REKAPITULASI ANGGARAN BIAYA ESTIMITE ENGGENEER ( EE )


PEKERJAAN : LANJUTAN PENEGEMBANGAN GEDUNG SAT - INTEL DAN SAT - RESKIM LT. II POLRES KOTA TASIKMALAYA
LOKASI : KOTA TASIKMALAYA

JUMLAH
NO. URAIAN HARGA
Rp.
1 2 3

LANJUTAN PENEGEMBANGAN GEDUNG SAT - INTEL DAN SAT - RESKIM LT. II POLRES KOTA TASIKMALAYA
A. PEK. PERSIAPAN 41.999.992,00
Sub jumlah 41.999.992,00
PEKERJAAN KONTRUKSI
B. PEKERJAAN LANTAI I
B.I. PEK. BONGKARAN -
B.II. PEK. TANAH DAN PONDASI -
B.III. PEK. BETON -
B.IV. PEK. DINDING DAN PASANGAN -
B.V. PEK. PLAFOND -
B.VI. PEK. LANTAI DAN DINDING KERAMIK -
B.VII. PEK. KUSEN,PINTU, JENDELA ALMUNIUM -
B.VIII. PEK. KUNCI DAN KACA -
B.IX. PEK. SANITASI -
B.X. PEK. INSTALASI LISTRIK -
B.XI. PEK. PENGECATAN -
B.XII. PEK. TANGGA -
B.XIII. PEK. SALURAN AIR HUJAN P= 33,13 m -
B.XIV. PEK. SALURAN AIR HUJAN P= 4,00 m -
Sub jumlah -
C. PEKERJAAN LANTAI II
C.I. PEK. BETON 399.271.900,66
C.II. PEK. DINDING DAN PASANGAN 293.329.425,96
C.III. PEK. KUDA - KUDA, ATAP DAN PLAFOND 498.602.298,71
C.IV. PEK. LANTAI DAN DINDING KERAMIK 229.426.861,79
C.V. PEK. KUSEN,PINTU, JENDELA ALMUNIUM 203.825.251,94
C.VI. PEK. KUNCI DAN KACA 78.182.077,96
C.VII. PEK. SANITASI 99.746.452,34
C.VIII. PEK. LISTRIK 34.596.550,00
C.IX. PEK. PENGECATAN 69.044.823,24
C.X. PEK. RAM 78.254.756,60
Sub jumlah 1.984.280.399,20
D. PEK. LAIN - LAIN 3.500.000,00
Sub jumlah 3.500.000,00

JUMLAH TOTAL 2.029.780.391,20


PPN 11% 223.275.843,03
JUMLAH + PPN 2.253.056.234,23
DIBULATKAN 2.253.056.000,00
TERBILANG :
DUA MILYAR DUA RATUS LIMA PULUH TIGA JUTA LIMA PULUH ENAM RIBU RUPIAH
Page 2
RENCANA ANGGARAN BIAYA ESTIMITE ENGGENEER ( EE )
PEKERJAAN : LANJUTAN PENEGEMBANGAN GEDUNG SAT - INTEL DAN SAT - RESKIM LT. II POLRES KOTA TASIKMALAYA
LOKASI : KOTA TASIKMALAYA

HARGA JUMLAH
KODE
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN HARGA SATUAN
ANALISIS
Rp. Rp.
1 2 3 4 5 6 7

A. PEK. PERSIAPAN
1 Pengukuran - 1,00 m' 750.000,00 750.000,00
2 Papan nama kegiatan - 1,00 ls 300.000,00 300.000,00
3 Pengadaan air kerja - 1,00 ls 2.500.000,00 2.500.000,00
4 Sistem Manajemen Keselamaan Kntruksi K.3 1,00 ls 20.025.000,00 20.025.000,00
5 Pembuatan direksikeet /pengadaan 1.1.e (c) 12,00 ls 1.535.416,00 18.424.992,00
Sub jumlah 41.999.992,00

