Tanggal :
: 0
5-Sep-18
DEPT. HEAD
NAMA PROYEK : Retrofit Sistem Fire Protection GT 2.1 RENCANA AKTUAL PM HPMO MEIS PROJECT FSSE COST CONTROL FAT O&S HOB PRES. DIREKTUR
24 September s/d
DIRECT CUSTOMER : PT. Indobara Bahana 10 Desember 2018
100 Material 133,314,100 123,982,113 NILAI KONTRAK (D) SELISIH ANGGARAN (E) LABA KOTOR (G) LABA BERSIH (F)
(Exclude PPN)
300 Subcontractor 11,100,000 10,578,000 Kurs USD : (C) : 230,419,881 ( A ) : 212,390,363 ( C ) : 230,419,881
400 Temporary Facilities 26,199,000 24,462,250 IDR : 247,000,000 13,253,874 34,609,637 16,580,119
500 Site Expense 16,050,000 15,785,000 (E) / (B) : 5.44% (G) / (D) : 14.01% (F) / (D) : 6.71%
DIRECT 225,013,100 212,390,363
(B) (C)
F.ENG.042.02
06/20/2023
PROJECT NO. : 18NPR0140
BUDGET CONTROL TABLE (#100 ) MATERIAL & EQUIPMENT
KODE KOMPONEN ANGGARAN ANGGARAN PERUSAHAAN (1) RENCANA ANGGARAN PROYEK
QTY Unit
Vendor Harga Pokok Amount (IDR) Sub-Total (IDR) Harga Pokok Amount (IDR) Sub-Total (IDR)
101 - 00 INTERIOR MATERIAL 0 ###0
- 01 CEILLING MATERIAL 0 0
- 02 WALL MATERIAL 0 0
- 03 FLOOR MATERIAL 0 0
- 04 FURNITURE EQUIPMENT 0 0
- 04 KITCHEN 0 0
0
102 - 00 CIVIL WORK MATERIAL 0 0 ###0
- 01 FILLING WORK MATERIAL 0 0
- 02 FOUNDATION 0 0
- 03 FLOOR 0 0
- 04 COLOUM 0 0
- 05 BEAM & COLOUM 0 0
- 06 ROOF 0 0
- 08 PAINTING 0 0
- 07 SUPPORT 0 0
0 0
103 - 00 MECHANICAL & ELECTRICAL WORKS MATERIAL 0 Rp 133,314,100 0 Rp 123,982,113
###
01 0 Mechanical Equipment 0 0
1 PIPE SCH 80 SMLS ASTM A106 GR.B/A53 GR.B Dia. 2 In Ex Lokal 4 Btg Rp 700,000 Rp 2,800,000 686,000 Rp 2,604,000
2 PIPE SCH 40 SMLS ASTM A106 GR.B/A53 GR.B Dia. 2 In Ex Lokal 2 Btg Rp 550,000 Rp 1,100,000 539,000 Rp 1,023,000
3 PIPE SCH 40 SMLS ASTM A106 GR.B/A53 GR.B Dia. 1 In Ex Lokal 2 Btg Rp 260,000 Rp 520,000 254,800 Rp 483,600
4 PIPE SCH 40 SMLS ASTM A106 GR.B/A53 GR.B Dia. 1/2 In Ex Lokal 1 Btg Rp 170,000 Rp 170,000 166,600 Rp 158,100
5 Pipa Conduit Steel Galvanis Ex Lokal 100 Btg Rp 60,000 Rp 6,000,000 58,800 Rp 5,580,000
6 BESI KANAL UNP 100 x 50 x T. 4,7 mm, PANJANG 6 METER Ex. LOKAL 3 Btg Rp 340,000 Rp 1,020,000 333,200 Rp 948,600
7 BESI KANAL UNP 50 x 38 x T. 2,3 mm, PANJANG 6 METER Ex. LOKAL 4 Btg Rp 200,000 Rp 800,000 196,000 Rp 744,000
