400 m a) Hitunglah Q
b) Hitunglah Dimensi Saluran
c) Jika V bertambah 2x, Unsur yang lain tetap, parameter
C = 0.4 + 0.03 X apa yang berubah dan berapa persen perubahannya
I = 250 mm/jam (300 + 10 d) Jika Q bertambah 2x, Unsur yang lain tetap, parameter
St = 0.03 apa yang berubah dan berapa persen perubahannya

A PARAMETER YANG DIKETAHUI


L = (500 + 10 X)
Parameter Nilai
m
m=1 C 0.43 -
n = 0.0025 I 250 mm/jam
s = 0.005 St 0.03 (%)
V = 0.75 m/det L 510 meter
m 1 -
B n 0.0025 -
s 0.005 -
V 0.75 m/det

PERHITUNGAN LUAS AREA


Panjang Kemiringan
Panjang Lebar Luas Area
Petak Lahan (Lt) Lahan (St)
(m) (m) (Ha) (m)
A 310 400 12.4 506.063 0.03

PERHITUNGAN DEBIT
Qs = 0,00278 . Cs. Cr. I.A

2 tc Lt 0.77
Cs = to = 0.0197
2 tc + td St
Ls
td =
V
tc = to + td

Ket:
A= Luas area (Ha)
Ls = Panjang Saluran (m)
Lt = Panjang lahan terjauh (m)
St = Kemiringan lahan (%)
to = Waktu untuk mengalir dari permukaan lahan ke saluran terdekat (menit)
td = Waktu pengaliran dalam saluran (menit)
Waktu pengumpulan air
tc = (menit)
Cs = Koefisien penampungan
Cr = Koefisien pengaliran rata-rata
I= Intensitas curah hujan (mm/jam)
V= Kecepata rencana (m/dtk)
SALURAN A-B
Diketahui : A= 12.4 Ha = 124000 m^2
Ls = 510 m
Lt = 506.063 m
St = 0.03 %
V= 0.75 m/det
Cr = 0.43
I= 250 mm/jam = 6.94444E-05 m/det

Lt 0.77
to = 0.0197
St

506.063 0.77
to = 0.0197
0.03

to = 9.184 menit

Ls
td =
V
510
td =
0.75 x 60

td = 11.333 menit

tc = to + td
tc = 9.184 + 11.333
tc = 20.517 menit

2 tc
Cs =
2 tc + td
41.034
Cs =
41.034 + 11.333

Cs = 0.784

Cr = 0.43

Qs = 0,00278 . Cs. Cr. I.A


Qs = 0.00278 x 0.784 x 0.43 x 6.94444E-05 x 124000
3
Qs = 0.0081 m /dtk
Tabel Debit Rencana
Aliran Permukaan Aliran dalam Saluran Curah Hujan
Nama tc Luas (A) Q Rencana
Lt St to Ls V td Cs Cr I I
Saluran
(m) menit (m) m/dtk menit menit (mm/jam) (m/dtk) (m2) m3/dtk
Saluran
506.063 0.03 9.184 510 0.75 11.333 20.517 0.784 0.43 250 6.944E-05 124000 0.0081
A-B

PERHITUNGAN DIMENSI SALURAN


Saluran A-B
Dimensi Saluran Trapesium
Kecepatan Rencana (v) = 0.75 m/det
Koefisien Manning (n) = 0.0025
Kemiringan Talud Rencana (m:n) = 1 : 0.0025

1
h h
m

b
Penampang Ekonomis
b= 1.5 h

Luas Penampang Trapesium (A)


Q
A= dimana: A= (b+m.h) h
V

Keliling Basah (P)


P= b + 2h. 1 + m 2

Jari-Jari Hidrolik (R)


A (b+m.h) h
R=
P b + 2h. 1 + m 2

Dengan menggunakan rumus manning , Maka V (kecepatan) :


V= 1/n . R2/3 . S1/2

Dimana :
Q A
Q= ; R=
A P

Keterangan :
Q= debit (m3/dtk)
A= Luas (m2)
P= keliling basah (m)
R= jari-jari hidrolis
S= kemiringan saluran

