DAFTAR HARGA SATUAN UPAH

TAHUN 2017
HARGA
NO NAMA BARANG SPESIFIKASI SATUAN
(Rp.)
1 2 3 4 5

1 Mandor Hari 145,080.00


2 Kepala Tukang Hari 132,990.00
3 Tukang Politur Hari 120,900.00
4 Tukang Batu Hari 108,810.00
5 Tukang kayu Hari 120,900.00
6 Tukang Besi Hari 120,900.00
7 Tukang cat Hari 120,900.00
8 Tukang gali/buruh/ pekerja Hari 90,675.00
9 Tukang Listrik Hari 120,900.00
10 Tukang Pipa/ Tukang Ledeng Hari 120,900.00
11 Tukang Aspal Hari 120,900.00
12 Tukang masak Aspal/pekerja Hari 90,675.00
13 Pekerja Hari 90,675.00
14 Tukang Ukir Hari 120,900.00
15 Operator Hari 120,900.00
16 Pembantu Operator Hari 90,675.00
17 Mekanik Hari 120,900.00
18 Pembantu Mekanik Hari 90,675.00
19 Pasang Atap Alang-Alang Hari 120,900.00
20 Pasang Bata Gosok Dua Muka M2 359,074.00
21 Pasang Bata Gosok Satu Muka M2 192,836.00
22 Pasang Batu Paras Diukir M2 383,674.00
23 Pasang Patu Paras Siap Diukir M2 332,476.00
24 Tukang Bongkar Begesting Hari 108,810.00

Catatan :

Harga - harga hanya sebagai pedoman / pendukung


dalam perhitungan konstruksi ( tidak mengikat ).
UMP PROV. PAPUA BARAT 2017 2,421,500.00
SEKTOR PERTAMBANGAN MINYAK DAN GAS BUMI 3,141,000.00
SEKTOR PERTAMBANGAN KECUALI GALIAN C 2,660,000.00
SEKTOR KEHUTANAN, PERKEBUNAN, DAN
PERIKANAN 2,422,700.00
SEKTOR JASA KONSTRUKSI 2,619,000.00
Undang -undang no. 13 tahun 2003 tentang "ketenagakerjaan"
Jika dalam 1 hari bekerja selama 8 jam (5 hari kerja/ senin s/d jumat) maka dalam 1 bulan bekerja selama 21 hari
Jika dalam 1 hari bekerja selama 7 jam (6 hari kerja/ senin s/d sabtu) maka dalam 1 bulan bekerja selama 25 hari

Fakfak, APRIL 2017

PANITIA PENYUSUNAN STANDART HARGA SATUAN


TAHUN 2017

Sekretaris, Ketua,

RIZAL MINGGELE, ST LIZA NEIRASARI, ST


NIP. 19820701 200909 1 001 NIP. 19751016 200111 2 001

Mengetahui,
Plh. Kepala Dinas Pekerjaan Umum
Kabupaten Fakfak ,

YAKOBUS TANDUNG P, ST
NIP. 19720916 200111 1 001
PERHITU

UKURAN
NO JENIS/TYPE PAGAR Diameter
Melintang Panjang

A. PANEL PAGAR ELEKTROPLATING

1 Pagar BRC FP 90 EP 1,5 5,5 mm 90 cm 240 cm


2 Pagar BRC FP 90 EP 2,0 6,0 mm 90 cm 240 cm
3 Pagar BRC FP 120 EP 1,5 5,5 mm 120 cm 240 cm
4 Pagar BRC FP 120 EP 2,0 6,0 mm 120 cm 240 cm
5 Pagar BRC FP 150 EP 1,5 5,5 mm 150 cm 240 cm
6 Pagar BRC FP 150 EP 2,0 6,0 mm 150 cm 240 cm
7 Pagar BRC FP 175 EP 2,0 6,0 mm 175 cm 240 cm
8 Pagar BRC FP 175 EP 2,5 6,5 mm 175 cm 240 cm
9 Pagar BRC FP 190 EP 2,5 6,5 mm 190 cm 240 cm

B. TIANG ELEKTROPLATING TERMASUK MUR, BAUT DAN PENUTUP ATAS


NO TYPE TINGGI TIANG (M') TINGGI PANEL

1 P90 EP dia.1,5" 1.2 0.018 0,90 M'


2 P90 EP dia.2" 1.2 0.024 0,90 M'
3 P120 EP dia.1,5" 1.5 0.018 1,20 M'
4 P120 EP dia.2" 1.5 0.024 1,20 M'
5 P150 EP dia.1,5" 1.8 0.018 1,50 M'
6 P150 EP dia.2,0" 1.8 0.024 1,50 M'
7 P175 EP dia.2,0" 2.25 0.024 1,75 M'
8 P190 EP dia.1,0" 2.4 0.012 1,90 M'
PERHITUNGAN PAGAR BRC

HARGA PER PANEL DI TOKO SARANA MATERIAL SURABAYA Expedisi (SBI Jl. Demak Surabaya)

Jl. Gemblong Surabaya Telp. 031-3737649, Fax. 031-3710189 m3 Harga/m3

Rp 270,000 0.216 Rp 950,000


Rp 321,500 0.216 Rp 950,000
Rp 334,000 0.288 Rp 950,000
Rp 397,500 0.288 Rp 950,000
Rp 347,000 0.360 Rp 950,000
Rp 412,500 0.360 Rp 950,000
Rp 449,500 0.420 Rp 950,000
Rp 527,500 0.420 Rp 950,000
Rp 565,000 0.456 Rp 950,000

Harga Per Batang

119,500.00 0.0012 Rp 950,000


148,500.00 0.0022 Rp 950,000
143,000.00 0.0015 Rp 950,000
165,000.00 0.0027 Rp 950,000
164,500.00 0.0018 Rp 950,000
205,000.00 0.0033 Rp 950,000
246,000.00 0.0041 Rp 950,000
259,500.00 0.0011 Rp 950,000
Expedisi (SBI Jl. Demak Surabaya)
HARGA
Ongkos Kirim port to door +transport dan pikul

Rp 205,200 Rp 475,200.00
Rp 205,200 Rp 526,700.00
Rp 273,600 Rp 607,600.00
Rp 273,600 Rp 671,100.00
Rp 342,000 Rp 689,000.00
Rp 342,000 Rp 754,500.00
Rp 399,000 Rp 848,500.00
Rp 399,000 Rp 926,500.00
Rp 433,200 Rp 998,200.00

Rp 1,160 120,659.79
Rp 2,062 150,561.85
Rp 1,450 144,449.74
Rp 2,577 167,577.31
Rp 1,740 166,239.69
Rp 3,093 208,092.77
Rp 3,866 249,865.97
Rp 1,031 260,530.92
1/4 6" 0.222 KG/M' 2.442 11.00
5/16 8" 0.395 KG/M' 4.345 11.00
3/8 10" 0.617 KG/M' 6.787 11.00
1/2 12" 0.888 KG/M' 9.768 11.00
9/16 14" 1.208 KG/M' 13.288 11.00
5/8 16" 1.578 KG/M' 17.358 11.00
18" 2 KG/M' 22.000 11.00
3/4 19" 2.226 KG/M' 24.486 11.00

9.00

20" 2.464 KG/M' 27.104 11.00 ###


7/8 22" 2.984 KG/M' 32.824 11.00
24,000.00 9,828.01 9,828.01
43,000.00 9,896.43 9,896.43
67,500.00 9,945.48 9,945.48
89,000.00 9,111.38 9,111.38
- 10,053.00
174,500.00 10,053.00 7,363.64
162,000.00 7,363.64 6,641.09
- 62,839.03
8,977.00

6,641.09
-
PERHITUNGAN BESI BETON

TOKO SRIMAN TOKO LANGGENG TOKO KARYA TOKO SUMBER TOKO


NO JENIS BESI ISTILAH UKURAN KOEFISIEN TOKO DUTA JAYA TOKO ISTANA JAYA
DEPO BANGUNAN
PERKASA KALIURANG
SULITAMA BARU
1 BAJA BULAT 1/4 6' 0.222 Rp 23,000 Rp 30,000 Rp 35,000 Rp 28,000 Rp 36,000
1 BAJA BULAT 1/4 8' 0.395 Rp 43,000 Rp 68,000 Rp 49,000 Rp 47,000 Rp 55,000 Rp 60,000 Rp 55,000
3/8 10" 0.617 Rp 63,000 Rp 110,000 Rp 75,000 Rp 75,000 Rp 73,000 Rp 85,000 Rp 95,000 Rp 75,000
1/2 12" 0.888 Rp 93,000 Rp 160,000 Rp 100,000 Rp 105,000 Rp 105,000 Rp 100,000 Rp 155,000 Rp 115,000
13" 1.034 Rp 175,000
9/16 14" 1.208
15" 1.37
5/8 16" 1.578 Rp 167,000 Rp 190,000 Rp 175,000 Rp 185,000 Rp 239,000 Rp 185,000
18" 2
3/4 19" 2.226
20" 2.464
7/8 22" 2.984
24" 3.551
25" 3.853
1 26" 4.168

2 BATANG ULIR 10 0.56 Rp 180,000 Rp 110,000 Rp 72,000


12 0.995 Rp 105,000 Rp 125,000 Rp 95,000
16 1.56 Rp 180,000 Rp 190,000 Rp 175,000 Rp 195,000
19 2.25
22 3.04
25 3.98
29 5.04

HARGA RATA-RATA PER KG


SURYA MAS HARGA PER KG

Rp 28,000 Rp 12,285.01
Rp 46,000 Rp 12,169.16
Rp 73,000 Rp 11,852.72
Rp 103,000 Rp 11,784.51

Rp 185,000 Rp 10,913.04

Rp 298,000 Rp 12,170.22

Rp 19,588.74
Rp 9,897.97
Rp 195,000 Rp 10,897.44

average = Rp

Rp 12,395.43
1/4 6" 0.222 KG/M' 2.442 11.00 36,000.00 14,742.01

5/16 8" 0.395 KG/M' 4.345 11.00 84,600.00 19,470.66


36,000 3/8 10" 0.617 KG/M' 6.787 11.00 181,000.00 26,668.63
84,600 1/2 12" 0.888 KG/M' 9.768 11.00 259,000.00 26,515.15
181,000 9/16 14" 1.208 KG/M' 13.288 11.00 -
259,000 5/8 16" 1.578 KG/M' 17.358 11.00 331,500.00 19,097.82
18" 2 KG/M' 22.000 11.00 -
3/4 19" 2.226 KG/M' 24.486 11.00 -

331,500
9.00
298,000

120,667 1.236E-08
108,333
467,500
DAFTAR HARGA SATUAN BAHAN DAN UPAH
TAHUN 2018
A. Harga Satuan Bahan

NO NAMA BARANG SATUAN HARGA 1 HARGA 2 HARGA 3


1 2 3

FINISHING
1 Amplas lbr
2 Cat besi kg
3 Cat dasar kg
4 Cat emco kg
5 Cat menie besi kg
6 Cat menie kayu kg
7 Cat tembok Decolith kg
8 Cat tembok Dulux kg
9 Cat tembok Emco kg
10 Cat tembok Paragon kg
11 Cat tembok Toyopaint kg
12 Cat tembok Vinilex kg
13 Cat tembok Vinippaint kg
14 Dempul ltr
15 Kuas bh
16 Mild zak
17 Minyak cat ltr
18 Plamir kayu kg
19 Plamir tembok kg
20 Politur ultra ltr
21 Politur vernis ltr
22 Thiner A Bonanza ltr
23 Thiner B Spesial ltr

PENUTUP ATAP
24 Alang-alang panjang 2,4 meter lbr
25 Alluminium foil m2
26 Asbes Bubungan lbr
27 Asbes Gelombang 1,80 m x 0,80 m x 5 mm lbr
28 Asbes Gelombang 2,4 m x 1,05 m x 4 mm lbr
29 Asbes Rata 2 m x 1 m x 4 mm lbr
28 Atap metal Toratora 1 x 4 Extra m2
29 Atap metal Toratora 1 x 4 Premium m2
30 Atap metal Toratora 2 x 4 Extra m2
31 Atap metal Toratora 2 x 4 Premium m2
32 Atap metal Toratora 3 x 4 Extra m2
33 Atap metal Toratora 3 x 4 Premium m2
34 Atap metal Toratora 4 x 4 Extra m2
35 Atap metal Toratora 4 x 4 Premium m2
36 Bentala paras bh
37 Bentala tanah liat bh
38 Besi profil WF kg
39 Besi strip kg
40 Bubungan Biasa bj
41 Bubungan Karang Pilang (glazur) isi 3,5/m bj
42 Bubungan Karang Pilang isi 3,5/m bj
43 Bubungan Ngalayur isi 3,5/m bj
44 Bubungan Plentong bj
45 Bubungan Utama isi 3,5/m bj
46 Genteng Kanmuri (glazur) isi 14/m2 bj
47 Genteng Kodok Karang Pilang (Bambe) isi 20/m2 bj
48 Genteng Kodok Karang Pilang (Bisma) isi 20/m2 bj
49 Genteng Kodok Karang Pilang (Good Year) isi 20/m2 bj
50 Genteng Morando Abadi isi 18/m2 bj
51 Genteng Morando Jatiwangi isi 18/m2 bj
52 Genteng Morando Ngalayur isi 20/m2 bj
53 Genteng Plentong bj
54 Genteng plentong dicat bj
55 Genteng Plentong Jatiwangi isi 24/m2 bj
56 Ijuk kg
57 Ikut celedu paras bh
58 Ikut celedu tanah liat bh
59 Murda paras bh

Harga Barang dan Upah Hal. 10


NO NAMA BARANG SATUAN HARGA 1 HARGA 2 HARGA 3
1 2 3
60 Murda tanah liat bh
61 Seng BJLS 0,20 gelombang lbr
62 Seng BJLS 0,25 gelombang lbr
63 Seng BJLS 0,28 gelombang lbr
64 Seng BJLS 0,32 gelombang lbr
65 Seng Plat 3" x 6" BJLS 28 lbr
66 Sirap Jati bh
67 Tali Ijuk kg
68 Tali pengikat alang-alang ikat

PENGGANTUNG
69 Engsel kupu-kupu ps
70 Engsel nylon ps
71 Espagnoleth set
72 Grendel biasa bh
73 Grendel hararo bh
74 Kaca 3 mm bening m2
75 Kaca 5 mm bening m2
76 Kaca 6 mm bening m2
77 Kaca 8 mm bening m2
78 Kaca 10 mm bening m2
79 Kaca 12 mm bening m2
80 Kaca Es/Kapur 3 mm m2
81 Kaca Es/Kapur 5 mm m2
82 Kaca nako daun
83 Kaca nako teralis bening m2
84 Kaca ryben 3 mm m2
85 Kaca ryben 5 mm m2
86 Kait angin biasa bh
87 Kunci pintu TOP bh
88 Kunci pintu Union bh
89 Kunci pintu Vanesa bh
90 Kunci pintu Yale bh
91 Kunci pintu YURI bh
92 Kunci slot bh
93 Kunci tanam 2 slag bh

KAYU DAN PLAFOND


94 Bambu besar btg
95 Bambu sedang btg
96 Bambu kecil btg
97 Celling teak (0,62 x 2,40) m2 lbr
98 Eternit lbr
99 Formika lbr
100 Gedeg kulit kelas I m2
101 Gypsum Old lbr
102 Hard board MDF lbr
103 Kalsiboard 4,5 mm lbr
104 Kayu bekesting m3
105 Kayu bingkirai m3
106 Kayu bingkirai papan m3
107 Kayu dolken (pekerjaan sementara) btg
108 Kayu jati m3
109 Kayu jati papan m3
110 Kayu kamper balok m3
111 Kayu kamper usuk/reng m3
112 Kayu kamper papan m3
113 Kayu kruing balok m3
114 Kayu kruing usuk/reng m3
115 Kayu kruing papan m3
116 Kayu meranti balok m3
117 Kayu meranti usuk/reng m3
118 Kayu meranti papan m3
119 Kayu merbau m3
120 Kayu merbau papan m3
121 Kayu profil m1
122 Kayu seseh balok m3
123 Kayu seseh dolken m3
124 Lem Aibond kg
125 Lem Kayu ltr
126 List Gypsum standar m'

Harga Barang dan Upah Hal. 11


NO NAMA BARANG SATUAN HARGA 1 HARGA 2 HARGA 3
1 2 3
127 Minyak bekisting ltr
128 Multiplek 12 mm lbr
129 Multiplek 18 mm lbr
130 Multiplek 6 mm lbr
131 Multiplek 9 mm lbr
132 Plywood 12 mm lbr
133 Plywood 3 mm lbr
134 Plywood 4 mm lbr
135 Plywood 6 mm lbr
136 Plywood 9 mm lbr
137 Plywood aluminium lbr
138 Teak wood (0,9x2,00) m2 lbr
139 Teak wood (1,20x2,40) m2 lbr

KERAMIK
IKAD
140 Ikad (Keramik) Kw. I 10 x 20 cm m2
141 Ikad (Keramik) Kw. I 20 x 20 cm m2
142 Ikad (Keramik) Kw. I 20 x 30 cm m2
143 Ikad (Keramik) Kw. I 30 x 30 cm m2
144 Ikad (Keramik) Kw. I 40 x 40 cm m2
145 Ikad (Keramik) Kw. II 10 x 20 cm m2
146 Ikad (Keramik) Kw. II 20 x 20 cm m2
147 Ikad (Keramik) Kw. II 20 x 30 cm m2
148 Ikad (Keramik) Kw. II 30 x 30 cm m2
149 Ikad (Keramik) Kw. II 40 x 40 cm m2

INESA
150 Keramik 30 x 30 Kelas I (Onyx Phyrus Ruby Jade, P) m2
151 Keramik 30 x 30 Kelas I (Onyx Phyrus Ruby Jade, UP) m2
152 Keramik 30 x 30 Kelas I (Pearl Ghita Cat Eye, P) m2
153 Keramik 30 x 30 Kelas I (Pearl Ghita Cat Eye, UP) m2
154 Keramik 30 x 30 Kelas I (Sand Wheat Spruce Clay Charcoal, R) m2
155 Keramik 40 x 40 Kelas I (Corypha Roystonea Raphia, P) m2
156 Keramik 40 x 40 Kelas I (Onyx Phyrus Ruby Jade, P) m2
157 Keramik 40 x 40 Kelas I (Onyx Phyrus Ruby Jade, UP) m2
158 Keramik 40 x 40 Kelas I (Pearl Ghita Cat Eye, P) m2
159 Keramik 40 x 40 Kelas I (Pearl Ghita Cat Eye, UP) m2
160 Keramik 60 x 60 Kelas I (Corypha Roystonea Raphia, P) m2

ESSENZA
161 Keramik 30 x 30 Kelas I (Black Orchid, Coral Bell, P) m2
162 Keramik 30 x 30 Kelas I (Black Orchid, Coral Bell, UP) m2
163 Keramik 30 x 30 Kelas I (Pepper Grey Price Rubert Silver star, P) m2
164 Keramik 30 x 30 Kelas I (Pepper Grey Price Rubert Silver star, UP) m2
165 Keramik 40 x 40 Kelas I (Pepper Grey Price Rubert Silver star, P) m2
166 Keramik 40 x 40 Kelas I (Pepper Grey Price Rubert Silver star, UP) m2
167 Keramik 60 x 60 Kelas I (Pepper Grey Price Rubert Silver star, P) m2
168 Keramik Kelas I Domus m2
169 Keramik Kelas I Granity Imperiali m2
170 Keramik Kelas I Lavagna m2
171 Keramik Kelas I Mountain Peak m2

GARUDA
172 Keramik 20 x 20 kelas I Emboss Dasar Muda m2
173 Keramik 20 x 20 kelas I Emboss Dasar Tua m2
174 Keramik 20 x 20 kelas I Tesia m2
175 Keramik 20 x 20 kelas II Emboss Dasar Muda m2
176 Keramik 20 x 20 kelas II Emboss Dasar Tua m2
177 Keramik 20 x 20 kelas II Tesia m2
178 Keramik 20 x 25 kelas I Motif Dasar Medium m2
179 Keramik 20 x 25 kelas I Motif Dasar Muda m2
180 Keramik 20 x 25 kelas I Nuri Dark m2
181 Keramik 20 x 25 kelas I Polos m2
182 Keramik 30 x 30 kelas I Granity m2
183 Keramik 30 x 30 kelas I Motif Embose m2
184 Keramik 30 x 30 kelas II Granity m2
185 Keramik 30 x 30 kelas II Motif Embose m2
186 Keramik 40 x 40 kelas I Motif Dasar Muda m2
187 Keramik 40 x 40 kelas I Motif Dasar Muda m2

Harga Barang dan Upah Hal. 12


NO NAMA BARANG SATUAN HARGA 1 HARGA 2 HARGA 3
1 2 3
188 Keramik 40 x 40 kelas I Motif Embose m2
189 Keramik 40 x 40 kelas I Motif Granity Tua m2
190 Keramik 40 x 40 kelas I Motif Medium Color m2
191 Keramik 40 x 40 kelas I Motif Spesial Color m2
192 Keramik 50 x 50 kelas I m2

ASIA
193 Keramik 10 x 20 kelas I warna muda m2
194 Keramik 20 x 20 kelas I warna muda m2
195 Keramik 20 x 20 kelas I warna tua m2
196 Keramik 20 x 25 kelas I warna tua m2
197 Keramik 20 x 30 kelas I warna muda m2
198 Keramik 30 x 30 kelas I warna muda m2
199 Keramik 30 x 30 kelas I warna tua m2
200 Keramik 40 x 40 kelas I warna muda m2
201 Keramik 10 x 20 kelas II m2
202 Keramik 20 x 20 kelas II m2
203 Keramik 20 x 30 kelas II m2
204 Keramik 30 x 30 kelas II m2
205 Keramik 40 x 40 kelas II m2

MULIA
206 Keramik 10 x 20 cm kelas I m2
207 Keramik 20 x 20 cm kelas I m2
208 Keramik 20 x 30 cm kelas I m2
209 Keramik 30 x 30 cm kelas I m2
210 Keramik 40 x 40 cm kelas I m2
211 Keramik 10 x 20 cm kelas II m2
212 Keramik 20 x 20 cm kelas II m2
213 Keramik 20 x 30 cm kelas II m2
214 Keramik 30 x 30 cm kelas II m2
215 Keramik 40 x 40 cm kelas II m2

SANITAIR
201 Bak mandi fibre glass 70x70x66 cm bh
202 Bak mandi keramik bh
203 Floor Drain " TOTO TypeTx 1 Bv 1 " Square Flange " bh
204 Floor drain plastik bh
205 Floor drain stainless bh
206 Kloset duduk INA bh
207 Kloset duduk Amerika Standar bh
208 Kloset duduk " TOTO Type AVANTE CW 821 PJ / SW 821JP COMPLIT bh
209 Kloset duduk " TOTO Type AVANTE CW 821J"/ SW 821JP COMPLIT bh
210 Kloset duduk " TOTO Type AVANTE CW 823 J bh
211 Kloset duduk " TOTO Type CW 660J bh
212 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT bh
213 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT WARNA bh
214 Kloset duduk " TOTO Type CW 660J WARNA COMPLIT bh
215 Kloset duduk " TOTO Type CW 661JT1 BODI COMPLIT bh
216 Kloset duduk " TOTO Type CW 661JT1" / SW 661JP COMPLIT bh
217 Kloset duduk " TOTO Type CW 661JT1" / SW 784JP COMPLIT bh
218 Kloset jongkok " TOTO Type CE 6 COMPLIT bh
219 Kloset jongkok " TOTO Type CE 7 COMPLIT bh
220 Kloset porselin jongkok Kia (standar) bh
221 Kloset porselin jongkok Ina (standar) bh
222 Kran biasa bh
223 Kran SunEi bh
224 Kran TOTO T 205 LCSC bh
225 Kran TOTO T 205 MC bh
226 Kran TOTO T 23 B13 bh
227 Kran TOTO T 23 B13V7N bh
228 Kran TOTO T 26 - 13 bh
229 Kran TOTO TX 109 LH bh
230 Penyekat Urinoir " TOTO " Type A 100 " bh
231 Shower Spray " TOTO Tx 403SPIV ( Pastel Ivory ) bh
232 Soap holder " TOTO " Type S 6 N " bh
233 Seal tape bh
234 Urinoir " TOTO U 57 M bh
235 Urinoir " TOTO U 57 M BODI bh
236 Urinoir " TOTO UW 447 JT 1 " bh
237 Urinoir " TOTO UW 447 JT 1 BODI bh

Harga Barang dan Upah Hal. 13


NO NAMA BARANG SATUAN HARGA 1 HARGA 2 HARGA 3
1 2 3
238 Urinoir " TOTO UW 447 JT 1,M " bh
239 Urinoir " TOTO UW 447 JT 1,M "BODI bh
240 Wastagel KIA Standard bh
241 Wastagel KIA Warna bh
242 Wastafel Komplit " TOTO Tx " Type L 521V1A " bh
243 Wastafel Komplit top Counter" TOTO " Type CERABO LW 523 " bh

PAKU
244 Paku 10 cm kg
245 Paku kalsiboard kg
246 Paku list SQ kg
247 Paku pancing 60 x 230 kg
248 Paku reng/usuk SQ kg
249 Paku seng kg
250 Paku seng import bj
251 Paku skrup 1/2" kg
252 Paku skrup 2" kg
253 Paku skrup 3.5" kg
254 Paku sumbat 1/2" kg

PASIR, BATU, KERIKIL, BATA DAN PARAS


255 Bata gosok ex Tulikup bj
256 Bata pasang klas I bj
257 Batako kelas I bj
258 Batu kali m3
259 Batu karang m3
260 Batu lahar Singaraja m3
261 Batu pecah 5-7 cm (manual) m3
262 Batu pipih Singaraja m3
263 Glass block bj
264 Kerawang bh
265 Koral Beton m3
266 Limestone m3
267 Paras Batik bh
268 Paras Buahan bh
269 Paras Karang Bukit bh
270 Paras Kerobokan bh
271 Paras Malem bh
272 Paras Putih Bukit bh
273 Paras Silakarang tebal bh
274 Paras Silakarang tipis bh
275 Paras untuk pondasi bh
276 Pasir beton m3
277 Pasir pasang m3
278 Pasir urug m3
279 Sirtu m3
280 Tanah urug m3

PIPA
281 Pipa Galvanis 1/2" m1
282 Pipa Galvanis 3/4" m1
283 Pipa Galvanis 1 1/4" m1
284 Pipa Galvanis 1 1/2" m1
285 Pipa Galvanis 1" m1
286 Pipa Galvanis 1,5 BSA m1
287 Pipa Galvanis 2" m1
288 Pipa Galvanis 3" m1
289 Pipa Maspion AW 1 ljr
290 Pipa Maspion AW 1/2 ljr
291 Pipa Maspion AW 10 ljr
292 Pipa Maspion AW 1-1/2 ljr
293 Pipa Maspion AW 1-1/4 ljr
294 Pipa Maspion AW 12 ljr
295 Pipa Maspion AW 14 ljr
296 Pipa Maspion AW 16 ljr
297 Pipa Maspion AW 2 ljr
298 Pipa Maspion AW 2-1/2 ljr
299 Pipa Maspion AW 3 ljr
300 Pipa Maspion AW 3/4 ljr
301 Pipa Maspion AW 4 ljr
302 Pipa Maspion AW 5 ljr

Harga Barang dan Upah Hal. 14


NO NAMA BARANG SATUAN HARGA 1 HARGA 2 HARGA 3
1 2 3
303 Pipa Maspion AW 6 ljr
304 Pipa Maspion AW 8 ljr
305 Pipa Maspion C 1 ljr
306 Pipa Maspion C 1-1/2 ljr
307 Pipa Maspion C 1-1/4 ljr
308 Pipa Maspion C 2 ljr
309 Pipa Maspion C 2-1/2 ljr
310 Pipa Maspion C 3 ljr
311 Pipa Maspion C 3/4 ljr
312 Pipa Maspion C 4 ljr
313 Pipa Maspion C 5/8 ljr
314 Pipa Maspion D 10 ljr
315 Pipa Maspion D 1-1/2 ljr
316 Pipa Maspion D 1-1/4 ljr
317 Pipa Maspion D 12 ljr
318 Pipa Maspion D 14 ljr
319 Pipa Maspion D 16 ljr
320 Pipa Maspion D 2 ljr
321 Pipa Maspion D 2-1/2 ljr
322 Pipa Maspion D 3 ljr
323 Pipa Maspion D 4 ljr
324 Pipa Maspion D 5 ljr
325 Pipa Maspion D 6 ljr
326 Pipa Maspion D 8 ljr

SEMEN
327 Semen Bosowa 50 kg zak
328 Semen Gresik 40 kg zak
329 Semen Gresik 50 kg zak
330 Semen Tiga Roga 50 kg zak
331 Semen Tonasa 50 kg zak
332 Semen warna/semen grouting kg

BESI BETON DAN PAGAR


333 Besi beton kg
334 Kawat berduri roll
335 Kawat beton RRT kg
336 Pagar BRC asli T.120 diameter 6mm m'
337 Pagar BRC asli T.150 diameter 6mm m'
338 Pagar BRC asli T.175 diameter 7mm m'
339 Pagar BRC asli T.190 diameter 7mm m'
340 Pagar BRC asli T.90 diameter 6mm m'
341 Pagar HotDip Galvanized T.120 diameter 6mm m'
342 Pagar HotDip Galvanized T.150 diameter 7mm m'
343 Pagar HotDip Galvanized T.175 diameter 7mm m'
344 Pagar HotDip Galvanized T.190 diameter 7mm m'
345 Pagar HotDip Galvanized T.90 diameter 6mm m'
346 Tiang BRC asli T. 120 diameter 1 1/2" bh
347 Tiang BRC asli T. 150 diameter 2" bh
348 Tiang BRC asli T. 175 diameter 2" bh
349 Tiang BRC asli T. 190 diameter 2" bh
350 Tiang BRC asli T. 90 diameter 1 1/2" bh
351 Tiang HotDip Galvanized T. 120 diameter 1 1/2" bh
352 Tiang HotDip Galvanized T. 150 diameter 2" bh
353 Tiang HotDip Galvanized T. 175 diameter 2" bh
354 Tiang HotDip Galvanized T. 190 diameter 2" bh
355 Tiang HotDip Galvanized T. 90 diameter 1 1/2" bh

BAHAN LISTRIK
356 Saklar (Broco) bh
357 Stop Kontak bh
358 Fitting bh
359 Steker bh
360 Coaxial cable 5C - 75 ohm commscof m1
361 Kabel NYM 3 x 2.5 mm ex. Supreme m1
362 Kabel NYM 4 mm m1
363 Kabel telephone m1
364 Lampu pijar 10 Watt (Philip) bh
365 Lampu pijar 15 Watt (Philip) bh
366 Lampu pijar 25 Watt (Philip) bh
367 Lampu TL 10 Watt (10 Watt) bh

Harga Barang dan Upah Hal. 15


NO NAMA BARANG SATUAN HARGA 1 HARGA 2 HARGA 3
1 2 3
368 Lampu TL 20 Watt (10 Watt) bh
369 Lampu TL 25 Watt (10 Watt) bh
370 Pipa clipsal 20 mm bt
371 Pipa flexible clipsal 20 mm m1
372 Sock clipsal 20 mm bj
373 Tee dos clipsal 20 mm bh
374 Klem clipsal 20 mm bj
375 Inbow dos plastik clipsal E 157 P bj

BUIS BETON
376 Buis beton 10 x 75 bh
377 Buis beton 15 x 75 bh
378 Buis beton 20 x 75 bh
379 Buis beton 25 x 75 bh
380 Buis beton 30 x 75 bh
381 Buis beton 50 x 75 bh

PAVING
382 Paving 10 x 20 cm tebal 6 cm K225 m2
383 Paving 10 x 20 cm tebal 6 cm K300 m2
384 Paving 10 x 20 cm tebal 6 cm standard m2
385 Paving 10 x 20 cm tebal 8 cm K225 m2
386 Paving 10 x 20 cm tebal 8 cm K300 m2
387 Paving 10 x 20 cm tebal 8 cm standard m2
388 Paving Tiga Berlian tebal 6 cm K225 m2
389 Paving Tiga Berlian tebal 8 cm K225 m2
390 Kanstein Bulat 15x20x50 cm K225 m1
391 Kanstein Jumbo 15x30x50 cm K225 m1
392 Kanstein Super 17x25x60 cm K225 m1
393 Grass Block m2
394 Koral sikat zak

LAIN-LAIN
395 Dugul batu hitam 50 x 50 x 200 unit
396 Dugul batu hitam 60 x 70 x 250 unit
397 Dugul batu hitam 70 x 70 x 250 unit
398 Padmasari batu hitam 50 x 50 x 200 unit
399 Padmasari batu hitam 70 x 70 x 250 unit
400 Padmasari batu hitam 65 x 75 x 225 unit

Denpasar, April 2010


Kepala Dinas Cipta Karya
Kabupaten Badung

Ir. I Dewa Made Apramana, MM


Pembina Tk. I
NIP. 195904211987111002

Harga Barang dan Upah Hal. 16


AN UPAH

HARGA 4 HARGA 5 RATA-RATA


4

Harga Barang dan Upah Hal. 17


HARGA 4 HARGA 5 RATA-RATA
4

Harga Barang dan Upah Hal. 18


HARGA 4 HARGA 5 RATA-RATA
4

Harga Barang dan Upah Hal. 19


HARGA 4 HARGA 5 RATA-RATA
4

Harga Barang dan Upah Hal. 20


HARGA 4 HARGA 5 RATA-RATA
4

Harga Barang dan Upah Hal. 21


HARGA 4 HARGA 5 RATA-RATA
4

Harga Barang dan Upah Hal. 22


HARGA 4 HARGA 5 RATA-RATA
4

Harga Barang dan Upah Hal. 23


DAFTAR HARGA SATUAN BAHAN DAN UPAH
DAFTAR HARGA ALAT
TAHUN ANGGARAN 2018
PT. SINAR SAMA ATLANTIK ALAM
NO JENIS ALAT BERSAMA BANGUN
MANDIRI SEJATI NUR SYAFIRA
1 2 3 4 5

1 Asphal Mixing Flant


Spesifikasi 60-80 T
Merk AZP-100
Tahun Pembelian 2005
Harga Pembelian 9,135,000,000.00
Kondisi Baik
Harga Sewa 9,493,000/ Jam

2 Aspal Finisher
Spesifikasi 10 Ton
Merk LTD-450
Tahun Pembelian 2013
Harga Pembelian 1,150,000,000.00
Kondisi Baik
Harga Sewa 643,000/Jam

3 Asphal Sprayer
Spesifikasi 850 L
Merk ASP-100 L
Tahun Pembelian 2012
Harga Pembelian 324,600,000.00
Kondisi Baik
Harga Sewa 136,000/Jam

4 Bulldozer 100-150 HP
Spesifikasi 215 HP/1950 RPM D85ESS-2
Merk KOMATSU D85E-SS-2 Komatsu / Cat
Tahun Pembelian 2,010 2014
Harga Pembelian 2,172,060,000.00 2,055,000,000.00 3,6 m
Kondisi Baik Baik Rekondisi
Harga Sewa 1.100.000 / Jam 901,000/jam 155.000.000/ Bln

5 Bulldozer 100-150 HP
Spesifikasi 75
Merk Cat
Tahun Pembelian 2016
Harga Pembelian 4,2 m
Kondisi Rekondisi
Harga Sewa 155.000.000/ Bln

6 Compressor 4000-6500 L/M


Spesifikasi 5000 CPM(L/M)
Merk Airman PDS
Tahun Pembelian 2,013
Harga Pembelian 324,600,000.00
Kondisi Baik
Harga Sewa 254,000/Jam

7 Concrete Mixer 0.3-0.6 m3


Spesifikasi 500 L
Merk
Tahun Pembelian
Harga Pembelian 13,881,000
Kondisi Baik
Harga Sewa 101,000/jam

8 Crane 10 - 15 Ton
Spesifikasi 10-15 T Valpinsser
Merk SPK32080
Tahun Pembelian 2016
Harga Pembelian 1,488,000,000.00 2,000,000,000
Kondisi Baik Baru
Harga Sewa 721,000/jam 12.000.000/Hari

Harga Barang dan Upah Hal. 24


PT. SINAR SAMA ATLANTIK ALAM
NO JENIS ALAT BERSAMA BANGUN
MANDIRI SEJATI NUR SYAFIRA
1 2 3 4 5
9 Dump Truk 3-4 Ton
Spesifikasi Colt Diesel Fe Super HD 3,5T 5TON
Merk Mitsubhisi HINO 300
Tahun Pembelian 2012
Harga Pembelian 360,000,100.00 350,000,000.00 2008
Kondisi Baik Baik Baik
Harga Sewa 410.000 / Jam 352,000/Jam 20.000.000 /bulan

10 Dump Truk 3-4 M3


Spesifikasi 10 T 10 T
Merk Hino Hino Dutro HINO 130 HD
Tahun Pembelian 2011 2015 2016
Harga Pembelian 660,000,000.00 500,000,000.00 330 JT
Kondisi Baik Baik Baru
Harga Sewa 760.000/jam 594,000/Jam 20.000.000/Bln

11 Excavator 80-140 HP
Spesifikasi 246 HP (184 KW)/ 1950 RPM 0,9 M3 Zaxis 210 F
Merk Komatsu PC300 SE-8 Catepilar Hitachi
Tahun Pembelian 2012 2015 2015
Harga Pembelian 2,438,161,000.00 1,700,000,000.00 1,8 m
Kondisi Baik Baik Baik
Harga Sewa 1.330.000 / Jam 763,000/jam 110.000.000,00 /Bln

12 Flat Bed Truck 3-4 M3 10 T


Spesifikasi
Merk
Tahun Pembelian
Harga Pembelian 475,200,000
Kondisi Baik
Harga Sewa 588,000/jam

13 Generator Set
Spesifikasi 135 KVA 30 KVA
Merk Mitsubhisi
Tahun Pembelian 2013
Harga Pembelian 324,000,000.00 85 jt
Kondisi BAIK Baik
Harga Sewa 527,000/Jam 30.000.000/Bln

14 Motor Grader >100 HP


Spesifikasi 135 HP / 2900 RPM 100HP 75 D 511A
Merk Komatsu GD511A-1 Changlin Komatsu
Tahun Pembelian 2010 2012 2013
Harga Pembelian 1,519,346,400.00 1,350,000,000.00 1.8 m
Kondisi Baik Baik Baik
Harga Sewa 780.000/ Jam 680,000/jam 20.000.000/hari/8 jam

15 Track Loader 75-100 HP


Spesifikasi 0,8 M3
Merk
Tahun Pembelian
Harga Pembelian 900,000,000.00
Kondisi Baik
Harga Sewa 420,000/jam

16 Wheel Loader 1.0-1.6 m3


Spesifikasi 110 HP / 2400 RPM 1,5 m2
Merk Komatsu Changlin
Tahun Pembelian 2012
Harga Pembelian 3,947,900,000.00 770,000,000.00
Kondisi Baik Baik
Harga Sewa 1.250.000 / Jam 447,000/jam

17 Three Wheel Roller 6 - 8 T


Spesifikasi 8T
Merk
Tahun Pembelian
Harga Pembelian 350,000,000
Kondisi Baik
Harga Sewa 249,000/jam

Harga Barang dan Upah Hal. 25


PT. SINAR SAMA ATLANTIK ALAM
NO JENIS ALAT BERSAMA BANGUN
MANDIRI SEJATI NUR SYAFIRA
1 2 3 4 5

18 Tandem Roller 6-8 T


Spesifikasi 8T
Merk Sakai Biteli
Tahun Pembelian 2,012 2,012
Harga Pembelian 725,000,000.00 700,000,000.00
Kondisi Baik Baik
Harga Sewa 420.000/ Jam 398,000/jam

19 Tire Roller 8-10 T


Spesifikasi 10 T
Merk Sakai TS 200 Sakai
Tahun Pembelian 2012 2012
Harga Pembelian 940,000,000.00 1,000,000,000.00
Kondisi Baik Baik
Harga Sewa 540.000/ Jam 6,500,000/Jam

20 Vibrator Roller 5-8 T


Spesifikasi Single Drum Compactor 7T 11 Ton SV 512-D
Merk Bomag BW211D-40 Sakai V Sakai
Tahun Pembelian 2012 2011 2011
Harga Pembelian 800,250,000.00 750,000,000.00 1.1 m
Kondisi Baik Baik Baik
Harga Sewa 610.000 / Jam 410,000/jam 70.000.000/Bln

21 Concrete Vibrator
Spesifikasi
Merk
Tahun Pembelian
Harga Pembelian 7,000,000
Kondisi baik
Harga Sewa 57,000/jam

22 Stone Chrusher
Spesifikasi 50T/Jam
Merk
Tahun Pembelian
Harga Pembelian 1,500,000,000
Kondisi Baik
Harga 927,000/jam

23 Water Tanker 3000-4500 l


Spesifikasi 4000 L 4500 Ltr
Merk Hino
Tahun Pembelian 2010
Harga Pembelian 550,000,000.00 280 jt
Kondisi Baik Baik
Harga Sewa 402,000/jam 400.000/trip

24 Pedestrian Roller
Spesifikasi 835T
Merk
Tahun Pembelian
Harga Pembelian 150,000,000.00
Kondisi Baik
Harga Sewa 105,000/jam

25 Tamper
Spesifikasi 121 T
Merk
Tahun Pembelian
Harga Pembelian 25,000,000.00
Kondisi Baik
Harga Sewa 65000/jam

Harga Barang dan Upah Hal. 26


PT. SINAR SAMA ATLANTIK ALAM
NO JENIS ALAT BERSAMA BANGUN
MANDIRI SEJATI NUR SYAFIRA
1 2 3 4 5

26 Jack hammer
Spesifikasi 20 Ton, AOLF 210
Merk Asce
Tahun Pembelian 2015
Harga Pembelian 350,000,000.00 250,000,000
Kondisi Baik Baik
Harga Sewa 124,000/jam 3.000.000 / Hari

27 Fulvi Mixer
Spesifikasi
Merk
Tahun Pembelian
Harga Pembelian 900,000,000.00
Kondisi baik
Harga Sewa 124,000/jam

28 Concrete Pump
Spesifikasi 8m2
Merk
Tahun Pembelian
Harga Pembelian 112,500,000.00
Kondisi baik
Harga Sewa 291,000/jam

29 Trailer 20 TON
Spesifikasi
Merk
Tahun Pembelian
Harga Pembelian 750,000,000.00
Kondisi baik
Harga Sewa 609,000/Jam

30 Pile Drive + Hammer


Spesifikasi 2,5 T
Merk
Tahun Pembelian
Harga Pembelian 875,000,000.00
Kondisi baik
Harga Sewa 312,000/Jam

31 Crane On Track 35 TON


Spesifikasi 2,5 T
Merk
Tahun Pembelian
Harga Pembelian 850,000,000.00
Kondisi baik
Harga Sewa 519,000/jam

32 Welding Set
Spesifikasi 250 Amp
Merk
Tahun Pembelian
Harga Pembelian 17,500,000.00
Kondisi baik
Harga Sewa 133,000/jam

33 Bore Pile Machine


Spesifikasi 2000 m
Merk
Tahun Pembelian
Harga Pembelian 2,250,000,000.00
Kondisi baik
Harga Sewa 900,000/jam

34 Asphalt Liquid Mixer


Spesifikasi 1000 L

Harga Barang dan Upah Hal. 27


PT. SINAR SAMA ATLANTIK ALAM
NO JENIS ALAT BERSAMA BANGUN
MANDIRI SEJATI NUR SYAFIRA
1 2 3 4 5
Merk
Tahun Pembelian
Harga Pembelian 15,000,000.00
Kondisi baik
Harga Sewa 53,000/Jam

35 Trailer 15 ToN
Spesifikasi
Merk
Tahun Pembelian
Harga Pembelian 450,000,000.00
Kondisi baik
Harga Sewa 625,000/Jam

36 Cold Recycler
Spesifikasi 2,2 m
Merk
Tahun Pembelian
Harga Pembelian 19,500,000,000.00
Kondisi baik
Harga Sewa 6,966,000/Jam

37 Hot Recycler
Spesifikasi 3m
Merk
Tahun Pembelian
Harga Pembelian 29,250,000,000.00
Kondisi baik
Harga Sewa 8,251,000/jam

38 Aggregat ( Chip ) Spreader


Spesifikasi 3.5 m
Merk
Tahun Pembelian
Harga Pembelian 395,000,000.00
Kondisi baik
Harga Sewa 619,000/jam

