I PEKERJAAN PERSIAPAN/PENDAHULUAN 3.706.968,00 II PEKERJAAN STRUKTUR A. PEKERJAAN TANAH DAN PASIR 5.067.567,45 B. PEKERJAAN PONDASI, SLOOF , BALOK, KOLOM DAN PLAT 83.954.330,73 III PEKERJAAN ARSITEKTUR A. PEKERJAAN DINDING DAN PLESTERAN 55.911.156,36 B. PEKERJAAN KUSEN PINTU, DAUN PINTU / JENDELA, KACA 5.883.441,98 C. PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING 17.143.726,26 D. PEKERJAAN RANGKA DAN PLAFOND 16.119.685,71 E. PEK. KONSTRUKSI KUDA KUDA DAN ATAP 18.347.028,40 F. PEKERJAAN PENGECETAN 19.917.134,91 IV PEKERJAAN SANITASI DAN MEKANIKAL ELEKTRIKAL A. PEKERJAAN SANITASI DAN PLUMBING 15.991.114,40 B. PEKERJAAN MEKANIKAL ELEKTRIKAL 19.511.266,00 V PEKERJAAN AKHIR 1.000.000,00
A REAL COST 262.553.420,19
B. PPN (10%) 26.255.342,02 C. IMB (0 %) D. TOTAL COST ( A + B + C) 288.808.762,20 DIBULATKAN 288.808.000,00 Terbilang : DUA RATUS DELAPAN PULUH DELAPAN JUTA DELAPAN RATUS DELAPAN RUPIAH Kendari, Februari 2020 Penanggung Jawab