8 BESI SIKU 80 x 80 x T 6mm, PANJANG 6 METER Ex. LOKAL 13 Btg Rp 380,000 Rp 4,940,000 372,400 Rp 4,594,200
9 Plat Strip Galvanis 5 cm x 5 m X 6 m 5 Lbr Rp 128,000 Rp 640,000 125,440 Rp 595,200
10 Plat Baja Besi T 3 mm x L 1.2 m x P 2.4 m , Ex. LOKAL 4 Lbr Rp 450,000 Rp 1,800,000 441,000 Rp 1,674,000
11 ELBOW 90 LR ASTM/A105N CLASS 3000 NPT Dia. 2 In Ex Lokal 14 Ea Rp 250,000 Rp 3,500,000 245,000 Rp 3,255,000
12 ELBOW 90 LR ASTM/A105N CLASS 3000 NPT Dia. 1 In Ex Lokal 6 Ea Rp 83,200 Rp 499,200 81,536 Rp 464,256
13 TEE EQUAL ASTM/A105N CLASS 3000 NPT Dia. 2 In Ex Lokal 3 Ea Rp 215,000 Rp 645,000 210,700 Rp 599,850
14 TEE RED ASTM/A105N CLASS 3000 NPT Dia. 2 x 1/2 In Ex lokal 2 Ea Rp 507,000 Rp 1,014,000 496,860 Rp 943,020
15 TEE RED ASTM/A105N CLASS 3000 NPT Dia. 1 x 1/2 In Ex lokal 2 Ea Rp 200,000 Rp 400,000 196,000 Rp 372,000
16 TEE RED ASTM/A105N CLASS 3000 NPT Dia. 2x1 In Ex lokal 2 Ea Rp 550,000 Rp 1,100,000 539,000 Rp 1,023,000
17 END CAP ASTM/A105N CLASS 3000 NPT Dia. 2 In Ex Lokal 4 Ea Rp 50,000 Rp 200,000 49,000 Rp 186,000
18 COUPLING THREADED ASTM/A105N CLASS 3000 NPT Dia. 2 In Ex Lok 6 Ea Rp 90,000 Rp 540,000 88,200 Rp 502,200
19 COUPLING THREADED ASTM/A105N CLASS 3000 NPT Dia. 1 In Ex Lok 4 Ea Rp 75,000 Rp 300,000 73,500 Rp 279,000
20 THREADOUTLET ASTM/A105N CLASS 3000 NPT Dia. 1/2 In Ex Lokal 21 Ea Rp 60,000 Rp 1,260,000 58,800 Rp 1,171,800
21 BUSHING / VLOG RING ASTM/A105N CLASS 3000 NPT Dia. 1/2 x 3/8 In 4 Ea Rp 250,000 Rp 1,000,000 245,000 Rp 930,000
22 Hexagonal Bolt Full Drat Grade Class 8.8 Galvanis M12x 1,75 132 Ea Rp 3,000 Rp 396,000 2,940 Rp 368,280
23 Hexagonal Nut (Mur Heksagonal) M17 x 1 Grade Class 8.8 Galv 40 Ea Rp 3,500 Rp 140,000 3,430 Rp 130,200
24 Hexagonal Nut (Mur Heksagonal) M12x 1.75 Thread Grade Clas142 Ea Rp 2,000 Rp 284,000 1,960 Rp 264,120
25 U Bolt (Baut-U) Galvanis 3/8 x 2 Inch 32 Ea Rp 7,000 Rp 224,000 6,860 Rp 208,320
26 U Bolt (Baut-U) Galvanis 3/8 x 1 Inch 32 Ea Rp 5,000 Rp 160,000 4,900 Rp 148,800
27 DINABOLT GALVANIS Hole Drill / M 10 x P. 60 mm 79 Ea Rp 2,500 Rp 197,500 2,450 Rp 183,675
28 Washer Plate (Ring Plat) Galvanis M12 415 Ea Rp 1,000 Rp 415,000 980 Rp 385,950
Page 2
06/20/2023
BUDGET CONTROL TABLE (#100 ) MATERIAL & EQUIPMENT
KODE KOMPONEN ANGGARAN ANGGARAN PERUSAHAAN (1) RENCANA ANGGARAN PROYEK
QTY Unit
