PLN (Persero)
Proyek Induk Pembangkit dan Jaringan
Jawa, Bali dan Nusa Tenggara
Proyek Pembangkit dan Jaringan Jateng & DIY
PADAM
NO BAY KETERANGAN
HARI TANGGAL JAM
1 KLATEN II RABU 28-Apr-10 08.00 - 09.30
2 KENTUNGAN II RABU 28-Apr-10 10.00 - 11.30
3 KENTUNGAN I RABU 28-Apr-10 12.30 - 14.00
4 KLATEN I KAMIS 29-Apr-10 14.30 - 16.00
5 KOPEL KAMIS 29-Apr-10 08.00 - 09.30
6 WONOSARI I KAMIS 29-Apr-10 10.00 - 11.30
7 JAJAR I KAMIS 29-Apr-10 12.30 - 14.00
8 JAJAR II JUM'AT 30-Apr-10 10.00 - 11.30
9 WONOSARI II JUM'AT 30-Apr-10 12.30 - 14.00
+ PERBAIKAN KEBOCORAN MINYAK &
10 TRAFO II JUM'AT 30-Apr-10 08.00 - 16.00 PENYELESAIAN PENDING MATTERS
11 IBT II SABTU 1-May-10 08.00 - 09.30
12 TRAFO I SABTU 1-May-10 10.00 - 11.30
13 IBT I MINGGU 2-May-10 08.00 - 09.30
1. PEMADAMAN
2. PENJAMPERAN RANGKAIAN TRIPPING
A. PANEL BUSPRO
B. PANEL RELAY BAY TERKAIT
3. TEST TRIPPING VIA PROGRAM RELAY/ INJEKSI SEKUNDER
4. PENORMALAN BAY