PEKERJAAN BANGUNAN
RUMAH TINGGAL WONOGIRI
Keterangan :
- Untuk pekerjaan tambahan yang belum tertera akan dibuat perhitungan dikemudian hari
- Apabila terjadi perubahan atau penambahan ukuran, maka perubahan volume akan disesuaikan opname dilapangan dan dimasukan ke perhitun
pekerjaan tambahan
Catatan yang blm termasuk, sbb :
1. Tali air , filter air, dan semprot tekstur
2. Kalau ada tambahan menyusul kemudian
2 LANTAI 2
a. Plesteran
-Plesteran 2,334.00
-Acian 1,983.00
-Sponengan 1,220.00
3 LANTAI 3
a. Plesteran
-Plesteran 370.00
-Acian 300.00
-Sponengan 249.00
4 LANTAI ATAP
a. Plesteran
-Plesteran 96.00
-Acian 96.00
-Sponengan 45.00
PEKERJAAN ELEKTRIKAL
I PLUMBING
A. INSTALASI AIR BERSIH
1. PERALATAN UTAMA AIR BERSIH
a. Pompa & peralatan penunjang
- Pompa Pendorong Grundfos 2
- Gate Valve, Double nepel, water mur Dia. 1" 12
- Header Pipa Besi 4" 1
- Floating Valve Dia. 1" 2
- Multi Media Filter (MMF) 3
- Ground Water Tank 1550 Lt 2
- Tangki Atas 1050 lt 2
+ ACI DINDING
m2 85,000.00 291,720,000
m2 55,000.00 162,250,000
m' 22,500.00 44,083,125
SUB TOTAL I 498,053,125
m2 85,000.00 198,390,000
m2 55,000.00 109,065,000
m' 22,500.00 27,450,000
SUB TOTAL II 334,905,000
m2 85,000.00 31,450,000
m2 55,000.00 16,500,000
m' 22,500.00 5,602,500
SUB TOTAL III 53,552,500
m2 85,000.00 8,160,000
m2 55,000.00 5,280,000
m' 22,500.00 1,012,500
SUB TOTAL IV 14,452,500
GRAND TOTAL 900,963,125.00
KTRIKAL
-
211.0 350,000.0 85,000.00 91,785,000.00
63.0 340,000.0 85,000.00 26,775,000.00
4.0 350,000.0 85,000.00 1,740,000.00
120,300,000.00
-
155.0 350,000.0 85,000.00 67,425,000.00
42.0 340,000.0 85,000.00 17,850,000.00
4.0 350,000.0 85,000.00 1,740,000.00
87,015,000.00
-
47.0 350,000.0 85,000.00 20,445,000.00
7.0 340,000.0 85,000.00 2,975,000.00
23,420,000.00
255,435,000.00
255,435,000.00
ls 60,000,000.00 60,000,000
127,500 3,060,000
350,000 4,550,000
2,663,500 2,663,500
127,500 612,000
850,000 850,000
511,700 511,700
SUB TOTAL IV 12,247,200.00
TOTAL B 505,557,791.31
GRAND TOTAL 723,355,867.68