Vendor Harga Pokok Amount (IDR) Sub-Total (IDR) Harga Pokok Amount (IDR) Sub-Total (IDR)
29 Washer Plate (Ring Plat) Galvanis M6 630 Ea Rp 500 Rp 315,000 490 Rp 292,950
30 Washer Plate (Ring Plat) Galvanis M17 182 Ea Rp 1,200 Rp 218,400 1,176 Rp 203,112
31 SCREW AND FISHER S6 600 Ea Rp 1,000 Rp 600,000 980 Rp 558,000
32 OMEGA CLAMP GALVANIS 20 mm 400 Ea Rp 2,000 Rp 800,000 1,960 Rp 744,000
33 COUPLINGPIPE THREADED 20 mm GALVANIS Ex. Lokal 100 Ea Rp 27,000 Rp 2,700,000 26,460 Rp 2,511,000
34 COUPLINGPIPE THREADED 20 mm GALVANIS Ex. Lokal(Panel to 30 Ea Rp 27,000 Rp 810,000 26,460 Rp 753,300
35 COUPLING/SHOCK PIPE THREADLESS 20 mm GALVANIS Ex. Loka 228 Ea Rp 7,000 Rp 1,596,000 6,860 Rp 1,484,280
36 Baut Roofing Screw 12 x 50 166 Ea Rp 1,500 Rp 249,000 1,470 Rp 231,570
37 Long nut M17 Galvanis 40 Ea Rp 15,000 Rp 600,000 14,700 Rp 558,000
38 Long Drat 17 mm Galvanis 10 Ea Rp 30,000 Rp 300,000 29,400 Rp 279,000
39 Spring per beban 100 kg 18 Ea Rp 50,000 Rp 900,000 49,000 Rp 837,000
40 Tee Dus 3 Way E19/20mm 6 Ea Rp 39,000 Rp 234,000 38,220 Rp 217,620
41 Tee Dus 2 Way E19/20mm 10 Ea Rp 35,000 Rp 350,000 34,300 Rp 325,500
42 Unistrut Chanel 4 x 4 cm stainlees steel 1 Btg Rp 185,000 Rp 185,000 181,300 Rp 172,050
43 Semen 2 Kg Rp 68,000 Rp 136,000 66,640 Rp 126,480
44 Compound plafon(For Gedung CCR) 1 Kg Rp 65,000 Rp 65,000 63,700 Rp 60,450
45 sikat Kawat 2 Ea Rp 25,000 Rp 50,000 24,500 Rp 46,500
46 Cat GARDEX PRIMER, Jotun, White 2 Liter Rp 55,000 Rp 110,000 53,900 Rp 102,300
47 Cat JOTUN RED RAL 3000 2 Liter Rp 200,000 Rp 400,000 196,000 Rp 372,000
48 Thinner Gardex, Jotun 2 Liter Rp 30,000 Rp 60,000 29,400 Rp 55,800
49 Kuas rol 1 Ea Rp 30,000 Rp 30,000 29,400 Rp 27,900
50 Tongkat kuas rol 1 Ea Rp 25,000 Rp 25,000 24,500 Rp 23,250
51 Kuas 2" 2 Ea Rp 8,000 Rp 16,000 7,840 Rp 14,880
52 Kuas 1" 2 Ea Rp 3,000 Rp 6,000 2,940 Rp 5,580
02 0 Electrical Equipment
1 Juction Box 1 1 Unit Rp 2,000,000 Rp 2,000,000 1,960,000 Rp 1,860,000
2 Juction Box 2 1 Unit Rp 2,000,000 Rp 2,000,000 1,960,000 Rp 1,860,000
3 CABLE 16 AWG 1030A 1 PAIR Merk : BELDEN 3 Roll Rp 3,800,000 Rp 11,400,000 3,724,000 Rp 10,602,000
4 Kabel FRC 2 x 1.5 (KMI) @100 MTR 32 Roll Rp 1,400,000 Rp 44,800,000 1,372,000 Rp 41,664,000
