 2,660,616.19
TOTAL ( Rp ) 29,532,792.19

VOLUME /
QUANTITY : 37 SATUAN m3 HARGA SATUAN 798,183.57 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN BETON STRUKTUR/UNTUK KONTRUKSI K.175(KLS A)

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN K.725

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Material dikirim oleh Leveransir 1. Keperluan material dikirim ke tempat kpekerjaan oleh leveransir
2. Pasang begisting 9 lihat ( K.211 ) 2. Produksi 6,4 m3/hari 6 jam, 9 campuran/jam
3. Pengadukan Beton ditempat pekerjaan 3. Campuaran beton 1 : 2 : 3 ( atau 1 : 5 )
4. Adukan beton dituang ditempat yang dikehendaki 4. Untuk 1m3 dibutuhkan 7.5 PC (40 kg/zak) atau 300 kg/PC/m3
dan digetar supaya padat 5. Perancah langsung dipasang ditempat
6. Tidak termasuk pekerjaan pembesian
7. Dipakai Agregat pecah 2 - 3 cm

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Buruh Lapangan tak terlatih 12.00 1 L.101 12 30,000.00 360,000.00
K Buruh Lapangan agak terlatih 2.00 1 L.103 2 31,000.00 62,000.00
E
R
J
A
PEKERJA 465,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Agregat halus /Pasir Bersih 3.00 m3 M.041 130,000.00 390,000.00
T Portland Cement (PC) 1,800.00 kg M.080 1,352.00 2,433,600.00
E Alat - Alat bantu (set @ 3 alat) 0.60 set M.170 55,000.00 33,000.00
R Batu pecah 2 - 3 cm 4.60 m3 M.024 195,000.00 897,000.00
I
A
L
MATERIAL 3,753,600.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E CONCRETE VIBRATOR 1.00 1 E.089 5.00 11,619.95 58,099.75
R CONCRETE MEXER (Beton Molen) 0.125m3 1.00 1 E.251 5.00 11,222.10 56,110.48
A WATER PUMP (0 5 cm) 1.00 1 E.341 5.00 14,508.27 72,541.34
L
A
T
A
N
PERALATAN 186,751.57
TOTAL ( Rp ) 4,405,851.57

VOLUME /
QUANTITY : 6 SATUAN m3 HARGA SATUAN 734,308.60 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN BETON STRUKTUR K.275

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ( Mengaduk Alat Pengaduk Beton ) K.726

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Pemasok Mengirim Materail 1. Keperluan material dikirim ke tempat kpekerjaan oleh Pemasok
2. Acuan dan tulang besi beton dipasang 2. Dipakai Agregat pecah 2 - 3cm
3. Beton diaduk dilokasi pekerjaan 3. Dicor m3/hari dengan 48 adukan /6 jam/hari
4. Beton dicor dan digetar sampai padat 4. Adukan 2 PC : 3 Ps : 6 Kr (yaitu 2 : 9); semen : 400kg/m3 air: 170 kg/m3
2598 kg/m3
5. Anggap tiap adukan membutuhkan 2,5 zak (69,4 liter lepas semen portland;
104,2 ltr pasir; 208,3ltr kerikil; dan 42.5 ltr air
6. Tidak termasuk acuan dan tulangan besi yang sudah dipasang
7. Beton bertulang dipakai untuk bagian - baigan struktur utama
8. Sesuai peraturan Beton bertulang indonesia (PBI 1971 N.I.2)

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Buruh Lapangan tak terlatih 25.00 1 L.101 25 30,000.00 750,000.00
K Buruh Lapangan terlatih 3.00 1 L.106 3 40,000.00 120,000.00
E
R
J
A
PEKERJA 913,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
M Satuan (Rp/Unit ( Rp. ) ( Rp. )
A
T Agregat halus /Pasir Bersih 5.00 m3 M.041 130,000.00 650,000.00
E Portland Cement (PC) 4,800.00 kg M.080 1,352.00 6,489,600.00
R Alat - Alat bantu (set @ 3 alat) 1.00 set M.170 55,000.00 55,000.00
I Batu pecah 2 - 3 cm 10.00 m3 M.024 195,000.00 1,950,000.00
A
L
MATERIAL 9,144,600.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
P Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
E
R CONCRETE VIBRATOR 2.00 1 E.089 12 11,619.95 139,439.41
A CONCRETE MEXER (Beton Molen) 0.50m3 1.00 1 E.253 6 57,449.97 344,699.79
L WATER PUMP (0 5 cm) 1.00 1 E.341 2 14,508.27 29,016.54
A
T
A
N
PERALATAN 513,155.74
TOTAL ( Rp ) 10,571,255.74

VOLUME /
QUANTITY : 12 SATUAN m3 HARGA SATUAN 880,937.98 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN BETON STRUKTUR K.350

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ( Mengaduk Alat Pengaduk Beton 500 Liter) K.730

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Pemasok Mengirim Materail 1. Bahan - bahan dasar dikirim kelokasi pekerjaan oleh pemasok
2. Acuan dan tulang besi beton dipasang 2. Dipakai Agregat pecah 2 - 3 cm
3. Beton diaduk dilokasi pekerjaan 3. Di cor 22,6 m3/hari dengan adukan/6 jam/hari
4. Beton dicor dan digetar sampai padat 4. Adukan 4 PC : 6 Ps : 11 Kr (yaitu 4 : 17); semen : 425kg/m3 air: 180 kg/m3
2642 kg/m3
5. Anggap tiap adukan membutuhkan 5 zak (138,9 liter lepas semen portland;
208,3 ltr pasir; 381.9ltr kerikil; dan 84.7 ltr air
6. Tidak termasuk acuan dan tulangan besi yang sudah dipasang
7. Beton dipakai untuk bagian - bagian struktur pratekan, lantai jembatan