39 Aspalt Distribution
Spesifikasi 4000 L
Merk
Tahun Pembelian
Harga Pembelian 395,000,000.00
Kondisi baik
Harga Sewa 430,000/Jam

40 Split Form Paver


Spesifikasi 2,5 m
Merk
Tahun Pembelian
Harga Pembelian 1,340,000,000.00
Kondisi baik
Harga Sewa 619,000/jam

41 Concrete Pan Mixer


Spesifikasi 600 L
Merk
Tahun Pembelian
Harga Pembelian 1,000,000,000.00
Kondisi baik
Harga Sewa 746,000/ Jam

42 Concrete Breaker
Spesifikasi 20 m3/jam
Merk
Tahun Pembelian
Harga Pembelian 500,000,000.00
Kondisi baik
Harga Sewa 954,000/jam

Harga Barang dan Upah Hal. 28


PT. SINAR SAMA ATLANTIK ALAM
NO JENIS ALAT BERSAMA BANGUN
MANDIRI SEJATI NUR SYAFIRA
1 2 3 4 5

43 Asphalt Tanker
Spesifikasi 4000 L
Merk
Tahun Pembelian
Harga Pembelian 500,000,000.00
Kondisi baik
Harga Sewa 629,000/Jam

44 Cement Tanker
Spesifikasi 4000 L
Merk
Tahun Pembelian
Harga Pembelian 500,000,000.00
Kondisi baik
Harga Sewa 586,000/jam

45 Concrete Mixer (350)


Spesifikasi 350 L
Merk
Tahun Pembelian
Harga Pembelian 35,000,000.00
Kondisi baik
Harga Sewa 97,000/Jam

46 Vibrating Ramer
Spesifikasi 80 Kg
Merk
Tahun Pembelian
Harga Pembelian 20,000,000.00
Kondisi baik
Harga Sewa 60,000/jam

47 Truk Mixer
Spesifikasi 5m
Merk
Tahun Pembelian
Harga Pembelian 750,000,000.00
Kondisi baik
Harga Sewa 724,000/jam

48 Bore Pile Machine DIA 60


Spesifikasi 60 cm
Merk
Tahun Pembelian
Harga Pembelian 1,170,000,000.00
Kondisi baik
Harga Sewa 739,000/jam

49 Crane On Track 75-100


Spesifikasi 75 Ton
Merk
Tahun Pembelian
Harga Pembelian 900,000,000.00
Kondisi baik
Harga Sewa 716,000/ jam

50 Blending Equipment
Spesifikasi 30 Ton
Merk
Tahun Pembelian
Harga Pembelian 500,000,000.00
Kondisi baik
Harga Sewa 264,000/ Jam

Harga Barang dan Upah Hal. 29


PT. SINAR SAMA ATLANTIK ALAM
NO JENIS ALAT BERSAMA BANGUN
MANDIRI SEJATI NUR SYAFIRA
1 2 3 4 5

Asphalt Liquid Mixer ( KAP


51 20000 )
Spesifikasi 20 Liter
Merk
Tahun Pembelian
Harga Pembelian 15,000,000.00
Kondisi baik
Harga Sewa 132,000/ jam

Fakfak,12 Februari 2018


PANITIA PENYUSUNAN STANDARD HARGA SATUAN TAHUN 2018

Sekretaris, Ketua,

RIZAL MINGGELE, ST LIZA NEIRASARI, ST


NIP. 19820701 200909 1 001 NIP. 19751016 200111 2 001

Mengetahui,
Kepala Dinas PU, Penataan Ruang, Perumahan Rakyat
dan Kawasan Permukiman
Kabupaten Fakfak ,

SAMAUN DAHLAN, S. Sos, MAP


NIP. 19681005 199108 1 002

Harga Barang dan Upah Hal. 30


PEMERINTAH KABUPATEN FAKFAK
DINAS PU, PENATAAN RUANG, PERUMAHAN RAKYAT
DAN KAWASAN PERMUKIMAN
Jl. Achmad Yani No. 08 Fakfak, Telp. (0956) 22320 - 22709

DAFTAR HARGA SATUAN BAHAN DAN UPAH


TAHUN ANGGARAN 2017
NAMA TOKO : ............................... `

NO NAMA BARANG SATUAN


NO NAMA BARANG SATUAN HARGA SURVEYDISTRIK
1 2 3 4 ###
###
FINISHING
1 Amplas lbr ###
2 Amplas mtr ###
3 Amplas kain lbr ###
4 Kawat has m' ###
5 Kawat has Plastik lbr ###
6 Cat besi (Hamerton) Kaleng 1 kg kg ###
7 Cat besi (Avian) Kaleng 1 kg kg ###
8 Cat Besi (polibest) kaleng 1 kg kg ###
9 Cat Meni Besi/dasar (Polibest) Kaleng 0,8 kg kg ###
10 Cat Meni Besi/dasar (Yoko) Kaleng 0,8 kg kg ###
11 Cat kayu+Besi/dasar (polibest) kaleng 0.8 kg kg ###
12 Cat kayu+Besi/dasar (Yoko) kaleng 0.8 kg kg ###
13 Cat Kayu Yoko kg ###
14 Cat menie besi (Glotex) Kaleng 1 kg kg ###
15 Cat menie besi (Yoko) Kaleng 1 kg kg ###
16 Cat menie besi (Delmas) Kaleng 1 kg kg ###
17 Cat menie besi (Avian) Kaleng 1 kg kg ###
18 Cat menie kayu (polibest) 0,8 kg kg ###
19 Cat menie kayu (Avian) 1kg kg ###
20 Cat tembok Decolith kg ###
21 Cat tembok (Jotun) kg ###
22 Cat tembok Grahalux 5 Kg kg ###
23 Cat tembok Paragon 5 Kg kg ###
24 Cat tembok (aries) 5 kg kg ###
25 Cat tembok Toyopaint kg ###
26 Cat tembok (vitex) Kaleng 5 kg kg ###
27 Cat tembok (vitex) Kaleng 4.5 kg kg ###
28 Cat tembok Vinippaint kg ###
29 Cat monilex klg ###
30 Dempul kayu (polibest) 0,8 Kg kg ###
31 Dempul kayu (Pedang) 0.8 kg kg ###
32 Dempul kayu (Impra) 1 kg liter ###
33 Dempul kayu Avian Yoko 1 kg liter ###
34 Kuas Besar 5 inch bh ###
35 Kuas Besar 4 inch bh ###
36 Kuas Sedang 3 inch bh ###
37 Kuas roll 10" bh ###
38 Kuas roll 4" bh ###
39 Kuas Kecil 2 inch bh ###
40 Mild zak ###
41 Minyak cat/Thiner A Kaleng 0,8 liter ltr ###
42 Plamir kayu 1kg kg ###
43 Plamir tembok 5 kg merk B0y0 kg ###
44 Plamir tembok 5 kg merk lion kg ###
45 Plamir tembok 5 kg merk Paragon kg ###
46 Plamir tembok 5 kg kg ###
47 Politur (Boyo) kaleng 1 liter ltr ###
48 Politur (Joly) kaleng 1 liter ltr ###
49 Politur (vernis) kaleng 1 liter kg ###
50 Politur (india) kaleng 1 liter ltr ###
51 Thiner A kaleng 1/2 liter Ltr ###

Harga Satauan Bahan dan Upah Hal. 31


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA SURVEYDISTRIK
1 2 3 4 ###
52 Thiner A Avian kaleng 1 liter ltr ###
53 Thiner A kaleng 1 liter Ltr ###
54 Thiner B Avian kaleng 1 liter ltr ###
55 Thiner B Super kaleng 1 liter Ltr ###
56 Thiner Super 5 kg kg ###
57 Thiner A Spesial 5 kg kg ###
58 Impra 1 Liter ltr ###
59 impra clear / sanding 1 l Ltr ###
60 impra wood stain 1 l Ltr ###
###
BAHAN BAKAR MINYAK ###
1 Premium ###
2 Minyak Tanah ###
3 Minyak Solar ###
4 Minyak Diesel ###
5 Minyak Bakar ###
6 Gemuk /Stempel 20 kg kg ###
7 Gemuk /Stempel 16 kg kg ###
###
PENUTUP ATAP ###
1 Alang-alang panjang 2,4 meter lbr ###
2 Alluminium foil m2 ###
3 Asbes Bubungan lbr ###
4 Asbes Gelombang 1,80 m x 0,80 m x 5 mm lbr ###
5 Asbes Gelombang 2,4 m x 1,05 m x 4 mm lbr ###
6 Asbes Rata 2 m x 1 m x 4 mm lbr ###
7 Besi profil WF kg ###
8 Besi strip 1kg kg ###
9 Bubungan Biasa bj ###
10 Bubungan Plentong bj ###
11 Genteng plentong dicat bj ###
12 Genteng Plentong bj ###
13 Ijuk m3 ###
14 Tali Ijuk Kg ###
15 Formite/Penjaga Jarak Bekisting/Spacer Bh ###
16 Seng BJLS 0,20 gelombang lbr ###
17 Seng BJLS 0.20 gelombang gajah berlian lbr ###
18 Seng BJLS 0,25 gelombang lbr ###
19 Seng BJLS 0,28 gelombang lbr ###
20 Seng BJLS 0,30 gelombang lbr ###
21 Seng Plat BJLS 30 lebar 28 cm lbr ###
22 Seng Plat BJLS 30 lebar 30 cm m' ###
23 Seng Plat BJLS 30 lebar 38 cm m' ###
24 Seng Plat BJLS 30 lebar 40 cm m' ###
25 Seng Plat BJLS 30 lebar 44 cm m' ###
26 Seng Plat BJLS 20 lebar 30 cm m' ###
27 Seng Plat BJLS 20 lebar 28 cm m' ###
28 Seng Plat BJLS 20 lebar 40 cm m' ###
29 Seng Plat BJLS 30 pintu lbr ###
30 Seng Plat BJLS 20 pintu lbr ###
31 Seng plastik gelombang besar tebal lbr ###
32 Seng plastik gelombang kecil tebal lbr ###
33 Seng plastik gelombang besar tipis lbr ###
34 Seng Fiber gelombang besar tebal lbr ###
35 Sirap Jati bh ###
36 AT roof Bjls 30, 0,8x0,8 lbr ###
37 Rainbouw roof Bjls 30, 0,3x1,2 lbr ###
38 Bubungan rainbouw roof Bjls 30, 1,2 m' Bh ###
39 Multiroof BJ 300 lbr ###
40 Bubungan multiroof Bh ###
41 Igi roof 0,2 uk. 0,8x0,8 m' lbr ###
42 Sakura roof BJ 30 lbr ###

PENGGANTUNG
1 Engsel jendela biasa ps ###
2 Engsel jendela biasa Merk King ps ###
3 Engsel jendela biasa merk king 3' ps ###

Harga Satauan Bahan dan Upah Hal. 32


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA SURVEYDISTRIK
1 2 3 4 ###
4 Engsel jendela merek King 4" ps ###
5 Engsel kupu-kupu jendela biasa ps ###
6 Engsel kupu-kupu jendela biasa 3" ps ###
7 Engsel Jendela Bagus Kuningan ps ###
8 Engsel jendela bagus kuningan modem 4' ps ###
9 Engsel jendela bagus kuningan 4' ps ###
10 Engsel kupu-kupu pintu biasa ps ###
11 Engsel kupu-kupu pintu biasa 4" ps ###
12 Engsel kupu-kupu pintu biasa 4cmx3cmx3mm merk jezz ps ###
13 Engsel kupu-kupu pintu biasa AFC 4cmx3cmx3mm merk kin ps ###
14 Engsel kupu-kupu pintu biasa 4cmx3cmx3mm merk viper ps ###
15 Engsel nylon ps ###
16 Espagnoleth set ###
17 Grendel kecil biasa bh ###
18 Grendel kecil bagus bh ###
19 Grendel kecil spring knife brabus/ses bh ###
20 Grendel kecil biasa 3" bh ###
21 Grendel kecil bagus 2" bh ###
22 Grendel kecil spring knife bh ###
23 Grendel besar 12" bh ###
24 Grendel besar bh ###
25 Grendel hararo bh ###
26 Kaca 3 mm bening m2 ###
27 Kaca 3 mm bening 153x122 m2 m2 ###
28 Kaca 5 mm bening m2 ###
29 Kaca 5 mm bening 200 x 100 m2 ###
30 Kaca 5 mm bening 153x122 m2 m2 ###
31 Kaca 6 mm bening 153x122 m2 m2 ###
32 Kaca 8 mm bening 153x122 m2 m2 ###
33 Kaca 10 mm bening m2 ###
34 Kaca 12 mm bening m2 ###
35 Kaca Es/Kapur 3 mm m2 ###
36 Kaca Es/Kapur 5 mm m2
37 Kaca nako bening bh ###
38 Kaca nako rayben bh ###
39 Kaca ryben 3 mm 153x122 cm m2 ###
40 Kaca ryben 5 mm 153x122 cm m2 ###
41 Kaca Ryben 5 mm 185 x 122 cm m2 ###
42 Cermin 3 mm 153x122 cm m2 ###
43 Cermin 5 mm 183 x 122 m2 ###
44 Kait angin biasa ps ###
45 Kait angin bagus bh ###
46 Kunci pintu Delmanao bh ###
47 Kunci pintu Zeis bh ###
48 Kunci pintu TOP bh ###
49 Kunci pintu Union bh ###
50 Kunci pintu Cap Kuda bodi kecil bh ###
51 Kunci pintu Cap Kuda bodi besar bh ###
52 Kunci pintu Royal bh ###
53 Kunci pintu Yale bh ###
54 Kunci pintu vanessa bh ###
55 Kunci pintu Kodai bh ###
56 Kunci pintu Sapphire bh ###
57 Kunci slot kecil HPP bh ###
58 Kunci slot sedang HPP bh ###
59 Kunci slot besar HPP bh ###
60 Kunci slot kecil bh ###
61 Kunci slot kecil ATS bh ###
62 Kunci slot sedang bh ###
63 Kunci slot sedang ATS bh ###
64 Kunci slot besar bh ###
65 Kunci Silinder bh ###
66 Kunci tanam 2 slag Biasa bh ###
67 Kunci tanam 2 slag Bagus bh ###
68 Kunci tanam 2 slag bagus merk Azzuro bh ###
69 Kunci tanam 2 slag bagus merk Giardano bh ###

Harga Satauan Bahan dan Upah Hal. 33


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA SURVEYDISTRIK
1 2 3 4 ###
###
KAYU DAN PLAFOND ###
1 Bambu besar Ukuran 4 m btg ###
2 Bambu sedang Ukuran 4 m btg ###
3 Bambu kecil Ukuran 4 m btg ###
4 Celling teak (0,62 x 2,40) m2 lbr ###
5 Eternit lbr ###
6 Formika lbr ###
7 Gedeg kulit kelas I m2 ###
8 Gypsum Old lbr ###
9 Hard board MDF lbr ###
10 Kalsiboard 4,5 mm lbr ###
11 Kayu bekesting / kayu putih m3 ###
12 Kayu Besi 10 x 10, panjang 4 m' m3 ###
13 Kayu Besi 5 x 10, panjang 4 m' m3 ###
14 Kayu Besi 5 x 5, panjang 4 m' m3 ###
15 Kayu Besi 2.5 x 20, panjang 4 m' m3 ###
16 Kayu Besi 10 x 10, panjang 3 m' m3 ###
17 Kayu Besi 6x 12, panjang 4 m' m3 ###
18 Reng Kayu Besi 2 x 3 m3 ###
19 Kayu Besi 4x 25, panjang 4 m' m3 ###
20 Papan Kayu besi 2,5 x 25, panjang 4 m' m3 ###
21 Papan Cor/Papan Kayu Putih m3 ###
22 Kayu Matoa 10 x10, panjang 4 m' m3 ###
23 Kayu Matoa 5 x 10, panjang 4 m' m3 ###
24 Kayu Matoa 5 x 5, panjang 4 m' m3 ###
25 Kayu Matoa m3 ###
26 Kayu Merbau m3 ###
27 Papan Kayu Matoa 2,5 x 25, panjang 4 m' m3 ###
28 Papan Kayu Matoa 2,5 x 20, panjang 4 m' m3 ###
29 Papan Kayu Matoa 3 x 25, panjang 4 m' m3 ###
30 Kayu bingkirai m3 ###
31 Kayu bingkirai papan m3 ###
32 Kayu dolken (pekerjaan sementara) btg ###
33 Kayu jati m3 ###
34 Kayu jati papan m3 ###
35 Kayu kamper balok m3 ###
36 Kayu kamper usuk/reng m3 ###
37 Kayu kamper papan m3 ###
38 Kayu kruing balok m3 ###
39 Kayu kruing usuk/reng m3 ###
40 Kayu kruing papan m3 ###
41 Kayu meranti balok m3 ###
42 Kayu meranti usuk/reng m3 ###
43 Kayu meranti papan m3 ###
44 Kayu merbau papan m3 ###
45 Kayu profil m1 ###
46 Kayu seseh balok m3 ###
47 Kayu seseh dolken m3 ###
48 Lem Aibond 450 gr gr ###
49 Lem Aibond 700 gr gr ###
50 Lem Kayu (fox) kg ###
51 Lem Kayu (fox) besar klg ###
52 Lem Kayu (Fox) 0.6 klg ###
53 Lem Kayu (Fox) klg ###
54 Lem Kayu (Fox) Rajawali kg ###
55 List Gypsum standar m' ###
56 Minyak bekisting ltr ###
57 Tripleks 2.7 mm lbr ###
58 Tripleks 3 mm Lbr ###
59 Tripleks 3 mm semi meranti Lbr ###
60 Tripleks 3.6 mm lbr ###
61 Plywood 3 mm Lbr ###
62 Tripleks 4 mm Lbr ###
63 Tripleks 4 mm semi meranti Lbr ###
64 Plywood 4 mm lbr ###

Harga Satauan Bahan dan Upah Hal. 34


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA SURVEYDISTRIK
1 2 3 4 ###
65 Trileks 5 mm lbr ###
66 Multiplek 6 mm lbr ###
67 Plywood 6 mm lbr ###
68 Multiplek 9 mm lbr ###
69 Plywood 9 mm lbr ###
70 Multiplek 12 mm lbr ###
71 Plywood 12 mm lbr ###
72 Multiplek 18 mm lbr ###
73 Plywood aluminium lbr ###
74 Teak wood (0,9x2,20) m2 lbr ###
75 Teak wood (1,20x2,40) m2 lbr ###
###
KERAMIK ###
IKAD ###
1 Ikad (Keramik) Kw. I 10 x 20 cm m2 ###
2 Ikad (Keramik) Kw. I 20 x 20 cm m2 ###
3 Ikad (Keramik) Kw. I 20 x 30 cm m2 ###
4 Ikad (Keramik) Kw. I 30 x 30 cm m2 ###
5 Ikad (Keramik) Kw. I 40 x 40 cm m2 ###
6 Ikad (Keramik) Kw. II 10 x 20 cm m2 ###
7 Ikad (Keramik) Kw. II 20 x 20 cm m2 ###
8 Ikad (Keramik) Kw. II 20 x 30 cm m2 ###
9 Ikad (Keramik) Kw. II 30 x 30 cm m2 ###
10 Ikad (Keramik) Kw. II 40 x 40 cm m2 ###
###
INESA ###
1 Keramik 30 x 30 Kelas I (Onyx Phyrus Ruby Jade, P) m2 ###
2 Keramik 30 x 30 Kelas I (Onyx Phyrus Ruby Jade, UP) m2
3 Keramik 30 x 30 Kelas I (Pearl Ghita Cat Eye, P) m2
4 Keramik 30 x 30 Kelas I (Pearl Ghita Cat Eye, UP) m2
5 Keramik 30 x 30 Kelas I (Sand Wheat Spruce Clay Charcoal m2
6 Keramik 40 x 40 Kelas I (Corypha Roystonea Raphia, P) m2
7 Keramik 40 x 40 Kelas I (Onyx Phyrus Ruby Jade, P) m2
8 Keramik 40 x 40 Kelas I (Onyx Phyrus Ruby Jade, UP) m2
9 Keramik 40 x 40 Kelas I (Pearl Ghita Cat Eye, P) m2
10 Keramik 40 x 40 Kelas I (Pearl Ghita Cat Eye, UP) m2
11 Keramik 60 x 60 Kelas I (Corypha Roystonea Raphia, P) m2

ESSENZA
1 Keramik 30 x 30 Kelas I (Black Orchid, Coral Bell, P) m2
Keramik 30 x 30 Kelas I (Black Orchid, Coral Bell, UP) m2
2
Keramik 30 x 30 Kelas I (Pepper Grey Price Rubert Silver
m2
3 star, P)
Keramik 30 x 30 Kelas I (Pepper Grey Price Rubert Silver
m2
4 star, UP)
Keramik 40 x 40 Kelas I (Pepper Grey Price Rubert Silver
m2
5 star, P)
Keramik 40 x 40 Kelas I (Pepper Grey Price Rubert Silver
m2
6 star, UP)
Keramik 60 x 60 Kelas I (Pepper Grey Price Rubert Silver
m2
7 star, P)
8 Keramik Kelas I Domus m2
9 Keramik Kelas I Granity Imperiali m2
10 Keramik Kelas I Lavagna m2
11 Keramik Kelas I Mountain Peak m2

GARUDA ###
1 Keramik 20 x 20 kelas I Emboss Dasar Muda m2 ###
2 Keramik 20 x 20 kelas I Emboss Dasar Tua m2 ###
3 Keramik 20 x 20 kelas I Tesia m2 ###
4 Keramik 20 x 20 kelas II Emboss Dasar Muda m2 ###
5 Keramik 20 x 20 kelas II Emboss Dasar Tua m2 ###
6 Keramik 20 x 20 kelas II Tesia m2 ###
7 Keramik 20 x 25 kelas I Motif Dasar Medium m2 ###
8 Keramik 20 x 25 kelas I Motif Dasar Muda m2 ###

Harga Satauan Bahan dan Upah Hal. 35


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA SURVEYDISTRIK
1 2 3 4 ###
9 Keramik 20 x 25 kelas I Nuri Dark m2 ###
10 Keramik 20 x 25 kelas I Polos m2 ###
11 Keramik 30 x 30 kelas I Granity m2 ###
12 Keramik 30 x 30 kelas I Motif Embose m2 ###
13 Keramik 30 x 30 kelas II Granity m2 ###
14 Keramik 30 x 30 kelas II Motif Embose m2 ###
15 Keramik 40 x 40 kelas I Motif Dasar Muda m2 ###
16 Keramik 40 x 40 kelas I Motif Dasar Muda m2 ###
17 Keramik 40 x 40 kelas I Motif Embose m2 ###
18 Keramik 40 x 40 kelas I Motif Granity Tua m2 ###
19 Keramik 40 x 40 kelas I Motif Medium Color m2 ###
20 Keramik 40 x 40 kelas I Motif Spesial Color m2 ###
21 Keramik 50 x 50 kelas I m2 ###
22 Granito 60 x 60 m2 ###

ASIA ###
1 Keramik 10 x 10 kelas I warna muda m2 ###
2 Keramik 10 x 20 kelas I warna muda m2 ###
3 Keramik 20 x 20 kelas I warna muda m2 ###
4 Keramik 20 x 20 kelas I warna tua m2 ###
5 Keramik 20 x 25 kelas I warna tua m2 ###
6 Keramik 20 x 30 kelas I warna muda m2 ###
7 Keramik 30 x 30 kelas I warna muda m2 ###
8 Keramik 30 x 30 kelas I warna tua m2 ###
9 Keramik 40 x 40 kelas I warna muda m2 ###
10 Keramik 40 x 40 warna platinum m2 ###
11 Keramik 10 x 20 kelas II m2 ###
12 Keramik 20 x 20 kelas II m2 ###
13 Keramik 20 x 30 kelas II m2 ###
14 Keramik 30 x 30 kelas II m2 ###
15 Keramik 40 x 40 kelas II m2 ###
###
MULIA ###
1 Keramik 10 x 20 cm kelas I m2 ###
2 Keramik 20 x 20 cm kelas I m2 ###
3 Keramik 20 x 30 cm kelas I m2 ###
4 Keramik 30 x 30 cm kelas I m2 ###
5 Keramik 40 x 40 cm kelas I m2 ###
6 Keramik 10 x 20 cm kelas II m2 ###
7 Keramik 20 x 20 cm kelas II m2 ###
8 Keramik 20 x 30 cm kelas II m2 ###
9 Keramik 30 x 30 cm kelas II m2 ###
10 Keramik 40 x 40 cm kelas II m2 ###
###
PICASSO ###
1 Ikad Keramik KW 1 20 x 20 cm m2 ###
2 Ikad Keramik KW 1 20 x 25 cm m2 ###
3 Ikad Keramik KW 1 30 x 30 cm m2 ###
4 Ikad Keramik KW 1 40 x 40 cm m2 ###
###
SANITAIR ###
1 Bak mandi fibre glass 70x70x66 cm biasa bh ###
2 Bak mandi fibre glass 70x70x66 cm sudut bh ###
3 Bak mandi keramik 50x50 bh ###
4 Floor Drain " TOTO TypeTx 1 Bv 1 " Square Flange " bh ###
5 Floor drain plastik bh ###
6 Floor drain stainless bh ###
7 Floor drain plastik oda bh ###
8 Kloset duduk DATA komplit bh ###
9 Kloset duduk INA Komplit bh ###
10 Kloset duduk INA standard bh ###
11 Kloset duduk Amerika Standar bh ###
Kloset duduk " TOTO Type AVANTE CW 821 PJ / SW
12 bh ###
821JP COMPLIT
Kloset duduk " TOTO Type AVANTE CW 821J"/ SW 821JP
13 bh ###
COMPLIT

Harga Satauan Bahan dan Upah Hal. 36


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA SURVEYDISTRIK
1 2 3 4 ###
14 Kloset duduk " TOTO Type AVANTE CW 823 J bh ###
15 Kloset duduk " TOTO Type CW 660J bh ###
16 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT bh ###
Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT
17 bh ###
WARNA
18 Kloset duduk LOLO warna COMPLIT bh ###
19 Kloset duduk " TOTO Type CW 661JT1 BODI COMPLIT bh ###

Kloset duduk " TOTO Type CW 661JT1" / SW 661JP


20 bh ###
COMPLIT
Kloset duduk " TOTO Type CW 661JT1" / SW 784JP
21 bh ###
COMPLIT
22 Kloset jongkok " TOTO Type CE 6 COMPLIT bh ###
23 Kloset jongkok " TOTO bh ###
24 Kloset jongkok " TOTO Type CE 7 COMPLIT Set ###
25 Kloset porselin jongkok Avena (standar) bh ###
26 Kloset porselin jongkok Kia (standar) bh ###
27 Kloset porselin jongkok VITO (standar) bh ###
28 Kloset porselin jongkok Ina (standar) bh ###
29 Kloset porselin jongkok America (standar) bh ###
30 Kloset porselin jongkok DUTY bh ###
31 Kloset porselin jongkok DATA bh ###
32 Kloset porselin jongkok ROSI bh ###
33 Kloset porselin jongkok CHELSEA bh ###
34 Kran air 3/4 biasa dari besi bh ###
35 Kran air 3/4 biasa dari plastik bh ###
36 Kran air 1/2 biasa dari besi bh ###
37 Kran SunEi bh ###
38 Kran TOTO T 205 LCSC bh ###
39 Kran TOTO T 205 MC bh ###
40 Kran TOTO T 23 B13 bh ###
41 Kran TOTO T 23 B13V7N bh ###
42 Kran TOTO T 26 - 13 bh ###
43 Kran TOTO TX 109 LH bh ###
44 Kran washtafel bh ###
45 Kran cuci piring bh ###
46 Penyekat Urinoir " TOTO " Type A 100 " bh ###
47 Shower Spray " TOTO Tx 403SPIV ( Pastel Ivory ) bh ###
48 Shower Spray biasa bh ###
49 Shower Spray TOTO thx -48-2B bh ###
50 Shower Spray TOTO bh ###
51 Soap holder " TOTO " Type S 6 N " bh ###
52 Seal tape Besar bh ###
53 Seal tape kecil bh ###
54 Urinoir " TOTO U 57 M bh ###
55 Urinoir " TOTO U 57 M BODI bh ###
56 Wastagel KIA Standard bh ###
57 Wastagel INA bh ###
58 Wastafel Komplit " TOTO Tx " Type L 521V1A " bh ###
59 Wastafel Komplit top Counter" TOTO " Type CERABO LW bh ###
60 Washtafel LOLO bh ###
61 Wastafel KIA Standar 2 (Lubang) bh ###
61 Washtafel cuci tangan kecil (Standard) bh ###
62 Washtafel cuci tangan besar (Standard) bh ###
63 Washtafel cuci piring 2 lubang bh ###
64 Washtafel cuci piring 1 lubang bh ###
65 Bak cuci piring single besar bh ###
66 Bak cuci piring double besar bh ###
67 Bak cuci piring single kecil bh ###
###
PAKU ###
1 Paku 3 kg ###
1 Paku 4 kg ###
1 Paku 5 biasa kg ###
2 Paku 5 putih kg ###
3 Paku 7 biasa kg ###
4 Paku 7 putih kg ###

Harga Satauan Bahan dan Upah Hal. 37


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA SURVEYDISTRIK
1 2 3 4 ###
5 Paku 8 putih kg ###
6 Paku 9 putih kg ###
7 Paku 10 biasa kg ###
8 Paku 10 putih kg ###
9 Paku 12 biasa kg ###
10 Paku 12 putih kg ###
11 Paku 14 biasa kg ###
12 Paku 15 biasa kg ###
13 Paku 15 putih kg ###
14 Paku kalsiboard kg ###
25 Paku list SQ kg ###
16 Paku pancing 60 x 230 kg ###
17 Paku reng/usuk SQ kg ###
18 Paku seng 1Kg kg ###
19 Paku seng import bj ###
20 Paku skrup 1/2" Kg ###
21 Paku skrup 2" Kg ###
22 Paku skrup 3.5" bh ###
23 Paku skrup 1" kg ###
24 Paku beton kg ###
25 Paku tripleks kg ###
###
PASIR, BATU, KERIKIL, BATA DAN PARAS ###
1 Bata gosok ex Tobacco bj ###
2 Bata Merah 5 x 11 x 22 cm bj ###
3 Bata Ringan/ Bataco bj ###
4 Bata Ringan/ Bataco 8 x 20 x 60 bj ###
5 Bata Ringan/ Bataco 10 x 20 x 60 bj ###
6 Batu tela bj ###
7 Batu gunung/ belah m3 ###
8 Batu karang m3 ###
9 Batu lahar Singaraja m3 ###
10 Batu Pecah 2-3 m3 ###
11 Batu Pecah 0.5-1/ciping m3 ###
12 Batu Pecah 10-19 m3 ###
13 Batu pipih Singaraja m3 ###
14 Glass block 20cmx20cm bj ###
15 Glass block 30cmx30cm bh ###
16 Roster Keramik 30cmx30cm bh ###
17 Koral Beton m3 ###
18 Limestone m3 ###
19 Paras Batik bh ###
20 Paras Buahan bh ###
21 Paras Karang Bukit bh ###
22 Paras Kerobokan Tebal 5 bh ###
23 Paras Malem bh ###
24 Paras Putih Bukit bh ###
25 Paras Silakarang tebal bh ###
26 Paras Silakarang tipis bh ###
27 Paras untuk pondasi bh ###
28 Pasir halus m3 ###
29 Pasir kasar m3 ###
30 Pasir sedot m3 ###
31 Sirtu m3 ###
32 Tanah urug m3 ###
33 Filler/abu batu m3 ###
34 Aspal drum ###
###
PIPA ###
1 Pipa Galvanis 1/2" Medium A (tebal) m1 ###
2 Pipa Galvanis 1/2" Medium B (tipis) m1 ###
3 Pipa Galvanis 1/2' medium B (sedang) m1 ###
4 Pipa Galvanis 3/4" Medium A (tebal) m1 ###
5 Pipa Galvanis 3/4" Medium A sedang m1 ###
6 Pipa Galvanis 3/4" Medium B m1 ###
7 Pipa Galvanis 1 1/4" m1 ###
8 Pipa Galvanis 1 1/2" m1 ###

Harga Satauan Bahan dan Upah Hal. 38


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA SURVEYDISTRIK
1 2 3 4 ###
9 Pipa Galvanis 1 1/2 " M.B m1 ###
10 Pipa Galvanis 1" m1 ###

Harga Satauan Bahan dan Upah Hal. 39


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA SURVEYDISTRIK
1 2 3 4 ###
11 Pipa Galvanis 1" MA m1 ###
12 Pipa Galvanis 1" MB m1 ###
13 Pipa Galvanis 1,5 BSA m1 ###
14 Pipa Galvanis 2" m1 ###
15 Pipa Galvanis 2" MA m1 ###
16 Pipa Galvanis 2" MB m1 ###
17 Pipa Galvanis 3" m1 ###
18 Pipa Galvanis 3" MA m1 ###
19 Pipa Galvanis 3" MB m1 ###
20 Pipa Maspion AW 1 m1 ###
21 Pipa Maspion AW 1/2 m1 ###
22 Pipa Maspion AW 10 m1 ###
23 Pipa Maspion AW 1-1/2/Wincon m1 ###
24 Pipa Maspion D 1-1/2/Wincon m1 ###
25 Pipa Maspion AW 1-1/4 / Wincoon m1 ###
26 Pipa Maspion AW 12 m1 ###
27 Pipa Maspion AW 14 m1 ###
28 Pipa Maspion AW 16 m1 ###
29 Pipa Maspion AW 2/ Wincon m1 ###
30 Pipa Maspion D 2 / Wincon m1 ###
31 Pipa Maspion AW 2-1/2 m1 ###
32 Pipa Maspion D 2-1/2 m1 ###
33 Pipa Maspion AW 3 / Wincon m1 ###
34 Pipa Maspion AW 3/4 m1 ###
35 Pipa Maspion AW 4 m1 ###
36 Pipa Maspion D 4" m1 ###
37 Pipa Maspion AW 5 m1 ###
38 Pipa Maspion AW 6 m1 ###
39 Pipa Maspion AW 8 m1 ###
40 Pipa Maspion C 1 m1 ###
41 Pipa Maspion C 1-1/2 m1 ###
42 Pipa Maspion C 1-1/4 m1 ###
43 Pipa Maspion C 2 m1 ###
44 Pipa Maspion C 2-1/2 m1 ###
45 Pipa Maspion C 3 m1 ###
46 Pipa Maspion C 3/4 m1 ###
47 Pipa Maspion C 4 m1 ###
48 Pipa Maspion C 5/8 m1 ###
49 Pipa Maspion D 10 m1 ###
50 Pipa Maspion D 1-1/2 m1 ###
51 Pipa Maspion D 1-1/4 m1 ###
52 Pipa Maspion D 12 m1
53 Pipa Maspion D 14 m1 ###
54 Pipa Maspion D 16 m1 ###
55 Pipa Maspion D 2 m1 ###
56 Pipa Maspion D 2-1/2 m1 ###
57 Pipa Maspion D 3 m1 ###
58 Pipa Maspion D 4 m1 ###
59 Pipa Maspion D 5 m1 ###
60 Pipa Maspion D 6 m1 ###
61 Pipa Maspion D 8 m1 ###
62 Elbo 1/2" PVC bh ###
63 Elbo 3/4" PVC bh ###
64 Elbo PVC 4" bh ###
65 Elbo PVC 3" bh ###
66 Elbo PVC 2,5" bh ###
67 Selang hipres 1" m1 ###
68 Selang hipres 2" m1 ###
69 Selang hipres 1,5" m1 ###
70 Selang hipres 0,5" m1 ###
71 Selang spiral 2" m1 ###
###
SEMEN ###
1 Semen Gresik 40 kg kg ###
2 Semen Tiga Roga 40 kg kg ###
3 Semen Tonasa 40 kg kg ###
4 Semen Bosowa 40 kg kg ###
5 Semen warna/semen grouting kg ###

Harga Satauan Bahan dan Upah Hal. 40


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA SURVEYDISTRIK
1 2 3 4 ###
6 Semen putih kg ###

Harga Satauan Bahan dan Upah Hal. 41


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA SURVEYDISTRIK
1 2 3 4 ###
###
BESI BETON DAN PAGAR ###
1 Besi beton kg ###
2 Besi beton Kg ###
3 Besi Beton Ulir ###
Besi Beton Ulir 16 mm btg ###
Besi Beton Ulir 12 mm btg ###
Besi Beton Ulir 10 mm btg ###
4 Besi Beton ###
Diameter 5.5 mm btg ###
Diameter 6 mm btg ###
Diameter 8 mm btg ###
Diameter 9 mm btg ###
Diameter 10 mm btg ###
Diameter 12 mm btg ###
Diameter 16 mm btg ###
Diameter 19 mm btg ###
Diameter 22 mm btg ###
Diameter 25 mm btg ###
5 Besi Siku 4x4 btg ###
6 Besi Siku 5 X 5 btg ###
7 Besi Siku Lubang btg ###
8 Besi UN 60 btg ###
9 Besi UN 80 btg ###
10 Besi Holous 20 x 40 btg ###
11 Besi Holous 40 x 40 btg ###
12 Kawat Bronjong ukuran 2 m kg ###
13 Kawat Bronjong ukuran 2,7 m kg ###
14 Kawat Bronjong ukuran 3 m kg ###
15 Kawat Bronjong ukuran 3,4 m kg ###
16 Kawat Bronjong ukuran 4 m kg ###
17 Kawat berduri roll ###
18 Kawat beton RRT 1 Kg kg ###
19 Kawat ram m' ###
20 Kawat nyamuk m' ###
21 Kawat ayakan m' ###
22 Kawat Las RB Dos ###
23 Kawat Las 1kg kg ###
24 Kawat Ikat kg ###
25 Kawat Harmonika besar mtr ###
26 Kawat Harmonika sedang mtr ###
27 Pagar BRC FP 90 EP 1,5 Panil ###
28 Pagar BRC FP 90 EP 2,0 Panil ###
29 Pagar BRC FP 120 EP 1,5 Panil ###
30 Pagar BRC FP 120 EP 2,0 Panil ###
31 Pagar BRC FP 150 EP 1,5 Panil ###
32 Pagar BRC FP 150 EP 2,0 Panil ###
33 Pagar BRC FP 175 EP 2,0 Panil ###
34 Pagar BRC FP 175 EP 2,5 Panil ###
35 Pagar BRC FP 190 EP 2,5 Panil ###
36 P90 EP dia.1,5" bh ###
37 P90 EP dia.2" bh ###
38 P120 EP dia.1,5" bh ###
39 P120 EP dia.2" bh ###
40 P150 EP dia.1,5" bh ###
41 P150 EP dia.2,0" bh ###
42 P175 EP dia.2,0" bh ###
43 P190 EP dia.1,0" bh ###
###
BAHAN LISTRIK ###
1 Saklar (Broco) double bh ###
2 Saklar (Broco) engkle bh ###
3 Saklar (Oni) double bh ###
4 Saklar (Oni) engkle bh ###
5 Saklar tunggal philip bh ###
6 Saklar ganda philip bh ###
7 Stop kontak philip bh ###
8 Stop Kontak (Oni) bh ###

Harga Satauan Bahan dan Upah Hal. 42


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA SURVEYDISTRIK
1 2 3 4 ###
9 Stop Kontak (Oni) 2 lubang bh ###

Harga Satauan Bahan dan Upah Hal. 43


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA SURVEYDISTRIK
1 2 3 4 ###
10 Stop Kontak (Oni) 3 lubang bh ###
11 Stop Kontak (Oni) 4 lubang bh ###
12 Fitting Biasa bh ###
13 Fitting keramik bh ###
14 Steker biasa bh ###
15 Steker Broco bh ###
16 Coaxial cable 5C - 75 ohm commscof m1 ###
17 Kabel NYM 3 x 2.5 mm ex. Supreme m1 ###
18 Kabel NYM 3 x 2.5 mm ex. Eterna m1 ###
19 Kabel NYM 4 mm m1 ###
20 Kabel NYA 4mm rol ###
21 Kabel telephone m1 ###
22 Lampu 8 Watt (Philip) bh ###
23 Lampu 8 Watt (Philip) Tornado bh ###
24 Lampu 11 Watt (Philip) bh ###
25 Lampu 14 Watt (Philip) bh ###
26 Lampu 18 Watt (Philip) bh ###
27 Lampu 23 Watt (Philip) bh ###
28 Lampu 24 Watt (Philip) tornado bh ###
29 Lampu 15 Watt (Philip) tornado bh ###
30 Lampu downlight 3,5" bh ###
31 Lampu downlight 4" bh ###
32 Lampu downlight 5" bh ###
33 Isolasi unibelt bh ###
34 Pipa clipsal 20 mm bt ###
35 Pipa flexible clipsal 20 mm m1 ###
36 Sock clipsal 20 mm bj ###
37 Tee dos clipsal 20 mm bh ###
38 Klem clipsal 0,5 " bj ###
39 Inbow dos plastik clipsal E 157 P bj ###
###
PAVING ###
1 Paving 10 x 20 cm tebal 6 cm K225 m2
2 Paving 10 x 20 cm tebal 6 cm K350 m2
3 Paving 10 x 20 cm tebal 8 cm K225 m2
4 Paving 10 x 20 cm tebal 8 cm K350 m2
5 Paving 10 x 20 cm tebal 8 cm K425 m2
6 Paving 20 x 20 cm tebal 6 cm K225 m2
7 Paving 20 x 20 cm tebal 6 cm K350 m2
8 Paving 20 x 20 cm tebal 8 cm K225 m2
9 Paving 20 x 20 cm tebal 8 cm K350 m2
10 Paving 20 x 20 cm tebal 8 cm K425 m2
11 Paving 20 x 20 cm tebal 10 cm K225 m2
12 Paving 20 x 20 cm tebal 10 cm K350 m2
13 Paving 20 x 20 cm tebal 10 cm K425 m2
14 Paving Tiga Berlian tebal 6 cm K225 m2
15 Kanstein Bulat (P:50,T:30,La:10,Lb:16 cm K225) m1
16 Kanstein Jumbo (P:50,L:15,T:30 cm K225) m1
17 Kanstein Segi Lima Jumbo (P:50,L:15, T:40 cm K225) m1
18 Grass Block 36 X 54 cm tebal 9 cm K 225 m2 ###
19 Koral Sikat zak

LAIN-LAIN ###
1 Dugul batu hitam 50 x 50 x 200 unit
2 Dugul batu hitam 60 x 70 x 250 unit
3 Dugul batu hitam 70 x 70 x 250 unit
4 Padmasari batu hitam 50 x 50 x 200 unit
5 Padmasari batu hitam 70 x 70 x 250 unit
6 Padmasari batu hitam 65 x 75 x 225 unit
7 Karpet plastik m2 ###
8 Talang PVC P= 4M', L=8" bentuk kotak buah ###
9 Talang PVC P= 4M', L=6" bentuk bulat buah ###
10 Talang PVC P= 4M', L=40" bentuk bulat buah ###
11 Talang PVC P= 4M', L=40 mm" bentuk kotak buah ###
12 Talang PVC P= 4M', L: 8' buah ###

Harga Satauan Bahan dan Upah Hal. 44


PEMERINTAH KABUPATEN FAKFAK
DINAS PU, PENATAAN RUANG, PERUMAHAN RAKYAT
DAN KAWASAN PERMUKIMAN
Jl. Achmad Yani No. 08 Fakfak, Telp. (0956) 22320 - 22709

DAFTAR HARGA SATUAN UPAH


TAHUN 2018
###
HARGA ###
NO NAMA BARANG SPESIFIKASI SATUAN
(Rp.) ###
1 2 3 4 5 ###
1 Mandor Hari 159,275.00###
2 Kepala Tukang Hari 154,100.00###
3 Tukang Politur Hari 148,350.00###
4 Tukang Batu Hari 142,600.00###
5 Tukang kayu Hari 148,350.00###
6 Tukang Besi Hari 148,350.00###
7 Tukang cat Hari 148,350.00###
8 Tukang gali/buruh/ pekerja Hari 115,000.00###
9 Tukang Listrik Hari 148,350.00###
10 Tukang Pipa/ Tukang Ledeng Hari 148,350.00###
11 Tukang Aspal Hari 148,350.00###
12 Tukang masak Aspal/pekerja Hari 115,000.00###
13 Pekerja Hari 115,000.00###
14 Tukang Ukir Hari 148,350.00###
15 Operator Hari 148,350.00###
16 Pembantu Operator Hari 115,000.00###
17 Mekanik Hari 148,350.00###
18 Pembantu Mekanik Hari 115,000.00###
19 Pasang Atap Alang-Alang Hari 148,350.00###
20 Pasang Bata Gosok Dua Muka M2 359,074.00###
21 Pasang Bata Gosok Satu Muka M2 192,836.00###
22 Pasang Batu Paras Diukir M2 383,674.00###
23 Pasang Patu Paras Siap Diukir M2 332,476.00###
24 Tukang Bongkar Begesting Hari 142,600.00###