C. PEKERJAAN LANTAI II
PEKERJAAN KONTRUKSI
C.I. PEK. BETON
1 Pek. Kolom beton, K1 25/30 cm
a. Pas. Bekisting A.4.1.1.20 133,65 m2 407.802,00 54.502.737,30
b. Pas. Besi beton polos/uril 2.2.6.1.b.(c) 1.695,23 kg 18.476,70 31.322.256,14
c. Beton Site Mix (K225) A.4.1.1.7. 9,12 m3 1.215.700,00 11.087.184,00
2 Pek. Kolom beton, K2 20/20 cm
a. Pas. Bekisting A.4.1.1.20 38,48 m2 407.802,00 15.692.220,96
b. Pas. Besi beton polos/uril 2.2.6.1.b.(c) 663,74 kg 18.476,70 12.263.724,86
c. Beton Site Mix (K225) A.4.1.1.7. 3,08 m3 1.215.700,00 3.744.356,00
3 Pek. Kolom beton, KP 12/12
a. Pas. Bekisting A.4.1.1.20 52,25 m2 407.802,00 21.307.654,50
b. Pas. Besi beton polos 2.2.6.1.b.(c) 635,09 kg 18.476,70 11.734.367,40
c. Beton Site Mix (K225) A.4.1.1.7. 2,51 m3 1.215.700,00 3.051.407,00
4 Pek. balok lintel beton, BL 12/20 cm
a. Pas. Bekisting A.4.1.1.21 56,77 m2 417.462,00 23.699.317,74
b. Pas. Besi beton polos 2.2.6.1.b.(c) 3.053,63 kg 18.476,70 56.421.005,42
c. Beton Site Mix (K225) A.4.1.1.7. 3,41 m3 1.215.700,00 4.145.537,00
5 Pek. balok beton, B/RB2, 15/20 cm
a. Pas. Bekisting A.4.1.1.21 1,13 m2 417.462,00 471.732,06
b. Pas. Besi beton polos/uril 2.2.6.1.b.(c) 16,12 kg 18.476,70 297.844,40
c. Beton Site Mix (K225) A.4.1.1.7. 0,09 m3 1.215.700,00 109.413,00
6 Pek. balok beton, B3 20/30 cm
a. Pas. Bekisting A.4.1.1.21 22,25 m2 417.462,00 9.288.529,50
b. Pas. Besi beton polos/uril 2.2.6.1.b.(c) 244,91 kg 18.476,70 4.525.128,60
c. Beton Site Mix (K225) A.4.1.1.7. 1,67 m3 1.215.700,00 2.030.219,00
7 Pek. balok beton, B3A 20/30 cm
a. Pas. Bekisting A.4.1.1.21 7,58 m2 417.462,00 3.164.361,96
b. Pas. Besi beton polos/uril 2.2.6.1.b.(c) 75,07 kg 18.476,70 1.387.045,87
c. Beton Site Mix (K225) A.4.1.1.7. 0,57 m3 1.215.700,00 692.949,00
8 Pek. plat Lantai beton t = 10 cm,
a. Pas. Floordeck B.12.b 54,36 m2 243.541,00 13.238.888,76
a. Pas. Besi Wiremesh M 8 + Plastik 2.2.7.a.(a) 54,36 kg 16.526,79 898.396,30
c. Beton Site Mix (K. 225) A.4.1.1.7. 5,44 m3 1.215.700,00 6.613.408,00
9 Pek. Lesplank beton t = 7 cm,
a. Pas. Bekisting A.4.1.1.22 15,07 m2 465.302,00 7.012.101,14
b. Pas. Besi beton polos 2.2.6.1.b.(c) 85,29 kg 18.476,70 1.575.877,74
c. Beton Site Mix (K. 225) A.4.1.1.7. 0,92 m3 1.215.700,00 1.118.444,00
10 Pek. Topi beton t = 7 cm,
a. Pas. Bekisting A.4.1.1.22 37,34 m2 465.302,00 17.374.376,68
