Anda di halaman 1dari 10

TANGGAL: 09 Agustus 2022

JASA-JASA PENYEDIAAN DAN


PERAWATAN TERINTEGRASI - SISTEM
TRANSMISI & DISTRIBUSI - PGT
NO. SPHR00129A
REVISI: 0
PT. PERTAMINA HULU ROKAN

Check and electrical test for Transformer HALAMAN: 1 of 10

PT. Radiant Utama Interinsco

Document No RUI-MTCN-NORTH-PHR-82
RUR-6 : Senior Technician
Job Code
RUR-7 : Junior Technician

Description

Requestor Pertamina Hulu Rokan


No. ITP/SPK 388/MTCN/SPHR00129A/2/2023
Purchasing Group RK7-HR-TM MTCE SBS NORTH
Contract Ref. No 4710006117
Work Area
Location
No. TKI RUI-TKPA-TF-MTCNS-004
RUI-TKPA-TOOLS-MTCN/S-003 (IR Thermometer)
RUI-TKPA-TOOLS-MTCN/S-004/12 (Insulation Tester)
No. TKPA RUI-TKPA-TOOLS-MTCN/S-007 (Multimeter)
RUI-TKPA-TOOLS-MTCN/S-014 (Micro Ohm Meter)
RUI-TKPA-TOOLS-MTCN/S-016 (Thermometer Room)
Date Execution Start: Finish:

PT. RADIANT UTAMA INTERINSCO PT PERTAMINA HULU ROKAN


Execution by: Prepare by: Approved by: Acknowledge by:

Name: Name: Name: Name:


Position: Senior Tech Position: Elect. Analyst Position: Substation SPV Position:
Date: Date: Date Date:
TANGGAL: 09 Agustus 2022
JASA-JASA PENYEDIAAN DAN
PERAWATAN TERINTEGRASI - SISTEM
TRANSMISI & DISTRIBUSI - PGT
NO. SPHR00129A
REVISI: 0
PT. PERTAMINA HULU ROKAN

Check and electrical test for Transformer HALAMAN: 2 of 10

PT. Radiant Utama Interinsco

Date Description Paraf Remark


TANGGAL: 09 Agustus 2022
JASA-JASA PENYEDIAAN DAN
PERAWATAN TERINTEGRASI - SISTEM
TRANSMISI & DISTRIBUSI - PGT
NO. SPHR00129A
REVISI: 0
PT. PERTAMINA HULU ROKAN

Check and electrical test for Transformer HALAMAN: 3 of 10

PT. Radiant Utama Interinsco

REVISION
PAGE
0 1 2 3 4 5 6 7
1 X
2 X
3 X
4 X
5 X
6 X
7 X
8 X
TANGGAL: 09 Agustus 2022
JASA-JASA PENYEDIAAN DAN
PERAWATAN TERINTEGRASI - SISTEM
TRANSMISI & DISTRIBUSI - PGT
NO. SPHR00129A
REVISI: 0
PT. PERTAMINA HULU ROKAN

Check and electrical test for Transformer HALAMAN: 4 of 10

PT. Radiant Utama Interinsco

DAFTAR ISI

1. TUJUAN..................................................................................................................5
2. SUMBER DAYA MANUSIA DAN ALAT PENDUKUNG........................................5
3. RUANG LINGKUP PEKERJAAN...........................................................................6
4. DATA DAN RINGKASAN PEKERJAAN................................................................6
5. KESIMPULAN.........................................................................................................8
6. SARAN....................................................................................................................8
7. PHOTO DATA PEKERJAAN..................................................................................8
8. LAMPIRAN...............................................................................................................8
TANGGAL: 09 Agustus 2022
JASA-JASA PENYEDIAAN DAN
PERAWATAN TERINTEGRASI - SISTEM
TRANSMISI & DISTRIBUSI - PGT
NO. SPHR00129A
REVISI: 0
PT. PERTAMINA HULU ROKAN