Catatan :
Harga - harga hanya sebagai pedoman / pendukung
dalam perhitungan konstruksi ( tidak mengikat ).
UMP PROV. PAPUA BARAT 2018 2,667,000.00
SEKTOR PERTAMBANGAN MINYAK DAN GAS BUMI 3,500,000.00
SEKTOR PERTAMBANGAN KECUALI
SEKTOR KEHUTANAN, PERKEBUNAN, DAN GALIAN C 2,806,000.00
PERIKANAN 2,667,000.00
SEKTOR JASA KONSTRUKSI 2,875,000.00
Undang -undang no. 13 tahun 2003 tentang "ketenagakerjaan"
Jika dalam 1 hari bekerja selama 8 jam (5 hari kerja/ senin s/d jumat) maka dalam 1 bulan bekerja selama 21 hari
Jika dalam 1 hari bekerja selama 7 jam (6 hari kerja/ senin s/d sabtu) maka dalam 1 bulan bekerja selama 25 hari

Fakfak, 12 Februari 2018


PANITIA PENYUSUNAN STANDARD HARGA SATUAN TAHUN 2018

Sekretaris, Ketua,

RIZAL MINGGELE, ST LIZA NEIRASARI, ST


NIP. 19820701 200909 1 001 NIP. 19751016 200111 2 001

Mengetahui,
Kepala Dinas PU, Penataan Ruang,
Perumahan Rakyat dan Kawasan Permukiman
Kabupaten Fakfak ,

SAMAUN DAHLAN S.Sos, MAP


NIP. 19681005 199108 1 002
SAMAUN DAHLAN S.Sos, MAP
NIP. 19681005 199108 1 002
PEMERINTAH KABUPATEN FAKFAK
DINAS PU, PENATAAN RUANG, PERUMAHAN RAKYAT
DAN KAWASAN PERMUKIMAN
Jl. Achmad Yani No. 08 Fakfak, Telp. (0956) 22320 - 22709

DAFTAR HARGA SATUAN BAHAN DAN UPAH


TAHUN ANGGARAN 2018
A. Harga Satuan Bahan `

NO NAMA BARANG SATUAN


NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA KRAMONGMONGGA MBAHAMDANDARA KARAS TELUK PATIPI ARGUNI FURWAGI BOMBERAY TOMAGE
DASAR
1 2 3 4 5 7 8 9 10 11 12 13 14
1.075 1.1 1.15 1.1 1.1 1.1 1.15 1.175
FINISHING
1 Amplas lbr 8,000.00 12,602.67 11,530.11 11,798.25 12,334.53 11,798.25 11,798.25 11,798.25 12,334.53 12,602.67
2 Amplas mtr 20,000.00 28,856.59 26,400.71 27,014.68 28,242.62 27,014.68 27,014.68 27,014.68 28,242.62 28,856.59
3 Amplas kain lbr 15,000.00 22,084.13 20,204.63 20,674.50 21,614.25 20,674.50 20,674.50 20,674.50 21,614.25 22,084.13
4 Kawat has m' 45,000.00 62,718.92 57,381.14 58,715.58 61,384.47 58,715.58 58,715.58 58,715.58 61,384.47 62,718.92
5 Kawat has Plastik lbr 20,000.00 28,856.59 26,400.71 27,014.68 28,242.62 27,014.68 27,014.68 27,014.68 28,242.62 28,856.59
6 Cat besi (Hamerton) Kaleng 1 kg kg 85,000.00 116,898.64 106,949.82 109,437.02 114,411.43 109,437.02 109,437.02 109,437.02 114,411.43 116,898.64
7 Cat besi (Avian) Kaleng 1 kg kg 75,000.00 103,353.71 94,557.65 96,756.66 101,154.69 96,756.66 96,756.66 96,756.66 101,154.69 103,353.71
8 Cat Besi (polibest) kaleng 1 kg kg 68,750.00 94,888.12 86,812.54 88,831.44 92,869.23 88,831.44 88,831.44 88,831.44 92,869.23 94,888.12
9 Cat Meni Besi/dasar (Polibest) Kaleng 0,8 kg kg 68,750.00 94,888.12 86,812.54 88,831.44 92,869.23 88,831.44 88,831.44 88,831.44 92,869.23 94,888.12
10 Cat Meni Besi/dasar (Yoko) Kaleng 0,8 kg kg 47,500.00 66,105.15 60,479.18 61,885.67 64,698.66 61,885.67 61,885.67 61,885.67 64,698.66 66,105.15
11 Cat kayu+Besi/dasar (polibest) kaleng 0.8 kg kg 75,000.00 103,353.71 94,557.65 96,756.66 101,154.69 96,756.66 96,756.66 96,756.66 101,154.69 103,353.71
12 Cat kayu+Besi/dasar (Yoko) kaleng 0.8 kg kg 62,500.00 86,422.54 79,067.43 80,906.21 84,583.77 80,906.21 80,906.21 80,906.21 84,583.77 86,422.54
13 Cat Kayu Yoko kg 65,000.00 89,808.78 82,165.48 84,076.30 87,897.95 84,076.30 84,076.30 84,076.30 87,897.95 89,808.78
14 Cat menie besi (Glotex) Kaleng 1 kg kg 35,000.00 49,173.99 44,988.97 46,035.22 48,127.73 46,035.22 46,035.22 46,035.22 48,127.73 49,173.99
15 Cat menie besi (Yoko) Kaleng 1 kg kg 25,000.00 35,629.06 32,596.80 33,354.86 34,870.99 33,354.86 33,354.86 33,354.86 34,870.99 35,629.06
16 Cat menie besi (Delmas) Kaleng 1 kg kg - - - - - - - - - -
17 Cat menie besi (Avian) Kaleng 1 kg kg 65,000.00 89,808.78 82,165.48 84,076.30 87,897.95 84,076.30 84,076.30 84,076.30 87,897.95 89,808.78
18 Cat menie kayu (polibest) 0,8 kg kg 60,000.00 83,036.31 75,969.39 77,736.12 81,269.58 77,736.12 77,736.12 77,736.12 81,269.58 83,036.31
19 Cat menie kayu (Avian) 1kg kg 80,000.00 110,126.17 100,753.73 103,096.84 107,783.06 103,096.84 103,096.84 103,096.84 107,783.06 110,126.17
20 Cat tembok Decolith kg - - - - - - - - - -
21 Cat tembok (Jotun) kg 265,000.00 308,488.60 331,625.25 339,337.46 354,761.89 339,337.46 339,337.46 339,337.46 354,761.89 362,474.11
22 Cat tembok Grahalux 5 Kg kg - - - - - - - -
23 Cat tembok Paragon 5 Kg kg 27,000.00 34,131.72 36,691.60 37,544.89 39,251.48 37,544.89 37,544.89 37,544.89 39,251.48 40,104.77
24 Cat tembok (aries) 5 kg kg 21,000.00 27,215.16 29,256.30 29,936.68 31,297.43 29,936.68 29,936.68 29,936.68 31,297.43 31,977.81
25 Cat tembok Toyopaint kg - - - - - - - - - -
26 Cat tembok (vitex) Kaleng 5 kg kg 24,000.00 30,673.44 32,973.95 33,740.78 35,274.46 33,740.78 33,740.78 33,740.78 35,274.46 36,041.29
27 Cat tembok (vitex) Kaleng 4.5 kg kg 13,333.33 18,377.33 19,755.63 20,215.07 21,133.93 20,215.07 20,215.07 20,215.07 21,133.93 21,593.37
29 Cat monilex klg 125,000.00 147,102.20 158,134.87 161,812.42 169,167.53 161,812.42 161,812.42 161,812.42 169,167.53 172,845.09
30 Dempul kayu (polibest) 0,8 Kg kg 50,000.00 60,645.20 65,193.59 66,709.72 69,741.98 66,709.72 66,709.72 66,709.72 69,741.98 71,258.11
31 Dempul kayu (Pedang) 0.8 kg kg 60,000.00 72,172.80 77,585.76 79,390.08 82,998.72 79,390.08 79,390.08 79,390.08 82,998.72 84,803.04
32 Dempul kayu (Impra) 1 kg liter 65,000.00 77,936.60 83,781.85 85,730.26 89,627.09 85,730.26 85,730.26 85,730.26 89,627.09 91,575.51
34 Kuas Besar 5 inch bh 35,000.00 43,353.80 46,605.34 47,689.18 49,856.87 47,689.18 47,689.18 47,689.18 49,856.87 50,940.72
35 Kuas Besar 4 inch bh 30,000.00 37,590.00 40,409.25 41,349.00 43,228.50 41,349.00 41,349.00 41,349.00 43,228.50 44,168.25
36 Kuas Sedang 3 inch bh 25,000.00 31,826.20 34,213.17 35,008.82 36,600.13 35,008.82 35,008.82 35,008.82 36,600.13 37,395.79
37 Kuas roll 7" bh 40,000.00 49,117.60 52,801.42 54,029.36 56,485.24 54,029.36 54,029.36 54,029.36 56,485.24 57,713.18
38 Kuas roll 10" bh 50,000.00 60,645.20 65,193.59 66,709.72 69,741.98 66,709.72 66,709.72 66,709.72 69,741.98 71,258.11
38 Kuas roll 4" bh 33,000.00 41,048.28 44,126.90 45,153.11 47,205.52 45,153.11 45,153.11 45,153.11 47,205.52 48,231.73
39 Kuas Kecil 2 inch bh 20,000.00 26,062.40 28,017.08 28,668.64 29,971.76 28,668.64 28,668.64 28,668.64 29,971.76 30,623.32
40 Mild zak 30,000.00 37,590.00 40,409.25 41,349.00 43,228.50 41,349.00 41,349.00 41,349.00 43,228.50 44,168.25
41 Minyak cat/Thiner A Kaleng 0,8 liter ltr 50,000.00 60,645.20 65,193.59 66,709.72 69,741.98 66,709.72 66,709.72 66,709.72 69,741.98 71,258.11
42 Plamir kayu 1kg kg 80,000.00 95,228.00 102,370.10 104,750.80 109,512.20 104,750.80 104,750.80 104,750.80 109,512.20 111,892.90
43 Plamir tembok 5 kg merk B0y0 kg 16,000.00 21,451.36 23,060.21 23,596.50 24,669.06 23,596.50 23,596.50 23,596.50 24,669.06 25,205.35
44 Plamir tembok 5 kg merk lion kg 11,000.00 15,687.56 16,864.13 17,256.32 18,040.69 17,256.32 17,256.32 17,256.32 18,040.69 18,432.88
45 Plamir tembok 5 kg merk Paragon kg 17,000.00 22,604.12 24,299.43 24,864.53 25,994.74 24,864.53 24,864.53 24,864.53 25,994.74 26,559.84
46 Plamir tembok 5 kg kg 11,000.00 15,687.56 16,864.13 17,256.32 18,040.69 17,256.32 17,256.32 17,256.32 18,040.69 18,432.88
47 Politur (Boyo) kaleng 1 liter ltr 75,000.00 89,464.20 96,174.02 98,410.62 102,883.83 98,410.62 98,410.62 98,410.62 102,883.83 105,120.44
48 Politur (Joly) kaleng 1 liter ltr 45,000.00 54,881.40 58,997.51 60,369.54 63,113.61 60,369.54 60,369.54 60,369.54 63,113.61 64,485.65
49 Politur (vernis) kaleng 1 liter kg 80,000.00 95,228.00 102,370.10 104,750.80 109,512.20 104,750.80 104,750.80 104,750.80 109,512.20 111,892.90
50 Politur (india) kaleng 1 liter ltr 47,500.00 57,763.30 62,095.55 63,539.63 66,427.80 63,539.63 63,539.63 63,539.63 66,427.80 67,871.88
51 Thiner A kaleng 1/2 liter Ltr 60,000.00 72,172.80 77,585.76 79,390.08 82,998.72 79,390.08 79,390.08 79,390.08 82,998.72 84,803.04
52 Thiner A Avian kaleng 1 liter ltr 55,000.00 66,409.00 71,389.68 73,049.90 76,370.35 73,049.90 73,049.90 73,049.90 76,370.35 78,030.58
53 Thiner A kaleng 1 liter Ltr 44,000.00 53,728.64 57,758.29 59,101.50 61,787.94 59,101.50 59,101.50 59,101.50 61,787.94 63,131.15
54 Thiner B Avian kaleng 1 liter ltr 40,000.00 49,117.60 52,801.42 54,029.36 56,485.24 54,029.36 54,029.36 54,029.36 56,485.24 57,713.18

Harga Satauan Bahan dan Upah Hal. 47


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA KRAMONGMONGGA MBAHAMDANDARA KARAS TELUK PATIPI ARGUNI FURWAGI BOMBERAY TOMAGE
DASAR
1 2 3 4 5 7 8 9 10 11 12 13 14
55 Thiner B Super kaleng 1 liter Ltr 32,000.00 39,895.52 42,887.68 43,885.07 45,879.85 43,885.07 43,885.07 43,885.07 45,879.85 46,877.24
56 Thiner Super 5 kg kg 40,000.00 49,117.60 52,801.42 54,029.36 56,485.24 54,029.36 54,029.36 54,029.36 56,485.24 57,713.18
57 Thiner A Spesial 5 kg kg 38,000.00 46,812.08 50,322.99 51,493.29 53,833.89 51,493.29 51,493.29 51,493.29 53,833.89 55,004.19
58 Impra 1 Liter ltr 70,000.00 83,700.40 89,977.93 92,070.44 96,255.46 92,070.44 92,070.44 92,070.44 96,255.46 98,347.97
59 impra clear / sanding 1 l Ltr 73,000.00 87,158.68 93,695.58 95,874.55 100,232.48 95,874.55 95,874.55 95,874.55 100,232.48 102,411.45
60 impra wood stain 1 l Ltr 76,000.00 90,616.96 97,413.23 99,678.66 104,209.50 99,678.66 99,678.66 99,678.66 104,209.50 106,474.93
- - - - - - - - -
BAHAN BAKAR MINYAK - - - - - - - - -
1 Premium Ltr 8,823.16 13,178.19 14,166.55 14,496.00 15,154.91 14,496.00 14,496.00 14,496.00 15,154.91 15,484.37
2 Minyak Tanah Ltr 9,893.90 14,412.49 15,493.43 15,853.74 16,574.37 15,853.74 15,853.74 15,853.74 16,574.37 16,934.68
3 Minyak Solar Ltr 10,989.30 15,675.23 16,850.87 17,242.75 18,026.51 17,242.75 17,242.75 17,242.75 18,026.51 18,418.39
4 Minyak Diesel Ltr - - - - - - - - -
5 Minyak Bakar Ltr - - - - - - - - -
6 Gemuk /Stempel 20 kg kg - - - - - - - - - -
7 Gemuk /Stempel 16 kg kg -
- - - - - - - - -
PENUTUP ATAP - - - - - - - - -
1 Alang-alang panjang 2,4 meter lbr -
2 Alluminium foil m2 29,000.00 34,933.64 37,553.66 38,427.00 40,173.69 38,427.00 38,427.00 38,427.00 40,173.69 41,047.03
3 Asbes Bubungan lbr 24,000.00 29,169.84 31,357.58 32,086.82 33,545.32 32,086.82 32,086.82 32,086.82 33,545.32 34,274.56
4 Asbes Gelombang 1,80 m x 0,80 m x 5 mm lbr 33,600.00 40,236.34 43,254.06 44,259.97 46,271.79 44,259.97 44,259.97 44,259.97 46,271.79 47,277.69
5 Asbes Gelombang 2,4 m x 1,05 m x 4 mm lbr 42,000.00 49,919.52 53,663.48 54,911.47 57,407.45 54,911.47 54,911.47 54,911.47 57,407.45 58,655.44
6 Asbes Rata 2 m x 1 m x 4 mm lbr 18,000.00 22,253.28 23,922.28 24,478.61 25,591.27 24,478.61 24,478.61 24,478.61 25,591.27 26,147.60
7 Besi profil WF kg 16,500.00 20,524.14 22,063.45 22,576.55 23,602.76 22,576.55 22,576.55 22,576.55 23,602.76 24,115.86
8 Besi strip 1kg kg 7,260.00 9,872.64 10,613.09 10,859.90 11,353.53 10,859.90 10,859.90 10,859.90 11,353.53 11,600.35
9 Bubungan Biasa bj
10 Bubungan Plentong bj 7,200.00 9,803.47 10,538.73 10,783.82 11,273.99 10,783.82 10,783.82 10,783.82 11,273.99 11,519.08
11 Genteng plentong dicat bj 1,380.00 3,094.41 3,326.49 3,403.85 3,558.57 3,403.85 3,403.85 3,403.85 3,558.57 3,635.93
12 Genteng Plentong bj 1,560.00 3,301.91 3,549.55 3,632.10 3,797.19 3,632.10 3,632.10 3,632.10 3,797.19 3,879.74
13 Ijuk m3 20,000.00 24,558.80 26,400.71 27,014.68 28,242.62 27,014.68 27,014.68 27,014.68 28,242.62 28,856.59
14 Tali Ijuk Kg - - - - - - - - -
15 Formite/Penjaga Jarak Bekisting/Spacer Bh - - - - - - - - -
16 Seng BJLS 0,20 gelombang lbr 65,000.00 76,433.00 82,165.48 84,076.30 87,897.95 84,076.30 84,076.30 84,076.30 87,897.95 89,808.78
17 Seng BJLS 0.20 gelombang gajah berlian lbr 59,000.00 69,516.44 74,730.17 76,468.08 79,943.91 76,468.08 76,468.08 76,468.08 79,943.91 81,681.82
18 Seng BJLS 0,25 gelombang lbr 68,000.00 79,891.28 85,883.13 87,880.41 91,874.97 87,880.41 87,880.41 87,880.41 91,874.97 93,872.25
19 Seng BJLS 0,28 gelombang lbr - - - - - - - - - -
20 Seng BJLS 0,30 gelombang lbr 80,000.00 93,724.40 100,753.73 103,096.84 107,783.06 103,096.84 103,096.84 103,096.84 107,783.06 110,126.17
21 Seng Plat BJLS 30 lebar 28 cm lbr 22,000.00 26,864.32 28,879.14 29,550.75 30,893.97 29,550.75 29,550.75 29,550.75 30,893.97 31,565.58
22 Seng Plat BJLS 30 lebar 30 cm m' 25,000.00 30,322.60 32,596.80 33,354.86 34,870.99 33,354.86 33,354.86 33,354.86 34,870.99 35,629.06
23 Seng Plat BJLS 30 lebar 38 cm m' 32,000.00 38,391.92 41,271.31 42,231.11 44,150.71 42,231.11 42,231.11 42,231.11 44,150.71 45,110.51
24 Seng Plat BJLS 30 lebar 40 cm m' 30,000.00 36,086.40 38,792.88 39,695.04 41,499.36 39,695.04 39,695.04 39,695.04 41,499.36 42,401.52
25 Seng Plat BJLS 30 lebar 44 cm m' 35,000.00 41,850.20 44,988.97 46,035.22 48,127.73 46,035.22 46,035.22 46,035.22 48,127.73 49,173.99
26 Seng Plat BJLS 20 lebar 30 cm m' 15,000.00 18,795.00 20,204.63 20,674.50 21,614.25 20,674.50 20,674.50 20,674.50 21,614.25 22,084.13
27 Seng Plat BJLS 20 lebar 28 cm m' 15,000.00 18,795.00 20,204.63 20,674.50 21,614.25 20,674.50 20,674.50 20,674.50 21,614.25 22,084.13
28 Seng Plat BJLS 20 lebar 40 cm m' 25,000.00 30,322.60 32,596.80 33,354.86 34,870.99 33,354.86 33,354.86 33,354.86 34,870.99 35,629.06
29 Seng Plat BJLS 30 pintu lbr 82,000.00 96,029.92 103,232.16 105,632.91 110,434.41 105,632.91 105,632.91 105,632.91 110,434.41 112,835.16
30 Seng Plat BJLS 20 pintu m' 63,000.00 74,127.48 79,687.04 81,540.23 85,246.60 81,540.23 81,540.23 81,540.23 85,246.60 87,099.79
31 Seng plastik gelombang besar tebal lbr 95,000.00 111,015.80 119,341.99 122,117.38 127,668.17 122,117.38 122,117.38 122,117.38 127,668.17 130,443.57
32 Seng plastik gelombang kecil tebal lbr 55,000.00 64,905.40 69,773.31 71,395.94 74,641.21 71,395.94 71,395.94 71,395.94 74,641.21 76,263.85
33 Seng plastik gelombang besar tipis lbr 80,000.00 93,724.40 100,753.73 103,096.84 107,783.06 103,096.84 103,096.84 103,096.84 107,783.06 110,126.17
34 Seng Fiber gelombang besar tebal lbr 70,000.00 82,196.80 88,361.56 90,416.48 94,526.32 90,416.48 90,416.48 90,416.48 94,526.32 96,581.24
35 Sirap Jati bh 10,200.00 13,261.75 14,256.38 14,587.93 15,251.01 14,587.93 14,587.93 14,587.93 15,251.01 15,582.56
36 AT roof Bjls 30, 0,8x0,8 lbr 47,000.00 55,683.32 59,859.57 61,251.65 64,035.82 61,251.65 61,251.65 61,251.65 64,035.82 65,427.90
37 Rainbouw roof Bjls 30, 0,3x1,2 lbr 45,000.00 53,377.80 57,381.14 58,715.58 61,384.47 58,715.58 58,715.58 58,715.58 61,384.47 62,718.92
38 Bubungan rainbouw roof Bjls 30, 1,2 m' Bh 45,000.00 53,377.80 57,381.14 58,715.58 61,384.47 58,715.58 58,715.58 58,715.58 61,384.47 62,718.92
39 Multiroof BJ 300 lbr 90,000.00 105,252.00 113,145.90 115,777.20 121,039.80 115,777.20 115,777.20 115,777.20 121,039.80 123,671.10
40 Bubungan multiroof Bh 55,000.00 64,905.40 69,773.31 71,395.94 74,641.21 71,395.94 71,395.94 71,395.94 74,641.21 76,263.85
41 Igi roof 0,2 uk. 0,8x0,8 m' lbr 45,000.00 53,377.80 57,381.14 58,715.58 61,384.47 58,715.58 58,715.58 58,715.58 61,384.47 62,718.92
42 Sakura roof BJ 30 lbr 48,000.00 56,836.08 61,098.79 62,519.69 65,361.49 62,519.69 62,519.69 62,519.69 65,361.49 66,782.39
-
PENGGANTUNG -
1 Engsel jendela biasa ps 20,000.00 24,558.80 26,400.71 27,014.68 28,242.62 27,014.68 27,014.68 27,014.68 28,242.62 28,856.59
2 Engsel jendela biasa Merk King ps 30,000.00 36,086.40 38,792.88 39,695.04 41,499.36 39,695.04 39,695.04 39,695.04 41,499.36 42,401.52
3 Engsel jendela biasa merk king 3' ps 45,000.00 53,377.80 57,381.14 58,715.58 61,384.47 58,715.58 58,715.58 58,715.58 61,384.47 62,718.92
4 Engsel jendela merek King 4" ps 30,000.00 36,086.40 38,792.88 39,695.04 41,499.36 39,695.04 39,695.04 39,695.04 41,499.36 42,401.52
5 Engsel kupu-kupu jendela biasa ps 25,000.00 30,322.60 32,596.80 33,354.86 34,870.99 33,354.86 33,354.86 33,354.86 34,870.99 35,629.06
6 Engsel kupu-kupu jendela biasa 3" ps 85,000.00 99,488.20 106,949.82 109,437.02 114,411.43 109,437.02 109,437.02 109,437.02 114,411.43 116,898.64

Harga Satauan Bahan dan Upah Hal. 48


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA KRAMONGMONGGA MBAHAMDANDARA KARAS TELUK PATIPI ARGUNI FURWAGI BOMBERAY TOMAGE
DASAR
1 2 3 4 5 7 8 9 10 11 12 13 14
7 Engsel Jendela Bagus Kuningan ps 50,000.00 59,141.60 63,577.22 65,055.76 68,012.84 65,055.76 65,055.76 65,055.76 68,012.84 69,491.38
8 Engsel jendela bagus kuningan modem 4' ps 50,000.00 59,141.60 63,577.22 65,055.76 68,012.84 65,055.76 65,055.76 65,055.76 68,012.84 69,491.38
9 Engsel jendela bagus kuningan 4' ps 30,000.00 36,086.40 38,792.88 39,695.04 41,499.36 39,695.04 39,695.04 39,695.04 41,499.36 42,401.52
10 Engsel kupu-kupu pintu biasa ps 45,000.00 53,377.80 57,381.14 58,715.58 61,384.47 58,715.58 58,715.58 58,715.58 61,384.47 62,718.92
11 Engsel kupu-kupu pintu biasa 4" ps 25,000.00 30,322.60 32,596.80 33,354.86 34,870.99 33,354.86 33,354.86 33,354.86 34,870.99 35,629.06
12 Engsel kupu-kupu pintu biasa 4cmx3cmx3mm merk jezz ps 35,000.00 41,850.20 44,988.97 46,035.22 48,127.73 46,035.22 46,035.22 46,035.22 48,127.73 49,173.99
13 Engsel kupu-kupu pintu biasa AFC 4cmx3cmx3mm merk king ps -
14 Engsel kupu-kupu pintu biasa 4cmx3cmx3mm merk viper ps 30,000.00 36,086.40 38,792.88 39,695.04 41,499.36 39,695.04 39,695.04 39,695.04 41,499.36 42,401.52
15 Engsel nylon ps 20,000.00 24,558.80 26,400.71 27,014.68 28,242.62 27,014.68 27,014.68 27,014.68 28,242.62 28,856.59
16 Espagnoleth set 35,000.00 41,850.20 44,988.97 46,035.22 48,127.73 46,035.22 46,035.22 46,035.22 48,127.73 49,173.99
17 Grendel kecil biasa bh 12,000.00 15,336.72 16,486.97 16,870.39 17,637.23 16,870.39 16,870.39 16,870.39 17,637.23 18,020.65
18 Grendel kecil bagus bh 20,000.00 24,558.80 26,400.71 27,014.68 28,242.62 27,014.68 27,014.68 27,014.68 28,242.62 28,856.59
19 Grendel kecil spring knife brabus/ses bh 30,000.00 36,086.40 38,792.88 39,695.04 41,499.36 39,695.04 39,695.04 39,695.04 41,499.36 42,401.52
20 Grendel kecil biasa 3" bh 20,000.00 24,558.80 26,400.71 27,014.68 28,242.62 27,014.68 27,014.68 27,014.68 28,242.62 28,856.59
21 Grendel kecil bagus 2" bh 15,000.00 18,795.00 20,204.63 20,674.50 21,614.25 20,674.50 20,674.50 20,674.50 21,614.25 22,084.13
22 Grendel kecil spring knife bh 15,000.00 18,795.00 20,204.63 20,674.50 21,614.25 20,674.50 20,674.50 20,674.50 21,614.25 22,084.13
23 Grendel besar 12" bh 45,000.00 53,377.80 57,381.14 58,715.58 61,384.47 58,715.58 58,715.58 58,715.58 61,384.47 62,718.92
24 Grendel besar bh 15,000.00 18,795.00 20,204.63 20,674.50 21,614.25 20,674.50 20,674.50 20,674.50 21,614.25 22,084.13
25 Grendel hararo bh 18,425.00 22,743.20 24,448.94 25,017.52 26,154.68 25,017.52 25,017.52 25,017.52 26,154.68 26,723.26
26 Kaca 3 mm bening lbr 230,000.00 266,638.40 286,636.28 293,302.24 306,634.16 293,302.24 293,302.24 293,302.24 306,634.16 313,300.12
27 Kaca 3 mm bening 153x122 m2 m2 133,933.35 155,896.61 167,588.86 171,486.28 179,281.11 171,486.28 171,486.28 171,486.28 179,281.11 183,178.52
28 Kaca 5 mm bening lbr 325,000.00 376,150.60 404,361.90 413,765.66 432,573.19 413,765.66 413,765.66 413,765.66 432,573.19 441,976.96
29 Kaca 5 mm bening 200 x 100 m2 147,500.00 171,535.70 184,400.88 188,689.27 197,266.06 188,689.27 188,689.27 188,689.27 197,266.06 201,554.45
30 Kaca 5 mm bening 153x122 m2 m2 187,506.70 217,653.82 233,977.86 239,419.20 250,301.89 239,419.20 239,419.20 239,419.20 250,301.89 255,743.24
31 Kaca 6 mm bening 153x122 m2 m2 -
32 Kaca 8 mm bening 153x122 m2 m2 -
33 Kaca 10 mm bening m2 - - - - - - - - - -
34 Kaca 12 mm bening m2 - - - - - - - - - -
35 Kaca Es/Kapur 3 mm m2 - - - - - - - - - -
36 Kaca Es/Kapur 5 mm m2 - -
37 Kaca nako bening bh 21,000.00 25,711.56 27,639.93 28,282.72 29,568.29 28,282.72 28,282.72 28,282.72 29,568.29 30,211.08
38 Kaca nako rayben bh 25,000.00 30,322.60 32,596.80 33,354.86 34,870.99 33,354.86 33,354.86 33,354.86 34,870.99 35,629.06
39 Kaca ryben 3 mm 153x122 cm m2 187,506.70 217,653.82 233,977.86 239,419.20 250,301.89 239,419.20 239,419.20 239,419.20 250,301.89 255,743.24
40 Kaca ryben 5 mm 153x122 cm m2 200,900.03 233,093.12 250,575.11 256,402.43 268,057.09 256,402.43 256,402.43 256,402.43 268,057.09 273,884.42
41 Kaca Ryben 5 mm 183 x 132 cm m2 124,192.75 144,668.03 155,518.13 159,134.83 166,368.24 159,134.83 159,134.83 159,134.83 166,368.24 169,984.94
42 Kaca ryben 5 mm 200x100 cm m2 157,500.00 183,063.30 196,793.05 201,369.63 210,522.80 201,369.63 201,369.63 201,369.63 210,522.80 215,099.38
43 Cermin 3 mm 153x122 cm m2 310,725.38 359,695.39 386,672.55 395,664.93 413,649.70 395,664.93 395,664.93 395,664.93 413,649.70 422,642.09
44 Cermin 5 mm 183 x 122 m2 194,840.10 226,107.47 243,065.53 248,718.22 260,023.59 248,718.22 248,718.22 248,718.22 260,023.59 265,676.28
45 Kait angin biasa ps 20,000.00 24,558.80 26,400.71 27,014.68 28,242.62 27,014.68 27,014.68 27,014.68 28,242.62 28,856.59
46 Kait angin bagus bh 45,000.00 53,377.80 57,381.14 58,715.58 61,384.47 58,715.58 58,715.58 58,715.58 61,384.47 62,718.92
47 Kunci pintu Delmanao bh - - - - - - - - -
48 Kunci pintu Zeis bh 285,000.00 330,040.20 354,793.22 363,044.22 379,546.23 363,044.22 363,044.22 363,044.22 379,546.23 387,797.24
49 Kunci pintu TOP bh 65,000.00 76,433.00 82,165.48 84,076.30 87,897.95 84,076.30 84,076.30 84,076.30 87,897.95 89,808.78
50 Kunci pintu Union bh -
51 Kunci pintu Cap Kuda bodi kecil bh 120,000.00 139,834.80 150,322.41 153,818.28 160,810.02 153,818.28 153,818.28 153,818.28 160,810.02 164,305.89
52 Kunci pintu Cap Kuda bodi besar bh 135,000.00 157,126.20 168,910.67 172,838.82 180,695.13 172,838.82 172,838.82 172,838.82 180,695.13 184,623.29
53 Kunci pintu Royal bh 160,000.00 185,945.20 199,891.09 204,539.72 213,836.98 204,539.72 204,539.72 204,539.72 213,836.98 218,485.61
54 Kunci pintu Globe K bh 135,000.00 157,126.20 168,910.67 172,838.82 180,695.13 172,838.82 172,838.82 172,838.82 180,695.13 184,623.29
55 Kunci pintu Yale bh 225,000.00 260,874.60 280,440.20 286,962.06 300,005.79 286,962.06 286,962.06 286,962.06 300,005.79 306,527.66
56 Kunci pintu vanessa bh 125,000.00 145,598.60 156,518.50 160,158.46 167,438.39 160,158.46 160,158.46 160,158.46 167,438.39 171,078.36
57 Kunci pintu Kodai bh 185,000.00 214,764.20 230,871.52 236,240.62 246,978.83 236,240.62 236,240.62 236,240.62 246,978.83 252,347.94
58 Kunci pintu Sapphire bh 275,000.00 318,512.60 342,401.05 350,363.86 366,289.49 350,363.86 350,363.86 350,363.86 366,289.49 374,252.31
59 Kunci slot kecil HPP bh 28,000.00 33,780.88 36,314.45 37,158.97 38,848.01 37,158.97 37,158.97 37,158.97 38,848.01 39,692.53
60 Kunci slot sedang HPP bh 35,000.00 41,850.20 44,988.97 46,035.22 48,127.73 46,035.22 46,035.22 46,035.22 48,127.73 49,173.99
61 Kunci slot besar HPP bh 55,000.00 64,905.40 69,773.31 71,395.94 74,641.21 71,395.94 71,395.94 71,395.94 74,641.21 76,263.85
62 Kunci slot kecil bh 40,000.00 47,614.00 51,185.05 52,375.40 54,756.10 52,375.40 52,375.40 52,375.40 54,756.10 55,946.45
63 Kunci slot kecil ATS bh 48,000.00 56,836.08 61,098.79 62,519.69 65,361.49 62,519.69 62,519.69 62,519.69 65,361.49 66,782.39
64 Kunci slot sedang bh 32,000.00 38,391.92 41,271.31 42,231.11 44,150.71 42,231.11 42,231.11 42,231.11 44,150.71 45,110.51
65 Kunci slot sedang ATS bh 35,000.00 41,850.20 44,988.97 46,035.22 48,127.73 46,035.22 46,035.22 46,035.22 48,127.73 49,173.99
66 Kunci slot besar bh 50,000.00 59,141.60 63,577.22 65,055.76 68,012.84 65,055.76 65,055.76 65,055.76 68,012.84 69,491.38
67 Kunci Silinder bh 55,000.00 64,905.40 69,773.31 71,395.94 74,641.21 71,395.94 71,395.94 71,395.94 74,641.21 76,263.85
68 Kunci tanam 2 slag Biasa bh 175,000.00 203,236.60 218,479.35 223,560.26 233,722.09 223,560.26 223,560.26 223,560.26 233,722.09 238,803.01
69 Kunci tanam 2 slag Bagus bh 195,000.00 226,291.80 243,263.69 248,920.98 260,235.57 248,920.98 248,920.98 248,920.98 260,235.57 265,892.87
70 Kunci tanam 2 slag bagus merk Azzuro bh - - - - - - - - - -
71 Kunci tanam 2 slag bagus merk Giardano bh - - - - - - - - - -
- - - - - - - - -
KAYU DAN PLAFOND - - - - - - - - -

Harga Satauan Bahan dan Upah Hal. 49


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA KRAMONGMONGGA MBAHAMDANDARA KARAS TELUK PATIPI ARGUNI FURWAGI BOMBERAY TOMAGE
DASAR
1 2 3 4 5 7 8 9 10 11 12 13 14
1 Bambu besar Ukuran 4 m btg 20,000.00 24,558.80 26,400.71 27,014.68 28,242.62 27,014.68 27,014.68 27,014.68 28,242.62 28,856.59
2 Bambu sedang Ukuran 4 m btg 15,000.00 18,795.00 20,204.63 20,674.50 21,614.25 20,674.50 20,674.50 20,674.50 21,614.25 22,084.13
3 Bambu kecil Ukuran 4 m btg 10,000.00 13,031.20 14,008.54 14,334.32 14,985.88 14,334.32 14,334.32 14,334.32 14,985.88 15,311.66
4 Celling teak (0,62 x 2,40) m2 lbr 65,000.00 76,433.00 82,165.48 84,076.30 87,897.95 84,076.30 84,076.30 84,076.30 87,897.95 89,808.78
5 Eternit lbr 47,000.00 55,683.32 59,859.57 61,251.65 64,035.82 61,251.65 61,251.65 61,251.65 64,035.82 65,427.90
6 Formika lbr 95,000.00 111,015.80 119,341.99 122,117.38 127,668.17 122,117.38 122,117.38 122,117.38 127,668.17 130,443.57
7 Melamine Lbr 130,000.00 151,362.40 162,714.58 166,498.64 174,066.76 166,498.64 166,498.64 166,498.64 174,066.76 177,850.82
8 Gedeg kulit kelas I m2 21,000.00 25,711.56 27,639.93 28,282.72 29,568.29 28,282.72 28,282.72 28,282.72 29,568.29 30,211.08
9 Gypsum Old lbr -
10 Hard board MDF lbr 105,000.00 124,047.00 133,350.53 136,451.70 142,654.05 136,451.70 136,451.70 136,451.70 142,654.05 145,755.23
11 Kalsiboard 4,5 mm lbr -
12 Kayu bekesting / kayu putih m3 2,300,000.00 2,654,355.20 2,853,431.84 2,919,790.72 3,052,508.48 2,919,790.72 2,919,790.72 2,919,790.72 3,052,508.48 3,118,867.36
13 Kayu Besi 10 x 10, panjang 4 m' m3 3,300,000.00 3,807,115.20 4,092,648.84 4,187,826.72 4,378,182.48 4,187,826.72 4,187,826.72 4,187,826.72 4,378,182.48 4,473,360.36
14 Kayu Besi 5 x 10, panjang 4 m' m3 4,500,000.00 5,190,427.20 5,579,709.24 5,709,469.92 5,968,991.28 5,709,469.92 5,709,469.92 5,709,469.92 5,968,991.28 6,098,751.96
15 Kayu Besi 5 x 5, panjang 4 m' m3 3,600,000.00 4,152,943.20 4,464,413.94 4,568,237.52 4,775,884.68 4,568,237.52 4,568,237.52 4,568,237.52 4,775,884.68 4,879,708.26
16 Kayu Besi 2.5 x 20, panjang 4 m' m3 4,500,000.00 5,190,427.20 5,579,709.24 5,709,469.92 5,968,991.28 5,709,469.92 5,709,469.92 5,709,469.92 5,968,991.28 6,098,751.96
17 Kayu Besi 10 x 10, panjang 3 m' m3 4,600,000.00 5,305,703.20 5,703,630.94 5,836,273.52 6,101,558.68 5,836,273.52 5,836,273.52 5,836,273.52 6,101,558.68 6,234,201.26
18 Kayu Besi 6x 12, panjang 4 m' m3 5,750,000.00 6,631,377.20 7,128,730.49 7,294,514.92 7,626,083.78 7,294,514.92 7,294,514.92 7,294,514.92 7,626,083.78 7,791,868.21
19 Reng Kayu Besi 2 x 3 m3 5,300,000.00 6,112,635.20 6,571,082.84 6,723,898.72 7,029,530.48 6,723,898.72 6,723,898.72 6,723,898.72 7,029,530.48 7,182,346.36
20 Kayu Besi 4x 25, panjang 4 m' m3 3,500,000.00 4,037,667.20 4,340,492.24 4,441,433.92 4,643,317.28 4,441,433.92 4,441,433.92 4,441,433.92 4,643,317.28 4,744,258.96
21 Papan Kayu besi 2,5 x 25, panjang 4 m' m3 3,500,000.00 4,037,667.20 4,340,492.24 4,441,433.92 4,643,317.28 4,441,433.92 4,441,433.92 4,441,433.92 4,643,317.28 4,744,258.96
22 Papan Cor/Papan Kayu Putih m3 2,000,000.00 2,308,527.20 2,481,666.74 2,539,379.92 2,654,806.28 2,539,379.92 2,539,379.92 2,539,379.92 2,654,806.28 2,712,519.46
23 Kayu Matoa 10 x10, panjang 4 m' m3 2,300,000.00 2,654,355.20 2,853,431.84 2,919,790.72 3,052,508.48 2,919,790.72 2,919,790.72 2,919,790.72 3,052,508.48 3,118,867.36
24 Kayu Matoa 5 x 10, panjang 4 m' m3 2,300,000.00 2,654,355.20 2,853,431.84 2,919,790.72 3,052,508.48 2,919,790.72 2,919,790.72 2,919,790.72 3,052,508.48 3,118,867.36
25 Kayu Matoa 5 x 5, panjang 4 m' m3 2,500,000.00 2,884,907.20 3,101,275.24 3,173,397.92 3,317,643.28 3,173,397.92 3,173,397.92 3,173,397.92 3,317,643.28 3,389,765.96
26 Kayu Matoa m3 2,300,000.00 2,654,355.20 2,853,431.84 2,919,790.72 3,052,508.48 2,919,790.72 2,919,790.72 2,919,790.72 3,052,508.48 3,118,867.36
27 Kayu Merbau m3 3,300,000.00 3,807,115.20 4,092,648.84 4,187,826.72 4,378,182.48 4,187,826.72 4,187,826.72 4,187,826.72 4,378,182.48 4,473,360.36
28 Papan Kayu Matoa 2,5 x 25, panjang 4 m' m3 2,500,000.00 2,884,907.20 3,101,275.24 3,173,397.92 3,317,643.28 3,173,397.92 3,173,397.92 3,173,397.92 3,317,643.28 3,389,765.96
29 Papan Kayu Matoa 2,5 x 20, panjang 4 m' m3 4,500,000.00 5,190,427.20 5,579,709.24 5,709,469.92 5,968,991.28 5,709,469.92 5,709,469.92 5,709,469.92 5,968,991.28 6,098,751.96
30 Papan Kayu Matoa 3 x 25, panjang 4 m' m3 2,500,000.00 2,884,907.20 3,101,275.24 3,173,397.92 3,317,643.28 3,173,397.92 3,173,397.92 3,173,397.92 3,317,643.28 3,389,765.96
31 Kayu bingkirai m3 - - - - - - - - - -
32 Kayu bingkirai papan m3 - - - - - - - - - -
33 Kayu dolken (pekerjaan sementara) btg 36,000.00 43,002.96 46,228.18 47,303.26 49,453.40 47,303.26 47,303.26 47,303.26 49,453.40 50,528.48
34 Kayu jati m3 - - - - - - - - - -
35 Kayu jati papan m3 - - - - - - - - - -
36 Kayu kamper balok m3 - - - - - - - - - -
37 Kayu kamper usuk/reng m3 - - - - - - - - - -
38 Kayu kamper papan m3 - - - - - - - - - -
39 Kayu kruing balok m3 - - - - - - - - - -
40 Kayu kruing usuk/reng m3 - - - - - - - - - -
41 Kayu kruing papan m3 - - - - - - - - - -
42 Kayu meranti balok m3 - - - - - - - - - -
43 Kayu meranti usuk/reng m3 - - - - - - - - - -
44 Kayu meranti papan m3 -
45 Kayu merbau papan m3 - - - - - - - - - -
46 Kayu profil m1 10,000.00 13,031.20 14,008.54 14,334.32 14,985.88 14,334.32 14,334.32 14,334.32 14,985.88 15,311.66
47 Kayu seseh balok m3 - - - - - - - - - -
48 Kayu seseh dolken m3 - - - - - - - - - -
49 Lem Aibond 450 gr kg 100,000.00 116,779.60 125,538.07 128,457.56 134,296.54 128,457.56 128,457.56 128,457.56 134,296.54 137,216.03
50 Lem Aibond 700 gr kg 92,857.14 108,545.60 116,686.52 119,400.16 124,827.44 119,400.16 119,400.16 119,400.16 124,827.44 127,541.08
51 Lem Kayu (fox) kg 40,000.00 47,614.00 51,185.05 52,375.40 54,756.10 52,375.40 52,375.40 52,375.40 54,756.10 55,946.45
52 Lem Kayu (fox) besar klg 68,000.00 79,891.28 85,883.13 87,880.41 91,874.97 87,880.41 87,880.41 87,880.41 91,874.97 93,872.25
53 Lem Kayu (Fox) 0.6 klg 40,000.00 47,614.00 51,185.05 52,375.40 54,756.10 52,375.40 52,375.40 52,375.40 54,756.10 55,946.45
54 Lem Kayu (Fox) klg 55,000.00 64,905.40 69,773.31 71,395.94 74,641.21 71,395.94 71,395.94 71,395.94 74,641.21 76,263.85
55 Lem Kayu (Fox) Rajawali kg 35,000.00 41,850.20 44,988.97 46,035.22 48,127.73 46,035.22 46,035.22 46,035.22 48,127.73 49,173.99
56 List Gypsum standar m' - - - - - - - - - -
57 Minyak bekisting ltr 15,000.00 18,795.00 20,204.63 20,674.50 21,614.25 20,674.50 20,674.50 20,674.50 21,614.25 22,084.13
58 Tripleks 2.7 mm lbr 68,000.00 79,891.28 85,883.13 87,880.41 91,874.97 87,880.41 87,880.41 87,880.41 91,874.97 93,872.25
59 Tripleks 3 mm Lbr 95,000.00 111,015.80 119,341.99 122,117.38 127,668.17 122,117.38 122,117.38 122,117.38 127,668.17 130,443.57
60 Tripleks 3 mm semi meranti Lbr 70,000.00 82,196.80 88,361.56 90,416.48 94,526.32 90,416.48 90,416.48 90,416.48 94,526.32 96,581.24
61 Tripleks 3.6 mm lbr 78,000.00 91,418.88 98,275.30 100,560.77 105,131.71 100,560.77 100,560.77 100,560.77 105,131.71 107,417.18
62 Plywood 3 mm Lbr 95,000.00 111,015.80 119,341.99 122,117.38 127,668.17 122,117.38 122,117.38 122,117.38 127,668.17 130,443.57
63 Tripleks 4 mm Lbr 110,000.00 128,307.20 137,930.24 141,137.92 147,553.28 141,137.92 141,137.92 141,137.92 147,553.28 150,760.96
64 Tripleks 4 mm semi meranti Lbr 80,000.00 93,724.40 100,753.73 103,096.84 107,783.06 103,096.84 103,096.84 103,096.84 107,783.06 110,126.17
65 Plywood 4 mm lbr 82,500.00 96,606.30 103,851.77 106,266.93 111,097.25 106,266.93 106,266.93 106,266.93 111,097.25 113,512.40
66 Tripleks 5 mm lbr 150,000.00 174,417.60 187,498.92 191,859.36 200,580.24 191,859.36 191,859.36 191,859.36 200,580.24 204,940.68
67 Multiplek 6 mm lbr 125,000.00 145,598.60 156,518.50 160,158.46 167,438.39 160,158.46 160,158.46 160,158.46 167,438.39 171,078.36