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 2.00 6 L.061 12 43,500.00 522,000.00
E Buruh Lapangan tak terlatih 50.00 6 L.101 300 30,000.00 9,000,000.00
K Buruh Lapangan terlatih 5.00 6 L.106 30 40,000.00 1,200,000.00
E
R
J
A
PEKERJA 10,722,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
M Satuan (Rp/Unit ( Rp. ) ( Rp. )
A
T Agregat halus /Pasir Bersih 60.00 m3 M.041 130,000.00 7,800,000.00
E Portland Cement (PC) 57,375.00 kg M.080 1,352.00 77,571,000.00
R Alat - Alat bantu (set @ 3 alat) 12.00 set M.170 55,000.00 660,000.00
I Batu pecah 2 - 3 cm 110.00 m3 M.024 195,000.00 21,450,000.00
A
L
MATERIAL 107,481,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
P Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
E
R CONCRETE VIBRATOR 4.00 6 E.089 144 11,619.95 1,673,272.94
A CONCRETE MEXER (Beton Molen) 0.50m3 1.00 6 E.253 36 57,449.97 2,068,198.74
L WATER PUMP (0 5 cm) 1.00 6 E.341 12 14,508.27 174,099.22
A
T
A
N
PERALATAN 3,915,570.90
TOTAL ( Rp ) 122,118,570.90

VOLUME /
QUANTITY : 135 SATUAN m3 HARGA SATUAN 904,582.01 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN KONTRUKSI PASANGAN BATU

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.810.A

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Materail disiapkan dilokasi oleh leveransir 1. Dilakukan untuk pekerjaan gorong- gorong jembatan, dinding
2. Pekerjaan membawa batu pecah ketempat tukang batu berkerja penahan tanh dan struktur lainnya yang menggunakan konstruksi
3. Tukang batu memasang batu pecah dengan adukan pasir semen pasangan batu
2. Material pekerjaan dikirim ketempat pekerjaan oleh leveransir
3. Tidak termasuk galian/timbunan
4. Bagian M.170 diperbolehkan pakai batu
5. Batu besar belah didapat dari lokasi pekerjaan

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Tukang 4.00 1 L.079 4 40,500.00 162,000.00
K Buruh lapangan tak terlatih 13.00 1 L.101 13 30,000.00 390,000.00
E
R
J
A
PEKERJA 595,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Batu Aquary/batu besar belah (0,5 x M.010) 5.00 m3 M.010 71,500.00 357,500.00
T Agregat Halus / pasir belah 1.20 m3 M.041 130,000.00 156,000.00
E Portland Cement 760.00 kg M.080 1,352.00 1,027,520.00
R Alat - alat bantu (set @3 alat) 0.70 set M.170 55,000.00 38,500.00
I
A
L
MATERIAL 1,579,520.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R
A
L
A
T
A
N
PERALATAN -
TOTAL ( Rp ) 2,175,020.00

VOLUME /
QUANTITY : 5 SATUAN m3 HARGA SATUAN 435,004.00 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN KONTRUKSI PASANGAN BATU

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.810

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Materail disiapkan dilokasi oleh leveransir 1. Dilakukan untuk pekerjaan gorong- gorong jembatan, dinding
2. Pekerjaan membawa batu pecah ketempat tukang batu berkerja penahan tanh dan struktur lainnya yang menggunakan konstruksi
3. Tukang batu memasang batu pecah dengan adukan pasir semen pasangan batu
2. Material pekerjaan dikirim ketempat pekerjaan oleh leveransir
3. Tidak termasuk galian/timbunan
4. Bagian M.170 diperbolehkan pakai batu

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 1 L.061 1 43,500.00 43,500.00
E Tukang 4.00 1 L.079 4 40,500.00 162,000.00
K Buruh lapangan tak terlatih 13.00 1 L.101 13 30,000.00 390,000.00
E
R
J
A
PEKERJA 595,500.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Batu Aquary/batu besar belah 5.00 m3 M.010 143,000.00 715,000.00
T Agregat Halus / pasir belah 1.20 m3 M.041 130,000.00 156,000.00
E Portland Cement 760.00 kg M.080 1,352.00 1,027,520.00
R Alat - alat bantu (set @3 alat) 0.70 set M.170 55,000.00 38,500.00
I
A
L
MATERIAL 1,937,020.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R
A
L
A
T
A
N
PERALATAN -
TOTAL ( Rp ) 2,532,520.00

VOLUME /
QUANTITY : 5 SATUAN m3 HARGA SATUAN 506,504.00 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN BRONJONG PENAHAN

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.815

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Gali muka tanah untuk tempat Bronjong 1. Batu dikirim ke Lapangan oleh Laveransir
2. Rangkai dan bentuk anyaman bronjong 2. Kawat Bronjong Anyaman Dia 4mm
3. Isi anyaman kawat dengan batu 3. Selesai dalam 2 (dua) hari
4. Urug kembali hingga mantap

