MESYUARAT PENGUJIAN PENERIMAAN AKHIR

(FAT)
SEBUT HARGA PERKHIDMATAN PEMBANGUNAN SISTEM PEMPROSESAN
DATA “GEOGRAPHIC INFORMATION SYSTEM (GIS)” TERMASUK
“PEMBANGUNAN SISTEM CONVERSION DATA, MIGRATION AND
TRANSFORMATION DATA, INTEGRATION DATA” UNTUK JABATAN
PERANCANGAN PEMBANGUNAN, MAJLIS BANDARAYA PULAU PINANG 2021

TARIKH : 13 JANUARI 2022


TEMPAT : MBPP,KOMTAR
MASA: 2.00 PETANG

Making GIS Grow, Together


AGENDA

1. STATUS PEMBANGUNAN
2. ISU DALAM PEMBANGUNAN SISTEM
3. DEMO SISTEM

Making GIS Grow, Together


JADUAL PERLAKSANAAN

Making GIS Grow, Together


STATUS PEMBANGUNAN
Task Name Duration Start Finish Status

“PEMBANGUNAN SISTEM CONVERSION DATA,


MIGRATION AND TRANSFORMATION DATA, 130 days 1/9/21 1/3/22
INTEGRATION DATA” UNTUK JABATAN PERANCANGAN
PEMBANGUNAN MBPP

SURAT SETUJU TERIMA 1 day 1/9/21 1/9/21


MESYUARAT KICK-OFF 1 day 2/9/21 2/9/21
KAJIAN KEPERLUAN PENGGUNA 29 days 3/9/21 13/10/21
Pra-Kajian Keperluan Pengguna 26 days 3/9/21 8/10/21
Kajian Spesifikasi Infrastruktur Sistem 3 days 11/10/21 13/10/21
Kajian Spesifikasi Fungsi dan Modul Sistem 3 days 11/10/21 13/10/21

Kajian Spesifikasi Fungsi dan Modul Integrasi 3 days 11/10/21 13/10/21

PENGHASILAN PROTOTAIP SISTEM 30 days 3/9/21 14/10/21

PEMBANGUNAN REKABENTUK PANGKALAN DATA


5 days 14/10/21 20/10/21
DAN ALIRAN SISTEM

Making GIS Grow, Together


Task Name Duration Start Finish Status
PEMBANGUNAN SISTEM SMART 35 days 21/10/21 8/12/21
GEOCONVERTER

Modul Semakan Data (varifikasi) 20 days 21/10/21 17/11/21


Layer 20 days 21/10/21 17/11/21
Attribute 20 days 21/10/21 17/11/21
Position 20 days 21/10/21 17/11/21
Shape 20 days 21/10/21 17/11/21
Sufficient 20 days 21/10/21 17/11/21
Modul Pemprosesan Data 15 days 18/11/21 8/12/21
Penukaran format ACAD ke GIS 15 days 18/11/21 8/12/21
Transformasi Koordinat 15 days 18/11/21 8/12/21
Migrasi Attribut ke Skema Pangkalan
15 days 18/11/21 8/12/21
Data SMART GEOCONVERTER
KERJA-KERJA PENGUJIAN DAN 5 days 9/12/21 15/12/21
PENTAULIAHAN AWAL (UAT)
System Compatibility Check 3 days 13/12/21 15/12/21
User Acceptance Test (UAT) 2 days 14/12/21 15/12/21
Deploying UAT Changes 2 days 14/12/21 15/12/21
Pembayaran Pertama (UAT) 0 days
Making GIS Grow, Together
Task Name Duration Start Finish Status

INTEGRASI PANGKALAN DATA


18 days 16/12/21 10/1/22
ILCS DAN SMART GEOCONVERTER
Modul Integrasi 12 days 16/12/21 31/12/21
(antara sistem)
- Sub Modul Muatnaik Fail 12 days 16/12/21 31/12/21
- Capaian Integrasi 12 days 16/12/21 31/12/21

Modul Paparan Data Spatial Ke Memaparkan data


5 days 4/1/22 10/1/22 spatial di server
PiMAP development
Kerja-Kerja Konfigurasi Dan
7 days 11/1/22 19/1/22
Penstrukturan Capaian
KERJA-KERJA PENGUJIAN DAN 3 days 20/1/22 24/1/22
PENTAULIAHAN AKHIR (FAT)
Pembayaran Terakhir (FAT) 0 days 20/1/22 20/1/22
LATIHAN DAN PEMINDAHAN 2 days 26/1/22 27/1/22
TEKNOLOGI (TOT)
GO LIVE 1 day 28/1/22 28/1/22
JAMINAN DAN SOKONGAN 129 days 1/2/22 29/7/22 6 Bulan
TEKNIKAL
Serahan Sistem 1 day 1/8/22 1/8/22
Making GIS Grow, Together
ISU DALAM PEMBANGUNAN

1. Capaian ke pangkalan data ILCS


2. Proses migrasi sistem ke server PiMAP

Making GIS Grow, Together


Isu 1 : Capaian ke pangkalan data ILCS
Solusi
• Permohonan rasmi API telah di hantar ke vendor ILCS
• Dijangkakan API ILCS akan diperoleh pada penghujung bulan Januari
• Proses integrasi data akan dilakukan semasa tempoh waranti

Making GIS Grow, Together


Isu 2 : Proses migrasi sistem ke server
PiMAP
Solusi
• Pasukan pembangunan berhubung dengan pihak ESRI untuk bantuan
teknikal
• Server PiMAP perlu melalui konfigurasi khususnya berkaitan dengan
capaian ArcGIS processing tool
• Dalam proses konfigurasi

Making GIS Grow, Together


Making GIS Grows, Together

THANK YOU
Do you have any questions?
sales@map2u.com.my
06 8516463
www.map2u.com.my