Harga Satauan Bahan dan Upah Hal. 50


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA KRAMONGMONGGA MBAHAMDANDARA KARAS TELUK PATIPI ARGUNI FURWAGI BOMBERAY TOMAGE
DASAR
1 2 3 4 5 7 8 9 10 11 12 13 14
68 Plywood 6 mm lbr 102,487.00 119,646.51 128,620.00 131,611.17 137,593.49 131,611.17 131,611.17 131,611.17 137,593.49 140,584.65
69 Multiplek 9 mm lbr 183,000.00 212,458.68 228,393.08 233,704.55 244,327.48 233,704.55 233,704.55 233,704.55 244,327.48 249,638.95
70 Plywood 9 mm lbr 160,000.00 185,945.20 199,891.09 204,539.72 213,836.98 204,539.72 204,539.72 204,539.72 213,836.98 218,485.61
71 Multiplek 12 mm lbr 225,000.00 260,874.60 280,440.20 286,962.06 300,005.79 286,962.06 286,962.06 286,962.06 300,005.79 306,527.66
72 Plywood 12 mm lbr 210,000.00 243,583.20 261,851.94 267,941.52 280,120.68 267,941.52 267,941.52 267,941.52 280,120.68 286,210.26
73 Multiplek 18 mm lbr 290,000.00 335,804.00 360,989.30 369,384.40 386,174.60 369,384.40 369,384.40 369,384.40 386,174.60 394,569.70
74 Plywood aluminium lbr -
75 Teak wood (0,9x2,20) m2 lbr 98,000.00 115,977.68 124,676.01 127,575.45 133,374.33 127,575.45 127,575.45 127,575.45 133,374.33 136,273.77
76 Teak wood (1,20x2,40) m2 lbr 95,000.00 112,519.40 120,958.36 123,771.34 129,397.31 123,771.34 123,771.34 123,771.34 129,397.31 132,210.30
- - - - - - - - -
KERAMIK - - - - - - - - -
IKAD - - - - - - - - -
1 Ikad (Keramik) Kw. I 10 x 20 cm m2 51,480.00 62,351.28 67,027.63 68,586.41 71,703.98 68,586.41 68,586.41 68,586.41 71,703.98 73,262.76
2 Ikad (Keramik) Kw. I 20 x 20 cm m2 67,500.00 80,818.50 86,879.89 88,900.35 92,941.28 88,900.35 88,900.35 88,900.35 92,941.28 94,961.74
3 Ikad (Keramik) Kw. I 20 x 30 cm m2 85,000.00 100,991.80 108,566.19 111,090.98 116,140.57 111,090.98 111,090.98 111,090.98 116,140.57 118,665.37
4 Ikad (Keramik) Kw. I 30 x 30 cm m2 85,000.00 100,991.80 108,566.19 111,090.98 116,140.57 111,090.98 111,090.98 111,090.98 116,140.57 118,665.37
5 Ikad (Keramik) Kw. I 40 x 40 cm m2 78,000.00 92,922.48 99,891.67 102,214.73 106,860.85 102,214.73 102,214.73 102,214.73 106,860.85 109,183.91
6 Ikad (Keramik) Kw. II 10 x 20 cm m2 37,500.00 46,235.70 49,703.38 50,859.27 53,171.06 50,859.27 50,859.27 50,859.27 53,171.06 54,326.95
7 Ikad (Keramik) Kw. II 20 x 20 cm m2 39,500.00 48,541.22 52,181.81 53,395.34 55,822.40 53,395.34 53,395.34 53,395.34 55,822.40 57,035.93
8 Ikad (Keramik) Kw. II 20 x 30 cm m2 46,500.00 56,610.54 60,856.33 62,271.59 65,102.12 62,271.59 62,271.59 62,271.59 65,102.12 66,517.38
9 Ikad (Keramik) Kw. II 30 x 30 cm m2 48,500.00 58,916.06 63,334.76 64,807.67 67,753.47 64,807.67 64,807.67 64,807.67 67,753.47 69,226.37
10 Ikad (Keramik) Kw. II 40 x 40 cm m2 55,500.00 66,985.38 72,009.28 73,683.92 77,033.19 73,683.92 73,683.92 73,683.92 77,033.19 78,707.82
-
ELEYSIUM - - - - - - - - -
1 Ikad (Keramik) Kw. I 20 x 20 cm m2 60,000.00 72,172.80 77,585.76 79,390.08 82,998.72 79,390.08 79,390.08 79,390.08 82,998.72 84,803.04
2 Ikad (Keramik) Kw. I 20 x 30 cm m2 - - - - - - - - -
3 Ikad (Keramik) Kw. I 30 x 30 cm m2 90,000.00 106,755.60 114,762.27 117,431.16 122,768.94 117,431.16 117,431.16 117,431.16 122,768.94 125,437.83
4 Ikad (Keramik) Kw. I 40 x 40 cm m2 90,000.00 106,755.60 114,762.27 117,431.16 122,768.94 117,431.16 117,431.16 117,431.16 122,768.94 125,437.83
-
INESA - - - - - - - - -
1 Keramik 30 x 30 Kelas I (Onyx Phyrus Ruby Jade, P) m2 - - - - - - - - - -
2 Keramik 30 x 30 Kelas I (Onyx Phyrus Ruby Jade, UP) m2 - Err:522
3 Keramik 30 x 30 Kelas I (Pearl Ghita Cat Eye, P) m2 - Err:522
4 Keramik 30 x 30 Kelas I (Pearl Ghita Cat Eye, UP) m2 - Err:522
5 Keramik 30 x 30 Kelas I (Sand Wheat Spruce Clay Charcoal, R) m2 - Err:522
6 Keramik 40 x 40 Kelas I (Corypha Roystonea Raphia, P) m2 - -
7 Keramik 40 x 40 Kelas I (Onyx Phyrus Ruby Jade, P) m2 - Err:522
8 Keramik 40 x 40 Kelas I (Onyx Phyrus Ruby Jade, UP) m2 - Err:522
9 Keramik 40 x 40 Kelas I (Pearl Ghita Cat Eye, P) m2 - Err:522
10 Keramik 40 x 40 Kelas I (Pearl Ghita Cat Eye, UP) m2 - Err:522
11 Keramik 60 x 60 Kelas I (Corypha Roystonea Raphia, P) m2 - Err:522
-
ESSENZA -
1 Keramik 30 x 30 Kelas I (Black Orchid, Coral Bell, P) m2 - Err:522

Keramik 30 x 30 Kelas I (Black Orchid, Coral Bell, UP) -


2 m2 Err:522
3 Keramik 30 x 30 Kelas I (Pepper Grey Price Rubert Silver star, P) m2 - Err:522
4 Keramik 30 x 30 Kelas I (Pepper Grey Price Rubert Silver star, UP) m2 - Err:522
5 Keramik 40 x 40 Kelas I (Pepper Grey Price Rubert Silver star, P) m2 - Err:522
6 Keramik 40 x 40 Kelas I (Pepper Grey Price Rubert Silver star, UP) m2 - Err:522
7 Keramik 60 x 60 Kelas I (Pepper Grey Price Rubert Silver star, P) m2 - Err:522
8 Keramik Kelas I Domus m2 - Err:522
9 Keramik Kelas I Granity Imperiali m2 - Err:522
10 Keramik Kelas I Lavagna m2 - Err:522
11 Keramik Kelas I Mountain Peak m2 - Err:522
-
GARUDA - - - - - - - - -
1 Keramik 20 x 20 kelas I Emboss Dasar Muda m2 - - - - - - - - - -
2 Keramik 20 x 20 kelas I Emboss Dasar Tua m2 - - - - - - - - - -
3 Keramik 20 x 20 kelas I Tesia m2 - - - - - - - - - -
4 Keramik 20 x 20 kelas II Emboss Dasar Muda m2 - - - - - - - - - -
5 Keramik 20 x 20 kelas II Emboss Dasar Tua m2 - - - - - - - - - -
6 Keramik 20 x 20 kelas II Tesia m2 - - - - - - - - - -
7 Keramik 20 x 25 kelas I Motif Dasar Medium m2 - - - - - - - - - -
8 Keramik 20 x 25 kelas I Motif Dasar Muda m2 - - - - - - - - - -

Harga Satauan Bahan dan Upah Hal. 51


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA KRAMONGMONGGA MBAHAMDANDARA KARAS TELUK PATIPI ARGUNI FURWAGI BOMBERAY TOMAGE
DASAR
1 2 3 4 5 7 8 9 10 11 12 13 14
9 Keramik 20 x 25 kelas I Nuri Dark m2 - - - - - - - - - -
10 Keramik 20 x 25 kelas I Polos m2 - - - - - - - - - -
11 Keramik 30 x 30 kelas I Granity m2 - - - - - - - - - -
12 Keramik 30 x 30 kelas I Motif Embose m2 - - - - - - - - - -
13 Keramik 30 x 30 kelas II Granity m2 - - - - - - - - - -
14 Keramik 30 x 30 kelas II Motif Embose m2 - - - - - - - - - -
15 Keramik 40 x 40 kelas I Motif Dasar Muda m2 - - - - - - - - - -
16 Keramik 40 x 40 kelas I Motif Dasar Muda m2 - - - - - - - - - -
17 Keramik 40 x 40 kelas I Motif Embose m2 - - - - - - - - - -
18 Keramik 40 x 40 kelas I Motif Granity Tua m2 - - - - - - - - - -
19 Keramik 40 x 40 kelas I Motif Medium Color m2 - - - - - - - - - -
20 Keramik 40 x 40 kelas I Motif Spesial Color m2 - - - - - - - - - -
21 Keramik 50 x 50 kelas I m2 - - - - - - - - - -
22 Granito 60 x 60 m2 250,000.00 291,197.20 313,036.99 320,316.92 334,876.78 320,316.92 320,316.92 320,316.92 334,876.78 342,156.71
-
ASIA - - - - - - - - -
1 Keramik 10 x 10 kelas I warna muda m2 52,000.00 62,950.72 67,672.02 69,245.79 72,393.33 69,245.79 69,245.79 69,245.79 72,393.33 73,967.10
2 Keramik 10 x 20 kelas I warna muda m2 - 3,007.20 3,232.74 3,307.92 3,458.28 3,307.92 3,307.92 3,307.92 3,458.28 3,533.46
3 Keramik 20 x 20 kelas I warna muda m2 61,000.00 73,325.56 78,824.98 80,658.12 84,324.39 80,658.12 80,658.12 80,658.12 84,324.39 86,157.53
4 Keramik 20 x 20 kelas I warna tua m2 - 3,007.20 3,232.74 3,307.92 3,458.28 3,307.92 3,307.92 3,307.92 3,458.28 3,533.46
5 Keramik 20 x 25 kelas I warna tua m2 62,000.00 74,478.32 80,064.19 81,926.15 85,650.07 81,926.15 81,926.15 81,926.15 85,650.07 87,512.03
6 Keramik 20 x 30 kelas I warna muda m2 58,000.00 69,867.28 75,107.33 76,854.01 80,347.37 76,854.01 76,854.01 76,854.01 80,347.37 82,094.05
7 Keramik 30 x 30 kelas I warna muda m2 -
8 Keramik 30 x 30 kelas I warna tua m2 -
9 Keramik 40 x 40 kelas I warna muda m2 63,000.00 75,631.08 81,303.41 83,194.19 86,975.74 83,194.19 83,194.19 83,194.19 86,975.74 88,866.52
10 Keramik 40 x 40 warna platinum m2 70,000.00 83,700.40 89,977.93 92,070.44 96,255.46 92,070.44 92,070.44 92,070.44 96,255.46 98,347.97
11 Keramik 10 x 20 kelas II m2 88,000.00 - - - - - - - - -
12 Keramik 20 x 20 kelas II m2 - - - - - - - - - -
13 Keramik 20 x 30 kelas II m2 62,000.00 - - - - - - - - -
14 Keramik 30 x 30 kelas II m2 65,000.00 - - - - - - - - -
15 Keramik 40 x 40 kelas II m2 70,000.00 - - - - - - - - -
- - - - - - - - -
MULIA - - - - - - - - -
1 Keramik 10 x 20 cm kelas I m2 - - - - - - - - - -
2 Keramik 20 x 20 cm kelas I m2 85,000.00 100,991.80 108,566.19 111,090.98 116,140.57 111,090.98 111,090.98 111,090.98 116,140.57 118,665.37
3 Keramik 20 x 30 cm kelas I m2 - - - - - - - - - -
4 Keramik 30 x 30 cm kelas I m2 80,000.00 - - - - - - - - -
5 Keramik 40 x 40 cm kelas I m2 85,000.00 100,991.80 108,566.19 111,090.98 116,140.57 111,090.98 111,090.98 111,090.98 116,140.57 118,665.37
6 Keramik 10 x 20 cm kelas II m2 - - - - - - - - - -
7 Keramik 20 x 20 cm kelas II m2 - - - - - - - - - -
8 Keramik 20 x 30 cm kelas II m2 - - - - - - - - - -
9 Keramik 30 x 30 cm kelas II m2 - - - - - - - - - -
10 Keramik 40 x 40 cm kelas II m2 - - - - - - - - - -
- - - - - - - - -
PICASSO - - - - - - - - -
1 Ikad Keramik KW 1 20 x 20 cm m2 90,000.00 106,755.60 114,762.27 117,431.16 122,768.94 117,431.16 117,431.16 117,431.16 122,768.94 125,437.83
2 Ikad Keramik KW 1 20 x 25 cm m2 88,000.00 104,450.08 112,283.84 114,895.09 120,117.59 114,895.09 114,895.09 114,895.09 120,117.59 122,728.84
3 Ikad Keramik KW 1 30 x 30 cm m2 85,000.00 100,991.80 108,566.19 111,090.98 116,140.57 111,090.98 111,090.98 111,090.98 116,140.57 118,665.37
4 Ikad Keramik KW 1 40 x 40 cm m2 88,000.00 104,450.08 112,283.84 114,895.09 120,117.59 114,895.09 114,895.09 114,895.09 120,117.59 122,728.84
- - - - - - - - -
SANITAIR - - - - - - - - -
1 Bak mandi fibre glass 70x70x66 cm biasa bh 350,000.00 410,482.80 441,269.01 451,531.08 472,055.22 451,531.08 451,531.08 451,531.08 472,055.22 482,317.29
2 Bak mandi fibre glass 70x70x66 cm sudut bh 600,000.00 698,672.80 751,073.26 768,540.08 803,473.72 768,540.08 768,540.08 768,540.08 803,473.72 820,940.54
3 Bak mandi keramik 50x50 bh 165,000.00 197,222.20 212,013.87 216,944.42 226,805.53 216,944.42 216,944.42 216,944.42 226,805.53 231,736.09
4 Floor Drain " TOTO TypeTx 1 Bv 1 " Square Flange " bh 38,000.00 50,821.68 54,633.31 55,903.85 58,444.93 55,903.85 55,903.85 55,903.85 58,444.93 59,715.47
5 Floor drain plastik bh 20,000.00 30,072.00 32,327.40 33,079.20 34,582.80 33,079.20 33,079.20 33,079.20 34,582.80 35,334.60
6 Floor drain stainless bh 65,000.00 81,946.20 88,092.17 90,140.82 94,238.13 90,140.82 90,140.82 90,140.82 94,238.13 96,286.79
7 Floor drain plastik onda bh 28,000.00 39,294.08 42,241.14 43,223.49 45,188.19 43,223.49 43,223.49 43,223.49 45,188.19 46,170.54
8 Kloset duduk DATA komplit bh 900,000.00 1,044,500.80 1,122,838.36 1,148,950.88 1,201,175.92 1,148,950.88 1,148,950.88 1,148,950.88 1,201,175.92 1,227,288.44
9 Kloset duduk INA Komplit bh 2,400,000.00 2,773,640.80 2,981,663.86 3,051,004.88 3,189,686.92 3,051,004.88 3,051,004.88 3,051,004.88 3,189,686.92 3,259,027.94
10 Kloset duduk INA standard bh 750,000.00 871,586.80 936,955.81 958,745.48 1,002,324.82 958,745.48 958,745.48 958,745.48 1,002,324.82 1,024,114.49
11 Kloset duduk Amerika Standar bh -
Kloset duduk " TOTO Type AVANTE CW 821 PJ / SW 821JP
12 bh 3,000,000.00 3,725,194.06 3,811,826.48 3,985,091.32 3,811,826.48 3,811,826.48 3,811,826.48 3,985,091.32 4,071,723.74
COMPLIT 3,465,296.80

13 Kloset duduk " TOTO Type AVANTE CW 821J"/ SW 821JP COMPLIT bh 5,610,000.00 6,959,550.43 7,121,400.44 7,445,100.46 7,121,400.44 7,121,400.44 7,121,400.44 7,445,100.46 7,606,950.47
6,474,000.40

Harga Satauan Bahan dan Upah Hal. 52


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA KRAMONGMONGGA MBAHAMDANDARA KARAS TELUK PATIPI ARGUNI FURWAGI BOMBERAY TOMAGE
DASAR
1 2 3 4 5 7 8 9 10 11 12 13 14

14 Kloset duduk " TOTO Type AVANTE CW 823 J bh 5,600,000.00 6,947,158.26 7,108,720.08 7,431,843.72 7,108,720.08 7,108,720.08 7,108,720.08 7,431,843.72 7,593,405.54
6,462,472.80
15 Kloset duduk " TOTO Type CW 660J bh 602,800.00 701,900.53 754,543.07 772,090.58 807,185.61 772,090.58 772,090.58 772,090.58 807,185.61 824,733.12

16 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT bh 2,575,000.00 2,975,373.80 3,198,526.84 3,272,911.18 3,421,679.87 3,272,911.18 3,272,911.18 3,272,911.18 3,421,679.87 3,496,064.22

17 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT WARNA bh 1,491,000.00 1,855,215.61 1,898,360.16 1,984,649.25 1,898,360.16 1,898,360.16 1,898,360.16 1,984,649.25 2,027,793.80
1,725,781.96
18 Kloset duduk LOLO warna COMPLIT bh 1,800,000.00 2,081,984.80 2,238,133.66 2,290,183.28 2,394,282.52 2,290,183.28 2,290,183.28 2,290,183.28 2,394,282.52 2,446,332.14

19 Kloset duduk " TOTO Type CW 661JT1 BODI COMPLIT bh 2,796,200.00 3,472,641.64 3,553,400.74 3,714,918.96 3,553,400.74 3,553,400.74 3,553,400.74 3,714,918.96 3,795,678.07
3,230,364.31

20 Kloset duduk " TOTO Type CW 661JT1" / SW 661JP COMPLIT bh 2,190,000.00 2,721,428.29 2,784,717.32 2,911,295.38 2,784,717.32 2,784,717.32 2,784,717.32 2,911,295.38 2,974,584.41
2,531,561.20

21 Kloset duduk " TOTO Type CW 661JT1" / SW 784JP COMPLIT bh 1,734,700.00 2,157,212.79 2,207,380.53 2,307,716.01 2,207,380.53 2,207,380.53 2,207,380.53 2,307,716.01 2,357,883.75
2,006,709.57
22 Kloset jongkok " TOTO Type CE 6 COMPLIT bh 345,000.00 404,719.00 435,072.93 445,190.90 465,426.85 445,190.90 445,190.90 445,190.90 465,426.85 475,544.83
23 Kloset jongkok " TOTO bh 370,000.00 433,538.00 466,053.35 476,891.80 498,568.70 476,891.80 476,891.80 476,891.80 498,568.70 509,407.15
24 Kloset jongkok " TOTO Type CE 7 COMPLIT Set -
25 Kloset porselin jongkok Avena (standar) bh 150,000.00 179,930.80 193,425.61 197,923.88 206,920.42 197,923.88 197,923.88 197,923.88 206,920.42 211,418.69
26 Kloset porselin jongkok Kia (standar) bh 175,000.00 208,749.80 224,406.04 229,624.78 240,062.27 229,624.78 229,624.78 229,624.78 240,062.27 245,281.02
27 Kloset porselin jongkok VITO (standar) bh 190,000.00 226,041.20 242,994.29 248,645.32 259,947.38 248,645.32 248,645.32 248,645.32 259,947.38 265,598.41
28 Kloset porselin jongkok Ina (standar) bh 450,000.00 525,758.80 565,190.71 578,334.68 604,622.62 578,334.68 578,334.68 578,334.68 604,622.62 617,766.59
29 Kloset porselin jongkok America (standar) bh
30 Kloset porselin jongkok DUTY bh 150,000.00 179,930.80 193,425.61 197,923.88 206,920.42 197,923.88 197,923.88 197,923.88 206,920.42 211,418.69
31 Kloset porselin jongkok DATA bh -
32 Kloset porselin jongkok ROSI bh -
33 Kloset porselin jongkok CHELSEA bh -
34 Kran air 3/4 biasa dari besi bh 45,000.00 58,891.00 63,307.83 64,780.10 67,724.65 64,780.10 64,780.10 64,780.10 67,724.65 69,196.93
35 Kran air 3/4 biasa dari plastik bh 25,000.00 35,835.80 38,523.49 39,419.38 41,211.17 39,419.38 39,419.38 39,419.38 41,211.17 42,107.07
36 Kran air 1/2 biasa dari besi bh 40,000.00 53,127.20 57,111.74 58,439.92 61,096.28 58,439.92 58,439.92 58,439.92 61,096.28 62,424.46
37 Kran SunEi bh 99,000.00 121,140.04 130,225.54 133,254.04 139,311.05 133,254.04 133,254.04 133,254.04 139,311.05 142,339.55
38 Kran TOTO T 205 LCSC bh - - - - - - - - - -
39 Kran TOTO T 205 MC bh - - - - - - - - - -
40 Kran TOTO T 23 B13 bh - - - - - - - - - -
41 Kran TOTO T 23 B13V7N bh - - - - - - - - - -
42 Kran TOTO T 26 - 13 bh - - - - - - - - - -
43 Kran TOTO TX 109 LH bh - - - - - - - - - -
44 Kran washtafel bh 100,000.00 116,779.60 125,538.07 128,457.56 134,296.54 128,457.56 128,457.56 128,457.56 134,296.54 137,216.03
45 Kran cuci piring bh 120,000.00 139,834.80 150,322.41 153,818.28 160,810.02 153,818.28 153,818.28 153,818.28 160,810.02 164,305.89
46 Penyekat Urinoir " TOTO " Type A 100 " bh - - - - - - - - - -
47 Shower Spray " TOTO Tx 403SPIV ( Pastel Ivory ) bh 265,000.00 - - - - - - - - -
48 Shower Spray biasa bh 220,000.00 255,110.80 274,244.11 280,621.88 293,377.42 280,621.88 280,621.88 280,621.88 293,377.42 299,755.19
49 Shower Spray TOTO 12 bh - - - - - - - - - -
50 Shower Spray TOTO bh -
51 Soap holder " TOTO " Type S 6 N " bh - - - - - - - - -
52 Seal tape Besar bh 15,000.00 18,795.00 20,204.63 20,674.50 21,614.25 20,674.50 20,674.50 20,674.50 21,614.25 22,084.13
53 Seal tape kecil bh 10,000.00 13,031.20 14,008.54 14,334.32 14,985.88 14,334.32 14,334.32 14,334.32 14,985.88 15,311.66
54 Urinoir " TOTO U 57 M bh 1,052,000.00 1,214,207.12 1,305,272.65 1,335,627.83 1,396,338.19 1,335,627.83 1,335,627.83 1,335,627.83 1,396,338.19 1,426,693.37
55 Urinoir " TOTO U 57 M BODI bh - - - - - - - - -
56 Wastagel KIA Standard bh 595,000.00 687,395.80 738,950.49 756,135.38 790,505.17 756,135.38 756,135.38 756,135.38 790,505.17 807,690.07
57 Wastagel INA bh 900,000.00 1,038,987.60 1,116,911.67 1,142,886.36 1,194,835.74 1,142,886.36 1,142,886.36 1,142,886.36 1,194,835.74 1,220,810.43
58 Wastafel Komplit " TOTO Tx " Type L 521V1A " bh - - - - - - - - -
59 Wastafel Komplit top Counter" TOTO " Type CERABO LW 523 " bh - - - - - - - - -
60 Washtafel LOLO bh 750,000.00 871,586.80 936,955.81 958,745.48 1,002,324.82 958,745.48 958,745.48 958,745.48 1,002,324.82 1,024,114.49
61 Wastafel KIA Standar 2 (Lubang) bh 650,000.00 756,310.80 813,034.11 831,941.88 869,757.42 831,941.88 831,941.88 831,941.88 869,757.42 888,665.19
61 Washtafel cuci tangan kecil (Standard) bh 750,000.00 871,586.80 936,955.81 958,745.48 1,002,324.82 958,745.48 958,745.48 958,745.48 1,002,324.82 1,024,114.49
62 Washtafel cuci tangan besar (Standard) bh 650,000.00 756,310.80 813,034.11 831,941.88 869,757.42 831,941.88 831,941.88 831,941.88 869,757.42 888,665.19
63 Washtafel cuci piring 2 lubang bh 600,000.00 698,672.80 751,073.26 768,540.08 803,473.72 768,540.08 768,540.08 768,540.08 803,473.72 820,940.54
64 Washtafel cuci piring 1 lubang bh 300,000.00 352,844.80 379,308.16 388,129.28 405,771.52 388,129.28 388,129.28 388,129.28 405,771.52 414,592.64
65 Bak cuci piring single besar bh 650,000.00 756,310.80 813,034.11 831,941.88 869,757.42 831,941.88 831,941.88 831,941.88 869,757.42 888,665.19
66 Bak cuci piring double besar bh 450,000.00 525,758.80 565,190.71 578,334.68 604,622.62 578,334.68 578,334.68 578,334.68 604,622.62 617,766.59
67 Bak cuci piring single kecil bh 225,000.00 266,387.80 286,366.89 293,026.58 306,345.97 293,026.58 293,026.58 293,026.58 306,345.97 313,005.67
- - - - - - - - -
PAKU - - - - - - - - -
1 Paku 3 kg 27,000.00 32,628.12 35,075.23 35,890.93 37,522.34 35,890.93 35,890.93 35,890.93 37,522.34 38,338.04
2 Paku 4 kg 27,000.00 32,628.12 35,075.23 35,890.93 37,522.34 35,890.93 35,890.93 35,890.93 37,522.34 38,338.04

Harga Satauan Bahan dan Upah Hal. 53


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA KRAMONGMONGGA MBAHAMDANDARA KARAS TELUK PATIPI ARGUNI FURWAGI BOMBERAY TOMAGE
DASAR
1 2 3 4 5 7 8 9 10 11 12 13 14
3 Paku 5 biasa kg 30,000.00 36,086.40 38,792.88 39,695.04 41,499.36 39,695.04 39,695.04 39,695.04 41,499.36 42,401.52
4 Paku 5 putih kg 30,000.00 36,086.40 38,792.88 39,695.04 41,499.36 39,695.04 39,695.04 39,695.04 41,499.36 42,401.52
5 Paku 7 biasa kg 25,000.00 30,322.60 32,596.80 33,354.86 34,870.99 33,354.86 33,354.86 33,354.86 34,870.99 35,629.06
6 Paku 7 putih kg 30,000.00 36,086.40 38,792.88 39,695.04 41,499.36 39,695.04 39,695.04 39,695.04 41,499.36 42,401.52
7 Paku 8 putih kg -
8 Paku 9 putih kg -
9 Paku 10 biasa kg 25,000.00 30,322.60 32,596.80 33,354.86 34,870.99 33,354.86 33,354.86 33,354.86 34,870.99 35,629.06
10 Paku 10 putih kg 30,000.00 36,086.40 38,792.88 39,695.04 41,499.36 39,695.04 39,695.04 39,695.04 41,499.36 42,401.52
11 Paku 12 biasa kg 25,000.00 30,322.60 32,596.80 33,354.86 34,870.99 33,354.86 33,354.86 33,354.86 34,870.99 35,629.06
12 Paku 12 putih kg 30,000.00 36,086.40 38,792.88 39,695.04 41,499.36 39,695.04 39,695.04 39,695.04 41,499.36 42,401.52
13 Paku 14 biasa kg 22,000.00 26,864.32 28,879.14 29,550.75 30,893.97 29,550.75 29,550.75 29,550.75 30,893.97 31,565.58
14 Paku 15 biasa kg 25,000.00 30,322.60 32,596.80 33,354.86 34,870.99 33,354.86 33,354.86 33,354.86 34,870.99 35,629.06
15 Paku 15 putih kg 25,000.00 30,322.60 32,596.80 33,354.86 34,870.99 33,354.86 33,354.86 33,354.86 34,870.99 35,629.06
16 Paku kalsiboard kg 35,000.00 41,850.20 44,988.97 46,035.22 48,127.73 46,035.22 46,035.22 46,035.22 48,127.73 49,173.99
17 Paku list SQ kg 20,000.00 24,558.80 26,400.71 27,014.68 28,242.62 27,014.68 27,014.68 27,014.68 28,242.62 28,856.59
18 Paku pancing 60 x 230 kg 18,750.00 23,117.85 24,851.69 25,429.64 26,585.53 25,429.64 25,429.64 25,429.64 26,585.53 27,163.47
19 Paku reng/usuk SQ kg 20,000.00 24,558.80 26,400.71 27,014.68 28,242.62 27,014.68 27,014.68 27,014.68 28,242.62 28,856.59
20 Paku seng 1Kg kg 48,000.00 56,836.08 61,098.79 62,519.69 65,361.49 62,519.69 62,519.69 62,519.69 65,361.49 66,782.39
21 Paku seng import bj 55,000.00 64,905.40 69,773.31 71,395.94 74,641.21 71,395.94 71,395.94 71,395.94 74,641.21 76,263.85
22 Paku skrup 1/2" kg 120,000.00 139,834.80 150,322.41 153,818.28 160,810.02 153,818.28 153,818.28 153,818.28 160,810.02 164,305.89
23 Paku skrup 2" kg -
24 Paku skrup 3.5" kg 170,000.00 196,119.56 210,828.53 215,731.52 225,537.49 215,731.52 215,731.52 215,731.52 225,537.49 230,440.48
25 Paku skrup 1" bh 15,000.00 17,441.76 18,749.89 19,185.94 20,058.02 19,185.94 19,185.94 19,185.94 20,058.02 20,494.07
26 Paku beton kg 50,000.00 57,788.36 62,122.49 63,567.20 66,456.61 63,567.20 63,567.20 63,567.20 66,456.61 67,901.32
27 Paku tripleks kg 25,000.00 28,969.36- 31,142.06
- 31,866.30
- 33,314.76
- 31,866.30
- 31,866.30
- 31,866.30
- 33,314.76
- 34,039.00
-
PASIR, BATU, KERIKIL, BATA DAN PARAS - - - - - - - - -
1 Bata gosok ex Tobacco bj 50,000.00 59,848.11 64,336.72 65,832.92 68,825.33 65,832.92 65,832.92 65,832.92 68,825.33 70,321.53
2 Bata Merah 5 x 11 x 22 cm bj 8,000.00 11,432.19 12,289.61 12,575.41 13,147.02 12,575.41 12,575.41 12,575.41 13,147.02 13,432.82
3 Bata Ringan/ Bataco 7 x 20 x 60 bj 18,000.00 22,959.79 24,681.78 25,255.77 26,403.76 25,255.77 25,255.77 25,255.77 26,403.76 26,977.75
4 Bata Ringan/ Bataco 8 x 20 x 60 bj 20,000.00 25,265.31 27,160.21 27,791.84 29,055.11 27,791.84 27,791.84 27,791.84 29,055.11 29,686.74
5 Bata Ringan/ Bataco 10 x 20 x 60 bj 24,000.00 29,876.35 32,117.08 32,863.99 34,357.80 32,863.99 32,863.99 32,863.99 34,357.80 35,104.71
6 Batu tela bj 8,000.00 11,432.19 12,289.61 12,575.41 13,147.02 12,575.41 12,575.41 12,575.41 13,147.02 13,432.82
7 Batu gunung/ belah m3 500,000.00 777,862.40 836,202.08 855,648.64 894,541.76 855,648.64 855,648.64 855,648.64 894,541.76 913,988.32
8 Batu karang m3 128,571.00 349,693.91 375,920.95 384,663.30 402,147.99 384,663.30 384,663.30 384,663.30 402,147.99 410,890.34
9 Batu lahar Singaraja m3 138,000.00 360,563.28 387,605.53 396,619.61 414,647.77 396,619.61 396,619.61 396,619.61 414,647.77 423,661.85
10 Batu Pecah 2-3 m3 1,062,500.00 1,426,289.90 1,533,261.64 1,568,918.89 1,640,233.39 1,568,918.89 1,568,918.89 1,568,918.89 1,640,233.39 1,675,890.63
11 Batu Pecah 0.5-1/ciping m3 1,062,500.00 1,426,289.90 1,533,261.64 1,568,918.89 1,640,233.39 1,568,918.89 1,568,918.89 1,568,918.89 1,640,233.39 1,675,890.63
12 Batu Pecah 10-19 m3 1,000,000.00 1,354,242.40 1,455,810.58 1,489,666.64 1,557,378.76 1,489,666.64 1,489,666.64 1,489,666.64 1,557,378.76 1,591,234.82
13 Batu pipih Singaraja m3 150,000.00 374,396.40 402,476.13 411,836.04 430,555.86 411,836.04 411,836.04 411,836.04 430,555.86 439,915.77
14 Glass block 20cmx20cm bj 55,000.00 264,884.20 284,750.52 291,372.62 304,616.83 291,372.62 291,372.62 291,372.62 304,616.83 311,238.94
15 Glass block 30cmx30cm bh 250,000.00 489,672.40 526,397.83 538,639.64 563,123.26 538,639.64 538,639.64 538,639.64 563,123.26 575,365.07
16 Roster Keramik 30cmx30cm bh 85,000.00 299,467.00 321,927.03 329,413.70 344,387.05 329,413.70 329,413.70 329,413.70 344,387.05 351,873.73
17 Koral Beton m3 1,062,500.00 1,426,289.90 1,533,261.64 1,568,918.89 1,640,233.39 1,568,918.89 1,568,918.89 1,568,918.89 1,640,233.39 1,675,890.63
18 Limestone m3 79,000.00 292,550.44 314,491.72 321,805.48 336,433.01 321,805.48 321,805.48 321,805.48 336,433.01 343,746.77
19 Paras Batik bh - - - - - - - - -
20 Paras Buahan bh - - - - - - - - -
21 Paras Karang Bukit bh - - - - - - - - - -
22 Paras Kerobokan Tebal 5 bh - - - - - - - - - -
23 Paras Malem bh - - - - - - - - - -
24 Paras Putih Bukit bh - - - - - - - - - -
25 Paras Silakarang tebal bh - - - - - - - - - -
26 Paras Silakarang tipis bh - - - - - - - - - -
27 Paras untuk pondasi bh - - - - - - - - - -
28 Pasir halus m3 1,500,000.00 1,929,620.00 2,074,341.50 2,122,582.00 2,219,063.00 2,122,582.00 2,122,582.00 2,122,582.00 2,219,063.00 2,267,303.50
29 Pasir kasar m3 1,000,000.00 1,353,240.00 1,454,733.00 1,488,564.00 1,556,226.00 1,488,564.00 1,488,564.00 1,488,564.00 1,556,226.00 1,590,057.00
30 Pasir sedot / Lokal m3 500,000.00 776,860.00 835,124.50 854,546.00 893,389.00 854,546.00 854,546.00 854,546.00 893,389.00 912,810.50
31 Sirtu m3 250,000.00 488,670.00 525,320.25 537,537.00 561,970.50 537,537.00 537,537.00 537,537.00 561,970.50 574,187.25
32 Tanah urug m3 150,000.00 373,394.00 401,398.55 410,733.40 429,403.10 410,733.40 410,733.40 410,733.40 429,403.10 438,737.95
33 Filler/abu batu m3 1,062,500.00 1,425,287.50 1,532,184.06 1,567,816.25 1,639,080.63 1,567,816.25 1,567,816.25 1,567,816.25 1,639,080.63 1,674,712.81
34 Aspal drum 2,000,000.00 2,506,000.00 2,693,950.00 2,756,600.00 2,881,900.00 2,756,600.00 2,756,600.00 2,756,600.00 2,881,900.00 2,944,550.00
- - - - - - - - -
PIPA - - - - - - - - -
1 Pipa Galvanis 1/2" Medium A (tebal) m1 29,166.67 34,791.63 37,401.01 38,270.80 40,010.38 38,270.80 38,270.80 38,270.80 40,010.38 40,880.17
2 Pipa Galvanis 1/2" Medium B (tipis) m1 22,500.00 27,106.57 29,139.56 29,817.22 31,172.55 29,817.22 29,817.22 29,817.22 31,172.55 31,850.22
3 Pipa Galvanis 1/2' medium B (sedang) m1 24,166.67 29,027.83 31,204.92 31,930.62 33,382.01 31,930.62 31,930.62 31,930.62 33,382.01 34,107.70
4 Pipa Galvanis 3/4" Medium A (tebal) m1 36,333.33 43,053.08 46,282.06 47,358.39 49,511.04 47,358.39 47,358.39 47,358.39 49,511.04 50,587.37

Harga Satauan Bahan dan Upah Hal. 54


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA KRAMONGMONGGA MBAHAMDANDARA KARAS TELUK PATIPI ARGUNI FURWAGI BOMBERAY TOMAGE
DASAR
1 2 3 4 5 7 8 9 10 11 12 13 14
5 Pipa Galvanis 3/4" Medium A sedang m1 39,166.67 46,319.23 49,793.18 50,951.16 53,267.12 50,951.16 50,951.16 50,951.16 53,267.12 54,425.10
6 Pipa Galvanis 3/4" Medium B m1 30,000.00 35,752.27 38,433.69 39,327.49 41,115.11 39,327.49 39,327.49 39,327.49 41,115.11 42,008.91
7 Pipa Galvanis 1 1/4" m1 64,166.67 75,138.23 80,773.60 82,652.06 86,408.97 82,652.06 82,652.06 82,652.06 86,408.97 88,287.42
8 Pipa Galvanis 1 1/2" m1 74,166.67 86,665.83 93,165.77 95,332.42 99,665.71 95,332.42 95,332.42 95,332.42 99,665.71 101,832.35
9 Pipa Galvanis 1 1/2 " M.B m1 72,000.00 84,168.19 90,480.80 92,585.01 96,793.41 92,585.01 92,585.01 92,585.01 96,793.41 98,897.62
10 Pipa Galvanis 1" m1 -
11 Pipa Galvanis 1" MA m1 57,500.00 67,453.17 72,512.15 74,198.48 77,571.14 74,198.48 74,198.48 74,198.48 77,571.14 79,257.47
12 Pipa Galvanis 1" MB m1 58,333.33 68,413.80 73,544.84 75,255.18 78,675.87 75,255.18 75,255.18 75,255.18 78,675.87 80,386.22
13 Pipa Galvanis 1,5 BSA m1 55,500.00 65,147.65 70,033.72 71,662.41 74,919.79 71,662.41 71,662.41 71,662.41 74,919.79 76,548.48
14 Pipa Galvanis 2" m1 -
15 Pipa Galvanis 2" MA m1 100,000.00 116,445.47 125,178.88 128,090.01 133,912.29 128,090.01 128,090.01 128,090.01 133,912.29 136,823.42
16 Pipa Galvanis 2" MB m1 95,833.33 111,642.30 120,015.47 122,806.53 128,388.65 122,806.53 122,806.53 122,806.53 128,388.65 131,179.70
17 Pipa Galvanis 3" m1 137,500.00 159,673.97 171,649.51 175,641.36 183,625.06 175,641.36 175,641.36 175,641.36 183,625.06 187,616.91
18 Pipa Galvanis 3" MA m1 114,166.67 132,776.23 142,734.45 146,053.86 152,692.67 146,053.86 146,053.86 146,053.86 152,692.67 156,012.07
19 Pipa Galvanis 3" MB m1 175,833.33 203,863.10 219,152.83 224,249.41 234,442.57 224,249.41 224,249.41 224,249.41 234,442.57 239,539.14
20 Pipa Maspion AW 1 m1 12,500.00 15,578.97 16,747.39 17,136.86 17,915.81 17,136.86 17,136.86 17,136.86 17,915.81 18,305.29
21 Pipa Winlon AW 1 m1 15,000.00 18,460.87 19,845.43 20,306.95 21,230.00 20,306.95 20,306.95 20,306.95 21,230.00 21,691.52
22 Pipa Maspion AW 1/2 m1 8,750.00 11,256.12 12,100.33 12,381.73 12,944.53 12,381.73 12,381.73 12,381.73 12,944.53 13,225.94
23 Pipa Winlon AW 1/2 m1 8,750.00 11,256.12 12,100.33 12,381.73 12,944.53 12,381.73 12,381.73 12,381.73 12,944.53 13,225.94
24 Pipa Maspion AW 10 m1 -
25 Pipa Maspion AW 1-1/2 m1 - - - - - - - - - -
26 Pipa Winlon AW 1-1/2 m1 22,500.00 27,691.30 29,768.15 30,460.43 31,845.00 30,460.43 30,460.43 30,460.43 31,845.00 32,537.28
27 Pipa Maspion D 1-1/2 m1 - - - - - - - - - -
28 Pipa Winlon D 1-1/2 m1 13,750.00 17,604.65 18,925.00 19,365.12 20,245.35 19,365.12 19,365.12 19,365.12 20,245.35 20,685.46
29 Pipa Maspion AW 1-1/4 m1 - - - - - - - - - -
30 Pipa Winlon AW 1-1/4 m1 13,750.00 37,155.46 39,942.12 40,871.01 42,728.78 40,871.01 40,871.01 40,871.01 42,728.78 43,657.67
31 Pipa Maspion AW 12 m1 38,750.00 65,974.46 70,922.54 72,571.91 75,870.63 72,571.91 72,571.91 72,571.91 75,870.63 77,519.99
32 Pipa Maspion AW 14 m1 47,500.00 76,061.11 81,765.69 83,667.22 87,470.28 83,667.22 83,667.22 83,667.22 87,470.28 89,371.80
33 Pipa Maspion AW 16 m1 60,000.00 90,470.61 97,255.91 99,517.67 104,041.20 99,517.67 99,517.67 99,517.67 104,041.20 106,302.97
34 Pipa Maspion AW 2 m1 -
35 Pipa Winlon AW 2 m1 30,000.00 36,337.00 39,062.28 39,970.70 41,787.55 39,970.70 39,970.70 39,970.70 41,787.55 42,695.98
36 Pipa Maspion D 2 m1 -
37 Pipa Winlon D 2 m1 21,250.00 26,250.35 28,219.13 28,875.39 30,187.90 28,875.39 28,875.39 28,875.39 30,187.90 30,844.16
38 Pipa Maspion AW 2-1/2 m1 12,000.00 15,587.32 16,756.37 17,146.05 17,925.42 17,146.05 17,146.05 17,146.05 17,925.42 18,315.10
39 Pipa Maspion D 2-1/2 m1 - - - - - - - - - -
40 Pipa Winlon D 2-1/2 m1 22,500.00 27,691.30 29,768.15 30,460.43 31,845.00 30,460.43 30,460.43 30,460.43 31,845.00 32,537.28
41 Pipa Maspion AW 3 m1 - - - - - - - - - -
42 Pipa Winlon AW 3 m1 52,500.00 62,274.10 66,944.66 68,501.51 71,615.22 68,501.51 68,501.51 68,501.51 71,615.22 73,172.07
43 Pipa Maspion AW 3/4 m1 10,000.00 13,281.80 14,277.94 14,609.98 15,274.07 14,609.98 14,609.98 14,609.98 15,274.07 15,606.12
44 Pipa Winlon AW 3/4 m1 10,000.00 13,281.80 14,277.94 14,609.98 15,274.07 14,609.98 14,609.98 14,609.98 15,274.07 15,606.12
45 Pipa Maspion AW 4 m1 -
46 Pipa Winlon AW 4 m1 93,750.00 109,825.45 118,062.36 120,808.00 126,299.27 120,808.00 120,808.00 120,808.00 126,299.27 129,044.90
47 Pipa Maspion D 4" m1 40,000.00 47,864.60 51,454.45 52,651.06 55,044.29 52,651.06 52,651.06 52,651.06 55,044.29 56,240.91
48 Pipa Winlon D 4" m1 66,250.00 78,124.55 83,983.89 85,937.01 89,843.23 85,937.01 85,937.01 85,937.01 89,843.23 91,796.35
49 Pipa Maspion AW 5 m1 - - - - - - - - - -
50 Pipa Maspion AW 6 m1 - - - - - - - - - -
51 Pipa Maspion AW 8 m1 - - - - - - - - - -
52 Pipa Maspion C 1 m1 - - - - - - - - - -
53 Pipa Maspion C 1-1/2 m1 - - - - - - - - - -
54 Pipa Maspion C 1-1/4 m1 - - - - - - - - - -
55 Pipa Maspion C 2 m1 - - - - - - - - - -
56 Pipa Maspion C 2-1/2 m1 - - - - - - - - - -
57 Pipa Maspion C 3 m1 - - - - - - - - - -
58 Pipa Maspion C 3/4 m1 - - - - - - - - - -
59 Pipa Maspion C 4 m1 - - - - - - - - - -
60 Pipa Maspion C 5/8 m1 - - - - - - - - - -
61 Pipa Maspion D 10 m1 - - - - - - - - - -
62 Pipa Maspion D 1-1/2 m1 - - - - - - - - - -
63 Pipa Winlon D 1-1/2 m1 13,750.00 17,604.65 18,925.00 19,365.12 20,245.35 19,365.12 19,365.12 19,365.12 20,245.35 20,685.46
64 Pipa Winlon D 1-1/4 m1 12,500.00 16,163.70 17,375.98 17,780.07 18,588.26 17,780.07 17,780.07 17,780.07 18,588.26 18,992.35
65 Pipa Maspion D 1-1/4 m1 -
66 Pipa Maspion D 12 m1 - -
67 Pipa Maspion D 14 m1 - - - - - - - - - -
68 Pipa Maspion D 16 m1 - - - - - - - - - -
69 Pipa Maspion D 2 m1 - - - - - - - - - -
70 Pipa Maspion D 2-1/2 m1 -
71 Pipa Maspion D 3 m1 -