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 2 L.061 2 43,500.00 87,000.00
E Buruh lapangan tak terlatih 35.00 2 L.101 70 30,000.00 2,100,000.00
K Buruh Lapangan agak terlatih 5.00 2 L.103 10 31,000.00 310,000.00
E Buruh Lapangan terlatih 2.00 2 L.106 4 40,000.00 160,000.00
R
J
A
PEKERJA 2,657,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Batu Besar belah x 100% 25.00 m3 M.010 143,000.00 3,575,000.00
T Baja Anyaman Bronjong Galvanis Dia 4mm 375.00 kg M.162 24,700.00 9,262,500.00
E Alat - alat bantu (set @3 alat) 3.30 set M.170 55,000.00 181,500.00
R
I
A
L
MATERIAL 13,019,000.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R
A
L
A
T
A
N
PERALATAN -
TOTAL ( Rp ) 15,676,000.00

VOLUME /
QUANTITY : 25 SATUAN m3 HARGA SATUAN 627,040.00 Per m3
KODE
DIREKTORAT JEND. BINA MARGA ANALISA BIAYA PEKERJAAN
DIREKTORAT BINA PROGRAM JALAN BRONJONG PENAHAN

SUB DIT, PERENC. JALAN LOKAL & KABUPATEN (MENGGUNAKAN BURUH) K.815.A

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29 TANGGL …………/ ………./ ……

PROSES ANGGAPAN / ASUMSI


1. Gali muka tanah untuk tempat Bronjong 1. Batu tersedia dilapangan
2. Rangkai dan bentuk anyaman bronjong 2. Kawat Bronjong Anyaman Dia 4mm
3. Isi anyaman kawat dengan batu 3. Selesai dalam 2 (dua) hari
4. Urug kembali hingga mantap

PEKERJAAN VOLUIME HARI / KODE Jumlah UPAH BIAYA SUB TOTAL


ORANG Hari - Orang ( Rp./Org/Hari ) ( Rp. ) ( Rp. )
P Mandor Lapangan 1.00 2 L.061 2 43,500.00 87,000.00
E Buruh lapangan tak terlatih 35.00 2 L.101 70 30,000.00 2,100,000.00
K Buruh Lapangan agak terlatih 5.00 2 L.103 10 31,000.00 310,000.00
E Buruh Lapangan terlatih 2.00 2 L.106 4 40,000.00 160,000.00
R
J
A
PEKERJA 2,657,000.00
MATERIAL Jumlah Volume KODE HARGA BIAYA SUB TOTAL
Satuan (Rp/Unit ( Rp. ) ( Rp. )
M
A Batu Besar belah x 50% 25.00 m3 M.010 71,500.00 1,787,500.00
T Baja Anyaman Bronjong Galvanis Dia 4mm 375.00 kg M.162 24,700.00 9,262,500.00
E Alat - alat bantu (set @3 alat) 3.30 set M.170 55,000.00 181,500.00
R
I
A
L
MATERIAL 11,231,500.00
PERALATAN Jumlah Hari KODE Jam HARGA BIAYA SUB TOTAL
Alat Kerja Kerja (Rp-jam) ( Rp. ) ( Rp. )
P
E
R
A
L
A
T
A
N
PERALATAN -
TOTAL ( Rp ) 13,888,500.00

VOLUME /
QUANTITY : 25 SATUAN m3 HARGA SATUAN 555,540.00 Per m3
2.38
583.333333 194.44444
100.00
55.36
27.68
12,000.00 80.00
6.43
500.00
14.46
6.25
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.001

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : BULDOZER E.001


HARGA : 880,000,000.00 TENAGA : 100.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 1,600.00 JAM
HARGA ALAT : 880,000,000.00 FAKTOR : 0.2048
UMUR KERJA : 8.00 TAHUN
(1 TAHUN = 300 HARI KERJA, 1 HARI = 4 JAM KERJA)
= 9,600.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 880,000,000.00 x 0.20483 1
1,200.00 = Rp. 135,187.80
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 880,000,000.00 = Rp. 22,000.00
1,200.00

SUB TOTAL = Rp. 157,187.80

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 100 x 5,850.00 = Rp. 93,600.00
Pelumas = Rp. 0.006 x 100.00 x 33,150.00 = Rp. 19,890.00
Perbaikan & Sparepart = Rp. 0.600 x 135,187.80 = Rp. 81,112.68
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 1,600.00

SUB TOTAL = Rp. 194,602.68

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 157,187.80 + 194,602.68


= Rp. 351,790.48 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.010

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : MOTOR GRADER E.010


HARGA : 1,501,500,000.00 TENAGA : 115.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 1,600.00 JAM
HARGA ALAT : 1,501,500,000.00 FAKTOR : 0.20483
UMUR KERJA : 8.00 TAHUN
(1 TAHUN = 300 HARI KERJA, 1 HARI = 5 JAM KERJA)
= 12,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 1,501,500,000.00 x 0.20483 1
1,500.00 = Rp. 184,531.35
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 1,501,500,000.00 = Rp. 30,030.00
1,500.00

SUB TOTAL = Rp. 214,561.35

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 115 x 5,850.00 = Rp. 107,640.00
Pelumas = Rp. 0.006 x 115 x 33,150.00 = Rp. 22,873.50
Perbaikan & Sparepart = Rp. 0.600 x 184,531.35 = Rp. 110,718.81
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 1,600.00

