NO. URAIAN JENIS BAHAN SATUAN SATUAN
( RP.)
1 2 3 4
I. BAHAN PENUTUP ATAP & PLAFON
1 Asbes Bubungan Gelombang Besar t. 5 mm 2/m' 68.000
2 Asbes Bubungan Gelombang Kecil t. 4 mm 2/m' 31.900
3 Asbes gelombang besar t. 6 mm ( 3.00 x 1.08 ) Lbr 128.300
4 Asbes gelombang kecil t. 4 mm ( 3.00 x 1.05 ) Lbr 72.400
5 Asbes plat 1/1 m Ex Gresik (Harpleks) m2 16.100
6 Asbes plat 1/1 m Cap Kerang (ETERNIT) m2 13.300
7 Genteng bubungan Bambe (5 bj/m') bj 19.700
8 Genteng bubungan Karangpilang model layur (5 bj/m') bj 5.600
9 Genteng bubungan lokal m' 4.500
10 Genteng bubungan model Abadi (4 bj/m') bj 17.200
11 Genteng Bubungan Beton bj 7.500
12 Genteng model Karangpilang ex. nglayur bh 2.100
13 Genteng model Abadi morando bh 7.000
14 Genteng model Abadi morando ALTO bh 4.700
15 Genteng model kr.pilang ex. Bambe bh 4.800
16 Genteng pres Kluntung bh 1.800
17 Genteng vlam pres lokal bh 1.300
18 Genteng Beton bh 6.400
19 Kalsi BOARD 122 x 244 cm GRC 4mm Lbr 52.400
20 Seng Gelombang BJLS 030 x 180 polos Lbr 68.400
21 Seng Gelombang BJLS 030 x 55 Lbr 50.000
22 Seng Gelombang BJLS 030 x 90 Lbr 56.000
23 Seng Gelombang BJLS 30, 80 x 180 cm Lbr 75.200
24 Seng Gelombang BJLS 30, 80 x 300 cm Lbr 120.200
25 Seng plat datar BJLS. 020 x 55 cm m' 20.000
26 Seng plat datar BJLS. 020 x 60 cm m' 22.600
27 Seng plat datar BJLS. 020 x 75 cm m' 27.200
28 Seng plat datar BJLS. 028 x 90 cm m' 37.600
29 Seng plat datar BJLS. 028 x 55 cm m' 27.700
30 Seng plat datar BJLS. 030 x 45 cm m' 23.700
31 Seng plat datar BJLS. 030 x 55 cm m' 31.300
32 Teakwood 122 x 244 x 4 mm Lbr 85.000
33 Teakwood 95 x 205 x 4 mm Lbr 86.700
34 Teakwood Lapis Aluminium 95 x 205 x 4 mm Lbr 111.100
35 Triplek 090 x 210 cm x 3 mm Lbr 50.500
36 Triplek 122 x 244 cm x 4 mm Lbr 62.900
37 Triplek 122 x 244 cm x 3 mm Lbr 50.100
38 Triplek 122 x 244 x 9 mm Lbr 105.100
39 Multiplex 9 mm Lbr 127.700
40 Formika Mellamin Putih 1,20 x 2,40 M ( t: 1 mm) Lbr 102.500
41 Lem Kayu Kg 17.600
42 Gypboard 1,2 x 2,4 x 9 mm Lbr 52.200
43 Ramset buah 7.900
44 Genteng Kaca Bh 13.900
45 Atap Bitumen Bergelombang Monolayer 200x95x0,35cm Lbr 168.000
46 Genteng Bitumen Bergelombang Monolayer (Merah, Coklat, Hitam,Hijau) 106x40x0,30cm Lbr 54.400
HARGA
NO. URAIAN JENIS BAHAN SATUAN SATUAN
( RP.)
1 2 3 4
47 Genteng Bitumen Bergelombang Monolayer 200x97x0,3cm Lbr 165.000
48 Nok Standard (Merah, Coklat, Hitam,Hijau) 100x50 cm Lbr 85.000
HARGA
No. Peralatan Kode Satuan SATUAN
(Rp.)