Harga Satauan Bahan dan Upah Hal. 55


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA KRAMONGMONGGA MBAHAMDANDARA KARAS TELUK PATIPI ARGUNI FURWAGI BOMBERAY TOMAGE
DASAR
1 2 3 4 5 7 8 9 10 11 12 13 14
72 Pipa Maspion D 4 m1 - - - - - - - - - -
73 Pipa Maspion D 5 m1 - - - - - - - - - -
74 Pipa Maspion D 6 m1 - - - - - - - - - -
75 Pipa Maspion D 8 m1 - - - - - - - - - -
76 Elbo 1/2" PVC bh 6,000.00 8,420.16 9,051.67 9,262.18 9,683.18 9,262.18 9,262.18 9,262.18 9,683.18 9,893.69
77 Elbo 3/4" PVC bh 8,000.00 10,725.68 11,530.11 11,798.25 12,334.53 11,798.25 11,798.25 11,798.25 12,334.53 12,602.67
78 Elbo PVC 4" bh 55,000.00 64,905.40 69,773.31 71,395.94 74,641.21 71,395.94 71,395.94 71,395.94 74,641.21 76,263.85
79 Elbo PVC 3" bh 30,000.00 36,086.40 38,792.88 39,695.04 41,499.36 39,695.04 39,695.04 39,695.04 41,499.36 42,401.52
80 Elbo PVC 2,5" bh 21,000.00 25,711.56 27,639.93 28,282.72 29,568.29 28,282.72 28,282.72 28,282.72 29,568.29 30,211.08
81 Selang hipres 1" m1 35,000.00 41,850.20 44,988.97 46,035.22 48,127.73 46,035.22 46,035.22 46,035.22 48,127.73 49,173.99
82 Selang hipres 2" m1 95,000.00 111,015.80 119,341.99 122,117.38 127,668.17 122,117.38 122,117.38 122,117.38 127,668.17 130,443.57
83 Selang hipres 1,5" m1 40,000.00 47,614.00 51,185.05 52,375.40 54,756.10 52,375.40 52,375.40 52,375.40 54,756.10 55,946.45
84 Selang hipres 0,5" m1 11,000.00 14,183.96 15,247.76 15,602.36 16,311.55 15,602.36 15,602.36 15,602.36 16,311.55 16,666.15
85 Selang spiral 2" m1 90,000.00 105,252.00 113,145.90 115,777.20 121,039.80 115,777.20 115,777.20 115,777.20 121,039.80 123,671.10
- - - - - - - - -
SEMEN - - - - - - - - -
1 Semen Gresik 40 kg kg 1,875.00 2,336.85 2,512.11 2,570.53 2,687.37 2,570.53 2,570.53 2,570.53 2,687.37 2,745.79
2 Semen Tiga Roga 40 kg kg - - - - - - - - - -
3 Semen Tonasa 40 kg kg 2,000.00 2,480.94 2,667.01 2,729.03 2,853.08 2,729.03 2,729.03 2,729.03 2,853.08 2,915.10
4 Semen Bosowa 40 kg kg - - - - - - - - - -
5 Semen warna/semen grouting kg 13,000.00 16,489.48 17,726.19 18,138.43 18,962.90 18,138.43 18,138.43 18,138.43 18,962.90 19,375.14
6 Semen putih kg 20,000.00 24,558.80 26,400.71 27,014.68 28,242.62 27,014.68 27,014.68 27,014.68 28,242.62 28,856.59
- - - - - - - - -
BESI BETON DAN PAGAR - - - - - - - - -
1 Besi beton kg 12,395.43 19,417.41 20,873.71 21,359.15 22,330.02 21,359.15 21,359.15 21,359.15 22,330.02 22,815.45
2 Besi beton Kg 12,395.43 19,417.41 20,873.71 21,359.15 22,330.02 21,359.15 21,359.15 21,359.15 22,330.02 22,815.45
3 Besi Beton Ulir - - - - - - - - -
Besi Beton Ulir 16 mm btg 195,000.00 - - - - - - - - -
Besi Beton Ulir 12 mm btg 105,000.00 - - - - - - - - -
Besi Beton Ulir 10 mm btg 75,000.00 - - - - - - - - -
4 Besi Beton - - - - - - - - -
Diameter 5.5 mm btg 30,000.00 - - - - - - - - -
Diameter 6 mm btg 36,000.00 - - - - - - - - -
Diameter 8 mm btg 68,000.00 - - - - - - - - -
Diameter 9 mm btg 75,000.00 - - - - - - - - -
Diameter 10 mm btg 110,000.00 - - - - - - - - -
Diameter 12 mm btg 160,000.00 - - - - - - - - -
Diameter 16 mm btg 239,000.00 - - - - - - - - -
Diameter 19 mm btg 298,000.00 - - - - - - - - -
Diameter 22 mm btg - - - - - - - - - -
Diameter 25 mm btg - - - - - - - - - -
5 Besi Siku 4x4 btg 210,000.00 245,086.80 263,468.31 269,595.48 281,849.82 269,595.48 269,595.48 269,595.48 281,849.82 287,976.99
6 Besi Siku 5 X 5 btg 375,000.00 435,292.20 467,939.12 478,821.42 500,586.03 478,821.42 478,821.42 478,821.42 500,586.03 511,468.34
7 Besi Siku Lubang btg 190,000.00 222,031.60 238,683.97 244,234.76 255,336.34 244,234.76 244,234.76 244,234.76 255,336.34 260,887.13
8 Besi UN 60 btg 405,000.00 469,875.00 505,115.63 516,862.50 540,356.25 516,862.50 516,862.50 516,862.50 540,356.25 552,103.13
9 Besi UN 80 btg 540,000.00 625,497.60 672,409.92 688,047.36 719,322.24 688,047.36 688,047.36 688,047.36 719,322.24 734,959.68
10 Besi Holous 20 x 40 btg 135,000.00 158,629.80 170,527.04 174,492.78 182,424.27 174,492.78 174,492.78 174,492.78 182,424.27 186,390.02
11 Besi Holous 40 x 40 btg 240,000.00 279,669.60 300,644.82 307,636.56 321,620.04 307,636.56 307,636.56 307,636.56 321,620.04 328,611.78
12 Kawat Bronjong ukuran 2 m kg 25,000.00 31,826.20 34,213.17 35,008.82 36,600.13 35,008.82 35,008.82 35,008.82 36,600.13 37,395.79
13 Kawat Bronjong ukuran 2,7 m kg - - - - - - - - - -
14 Kawat Bronjong ukuran 3 m kg - - - - - - - - - -
15 Kawat Bronjong ukuran 3,4 m kg -
16 Kawat Bronjong ukuran 4 m kg - - - - - - - - - -
17 Kawat berduri roll 130,000.00 156,875.60 168,641.27 172,563.16 180,406.94 172,563.16 172,563.16 172,563.16 180,406.94 184,328.83
18 Kawat beton RRT 1 Kg kg 25,000.00 35,835.80 38,523.49 39,419.38 41,211.17 39,419.38 39,419.38 39,419.38 41,211.17 42,107.07
19 Kawat ram m' 55,000.00 70,418.60 75,700.00 77,460.46 80,981.39 77,460.46 77,460.46 77,460.46 80,981.39 82,741.86
20 Kawat nyamuk m' 35,000.00 47,363.40 50,915.66 52,099.74 54,467.91 52,099.74 52,099.74 52,099.74 54,467.91 55,652.00
21 Kawat ayakan m' 45,000.00 58,891.00 63,307.83 64,780.10 67,724.65 64,780.10 64,780.10 64,780.10 67,724.65 69,196.93
22 Kawat Las RB Dos 300,000.00 352,844.80 379,308.16 388,129.28 405,771.52 388,129.28 388,129.28 388,129.28 405,771.52 414,592.64
23 Kawat Las 1kg kg 120,000.00 145,348.00 156,249.10 159,882.80 167,150.20 159,882.80 159,882.80 159,882.80 167,150.20 170,783.90
24 Kawat Ikat kg 30,000.00 41,599.60 44,719.57 45,759.56 47,839.54 45,759.56 45,759.56 45,759.56 47,839.54 48,879.53
25 Kawat Harmonika besar mtr 65,000.00 81,946.20 88,092.17 90,140.82 94,238.13 90,140.82 90,140.82 90,140.82 94,238.13 96,286.79
26 Kawat Harmonika sedang mtr 55,000.00 70,418.60 75,700.00 77,460.46 80,981.39 77,460.46 77,460.46 77,460.46 80,981.39 82,741.86
27 Pagar BRC FP 90 EP 1,5 Panil 475,200.00 554,808.35 596,418.98 610,289.19 638,029.60 610,289.19 610,289.19 610,289.19 638,029.60 651,899.81
28 Pagar BRC FP 90 EP 2,0 Panil 526,700.00 614,175.49 660,238.65 675,593.04 706,301.82 675,593.04 675,593.04 675,593.04 706,301.82 721,656.20
29 Pagar BRC FP 120 EP 1,5 Panil 607,600.00 707,433.78 760,491.31 778,177.15 813,548.84 778,177.15 778,177.15 778,177.15 813,548.84 831,234.69
30 Pagar BRC FP 120 EP 2,0 Panil 671,100.00 780,634.04 839,181.59 858,697.44 897,729.14 858,697.44 858,697.44 858,697.44 897,729.14 917,244.99

Harga Satauan Bahan dan Upah Hal. 56


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA KRAMONGMONGGA MBAHAMDANDARA KARAS TELUK PATIPI ARGUNI FURWAGI BOMBERAY TOMAGE
DASAR
1 2 3 4 5 7 8 9 10 11 12 13 14
31 Pagar BRC FP 150 EP 1,5 Panil 689,000.00 801,268.44 861,363.57 881,395.28 921,458.71 881,395.28 881,395.28 881,395.28 921,458.71 941,490.42
32 Pagar BRC FP 150 EP 2,0 Panil 754,500.00 876,774.22 942,532.29 964,451.64 1,008,290.35 964,451.64 964,451.64 964,451.64 1,008,290.35 1,030,209.71
33 Pagar BRC FP 175 EP 2,0 Panil 848,500.00 985,133.66 1,059,018.68 1,083,647.03 1,132,903.71 1,083,647.03 1,083,647.03 1,083,647.03 1,132,903.71 1,157,532.05
34 Pagar BRC FP 175 EP 2,5 Panil 926,500.00 1,075,048.94 1,155,677.61 1,182,553.83 1,236,306.28 1,182,553.83 1,182,553.83 1,182,553.83 1,236,306.28 1,263,182.50
35 Pagar BRC FP 190 EP 2,5 Panil 998,200.00 1,157,701.83 1,244,529.47 1,273,472.02 1,331,357.11 1,273,472.02 1,273,472.02 1,273,472.02 1,331,357.11 1,360,299.65
36 P90 EP dia.1,5" bh 120,659.79 146,108.58 157,066.72 160,719.44 168,024.87 160,719.44 160,719.44 160,719.44 168,024.87 171,677.58
37 P90 EP dia.2" bh 150,561.85 180,578.48 194,121.86 198,636.33 207,665.25 198,636.33 198,636.33 198,636.33 207,665.25 212,179.71
38 P120 EP dia.1,5" bh 144,449.74 173,532.68 186,547.63 190,885.95 199,562.58 190,885.95 190,885.95 190,885.95 199,562.58 203,900.90
39 P120 EP dia.2" bh 167,577.31 200,193.22 215,207.71 220,212.54 230,222.21 220,212.54 220,212.54 220,212.54 230,222.21 235,227.04
40 P150 EP dia.1,5" bh 166,239.69 198,651.26 213,550.10 218,516.39 228,448.95 218,516.39 218,516.39 218,516.39 228,448.95 233,415.23
41 P150 EP dia.2,0" bh 208,092.77 246,897.83 265,415.16 271,587.61 283,932.50 271,587.61 271,587.61 271,587.61 283,932.50 290,104.95
42 P175 EP dia.2,0" bh 249,865.97 295,052.29 317,181.22 324,557.52 339,310.14 324,557.52 324,557.52 324,557.52 339,310.14 346,686.44
43 P190 EP dia.1,0" bh 260,530.92 307,346.43 330,397.41 338,081.07 353,448.39 338,081.07 338,081.07 338,081.07 353,448.39 361,132.05
- - - - - - - - -
BAHAN LISTRIK - - - - - - - - -
1 Saklar (Broco) double bh 35,000.00 41,850.20 44,988.97 46,035.22 48,127.73 46,035.22 46,035.22 46,035.22 48,127.73 49,173.99
2 Saklar (Broco) engkle bh 32,000.00 38,391.92 41,271.31 42,231.11 44,150.71 42,231.11 42,231.11 42,231.11 44,150.71 45,110.51
3 Saklar (Oni) double bh 14,000.00 17,642.24 18,965.41 19,406.46 20,288.58 19,406.46 19,406.46 19,406.46 20,288.58 20,729.63
4 Saklar (Oni) engkle bh 13,000.00 16,489.48 17,726.19 18,138.43 18,962.90 18,138.43 18,138.43 18,138.43 18,962.90 19,375.14
5 Saklar tunggal philip bh 55,000.00 64,905.40 69,773.31 71,395.94 74,641.21 71,395.94 71,395.94 71,395.94 74,641.21 76,263.85
6 Saklar ganda philip bh 45,000.00 53,377.80 57,381.14 58,715.58 61,384.47 58,715.58 58,715.58 58,715.58 61,384.47 62,718.92
7 Stop kontak philip bh 45,000.00 53,377.80 57,381.14 58,715.58 61,384.47 58,715.58 58,715.58 58,715.58 61,384.47 62,718.92
8 Stop Kontak (Oni) bh 12,000.00 15,336.72 16,486.97 16,870.39 17,637.23 16,870.39 16,870.39 16,870.39 17,637.23 18,020.65
9 Stop Kontak (Oni) 2 lubang bh 20,000.00 24,558.80 26,400.71 27,014.68 28,242.62 27,014.68 27,014.68 27,014.68 28,242.62 28,856.59
10 Stop Kontak (Vticon) 2 lubang bh 15,000.00 18,795.00 20,204.63 20,674.50 21,614.25 20,674.50 20,674.50 20,674.50 21,614.25 22,084.13
11 Stop Kontak (Oni) 3 lubang bh 30,000.00 36,086.40 38,792.88 39,695.04 41,499.36 39,695.04 39,695.04 39,695.04 41,499.36 42,401.52
12 Stop Kontak (Oni) 4 lubang bh 40,000.00 47,614.00 51,185.05 52,375.40 54,756.10 52,375.40 52,375.40 52,375.40 54,756.10 55,946.45
13 Fitting Biasa bh 24,000.00 29,169.84 31,357.58 32,086.82 33,545.32 32,086.82 32,086.82 32,086.82 33,545.32 34,274.56
14 Fitting keramik bh 80,000.00 93,724.40 100,753.73 103,096.84 107,783.06 103,096.84 103,096.84 103,096.84 107,783.06 110,126.17
15 Steker biasa bh 20,000.00 24,558.80 26,400.71 27,014.68 28,242.62 27,014.68 27,014.68 27,014.68 28,242.62 28,856.59
16 Steker Broco bh 20,000.00 24,558.80 26,400.71 27,014.68 28,242.62 27,014.68 27,014.68 27,014.68 28,242.62 28,856.59
17 Coaxial cable 5C - 75 ohm commscof m1 5,700.00 8,074.33 8,679.91 8,881.77 9,285.48 8,881.77 8,881.77 8,881.77 9,285.48 9,487.34
18 Kabel NYM 3 x 2.5 mm ex. Supreme m1 20,000.00 24,558.80 26,400.71 27,014.68 28,242.62 27,014.68 27,014.68 27,014.68 28,242.62 28,856.59
19 Kabel NYM 3 x 1.5 mm ex. Eterna m1 16,000.00 19,947.76 21,443.84 21,942.54 22,939.92 21,942.54 21,942.54 21,942.54 22,939.92 23,438.62
20 Kabel NYM 4 mm m1 21,000.00 25,711.56 27,639.93 28,282.72 29,568.29 28,282.72 28,282.72 28,282.72 29,568.29 30,211.08
21 Kabel NYA 4mm rol 500,000.00 577,883.60 621,224.87 635,671.96 664,566.14 635,671.96 635,671.96 635,671.96 664,566.14 679,013.23
22 Kabel telephone m1 5,000.00 7,267.40 7,812.46 7,994.14 8,357.51 7,994.14 7,994.14 7,994.14 8,357.51 8,539.20
23 Lampu 8 Watt (Philip) bh 45,000.00 53,377.80 57,381.14 58,715.58 61,384.47 58,715.58 58,715.58 58,715.58 61,384.47 62,718.92
24 Lampu 8 Watt (Philip) Tornado bh 45,000.00 53,377.80 57,381.14 58,715.58 61,384.47 58,715.58 58,715.58 58,715.58 61,384.47 62,718.92
25 Lampu 11 Watt (Philip) bh 36,000.00 43,002.96 46,228.18 47,303.26 49,453.40 47,303.26 47,303.26 47,303.26 49,453.40 50,528.48
26 Lampu 14 Watt (Philip) bh 40,000.00 47,614.00 51,185.05 52,375.40 54,756.10 52,375.40 52,375.40 52,375.40 54,756.10 55,946.45
27 Lampu 18 Watt (Philip) bh 45,000.00 53,377.80 57,381.14 58,715.58 61,384.47 58,715.58 58,715.58 58,715.58 61,384.47 62,718.92
28 Lampu 20 Watt (Philip) bh 53,000.00 62,599.88 67,294.87 68,859.87 71,989.86 68,859.87 68,859.87 68,859.87 71,989.86 73,554.86
29 Lampu 23 Watt (Philip) bh 60,000.00 70,669.20 75,969.39 77,736.12 81,269.58 77,736.12 77,736.12 77,736.12 81,269.58 83,036.31
30 Lampu 24 Watt (Philip) bh 60,000.00 70,669.20 75,969.39 77,736.12 81,269.58 77,736.12 77,736.12 77,736.12 81,269.58 83,036.31
31 Lampu 24 Watt (Philip) tornado bh 58,000.00 68,363.68 73,490.96 75,200.05 78,618.23 75,200.05 75,200.05 75,200.05 78,618.23 80,327.32
32 Lampu 15 Watt (Philip) tornado bh 50,000.00 59,141.60 63,577.22 65,055.76 68,012.84 65,055.76 65,055.76 65,055.76 68,012.84 69,491.38
33 Lampu downlight 3,5" bh 45,000.00 53,377.80 57,381.14 58,715.58 61,384.47 58,715.58 58,715.58 58,715.58 61,384.47 62,718.92
34 Lampu downlight 4" bh 70,000.00 82,196.80 88,361.56 90,416.48 94,526.32 90,416.48 90,416.48 90,416.48 94,526.32 96,581.24
35 Lampu downlight 5" bh 85,000.00 99,488.20 106,949.82 109,437.02 114,411.43 109,437.02 109,437.02 109,437.02 114,411.43 116,898.64
36 Isolasi unibelt bh 20,000.00 24,558.80 26,400.71 27,014.68 28,242.62 27,014.68 27,014.68 27,014.68 28,242.62 28,856.59
37 Pipa clipsal 20 mm bt 25,000.00 30,322.60 32,596.80 33,354.86 34,870.99 33,354.86 33,354.86 33,354.86 34,870.99 35,629.06
38 Pipa flexible clipsal 20 mm m1 40,000.00 47,614.00 51,185.05 52,375.40 54,756.10 52,375.40 52,375.40 52,375.40 54,756.10 55,946.45
39 Sock clipsal 20 mm bj 4,000.00 6,114.64 6,573.24 6,726.10 7,031.84 6,726.10 6,726.10 6,726.10 7,031.84 7,184.70
40 Tee dos clipsal 20 mm bh 10,000.00 13,031.20 14,008.54 14,334.32 14,985.88 14,334.32 14,334.32 14,334.32 14,985.88 15,311.66
41 Klem clipsal 0,5 " bj 5,000.00 7,267.40 7,812.46 7,994.14 8,357.51 7,994.14 7,994.14 7,994.14 8,357.51 8,539.20
42 Inbow dos plastik clipsal E 157 P bj 13,000.00 16,489.48 17,726.19 18,138.43 18,962.90 18,138.43 18,138.43 18,138.43 18,962.90 19,375.14
- - - - - - - - -
PAVING - - - - - - - - -
1 Paving 10 x 20 cm tebal 6 cm K225 m2 - -
2 Paving 10 x 20 cm tebal 6 cm K350 m2 - -
3 Paving 10 x 20 cm tebal 8 cm K225 m2 - -
4 Paving 10 x 20 cm tebal 8 cm K350 m2 - -
5 Paving 10 x 20 cm tebal 8 cm K425 m2 - -
6 Paving 20 x 20 cm tebal 6 cm K225 m2 - -
7 Paving 20 x 20 cm tebal 6 cm K350 m2 - -
8 Paving 20 x 20 cm tebal 8 cm K225 m2 - -

Harga Satauan Bahan dan Upah Hal. 57


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA KRAMONGMONGGA MBAHAMDANDARA KARAS TELUK PATIPI ARGUNI FURWAGI BOMBERAY TOMAGE
DASAR
1 2 3 4 5 7 8 9 10 11 12 13 14
9 Paving 20 x 20 cm tebal 8 cm K350 m2 - -
10 Paving 20 x 20 cm tebal 8 cm K425 m2 - -
11 Paving 20 x 20 cm tebal 10 cm K225 m2 - -
12 Paving 20 x 20 cm tebal 10 cm K350 m2 - -
13 Paving 20 x 20 cm tebal 10 cm K425 m2 - -
14 Paving Tiga Berlian tebal 6 cm K225 m2 - -
15 Kanstein Bulat (P:50,T:30,La:10,Lb:16 cm K225) m1 - -
16 Kanstein Jumbo (P:50,L:15,T:30 cm K225) m1 - -
17 Kanstein Segi Lima Jumbo (P:50,L:15, T:40 cm K225) m1 - -
18 Grass Block 36 X 54 cm tebal 9 cm K 225 m2 - - - - - - - - - -
19 Koral Sikat zak/10 kg -
-
LAIN-LAIN - - - - - - - - -
1 Dugul batu hitam 50 x 50 x 200 unit - -
2 Dugul batu hitam 60 x 70 x 250 unit - -
3 Dugul batu hitam 70 x 70 x 250 unit - -
4 Padmasari batu hitam 50 x 50 x 200 unit - -
5 Padmasari batu hitam 70 x 70 x 250 unit - -
6 Padmasari batu hitam 65 x 75 x 225 unit - -
7 Karpet plastik m2 18,000.00 27,766.48 29,848.97 30,543.13 31,931.45 30,543.13 30,543.13 30,543.13 31,931.45 32,625.61
8 Talang PVC P= 4M', L=4" bentuk bulat buah 145,000.00 174,167.00 187,229.53 191,583.70 200,292.05 191,583.70 191,583.70 191,583.70 200,292.05 204,646.23
9 Talang PVC P= 4M', L=4" bentuk kotak buah 175,000.00 208,749.80 224,406.04 229,624.78 240,062.27 229,624.78 229,624.78 229,624.78 240,062.27 245,281.02
10 Talang PVC P= 4M', L=8" bentuk kotak buah 250,000.00 295,206.80 317,347.31 324,727.48 339,487.82 324,727.48 324,727.48 324,727.48 339,487.82 346,867.99
11 Talang PVC P= 4M', L=6" bentuk bulat buah 90,000.00 110,765.20 119,072.59 121,841.72 127,379.98 121,841.72 121,841.72 121,841.72 127,379.98 130,149.11
12 Talang PVC P= 4M', L=40" bentuk bulat buah -
13 Talang PVC P= 4M', L=140 mm" bentuk kotak buah 115,000.00 139,584.20 150,053.02 153,542.62 160,521.83 153,542.62 153,542.62 153,542.62 160,521.83 164,011.44
14 Talang PVC P= 4M', L: 8' buah 98,000.00 119,987.28 128,986.33 131,986.01 137,985.37 131,986.01 131,986.01 131,986.01 137,985.37 140,985.05

Fakfak, 12 Februari 2018


PANITIA PENYUSUNAN STANDART HARGA SATUAN HARGA
TAHUN 2018

Sekretaris, Ketua,

RIZAL MINGGELE, ST LIZA NEIRASARI, ST


NIP. 19820701 200909 1 001 NIP. 19751016 200111 2 001

Mengetahui,
Kepala Dinas PU, Penataan Ruang, Perumahan Rakyat
dan Kawasan Permukiman
Kabupaten Fakfak ,

SAMAUN DAHLAN S.Sos, MAP


NIP. 19681005 199108 1 002

Harga Satauan Bahan dan Upah Hal. 58


PEMERINTAH KABUPATEN FAKFAK
DINAS PU, PENATAAN RUANG, PERUMAHAN RAKYAT
DAN KAWASAN PERMUKIMAN
Jl. Achmad Yani No. 08 Fakfak, Telp. (0956) 22320 - 22709

DAFTAR HARGA SATUAN BAHAN DAN UPAH


TAHUN ANGGARAN 2018
A. Harga Satuan Bahan
NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA FAKFAK FAKFAK TENGAH PARIWARI FAKFAK BARAT WARTUTIN FAKFAK TIMUR FAKFAK TIMUR KOKAS KAYUNI
DASAR TENGAH

1 2 3 4 5 6 7 8 9 10 11 12 13 6
1.00 1.015 1.015 1.025 1.04 1.1 1.04 1.1 1.06
FINISHING
1 Amplas lbr 8,000.00 10,725.68 10,725.68 10,886.57 10,886.57 10,993.82 11,154.71 11,798.25 11,154.71 11,798.25 11,369.22
2 Amplas mtr 20,000.00 24,558.80 24,558.80 24,927.18 24,927.18 25,172.77 25,541.15 27,014.68 25,541.15 27,014.68 26,032.33
3 Amplas kain lbr 15,000.00 18,795.00 18,795.00 19,076.93 19,076.93 19,264.88 19,546.80 20,674.50 19,546.80 20,674.50 19,922.70
4 Kawat has m' 45,000.00 53,377.80 53,377.80 54,178.47 54,178.47 54,712.25 55,512.91 58,715.58 55,512.91 58,715.58 56,580.47
5 Kawat has Plastik lbr 20,000.00 24,558.80 24,558.80 24,927.18 24,927.18 25,172.77 25,541.15 27,014.68 25,541.15 27,014.68 26,032.33
6 Cat besi (Hamerton) Kaleng 1 kg kg 85,000.00 99,488.20 99,488.20 100,980.52 100,980.52 101,975.41 103,467.73 109,437.02 103,467.73 109,437.02 105,457.49
7 Cat besi (Avian) Kaleng 1 kg kg 75,000.00 87,960.60 87,960.60 89,280.01 89,280.01 90,159.62 91,479.02 96,756.66 91,479.02 96,756.66 93,238.24
8 Cat Besi (polibest) kaleng 1 kg kg 68,750.00 80,755.85 80,755.85 81,967.19 81,967.19 82,774.75 83,986.08 88,831.44 83,986.08 88,831.44 85,601.20
9 Cat Meni Besi/dasar (Polibest) Kaleng 0,8 kg kg 68,750.00 80,755.85 80,755.85 81,967.19 81,967.19 82,774.75 83,986.08 88,831.44 83,986.08 88,831.44 85,601.20
10 Cat Meni Besi/dasar (Yoko) Kaleng 0,8 kg kg 47,500.00 56,259.70 56,259.70 57,103.60 57,103.60 57,666.19 58,510.09 61,885.67 58,510.09 61,885.67 59,635.28
11 Cat kayu+Besi/dasar (polibest) kaleng 0.8 kg kg 75,000.00 87,960.60 87,960.60 89,280.01 89,280.01 90,159.62 91,479.02 96,756.66 91,479.02 96,756.66 93,238.24
12 Cat kayu+Besi/dasar (Yoko) kaleng 0.8 kg kg 62,500.00 73,551.10 73,551.10 74,654.37 74,654.37 75,389.88 76,493.14 80,906.21 76,493.14 80,906.21 77,964.17
13 Cat Kayu Yoko kg 65,000.00 76,433.00 76,433.00 77,579.50 77,579.50 78,343.83 79,490.32 84,076.30 79,490.32 84,076.30 81,018.98
14 Cat menie besi (Glotex) Kaleng 1 kg kg 35,000.00 41,850.20 41,850.20 42,477.95 42,477.95 42,896.46 43,524.21 46,035.22 43,524.21 46,035.22 44,361.21
15 Cat menie besi (Yoko) Kaleng 1 kg kg 25,000.00 30,322.60 30,322.60 30,777.44 30,777.44 31,080.67 31,535.50 33,354.86 31,535.50 33,354.86 32,141.96
16 Cat menie besi (Delmas) Kaleng 1 kg kg - - - - - - - - - -
17 Cat menie besi (Avian) Kaleng 1 kg kg 65,000.00 76,433.00 76,433.00 77,579.50 77,579.50 78,343.83 79,490.32 84,076.30 79,490.32 84,076.30 81,018.98
18 Cat menie kayu (polibest) 0,8 kg kg 60,000.00 70,669.20 70,669.20 71,729.24 71,729.24 72,435.93 73,495.97 77,736.12 73,495.97 77,736.12 74,909.35
19 Cat menie kayu (Avian) 1kg kg 80,000.00 93,724.40 93,724.40 95,130.27 95,130.27 96,067.51 97,473.38 103,096.84 97,473.38 103,096.84 99,347.86
20 Cat tembok Decolith kg - - - - - - - - - -
21 Cat tembok (Jotun) kg 265,000.00 308,488.60 308,488.60 313,115.93 313,115.93 316,200.82 320,828.14 339,337.46 320,828.14 339,337.46 326,997.92
22 Cat tembok Grahalux 5 Kg kg - - -
23 Cat tembok Paragon 5 Kg kg 27,000.00 34,131.72 34,131.72 34,643.70 34,643.70 34,985.01 35,496.99 37,544.89 35,496.99 37,544.89 36,179.62
24 Cat tembok (aries) 5 kg kg 21,000.00 27,215.16 27,215.16 27,623.39 27,623.39 27,895.54 28,303.77 29,936.68 28,303.77 29,936.68 28,848.07
25 Cat tembok Toyopaint kg - - - - - - - - - -
26 Cat tembok (vitex) Kaleng 5 kg kg 24,000.00 30,673.44 30,673.44 31,133.54 31,133.54 31,440.28 31,900.38 33,740.78 31,900.38 33,740.78 32,513.85
27 Cat tembok (vitex) Kaleng 4.5 kg kg 13,333.33 18,377.33 18,377.33 18,652.99 18,652.99 18,836.77 19,112.43 20,215.07 19,112.43 20,215.07 19,479.97
29 Cat monilex klg 125,000.00 147,102.20 147,102.20 149,308.73 149,308.73 150,779.76 152,986.29 161,812.42 152,986.29 161,812.42 155,928.33
30 Dempul kayu (polibest) 0,8 Kg kg 50,000.00 60,645.20 60,645.20 61,554.88 61,554.88 62,161.33 63,071.01 66,709.72 63,071.01 66,709.72 64,283.91
31 Dempul kayu (Pedang) 0.8 kg kg 60,000.00 72,172.80 72,172.80 73,255.39 73,255.39 73,977.12 75,059.71 79,390.08 75,059.71 79,390.08 76,503.17
32 Dempul kayu (Impra) 1 kg liter 65,000.00 77,936.60 77,936.60 79,105.65 79,105.65 79,885.02 81,054.06 85,730.26 81,054.06 85,730.26 82,612.80
34 Kuas Besar 5 inch bh 35,000.00 43,353.80 43,353.80 44,004.11 44,004.11 44,437.65 45,087.95 47,689.18 45,087.95 47,689.18 45,955.03
35 Kuas Besar 4 inch bh 30,000.00 37,590.00 37,590.00 38,153.85 38,153.85 38,529.75 39,093.60 41,349.00 39,093.60 41,349.00 39,845.40
36 Kuas Sedang 3 inch bh 25,000.00 31,826.20 31,826.20 32,303.59 32,303.59 32,621.86 33,099.25 35,008.82 33,099.25 35,008.82 33,735.77
37 Kuas roll 7" bh 40,000.00 49,117.60 49,117.60 49,854.36 49,854.36 50,345.54 51,082.30 54,029.36 51,082.30 54,029.36 52,064.66
38 Kuas roll 10" bh 50,000.00 60,645.20 60,645.20 61,554.88 61,554.88 62,161.33 63,071.01 66,709.72 63,071.01 66,709.72 64,283.91
38 Kuas roll 4" bh 33,000.00 41,048.28 41,048.28 41,664.00 41,664.00 42,074.49 42,690.21 45,153.11 42,690.21 45,153.11 43,511.18
39 Kuas Kecil 2 inch bh 20,000.00 26,062.40 26,062.40 26,453.34 26,453.34 26,713.96 27,104.90 28,668.64 27,104.90 28,668.64 27,626.14
40 Mild zak 30,000.00 37,590.00 37,590.00 38,153.85 38,153.85 38,529.75 39,093.60 41,349.00 39,093.60 41,349.00 39,845.40
41 Minyak cat/Thiner A Kaleng 0,8 liter ltr 50,000.00 60,645.20 60,645.20 61,554.88 61,554.88 62,161.33 63,071.01 66,709.72 63,071.01 66,709.72 64,283.91
42 Plamir kayu 1kg kg 80,000.00 95,228.00 95,228.00 96,656.42 96,656.42 97,608.70 99,037.12 104,750.80 99,037.12 104,750.80 100,941.68
43 Plamir tembok 5 kg merk B0y0 kg 16,000.00 21,451.36 21,451.36 21,773.13 21,773.13 21,987.64 22,309.41 23,596.50 22,309.41 23,596.50 22,738.44
44 Plamir tembok 5 kg merk lion kg 11,000.00 15,687.56 15,687.56 15,922.87 15,922.87 16,079.75 16,315.06 17,256.32 16,315.06 17,256.32 16,628.81
45 Plamir tembok 5 kg merk Paragon kg 17,000.00 22,604.12 22,604.12 22,943.18 22,943.18 23,169.22 23,508.28 24,864.53 23,508.28 24,864.53 23,960.37
46 Plamir tembok 5 kg kg 11,000.00 15,687.56 15,687.56 15,922.87 15,922.87 16,079.75 16,315.06 17,256.32 16,315.06 17,256.32 16,628.81
47 Politur (Boyo) kaleng 1 liter ltr 75,000.00 89,464.20 89,464.20 90,806.16 90,806.16 91,700.81 93,042.77 98,410.62 93,042.77 98,410.62 94,832.05
48 Politur (Joly) kaleng 1 liter ltr 45,000.00 54,881.40 54,881.40 55,704.62 55,704.62 56,253.44 57,076.66 60,369.54 57,076.66 60,369.54 58,174.28
49 Politur (vernis) kaleng 1 liter kg 80,000.00 95,228.00 95,228.00 96,656.42 96,656.42 97,608.70 99,037.12 104,750.80 99,037.12 104,750.80 100,941.68
50 Politur (india) kaleng 1 liter ltr 47,500.00 57,763.30 57,763.30 58,629.75 58,629.75 59,207.38 60,073.83 63,539.63 60,073.83 63,539.63 61,229.10
51 Thiner A kaleng 1/2 liter Ltr 60,000.00 72,172.80 72,172.80 73,255.39 73,255.39 73,977.12 75,059.71 79,390.08 75,059.71 79,390.08 76,503.17
52 Thiner A Avian kaleng 1 liter ltr 55,000.00 66,409.00 66,409.00 67,405.14 67,405.14 68,069.23 69,065.36 73,049.90 69,065.36 73,049.90 70,393.54
53 Thiner A kaleng 1 liter Ltr 44,000.00 53,728.64 53,728.64 54,534.57 54,534.57 55,071.86 55,877.79 59,101.50 55,877.79 59,101.50 56,952.36
54 Thiner B Avian kaleng 1 liter ltr 40,000.00 49,117.60 49,117.60 49,854.36 49,854.36 50,345.54 51,082.30 54,029.36 51,082.30 54,029.36 52,064.66

Harga Satauan Bahan dan Upah Hal. 59


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA FAKFAK FAKFAK TENGAH PARIWARI FAKFAK BARAT WARTUTIN FAKFAK TIMUR FAKFAK TIMUR KOKAS KAYUNI
DASAR TENGAH