SUB TOTAL = Rp. 241,232.31

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 214,561.35 + 241,232.31


= Rp. 455,793.66 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.031

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : CRUSHER 30 T/hr E.031


HARGA : 1,980,000,000.00 TENAGA : 140.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 1,980,000,000.00 FAKTOR : 0.18062
UMUR KERJA : 10.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 5 JAM KERJA)
= 15,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 1,980,000,000.00 x 0.18062 1
1,500.00 = Rp. 214,576.56
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 1,980,000,000.00 = Rp. 39,600.00
1,500.00

SUB TOTAL = Rp. 254,176.56

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,900.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 140.00 x 5,900.00 = Rp. 132,160.00
Pelumas = Rp. 0.006 x 140.00 x 33,150.00 = Rp. 27,846.00
Perbaikan & Sparepart = Rp. 0.600 x 214,576.56 = Rp. 128,745.94
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 1,600.00

SUB TOTAL = Rp. 288,751.94

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 254,176.56 + 288,751.94


= Rp. 542,928.50 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.040

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : SCREENING PLANT E.040


HARGA : 499,991,250.00 TENAGA : 80.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 499,991,250.00 FAKTOR : 0.20483
UMUR KERJA : 8.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 5 JAM KERJA)
= 12,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 499,991,250.00 x 0.20483 1
1,500.00 = Rp. 61,447.92
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 499,991,250.00 = Rp. 9,999.83
1,500.00

SUB TOTAL = Rp. 71,447.75

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 80.00 x 5,850.00 = Rp. 74,880.00
Pelumas = Rp. 0.006 x 80.00 x 33,150.00 = Rp. 15,912.00
Perbaikan & Sparepart = Rp. 0.600 x 61,447.92 = Rp. 36,868.75
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 1,600.00

SUB TOTAL = Rp. 127,660.75

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 71,447.75 + 127,660.75


= Rp. 199,108.50 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.052

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : LOADER WHEELED E.052


HARGA : 698,500,000.00 TENAGA : 115.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 698,500,000.00 FAKTOR : 0.20483
UMUR KERJA : 8.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 5 JAM KERJA)
= 12,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 698,500,000.00 x 0.20483 1
1,500.00 = Rp. 85,844.25
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 698,500,000.00 = Rp. 13,970.00
1,500.00

SUB TOTAL = Rp. 99,814.25

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 115 x 5,850.00 = Rp. 107,640.00
Pelumas = Rp. 0.006 x 115 x 33,150.00 = Rp. 22,873.50
Perbaikan & Sparepart = Rp. 0.600 x 85,844.25 = Rp. 51,506.55
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 1,600.00

SUB TOTAL = Rp. 182,020.05

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 99,814.25 + 182,020.05


= Rp. 281,834.30 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.053

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : TRACTOR WHEELED E.053


HARGA : 199,657,050.00 TENAGA : 60.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 199,657,050.00 FAKTOR : 0.18062
UMUR KERJA : 10.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 5 JAM KERJA)
= 15,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 199,657,050.00 x 0.18062 1
1,500.00 = Rp. 21,637.23
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 199,657,050.00 = Rp. 3,993.14
1,500.00

SUB TOTAL = Rp. 25,630.37

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 60 x 5,850.00 = Rp. 56,160.00
Pelumas = Rp. 0.006 x 60 x 33,150.00 = Rp. 11,934.00
Perbaikan & Sparepart = Rp. 0.600 x 21,637.23 = Rp. 12,982.34
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 1,600.00

SUB TOTAL = Rp. 81,076.34

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 25,630.37 + 81,076.34


= Rp. 106,706.72 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.080

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : ROLLER THREE WHEEL 8 - ton E.080


HARGA : 412,500,000.00 TENAGA : 51.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 412,500,000.00 FAKTOR : 0.18062
UMUR KERJA : 10.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 5 JAM KERJA)
= 15,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 412,500,000.00 x 0.18062 1
1,500.00 = Rp. 44,703.45
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 412,500,000.00 = Rp. 8,250.00
1,500.00

SUB TOTAL = Rp. 52,953.45

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 51 x 5,850.00 = Rp. 47,736.00
Pelumas = Rp. 0.006 x 51 x 33,150.00 = Rp. 10,143.90
Perbaikan & Sparepart = Rp. 0.600 x 44,703.45 = Rp. 26,822.07
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 0.00

SUB TOTAL = Rp. 84,701.97

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 52,953.45 + 84,701.97


= Rp. 137,655.42 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.081

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : TANDEM ROLLER 6 - 10 ton E.081


HARGA : 473,000,000.00 TENAGA : 40.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 473,000,000.00 FAKTOR : 0.18062
UMUR KERJA : 10.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 5 JAM KERJA)
= 15,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 473,000,000.00 x 0.18062 1
1,500.00 = Rp. 51,259.96
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 473,000,000.00 = Rp. 9,460.00
1,500.00

SUB TOTAL = Rp. 60,719.96

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 40 x 5,850.00 = Rp. 37,440.00
Pelumas = Rp. 0.006 x 40 x 33,150.00 = Rp. 7,956.00
Perbaikan & Sparepart = Rp. 0.600 x 51,259.96 = Rp. 30,755.97
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 0.00

