MILESTONE SCHEDULE

THE BELTON RESIDENCES

ID % URAIAN PEKERJAAN DURASI Start Finish


Complete 2023
Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Q
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
1 100% 1 THE BELTON RESIDENCE 418 days Tue 01/08/23 Fri 25/10/24
2
3 13% 2 DAFTAR NO. 1 : PEKERJAAN PERSIAPAN, PRASARANA DAN 420 days Tue 01/08/23 Sun 27/10/24
PENUNJANG
4
5 1% 3 DAFTAR NO. 2 : PEKERJAAN TANAH 42 days Tue 01/08/23 Tue 12/09/23
6
7 7% 4 DAFTAR NO. 3 : PEKERJAAN STRUKTUR BAWAH 49 days Mon 21/08/23 Mon 09/10/23
8
9 6% 5 DAFTAR NO. 4 : PEKERJAAN STRUKTUR ATAS PODIUM 56 days Fri 01/09/23 Fri 27/10/23
10
11 19% 6 DAFTAR NO. 5 : PEKERJAAN STRUKTUR ATAS TOWER 140 days Mon 02/10/23 Fri 23/02/24
12
13 9% 7 DAFTAR NO. 6 : PEKERJAAN DINDING 161 days Mon 30/10/23 Thu 02/05/24
14
15 4% 8 DAFTAR NO. 7 : PEKERJAAN LANTAI 112 days Mon 01/04/24 Sun 11/08/24
16
17 2% 9 DAFTAR NO. 8 : PEKERJAAN PLAFOND 70 days Thu 01/02/24 Thu 02/05/24
18
19 10% 10 DAFTAR NO. 9 : PEKERJAAN PINTU JENDELA 84 days Mon 01/04/24 Sun 14/07/24
20
21 1% 11 DAFTAR NO. 10 : PEKERJAAN SANITARY FIXTURE 126 days Mon 17/06/24 Wed 23/10/24
22
23 5% 12 DAFTAR NO. 11 : PEKERJAAN LAIN-LAIN 203 days Mon 04/03/24 Sat 19/10/24
24
25 8% 13 DAFTAR NO. 12 : PEKERJAAN FAÇADE DAN ATAP KANOPI 196 days Mon 23/10/23 Sun 02/06/24
26
27 12% 14 DAFTAR NO. 13 : PEKERJAAN PLUMBING 420 days Tue 01/08/23 Sun 27/10/24
28
29 2% 15 DAFTAR NO. 14 : PEK. INSTALASI MVAC AREA UNIT HUNIAN 70 days Mon 19/02/24 Sun 19/05/24
30
31 1% 16 DAFTAR NO. 15 : PEKERJAAN PROVISIONAL SUM 30 days Mon 01/04/24 Fri 17/05/24

Task Manual Task Deadline Baseline Milestone

Split Duration-only Critical Baseline Summary

Milestone Manual Summary Rollup Critical Split Progress

Project: Summary Manual Summary Late Manual Progress


Date: Thu 27/07/23 Project Summary Start-only Path Driven Successor Milestone Task Slippage

Inactive Task Finish-only Path Driven Successor Summary Task

Inactive Milestone External Tasks Path Driven Successor Normal Task

Inactive Summary External Milestone Baseline