1 2 3 4 5 6 7 8 9 10 11 12 13 6
55 Thiner B Super kaleng 1 liter Ltr 32,000.00 39,895.52 39,895.52 40,493.95 40,493.95 40,892.91 41,491.34 43,885.07 41,491.34 43,885.07 42,289.25
56 Thiner Super 5 kg kg 40,000.00 49,117.60 49,117.60 49,854.36 49,854.36 50,345.54 51,082.30 54,029.36 51,082.30 54,029.36 52,064.66
57 Thiner A Spesial 5 kg kg 38,000.00 46,812.08 46,812.08 47,514.26 47,514.26 47,982.38 48,684.56 51,493.29 48,684.56 51,493.29 49,620.80
58 Impra 1 Liter ltr 70,000.00 83,700.40 83,700.40 84,955.91 84,955.91 85,792.91 87,048.42 92,070.44 87,048.42 92,070.44 88,722.42
59 impra clear / sanding 1 l Ltr 73,000.00 87,158.68 87,158.68 88,466.06 88,466.06 89,337.65 90,645.03 95,874.55 90,645.03 95,874.55 92,388.20
60 impra wood stain 1 l Ltr 76,000.00 90,616.96 90,616.96 91,976.21 91,976.21 92,882.38 94,241.64 99,678.66 94,241.64 99,678.66 96,053.98
- - - - - - - - -
BAHAN BAKAR MINYAK - - - - - - - - -
1 Premium PBBKB 100% Ltr 8,350.03 12,632.78 12,632.78 12,822.27 12,822.27 12,948.60 13,138.09 13,896.06 13,138.09 13,896.06 13,390.75
2 Minyak Tanah Ltr 10,000.90 14,535.84 14,535.84 14,753.88 14,753.88 14,899.23 15,117.27 15,989.42 15,117.27 15,989.42 15,407.99
3 Minyak Solar B-0 ( 1 KL ) PBBKB 17 % (1,275%) Ltr 10,400.00 14,995.90 14,995.90 15,220.84 15,220.84 15,370.80 15,595.74 16,495.49 15,595.74 16,495.49 15,895.66
4 Minyak Solar B-0 ( 1 KL ) PBBKB 90 % (6,75%) Ltr 10,400.00 14,995.90 14,995.90 15,220.84 15,220.84 15,370.80 15,595.74 16,495.49 15,595.74 16,495.49 15,895.66
5 Minyak Solar B-0 ( 1 KL ) PBBKB 100% (7,5%) Ltr 10,400.00 14,995.90 14,995.90 15,220.84 15,220.84 15,370.80 15,595.74 16,495.49 15,595.74 16,495.49 15,895.66
6 Minyak Diesel Ltr - - - - - - - - -
7 Minyak Bakar Ltr - - - - - - - - -
8 Gemuk /Stempel 20 kg kg - - - - - - - - - -
9 Gemuk /Stempel 16 kg kg - -
- - - - - - - - -
PENUTUP ATAP - - - - - - - - -
1 Alang-alang panjang 2,4 meter lbr - -
2 Alluminium foil m2 29,000.00 34,933.64 34,933.64 35,457.64 35,457.64 35,806.98 36,330.99 38,427.00 36,330.99 38,427.00 37,029.66
3 Asbes Bubungan lbr 24,000.00 29,169.84 29,169.84 29,607.39 29,607.39 29,899.09 30,336.63 32,086.82 30,336.63 32,086.82 30,920.03
4 Asbes Gelombang 1,80 m x 0,80 m x 5 mm lbr 33,600.00 40,236.34 40,236.34 40,839.88 40,839.88 41,242.24 41,845.79 44,259.97 41,845.79 44,259.97 42,650.52
5 Asbes Gelombang 2,4 m x 1,05 m x 4 mm lbr 42,000.00 49,919.52 49,919.52 50,668.31 50,668.31 51,167.51 51,916.30 54,911.47 51,916.30 54,911.47 52,914.69
6 Asbes Rata 2 m x 1 m x 4 mm lbr 18,000.00 22,253.28 22,253.28 22,587.08 22,587.08 22,809.61 23,143.41 24,478.61 23,143.41 24,478.61 23,588.48
7 Besi profil WF kg 16,500.00 20,524.14 20,524.14 20,832.00 20,832.00 21,037.24 21,345.11 22,576.55 21,345.11 22,576.55 21,755.59
8 Besi strip 1kg kg 7,260.00 9,872.64 9,872.64 10,020.73 10,020.73 10,119.45 10,267.54 10,859.90 10,267.54 10,859.90 10,465.00
9 Bubungan Biasa bj -
10 Bubungan Plentong bj 7,200.00 9,803.47 9,803.47 9,950.52 9,950.52 10,048.56 10,195.61 10,783.82 10,195.61 10,783.82 10,391.68
11 Genteng plentong dicat bj 1,380.00 3,094.41 3,094.41 3,140.82 3,140.82 3,171.77 3,218.19 3,403.85 3,218.19 3,403.85 3,280.07
12 Genteng Plentong bj 1,560.00 3,301.91 3,301.91 3,351.43 3,351.43 3,384.45 3,433.98 3,632.10 3,433.98 3,632.10 3,500.02
13 Ijuk m3 20,000.00 24,558.80 24,558.80 24,927.18 24,927.18 25,172.77 25,541.15 27,014.68 25,541.15 27,014.68 26,032.33
14 Tali Ijuk Kg - - - - - - - - - -
15 Formite/Penjaga Jarak Bekisting/Spacer Bh - - - - - - - - - -
16 Seng BJLS 0,20 gelombang lbr 65,000.00 76,433.00 76,433.00 77,579.50 77,579.50 78,343.83 79,490.32 84,076.30 79,490.32 84,076.30 81,018.98
17 Seng BJLS 0.20 gelombang gajah berlian lbr 59,000.00 69,516.44 69,516.44 70,559.19 70,559.19 71,254.35 72,297.10 76,468.08 72,297.10 76,468.08 73,687.43
18 Seng BJLS 0,25 gelombang lbr 68,000.00 79,891.28 79,891.28 81,089.65 81,089.65 81,888.56 83,086.93 87,880.41 83,086.93 87,880.41 84,684.76
19 Seng BJLS 0,28 gelombang lbr - - - - - - - - - -
20 Seng BJLS 0,30 gelombang lbr 80,000.00 93,724.40 93,724.40 95,130.27 95,130.27 96,067.51 97,473.38 103,096.84 97,473.38 103,096.84 99,347.86
21 Seng Plat BJLS 30 lebar 28 cm lbr 22,000.00 26,864.32 26,864.32 27,267.28 27,267.28 27,535.93 27,938.89 29,550.75 27,938.89 29,550.75 28,476.18
22 Seng Plat BJLS 30 lebar 30 cm m' 25,000.00 30,322.60 30,322.60 30,777.44 30,777.44 31,080.67 31,535.50 33,354.86 31,535.50 33,354.86 32,141.96
23 Seng Plat BJLS 30 lebar 38 cm m' 32,000.00 38,391.92 38,391.92 38,967.80 38,967.80 39,351.72 39,927.60 42,231.11 39,927.60 42,231.11 40,695.44
24 Seng Plat BJLS 30 lebar 40 cm m' 30,000.00 36,086.40 36,086.40 36,627.70 36,627.70 36,988.56 37,529.86 39,695.04 37,529.86 39,695.04 38,251.58
25 Seng Plat BJLS 30 lebar 44 cm m' 35,000.00 41,850.20 41,850.20 42,477.95 42,477.95 42,896.46 43,524.21 46,035.22 43,524.21 46,035.22 44,361.21
26 Seng Plat BJLS 20 lebar 30 cm m' 15,000.00 18,795.00 18,795.00 19,076.93 19,076.93 19,264.88 19,546.80 20,674.50 19,546.80 20,674.50 19,922.70
27 Seng Plat BJLS 20 lebar 28 cm m' 15,000.00 18,795.00 18,795.00 19,076.93 19,076.93 19,264.88 19,546.80 20,674.50 19,546.80 20,674.50 19,922.70
28 Seng Plat BJLS 20 lebar 40 cm m' 25,000.00 30,322.60 30,322.60 30,777.44 30,777.44 31,080.67 31,535.50 33,354.86 31,535.50 33,354.86 32,141.96
29 Seng Plat BJLS 30 pintu lbr 82,000.00 96,029.92 96,029.92 97,470.37 97,470.37 98,430.67 99,871.12 105,632.91 99,871.12 105,632.91 101,791.72
30 Seng Plat BJLS 20 pintu m' 63,000.00 74,127.48 74,127.48 75,239.39 75,239.39 75,980.67 77,092.58 81,540.23 77,092.58 81,540.23 78,575.13
31 Seng plastik gelombang besar tebal lbr 95,000.00 111,015.80 111,015.80 112,681.04 112,681.04 113,791.20 115,456.43 122,117.38 115,456.43 122,117.38 117,676.75
32 Seng plastik gelombang kecil tebal lbr 55,000.00 64,905.40 64,905.40 65,878.98 65,878.98 66,528.04 67,501.62 71,395.94 67,501.62 71,395.94 68,799.72
33 Seng plastik gelombang besar tipis lbr 80,000.00 93,724.40 93,724.40 95,130.27 95,130.27 96,067.51 97,473.38 103,096.84 97,473.38 103,096.84 99,347.86
34 Seng Fiber gelombang besar tebal lbr 70,000.00 82,196.80 82,196.80 83,429.75 83,429.75 84,251.72 85,484.67 90,416.48 85,484.67 90,416.48 87,128.61
35 Sirap Jati bh 10,200.00 13,261.75 13,261.75 13,460.68 13,460.68 13,593.30 13,792.22 14,587.93 13,792.22 14,587.93 14,057.46
36 AT roof Bjls 30, 0,8x0,8 lbr 47,000.00 55,683.32 55,683.32 56,518.57 56,518.57 57,075.40 57,910.65 61,251.65 57,910.65 61,251.65 59,024.32
37 Rainbouw roof Bjls 30, 0,3x1,2 lbr 45,000.00 53,377.80 53,377.80 54,178.47 54,178.47 54,712.25 55,512.91 58,715.58 55,512.91 58,715.58 56,580.47
38 Bubungan rainbouw roof Bjls 30, 1,2 m' Bh 45,000.00 53,377.80 53,377.80 54,178.47 54,178.47 54,712.25 55,512.91 58,715.58 55,512.91 58,715.58 56,580.47
39 Multiroof BJ 300 lbr 90,000.00 105,252.00 105,252.00 106,830.78 106,830.78 107,883.30 109,462.08 115,777.20 109,462.08 115,777.20 111,567.12
40 Bubungan multiroof Bh 55,000.00 64,905.40 64,905.40 65,878.98 65,878.98 66,528.04 67,501.62 71,395.94 67,501.62 71,395.94 68,799.72
41 Igi roof 0,2 uk. 0,8x0,8 m' lbr 45,000.00 53,377.80 53,377.80 54,178.47 54,178.47 54,712.25 55,512.91 58,715.58 55,512.91 58,715.58 56,580.47
42 Sakura roof BJ 30 lbr 48,000.00 56,836.08 56,836.08 57,688.62 57,688.62 58,256.98 59,109.52 62,519.69 59,109.52 62,519.69 60,246.24
-
PENGGANTUNG -
1 Engsel jendela biasa ps 20,000.00 24,558.80 24,558.80 24,927.18 24,927.18 25,172.77 25,541.15 27,014.68 25,541.15 27,014.68 26,032.33
2 Engsel jendela biasa Merk King ps 30,000.00 36,086.40 36,086.40 36,627.70 36,627.70 36,988.56 37,529.86 39,695.04 37,529.86 39,695.04 38,251.58
3 Engsel jendela biasa merk king 3' ps 45,000.00 53,377.80 53,377.80 54,178.47 54,178.47 54,712.25 55,512.91 58,715.58 55,512.91 58,715.58 56,580.47
4 Engsel jendela merek King 4" ps 30,000.00 36,086.40 36,086.40 36,627.70 36,627.70 36,988.56 37,529.86 39,695.04 37,529.86 39,695.04 38,251.58
5 Engsel kupu-kupu jendela biasa ps 25,000.00 30,322.60 30,322.60 30,777.44 30,777.44 31,080.67 31,535.50 33,354.86 31,535.50 33,354.86 32,141.96

Harga Satauan Bahan dan Upah Hal. 60


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA FAKFAK FAKFAK TENGAH PARIWARI FAKFAK BARAT WARTUTIN FAKFAK TIMUR FAKFAK TIMUR KOKAS KAYUNI
DASAR TENGAH

1 2 3 4 5 6 7 8 9 10 11 12 13 6
6 Engsel kupu-kupu jendela biasa 3" ps 85,000.00 99,488.20 99,488.20 100,980.52 100,980.52 101,975.41 103,467.73 109,437.02 103,467.73 109,437.02 105,457.49
7 Engsel Jendela Bagus Kuningan ps 50,000.00 59,141.60 59,141.60 60,028.72 60,028.72 60,620.14 61,507.26 65,055.76 61,507.26 65,055.76 62,690.10
8 Engsel jendela bagus kuningan modem 4' ps 50,000.00 59,141.60 59,141.60 60,028.72 60,028.72 60,620.14 61,507.26 65,055.76 61,507.26 65,055.76 62,690.10
9 Engsel jendela bagus kuningan 4' ps 30,000.00 36,086.40 36,086.40 36,627.70 36,627.70 36,988.56 37,529.86 39,695.04 37,529.86 39,695.04 38,251.58
10 Engsel kupu-kupu pintu biasa ps 45,000.00 53,377.80 53,377.80 54,178.47 54,178.47 54,712.25 55,512.91 58,715.58 55,512.91 58,715.58 56,580.47
11 Engsel kupu-kupu pintu biasa 4" ps 25,000.00 30,322.60 30,322.60 30,777.44 30,777.44 31,080.67 31,535.50 33,354.86 31,535.50 33,354.86 32,141.96
12 Engsel kupu-kupu pintu biasa 4cmx3cmx3mm merk jezz ps 35,000.00 41,850.20 41,850.20 42,477.95 42,477.95 42,896.46 43,524.21 46,035.22 43,524.21 46,035.22 44,361.21
13 Engsel kupu-kupu pintu biasa AFC 4cmx3cmx3mm merk king ps - -
14 Engsel kupu-kupu pintu biasa 4cmx3cmx3mm merk viper ps 30,000.00 36,086.40 36,086.40 36,627.70 36,627.70 36,988.56 37,529.86 39,695.04 37,529.86 39,695.04 38,251.58
15 Engsel nylon ps 20,000.00 24,558.80 24,558.80 24,927.18 24,927.18 25,172.77 25,541.15 27,014.68 25,541.15 27,014.68 26,032.33
16 Espagnoleth set 35,000.00 41,850.20 41,850.20 42,477.95 42,477.95 42,896.46 43,524.21 46,035.22 43,524.21 46,035.22 44,361.21
17 Grendel kecil biasa bh 12,000.00 15,336.72 15,336.72 15,566.77 15,566.77 15,720.14 15,950.19 16,870.39 15,950.19 16,870.39 16,256.92
18 Grendel kecil bagus bh 20,000.00 24,558.80 24,558.80 24,927.18 24,927.18 25,172.77 25,541.15 27,014.68 25,541.15 27,014.68 26,032.33
19 Grendel kecil spring knife brabus/ses bh 30,000.00 36,086.40 36,086.40 36,627.70 36,627.70 36,988.56 37,529.86 39,695.04 37,529.86 39,695.04 38,251.58
20 Grendel kecil biasa 3" bh 20,000.00 24,558.80 24,558.80 24,927.18 24,927.18 25,172.77 25,541.15 27,014.68 25,541.15 27,014.68 26,032.33
21 Grendel kecil bagus 2" bh 15,000.00 18,795.00 18,795.00 19,076.93 19,076.93 19,264.88 19,546.80 20,674.50 19,546.80 20,674.50 19,922.70
22 Grendel kecil spring knife bh 15,000.00 18,795.00 18,795.00 19,076.93 19,076.93 19,264.88 19,546.80 20,674.50 19,546.80 20,674.50 19,922.70
23 Grendel besar 12" bh 45,000.00 53,377.80 53,377.80 54,178.47 54,178.47 54,712.25 55,512.91 58,715.58 55,512.91 58,715.58 56,580.47
24 Grendel besar bh 15,000.00 18,795.00 18,795.00 19,076.93 19,076.93 19,264.88 19,546.80 20,674.50 19,546.80 20,674.50 19,922.70
25 Grendel hararo bh 18,425.00 22,743.20 22,743.20 23,084.35 23,084.35 23,311.78 23,652.93 25,017.52 23,652.93 25,017.52 24,107.80
26 Kaca 3 mm bening lbr 230,000.00 266,638.40 266,638.40 270,637.98 270,637.98 273,304.36 277,303.94 293,302.24 277,303.94 293,302.24 282,636.70
27 Kaca 3 mm bening 153x122 m2 m2 133,933.35 155,896.61 155,896.61 158,235.06 158,235.06 159,794.03 162,132.48 171,486.28 162,132.48 171,486.28 165,250.41
28 Kaca 5 mm bening lbr 325,000.00 376,150.60 376,150.60 381,792.86 381,792.86 385,554.37 391,196.62 413,765.66 391,196.62 413,765.66 398,719.64
29 Kaca 5 mm bening 200 x 100 m2 147,500.00 171,535.70 171,535.70 174,108.74 174,108.74 175,824.09 178,397.13 188,689.27 178,397.13 188,689.27 181,827.84
30 Kaca 5 mm bening 153x122 m2 m2 187,506.70 217,653.82 217,653.82 220,918.63 220,918.63 223,095.17 226,359.97 239,419.20 226,359.97 239,419.20 230,713.05
31 Kaca 6 mm bening 153x122 m2 m2 - - - -
32 Kaca 8 mm bening 153x122 m2 m2 - - - -
33 Kaca 10 mm bening m2 - - - - - - - - - -
34 Kaca 12 mm bening m2 - - - - - - - - - -
35 Kaca Es/Kapur 3 mm m2 - - - - - - - - - - -
36 Kaca Es/Kapur 5 mm m2 - -
37 Kaca nako bening bh 21,000.00 25,711.56 25,711.56 26,097.23 26,097.23 26,354.35 26,740.02 28,282.72 26,740.02 28,282.72 27,254.25
38 Kaca nako rayben bh 25,000.00 30,322.60 30,322.60 30,777.44 30,777.44 31,080.67 31,535.50 33,354.86 31,535.50 33,354.86 32,141.96
39 Kaca ryben 3 mm 153x122 cm m2 187,506.70 217,653.82 217,653.82 220,918.63 220,918.63 223,095.17 226,359.97 239,419.20 226,359.97 239,419.20 230,713.05
40 Kaca ryben 5 mm 153x122 cm m2 200,900.03 233,093.12 233,093.12 236,589.52 236,589.52 238,920.45 242,416.85 256,402.43 242,416.85 256,402.43 247,078.71
41 Kaca Ryben 5 mm 183 x 132 cm m2 124,192.75 144,668.03 144,668.03 146,838.05 146,838.05 148,284.73 150,454.75 159,134.83 150,454.75 159,134.83 153,348.11
42 Kaca ryben 5 mm 200x100 cm m2 157,500.00 183,063.30 183,063.30 185,809.25 185,809.25 187,639.88 190,385.83 201,369.63 190,385.83 201,369.63 194,047.10
43 Cermin 3 mm 153x122 cm m2 310,725.38 359,695.39 359,695.39 365,090.82 365,090.82 368,687.78 374,083.21 395,664.93 374,083.21 395,664.93 381,277.12
44 Cermin 5 mm 183 x 122 m2 194,840.10 226,107.47 226,107.47 229,499.08 229,499.08 231,760.16 235,151.77 248,718.22 235,151.77 248,718.22 239,673.92
45 Kait angin biasa ps 20,000.00 24,558.80 24,558.80 24,927.18 24,927.18 25,172.77 25,541.15 27,014.68 25,541.15 27,014.68 26,032.33
46 Kait angin bagus bh 45,000.00 53,377.80 53,377.80 54,178.47 54,178.47 54,712.25 55,512.91 58,715.58 55,512.91 58,715.58 56,580.47
47 Kunci pintu Delmanao bh - - - - - - - - - -
48 Kunci pintu Zeis bh 285,000.00 330,040.20 330,040.20 334,990.80 334,990.80 338,291.21 343,241.81 363,044.22 343,241.81 363,044.22 349,842.61
49 Kunci pintu TOP bh 65,000.00 76,433.00 76,433.00 77,579.50 77,579.50 78,343.83 79,490.32 84,076.30 79,490.32 84,076.30 81,018.98
50 Kunci pintu Union bh - -
51 Kunci pintu Cap Kuda bodi kecil bh 120,000.00 139,834.80 139,834.80 141,932.32 141,932.32 143,330.67 145,428.19 153,818.28 145,428.19 153,818.28 148,224.89
52 Kunci pintu Cap Kuda bodi besar bh 135,000.00 157,126.20 157,126.20 159,483.09 159,483.09 161,054.36 163,411.25 172,838.82 163,411.25 172,838.82 166,553.77
53 Kunci pintu Royal bh 160,000.00 185,945.20 185,945.20 188,734.38 188,734.38 190,593.83 193,383.01 204,539.72 193,383.01 204,539.72 197,101.91
54 Kunci pintu Globe K bh 135,000.00 157,126.20 157,126.20 159,483.09 159,483.09 161,054.36 163,411.25 172,838.82 163,411.25 172,838.82 166,553.77
55 Kunci pintu Yale bh 225,000.00 260,874.60 260,874.60 264,787.72 264,787.72 267,396.47 271,309.58 286,962.06 271,309.58 286,962.06 276,527.08
56 Kunci pintu vanessa bh 125,000.00 145,598.60 145,598.60 147,782.58 147,782.58 149,238.57 151,422.54 160,158.46 151,422.54 160,158.46 154,334.52
57 Kunci pintu Kodai bh 185,000.00 214,764.20 214,764.20 217,985.66 217,985.66 220,133.31 223,354.77 236,240.62 223,354.77 236,240.62 227,650.05
58 Kunci pintu Sapphire bh 275,000.00 318,512.60 318,512.60 323,290.29 323,290.29 326,475.42 331,253.10 350,363.86 331,253.10 350,363.86 337,623.36
59 Kunci slot kecil HPP bh 28,000.00 33,780.88 33,780.88 34,287.59 34,287.59 34,625.40 35,132.12 37,158.97 35,132.12 37,158.97 35,807.73
60 Kunci slot sedang HPP bh 35,000.00 41,850.20 41,850.20 42,477.95 42,477.95 42,896.46 43,524.21 46,035.22 43,524.21 46,035.22 44,361.21
61 Kunci slot besar HPP bh 55,000.00 64,905.40 64,905.40 65,878.98 65,878.98 66,528.04 67,501.62 71,395.94 67,501.62 71,395.94 68,799.72
62 Kunci slot kecil bh 40,000.00 47,614.00 47,614.00 48,328.21 48,328.21 48,804.35 49,518.56 52,375.40 49,518.56 52,375.40 50,470.84
63 Kunci slot kecil ATS bh 48,000.00 56,836.08 56,836.08 57,688.62 57,688.62 58,256.98 59,109.52 62,519.69 59,109.52 62,519.69 60,246.24
64 Kunci slot sedang bh 32,000.00 38,391.92 38,391.92 38,967.80 38,967.80 39,351.72 39,927.60 42,231.11 39,927.60 42,231.11 40,695.44
65 Kunci slot sedang ATS bh 35,000.00 41,850.20 41,850.20 42,477.95 42,477.95 42,896.46 43,524.21 46,035.22 43,524.21 46,035.22 44,361.21
66 Kunci slot besar bh 50,000.00 59,141.60 59,141.60 60,028.72 60,028.72 60,620.14 61,507.26 65,055.76 61,507.26 65,055.76 62,690.10
67 Kunci Silinder bh 55,000.00 64,905.40 64,905.40 65,878.98 65,878.98 66,528.04 67,501.62 71,395.94 67,501.62 71,395.94 68,799.72
68 Kunci tanam 2 slag Biasa bh 175,000.00 203,236.60 203,236.60 206,285.15 206,285.15 208,317.52 211,366.06 223,560.26 211,366.06 223,560.26 215,430.80
69 Kunci tanam 2 slag Bagus bh 195,000.00 226,291.80 226,291.80 229,686.18 229,686.18 231,949.10 235,343.47 248,920.98 235,343.47 248,920.98 239,869.31
70 Kunci tanam 2 slag bagus merk Azzuro bh - - - - - - - - - -
71 Kunci tanam 2 slag bagus merk Giardano bh - - - - - - - - - - -
- - - - - - - - -

Harga Satauan Bahan dan Upah Hal. 61


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA FAKFAK FAKFAK TENGAH PARIWARI FAKFAK BARAT WARTUTIN FAKFAK TIMUR FAKFAK TIMUR KOKAS KAYUNI
DASAR TENGAH

1 2 3 4 5 6 7 8 9 10 11 12 13 6
KAYU DAN PLAFOND - - - - - - - - -
1 Bambu besar Ukuran 4 m btg 20,000.00 24,558.80 24,558.80 24,927.18 24,927.18 25,172.77 25,541.15 27,014.68 25,541.15 27,014.68 26,032.33
2 Bambu sedang Ukuran 4 m btg 15,000.00 18,795.00 18,795.00 19,076.93 19,076.93 19,264.88 19,546.80 20,674.50 19,546.80 20,674.50 19,922.70
3 Bambu kecil Ukuran 4 m btg 10,000.00 13,031.20 13,031.20 13,226.67 13,226.67 13,356.98 13,552.45 14,334.32 13,552.45 14,334.32 13,813.07
4 Celling teak (0,62 x 2,40) m2 lbr 65,000.00 76,433.00 76,433.00 77,579.50 77,579.50 78,343.83 79,490.32 84,076.30 79,490.32 84,076.30 81,018.98
5 Eternit lbr 47,000.00 55,683.32 55,683.32 56,518.57 56,518.57 57,075.40 57,910.65 61,251.65 57,910.65 61,251.65 59,024.32
6 Formika lbr 95,000.00 111,015.80 111,015.80 112,681.04 112,681.04 113,791.20 115,456.43 122,117.38 115,456.43 122,117.38 117,676.75
7 Melamine Lbr 130,000.00 151,362.40 151,362.40 153,632.84 153,632.84 155,146.46 157,416.90 166,498.64 157,416.90 166,498.64 160,444.14
8 Gedeg kulit kelas I m2 21,000.00 25,711.56 25,711.56 26,097.23 26,097.23 26,354.35 26,740.02 28,282.72 26,740.02 28,282.72 27,254.25
9 Gypsum Old lbr - -
10 Hard board MDF lbr 105,000.00 124,047.00 124,047.00 125,907.71 125,907.71 127,148.18 129,008.88 136,451.70 129,008.88 136,451.70 131,489.82
11 Kalsiboard 4,5 mm lbr - -
12 Kayu bekesting / kayu putih m3 2,300,000.00 2,654,355.20 2,654,355.20 2,694,170.53 2,694,170.53 2,720,714.08 2,760,529.41 2,919,790.72 2,760,529.41 2,919,790.72 2,813,616.51
13 Kayu Besi 10 x 10, panjang 4 m' m3 3,300,000.00 3,807,115.20 3,807,115.20 3,864,221.93 3,864,221.93 3,902,293.08 3,959,399.81 4,187,826.72 3,959,399.81 4,187,826.72 4,035,542.11
14 Kayu Besi 5 x 10, panjang 4 m' m3 4,500,000.00 5,190,427.20 5,190,427.20 5,268,283.61 5,268,283.61 5,320,187.88 5,398,044.29 5,709,469.92 5,398,044.29 5,709,469.92 5,501,852.83
15 Kayu Besi 5 x 5, panjang 4 m' m3 3,600,000.00 4,152,943.20 4,152,943.20 4,215,237.35 4,215,237.35 4,256,766.78 4,319,060.93 4,568,237.52 4,319,060.93 4,568,237.52 4,402,119.79
16 Kayu Besi 2.5 x 20, panjang 4 m' m3 4,500,000.00 5,190,427.20 5,190,427.20 5,268,283.61 5,268,283.61 5,320,187.88 5,398,044.29 5,709,469.92 5,398,044.29 5,709,469.92 5,501,852.83
17 Kayu Besi 10 x 10, panjang 3 m' m3 4,600,000.00 5,305,703.20 5,305,703.20 5,385,288.75 5,385,288.75 5,438,345.78 5,517,931.33 5,836,273.52 5,517,931.33 5,836,273.52 5,624,045.39
18 Kayu Besi 6x 12, panjang 4 m' m3 5,750,000.00 6,631,377.20 6,631,377.20 6,730,847.86 6,730,847.86 6,797,161.63 6,896,632.29 7,294,514.92 6,896,632.29 7,294,514.92 7,029,259.83
19 Reng Kayu Besi 2 x 3 m3 5,300,000.00 6,112,635.20 6,112,635.20 6,204,324.73 6,204,324.73 6,265,451.08 6,357,140.61 6,723,898.72 6,357,140.61 6,723,898.72 6,479,393.31
20 Kayu Besi 4x 25, panjang 4 m' m3 3,500,000.00 4,037,667.20 4,037,667.20 4,098,232.21 4,098,232.21 4,138,608.88 4,199,173.89 4,441,433.92 4,199,173.89 4,441,433.92 4,279,927.23
21 Papan Kayu besi 2,5 x 25, panjang 4 m' m3 3,500,000.00 4,037,667.20 4,037,667.20 4,098,232.21 4,098,232.21 4,138,608.88 4,199,173.89 4,441,433.92 4,199,173.89 4,441,433.92 4,279,927.23
22 Papan Cor/Papan Kayu Putih m3 2,000,000.00 2,308,527.20 2,308,527.20 2,343,155.11 2,343,155.11 2,366,240.38 2,400,868.29 2,539,379.92 2,400,868.29 2,539,379.92 2,447,038.83
23 Kayu Matoa 10 x10, panjang 4 m' m3 2,300,000.00 2,654,355.20 2,654,355.20 2,694,170.53 2,694,170.53 2,720,714.08 2,760,529.41 2,919,790.72 2,760,529.41 2,919,790.72 2,813,616.51
24 Kayu Matoa 5 x 10, panjang 4 m' m3 2,300,000.00 2,654,355.20 2,654,355.20 2,694,170.53 2,694,170.53 2,720,714.08 2,760,529.41 2,919,790.72 2,760,529.41 2,919,790.72 2,813,616.51
25 Kayu Matoa 5 x 5, panjang 4 m' m3 2,500,000.00 2,884,907.20 2,884,907.20 2,928,180.81 2,928,180.81 2,957,029.88 3,000,303.49 3,173,397.92 3,000,303.49 3,173,397.92 3,058,001.63
26 Kayu Matoa m3 2,300,000.00 2,654,355.20 2,654,355.20 2,694,170.53 2,694,170.53 2,720,714.08 2,760,529.41 2,919,790.72 2,760,529.41 2,919,790.72 2,813,616.51
27 Kayu Merbau m3 3,300,000.00 3,807,115.20 3,807,115.20 3,864,221.93 3,864,221.93 3,902,293.08 3,959,399.81 4,187,826.72 3,959,399.81 4,187,826.72 4,035,542.11
28 Papan Kayu Matoa 2,5 x 25, panjang 4 m' m3 2,500,000.00 2,884,907.20 2,884,907.20 2,928,180.81 2,928,180.81 2,957,029.88 3,000,303.49 3,173,397.92 3,000,303.49 3,173,397.92 3,058,001.63
29 Papan Kayu Matoa 2,5 x 20, panjang 4 m' m3 4,500,000.00 5,190,427.20 5,190,427.20 5,268,283.61 5,268,283.61 5,320,187.88 5,398,044.29 5,709,469.92 5,398,044.29 5,709,469.92 5,501,852.83
30 Papan Kayu Matoa 3 x 25, panjang 4 m' m3 2,500,000.00 2,884,907.20 2,884,907.20 2,928,180.81 2,928,180.81 2,957,029.88 3,000,303.49 3,173,397.92 3,000,303.49 3,173,397.92 3,058,001.63
31 Kayu bingkirai m3 - - - - - - - - - -
32 Kayu bingkirai papan m3 - - - - - - - - - -
33 Kayu dolken (pekerjaan sementara) btg 36,000.00 43,002.96 43,002.96 43,648.00 43,648.00 44,078.03 44,723.08 47,303.26 44,723.08 47,303.26 45,583.14
34 Kayu jati m3 - - - - - - - - - -
35 Kayu jati papan m3 - - - - - - - - - -
36 Kayu kamper balok m3 - - - - - - - - - -
37 Kayu kamper usuk/reng m3 - - - - - - - - - -
38 Kayu kamper papan m3 - - - - - - - - - -
39 Kayu kruing balok m3 - - - - - - - - - -
40 Kayu kruing usuk/reng m3 - - - - - - - - - -
41 Kayu kruing papan m3 - - - - - - - - - -
42 Kayu meranti balok m3 - - - - - - - - - -
43 Kayu meranti usuk/reng m3 - - - - - - - - - -
44 Kayu meranti papan m3 - -
45 Kayu merbau papan m3 - - - - - - - - - -
46 Kayu profil m1 10,000.00 13,031.20 13,031.20 13,226.67 13,226.67 13,356.98 13,552.45 14,334.32 13,552.45 14,334.32 13,813.07
47 Kayu seseh balok m3 - - - - - - - - - -
48 Kayu seseh dolken m3 - - - - - - - - - -
49 Lem Aibond 450 gr kg 100,000.00 116,779.60 116,779.60 118,531.29 118,531.29 119,699.09 121,450.78 128,457.56 121,450.78 128,457.56 123,786.38
50 Lem Aibond 700 gr kg 92,857.14 108,545.60 108,545.60 110,173.78 110,173.78 111,259.24 112,887.42 119,400.16 112,887.42 119,400.16 115,058.34
51 Lem Kayu (fox) kg 40,000.00 47,614.00 47,614.00 48,328.21 48,328.21 48,804.35 49,518.56 52,375.40 49,518.56 52,375.40 50,470.84
52 Lem Kayu (fox) besar klg 68,000.00 79,891.28 79,891.28 81,089.65 81,089.65 81,888.56 83,086.93 87,880.41 83,086.93 87,880.41 84,684.76
53 Lem Kayu (Fox) 0.6 klg 40,000.00 47,614.00 47,614.00 48,328.21 48,328.21 48,804.35 49,518.56 52,375.40 49,518.56 52,375.40 50,470.84
54 Lem Kayu (Fox) klg 55,000.00 64,905.40 64,905.40 65,878.98 65,878.98 66,528.04 67,501.62 71,395.94 67,501.62 71,395.94 68,799.72
55 Lem Kayu (Fox) Rajawali kg 35,000.00 41,850.20 41,850.20 42,477.95 42,477.95 42,896.46 43,524.21 46,035.22 43,524.21 46,035.22 44,361.21
56 List Gypsum standar m' - - - - - - - - - - -
57 Minyak bekisting ltr 15,000.00 18,795.00 18,795.00 19,076.93 19,076.93 19,264.88 19,546.80 20,674.50 19,546.80 20,674.50 19,922.70
58 Tripleks 2.7 mm lbr 68,000.00 79,891.28 79,891.28 81,089.65 81,089.65 81,888.56 83,086.93 87,880.41 83,086.93 87,880.41 84,684.76
59 Tripleks 3 mm Lbr 95,000.00 111,015.80 111,015.80 112,681.04 112,681.04 113,791.20 115,456.43 122,117.38 115,456.43 122,117.38 117,676.75
60 Tripleks 3 mm semi meranti Lbr 70,000.00 82,196.80 82,196.80 83,429.75 83,429.75 84,251.72 85,484.67 90,416.48 85,484.67 90,416.48 87,128.61
61 Tripleks 3.6 mm lbr 78,000.00 91,418.88 91,418.88 92,790.16 92,790.16 93,704.35 95,075.64 100,560.77 95,075.64 100,560.77 96,904.01
62 Plywood 3 mm Lbr 95,000.00 111,015.80 111,015.80 112,681.04 112,681.04 113,791.20 115,456.43 122,117.38 115,456.43 122,117.38 117,676.75
63 Tripleks 4 mm Lbr 110,000.00 128,307.20 128,307.20 130,231.81 130,231.81 131,514.88 133,439.49 141,137.92 133,439.49 141,137.92 136,005.63
64 Tripleks 4 mm semi meranti Lbr 80,000.00 93,724.40 93,724.40 95,130.27 95,130.27 96,067.51 97,473.38 103,096.84 97,473.38 103,096.84 99,347.86
65 Plywood 4 mm lbr 82,500.00 96,606.30 96,606.30 98,055.39 98,055.39 99,021.46 100,470.55 106,266.93 100,470.55 106,266.93 102,402.68
66 Tripleks 5 mm lbr 150,000.00 174,417.60 174,417.60 177,033.86 177,033.86 178,778.04 181,394.30 191,859.36 181,394.30 191,859.36 184,882.66

Harga Satauan Bahan dan Upah Hal. 62


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA FAKFAK FAKFAK TENGAH PARIWARI FAKFAK BARAT WARTUTIN FAKFAK TIMUR FAKFAK TIMUR KOKAS KAYUNI
DASAR TENGAH

1 2 3 4 5 6 7 8 9 10 11 12 13 6
67 Multiplek 6 mm lbr 125,000.00 145,598.60 145,598.60 147,782.58 147,782.58 149,238.57 151,422.54 160,158.46 151,422.54 160,158.46 154,334.52
68 Plywood 6 mm lbr 102,487.00 119,646.51 119,646.51 121,441.21 121,441.21 122,637.68 124,432.37 131,611.17 124,432.37 131,611.17 126,825.30
69 Multiplek 9 mm lbr 183,000.00 212,458.68 212,458.68 215,645.56 215,645.56 217,770.15 220,957.03 233,704.55 220,957.03 233,704.55 225,206.20
70 Plywood 9 mm lbr 160,000.00 185,945.20 185,945.20 188,734.38 188,734.38 190,593.83 193,383.01 204,539.72 193,383.01 204,539.72 197,101.91
71 Multiplek 12 mm lbr 225,000.00 260,874.60 260,874.60 264,787.72 264,787.72 267,396.47 271,309.58 286,962.06 271,309.58 286,962.06 276,527.08
72 Plywood 12 mm lbr 210,000.00 243,583.20 243,583.20 247,236.95 247,236.95 249,672.78 253,326.53 267,941.52 253,326.53 267,941.52 258,198.19
73 Multiplek 18 mm lbr 290,000.00 335,804.00 335,804.00 340,841.06 340,841.06 344,199.10 349,236.16 369,384.40 349,236.16 369,384.40 355,952.24
74 Plywood aluminium lbr - -
75 Teak wood (0,9x2,20) m2 lbr 98,000.00 115,977.68 115,977.68 117,717.35 117,717.35 118,877.12 120,616.79 127,575.45 120,616.79 127,575.45 122,936.34
76 Teak wood (1,20x2,40) m2 lbr 95,000.00 112,519.40 112,519.40 114,207.19 114,207.19 115,332.39 117,020.18 123,771.34 117,020.18 123,771.34 119,270.56
- - - - - - - - -
KERAMIK - - - - - - - - -
IKAD - - - - - - - - -
1 Ikad (Keramik) Kw. I 10 x 20 cm m2 51,480.00 62,351.28 62,351.28 63,286.55 63,286.55 63,910.07 64,845.34 68,586.41 64,845.34 68,586.41 66,092.36
2 Ikad (Keramik) Kw. I 20 x 20 cm m2 67,500.00 80,818.50 80,818.50 82,030.78 82,030.78 82,838.96 84,051.24 88,900.35 84,051.24 88,900.35 85,667.61
3 Ikad (Keramik) Kw. I 20 x 30 cm m2 85,000.00 100,991.80 100,991.80 102,506.68 102,506.68 103,516.60 105,031.47 111,090.98 105,031.47 111,090.98 107,051.31
4 Ikad (Keramik) Kw. I 30 x 30 cm m2 85,000.00 100,991.80 100,991.80 102,506.68 102,506.68 103,516.60 105,031.47 111,090.98 105,031.47 111,090.98 107,051.31
5 Ikad (Keramik) Kw. I 40 x 40 cm m2 78,000.00 92,922.48 92,922.48 94,316.32 94,316.32 95,245.54 96,639.38 102,214.73 96,639.38 102,214.73 98,497.83
6 Ikad (Keramik) Kw. II 10 x 20 cm m2 37,500.00 46,235.70 46,235.70 46,929.24 46,929.24 47,391.59 48,085.13 50,859.27 48,085.13 50,859.27 49,009.84
7 Ikad (Keramik) Kw. II 20 x 20 cm m2 39,500.00 48,541.22 48,541.22 49,269.34 49,269.34 49,754.75 50,482.87 53,395.34 50,482.87 53,395.34 51,453.69
8 Ikad (Keramik) Kw. II 20 x 30 cm m2 46,500.00 56,610.54 56,610.54 57,459.70 57,459.70 58,025.80 58,874.96 62,271.59 58,874.96 62,271.59 60,007.17
9 Ikad (Keramik) Kw. II 30 x 30 cm m2 48,500.00 58,916.06 58,916.06 59,799.80 59,799.80 60,388.96 61,272.70 64,807.67 61,272.70 64,807.67 62,451.02
10 Ikad (Keramik) Kw. II 40 x 40 cm m2 55,500.00 66,985.38 66,985.38 67,990.16 67,990.16 68,660.01 69,664.80 73,683.92 69,664.80 73,683.92 71,004.50
-
ELEYSIUM - - - - - - - - -
1 Ikad (Keramik) Kw. I 20 x 20 cm m2 60,000.00 72,172.80 72,172.80 73,255.39 73,255.39 73,977.12 75,059.71 79,390.08 75,059.71 79,390.08 76,503.17
2 Ikad (Keramik) Kw. I 20 x 30 cm m2 - - - - - - - - - -
3 Ikad (Keramik) Kw. I 30 x 30 cm m2 90,000.00 106,755.60 106,755.60 108,356.93 108,356.93 109,424.49 111,025.82 117,431.16 111,025.82 117,431.16 113,160.94
4 Ikad (Keramik) Kw. I 40 x 40 cm m2 90,000.00 106,755.60 106,755.60 108,356.93 108,356.93 109,424.49 111,025.82 117,431.16 111,025.82 117,431.16 113,160.94
-
INESA - - - - - - - - -
1 Keramik 30 x 30 Kelas I (Onyx Phyrus Ruby Jade, P) m2 - - - - - - - - - -
2 Keramik 30 x 30 Kelas I (Onyx Phyrus Ruby Jade, UP) m2 - Err:522
3 Keramik 30 x 30 Kelas I (Pearl Ghita Cat Eye, P) m2 - Err:522
4 Keramik 30 x 30 Kelas I (Pearl Ghita Cat Eye, UP) m2 - Err:522
5 Keramik 30 x 30 Kelas I (Sand Wheat Spruce Clay Charcoal, R) m2 - Err:522
6 Keramik 40 x 40 Kelas I (Corypha Roystonea Raphia, P) m2 - -
7 Keramik 40 x 40 Kelas I (Onyx Phyrus Ruby Jade, P) m2 - Err:522
8 Keramik 40 x 40 Kelas I (Onyx Phyrus Ruby Jade, UP) m2 - Err:522
9 Keramik 40 x 40 Kelas I (Pearl Ghita Cat Eye, P) m2 - Err:522
10 Keramik 40 x 40 Kelas I (Pearl Ghita Cat Eye, UP) m2 - Err:522
11 Keramik 60 x 60 Kelas I (Corypha Roystonea Raphia, P) m2 - Err:522

ESSENZA
1 Keramik 30 x 30 Kelas I (Black Orchid, Coral Bell, P) m2 - Err:522
Keramik 30 x 30 Kelas I (Black Orchid, Coral Bell, UP) -
2 m2 Err:522
3 Keramik 30 x 30 Kelas I (Pepper Grey Price Rubert Silver star, P) m2 - Err:522
4 Keramik 30 x 30 Kelas I (Pepper Grey Price Rubert Silver star, UP) m2 - Err:522
5 Keramik 40 x 40 Kelas I (Pepper Grey Price Rubert Silver star, P) m2 - Err:522
6 Keramik 40 x 40 Kelas I (Pepper Grey Price Rubert Silver star, UP) m2 - Err:522
7 Keramik 60 x 60 Kelas I (Pepper Grey Price Rubert Silver star, P) m2 - Err:522
8 Keramik Kelas I Domus m2 - Err:522
9 Keramik Kelas I Granity Imperiali m2 - Err:522
10 Keramik Kelas I Lavagna m2 - Err:522
11 Keramik Kelas I Mountain Peak m2 - Err:522

GARUDA - - - - - - - -
1 Keramik 20 x 20 kelas I Emboss Dasar Muda m2 - - - - - - - - -
2 Keramik 20 x 20 kelas I Emboss Dasar Tua m2 - - - - - - - - -
3 Keramik 20 x 20 kelas I Tesia m2 - - - - - - - - -
4 Keramik 20 x 20 kelas II Emboss Dasar Muda m2 - - - - - - - - -
5 Keramik 20 x 20 kelas II Emboss Dasar Tua m2 - - - - - - - - -
6 Keramik 20 x 20 kelas II Tesia m2 - - - - - - - - -
7 Keramik 20 x 25 kelas I Motif Dasar Medium m2 - - - - - - - - -

Harga Satauan Bahan dan Upah Hal. 63


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA FAKFAK FAKFAK TENGAH PARIWARI FAKFAK BARAT WARTUTIN FAKFAK TIMUR FAKFAK TIMUR KOKAS KAYUNI
DASAR TENGAH