5 Kabel FRC 2 x 2.5(KMI) @100 MTR 6 Roll Rp 2,800,000 Rp 16,800,000 2,744,000 Rp 15,624,000
6 Kabel FRC 2 x 2 x 2.5 (KMI) @100 MTR 2 Roll Rp 3,200,000 Rp 6,400,000 3,136,000 Rp 5,952,000
7 TRUNKING CABLE DUCT METAL PLUS COVER 40x 40 mm 10 Btg Rp 350,000 Rp 3,500,000 343,000 Rp 3,255,000
8 ELBOW KABEL DUCT METAL PLUS COVER 40x 40 mm 3 Ea Rp 161,000 Rp 483,000 157,780 Rp 449,190
9 Outside Vertical ELBOW KABEL DUCT METAL PLUS COVER 40x 40 m 3 Ea Rp 170,000 Rp 510,000 166,600 Rp 474,300
10 Inside Vertical ELBOW KABEL DUCT METAL PLUS COVER 40x 40 mm 3 Ea Rp 170,000 Rp 510,000 166,600 Rp 474,300
11 Cable Scun Y 1.5 mm Hitam @100 4 Ea Rp 20,000 Rp 80,000 19,600 Rp 74,400
12 Cable Scun Y 1.5 mm Hitam @100 4 Ea Rp 20,000 Rp 80,000 19,600 Rp 74,400
13 Cable ties 200mm @100 Pcs 2 Ea Rp 25,000 Rp 50,000 24,500 Rp 46,500
14 TERMINAL BLOCK 24v 12pole, local 2 Ea Rp 15,000 Rp 30,000 14,700 Rp 27,900
15 REL MCB 2 Ea Rp 20,000 Rp 40,000 19,600 Rp 37,200
16 FLEXIBLE STEEL CONDUIT 20MM (ROLL) 3 Ea Rp 300,000 Rp 900,000 294,000 Rp 837,000
17 Sealtape onda putih @ dus 60 Roll 1 Ea Rp 225,000 Rp 225,000 220,500 Rp 209,250
18 MCB 2 POLE 6A, Schneider 2 Ea Rp 150,000 Rp 300,000 147,000 Rp 279,000
19 Kabel Marker, 0,75- 3,5 mm 1 Ea Rp 50,000 Rp 50,000 49,000 Rp 46,500
Page 3
06/20/2023
BUDGET CONTROL TABLE (#100 ) MATERIAL & EQUIPMENT
KODE KOMPONEN ANGGARAN ANGGARAN PERUSAHAAN (1) RENCANA ANGGARAN PROYEK
QTY Unit
Vendor Harga Pokok Amount (IDR) Sub-Total (IDR) Harga Pokok Amount (IDR) Sub-Total (IDR)
20 Isolasi Kertas Lebar 3 Roll Rp 12,000 Rp 36,000 11,760 Rp 33,480
21 Isolasi Listrik Hitam ( Roll ) 30 Roll Rp 10,000 Rp 300,000 9,800 Rp 279,000
22
0 0 0
Page 4
06/20/2023
203 - 00 WAGES/SALARY 0 0
00 01 SITE STAFF CONTRACT PROJECT 0 0
00 02 DAILY WORKER 0 0
00 03 SECURITY 0 0
204 - 00 COMMISSIONING 0 0
00 01 MAINTENANCE & INSPECTION Team Testcomm
00 02 TESTING & COMMISSIONING 0 0
00 03
Page 5
PROJECT NO. : 18NPR0140 06/20/2023
BUDGET CONTROL TABLE (#300) SUB CONTRACT SUPPLY
Page 6
06/20/2023
Page 7 400
06/20/2023
Page 8 400
06/20/2023
402 SUB-TOTAL 0 0
403 CONSUMABLE
403 01 A. CONSUMABLE MEKANIKAL Rp 1,000,000 950,000 Month
404 TRANSPORTATION
404 01 A. TRANSPORTATION Rp 3,000,000 2,940,000 ###
a. Material Mobilization Insite Project from Jakarta to Site Trip 2 Rp 1,500,000 Rp 3,000,000 Trip 2 1,470,000 2,940,000 lot