b. Pas. Besi beton polos 2.2.6.1.b.(c) 211,30 kg 18.476,70 3.904.126,71
c. Beton Site Mix (K. 225) A.4.1.1.7. 2,28 m3 1.215.700,00 2.771.796,00
11 Pek. Ring balok beton, RB1 20/30 cm
a. Pas. Bekisting A.4.1.1.21 67,83 m2 417.462,00 28.316.447,46
b. Pas. Besi beton polos/uril 2.2.6.1.b.(c) 896,96 kg 18.476,70 16.572.860,83
c. Beton Site Mix (K225) A.4.1.1.7. 5,82 m3 1.215.700,00 7.075.374,00
Page 3
HARGA JUMLAH
KODE
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN HARGA SATUAN
ANALISIS
Rp. Rp.
1 2 3 4 5 6 7
12 Pek. Ring balok beton, RB2 0,15/20 cm
a. Pas. Bekisting A.4.1.1.21 25,43 m2 417.462,00 10.616.058,66
b. Pas. Besi beton polos/uril 2.2.6.1.b.(c) 363,69 kg 18.476,70 6.719.791,02
c. Beton Site Mix (K225) A.4.1.1.7. 1,90 m3 1.215.700,00 2.309.830,00
13 Pek. Meja beton wastafel t = 10 cm,
a. Pas. Bekisting A.4.1.1.22 2,93 m2 465.302,00 1.363.334,86
b. Pas. Besi beton polos 2.2.6.1.b.(c) 30,31 kg 18.476,70 560.028,78
c. Beton Site Mix (K. 225) A.4.1.1.7. 0,24 m3 1.215.700,00 291.768,00
Sub jumlah 399.271.900,66
C.II. PEK. DINDING DAN PASANGAN
1 Pek. dinding 1/2 bata ringan t =7,5 cm, dengan mortar siap pakai A.4.4.1.25. 616,84 m2 202.219,00 124.736.767,96
2 Pek. plesteran 1 : 5 T= 15 mm 3.2.1. (c) 1.233,68 m2 70.627,00 87.131.117,36
3 Pek. Acian plesteran dan beton. 3.2.2.(c) 1.474,68 m2 43.573,00 64.256.231,64
4 Pas. Partisi Gypsum, Type A Dihitung 4,00 unt 3.848.984,00 15.395.936,00
5 Pas. Partisi Gypsum, Type B Dihitung 1,00 unt 1.809.373,00 1.809.373,00
Sub jumlah 293.329.425,96
C.III. PEK. KUDA - KUDA, ATAP DAN PLAFOND
1 Pas. rangka atap dan kuda - kuda baja ringan t= 1 mm Upah+Bahan 583,66 m2 344.500,00 201.070.870,00
2 Pas. Genteng Keramik KIA A.4.5.2.2.a 587,86 m2 258.373,00 151.887.151,78
3 Pas. Bubung Keramik KIA A.4.5.2.5.a 66,00 m' 250.918,00 16.560.588,00
4 Pas. Lispank Wood flange L= 30 cm, T= 8 mm A.4.6.1.22.a 108,20 m' 79.194,00 8.568.790,80
5 Pas. Rangka Plafon dari besi hollow A.4.2.1.21. 471,00 m2 133.564,00 62.908.644,00
6 Pas. Plafon dari Gypsum T= 9 mm A.4.5.1.7. 375,05 m2 51.509,00 19.318.450,45
7 Pas. Plafon dari GRC T= 4 mm A.4.5.1.7.a 95,96 m2 47.868,00 4.593.413,28
8 Pas. List Plafon dari Gypsum L = 10 cm A.4.5.1.10.a 632,60 m' 34.152,00 21.604.555,20
9 Pas. Talang dari plat besi Ø 20 cm A.4.2.1.19 .a 108,20 m' 111.736,00 12.089.835,20
Sub jumlah 498.602.298,71