1 2 3 4 5 6 7 8 9 10 11 12 13 6
8 Keramik 20 x 25 kelas I Motif Dasar Muda m2 - - - - - - - - -
9 Keramik 20 x 25 kelas I Nuri Dark m2 - - - - - - - - -
10 Keramik 20 x 25 kelas I Polos m2 - - - - - - - - -
11 Keramik 30 x 30 kelas I Granity m2 - - - - - - - - -
12 Keramik 30 x 30 kelas I Motif Embose m2 - - - - - - - - -
13 Keramik 30 x 30 kelas II Granity m2 - - - - - - - - -
14 Keramik 30 x 30 kelas II Motif Embose m2 - - - - - - - - -
15 Keramik 40 x 40 kelas I Motif Dasar Muda m2 - - - - - - - - -
16 Keramik 40 x 40 kelas I Motif Dasar Muda m2 - - - - - - - - - -
17 Keramik 40 x 40 kelas I Motif Embose m2 - - - - - - - - - -
18 Keramik 40 x 40 kelas I Motif Granity Tua m2 - - - - - - - - - -
19 Keramik 40 x 40 kelas I Motif Medium Color m2 - - - - - - - - - -
20 Keramik 40 x 40 kelas I Motif Spesial Color m2 - - - - - - - - - -
21 Keramik 50 x 50 kelas I m2 - - - - - - - - - -
22 Granito 60 x 60 m2 250,000.00 291,197.20 291,197.20 295,565.16 295,565.16 298,477.13 302,845.09 320,316.92 302,845.09 320,316.92 308,669.03
-
ASIA - - - - - - - - -
1 Keramik 10 x 10 kelas I warna muda m2 52,000.00 62,950.72 62,950.72 63,894.98 63,894.98 64,524.49 65,468.75 69,245.79 65,468.75 69,245.79 66,727.76
2 Keramik 10 x 20 kelas I warna muda m2 -
3 Keramik 20 x 20 kelas I warna muda m2 61,000.00 73,325.56 73,325.56 74,425.44 74,425.44 75,158.70 76,258.58 80,658.12 76,258.58 80,658.12 77,725.09
4 Keramik 20 x 20 kelas I warna tua m2 -
5 Keramik 20 x 25 kelas I warna tua m2 62,000.00 74,478.32 74,478.32 75,595.49 75,595.49 76,340.28 77,457.45 81,926.15 77,457.45 81,926.15 78,947.02
6 Keramik 20 x 30 kelas I warna muda m2 58,000.00 69,867.28 69,867.28 70,915.29 70,915.29 71,613.96 72,661.97 76,854.01 72,661.97 76,854.01 74,059.32
7 Keramik 30 x 30 kelas I warna muda m2 - -
8 Keramik 30 x 30 kelas I warna tua m2 - -
9 Keramik 40 x 40 kelas I warna muda m2 63,000.00 75,631.08 75,631.08 76,765.55 76,765.55 77,521.86 78,656.32 83,194.19 78,656.32 83,194.19 80,168.94
10 Keramik 40 x 40 warna platinum m2 70,000.00 83,700.40 83,700.40 84,955.91 84,955.91 85,792.91 87,048.42 92,070.44 87,048.42 92,070.44 88,722.42
11 Keramik 10 x 20 kelas II m2 88,000.00 104,450.08 104,450.08 106,016.83 106,016.83 107,061.33 108,628.08 114,895.09 108,628.08 114,895.09 110,717.08
12 Keramik 20 x 20 kelas II m2
13 Keramik 20 x 30 kelas II m2 62,000.00 74,478.32 74,478.32 75,595.49 75,595.49 76,340.28 77,457.45 81,926.15 77,457.45 81,926.15 78,947.02
14 Keramik 30 x 30 kelas II m2 65,000.00 77,936.60 77,936.60 79,105.65 79,105.65 79,885.02 81,054.06 85,730.26 81,054.06 85,730.26 82,612.80
15 Keramik 40 x 40 kelas II m2 70,000.00 83,700.40 83,700.40 84,955.91 84,955.91 85,792.91 87,048.42 92,070.44 87,048.42 92,070.44 88,722.42
- - - - - - - - -
MULIA - - - - - - - - -
1 Keramik 10 x 20 cm kelas I m2 - - - - - - - - - - -
2 Keramik 20 x 20 cm kelas I m2 85,000.00 100,991.80 100,991.80 102,506.68 102,506.68 103,516.60 105,031.47 111,090.98 105,031.47 111,090.98 107,051.31
3 Keramik 20 x 30 cm kelas I m2 - - - - - - - - - -
4 Keramik 30 x 30 cm kelas I m2 80,000.00 95,228.00 95,228.00 96,656.42 96,656.42 97,608.70 99,037.12 104,750.80 99,037.12 104,750.80 100,941.68
5 Keramik 40 x 40 cm kelas I m2 85,000.00 100,991.80 100,991.80 102,506.68 102,506.68 103,516.60 105,031.47 111,090.98 105,031.47 111,090.98 107,051.31
6 Keramik 10 x 20 cm kelas II m2 - - - - - - - - - - -
7 Keramik 20 x 20 cm kelas II m2 - - - - - - - - - - -
8 Keramik 20 x 30 cm kelas II m2 - - - - - - - - - - -
9 Keramik 30 x 30 cm kelas II m2 - - - - - - - - - - -
10 Keramik 40 x 40 cm kelas II m2 - - - - - - - - - - -
- - - - - - - - -
PICASSO - - - - - - - - -
1 Ikad Keramik KW 1 20 x 20 cm m2 90,000.00 106,755.60 106,755.60 108,356.93 108,356.93 109,424.49 111,025.82 117,431.16 111,025.82 117,431.16 113,160.94
2 Ikad Keramik KW 1 20 x 25 cm m2 88,000.00 104,450.08 104,450.08 106,016.83 106,016.83 107,061.33 108,628.08 114,895.09 108,628.08 114,895.09 110,717.08
3 Ikad Keramik KW 1 30 x 30 cm m2 85,000.00 100,991.80 100,991.80 102,506.68 102,506.68 103,516.60 105,031.47 111,090.98 105,031.47 111,090.98 107,051.31
4 Ikad Keramik KW 1 40 x 40 cm m2 88,000.00 104,450.08 104,450.08 106,016.83 106,016.83 107,061.33 108,628.08 114,895.09 108,628.08 114,895.09 110,717.08
- - - - - - - - -
SANITAIR - - - - - - - - -
1 Bak mandi fibre glass 70x70x66 cm biasa bh 350,000.00 410,482.80 410,482.80 416,640.04 416,640.04 420,744.87 426,902.11 451,531.08 426,902.11 451,531.08 435,111.77
2 Bak mandi fibre glass 70x70x66 cm sudut bh 600,000.00 698,672.80 698,672.80 709,152.89 709,152.89 716,139.62 726,619.71 768,540.08 726,619.71 768,540.08 740,593.17
3 Bak mandi keramik 50x50 bh 165,000.00 197,222.20 197,222.20 200,180.53 200,180.53 202,152.76 205,111.09 216,944.42 205,111.09 216,944.42 209,055.53
4 Floor Drain " TOTO TypeTx 1 Bv 1 " Square Flange " bh 38,000.00 50,821.68 50,821.68 51,584.01 51,584.01 52,092.22 52,854.55 55,903.85 52,854.55 55,903.85 53,870.98
5 Floor drain plastik bh 20,000.00 30,072.00 30,072.00 30,523.08 30,523.08 30,823.80 31,274.88 33,079.20 31,274.88 33,079.20 31,876.32
6 Floor drain stainless bh 65,000.00 81,946.20 81,946.20 83,175.39 83,175.39 83,994.86 85,224.05 90,140.82 85,224.05 90,140.82 86,862.97
7 Floor drain plastik onda bh 28,000.00 39,294.08 39,294.08 39,883.49 39,883.49 40,276.43 40,865.84 43,223.49 40,865.84 43,223.49 41,651.72
8 Kloset duduk DATA komplit bh 900,000.00 1,044,500.80 1,044,500.80 1,060,168.31 1,060,168.31 1,070,613.32 1,086,280.83 1,148,950.88 1,086,280.83 1,148,950.88 1,107,170.85
9 Kloset duduk INA Komplit bh 2,400,000.00 2,773,640.80 2,773,640.80 2,815,245.41 2,815,245.41 2,842,981.82 2,884,586.43 3,051,004.88 2,884,586.43 3,051,004.88 2,940,059.25
10 Kloset duduk INA standard bh 750,000.00 871,586.80 871,586.80 884,660.60 884,660.60 893,376.47 906,450.27 958,745.48 906,450.27 958,745.48 923,882.01
11 Kloset duduk Amerika Standar bh - -
Kloset duduk " TOTO Type AVANTE CW 821 PJ / SW 821JP
12 bh 3,000,000.00 3,517,276.25 3,517,276.25 3,551,929.22 3,603,908.67 3,811,826.48 3,603,908.67 3,811,826.48 3,673,214.61
COMPLIT 3,465,296.80 3,465,296.80

13 Kloset duduk " TOTO Type AVANTE CW 821J"/ SW 821JP COMPLIT bh 5,610,000.00 6,571,110.41 6,571,110.41 6,635,850.41 6,732,960.42 7,121,400.44 6,732,960.42 7,121,400.44 6,862,440.42
6,474,000.40 6,474,000.40

Harga Satauan Bahan dan Upah Hal. 64


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA FAKFAK FAKFAK TENGAH PARIWARI FAKFAK BARAT WARTUTIN FAKFAK TIMUR FAKFAK TIMUR KOKAS KAYUNI
DASAR TENGAH

1 2 3 4 5 6 7 8 9 10 11 12 13 6

14 Kloset duduk " TOTO Type AVANTE CW 823 J bh 5,600,000.00 6,559,409.89 6,559,409.89 6,624,034.62 6,720,971.71 7,108,720.08 6,720,971.71 7,108,720.08 6,850,221.17
6,462,472.80 6,462,472.80
15 Kloset duduk " TOTO Type CW 660J bh 602,800.00 701,900.53 701,900.53 712,429.04 712,429.04 719,448.04 729,976.55 772,090.58 729,976.55 772,090.58 744,014.56

16 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT bh 2,575,000.00 2,975,373.80 2,975,373.80 3,020,004.41 3,020,004.41 3,049,758.15 3,094,388.75 3,272,911.18 3,094,388.75 3,272,911.18 3,153,896.23

17 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT WARNA bh 1,491,000.00
1,725,781.96 1,725,781.96 1,751,668.69 1,751,668.69 1,768,926.51 1,794,813.24 1,898,360.16 1,794,813.24 1,898,360.16 1,829,328.88

18 Kloset duduk LOLO warna COMPLIT bh 1,800,000.00 2,081,984.80 2,081,984.80 2,113,214.57 2,113,214.57 2,134,034.42 2,165,264.19 2,290,183.28 2,165,264.19 2,290,183.28 2,206,903.89

19 Kloset duduk " TOTO Type CW 661JT1 BODI COMPLIT bh 2,796,200.00 3,278,819.78 3,278,819.78 3,311,123.42 3,359,578.88 3,553,400.74 3,359,578.88 3,553,400.74 3,424,186.17
3,230,364.31 3,230,364.31

20 Kloset duduk " TOTO Type CW 661JT1" / SW 661JP COMPLIT bh 2,190,000.00 2,569,534.62 2,569,534.62 2,594,850.23 2,632,823.65 2,784,717.32 2,632,823.65 2,784,717.32 2,683,454.87
2,531,561.20 2,531,561.20

21 Kloset duduk " TOTO Type CW 661JT1" / SW 784JP COMPLIT bh 1,734,700.00 2,036,810.22 2,036,810.22 2,056,877.31 2,086,977.95 2,207,380.53 2,086,977.95 2,207,380.53 2,127,112.15
2,006,709.57 2,006,709.57
22 Kloset jongkok " TOTO Type CE 6 COMPLIT bh 345,000.00 404,719.00 404,719.00 410,789.79 410,789.79 414,836.98 420,907.76 445,190.90 420,907.76 445,190.90 429,002.14
23 Kloset jongkok " TOTO bh 370,000.00 433,538.00 433,538.00 440,041.07 440,041.07 444,376.45 450,879.52 476,891.80 450,879.52 476,891.80 459,550.28
24 Kloset jongkok " TOTO Type CE 7 COMPLIT Set - -
25 Kloset porselin jongkok Avena (standar) bh 150,000.00 179,930.80 179,930.80 182,629.76 182,629.76 184,429.07 187,128.03 197,923.88 187,128.03 197,923.88 190,726.65
26 Kloset porselin jongkok Kia (standar) bh 175,000.00 208,749.80 208,749.80 211,881.05 211,881.05 213,968.55 217,099.79 229,624.78 217,099.79 229,624.78 221,274.79
27 Kloset porselin jongkok VITO (standar) bh 190,000.00 226,041.20 226,041.20 229,431.82 229,431.82 231,692.23 235,082.85 248,645.32 235,082.85 248,645.32 239,603.67
28 Kloset porselin jongkok Ina (standar) bh 450,000.00 525,758.80 525,758.80 533,645.18 533,645.18 538,902.77 546,789.15 578,334.68 546,789.15 578,334.68 557,304.33
29 Kloset porselin jongkok America (standar) bh -
30 Kloset porselin jongkok DUTY bh 150,000.00 179,930.80 179,930.80 182,629.76 182,629.76 184,429.07 187,128.03 197,923.88 187,128.03 197,923.88 190,726.65
31 Kloset porselin jongkok DATA bh - -
32 Kloset porselin jongkok ROSI bh - -
33 Kloset porselin jongkok CHELSEA bh - -
34 Kran air 3/4 biasa dari besi bh 45,000.00 58,891.00 58,891.00 59,774.37 59,774.37 60,363.28 61,246.64 64,780.10 61,246.64 64,780.10 62,424.46
35 Kran air 3/4 biasa dari plastik bh 25,000.00 35,835.80 35,835.80 36,373.34 36,373.34 36,731.70 37,269.23 39,419.38 37,269.23 39,419.38 37,985.95
36 Kran air 1/2 biasa dari besi bh 40,000.00 53,127.20 53,127.20 53,924.11 53,924.11 54,455.38 55,252.29 58,439.92 55,252.29 58,439.92 56,314.83
37 Kran SunEi bh 99,000.00 121,140.04 121,140.04 122,957.14 122,957.14 124,168.54 125,985.64 133,254.04 125,985.64 133,254.04 128,408.44
38 Kran TOTO T 205 LCSC bh - - - - - - - - - - -
39 Kran TOTO T 205 MC bh - - - - - - - - - - -
40 Kran TOTO T 23 B13 bh - - - - - - - - - - -
41 Kran TOTO T 23 B13V7N bh - - - - - - - - - - -
42 Kran TOTO T 26 - 13 bh - - - - - - - - - - -
43 Kran TOTO TX 109 LH bh - - - - - - - - - - -
44 Kran washtafel bh 100,000.00 116,779.60 116,779.60 118,531.29 118,531.29 119,699.09 121,450.78 128,457.56 121,450.78 128,457.56 123,786.38
45 Kran cuci piring bh 120,000.00 139,834.80 139,834.80 141,932.32 141,932.32 143,330.67 145,428.19 153,818.28 145,428.19 153,818.28 148,224.89
46 Penyekat Urinoir " TOTO " Type A 100 " bh - - - - - - - - - -
47 Shower Spray " TOTO Tx 403SPIV ( Pastel Ivory ) bh 265,000.00 306,985.00 306,985.00 311,589.78 311,589.78 314,659.63 319,264.40 337,683.50 319,264.40 337,683.50 325,404.10
48 Shower Spray biasa bh 220,000.00 255,110.80 255,110.80 258,937.46 258,937.46 261,488.57 265,315.23 280,621.88 265,315.23 280,621.88 270,417.45
49 Shower Spray TOTO 12 bh - - - - - - - - - - -
50 Shower Spray TOTO bh - -
51 Soap holder " TOTO " Type S 6 N " bh - - - - - - - - -
52 Seal tape Besar bh 15,000.00 18,795.00 18,795.00 19,076.93 19,076.93 19,264.88 19,546.80 20,674.50 19,546.80 20,674.50 19,922.70
53 Seal tape kecil bh 10,000.00 13,031.20 13,031.20 13,226.67 13,226.67 13,356.98 13,552.45 14,334.32 13,552.45 14,334.32 13,813.07
54 Urinoir " TOTO U 57 M bh 1,052,000.00 1,214,207.12 1,214,207.12 1,232,420.23 1,232,420.23 1,244,562.30 1,262,775.40 1,335,627.83 1,262,775.40 1,335,627.83 1,287,059.55
55 Urinoir " TOTO U 57 M BODI bh - - - - - - - - - -
56 Wastagel KIA Standard bh 595,000.00 687,395.80 687,395.80 697,706.74 697,706.74 704,580.70 714,891.63 756,135.38 714,891.63 756,135.38 728,639.55
57 Wastagel INA bh 900,000.00 1,038,987.60 1,038,987.60 1,054,572.41 1,054,572.41 1,064,962.29 1,080,547.10 1,142,886.36 1,080,547.10 1,142,886.36 1,101,326.86
58 Wastafel Komplit " TOTO Tx " Type L 521V1A " bh - - - - - - - - - -
59 Wastafel Komplit top Counter" TOTO " Type CERABO LW 523 " bh - - - - - - - - - -
60 Washtafel LOLO bh 750,000.00 871,586.80 871,586.80 884,660.60 884,660.60 893,376.47 906,450.27 958,745.48 906,450.27 958,745.48 923,882.01
61 Wastafel KIA Standar 2 (Lubang) bh 650,000.00 756,310.80 756,310.80 767,655.46 767,655.46 775,218.57 786,563.23 831,941.88 786,563.23 831,941.88 801,689.45
61 Washtafel cuci tangan kecil (Standard) bh 750,000.00 871,586.80 871,586.80 884,660.60 884,660.60 893,376.47 906,450.27 958,745.48 906,450.27 958,745.48 923,882.01
62 Washtafel cuci tangan besar (Standard) bh 650,000.00 756,310.80 756,310.80 767,655.46 767,655.46 775,218.57 786,563.23 831,941.88 786,563.23 831,941.88 801,689.45
63 Washtafel cuci piring 2 lubang bh 600,000.00 698,672.80 698,672.80 709,152.89 709,152.89 716,139.62 726,619.71 768,540.08 726,619.71 768,540.08 740,593.17
64 Washtafel cuci piring 1 lubang bh 300,000.00 352,844.80 352,844.80 358,137.47 358,137.47 361,665.92 366,958.59 388,129.28 366,958.59 388,129.28 374,015.49
65 Bak cuci piring single besar bh 650,000.00 756,310.80 756,310.80 767,655.46 767,655.46 775,218.57 786,563.23 831,941.88 786,563.23 831,941.88 801,689.45
66 Bak cuci piring double besar bh 450,000.00 525,758.80 525,758.80 533,645.18 533,645.18 538,902.77 546,789.15 578,334.68 546,789.15 578,334.68 557,304.33
67 Bak cuci piring single kecil bh 225,000.00 266,387.80 266,387.80 270,383.62 270,383.62 273,047.50 277,043.31 293,026.58 277,043.31 293,026.58 282,371.07
- - - - - - - - -
PAKU - - - - - - - - -
1 Paku 3 kg 27,000.00 32,628.12 32,628.12 33,117.54 33,117.54 33,443.82 33,933.24 35,890.93 33,933.24 35,890.93 34,585.81
2 Paku 4 kg 27,000.00 32,628.12 32,628.12 33,117.54 33,117.54 33,443.82 33,933.24 35,890.93 33,933.24 35,890.93 34,585.81

Harga Satauan Bahan dan Upah Hal. 65


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA FAKFAK FAKFAK TENGAH PARIWARI FAKFAK BARAT WARTUTIN FAKFAK TIMUR FAKFAK TIMUR KOKAS KAYUNI
DASAR TENGAH

1 2 3 4 5 6 7 8 9 10 11 12 13 6
3 Paku 5 biasa kg 30,000.00 36,086.40 36,086.40 36,627.70 36,627.70 36,988.56 37,529.86 39,695.04 37,529.86 39,695.04 38,251.58
4 Paku 5 putih kg 30,000.00 36,086.40 36,086.40 36,627.70 36,627.70 36,988.56 37,529.86 39,695.04 37,529.86 39,695.04 38,251.58
5 Paku 7 biasa kg 25,000.00 30,322.60 30,322.60 30,777.44 30,777.44 31,080.67 31,535.50 33,354.86 31,535.50 33,354.86 32,141.96
6 Paku 7 putih kg 30,000.00 36,086.40 36,086.40 36,627.70 36,627.70 36,988.56 37,529.86 39,695.04 37,529.86 39,695.04 38,251.58
7 Paku 8 putih kg - -
8 Paku 9 putih kg - -
9 Paku 10 biasa kg 25,000.00 30,322.60 30,322.60 30,777.44 30,777.44 31,080.67 31,535.50 33,354.86 31,535.50 33,354.86 32,141.96
10 Paku 10 putih kg 30,000.00 36,086.40 36,086.40 36,627.70 36,627.70 36,988.56 37,529.86 39,695.04 37,529.86 39,695.04 38,251.58
11 Paku 12 biasa kg 25,000.00 30,322.60 30,322.60 30,777.44 30,777.44 31,080.67 31,535.50 33,354.86 31,535.50 33,354.86 32,141.96
12 Paku 12 putih kg 30,000.00 36,086.40 36,086.40 36,627.70 36,627.70 36,988.56 37,529.86 39,695.04 37,529.86 39,695.04 38,251.58
13 Paku 14 biasa kg 22,000.00 26,864.32 26,864.32 27,267.28 27,267.28 27,535.93 27,938.89 29,550.75 27,938.89 29,550.75 28,476.18
14 Paku 15 biasa kg 25,000.00 30,322.60 30,322.60 30,777.44 30,777.44 31,080.67 31,535.50 33,354.86 31,535.50 33,354.86 32,141.96
15 Paku 15 putih kg 25,000.00 30,322.60 30,322.60 30,777.44 30,777.44 31,080.67 31,535.50 33,354.86 31,535.50 33,354.86 32,141.96
16 Paku kalsiboard kg 35,000.00 41,850.20 41,850.20 42,477.95 42,477.95 42,896.46 43,524.21 46,035.22 43,524.21 46,035.22 44,361.21
17 Paku list SQ kg 20,000.00 24,558.80 24,558.80 24,927.18 24,927.18 25,172.77 25,541.15 27,014.68 25,541.15 27,014.68 26,032.33
18 Paku pancing 60 x 230 kg 18,750.00 23,117.85 23,117.85 23,464.62 23,464.62 23,695.80 24,042.56 25,429.64 24,042.56 25,429.64 24,504.92
19 Paku reng/usuk SQ kg 20,000.00 24,558.80 24,558.80 24,927.18 24,927.18 25,172.77 25,541.15 27,014.68 25,541.15 27,014.68 26,032.33
20 Paku seng 1Kg kg 48,000.00 56,836.08 56,836.08 57,688.62 57,688.62 58,256.98 59,109.52 62,519.69 59,109.52 62,519.69 60,246.24
21 Paku seng import bj 55,000.00 64,905.40 64,905.40 65,878.98 65,878.98 66,528.04 67,501.62 71,395.94 67,501.62 71,395.94 68,799.72
22 Paku skrup 1/2" kg 120,000.00 139,834.80 139,834.80 141,932.32 141,932.32 143,330.67 145,428.19 153,818.28 145,428.19 153,818.28 148,224.89
23 Paku skrup 2" kg - -
24 Paku skrup 3.5" kg 170,000.00 196,119.56 196,119.56 199,061.35 199,061.35 201,022.55 203,964.34 215,731.52 203,964.34 215,731.52 207,886.73
25 Paku skrup 1" bh 15,000.00 17,441.76 17,441.76 17,703.39 17,703.39 17,877.80 18,139.43 19,185.94 18,139.43 19,185.94 18,488.27
26 Paku beton kg 50,000.00 57,788.36 57,788.36 58,655.19 58,655.19 59,233.07 60,099.89 63,567.20 60,099.89 63,567.20 61,255.66
27 Paku tripleks kg 25,000.00 28,969.36- 28,969.36 29,403.90
- 29,403.90
- 29,693.59
- 30,128.13
- 31,866.30
- 30,128.13
- 31,866.30
- 30,707.52
-
PASIR, BATU, KERIKIL, BATA DAN PARAS - - - - - - - - -
1 Bata gosok ex Tobacco bj 50,000.00 59,848.11 59,848.11 60,745.83 60,745.83 61,344.31 62,242.04 65,832.92 62,242.04 65,832.92 63,439.00
2 Bata Merah 5 x 11 x 22 cm bj 8,000.00 11,432.19 11,432.19 11,603.67 11,603.67 11,718.00 11,889.48 12,575.41 11,889.48 12,575.41 12,118.12
3 Bata Ringan/ Bataco 7 x 20 x 60 bj 18,000.00 22,959.79 22,959.79 23,304.19 23,304.19 23,533.79 23,878.18 25,255.77 23,878.18 25,255.77 24,337.38
4 Bata Ringan/ Bataco 8 x 20 x 60 bj 20,000.00 25,265.31 25,265.31 25,644.29 25,644.29 25,896.94 26,275.92 27,791.84 26,275.92 27,791.84 26,781.23
5 Bata Ringan/ Bataco 10 x 20 x 60 bj 24,000.00 29,876.35 29,876.35 30,324.50 30,324.50 30,623.26 31,071.40 32,863.99 31,071.40 32,863.99 31,668.93
6 Batu tela bj 8,000.00 11,432.19 11,432.19 11,603.67 11,603.67 11,718.00 11,889.48 12,575.41 11,889.48 12,575.41 12,118.12
7 Batu gunung/ belah m3 500,000.00 777,862.40 777,862.40 789,530.34 789,530.34 797,308.96 808,976.90 855,648.64 808,976.90 855,648.64 824,534.14
8 Batu karang m3 128,571.00 349,693.91 349,693.91 354,939.31 354,939.31 358,436.25 363,681.66 384,663.30 363,681.66 384,663.30 370,675.54
9 Batu lahar Singaraja m3 138,000.00 360,563.28 360,563.28 365,971.73 365,971.73 369,577.36 374,985.81 396,619.61 374,985.81 396,619.61 382,197.08
10 Batu Pecah 2-3 m3 1,062,500.00 1,426,289.90 1,426,289.90 1,447,684.25 1,447,684.25 1,461,947.15 1,483,341.50 1,568,918.89 1,483,341.50 1,568,918.89 1,511,867.29
11 Batu Pecah 0.5-1/ciping m3 1,062,500.00 1,426,289.90 1,426,289.90 1,447,684.25 1,447,684.25 1,461,947.15 1,483,341.50 1,568,918.89 1,483,341.50 1,568,918.89 1,511,867.29
12 Batu Pecah 10-19 m3 1,000,000.00 1,354,242.40 1,354,242.40 1,374,556.04 1,374,556.04 1,388,098.46 1,408,412.10 1,489,666.64 1,408,412.10 1,489,666.64 1,435,496.94
13 Batu pipih Singaraja m3 150,000.00 374,396.40 374,396.40 380,012.35 380,012.35 383,756.31 389,372.26 411,836.04 389,372.26 411,836.04 396,860.18
14 Glass block 20cmx20cm bj 55,000.00 264,884.20 264,884.20 268,857.46 268,857.46 271,506.31 275,479.57 291,372.62 275,479.57 291,372.62 280,777.25
15 Glass block 30cmx30cm bh 250,000.00 489,672.40 489,672.40 497,017.49 497,017.49 501,914.21 509,259.30 538,639.64 509,259.30 538,639.64 519,052.74
16 Roster Keramik 30cmx30cm bh 85,000.00 299,467.00 299,467.00 303,959.01 303,959.01 306,953.68 311,445.68 329,413.70 311,445.68 329,413.70 317,435.02
17 Koral Beton m3 1,062,500.00 1,426,289.90 1,426,289.90 1,447,684.25 1,447,684.25 1,461,947.15 1,483,341.50 1,568,918.89 1,483,341.50 1,568,918.89 1,511,867.29
18 Limestone m3 79,000.00 292,550.44 292,550.44 296,938.70 296,938.70 299,864.20 304,252.46 321,805.48 304,252.46 321,805.48 310,103.47
19 Paras Batik bh - - - - - - - - - -
20 Paras Buahan bh - - - - - - - - - -
21 Paras Karang Bukit bh - - - - - - - - - - -
22 Paras Kerobokan Tebal 5 bh - - - - - - - - - - -
23 Paras Malem bh - - - - - - - - - - -
24 Paras Putih Bukit bh - - - - - - - - - - -
25 Paras Silakarang tebal bh - - - - - - - - - - -
26 Paras Silakarang tipis bh - - - - - - - - - - -
27 Paras untuk pondasi bh - - - - - - - - - - -
28 Pasir halus m3 1,500,000.00 1,929,620.00 1,929,620.00 1,958,564.30 1,958,564.30 1,977,860.50 2,006,804.80 2,122,582.00 2,006,804.80 2,122,582.00 2,045,397.20
29 Pasir kasar m3 1,000,000.00 1,353,240.00 1,353,240.00 1,373,538.60 1,373,538.60 1,387,071.00 1,407,369.60 1,488,564.00 1,407,369.60 1,488,564.00 1,434,434.40
30 Pasir sedot / Lokal m3 500,000.00 776,860.00 776,860.00 788,512.90 788,512.90 796,281.50 807,934.40 854,546.00 807,934.40 854,546.00 823,471.60
31 Sirtu m3 250,000.00 488,670.00 488,670.00 496,000.05 496,000.05 500,886.75 508,216.80 537,537.00 508,216.80 537,537.00 517,990.20
32 Tanah urug m3 150,000.00 373,394.00 373,394.00 378,994.91 378,994.91 382,728.85 388,329.76 410,733.40 388,329.76 410,733.40 395,797.64
33 Filler/abu batu m3 1,062,500.00 1,425,287.50 1,425,287.50 1,446,666.81 1,446,666.81 1,460,919.69 1,482,299.00 1,567,816.25 1,482,299.00 1,567,816.25 1,510,804.75
34 Aspal drum 2,000,000.00 2,506,000.00 2,506,000.00 2,543,590.00 2,543,590.00 2,568,650.00 2,606,240.00 2,756,600.00 2,606,240.00 2,756,600.00 2,656,360.00
- - - - - - - - -
PIPA - - - - - - - - -
1 Pipa Galvanis 1/2" Medium A (tebal) m1 29,166.67 34,791.63 34,791.63 35,313.51 35,313.51 35,661.42 36,183.30 38,270.80 36,183.30 38,270.80 36,879.13
2 Pipa Galvanis 1/2" Medium B (tipis) m1 22,500.00 27,106.57 27,106.57 27,513.17 27,513.17 27,784.23 28,190.83 29,817.22 28,190.83 29,817.22 28,732.96
3 Pipa Galvanis 1/2' medium B (sedang) m1 24,166.67 29,027.83 29,027.83 29,463.25 29,463.25 29,753.53 30,188.95 31,930.62 30,188.95 31,930.62 30,769.50
4 Pipa Galvanis 3/4" Medium A (tebal) m1 36,333.33 43,053.08 43,053.08 43,698.88 43,698.88 44,129.41 44,775.20 47,358.39 44,775.20 47,358.39 45,636.26

Harga Satauan Bahan dan Upah Hal. 66


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA FAKFAK FAKFAK TENGAH PARIWARI FAKFAK BARAT WARTUTIN FAKFAK TIMUR FAKFAK TIMUR KOKAS KAYUNI
DASAR TENGAH

1 2 3 4 5 6 7 8 9 10 11 12 13 6
5 Pipa Galvanis 3/4" Medium A sedang m1 39,166.67 46,319.23 46,319.23 47,014.02 47,014.02 47,477.21 48,172.00 50,951.16 48,172.00 50,951.16 49,098.39
6 Pipa Galvanis 3/4" Medium B m1 30,000.00 35,752.27 35,752.27 36,288.55 36,288.55 36,646.07 37,182.36 39,327.49 37,182.36 39,327.49 37,897.40
7 Pipa Galvanis 1 1/4" m1 64,166.67 75,138.23 75,138.23 76,265.31 76,265.31 77,016.69 78,143.76 82,652.06 78,143.76 82,652.06 79,646.53
8 Pipa Galvanis 1 1/2" m1 74,166.67 86,665.83 86,665.83 87,965.82 87,965.82 88,832.48 90,132.47 95,332.42 90,132.47 95,332.42 91,865.78
9 Pipa Galvanis 1 1/2 " M.B m1 72,000.00 84,168.19 84,168.19 85,430.71 85,430.71 86,272.39 87,534.91 92,585.01 87,534.91 92,585.01 89,218.28
10 Pipa Galvanis 1" m1 - -
11 Pipa Galvanis 1" MA m1 57,500.00 67,453.17 67,453.17 68,464.96 68,464.96 69,139.50 70,151.29 74,198.48 70,151.29 74,198.48 71,500.36
12 Pipa Galvanis 1" MB m1 58,333.33 68,413.80 68,413.80 69,440.01 69,440.01 70,124.15 71,150.35 75,255.18 71,150.35 75,255.18 72,518.63
13 Pipa Galvanis 1,5 BSA m1 55,500.00 65,147.65 65,147.65 66,124.86 66,124.86 66,776.34 67,753.55 71,662.41 67,753.55 71,662.41 69,056.51
14 Pipa Galvanis 2" m1 - -
15 Pipa Galvanis 2" MA m1 100,000.00 116,445.47 116,445.47 118,192.15 118,192.15 119,356.60 121,103.29 128,090.01 121,103.29 128,090.01 123,432.19
16 Pipa Galvanis 2" MB m1 95,833.33 111,642.30 111,642.30 113,316.93 113,316.93 114,433.36 116,107.99 122,806.53 116,107.99 122,806.53 118,340.84
17 Pipa Galvanis 3" m1 137,500.00 159,673.97 159,673.97 162,069.08 162,069.08 163,665.82 166,060.93 175,641.36 166,060.93 175,641.36 169,254.40
18 Pipa Galvanis 3" MA m1 114,166.67 132,776.23 132,776.23 134,767.88 134,767.88 136,095.64 138,087.28 146,053.86 138,087.28 146,053.86 140,742.81
19 Pipa Galvanis 3" MB m1 175,833.33 203,863.10 203,863.10 206,921.05 206,921.05 208,959.68 212,017.62 224,249.41 212,017.62 224,249.41 216,094.89
20 Pipa Maspion AW 1 m1 12,500.00 15,578.97 15,578.97 15,812.65 15,812.65 15,968.44 16,202.13 17,136.86 16,202.13 17,136.86 16,513.70
21 Pipa Winlon AW 1 m1 15,000.00 18,460.87 18,460.87 18,737.78 18,737.78 18,922.39 19,199.30 20,306.95 19,199.30 20,306.95 19,568.52
22 Pipa Maspion AW 1/2 m1 8,750.00 11,256.12 11,256.12 11,424.96 11,424.96 11,537.52 11,706.36 12,381.73 11,706.36 12,381.73 11,931.48
23 Pipa Winlon AW 1/2 m1 8,750.00 11,256.12 11,256.12 11,424.96 11,424.96 11,537.52 11,706.36 12,381.73 11,706.36 12,381.73 11,931.48
24 Pipa Maspion AW 10 m1 - -
25 Pipa Maspion AW 1-1/2 m1 - - - - - - - - - - -
26 Pipa Winlon AW 1-1/2 m1 22,500.00 27,691.30 27,691.30 28,106.67 28,106.67 28,383.58 28,798.95 30,460.43 28,798.95 30,460.43 29,352.78
27 Pipa Maspion D 1-1/2 m1 - - - - - - - - - - -
28 Pipa Winlon D 1-1/2 m1 13,750.00 17,604.65 17,604.65 17,868.72 17,868.72 18,044.77 18,308.84 19,365.12 18,308.84 19,365.12 18,660.93
29 Pipa Maspion AW 1-1/4 m1 - - - - - - - - - - -
30 Pipa Winlon AW 1-1/4 m1 13,750.00 37,155.46 37,155.46 37,712.79 37,712.79 38,084.35 38,641.68 40,871.01 38,641.68 40,871.01 39,384.79
31 Pipa Maspion AW 12 m1 38,750.00 65,974.46 65,974.46 66,964.08 66,964.08 67,623.82 68,613.44 72,571.91 68,613.44 72,571.91 69,932.93
32 Pipa Maspion AW 14 m1 47,500.00 76,061.11 76,061.11 77,202.03 77,202.03 77,962.64 79,103.55 83,667.22 79,103.55 83,667.22 80,624.78
33 Pipa Maspion AW 16 m1 60,000.00 90,470.61 90,470.61 91,827.67 91,827.67 92,732.37 94,089.43 99,517.67 94,089.43 99,517.67 95,898.85
34 Pipa Maspion AW 2 m1 - -
35 Pipa Winlon AW 2 m1 30,000.00 36,337.00 36,337.00 36,882.06 36,882.06 37,245.43 37,790.48 39,970.70 37,790.48 39,970.70 38,517.22
36 Pipa Maspion D 2 m1 - -
37 Pipa Winlon D 2 m1 21,250.00 26,250.35 26,250.35 26,644.11 26,644.11 26,906.61 27,300.36 28,875.39 27,300.36 28,875.39 27,825.37
38 Pipa Maspion AW 2-1/2 m1 12,000.00 15,587.32 15,587.32 15,821.13 15,821.13 15,977.00 16,210.81 17,146.05 16,210.81 17,146.05 16,522.56
39 Pipa Maspion D 2-1/2 m1 - - - - - - - - - - -
40 Pipa Winlon D 2-1/2 m1 22,500.00 27,691.30 27,691.30 28,106.67 28,106.67 28,383.58 28,798.95 30,460.43 28,798.95 30,460.43 29,352.78
41 Pipa Maspion AW 3 m1 - - - - - - - - - - -
42 Pipa Winlon AW 3 m1 52,500.00 62,274.10 62,274.10 63,208.21 63,208.21 63,830.95 64,765.06 68,501.51 64,765.06 68,501.51 66,010.55
43 Pipa Maspion AW 3/4 m1 10,000.00 13,281.80 13,281.80 13,481.03 13,481.03 13,613.85 13,813.07 14,609.98 13,813.07 14,609.98 14,078.71
44 Pipa Winlon AW 3/4 m1 10,000.00 13,281.80 13,281.80 13,481.03 13,481.03 13,613.85 13,813.07 14,609.98 13,813.07 14,609.98 14,078.71
45 Pipa Maspion AW 4 m1 - -
46 Pipa Winlon AW 4 m1 93,750.00 109,825.45 109,825.45 111,472.83 111,472.83 112,571.09 114,218.47 120,808.00 114,218.47 120,808.00 116,414.98
47 Pipa Maspion D 4" m1 40,000.00 47,864.60 47,864.60 48,582.57 48,582.57 49,061.22 49,779.18 52,651.06 49,779.18 52,651.06 50,736.48
48 Pipa Winlon D 4" m1 66,250.00 78,124.55 78,124.55 79,296.42 79,296.42 80,077.66 81,249.53 85,937.01 81,249.53 85,937.01 82,812.02
49 Pipa Maspion AW 5 m1 - - - - - - - - - -
50 Pipa Maspion AW 6 m1 - - - - - - - - - -
51 Pipa Maspion AW 8 m1 - - - - - - - - - -
52 Pipa Maspion C 1 m1 - - - - - - - - - - -
53 Pipa Maspion C 1-1/2 m1 - - - - - - - - - - -
54 Pipa Maspion C 1-1/4 m1 - - - - - - - - - - -
55 Pipa Maspion C 2 m1 - - - - - - - - - - -
56 Pipa Maspion C 2-1/2 m1 - - - - - - - - - - -
57 Pipa Maspion C 3 m1 - - - - - - - - - - -
58 Pipa Maspion C 3/4 m1 - - - - - - - - - - -
59 Pipa Maspion C 4 m1 - - - - - - - - - - -
60 Pipa Maspion C 5/8 m1 - - - - - - - - - - -
61 Pipa Maspion D 10 m1 - - - - - - - - - -
62 Pipa Maspion D 1-1/2 m1 - - - - - - - - - - -
63 Pipa Winlon D 1-1/2 m1 13,750.00 17,604.65 17,604.65 17,868.72 17,868.72 18,044.77 18,308.84 19,365.12 18,308.84 19,365.12 18,660.93
64 Pipa Winlon D 1-1/4 m1 12,500.00 16,163.70 16,163.70 16,406.16 16,406.16 16,567.79 16,810.25 17,780.07 16,810.25 17,780.07 17,133.52
65 Pipa Maspion D 1-1/4 m1 - -
66 Pipa Maspion D 12 m1 - - -
67 Pipa Maspion D 14 m1 - - - - - - - - - - -
68 Pipa Maspion D 16 m1 - - - - - - - - - - -
69 Pipa Maspion D 2 m1 - - - - - - - - - - -
70 Pipa Maspion D 2-1/2 m1 - -
71 Pipa Maspion D 3 m1 - -

Harga Satauan Bahan dan Upah Hal. 67


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA FAKFAK FAKFAK TENGAH PARIWARI FAKFAK BARAT WARTUTIN FAKFAK TIMUR FAKFAK TIMUR KOKAS KAYUNI
DASAR TENGAH

1 2 3 4 5 6 7 8 9 10 11 12 13 6
72 Pipa Maspion D 4 m1 - - - - - - - - - - -
73 Pipa Maspion D 5 m1 - - - - - - - - - - -
74 Pipa Maspion D 6 m1 - - - - - - - - - - -
75 Pipa Maspion D 8 m1 - - - - - - - - - - -
76 Elbo 1/2" PVC bh 6,000.00 8,420.16 8,420.16 8,546.46 8,546.46 8,630.66 8,756.97 9,262.18 8,756.97 9,262.18 8,925.37
77 Elbo 3/4" PVC bh 8,000.00 10,725.68 10,725.68 10,886.57 10,886.57 10,993.82 11,154.71 11,798.25 11,154.71 11,798.25 11,369.22
78 Elbo PVC 4" bh 55,000.00 64,905.40 64,905.40 65,878.98 65,878.98 66,528.04 67,501.62 71,395.94 67,501.62 71,395.94 68,799.72
79 Elbo PVC 3" bh 30,000.00 36,086.40 36,086.40 36,627.70 36,627.70 36,988.56 37,529.86 39,695.04 37,529.86 39,695.04 38,251.58
80 Elbo PVC 2,5" bh 21,000.00 25,711.56 25,711.56 26,097.23 26,097.23 26,354.35 26,740.02 28,282.72 26,740.02 28,282.72 27,254.25
81 Selang hipres 1" m1 35,000.00 41,850.20 41,850.20 42,477.95 42,477.95 42,896.46 43,524.21 46,035.22 43,524.21 46,035.22 44,361.21
82 Selang hipres 2" m1 95,000.00 111,015.80 111,015.80 112,681.04 112,681.04 113,791.20 115,456.43 122,117.38 115,456.43 122,117.38 117,676.75
83 Selang hipres 1,5" m1 40,000.00 47,614.00 47,614.00 48,328.21 48,328.21 48,804.35 49,518.56 52,375.40 49,518.56 52,375.40 50,470.84
84 Selang hipres 0,5" m1 11,000.00 14,183.96 14,183.96 14,396.72 14,396.72 14,538.56 14,751.32 15,602.36 14,751.32 15,602.36 15,035.00
85 Selang spiral 2" m1 90,000.00 105,252.00 105,252.00 106,830.78 106,830.78 107,883.30 109,462.08 115,777.20 109,462.08 115,777.20 111,567.12
- - - - - - - - -
SEMEN - - - - - - - - -
1 Semen Gresik 40 kg kg 1,875.00 2,336.85 2,336.85 2,371.90 2,371.90 2,395.27 2,430.32 2,570.53 2,430.32 2,570.53 2,477.06
2 Semen Tiga Roga 40 kg kg - - - - - - - - - - -
3 Semen Tonasa 40 kg kg 2,000.00 2,480.94 2,480.94 2,518.15 2,518.15 2,542.96 2,580.18 2,729.03 2,580.18 2,729.03 2,629.80
4 Semen Bosowa 40 kg kg - - - - - - - - - - -
5 Semen warna/semen grouting kg 13,000.00 16,489.48 16,489.48 16,736.82 16,736.82 16,901.72 17,149.06 18,138.43 17,149.06 18,138.43 17,478.85
6 Semen putih kg 20,000.00 24,558.80 24,558.80 24,927.18 24,927.18 25,172.77 25,541.15 27,014.68 25,541.15 27,014.68 26,032.33
- - - - - - - - -
BESI BETON DAN PAGAR - - - - - - - - -
1 Besi beton kg 12,395.43 19,417.41 19,417.41 19,708.67 19,708.67 19,902.84 20,194.10 21,359.15 20,194.10 21,359.15 20,582.45
2 Besi beton Kg 12,395.43 19,417.41 19,417.41 19,708.67 19,708.67 19,902.84 20,194.10 21,359.15 20,194.10 21,359.15 20,582.45
3 Besi Beton Ulir - - - - - - - - -
Besi Beton Ulir 16 mm btg 195,000.00 - - - - - - - - -
Besi Beton Ulir 12 mm btg 105,000.00 - - - - - - - - -
Besi Beton Ulir 10 mm btg 75,000.00 - - - - - - - - -
4 Besi Beton - - - - - - - - -
Diameter 5.5 mm btg 30,000.00 - - - - - - - - -
Diameter 6 mm btg 36,000.00 - - - - - - - - -
Diameter 8 mm btg 68,000.00 - - - - - - - - -
Diameter 9 mm btg 75,000.00 - - - - - - - - -
Diameter 10 mm btg 110,000.00 - - - - - - - - -
Diameter 12 mm btg 160,000.00 - - - - - - - - -
Diameter 16 mm btg 239,000.00 - - - - - - - - -
Diameter 19 mm btg 298,000.00 - - - - - - - - -
Diameter 22 mm btg - - - - - - - - - -
Diameter 25 mm btg - - - - - - - - - -
5 Besi Siku 4x4 btg 210,000.00 245,086.80 245,086.80 248,763.10 248,763.10 251,213.97 254,890.27 269,595.48 254,890.27 269,595.48 259,792.01
6 Besi Siku 5 X 5 btg 375,000.00 435,292.20 435,292.20 441,821.58 441,821.58 446,174.51 452,703.89 478,821.42 452,703.89 478,821.42 461,409.73
7 Besi Siku Lubang btg 190,000.00 222,031.60 222,031.60 225,362.07 225,362.07 227,582.39 230,912.86 244,234.76 230,912.86 244,234.76 235,353.50
8 Besi UN 60 btg 405,000.00 469,875.00 469,875.00 476,923.13 476,923.13 481,621.88 488,670.00 516,862.50 488,670.00 516,862.50 498,067.50
9 Besi UN 80 btg 540,000.00 625,497.60 625,497.60 634,880.06 634,880.06 641,135.04 650,517.50 688,047.36 650,517.50 688,047.36 663,027.46
10 Besi Holous 20 x 40 btg 135,000.00 158,629.80 158,629.80 161,009.25 161,009.25 162,595.55 164,974.99 174,492.78 164,974.99 174,492.78 168,147.59
11 Besi Holous 40 x 40 btg 240,000.00 279,669.60 279,669.60 283,864.64 283,864.64 286,661.34 290,856.38 307,636.56 290,856.38 307,636.56 296,449.78
12 Kawat Bronjong ukuran 2 m kg 25,000.00 31,826.20 31,826.20 32,303.59 32,303.59 32,621.86 33,099.25 35,008.82 33,099.25 35,008.82 33,735.77
13 Kawat Bronjong ukuran 2,7 m kg - - - - - - - - - - -
14 Kawat Bronjong ukuran 3 m kg - - - - - - - - - - -
15 Kawat Bronjong ukuran 3,4 m kg - -
16 Kawat Bronjong ukuran 4 m kg - - - - - - - - - - -
17 Kawat berduri roll 130,000.00 156,875.60 156,875.60 159,228.73 159,228.73 160,797.49 163,150.62 172,563.16 163,150.62 172,563.16 166,288.14
18 Kawat beton RRT 1 Kg kg 25,000.00 35,835.80 35,835.80 36,373.34 36,373.34 36,731.70 37,269.23 39,419.38 37,269.23 39,419.38 37,985.95
19 Kawat ram m' 55,000.00 70,418.60 70,418.60 71,474.88 71,474.88 72,179.07 73,235.34 77,460.46 73,235.34 77,460.46 74,643.72
20 Kawat nyamuk m' 35,000.00 47,363.40 47,363.40 48,073.85 48,073.85 48,547.49 49,257.94 52,099.74 49,257.94 52,099.74 50,205.20
21 Kawat ayakan m' 45,000.00 58,891.00 58,891.00 59,774.37 59,774.37 60,363.28 61,246.64 64,780.10 61,246.64 64,780.10 62,424.46
22 Kawat Las RB Dos 300,000.00 352,844.80 352,844.80 358,137.47 358,137.47 361,665.92 366,958.59 388,129.28 366,958.59 388,129.28 374,015.49
23 Kawat Las 1kg kg 120,000.00 145,348.00 145,348.00 147,528.22 147,528.22 148,981.70 151,161.92 159,882.80 151,161.92 159,882.80 154,068.88
24 Kawat Ikat kg 30,000.00 41,599.60 41,599.60 42,223.59 42,223.59 42,639.59 43,263.58 45,759.56 43,263.58 45,759.56 44,095.58
25 Kawat Harmonika besar mtr 65,000.00 81,946.20 81,946.20 83,175.39 83,175.39 83,994.86 85,224.05 90,140.82 85,224.05 90,140.82 86,862.97
26 Kawat Harmonika sedang mtr 55,000.00 70,418.60 70,418.60 71,474.88 71,474.88 72,179.07 73,235.34 77,460.46 73,235.34 77,460.46 74,643.72
27 Pagar BRC FP 90 EP 1,5 Panil 475,200.00 554,808.35 554,808.35 563,130.48 563,130.48 568,678.56 577,000.69 610,289.19 577,000.69 610,289.19 588,096.85
28 Pagar BRC FP 90 EP 2,0 Panil 526,700.00 614,175.49 614,175.49 623,388.12 623,388.12 629,529.88 638,742.51 675,593.04 638,742.51 675,593.04 651,026.02
29 Pagar BRC FP 120 EP 1,5 Panil 607,600.00 707,433.78 707,433.78 718,045.28 718,045.28 725,119.62 735,731.13 778,177.15 735,731.13 778,177.15 749,879.80
30 Pagar BRC FP 120 EP 2,0 Panil 671,100.00 780,634.04 780,634.04 792,343.55 792,343.55 800,149.89 811,859.40 858,697.44 811,859.40 858,697.44 827,472.08

