PERHITUNGAN KEBUTUHAN BAHAN
BANGUNAN BERDASARKAN STANDAR
NASIONAL INDONESIA(SNI)
(KHUSUS PEMULA)
A6. PERHITUNGAN KEBUTUHAN URUGAN TANAH KEMBALI
• CONTOH :
BERAPAKAH KEBUTUHAN MATERIAL UNTUK PEKERJAAN URUGAN TANAH KEMBALI DENGAN DENAH DAN
GAMBAR DETAIL PONDASI SEPERTI DIBAWAH INI?

QUANTITY’S CORNER
120

70
LANGKAH 1:
HITUNG PANJANG TOTAL STRUKTUR PONDASI BANGUNAN YANG DIBUTUHKAN.
DIMANA :
H1 = PANJANG HORISONTAL

QUANTITY’S CORNER
V1-V3 = PANJANG VERTIKAL
PERHITUNGAN:
H1 = 7.5 M x 4 = 30 M
V1 = 1.75 M x 3 = 5.25 M
V2 = 2.5 M x 4 = 10 M
V3 = 3.25 M x 3 = 9.75 M +
TOTAL PANJANG (L) = 55 M
LANGKAH 2:
HITUNG KEBUTUHAN MATERIAL A6 (PEKERJAAN TANAH URUG KEMBALI)
120
A6. PEKERJAAN TANAH URUG KEMBALI
VOL. TANAH URUG KEMBALI = VOL GALIAN – VOL. STRUKTUR PONDASI

QUANTITY’S CORNER
A1. VOLUME GALIAN = 55 M3
A2. VOLUME PASIR URUG = 2.2 M3
7
0

A3. VOLUME PASANGAN BATU KOSONG = 9.625 M3

A4. VOLUME PASANGAN BATU KALI = 19.25 M3

VOLUME TANAH URUG KEMBALI = A1 - ( A2 + A3 + A4 )

= 55 - ( 2.2 +9.625 + 19.25 )


= 23.925 M3
FAKTOR KEMBANG SUSUT TANAH RATA-RATA = 20%

VOLUME TANAH URUG KEMBALI = (100+20)% x 23.925

VOLUME TANAH URUG KEMBALI = 28.71 M3

JADI KEBUTUHAN MATERIAL TANAH URUG KEMBALI = 28.71 M3