2/3 1/2
Q 1 A
= . S
A n p

2/3 5/3 1/2


n.Q.P = A .S
5/3
A n. Q
= ................................................... ( 1 )
p2/3 S1/2

Untuk trapesium dimana b = 1.5 h, didapat:

A = (b + m.h).h misal m = 1

= ( 1.5h + 1 . h ) .h
2
= 2.5 h

b + 2h. 1 + m 2
p =
= 1.5h + 2h. 1 + 1
= 1.5 h + 2h . 2
= 4.328427 h
Dari Persamaan (1) Didapatkan :
A5/3 n. Q
2/3
=
p S1/2

( 2.5.h2 )5 1/3
n. Q
2
= ;n= 0.0025
(4.328.h) S1/2

97.6563 h10 0.0025 Q 3


=
18.7316 h2 S1/2

3
8
Q
5.2135 h = 1.5625E-08 1/2
S

3
8
Q
h 2.9971E-09
= S1/2

3/8
Q
h = 0.0860175
S1/2
h = 0.0381 m

b= 1.5 h
b= 1.5 x 0.0381
b= 0.05716 m

A= (b+m.h) h
A= 0.05716 + 1 0.0381 0.0381
A= 0.00363 m

b + 2h. 1 + m 2
P=
P= 0.05716 + 0.0762177 1 + 1
P= 0.16495

A 0.00363
R= =
P 0.16495
R= 0.0220

V Saluran = 1/n . R2/3 . S1/2


2/3 1/2
V Saluran = 400 x 0.0220 x 0.005
V Saluran = 2.221 m/det

Q Saluran = AxV
Q Saluran = 0.00363 x 2.221
Q Saluran = 0.0081 m3/dtk
Tabel Perhitungan Dimensi Saluran
V Dimensi Saluran V
Q maks w Q Saluran
Nama Saluran Rencana A h b n m P R S Saluran
m3/dtk m/dtk m2 m m m m / dtk m3/dtk
Saluran A-B 0.0081 0.75 0.00363 0.0381 0.0572 0.0025 1 0.16495 0.0220 0.005 0.310 2.221 0.0081

c) Jika V bertambah 2x, Unsur yang lain tetap, parameter apa yang berubah dan berapa persen perubahannya
Q= 0.0081 m3/dtk
A= 0.00363 m2
V= 2.221 m / dtk

V= 2.221 m / dtk
2V = 4.4429 m / dtk

sehingga lewat persamaan :


Q = A. V

Apabila Debit (Q) tetap maka parameter yang berubah ialah Dimensi Saluran(A)
Q 0.0081
A= =
V 2.221
A= 0.0036307 m2

Jadi parameter pertama yang berubah adalah A, nilai A untuk V awal sebesar = 0.0036307 m2
sedangkan nilai A untuk nilai V dua kali lebih besar adalah = 0.0018154 m2
Presentase perubahannya sebesar :
0.0036307 - 0.0018154
%= x 100
0.0018154
%= 100 %

Jadi Dimensi Saluran A presentase perubahannya 100 % jika nilai V dua kali lebih besar.

d) Jika Q bertambah 2x, Unsur yang lain tetap, parameter apa yang berubah dan
berapa persen perubahannya
Q= 0.0081 m3/dtk
A= 0.00363 m2
V= 2.221 m / dtk

Q= 0.0081 m3/dtk
2Q = 0.016131 m3/dtk

Apabila Dimensi Saluran (A) tetap maka parameter yang berubah ialah Kecepatan Aliran pada Saluran(V)
sehingga lewat persamaan :
Q = A.V
Q 0.0081
V= =
A 0.00363

V= 2.22144 m / dtk

Jadi parameter pertama yang berubah adalah V, nilai V untuk v awal sebesar = 2.22144
sedangkan nilai A untuk nilai Q dua kali lebih besar adalah = 4.442888

Presentase perubahannya sebesar :


2.2214442 - 4.4428885
%= x 100
4.4428885
%= -50 %

Jadi Kecepatan Aliran pada Saluran presentase perubahannya -50 % jika nilai Q dua kali lebih besar.