PERHITUNGAN KEBUTUHAN BAHAN
BANGUNAN BERDASARKAN STANDAR
NASIONAL INDONESIA(SNI)
(KHUSUS PEMULA)
A3. PERHITUNGAN KEBUTUHAN PASANGAN BATU KOSONG
• CONTOH :
BERAPAKAH KEBUTUHAN MATERIAL UNTUK PEKERJAAN PASANGAN BATU KOSONG DENGAN DENAH DAN
GAMBAR DETAIL PONDASI SEPERTI DIBAWAH INI?

QUANTITY’S CORNER
120

70
LANGKAH 1:
HITUNG PANJANG TOTAL STRUKTUR PONDASI BANGUNAN YANG DIBUTUHKAN.
DIMANA :
H1 = PANJANG HORISONTAL

QUANTITY’S CORNER
V1-V3 = PANJANG VERTIKAL
PERHITUNGAN:
H1 = 7.5 M x 4 = 30 M
V1 = 1.75 M x 3 = 5.25 M
V2 = 2.5 M x 4 = 10 M
V3 = 3.25 M x 3 = 9.75 M +
TOTAL PANJANG (L) = 55 M
LANGKAH 2 :
HITUNG KEBUTUHAN MATERIAL A3 (PEKERJAAN PASANGAN BATU KOSONG)

A3. PEKERJAAN PASANGAN BATU KOSONG

QUANTITY’S CORNER
LUAS PENAMPANG PAS. BATU KOSONG = (0.85 + 0.9) x 0.5 x 0.2 = 0.175 M2
120 PANJANG TOTAL PONDASI (L) = 55 M
VOLUME PASANGAN BATU KOSONG = 0.175 M2 x 55 M = 9.625 M3

KEBUTUHAN MATERIAL :

BERDASARKAN SNI, KEBUTUHAN MATERIAL PEKERJAAN


PASANGAN BATU KOSONG TIAP 1 M3 ADALAH :
70

- BATU KALI BELAH = 1.2 M3


- PASIR URUG = 0.3 M3

JADI KEBUTUHAN MATERIAL TOTAL :

- BATU KALI BELAH = 1.2 x 9.625 M3 = 11.55 M3 ≈ 12 m3


- PASIR URUG = 0.3 x 9.625 M3 = 2.89 M3 ≈ 3 m3
UNTUK PEKERJAAN A4 . PASANGAN BATU KALI

QUANTITY’S CORNER
SILAHKAN IKUTI DI VIDEO BERIKUTNYA

TERIMA KASIH