Page 9 400
PROJECT NO. : 18NPR0140
ANGGARAN PERUSAHAAN (1) RENCANA ANGGARAN PROYEK 06/20/2023
CODE JUMLAH JUMLAH JUMLAH JUMLAH
KOMPONEN ANGGARAN UNIT
SATUAN
HARGA / UNIT
HARGA
SUB-TOTAL TOTAL UNIT
SATUAN
HARGA / UNIT
HARGA
SUB-TOTAL TOTAL
CD1+2 CD3 CD4
500 SITE EXPENSES
501 SALARY
501 01 A. SALARY STAFF PROJECT BASE 8,500,000 8,300,000 Months
a. Project Manager Day 5 300,000 1,500,000 Day 5 300,000 1,500,000 Months
b. Site Manager month 1 6,000,000 6,000,000 month 1 6,000,000 6,000,000 Months
c. Tescom Day 4 250,000 1,000,000 Day 4 200,000 800,000 Months
d. Supervisor Month 1 0 0 Month 1 0 0
Daily Worker (Temporary) Months 0 0 Months 0 0 Months
a. Warehouse man Months 0 0 Months 0 0 0 Months
b. Cleaning Service Months 0 0 Months 0 0 0 Months
c. Security Months 0 0 Months 0 0 0 Months
502 STATIONERY
502 01 A. STATIONERY 1,000,000 950,000 ###
a. Stationery & Miscellaneous Lot 1 1,000,000 1,000,000 Lot 1 950,000 950,000 Month
Paper A3 & A4 size, Ball Point , Ink Printer Rim 2 0 0 Rim 2 0 0
B. COMPUTER
a. Laptop Lot 0 0 0 Lot 0 0 0 Nos
b. Software MS Office Nos 0 0 0 Nos 0 0 0 Nos
c. Camera Lot 0 0 0 Lot 0 0 0 Nos
C. PRINTER
a. Printer A3 Lot 0 Lot 0 No
b. Refill Times 0 Times 0 No
c. Modem Month 0 0 Month 0 0 0 Month
503 SUB-TOTAL 0 0
504 ENTERTAINMENT
504 01 A. ENTERTAINMENT CLIENT Month 0 0 0 0 Month 0 0 0 0 Month
Page 10 500
PROJECT NO. : 18NPR0140
ANGGARAN PERUSAHAAN (1) RENCANA ANGGARAN PROYEK 06/20/2023
CODE JUMLAH JUMLAH JUMLAH JUMLAH
KOMPONEN ANGGARAN UNIT
SATUAN
HARGA / UNIT
HARGA
SUB-TOTAL TOTAL UNIT
SATUAN
HARGA / UNIT
HARGA
SUB-TOTAL TOTAL
CD1+2 CD3 CD4
504 SUB-TOTAL 0 0
Page 11 500
PROJECT NO. : 18NPR0140
ANGGARAN PERUSAHAAN (1) RENCANA ANGGARAN PROYEK 06/20/2023
CODE JUMLAH JUMLAH JUMLAH JUMLAH
KOMPONEN ANGGARAN UNIT
SATUAN
HARGA / UNIT
HARGA
SUB-TOTAL TOTAL UNIT
SATUAN
HARGA / UNIT
HARGA
SUB-TOTAL TOTAL
CD1+2 CD3 CD4
c. Visa
C Transport of baggages
506 WELFARE
506 01 A. Site Office 150,000 142,500 ###
a. water , coffee,etc Month 0 0 0 Month 0 0 0 Month
b. Dispenser+Setrikaan No 0 0 0 No 0 0 0 No
c. Laundry Month 1 150,000 150,000 Month 1 142,500 142,500 No
d. Meals Allowance for 3 person Month 0 0 0 Month 0 0 0 Month
507 SUB-TOTAL 0 0
Page 13 500