SUB TOTAL = Rp. 76,151.97

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 60,719.96 + 76,151.97


= Rp. 136,871.93 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.083

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : TOWED VIBRATOR ROLLER 2 - 3 ton E.083


HARGA : 250,844,250.00 TENAGA : 6.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 250,844,250.00 FAKTOR : 0.20483
UMUR KERJA : 8.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 5 JAM KERJA)
= 12,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 250,844,250.00 x 0.20483 1
1,500.00 = Rp. 30,828.26
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 250,844,250.00 = Rp. 5,016.89
1,500.00

SUB TOTAL = Rp. 35,845.14

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 6 x 5,850.00 = Rp. 5,616.00
Pelumas = Rp. 0.006 x 6 x 33,150.00 = Rp. 1,193.40
Perbaikan & Sparepart = Rp. 0.600 x 30,828.26 = Rp. 18,496.95
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 0.00

SUB TOTAL = Rp. 25,306.35

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 35,845.14 + 25,306.35


= Rp. 61,151.50 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.084

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : PNEUMATIC ROLLER 8 - 15 ton E.084


HARGA : 652,204,350.00 TENAGA : 95.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 1,600.00 JAM
HARGA ALAT : 652,204,350.00 FAKTOR : 0.18062
UMUR KERJA : 10.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 5 JAM KERJA)
= 15,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 652,204,350.00 x 0.18062 1
1,500.00 = Rp. 70,680.69
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 652,204,350.00 = Rp. 13,044.09
1,500.00

SUB TOTAL = Rp. 83,724.78

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 95 x 5,850.00 = Rp. 88,920.00
Pelumas = Rp. 0.006 x 95 x 33,150.00 = Rp. 18,895.50
Perbaikan & Sparepart = Rp. 0.600 x 70,680.69 = Rp. 42,408.41
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 1,600.00

SUB TOTAL = Rp. 150,223.91

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 83,724.78 + 150,223.91


= Rp. 233,948.69 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.087

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : MESIN GILAS BERGETAR 1 ton E.087


HARGA : 104,638,950.00 TENAGA : 7.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 104,638,950.00 FAKTOR : 0.24668
UMUR KERJA : 6.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 4 JAM KERJA)
= 7,200.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 104,638,950.00 x 0.24668 1
1,200.00 = Rp. 19,359.25
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 104,638,950.00 = Rp. 2,615.97
1,200.00

SUB TOTAL = Rp. 21,975.23

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 7 x 5,850.00 = Rp. 6,552.00
Pelumas = Rp. 0.006 x 7 x 33,150.00 = Rp. 1,392.30
Perbaikan & Sparepart = Rp. 0.600 x 19,359.25 = Rp. 11,615.55
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 0.00

SUB TOTAL = Rp. 19,559.85

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 21,975.23 + 19,559.85


= Rp. 41,535.08 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.088

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : PLATE VIBRATOR TAMPER E.088


HARGA : 16,354,050.00 TENAGA : 4.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 16,354,050.00 FAKTOR : 0.24668
UMUR KERJA : 6.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 2.5 JAM KERJA)
= 4,500.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 16,354,050.00 x 0.24668 1
750.00 = Rp. 4,841.06
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 16,354,050.00 = Rp. 654.16
750.00

SUB TOTAL = Rp. 5,495.22

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 4 x 5,850.00 = Rp. 3,744.00
Pelumas = Rp. 0.006 x 4 x 33,150.00 = Rp. 795.60
Perbaikan & Sparepart = Rp. 0.600 x 4,841.06 = Rp. 2,904.64
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 0.00

SUB TOTAL = Rp. 7,444.24

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 5,495.22 + 7,444.24


= Rp. 12,939.46 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.089

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : CONCRETE VIBRATOR E.089


HARGA : 9,778,950.00 TENAGA : 4.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 9,778,950.00 FAKTOR : 0.28085
UMUR KERJA : 5.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 2 JAM KERJA)
= 3,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 9,778,950.00 x 0.28085 1
600.00 = Rp. 4,119.63
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 9,778,950.00 = Rp. 488.95
600.00

SUB TOTAL = Rp. 4,608.57

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 4 x 5,850.00 = Rp. 3,744.00
Pelumas = Rp. 0.006 x 4 x 33,150.00 = Rp. 795.60
Perbaikan & Sparepart = Rp. 0.600 x 4,119.63 = Rp. 2,471.78
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 0.00

SUB TOTAL = Rp. 7,011.38

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 4,608.57 + 7,011.38


= Rp. 11,619.95 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.130

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : CHIP SPREADER E.130


HARGA : 39,929,550.00 TENAGA : 0.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 39,929,550.00 FAKTOR : 0.24668
UMUR KERJA : 6.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 2 JAM KERJA)
= 3,600.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 39,929,550.00 x 0.24668 1
600.00 = Rp. 14,774.73
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 39,929,550.00 = Rp. 1,996.48
600.00

SUB TOTAL = Rp. 16,771.21

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 0 x 5,850.00 = Rp. 0.00
Pelumas = Rp. 0.006 x 0 x 33,150.00 = Rp. 0.00
Perbaikan & Sparepart = Rp. 0.600 x 14,774.73 = Rp. 8,864.84
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 0.00

SUB TOTAL = Rp. 8,864.84

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 16,771.21 + 8,864.84


= Rp. 25,636.05 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.152

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : SPRAYE SELPROPELLED (pemanas aspal) E.152