Check and electrical test for Transformer HALAMAN: 5 of 10

PT. Radiant Utama Interinsco

1. TUJUAN
 Pengujian electrical test TX dengan pengujian insulation, TTR dan ODS at shop PGT Maintenance North

2. SUMBER DAYA MANUSIA DAN ALAT PENDUKUNG

2.1. Personil
No Name Position Remark
1 Senior Technician PMCow

2 Junior Technician

3 Junior Technician

2.2. Peralatan kerja


No. Description Brand Specification/Type
1 Standard Electrical tools Box Various Brand Hand tool complete
2 Clamp ampere meter Fluke Fluke 376
3 Oil Dielectric strength Megger ODS OTS60SX
4 Infra-Red Thermometer Krisbow KWD
5 Multifunction Substatiion Test ISA STS 5000
6 Insulation Tester Megger KEW 3125A

2.3. Peralatan dan perlengkapan keselamatan kerja

No. Description Brand Specification/Type Remark


Flame Retardant, anti-
1 Coveralls Long-sleeve Flemings static and with reflective Personal
strive
Safety Shoes or safety SNI or ASTM F 2413-
2 Krusher Personal
boots 2005
Safety Helmets complete ANSI Z89.1-2003 type 1
3 MSA Personal
with chain strap. Class E & G
Safety Glasses complete
4 MSA ANSI Z87.1-2003 Personal
with side shield
5 Rubber Hand Glove Safety Work
6 Cotton Hand Glove Safety Work
7 Respirator (Masker) 3M P-100 Safety Work
TANGGAL: 09 Agustus 2022
JASA-JASA PENYEDIAAN DAN
PERAWATAN TERINTEGRASI - SISTEM
TRANSMISI & DISTRIBUSI - PGT
NO. SPHR00129A
REVISI: 0
PT. PERTAMINA HULU ROKAN

Check and electrical test for Transformer HALAMAN: 6 of 10

PT. Radiant Utama Interinsco

3. RUANG LINGKUP PEKERJAAN


- Melakukan pengujian electrical pada transformer meliputi Insulation, TTR, dan ODS

4. DATA DAN RINGKASAN PEKERJAAN


a. Inspeksi dan pembersihan part transformer
 Melakukan visual inspeksi pada semua terminal,bushing.
Data Name plate Transformer
DATA SPECIFICATION REMARK
Brand
Serial No
Phase
Frequency
Voltage HV /LV
Current HV / LV
Power Capacity
Winding Vector
Insulation Class

b. Pengujian tahanan Insulation Transformer


Data Pengujian Tahanan Insulation Transformer

Measuring Position Result test

Test Point
1 Menit 10 Menit PI
HV – LV
HV – Ground
LV - Ground
Kriteria Kelulusan:
- Mengacu pada Contract No: 39PHR20-0085 Lampiran A Pasal 1.5 Table 1 , Nilai Tahanan Isolasi dengan
tegangan aplikasi 115kV dan IR DC Test 5000 VDC minimum tahanan isolasi adalah 5 GΩ dan IR DC Test
500 VDC minimum tahanan isolasi adalah >25 MΩ

Summary:
TANGGAL: 09 Agustus 2022
JASA-JASA PENYEDIAAN DAN
PERAWATAN TERINTEGRASI - SISTEM
TRANSMISI & DISTRIBUSI - PGT
NO. SPHR00129A
REVISI: 0
PT. PERTAMINA HULU ROKAN

Check and electrical test for Transformer HALAMAN: 7 of 10

PT. Radiant Utama Interinsco

c. Pengujian Transformer Turn Ratio (TTR)


Data Pengujian Transformer Turn Ratio (TTR)
Tanggal Pengujian :
Temperature Ruang : ˚C
Cuaca : Cerah
Impedance Trafo
Transformer Turn Ratio
H3 – H1 Error H1– H2 Error H2 – H3 Error
TAP HV Side LV Side Calculated
X0 – X1 % X0 – X2 % X0 – X3 %
1
2
3
4
5
Kriteria Kelulusan:
- Standard IEEE C57.125.1991 menyatakan batasan toleransi kesalahan factor ratio dari transformer
adalah 0.5%
- ANSI/NETA ATS-2017 Menyatakan: “Turns-ratio test results shall not deviate by more than one-half
percent from either the adjacent coils or the calculated ratio”
Summary:

d. Pengujian insulasi minyak transformer (ODS).