C.IV. PEK. LANTAI DAN DINDING KERAMIK


1 Pek. urugan pasir bawah lantai 1.7.2.d 18,76 m3 165.174,00 3.098.664,24
2 Pas. Lantai Granit polish, 60 x 60 cm, polish type L1 A.4.4.3.13.a 358,10 m2 544.307,00 194.916.336,70
3 Pas. Lantai Keramik 40 x 40 Anti Sleep A.4.4.3.36. 16,95 m2 244.743,00 4.148.393,85
4 Pas. Dinding Keramik 20 x 40 Motip, WC A.4.4.3.53.a 74,47 m2 366.100,00 27.263.467,00
Sub jumlah 229.426.861,79

C.V. PEK. KUSEN,PINTU, JENDELA ALMUNIUM


1 Pas. Profil Pintu & Jendela Alumunium 4'', Brown Anodized Ex Alexindo, A.4.2.1.24. 616,30 m1 191.428,00 117.977.076,40
2 Pas. Daun Pintu Kaca Rangka Alumunium A.4.2.1.26 50,00 m2 982.900,00 49.145.000,00
3 Pas. Daun Pintu Strip Rangka Alumunium A.4.2.1.25. 11,06 m2 1.466.887,00 16.223.770,22
4 Pas. Daun Jendela Kaca Rangka Alumunium A.4.2.1.26.a 56,76 m2 360.807,00 20.479.405,32
Sub jumlah 203.825.251,94

C.VI. PEK. KUNCI DAN KACA


1 Pas. Kunci tanam biasa A.4.6.2.2. 17,00 bh 168.579,00 2.865.843,00
2 Pas. Kunci Kamar Mandi A.4.6.2.3. 7,00 bh 167.736,00 1.174.152,00
3 Pas. Engsel pintu A.4.6.2.5. 105,00 bh 38.408,00 4.032.840,00
4 Pas. Rell Sleding pintu A.4.6.2.14. 1,00 set 651.556,00 651.556,00
5 Pas. Espanyolet Dihitung 12,00 set 118.908,00 1.426.896,00
6 Pas. Tarikan pintu A.4.6.2.13.a 72,00 bh 415.898,00 29.944.656,00
7 Pas. Friction Stay Jendela A.4.6.2.9.a 63,00 bh 170.083,00 10.715.229,00
8 Pas. Casement Handle A.4.6.2.11.a 63,00 bh 88.960,00 5.604.480,00
9 Pas. Kaca Tebal 8 mm A.4.6.2.18. 36,14 m2 237.750,00 8.592.285,00
10 Pas. Kaca Tebal 5 mm A.4.6.2.17. 91,68 m2 143.697,00 13.174.140,96
78.182.077,96
Page 4
HARGA JUMLAH
KODE
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN HARGA SATUAN
ANALISIS
Rp. Rp.
1 2 3 4 5 6 7

C.VII. PEK. SANITASI


1 Pas. Closet Duduk porselin A.5.1.1.1. 7,00 bh 3.779.919,00 26.459.433,00
2 Pas. Wastafel sek. INA lengkap A.5.1.1 5. 5,00 bh 2.386.514,00 11.932.570,00
3 Pas. Pipa PVC Dia 4" ( AW ) Saluran Instalasi Air Padat A.5.1.1 32. 28,10 m' 435.759,00 12.244.827,90
4 Pas. Pipa PVC Dia 3" ( AW ) Saluran Instalasi Air Kotor A.5.1.1 31. 35,26 m' 129.364,00 4.561.374,64
5 Pas. Pipa PVC Dia 2,5" ( AW ) Saluran Instalasi Air Hujan A.5.1.1 30. 140,00 m' 111.106,00 15.554.840,00
6 Pas. Pipa PVC Dia 1" ( AW ) Saluran Instalasi Air Bersih A.5.1.1 27. 30,40 m' 37.872,00 1.151.308,80
7 Pas. Pipa PVC Dia 3/4" ( AW ) Saluran Instalasi Air Bersih A.5.1.1 26. 69,00 m' 32.749,00 2.259.681,00
8 Pas. Floor Drain Stainlees A.5.1.1 .36. 7,00 bh 56.914,00 398.398,00
9 Pas. Jet Washer A.5.1.1.35.b 7,00 bh 271.563,00 1.900.941,00
10 Pas. Kran Air 3/4" (Type Baling) A.5.1.1.35 7,00 bh 78.597,00 550.179,00
11 Pas. Stop Kran Air 1" A.5.1.1.35.d 2,00 bh 155.327,00 310.654,00
12 Pas. Radar / Automatis + lengkap kabel Upah+Bahan 1,00 bh 150.000,00 150.000,00
13 Pas. Tanki Air Kap. 1000 L dari Stainles Upah+Bahan 1,00 bh 5.200.000,00 5.200.000,00
14 Pas. Tanki Air Kap. 1000 L dari Fiber persegi Upah+Bahan 1,00 bh 3.445.000,00 3.445.000,00
15 Pas. Ground Tank dari pas Bata Dihitung 1,00 unt 10.777.645,00 10.777.645,00
16 Pas. Pompa Air Kap. 250 watt Upah+Bahan 1,00 bh 2.849.600,00 2.849.600,00
99.746.452,34