HARGA : 559,683,300.00 TENAGA : 38.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 1,600.00 JAM
HARGA ALAT : 559,683,300.00 FAKTOR : 0.24668
UMUR KERJA : 6.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 4 JAM KERJA)
= 7,200.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 559,683,300.00 x 0.24668 1
1,200.00 = Rp. 103,547.01
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 559,683,300.00 = Rp. 13,992.08
1,200.00

SUB TOTAL = Rp. 117,539.09

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 38 x 5,850.00 = Rp. 35,568.00
Pelumas = Rp. 0.006 x 38 x 33,150.00 = Rp. 7,558.20
Perbaikan & Sparepart = Rp. 0.600 x 103,547.01 = Rp. 62,128.20
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 1,600.00

SUB TOTAL = Rp. 105,254.40

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 117,539.09 + 105,254.40


= Rp. 222,793.49 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.153

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : ASPHLAT SPRAYER TOWED 350 L E.153


HARGA : 162,224,550.00 TENAGA : 7.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 1,600.00 JAM
HARGA ALAT : 162,224,550.00 FAKTOR : 0.24668
UMUR KERJA : 6.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 2.5 JAM KERJA)
= 4,500.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 162,224,550.00 x 0.24668 1
750.00 = Rp. 48,021.06
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 162,224,550.00 = Rp. 6,488.98
750.00

SUB TOTAL = Rp. 54,510.04

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 7 x 5,850.00 = Rp. 6,552.00
Pelumas = Rp. 0.006 x 7 x 33,150.00 = Rp. 1,392.30
Perbaikan & Sparepart = Rp. 0.600 x 48,021.06 = Rp. 28,812.64
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 1,600.00

SUB TOTAL = Rp. 36,756.94

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 54,510.04 + 36,756.94


= Rp. 91,266.98 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.155

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : ASPHLAT MIXING PLAN 30t/h E.155


HARGA : 2,893,000,000.00 TENAGA : 125.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 2,893,000,000.00 FAKTOR : 0.18062
UMUR KERJA : 10.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 4 JAM KERJA)
= 12,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 2,893,000,000.00 x 0.18062 1
1,200.00 = Rp. 391,900.25
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 2,893,000,000.00 = Rp. 72,325.00
1,200.00

SUB TOTAL = Rp. 464,225.25

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,900.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.125 x 125 x 5,900.00 = Rp. 92,187.50
Bahan Bakar Pemanas Material (Khusus AMP) = Rp. 12.000 x 21.00 x 5,900.00 = Rp. 1,486,800.00
Pelumas = Rp. 0.006 x 125 x 33,150.00 = Rp. 24,862.50
Perbaikan & Sparepart = Rp. 0.600 x 391,900.25 = Rp. 235,140.15
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 0.00

SUB TOTAL = Rp. 1,838,990.15

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 464,225.25 + 1,838,990.15


= Rp. 2,303,215.39 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.157

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : ASPHLAT FINISHER E.157


HARGA : 1,150,000,000.00 TENAGA : 30.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 1,150,000,000.00 FAKTOR : 0.22260
UMUR KERJA : 7.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 4 JAM KERJA)
= 8,400.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 1,150,000,000.00 x 0.22260 1
1,200.00 = Rp. 191,992.50
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 1,150,000,000.00 = Rp. 28,750.00
1,200.00

SUB TOTAL = Rp. 220,742.50

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 30 x 5,850.00 = Rp. 28,080.00
Pelumas = Rp. 0.006 x 30 x 33,150.00 = Rp. 5,967.00
Perbaikan & Sparepart = Rp. 0.600 x 191,992.50 = Rp. 115,195.50
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 0.00

SUB TOTAL = Rp. 149,242.50

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 220,742.50 + 149,242.50


= Rp. 369,985.00 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.182

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : TRUCK AIR (WATER TANK TRUCK) E.182


HARGA : 158,100,000.00 TENAGA : 115.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 1,600.00 JAM
HARGA ALAT : 158,100,000.00 FAKTOR : 0.24668
UMUR KERJA : 6.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 5 JAM KERJA)
= 9,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 158,100,000.00 x 0.24668 1
1,500.00 = Rp. 23,400.06
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 158,100,000.00 = Rp. 3,162.00
1,500.00

SUB TOTAL = Rp. 26,562.06

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 115 x 5,850.00 = Rp. 107,640.00
Pelumas = Rp. 0.006 x 115 x 33,150.00 = Rp. 22,873.50
Perbaikan & Sparepart = Rp. 0.600 x 23,400.06 = Rp. 14,040.04
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 1,600.00

SUB TOTAL = Rp. 144,553.54

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 26,562.06 + 144,553.54


= Rp. 171,115.60 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.211

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : DUMP TRUCK 3,5 ton E.211


HARGA : 186,000,000.00 TENAGA : 106.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 1,600.00 JAM
HARGA ALAT : 186,000,000.00 FAKTOR : 0.24668
UMUR KERJA : 6.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 5 JAM KERJA)
= 9,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 186,000,000.00 x 0.24668 1
1,500.00 = Rp. 27,529.49
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 186,000,000.00 = Rp. 3,720.00
1,500.00

