VI.C PEKERJAAN VENTILASI - -
Pekerjaan Lantai 1 - -
1 Exhaust Fan Ceilling Mount tipe 4.00 Unit 345,600.00 1,382,400.00
- Kap. 285 cfm/18w/220V/50Hz - -
Pekerjaan Lantai 2 - -
2 Exhaust Fan Ceilling Mount tipe 4.00 Unit 345,600.00 1,382,400.00
- Kap. 285 cfm/18w/220V/50Hz - -
- -
VI.D PEKERJAAN PEMADAM KEBAKARAN - -
Pekerjaan Alat Pemadam api Ringan - -
1 Portable Fire Extinguisher Dry Powder 6kg 9.00 Unit 403,200.00 3,628,800.00
- -
- -
VI.E PEKERJAAN ELEKTRONIKA - -
E.1 SISTEM FIRE ALARM - -
I Peralatan Utama Fire Alarm - -
1 MCFA Cap. 10 zone AH 033123-8 Convensional cabinet w/o 1.00 Unit 6,912,000.00 6,912,000.00
2 MTBFA 1.00 Unit 691,200.00 691,200.00
3 Batteray UPS Backup 1jam/ 2kva 1.00 Set 2,016,000.00 2,016,000.00
4 Pengkabelan kabel grounding dari bak kontrol ke unit main hub NYA 10mm 32.00 M' 4,320.00 138,240.00
Kabel Feeder Utama - -
1 Kabel dari TBFA 1 ke MCFA system d/kabel NYA 2x1x1,5mm2, + Conduit PVC 16.00 M' 4,896.00 78,336.00
2 Kabel dari TBFA 2 ke MCFA system d/kabel NYA 2x1x1,5mm2, + Conduit PVC 26.00 M' 4,896.00 127,296.00
3 Kabel dari TBFA 3 ke MCFA system d/kabel NYA 2x1x1,5mm2, + Conduit PVC 32.00 M' 4,896.00 156,672.00
- -
II Armature & Instalasi - -
Pekerjaan Lantai 1 - -
Armature - -
1 Head detector +ROR 16.00 bh 57,600.00 921,600.00
2 Alarm Bell 1.00 bh 201,600.00 201,600.00
3 Lampu Indikator 1.00 bh 63,360.00 63,360.00
4 Manual Push Button 1.00 bh 207,360.00 207,360.00
Instalasi - -
1 Instalasi titik detector kabel NYA 2x2x1,5mm2 dala conduit 3/4" 16.00 titik 95,040.00 1,520,640.00
2 Instalasi titik alarm bell kabel NYA 2x2x1,5mm2 dala conduit 3/4" 1.00 titik 72,000.00 72,000.00
3 Instalasi titik lampu indikator kabel NYA 2x2x1,5mm2 dala conduit 3/4" 1.00 titik 72,000.00 72,000.00
4 Instalasi titik manual push button kabel NYA 2x2x1,5mm2 dala conduit 3/4" 1.00 titik 72,000.00 72,000.00
- -
Pekerjaan Lantai 2 - -
Armature - -
1 Head detector +ROR 15.00 bh 57,600.00 864,000.00
2 Alarm Bell 1.00 bh 201,600.00 201,600.00
3 Lampu Indikator 1.00 bh 63,360.00 63,360.00
4 Manual Push Button 1.00 bh 207,360.00 207,360.00
Instalasi - -
1 Instalasi titik detector kabel NYA 2x2x1,5mm2 dala conduit 3/4" 15.00 titik 95,040.00 1,425,600.00
2 Instalasi titik alarm bell kabel NYA 2x2x1,5mm2 dala conduit 3/4" 1.00 titik 72,000.00 72,000.00
3 Instalasi titik lampu indikator kabel NYA 2x2x1,5mm2 dala conduit 3/4" 1.00 titik 72,000.00 72,000.00
4 Instalasi titik manual push button kabel NYA 2x2x1,5mm2 dala conduit 3/4" 1.00 titik 72,000.00 72,000.00
- -
Pekerjaan Lantai 3 - -
Armature - -
1 Head detector +ROR 11.00 bh 57,600.00 633,600.00
2 Alarm Bell 1.00 bh 201,600.00 201,600.00
3 Lampu Indikator 1.00 bh 63,360.00 63,360.00
4 Manual Push Button 1.00 bh 207,360.00 207,360.00
Instalasi - -
1 Instalasi titik detector kabel NYA 2x2x1,5mm2 dala conduit 3/4" 11.00 titik 95,040.00 1,045,440.00
2 Instalasi titik alarm bell kabel NYA 2x2x1,5mm2 dala conduit 3/4" 1.00 titik 72,000.00 72,000.00
3 Instalasi titik lampu indikator kabel NYA 2x2x1,5mm2 dala conduit 3/4" 1.00 titik 72,000.00 72,000.00
4 Instalasi titik manual push button kabel NYA 2x2x1,5mm2 dala conduit 3/4" 1.00 titik 72,000.00 72,000.00
Material Bantu 1.00 Lot 1,324,800.00 1,324,800.00
DINAS KEBUDAYAAN DAN PARIWISATA KABUPATEN DELI SERDANG
Lantai 3 - -
Armature - -
Ceiling Speaker 3 watt 8.00 Bh 112,320.00 898,560.00
TB sound sistem 1.00 Bh 403,200.00 403,200.00
Instalasi - -
Instalasi Ceiling speaker NYMHy 2x1,5 mm2 + PC conduit 8.00 Titik 86,400.00 691,200.00
Test 1.00 Lot 806,400.00 806,400.00
PEKERJAAN GROUNDING SISTEM ARUS LEMAH - -
Bak kontrol 40 x 40 cm 1.00 Unit 374,400.00 374,400.00
Grounding sistem kabel BC 50 mm tahanan max 1 ohm 1.00 Lot 1,065,600.00 1,065,600.00
Material Bantu 1.00 Lot 195,840.00 195,840.00
Testing & commisioning 1.00 Lot 172,800.00 172,800.00
- -
PEKERJAAN LIFT BARANG - -
LIFT BARANG 1.00 unit 58,752,000.00 58,752,000.00
- Kapasitas 2 ton - -
- Rangka Lift Plat Besi - -
- Pintu Lipat besi tiap lantai - -
- -
PEKERJAAN PENANGKAL PETIR - -
Penangkal petir light protection International (LPI) stormaster Radius 120 M 1.00 Unit 9,216,000.00 9,216,000.00
- Instalasi penangkal petir NYA Dia. 70mm 29.00 M' 43,200.00 1,252,800.00
- Tiang Penangkal petir pipa GIP medium 1.00 btg 449,280.00 449,280.00
- Instalasi sumur grounding BC 70 mm + bak kontrol 40x40cm 1.00 Lot 1,728,000.00 1,728,000.00
- Sumur grounding + Bak kontrol 40x40cm 1.00 Titik 691,200.00 691,200.00
- Material Bantu 1.00 Lot 576,000.00 576,000.00
test Comisioning Tahanan max 1 ohm 1.00 Lot 288,000.00 288,000.00
1,187,286,216.48
GRAND TOTAL