 Melakukan pengambilan sample transformer
 Melakukan pengukuran temperature minyak sample yang akan di uji
 Melakukan pengukuran gap electrode pada 2 mm
 Melakukan pengujian insulasi pada sample minyak transformer

Pengujian tegangan tembus dilakukan untuk mengetahui kemampuan minyak isolasi dalam menahan
stress tegangan
Data Tools ODS Tester
Merek Alat Test Megger
Type OTS60SX/2
Metoda Pengujian ASTM D-1816 (Gap 2 mm)

- Pengujian Oil Dielectric Strength Transformer


Data Pengujian ODS Transformer
Temperature Minyak = °C
Temperature Ruang = °C
Electrode Gap = 2 mm
No of Test Result Remark
1
2
3
4
5
Total
Average
TANGGAL: 09 Agustus 2022
JASA-JASA PENYEDIAAN DAN
PERAWATAN TERINTEGRASI - SISTEM
TRANSMISI & DISTRIBUSI - PGT
NO. SPHR00129A
REVISI: 0
PT. PERTAMINA HULU ROKAN

Check and electrical test for Transformer HALAMAN: 8 of 10

PT. Radiant Utama Interinsco

Kriteria Kelulusan:
- Mengacu pada contract document no. 39PHR20-0085 Hal.149(Metoda Uji ASTM D1816 dengan Gap
2mm adalah minimal 40 kV)
Summary:

e. Pengujian power Factor (tan dengan metoda UST-R


Data pengujian power factor (tan δ) pada bushing
Pengujian Power Factor Bushing

Loss pada 10KV


Test Position Power Factor (%) Criteria Test
(Watt)

Bushing #1
Bushing #2
Bushing #3
Kriteria Kelulusan:
- Standard nilai lulus pengujian power Factor bushing adalah maksimum 0.1 Watt.
Summary:

5. KESIMPULAN
Berdasarkan hasil pengetesan yang telah dilakukan dapat disimpulkan bahwa trafo dalam kondisi tidak
memenuhi standard pengujian.

6. SARAN
Lakukan service pada trafo dan penggantian minyak trafo.

7. PHOTO DATA PEKERJAAN


Inspect Transformer

Transformer Nama plate


TANGGAL: 09 Agustus 2022
JASA-JASA PENYEDIAAN DAN
PERAWATAN TERINTEGRASI - SISTEM
TRANSMISI & DISTRIBUSI - PGT
NO. SPHR00129A
REVISI: 0
PT. PERTAMINA HULU ROKAN

Check and electrical test for Transformer HALAMAN: 9 of 10

PT. Radiant Utama Interinsco

Pengujian tahanan isolasi trafo

HV-LV (PI) HV-GND (PI) LV-GND (PI)

Hasil Power Factor metode UST-R

Bushing #1 Bushing #2 Bushing #3

Hasil pengujian ODS

Test 1 Test 2

Posisi H3-H1, X0-X1

TAP 1 TAP 2 TAP 3 TAP 4 TAP 5


TANGGAL: 09 Agustus 2022
JASA-JASA PENYEDIAAN DAN
PERAWATAN TERINTEGRASI - SISTEM
TRANSMISI & DISTRIBUSI - PGT
NO. SPHR00129A
REVISI: 0
PT. PERTAMINA HULU ROKAN

Check and electrical test for Transformer HALAMAN: 10 of 10

PT. Radiant Utama Interinsco

POSISI H1-H2, X0-X2

TAP 1 TAP 2 TAP 3 TAP 4 TAP 5

POSISI H2-H3, X0-X3

TAP 1 TAP 2 TAP 3 TAP 4 TAP 5

8. LAMPIRAN
 Data hasil pengukuran di lapangan
 Berita AcaraPekerjaan