SUB TOTAL = Rp. 31,249.49

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 106 x 5,850.00 = Rp. 99,216.00
Pelumas = Rp. 0.006 x 106 x 33,150.00 = Rp. 21,083.40
Perbaikan & Sparepart = Rp. 0.600 x 27,529.49 = Rp. 16,517.69
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 1,600.00

SUB TOTAL = Rp. 136,817.09

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 31,249.49 + 136,817.09


= Rp. 168,066.58 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.212

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : DUMP TRUCK 5,00 ton E.212


HARGA : 232,500,000.00 TENAGA : 145.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 1,600.00 JAM
HARGA ALAT : 232,500,000.00 FAKTOR : 0.24668
UMUR KERJA : 6.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 5 JAM KERJA)
= 9,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 232,500,000.00 x 0.24668 1
1,500.00 = Rp. 34,411.86
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 232,500,000.00 = Rp. 4,650.00
1,500.00

SUB TOTAL = Rp. 39,061.86

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 145 x 5,850.00 = Rp. 135,720.00
Pelumas = Rp. 0.006 x 145 x 33,150.00 = Rp. 28,840.50
Perbaikan & Sparepart = Rp. 0.600 x 34,411.86 = Rp. 20,647.12
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 1,600.00

SUB TOTAL = Rp. 185,207.62

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 39,061.86 + 185,207.62


= Rp. 224,269.48 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.221

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : FLAT BED TRUCK 4 TON E.221


HARGA : 190,375,650.00 TENAGA : 80.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 1,600.00 JAM
HARGA ALAT : 190,375,650.00 FAKTOR : 0.24668
UMUR KERJA : 6.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 5 JAM KERJA)
= 9,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 190,375,650.00 x 0.24668 1
1,500.00 = Rp. 28,177.12
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 190,375,650.00 = Rp. 3,807.51
1,500.00

SUB TOTAL = Rp. 31,984.63

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 80 x 5,850.00 = Rp. 74,880.00
Pelumas = Rp. 0.006 x 80 x 33,150.00 = Rp. 15,912.00
Perbaikan & Sparepart = Rp. 0.600 x 28,177.12 = Rp. 16,906.27
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 1,600.00

SUB TOTAL = Rp. 107,698.27

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 31,984.63 + 107,698.27


= Rp. 139,682.90 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.154

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : SPRAYER TOWED 400 L E.154


HARGA : 30,800,000.00 TENAGA : 7.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 1,600.00 JAM
HARGA ALAT : 30,800,000.00 FAKTOR : 0.24668
UMUR KERJA : 6.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 2.5 JAM KERJA)
= 4,500.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 30,800,000.00 x 0.24668 1
750.00 = Rp. 9,117.29
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 30,800,000.00 = Rp. 1,232.00
750.00

SUB TOTAL = Rp. 10,349.29

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 7 x 5,850.00 = Rp. 6,552.00
Pelumas = Rp. 0.006 x 7 x 33,150.00 = Rp. 1,392.30
Perbaikan & Sparepart = Rp. 0.600 x 9,117.29 = Rp. 5,470.38
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 1,600.00

SUB TOTAL = Rp. 13,414.68

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 10,349.29 + 13,414.68


= Rp. 23,763.97 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.251

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : CONCRETE MIXER (Beton Molen) 0,125 m3 E.251


HARGA : 13,001,400.00 TENAGA : 6.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 13,001,400.00 FAKTOR : 0.33271
UMUR KERJA : 4.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 5 JAM KERJA)
= 6,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 13,001,400.00 x 0.33271 1
1,500.00 = Rp. 2,595.42
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 13,001,400.00 = Rp. 260.03
1,500.00

SUB TOTAL = Rp. 2,855.45

B. BIAYA OPERASI (OPERATION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 6 x 5,850.00 = Rp. 5,616.00
Pelumas = Rp. 0.006 x 6 x 33,150.00 = Rp. 1,193.40
Perbaikan & Sparepart = Rp. 0.600 x 2,595.42 = Rp. 1,557.25
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 0.00

SUB TOTAL = Rp. 8,366.65

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 2,855.45 + 8,366.65


= Rp. 11,222.10 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.252

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : CONCRETE MIXER (Beton Molen) 0,25 m3 E.252


HARGA : 60,022,200.00 TENAGA : 10.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 60,022,200.00 FAKTOR : 0.28085
UMUR KERJA : 5.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 5 JAM KERJA)
= 7,500.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 60,022,200.00 x 0.28085 1
1,500.00 = Rp. 10,114.34
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 60,022,200.00 = Rp. 1,200.44
1,500.00

SUB TOTAL = Rp. 11,314.78

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 10 x 5,850.00 = Rp. 9,360.00
Pelumas = Rp. 0.006 x 10 x 33,150.00 = Rp. 1,989.00
Perbaikan & Sparepart = Rp. 0.600 x 10,114.34 = Rp. 6,068.60
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 0.00

SUB TOTAL = Rp. 17,417.60

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 11,314.78 + 17,417.60


= Rp. 28,732.39 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.253

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : CONCRETE MIXER (Beton Molen) 0,50m3 E.253


HARGA : 119,993,250.00 TENAGA : 20.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 119,993,250.00 FAKTOR : 0.28085
UMUR KERJA : 5.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 5 JAM KERJA)
= 7,500.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 119,993,250.00 x 0.28085 1
1,500.00 = Rp. 20,220.06
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 119,993,250.00 = Rp. 2,399.87
1,500.00