C.VIII. PEK. LISTRIK


1 Pas. Box Sikring upah+bahan 1,00 bh 52.000,00 52.000,00
2 Pas. MCB 10 A upah+bahan 4,00 bh 65.000,00 260.000,00
3 Pek. instalasi titik cahaya upah+bahan 43,00 ttk 150.000,00 6.450.000,00
4 Pek. instalasi titik stop kontak upah+bahan 50,00 ttk 150.000,00 7.500.000,00
5 Pas.Lampu RMI 2 x 16 watt + box upah+bahan 19,00 ttk 235.000,00 4.465.000,00
6 Pas.Lampu Downlight LED 18 watt upah+bahan 20,00 bh 94.500,00 1.890.000,00
7 Pas. saklar tunggal, broco upah+bahan 4,00 bh 22.600,00 90.400,00
8 Pas. saklar ganda, broco upah+bahan 10,00 bh 36.600,00 366.000,00
9 Pas. stop kontak AC , broco upah+bahan 15,00 bh 205.210,00 3.078.150,00
10 Pas. stop kontak , broco upah+bahan 35,00 bh 27.000,00 945.000,00
11 Pentanahan Penangkal Petir upah+bahan 3,00 bh 1.300.000,00 3.900.000,00
12 Pek. Kabel BC 35 mm²+ Pemasangan upah+bahan 60,00 m' 85.000,00 5.100.000,00
13 Pek. Pemasangan Finial Petir upah+bahan 2,00 set 250.000,00 500.000,00
34.596.550,00

C.IX. PEK. PENGECATAN


1 Pek. cat dinding baru, Sanlex 3.3.10.(c) 1.474,7 m2 33.118,00 48.838.452,24
2 Pek. cat plafond baru, Sanlex 3.3.10.(b) 471,00 m2 42.901,00 20.206.371,00
Sub jumlah 69.044.823,24
Page 5
HARGA JUMLAH
KODE
NO. URAIAN PEKERJAAN VOLUME SAT. SATUAN HARGA SATUAN
ANALISIS
Rp. Rp.
1 2 3 4 5 6 7

C.X. PEK. RAM


1 Pek. balok beton, B5 15/30
a. Pas. Bekisting 126,48 m2 417.462,00 52.800.593,76
b. Pas. Besi beton polos/uril 1.897,36 kg 18.476,70 35.056.951,51
c. Beton Site Mix (K. 225) 9,49 m3 1.215.700,00 11.536.993,00
2 Pek. Plat beton t = 15 cm,
a. Pas. Bekisting 131,92 m2 465.302,00 61.382.639,84
b. Pas. Besi beton polos 2.430,89 kg 18.476,70 44.914.825,26
c. Beton Site Mix (K. 225) 14,57 m3 1.215.700,00 17.712.749,00
3 Pek. Kolom beton, KP 12/12
a. Pas. Bekisting 0,09 m2 407.802,00 36.702,18
b. Pas. Besi beton polos/ulir 0,12 kg 18.476,70 2.217,20
c. Beton Site Mix (K225) 0,08 m3 1.215.700,00 97.256,00
4 Pek. dinding 1/2 bata ringan t =7,5 cm, dengan mortar siap pakai 43,70 m2 202.219,00 8.836.970,30
5 Pek. plesteran 1 : 5 T= 15 mm 43,70 m2 70.627,00 3.086.399,90
6 Pek. Acian plesteran dan beton. 43,70 m2 43.573,00 1.904.140,10
7 Pas. Lantai Granit Anpolish, 60 x 60 cm, 97,10 m2 544.307,00 52.852.209,70
8 Pas. Relling Stenlis steel Ø 2" 46,55 m' 1.650.000,00 76.807.500,00
9 Pek. cat dinding baru setara sanlex 43,70 m2 33.118,00 1.447.256,60
Sub jumlah 78.254.756,60

