Anda di halaman 1dari 1

Pekerjaan :PEMBANGUNAN GEDUNG KANTOR SEMENTARA KPwBI PURWOKERTO

Lokasi :JL. AHMAD YANI NO. 30, PURWOKERTO KAB. BANYUMAS, PROV. JAWA TENGAH
Tahun : 2023

HARGA SATUAN
NO. URAIAN PEKERJAAN VOL SAT JUMLAH (Rp)
(Rp)

VI. PEKERJAAN PENANGKAL PETIR

1 Roof
- Air Terminal @1 mtr 3.00 bh 4,255,000 12,765,000
- Base Air Terminal 3.00 bh 1,455,000 4,365,000
- Kabel BCC 50 mm2 51.00 m 252,000 12,852,000
- Tape 25 x 3 mm 48.00 m 45,000 2,160,000
- DC Clip Non Metalic Clamp 48.00 bh 340,000 16,320,000
- Square Tape Claamp 4.00 bh 56,000 224,000
- Bimetalic Clamp 4.00 bh 70,000 280,000

2 Down Conductor
Kabel BCC 50 mm2 44.00 m 470,000 20,680,000
L Clamp 44.00 bh 270,000 11,880,000

3 Grounding System 2.00 titik 6,700,000 13,400,000


Pit PVC + Busbar
Rod 5/8 CU Bonded
Clamp Rod
Coupling
Kabel BC 50 mmm
dan detail

TOTAL PEKERJAAN PENANGKAL PETIR 94,926,000.00