SUB TOTAL = Rp. 22,619.93

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 20 x 5,850.00 = Rp. 18,720.00
Pelumas = Rp. 0.006 x 20 x 33,150.00 = Rp. 3,978.00
Perbaikan & Sparepart = Rp. 0.600 x 20,220.06 = Rp. 12,132.04
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 0.00

SUB TOTAL = Rp. 34,830.04

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 22,619.93 + 34,830.04


= Rp. 57,449.97 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.301

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : COMPRESOR AIR 150 m3 E.301


HARGA : 187,000,000.00 TENAGA : 20.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 1,600.00 JAM
HARGA ALAT : 187,000,000.00 FAKTOR : 0.20483
UMUR KERJA : 8.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 2.5 JAM KERJA)
= 6,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 187,000,000.00 x 0.20483 1
750.00 = Rp. 45,963.85
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 187,000,000.00 = Rp. 7,480.00
750.00

SUB TOTAL = Rp. 53,443.85

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 20 x 5,850.00 = Rp. 18,720.00
Pelumas = Rp. 0.006 x 20 x 33,150.00 = Rp. 3,978.00
Perbaikan & Sparepart = Rp. 0.600 x 45,963.85 = Rp. 27,578.31
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 1,600.00

SUB TOTAL = Rp. 50,276.31

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 53,443.85 + 50,276.31


= Rp. 103,720.16 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.341

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : WATER PUMP E.341


HARGA : 7,998,000.00 TENAGA : 8.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 7,998,000.00 FAKTOR : 0.33271
UMUR KERJA : 4.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 2.5 JAM KERJA)
= 3,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 7,998,000.00 x 0.33271 1
750.00 = Rp. 3,193.22
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 7,998,000.00 = Rp. 319.92
750.00

SUB TOTAL = Rp. 3,513.14

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 8 x 5,850.00 = Rp. 7,488.00
Pelumas = Rp. 0.006 x 8 x 33,150.00 = Rp. 1,591.20
Perbaikan & Sparepart = Rp. 0.600 x 3,193.22 = Rp. 1,915.93
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 0.00

SUB TOTAL = Rp. 10,995.13

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 3,513.14 + 10,995.13


= Rp. 14,508.27 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.401

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : TRACTOR EQUIPMENT,ETC E.401


HARGA : 101,532,750.00 TENAGA : 0.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 101,532,750.00 FAKTOR : 0.28085
UMUR KERJA : 5.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 2 JAM KERJA)
= 3,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 101,532,750.00 x 0.28085 1
600.00 = Rp. 42,773.21
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 101,532,750.00 = Rp. 5,076.64
600.00

SUB TOTAL = Rp. 47,849.85

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 0.00 x 5,850.00 = Rp. 0.00
Pelumas = Rp. 0.006 x 0.00 x 33,150.00 = Rp. 0.00
Perbaikan & Sparepart = Rp. 0.600 x 42,773.21 = Rp. 25,663.93
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 0.00

SUB TOTAL = Rp. 25,663.93

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 47,849.85 + 25,663.93


= Rp. 73,513.77 / Jam
TA. --/Bnd

DIREKTORAT JEND. BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN KODE


DIREKTORAT BINA PROGRAM JALAN
SUB DIT, PERENC. JALAN LOKAL & KABUPATEN ANALISA BIAYA PEKERJAAN E.402

PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH


JAWA TENGAH 33 BREBES 29

JENIS ALAT : GEROBAK DORONG (WHEEL BARROW) E.402


HARGA : 1,000,000.00 TENAGA : 0.00 HP
HARGA BAHAN : 0.00 UMUR BAN : 0.00 JAM
HARGA ALAT : 1,000,000.00 FAKTOR : 0.33271
UMUR KERJA : 4.00 TAHUN
(1 TAHUN = 300 HARI KERJA , 1 HARI = 5 JAM KERJA)
= 6,000.00 Jam

A. BIAYA PEMILIKAN (OWNERSHIP COST) (Rp/jam)


1. Depresiasi 90% x Alat x (CRF) 1
Jam/tahun
0.90 x 1,000,000.00 x 0.33271 1
1,500.00 = Rp. 199.63
2. Lain - lain
Asuransi 3% 0.30 x harga
Jam / tahun
0.03 x 1,000,000.00 = Rp. 20.00
1,500.00

SUB TOTAL = Rp. 219.63

B. BIAYA OPERASI (OPERTION COST) (Rp/jam)

Kebutuhan bahan bakar dan Pelumas tiap HP


Diesel = 0.160 liter/HP/jam
Bensin = 1.170 liter/HP/jam
Pelumas = 0.006 liter/HP/jam
Harga : Solar Minyak
Diesel = Rp. 5,850.00 / liter
Bensin = Rp. 5,850.00 / liter
Pelumas = Rp. 33,150.00
Bahan Bakar = Rp. 0.160 x 0.00 x 5,850.00 = Rp. 0.00
Pelumas = Rp. 0.006 x 0.00 x 33,150.00 = Rp. 0.00
Perbaikan & Sparepart = Rp. 0.600 x 199.63 = Rp. 119.78
(60% x Depresiasi)

Ban = Harga Ban = 0.00 = Rp. 0.00


Umur Ban 0.00

SUB TOTAL = Rp. 119.78

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT

A+B = Rp. 0.00 + 119.78


= Rp. 119.78 / Jam