PERHITUNGAN KEBUTUHAN BAHAN
BANGUNAN BERDASARKAN STANDAR
NASIONAL INDONESIA(SNI)
(KHUSUS PEMULA)
A4. PERHITUNGAN KEBUTUHAN PASANGAN BATU KALI
• CONTOH :
BERAPAKAH KEBUTUHAN MATERIAL UNTUK PEKERJAAN PASANGAN BATU KALI DENGAN DENAH DAN GAMBAR
DETAIL PONDASI SEPERTI DIBAWAH INI?

QUANTITY’S CORNER
120

70
LANGKAH 1:
HITUNG PANJANG TOTAL STRUKTUR PONDASI BANGUNAN YANG DIBUTUHKAN.
DIMANA :
H1 = PANJANG HORISONTAL

QUANTITY’S CORNER
V1-V3 = PANJANG VERTIKAL
PERHITUNGAN:
H1 = 7.5 M x 4 = 30 M
V1 = 1.75 M x 3 = 5.25 M
V2 = 2.5 M x 4 = 10 M
V3 = 3.25 M x 3 = 9.75 M +
TOTAL PANJANG (L) = 55 M
HITUNG KEBUTUHAN MATERIAL A4 (PEKERJAAN PASANGAN BATU KALI)

A4. PEKERJAAN PASANGAN BATU KALI

QUANTITY’S CORNER
LUAS PENAMPANG PAS. BATU KALI = (0.3 + 0.7) x 0.5 x 0.7 = 0.35 M2
120 PANJANG TOTAL PONDASI (L) = 55 M
VOLUME PASANGAN BATU KALI = 0.35 M2 x 55 M = 19.25 M3

KEBUTUHAN MATERIAL :

BERDASARKAN SNI, KEBUTUHAN MATERIAL PEKERJAAN


PASANGAN BATU KALI CAMPURAN 1:5 TIAP 1 M3 ADALAH :
70

- BATU KALI BELAH = 1.1 M3


- PASIR PASANG = 0.544 M3
- SEMEN PC = 136 KG

JADI KEBUTUHAN MATERIAL TOTAL :

- BATU KALI BELAH = 1.1 x 19.25 M3 = 21.18 M3


- PASIR PASANG = 0.544 x 19.25 M3 = 10.475 M3 ≈ 10.5 m3
- SEMEN PC = 136 x 19.25 M3 = 2618 KG ≈ 66 ZAK ( 40 KG)
UNTUK PEKERJAAN A5 .PEK SLOOF BETON

QUANTITY’S CORNER
SILAHKAN IKUTI DI VIDEO BERIKUTNYA