D. PEK. LAIN - LAIN


1 Pek. Pembersihan bekas pekerjaan - 1,00 ls 3.500.000,00 3.500.000,00
Sub jumlah 3.500.000,00
PEMBERI TUGAS

KEPOLISIAN REPUBLIK INDONESIA


KEPOLISIAN RESOR TASIKMALAYA KOTA
Jl. Letnan Harun, Sukarindik, Kec. Bungursari, Kab. Tasikmalaya, Jawa Barat 46151

PEKERJAAN

RENOVASI / PENGEMBANGAN
GEDUNG INTEL DAN RESKRIM
POLRES TASIKMALAYA KOTA

CATATAN
TANGGAL URAIAN PARAF

a
R. WC
LAKTASI FFL.+3.95
TOILET TOILET TOILET
R. KA UNIT 4 R. RAPAT R. PPA DISABILITAS
R. RESMOB FFL.+4.00
R. URMIN
FFL.+4.00 FFL.+4.00 FFL.+4.00
FFL.+4.00 R.
R. GANTI
RAMAH FFL.+4.00
ANAK
TURUN b
KORIDOR KORIDOR
FFL.+4.00 FFL.+4.00

GANTI
R. TUNGGU
R. KA UNIT 3 R. KASAT FFL.+4.00 R. KBO R. KA UNIT 2 R. KA UNIT 1 R. GDG
FFL.+4.00 FFL.+4.00 FFL.+4.00 FFL.+4.00 FFL.+4.00 FFL.+4.00
WC WC
WC
FFL.+3.95 FFL.+3.95 FFL.-0.05

c
DAK BETON
FFL.+3.95
d

1 2 3 4 5 6 7 8 9 10 11 12 13 14

DENAH RENCANA LT. 2

JUDUL GAMBAR SKALA

TAHUN NO.LEMBAR JML.LEMBAR

2022
PEMBERI TUGAS

KEPOLISIAN REPUBLIK INDONESIA


94 100 KEPOLISIAN RESOR TASIKMALAYA KOTA
Jl. Letnan Harun, Sukarindik, Kec. Bungursari, Kab. Tasikmalaya, Jawa Barat 46151

PEKERJAAN

RENOVASI / PENGEMBANGAN
GEDUNG INTEL DAN RESKRIM
400

POLRES TASIKMALAYA KOTA

CATATAN
TANGGAL URAIAN PARAF
400

1 2 3 4 5 6 7 8 9 10 11 12 13 14

POTONGAN A-A

100 105
80

80
RENCANA PLAFOND +7.70 RENCANA PLAFOND +7.70
400

400

PENDAFTARAN
400

400

+1.10 JUDUL GAMBAR SKALA

POTONGAN A-A
POTONGAN B-B 1 :150
POTONGAN C-C
d c b a d c b a

POTONGAN B-B POTONGAN C-C TAHUN NO.LEMBAR JML.LEMBAR

2022 21
PEMBERI TUGAS

KEPOLISIAN REPUBLIK INDONESIA


KEPOLISIAN RESOR TASIKMALAYA KOTA
Jl. Letnan Harun, Sukarindik, Kec. Bungursari, Kab. Tasikmalaya, Jawa Barat 46151

PEKERJAAN

RENOVASI / PENGEMBANGAN
GEDUNG INTEL DAN RESKRIM
POLRES TASIKMALAYA KOTA

CATATAN
TANGGAL URAIAN PARAF

TAMPAK DEPAN

JUDUL GAMBAR SKALA

TAMPAK BELAKANG TAMPAK DEPAN 1 :150


TAMPAK BELAKANG

TAHUN NO.LEMBAR JML.LEMBAR

2022 21
PEMBERI TUGAS

KEPOLISIAN REPUBLIK INDONESIA


KEPOLISIAN RESOR TASIKMALAYA KOTA
Jl. Letnan Harun, Sukarindik, Kec. Bungursari, Kab. Tasikmalaya, Jawa Barat 46151

PEKERJAAN

RENOVASI / PENGEMBANGAN
GEDUNG INTEL DAN RESKRIM
POLRES TASIKMALAYA KOTA

CATATAN
TANGGAL URAIAN PARAF

TAMPAK SAMPING KIRI TAMPAK SAMPING KANAN

JUDUL GAMBAR SKALA

TAMPAK DEPAN 1 :150


TAMPAK BELAKANG

TAHUN NO.LEMBAR JML.LEMBAR

2022 21