1 ASPHALT MIXING PLANT E01 Jam 3.673.750,00
2 ASPHALT FINISHER E02 Jam 262.800,00
3 POWER BROOM / ASPHALT SPRAYER E03 Jam 56.450,00
4 BULLDOZER 100-150 HP E04 Jam 612.350,00
5 COMPRESSOR 4000-6500 L\M E05 Jam 105.000,00
6 CONCRETE MIXER 0.3-0.6 M3 E06 Jam 71.750,00
7 CRANE 10-15 TON E07 Jam 503.200,00
8 DUMP TRUCK 3 - 4 M3 E08 Jam 198.350,00
9 DUMP TRUCK 6-8 M3 E09 Jam 282.850,00
10 EXCAVATOR 80-140 HP E10 Jam 356.600,00
11 MINI EXCAVATOR 40-60 HP E10a Jam 214.600,00
12 FLAT BED TRUCK 3-4 TON E11 Jam 254.700,00
13 GENERATOR SET E12 Jam 259.400,00
14 MOTOR GRADER >100 HP E13 Jam 366.300,00
15 TRACK LOADER 75-100 HP E14 Jam 288.550,00
16 WHEEL LOADER 1.0-1.6 M3 E15 Jam 362.950,00
17 THREE WHEEL ROLLER 6-8 T E16 Jam 206.100,00
18 TANDEM ROLLER 6-8 T. E17 Jam 392.400,00
19 TANDEM ROLLER 8-10 T. E17a Jam 395.550,00
20 TIRE ROLLER 8-10 T. E18 Jam 398.900,00
21 VIBRATORY ROLLER 5-8 T. E19 Jam 226.000,00
22 BABY VIBRATORY ROLLER 1-2 T. E19a Jam 72.900,00
23 CONCRETE VIBRATOR E20 Jam 42.850,00
24 STONE CRUSHER E21 Jam 861.150,00
25 WATER PUMP 70-100 mm E22 Jam 38.850,00
26 WATER TANKER 3000-4500 L. E23 Jam 225.000,00
27 PEDESTRIAN ROLLER E24 Jam 192.300,00
28 TAMPER E25 Jam 73.600,00
29 JACK HAMMER E26 Jam 38.300,00
30 FULVI MIXER E27 Jam 840.100,00
31 CONCRETE PUMP E28 Jam 873.000,00
32 TRAILER 20 TON E29 Jam 347.450,00
33 PILE DRIVER + HAMMER E30 Jam 123.950,00
34 CRANE ON TRACK 35 TON E31 Jam 1.063.100,00
35 WELDING SET E32 Jam 44.450,00
36 BORE PILE MACHINE E33 Jam 530.900,00
37 ASPHALT LIQUID MIXER E34 Jam 64.450,00
38 ASPHALT LIQUID MIXER E34a Jam 102.250,00
39 TRONTON 15 TON E35 Jam 394.700,00
40 Trailer Tronton 30 T; 200 HP E35a Jam 386.850,00
41 COLD MILLING E36 Jam 650.000,00
42 ROCK DRILL BREAKER E37 Jam 392.250,00
43 COLD RECYCLER E38 Jam 2.254.650,00
44 HOT RECYCLER E39 Jam 3.139.750,00
45 AGGREGAT (CHIP) SPREADER E40 Jam 356.200,00
46 ASPHALT DISTRIBUTOR E41 Jam 316.000,00
47 SLIP FORM PAVER E42 Jam 2.314.150,00
48 CONCRETE PAN MIXER E43 Jam 80.300,00
49 CONCRETE BREAKER E44 Jam 518.750,00
50 ASPAHLT TANKER E45 Jam 351.850,00
51 CEMENT TANKER E46 Jam 311.050,00
52 CONDRETE MIXER (350) E47 Jam 63.000,00
53 VIBRATING RAMMER E48 Jam 39.300,00
54 TRUK MIXER (AGITATOR) E49 Jam 504.400,00
55 BORE PILE MACHINE E50 Jam 402.050,00
56 CRANE ON TRACK 75-100 TON E51 Jam 1.993.250,00
57 BLENDING EQUIPMENT E52 Jam 184.900,00
58 BAR BENDER E53 Jam 51.950,00
59 BAR CUTTER E54 Jam 51.950,00
60 BREAKER E55 Jam 487.700,00
61 GROUTING PUMP E56 Jam 142.650,00
62 JACK HIDROLIC E57 Jam 43.500,00
63 MESIN LAS E58 Jam 34.600,00
64 PILE DRIVER LEADER, 75 kw E59 Jam 126.500,00
65 PILE HAMMER E60 Jam 43.750,00
66 PILE HAMMER, 2,5 Ton E61 Jam 48.350,00
67 STRESSING JACK E62 Jam 182.050,00
68 WELDING MACHINE, 300 A E63 Jam 37.250,00
69 WATER JET BLASTING E64 Jam 44.500,00
70 MESIN POTONG RUMPUT E65 Jam 3.650.000,00
71 Ponton + Tug Boat; 40 Ton; 80 HP E66 Jam 370.350,00
72 Silicon Seal pump E67 Jam 134.050,00
73 Pompa (+Mixer) pengisi bahan perekat epoxy, 600 Watt E68 Jam 35.400,00
74 Gerinda tangan GWS 750-100 4"; 1 HP E69 Jam 37.000,00
75 Hand Mixer E70 Jam 100.000,00
76 Mesin Bor E71 Jam 100.000,00
77 Mesin Amplas kayu E73 Jam 20.000,00
78 KUNCI TORSI 200-1000N.M E74 Jam 38.350,00
79 POMPA + MIXER EPOXY, 810 Watt E75 Jam 34.250,00
80 CONCRETE CUTTER 130 feet/mnt E76 Jam 43.950,00
81 SAND BLASTING E77 Jam 34.500,00
82 MOBILE CRANE 1 TON E78 Jam 179.850,00
83 DRUM MIXER E79 Jam 337.100,00
84 STAMPER E81 Jam 46.000,00
85 JACK HIDROLIK JEMBATAN E82 Jam 51.400,00
86 HYDROLIC PUMP E83 Jam 35.100,00
87 MANIFOLD E84 Jam 33.250,00
88 THERMOPLASTIC ROAD MARKING MACHINE E85 Jam 63.850,00
89 COLD PAINT SRAY MACHINE E86 Jam 50.050,00
B. HARGA SATUAN UPAH KERJA
1 2 3 4