Harga Satauan Bahan dan Upah Hal. 68


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA FAKFAK FAKFAK TENGAH PARIWARI FAKFAK BARAT WARTUTIN FAKFAK TIMUR FAKFAK TIMUR KOKAS KAYUNI
DASAR TENGAH

1 2 3 4 5 6 7 8 9 10 11 12 13 6
31 Pagar BRC FP 150 EP 1,5 Panil 689,000.00 801,268.44 801,268.44 813,287.47 813,287.47 821,300.15 833,319.18 881,395.28 833,319.18 881,395.28 849,344.55
32 Pagar BRC FP 150 EP 2,0 Panil 754,500.00 876,774.22 876,774.22 889,925.83 889,925.83 898,693.58 911,845.19 964,451.64 911,845.19 964,451.64 929,380.67
33 Pagar BRC FP 175 EP 2,0 Panil 848,500.00 985,133.66 985,133.66 999,910.66 999,910.66 1,009,762.00 1,024,539.01 1,083,647.03 1,024,539.01 1,083,647.03 1,044,241.68
34 Pagar BRC FP 175 EP 2,5 Panil 926,500.00 1,075,048.94 1,075,048.94 1,091,174.67 1,091,174.67 1,101,925.16 1,118,050.90 1,182,553.83 1,118,050.90 1,182,553.83 1,139,551.88
35 Pagar BRC FP 190 EP 2,5 Panil 998,200.00 1,157,701.83 1,157,701.83 1,175,067.36 1,175,067.36 1,186,644.38 1,204,009.91 1,273,472.02 1,204,009.91 1,273,472.02 1,227,163.94
36 P90 EP dia.1,5" bh 120,659.79 146,108.58 146,108.58 148,300.21 148,300.21 149,761.29 151,952.92 160,719.44 151,952.92 160,719.44 154,875.09
37 P90 EP dia.2" bh 150,561.85 180,578.48 180,578.48 183,287.15 183,287.15 185,092.94 187,801.62 198,636.33 187,801.62 198,636.33 191,413.19
38 P120 EP dia.1,5" bh 144,449.74 173,532.68 173,532.68 176,135.67 176,135.67 177,871.00 180,473.99 190,885.95 180,473.99 190,885.95 183,944.64
39 P120 EP dia.2" bh 167,577.31 200,193.22 200,193.22 203,196.12 203,196.12 205,198.05 208,200.95 220,212.54 208,200.95 220,212.54 212,204.82
40 P150 EP dia.1,5" bh 166,239.69 198,651.26 198,651.26 201,631.03 201,631.03 203,617.54 206,597.31 218,516.39 206,597.31 218,516.39 210,570.34
41 P150 EP dia.2,0" bh 208,092.77 246,897.83 246,897.83 250,601.29 250,601.29 253,070.27 256,773.74 271,587.61 256,773.74 271,587.61 261,711.70
42 P175 EP dia.2,0" bh 249,865.97 295,052.29 295,052.29 299,478.08 299,478.08 302,428.60 306,854.39 324,557.52 306,854.39 324,557.52 312,755.43
43 P190 EP dia.1,0" bh 260,530.92 307,346.43 307,346.43 311,956.63 311,956.63 315,030.09 319,640.29 338,081.07 319,640.29 338,081.07 325,787.21
- - - - - - - - -
BAHAN LISTRIK - - - - - - - - -
1 Saklar (Broco) double bh 35,000.00 41,850.20 41,850.20 42,477.95 42,477.95 42,896.46 43,524.21 46,035.22 43,524.21 46,035.22 44,361.21
2 Saklar (Broco) engkle bh 32,000.00 38,391.92 38,391.92 38,967.80 38,967.80 39,351.72 39,927.60 42,231.11 39,927.60 42,231.11 40,695.44
3 Saklar (Oni) double bh 14,000.00 17,642.24 17,642.24 17,906.87 17,906.87 18,083.30 18,347.93 19,406.46 18,347.93 19,406.46 18,700.77
4 Saklar (Oni) engkle bh 13,000.00 16,489.48 16,489.48 16,736.82 16,736.82 16,901.72 17,149.06 18,138.43 17,149.06 18,138.43 17,478.85
5 Saklar tunggal philip bh 55,000.00 64,905.40 64,905.40 65,878.98 65,878.98 66,528.04 67,501.62 71,395.94 67,501.62 71,395.94 68,799.72
6 Saklar ganda philip bh 45,000.00 53,377.80 53,377.80 54,178.47 54,178.47 54,712.25 55,512.91 58,715.58 55,512.91 58,715.58 56,580.47
7 Stop kontak philip bh 45,000.00 53,377.80 53,377.80 54,178.47 54,178.47 54,712.25 55,512.91 58,715.58 55,512.91 58,715.58 56,580.47
8 Stop Kontak (Oni) bh 12,000.00 15,336.72 15,336.72 15,566.77 15,566.77 15,720.14 15,950.19 16,870.39 15,950.19 16,870.39 16,256.92
9 Stop Kontak (Oni) 2 lubang bh 20,000.00 24,558.80 24,558.80 24,927.18 24,927.18 25,172.77 25,541.15 27,014.68 25,541.15 27,014.68 26,032.33
10 Stop Kontak (Vticon) 2 lubang bh 15,000.00 18,795.00 18,795.00 19,076.93 19,076.93 19,264.88 19,546.80 20,674.50 19,546.80 20,674.50 19,922.70
11 Stop Kontak (Oni) 3 lubang bh 30,000.00 36,086.40 36,086.40 36,627.70 36,627.70 36,988.56 37,529.86 39,695.04 37,529.86 39,695.04 38,251.58
12 Stop Kontak (Oni) 4 lubang bh 40,000.00 47,614.00 47,614.00 48,328.21 48,328.21 48,804.35 49,518.56 52,375.40 49,518.56 52,375.40 50,470.84
13 Fitting Biasa bh 24,000.00 29,169.84 29,169.84 29,607.39 29,607.39 29,899.09 30,336.63 32,086.82 30,336.63 32,086.82 30,920.03
14 Fitting keramik bh 80,000.00 93,724.40 93,724.40 95,130.27 95,130.27 96,067.51 97,473.38 103,096.84 97,473.38 103,096.84 99,347.86
15 Steker biasa bh 20,000.00 24,558.80 24,558.80 24,927.18 24,927.18 25,172.77 25,541.15 27,014.68 25,541.15 27,014.68 26,032.33
16 Steker Broco bh 20,000.00 24,558.80 24,558.80 24,927.18 24,927.18 25,172.77 25,541.15 27,014.68 25,541.15 27,014.68 26,032.33
17 Coaxial cable 5C - 75 ohm commscof m1 5,700.00 8,074.33 8,074.33 8,195.45 8,195.45 8,276.19 8,397.31 8,881.77 8,397.31 8,881.77 8,558.79
18 Kabel NYM 3 x 2.5 mm ex. Supreme m1 20,000.00 24,558.80 24,558.80 24,927.18 24,927.18 25,172.77 25,541.15 27,014.68 25,541.15 27,014.68 26,032.33
19 Kabel NYM 3 x 1.5 mm ex. Eterna m1 16,000.00 19,947.76 19,947.76 20,246.98 20,246.98 20,446.45 20,745.67 21,942.54 20,745.67 21,942.54 21,144.63
20 Kabel NYM 4 mm m1 21,000.00 25,711.56 25,711.56 26,097.23 26,097.23 26,354.35 26,740.02 28,282.72 26,740.02 28,282.72 27,254.25
21 Kabel NYA 4mm rol 500,000.00 577,883.60 577,883.60 586,551.85 586,551.85 592,330.69 600,998.94 635,671.96 600,998.94 635,671.96 612,556.62
22 Kabel telephone m1 5,000.00 7,267.40 7,267.40 7,376.41 7,376.41 7,449.09 7,558.10 7,994.14 7,558.10 7,994.14 7,703.44
23 Lampu 8 Watt (Philip) bh 45,000.00 53,377.80 53,377.80 54,178.47 54,178.47 54,712.25 55,512.91 58,715.58 55,512.91 58,715.58 56,580.47
24 Lampu 8 Watt (Philip) Tornado bh 45,000.00 53,377.80 53,377.80 54,178.47 54,178.47 54,712.25 55,512.91 58,715.58 55,512.91 58,715.58 56,580.47
25 Lampu 11 Watt (Philip) bh 36,000.00 43,002.96 43,002.96 43,648.00 43,648.00 44,078.03 44,723.08 47,303.26 44,723.08 47,303.26 45,583.14
26 Lampu 14 Watt (Philip) bh 40,000.00 47,614.00 47,614.00 48,328.21 48,328.21 48,804.35 49,518.56 52,375.40 49,518.56 52,375.40 50,470.84
27 Lampu 18 Watt (Philip) bh 45,000.00 53,377.80 53,377.80 54,178.47 54,178.47 54,712.25 55,512.91 58,715.58 55,512.91 58,715.58 56,580.47
28 Lampu 20 Watt (Philip) bh 53,000.00 62,599.88 62,599.88 63,538.88 63,538.88 64,164.88 65,103.88 68,859.87 65,103.88 68,859.87 66,355.87
29 Lampu 23 Watt (Philip) bh 60,000.00 70,669.20 70,669.20 71,729.24 71,729.24 72,435.93 73,495.97 77,736.12 73,495.97 77,736.12 74,909.35
30 Lampu 24 Watt (Philip) bh 60,000.00 70,669.20 70,669.20 71,729.24 71,729.24 72,435.93 73,495.97 77,736.12 73,495.97 77,736.12 74,909.35
31 Lampu 24 Watt (Philip) tornado bh 58,000.00 68,363.68 68,363.68 69,389.14 69,389.14 70,072.77 71,098.23 75,200.05 71,098.23 75,200.05 72,465.50
32 Lampu 15 Watt (Philip) tornado bh 50,000.00 59,141.60 59,141.60 60,028.72 60,028.72 60,620.14 61,507.26 65,055.76 61,507.26 65,055.76 62,690.10
33 Lampu downlight 3,5" bh 45,000.00 53,377.80 53,377.80 54,178.47 54,178.47 54,712.25 55,512.91 58,715.58 55,512.91 58,715.58 56,580.47
34 Lampu downlight 4" bh 70,000.00 82,196.80 82,196.80 83,429.75 83,429.75 84,251.72 85,484.67 90,416.48 85,484.67 90,416.48 87,128.61
35 Lampu downlight 5" bh 85,000.00 99,488.20 99,488.20 100,980.52 100,980.52 101,975.41 103,467.73 109,437.02 103,467.73 109,437.02 105,457.49
36 Isolasi unibelt bh 20,000.00 24,558.80 24,558.80 24,927.18 24,927.18 25,172.77 25,541.15 27,014.68 25,541.15 27,014.68 26,032.33
37 Pipa clipsal 20 mm bt 25,000.00 30,322.60 30,322.60 30,777.44 30,777.44 31,080.67 31,535.50 33,354.86 31,535.50 33,354.86 32,141.96
38 Pipa flexible clipsal 20 mm m1 40,000.00 47,614.00 47,614.00 48,328.21 48,328.21 48,804.35 49,518.56 52,375.40 49,518.56 52,375.40 50,470.84
39 Sock clipsal 20 mm bj 4,000.00 6,114.64 6,114.64 6,206.36 6,206.36 6,267.51 6,359.23 6,726.10 6,359.23 6,726.10 6,481.52
40 Tee dos clipsal 20 mm bh 10,000.00 13,031.20 13,031.20 13,226.67 13,226.67 13,356.98 13,552.45 14,334.32 13,552.45 14,334.32 13,813.07
41 Klem clipsal 0,5 " bj 5,000.00 7,267.40 7,267.40 7,376.41 7,376.41 7,449.09 7,558.10 7,994.14 7,558.10 7,994.14 7,703.44
42 Inbow dos plastik clipsal E 157 P bj 13,000.00 16,489.48 16,489.48 16,736.82 16,736.82 16,901.72 17,149.06 18,138.43 17,149.06 18,138.43 17,478.85
- - - - - - - - -
PAVING - - - - - - - - -
1 Paving 10 x 20 cm tebal 6 cm K225 m2 - Err:522
2 Paving 10 x 20 cm tebal 6 cm K350 m2 - Err:522
3 Paving 10 x 20 cm tebal 8 cm K225 m2 - Err:522
4 Paving 10 x 20 cm tebal 8 cm K350 m2 - Err:522
5 Paving 10 x 20 cm tebal 8 cm K425 m2 - Err:522
6 Paving 20 x 20 cm tebal 6 cm K225 m2 - Err:522
7 Paving 20 x 20 cm tebal 6 cm K350 m2 - Err:522
8 Paving 20 x 20 cm tebal 8 cm K225 m2 - Err:522

Harga Satauan Bahan dan Upah Hal. 69


NO NAMA BARANG SATUAN
NO NAMA BARANG SATUAN HARGA DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK DISTRIK
MSK ANALISA FAKFAK FAKFAK TENGAH PARIWARI FAKFAK BARAT WARTUTIN FAKFAK TIMUR FAKFAK TIMUR KOKAS KAYUNI
DASAR TENGAH

1 2 3 4 5 6 7 8 9 10 11 12 13 6
9 Paving 20 x 20 cm tebal 8 cm K350 m2 - Err:522
10 Paving 20 x 20 cm tebal 8 cm K425 m2 - Err:522
11 Paving 20 x 20 cm tebal 10 cm K225 m2 - Err:522
12 Paving 20 x 20 cm tebal 10 cm K350 m2 - Err:522
13 Paving 20 x 20 cm tebal 10 cm K425 m2 - Err:522
14 Paving Tiga Berlian tebal 6 cm K225 m2 - Err:522
15 Kanstein Bulat (P:50,T:30,La:10,Lb:16 cm K225) m1 - Err:522
16 Kanstein Jumbo (P:50,L:15,T:30 cm K225) m1 - Err:522
17 Kanstein Segi Lima Jumbo (P:50,L:15, T:40 cm K225) m1 - -
18 Grass Block 36 X 54 cm tebal 9 cm K 225 m2 - - - - - - - - - -
19 Koral Sikat zak/10 kg -

LAIN-LAIN - - - - - - - -
1 Dugul batu hitam 50 x 50 x 200 unit - Err:522
2 Dugul batu hitam 60 x 70 x 250 unit - Err:522
3 Dugul batu hitam 70 x 70 x 250 unit - Err:522
4 Padmasari batu hitam 50 x 50 x 200 unit - Err:522
5 Padmasari batu hitam 70 x 70 x 250 unit - Err:522
6 Padmasari batu hitam 65 x 75 x 225 unit - Err:522
7 Karpet plastik m2 18,000.00 27,766.48 27,766.48 28,182.98 28,182.98 28,460.64 28,877.14 30,543.13 28,877.14 30,543.13 29,432.47
8 Talang PVC P= 4M', L=4" bentuk bulat buah 145,000.00 174,167.00 174,167.00 176,779.51 176,779.51 178,521.18 181,133.68 191,583.70 181,133.68 191,583.70 184,617.02
9 Talang PVC P= 4M', L=4" bentuk kotak buah 175,000.00 208,749.80 208,749.80 211,881.05 211,881.05 213,968.55 217,099.79 229,624.78 217,099.79 229,624.78 221,274.79
10 Talang PVC P= 4M', L=8" bentuk kotak buah 250,000.00 295,206.80 295,206.80 299,634.90 299,634.90 302,586.97 307,015.07 324,727.48 307,015.07 324,727.48 312,919.21
11 Talang PVC P= 4M', L=6" bentuk bulat buah 90,000.00 110,765.20 110,765.20 112,426.68 112,426.68 113,534.33 115,195.81 121,841.72 115,195.81 121,841.72 117,411.11
12 Talang PVC P= 4M', L=40" bentuk bulat buah - -
13 Talang PVC P= 4M', L=140 mm" bentuk kotak buah 115,000.00 139,584.20 139,584.20 141,677.96 141,677.96 143,073.81 145,167.57 153,542.62 145,167.57 153,542.62 147,959.25
14 Talang PVC P= 4M', L: 8' buah 98,000.00 119,987.28 119,987.28 121,787.09 121,787.09 122,986.96 124,786.77 131,986.01 124,786.77 131,986.01 127,186.52

Fakfak, 12 Februari 2018


PANITIA PENYUSUNAN STANDART HARGA SATUAN HARGA
TAHUN 2018

Sekretaris, Ketua,

RIZAL MINGGELE, ST LIZA NEIRASARI, ST


NIP. 19820701 200909 1 001 NIP. 19751016 200111 2 001

Mengetahui,
Kepala Dinas PU, Penataan Ruang, Perumahan Rakyat
dan Kawasan Permukiman
Kabupaten Fakfak ,

SAMAUN DAHLAN S.Sos, MAP


NIP. 19681005 199108 1 002

Harga Satauan Bahan dan Upah Hal. 70


DAFTAR ANALISA PEKERJAAN
TAHUN 2018
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN (SNI 03-2835-2002)
1 1 M1 PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2
METER
1.2500 btg Bambu Sedang 18,795.00 23,493.75
2.5000 kg Semen Portland 2,336.85 5,842.11
1.2000 lbr Seng gelombang 3" - 5" 93,724.40 112,469.28
0.0050 m3 Pasir Beton 1,929,620.00 9,648.10
0.0090 m3 Koral beton 1,426,289.90 12,836.61
0.0720 m3 Kayu Matoa Usuk 5/7 2,884,907.20 207,713.32
0.0600 kg Paku biasa 2" - 5" 36,086.40 2,165.18
0.4500 kg Meni Besi 30,322.60 13,645.17
0.2000 oh Tukang Kayu 148,350.00 29,670.00
0.4000 oh Pekerja 115,000.00 46,000.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0200 oh Mandor 159,275.00 3,185.50
Total : 81,937.50 387,813.52 469,751.02

2 1 M1 PENGUKURAN DAN PEMASANGAN BOWPLANK


0.0120 m3 Kayu putih 5/7 2,884,907.20 34,618.89
0.0200 kg Paku Biasa 2" - 5" 36,086.40 721.73
0.0070 m3 Kayu Papan putih 3/20 2,308,527.20 16,159.69
0.1000 oh Tukang Kayu 148,350.00 14,835.00
0.1000 oh Pekerja 115,000.00 11,500.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0050 oh Mandor 159,275.00 796.38
Total : 28,672.38 51,500.30 80,172.68

3 1 M2 PEMBUATAN KANTOR SEMENTARA, DENGAN LANTAI


PLESTERAN
1.2500 btg Dolken Kayu Ø 8 - 10/4m 43,002.96 53,753.70
0.1800 m3 Kayu Matoa 2,654,355.20 477,783.94
0.8500 kg Paku Biasa 2" - 5" 36,086.40 30,673.44
1.1000 kg Besi Strip 9,872.64 10,859.90
35.0000 kg Semen Portland 2,336.85 81,789.58
0.1500 m3 Pasir Pasang 1,353,240.00 202,986.00
0.1000 m3 Pasir Beton 1,929,620.00 192,962.00
0.1500 m3 Koral Beton 1,426,289.90 213,943.49
30.0000 bh Batu tela 11,432.19 342,965.73
0.2500 lbr Seng Plat 18,795.00 4,698.75
2.0000 bh Jendela Nako 25,711.56 51,423.12
0.0800 m2 Kaca Polos 155,896.61 12,471.73
0.1500 bh Kunci Tanam 203,236.60 30,485.49
0.0600 lbr Tripleks 4 mm 128,307.20 7,698.43
2.0000 oh Tukang Kayu 148,350.00 296,700.00
1.0000 oh Tukang Batu 142,600.00 142,600.00
2.0000 oh Pekerja 115,000.00 230,000.00
0.3000 oh Kepala Tukang 154,100.00 46,230.00
0.0500 oh Mandor 159,275.00 7,963.75
Total : 723,493.75 1,714,495.28 2,437,989.03

4 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT


1.7000 btg Bambu Sedang 18,795.00 31,951.50
0.2100 m3 Kayu Matoa 2,654,355.20 557,414.59
0.3000 kg Paku Biasa 2" - 5" 36,086.40 10,825.92
10.5000 kg Semen Portland 2,336.85 24,536.87
0.0300 m3 Pasir Beton 1,929,620.00 57,888.60
0.0500 m3 Koral Beton 1,426,289.90 71,314.50
1.5000 lbr Seng gelombang BJLS 20 76,433.00 114,649.50
2.0000 oh Tukang Kayu 148,350.00 296,700.00
1.0000 oh Pekerja 115,000.00 115,000.00
0.2000 oh Kepala Tukang 154,100.00 30,820.00
0.0500 oh Mandor 159,275.00 7,963.75
Total : 450,483.75 868,581.48 1,319,065.23

5 1 M2 PEMBUATAN RUMAH JAGA/KONSTRUKSI KAYU


3.0000 btg Bambu Sedang 18,795.00 56,385.00
0.2760 m3 Kayu Matoa 2,654,355.20 732,602.04
0.7000 kg Paku biasa 2" - 5" 36,086.40 25,260.48
1.5000 lbr Seng gelombang BJLS 20 76,433.00 114,649.50
1.5000 oh Tukang Kayu 148,350.00 222,525.00
1.0000 oh Pekerja 115,000.00 115,000.00
0.1500 oh Kepala Tukang 154,100.00 23,115.00
0.0500 oh Mandor 159,275.00 7,963.75
Total : 368,603.75 928,897.02 1,297,500.77
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

6 1 M2 MEMBERSIHKAN LAPANGAN DAN PERATAAN


0.1000 oh Pekerja 115,000.00 11,500.00
0.0500 oh Mandor 159,275.00 7,963.75
Total : 19,463.75 19,463.75

7 1 M2 PEMBUATAN BEDENG BURUH


1.2500 btg Bambu Sedang 18,795.00 23,493.75
0.1860 m3 Kayu Matoa 2,654,355.20 493,710.07
0.3000 kg Paku Biasa 2" - 5" 36,086.40 10,825.92
18.0000 kg Semen Portland 2,336.85 42,063.21
0.0300 m3 Pasir Beton 1,929,620.00 57,888.60
0.0500 m3 Koral Beton 1,426,289.90 71,314.50
1.5000 lbr Seng gelombang BJLS 20 76,433.00 114,649.50
1.3500 lbr Triplex 4 mm 128,307.20 173,214.72
2.0000 oh Tukang Kayu 148,350.00 296,700.00
1.0000 oh Pekerja 115,000.00 115,000.00
0.2000 oh Kepala Tukang 154,100.00 30,820.00
0.0500 oh Mandor 159,275.00 7,963.75
Total : 450,483.75 987,160.26 1,437,644.01

8 1 M2 PEMBUATAN BAK ADUKAN UKURAN (40X50X20) CM


0.0360 m3 Kayu Matoa 2,654,355.20 95,556.79
0.0800 kg Paku Biasa 2" - 5" 36,086.40 2,886.91
1.0000 btg Matoa 5/5 28,849.07 28,849.07
0.3000 oh Tukang kayu 148,350.00 44,505.00
0.0015 oh Mandor 159,275.00 238.91
Total : 44,743.91 127,292.77 172,036.68

9 1 M2 PEMBUATAN STEGGER DARI BAMBU


1.0000 btg Bambu 18,795.00 18,795.00
0.2500 kg Tali Ijuk - -
0.0170 oh Tukang Kayu 148,350.00 2,521.95
0.0020 oh Pekerja 115,000.00 230.00
0.2500 oh Kepala Tukang 154,100.00 38,525.00
0.0130 oh Mandor 159,275.00 2,070.58
Total : 43,347.53 18,795.00 62,142.53

10 1 M2 PEMBUATAN JALAN SEMENTARA


0.1500 m3 Batu belah 777,862.40 116,679.36
0.0900 m3 Batu Pecah 5 - 7 1,354,242.40 121,881.82
0.0100 m3 Pasir Pasang 1,353,240.00 13,532.40
1.0000 oh Pekerja 115,000.00 115,000.00
0.0500 oh Mandor 159,275.00 7,963.75
Total : 122,963.75 252,093.58 375,057.33

11 1 M3 BONGKARAN BETON BERTULANG


6.6670 oh Pekerja 115,000.00 766,705.00
0.3330 oh Mandor 159,275.00 53,038.58
Total : 819,743.58 819,743.58

12 1 M3 BONGKARAN DINDING TEMBOK BATU TELA


6.6670 oh Pekerja 115,000.00 766,705.00
0.0330 oh Mandor 159,275.00 5,256.08
Total : 771,961.08 771,961.08

II PEKERJAAN TANAH (SNI 2835 : 2008)


1 1 M3 GALIAN TANAH BIASA DALAM 1 METER
0.7500 oh Pekerja 115,000.00 86,250.00
0.0250 oh Mandor 159,275.00 3,981.88
Total : 90,231.88 90,231.88
2 1 M3 GALIAN TANAH BIASA DALAM 2 METER
0.9000 oh Pekerja 115,000.00 103,500.00
0.0450 oh Mandor 159,275.00 7,167.38
Total : 110,667.38 110,667.38

3 1 M3 GALIAN TANAH BIASA DALAM 3 METER


1.0500 oh Pekerja 115,000.00 120,750.00
0.0670 oh Mandor 159,275.00 10,671.43
Total : 131,421.43 131,421.43

4 1 M3 GALIAN TANAH KERAS DALAM 1METER


1.0000 oh Pekerja 115,000.00 115,000.00
0.0320 oh Mandor 159,275.00 5,096.80
Total : 120,096.80 120,096.80

5 1 M3 GALIAN TANAH CADAS DALAM 1 METER


1.5000 oh Pekerja 115,000.00 172,500.00
0.0600 oh Mandor 159,275.00 9,556.50
Total : 182,056.50 182,056.50
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

6 1 M3 GALIAN TANAH LUMPUR DALAM 1 METER


1.2000 oh Pekerja 115,000.00 138,000.00
0.0450 oh Mandor 159,275.00 7,167.38
Total : 145,167.38 145,167.38

7 1 M2 PEKERJAAN STRIPPING SETINGGI 1 METER


0.0500 oh Pekerja 115,000.00 5,750.00
0.0050 oh Mandor 159,275.00 796.38
Total : 6,546.38 6,546.38

8 1 M3 PEMBUANGAN TANAH SEJAUH 15 METER


0.3300 oh Pekerja 115,000.00 37,950.00
0.0100 oh Mandor 159,275.00 1,592.75
Total : 39,542.75 39,542.75

9 1 M3 URUGAN KEMBALI
Mengurug Kembali 1 m3 galian dihitung dari 1/3 kali dari indeks pekerjaan galian

10 1 M3 PEMADATAN TANAH ( Per 20 Cm )


0.5000 oh Pekerja 115,000.00 57,500.00
0.0500 oh Mandor 159,275.00 7,963.75
Total : 65,463.75 65,463.75

11 1 M3 URUGAN PASIR
1.2000 m3 Pasir Urug 1,353,240.00 1,623,888.00
0.3000 oh Pekerja 115,000.00 34,500.00
0.0100 oh Mandor 159,275.00 1,592.75
Total : 36,092.75 1,623,888.00 1,659,980.75

12 1 M3 PEMASANGAN LAPISAN IJUK TEBAL 10 CM


6.0000 m3 Ijuk 24,558.80 147,352.80
0.1500 oh Pekerja 115,000.00 17,250.00
0.0150 oh Mandor 159,275.00 2,389.13
Total : 19,639.13 147,352.80 166,991.93

13 1 M3 URUGAN SIRTU PADAT Untuk Peninggian Lantai Bangunan


1.2000 m3 Sirtu 488,670.00 586,404.00
0.2500 oh Pekerja 115,000.00 28,750.00
0.0250 oh Mandor 159,275.00 3,981.88
Total : 32,731.88 586,404.00 619,135.88

14 1 M3 URUGAN TANAH PILIHAN DIPADATKAN


1.2000 m3 Tanah Urug 373,394.00 448,072.80
0.5000 oh Pekerja 115,000.00 57,500.00
0.0500 oh Mandor 159,275.00 7,963.75
Total : 65,463.75 448,072.80 513,536.55
15 1 M3 URUGAN LIMESTONE PADAT
1.2000 m3 Limestone 292,550.44 351,060.53
0.2500 oh Pekerja 115,000.00 28,750.00
0.0250 oh Mandor 159,275.00 3,981.88
Total : 32,731.88 351,060.53 383,792.40

III PEKERJAAN PONDASI (SNI 2836 : 2008)


1 1 M3 BATU KALI CAMP. 1 PC : 3 PS
1.2000 m3 Batu Kali / Batu Bulat 15/20 777,862.40 933,434.88
202.0000 kg Semen Portland 2,336.85 472,042.69
0.4850 m3 Pasir Pasang 1,353,240.00 656,321.40
1.5000 oh Pekerja 115,000.00 172,500.00
0.7500 oh Tukang Batu 142,600.00 106,950.00
0.0750 oh Kepala Tukang 154,100.00 11,557.50
0.0750 oh Mandor 159,275.00 11,945.63
Total : 302,953.13 2,061,798.97 2,364,752.10

2 1 M3 BATU KALI CAMP. 1 PC : 4 PS


1.2000 m3 Batu Kali / Batu Bulat 15/20 777,862.40 933,434.88
163.0000 kg Semen Portland 2,336.85 380,905.74
0.5200 m3 Pasir Pasang 1,353,240.00 703,684.80
1.5000 oh Pekerja 115,000.00 172,500.00
0.7500 oh Tukang Batu 142,600.00 106,950.00
0.0750 oh Kepala Tukang 154,100.00 11,557.50
0.0750 oh Mandor 159,275.00 11,945.63
Total : 302,953.13 2,018,025.42 2,320,978.54
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

3 1 M3 BATU KALI CAMP. 1 PC : 5 PS


1.2000 m3 Batu Kali / Batu Bulat 15/20 777,862.40 933,434.88
136.0000 kg Semen Portland 2,336.85 317,810.92
0.5440 m3 Pasir Pasang 1,353,240.00 736,162.56
1.5000 oh Pekerja 115,000.00 172,500.00
0.7500 oh Tukang Batu 142,600.00 106,950.00
0.0750 oh Kepala Tukang 154,100.00 11,557.50
0.0750 oh Mandor 159,275.00 11,945.63
Total : 302,953.13 1,987,408.36 2,290,361.49

4 1 M3 BATU KALI CAMP. 1 PC : 6 PS


1.2000 m3 Batu Kali / Batu Bulat 15/20 777,862.40 933,434.88
117.0000 kg Semen Portland 2,336.85 273,410.87
0.5610 m3 Pasir Pasang 1,353,240.00 759,167.64
1.5000 oh Pekerja 115,000.00 172,500.00
0.7500 oh Tukang Batu 142,600.00 106,950.00
0.0750 oh Kepala Tukang 154,100.00 11,557.50
0.0750 oh Mandor 159,275.00 11,945.63
Total : 302,953.13 1,966,013.39 2,268,966.51

5 1 M3 BATU KALI CAMP. 1 PC : 8 PS


1.2000 m3 Batu Kali / Batu Bulat 15/20 777,862.40 933,434.88
91.0000 kg Semen Portland 2,336.85 212,652.90
0.5840 m3 Pasir Pasang 1,353,240.00 790,292.16
1.5000 oh Pekerja 115,000.00 172,500.00
0.7500 oh Tukang Batu 142,600.00 106,950.00
0.0750 oh Kepala Tukang 154,100.00 11,557.50
0.0750 oh Mandor 159,275.00 11,945.63
Total : 302,953.13 1,936,379.94 2,239,333.06

6 1 M3 PASANGAN PONDASI SIKLOP, 40% BATU KALI


0.4800 m3 Batu Kali / Batu Bulat 15/20 777,862.40 373,373.95
194.0000 kg Semen Portland 2,336.85 453,347.93
0.3120 m3 Pasir Beton 1,929,620.00 602,041.44
0.4680 m3 Koral Beton 1,426,289.90 667,503.67
126.0000 kg Besi Beton 19,417.41 2,446,593.10
1.8000 kg Kawat Beton 35,835.80 64,504.44
3.4000 oh Pekerja 115,000.00 391,000.00
0.8500 oh Tukang Batu 142,600.00 121,210.00
0.0850 oh Kepala Tukang 154,100.00 13,098.50
0.1700 oh Mandor 159,275.00 27,076.75
Total : 552,385.25 4,607,364.53 5,159,749.78

7 1 M3 PASANGAN PONDASI SUMURAN DIAMETER 1 M


0.4500 m3 Batu Kali / Batu Bulat 15/20 777,862.40 350,038.08
194.0000 kg Semen Portland 2,336.85 453,347.93
0.3120 m3 Pasir Beton 1,929,620.00 602,041.44
0.4680 m3 Koral Beton 1,426,289.90 667,503.67
2.4000 oh Pekerja 115,000.00 276,000.00
0.8000 oh Tukang Batu 142,600.00 114,080.00
0.0800 oh Kepala Tukang 154,100.00 12,328.00
0.1190 oh Mandor 159,275.00 18,953.73
Total : 421,361.73 2,072,931.12 2,494,292.85

8 1 M3 PASANGAN BATU KOSONG


1.2000 m3 Batu Kali / Batu Bulat 15/20 15/20 777,862.40 933,434.88
0.4320 m3 Pasir Urug 1,353,240.00 584,599.68
0.7800 oh Pekerja 115,000.00 89,700.00
0.3900 oh Tukang Batu 142,600.00 55,614.00
0.0390 oh Kepala Tukang 154,100.00 6,009.90
0.0390 oh Mandor 159,275.00 6,211.73
Total : 157,535.63 1,518,034.56 1,675,570.19

IV PEKERJAAN DINDING (SNI 6897 : 2008)

1 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 2 PS


140.0000 bh Batu Tela 5 x 11 x 22 cm 11,432.19 1,600,506.72
43.5000 kg Semen Portland 2,336.85 101,652.76
0.0800 m3 Pasir Pasang 1,353,240.00 108,259.20
0.6000 oh Pekerja 115,000.00 69,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0300 oh Mandor 159,275.00 4,778.25
Total : 105,380.25 1,810,418.68 1,915,798.93
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

2 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 3 PS


140.0000 bh Batu Tela 5 x 11 x 22 cm 11,432.19 1,600,506.72
32.9500 kg Semen Portland 2,336.85 76,999.04
0.0910 m3 Pasir Pasang 1,353,240.00 123,144.84
0.6000 oh Pekerja 115,000.00 69,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0300 oh Mandor 159,275.00 4,778.25
Total : 105,380.25 1,800,650.60 1,906,030.85

3 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 4 PS


140.0000 bh Batu Tela 5 x 11 x 22 cm 11,432.19 1,600,506.72
26.5500 kg Semen Portland 2,336.85 62,043.23
0.0930 m3 Pasir Pasang 1,353,240.00 125,851.32
0.6000 oh Pekerja 115,000.00 69,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0300 oh Mandor 159,275.00 4,778.25
Total : 105,380.25 1,788,401.27 1,893,781.52

4 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 5 PS


140.0000 bh Batu Tela 5 x 11 x 22 cm 11,432.19 1,600,506.72
22.2000 kg Semen Portland 2,336.85 51,877.96
0.1020 m3 Pasir Pasang 1,353,240.00 138,030.48
0.6000 oh Pekerja 115,000.00 69,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0300 oh Mandor 159,275.00 4,778.25
Total : 105,380.25 1,790,415.16 1,895,795.41

5 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 6 PS


140.0000 bh Batu Tela 5 x 11 x 22 cm 11,432.19 1,600,506.72
18.5000 kg Semen Portland 2,336.85 43,231.63
0.1220 m3 Pasir Pasang 1,353,240.00 165,095.28
0.6000 oh Pekerja 115,000.00 69,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0300 oh Mandor 159,275.00 4,778.25
Total : 105,380.25 1,808,833.63 1,914,213.88

6 1 M2 PASANGAN BATU TELA TEBAL 1/2 TELA CAMP. 1 PC : 2 PS


70.0000 bh Batu Tela 5 x 11 x 22 cm 11,432.19 800,253.36
18.9500 kg Semen Portland 2,336.85 44,283.21
0.0380 m3 Pasir Pasang 1,353,240.00 51,423.12
0.3000 oh Pekerja 115,000.00 34,500.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0150 oh Mandor 159,275.00 2,389.13
Total : 52,690.13 895,959.69 948,649.82

7 1 M2 PASANGAN BATU TELA TEBAL 1/2 TELA CAMP. 1 PC : 3 PS


70.0000 bh Batu Tela 5 x 11 x 22 cm 11,432.19 800,253.36
14.3700 kg Semen Portland 2,336.85 33,580.46
0.0400 m3 Pasir Pasang 1,353,240.00 54,129.60
0.3000 oh Pekerja 115,000.00 34,500.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0150 oh Mandor 159,275.00 2,389.13
Total : 52,690.13 887,963.42 940,653.55

8 1 M2 PASANGAN BATU TELA TEBAL 1/2 TELA CAMP. 1 PC : 4 PS


70.0000 bh Batu Tela 5 x 11 x 22 cm 11,432.19 800,253.36
11.5000 kg Semen Portland 2,336.85 26,873.72
0.0430 m3 Pasir Pasang 1,353,240.00 58,189.32
0.3000 oh Pekerja 115,000.00 34,500.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0150 oh Mandor 159,275.00 2,389.13
Total : 52,690.13 885,316.40 938,006.52

9 1 M2 PASANGAN BATU TELA TEBAL 1/2 TELA CAMP. 1 PC : 5 PS


70.0000 bh Batu Tela 5 x 11 x 22 cm 11,432.19 800,253.36
9.6800 kg Semen Portland 2,336.85 22,620.66
0.0450 m3 Pasir Pasang 1,353,240.00 60,895.80
0.3000 oh Pekerja 115,000.00 34,500.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0150 oh Mandor 159,275.00 2,389.13
Total : 52,690.13 883,769.82 936,459.94
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
10 1 M2 PASANGAN BATU TELA TEBAL 1/2 TELA CAMP. 1 PC : 6 PS
70.0000 bh Batu Tela 5 x 11 x 22 cm 11,432.19 800,253.36
8.3200 kg Semen Portland 2,336.85 19,442.55
0.0490 m3 Pasir Pasang 1,353,240.00 66,308.76
0.3000 oh Pekerja 115,000.00 34,500.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0150 oh Mandor 159,275.00 2,389.13
Total : 52,690.13 886,004.67 938,694.79

11 1 M2 PASANGAN BATU TELA TEBAL 1/2 TELA CAMP. 1 PC : 8 PS


70.0000 bh Batu Tela 5 x 11 x 22 cm 11,432.19 800,253.36
6.5000 kg Semen Portland 2,336.85 15,189.49
0.0500 m3 Pasir Pasang 1,353,240.00 67,662.00
0.3000 oh Pekerja 115,000.00 34,500.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0150 oh Mandor 159,275.00 2,389.13
Total : 52,690.13 883,104.85 935,794.98

12 1 M2 PASANGAN DINDING HOLLOWBLOCK (HB. 10)


12.5000 bh Batako 29,876.35 373,454.39
7.5000 kg Semen Portland 2,336.85 17,526.34
0.0270 m3 Pasir Pasang 1,353,240.00 36,537.48
1.9500 kg Besi Beton 8 mm 19,417.41 37,863.94
0.3200 oh Pekerja 115,000.00 36,800.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0150 oh Mandor 159,275.00 2,389.13
Total : 54,990.13 465,382.14 520,372.27

13 1 M2 PASANGAN DINDING HOLLOWBLOCK (HB. 10) TANPA BESI


12.5000 bh Batako 29,876.35 373,454.39
7.5000 kg Semen Portland 2,336.85 17,526.34
0.0270 m3 Pasir Pasang 1,353,240.00 36,537.48
0.3200 oh Pekerja 115,000.00 36,800.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0150 oh Mandor 159,275.00 2,389.13
Total : 54,990.13 427,518.20 482,508.33

14 1 M2 PASANGAN DINDING Terawang/Roster (12 x 11 x 24) CM


30.0000 bh Roster Keramik 299,467.00 8,984,010.00
11.0000 kg Semen Portland 2,336.85 25,705.30
0.0350 m3 Pasir Pasang 1,353,240.00 47,363.40
0.3000 oh Pekerja 115,000.00 34,500.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0150 oh Mandor 159,275.00 2,389.13
Total : 52,690.13 9,057,078.70 9,109,768.82

15 1 M2 PASANGAN DINDING BEDEG, RANGKA KAYU


1.5000 m2 Bedeg/Bilik Bambu Kelas I 25,711.56 38,567.34
0.0140 m3 Kayu Matoa usuk/reng 2,654,355.20 37,160.97
0.0120 kg Paku Biasa 24,558.80 294.71
0.0030 m3 List Kayu 2/4 2,654,355.20 7,963.07
0.1000 oh Pekerja 115,000.00 11,500.00
0.0500 oh Tukang Kayu 148,350.00 7,417.50
0.0050 oh Kepala Tukang 154,100.00 770.50
0.0020 oh Mandor 159,275.00 318.55
Total : 20,006.55 83,986.08 103,992.63

V PEKERJAAN PLESTERAN (SNI 2837 : 2008)

1 1 M2 PLESTERAN CAMP. 1 PC : 1 PS TEBAL 15 MM


15.5040 kg Semen Portland 2,336.85 36,230.44
0.0160 m3 Pasir Pasang 1,929,620.00 30,873.92
0.3000 oh Pekerja 115,000.00 34,500.00
0.1500 oh Tukang Batu 142,600.00 21,390.00
0.0150 oh Kepala Tukang 154,100.00 2,311.50
0.0150 oh Mandor 159,275.00 2,389.13
Total : 60,590.63 67,104.36 127,694.99
2 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 15 MM
10.2240 kg Semen Portland 2,336.85 23,891.90
0.0200 m3 Pasir Pasang 1,929,620.00 38,592.40
0.3000 oh Pekerja 115,000.00 34,500.00
0.1500 oh Tukang Batu 142,600.00 21,390.00
0.0150 oh Kepala Tukang 154,100.00 2,311.50
0.0150 oh Mandor 159,275.00 2,389.13
Total : 60,590.63 62,484.30 123,074.93
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

3 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 15 MM


7.7760 kg Semen Portland 2,336.85 18,171.31
0.0230 m3 Pasir Pasang 1,929,620.00 44,381.26
0.3000 oh Pekerja 115,000.00 34,500.00
0.1500 oh Tukang Batu 142,600.00 21,390.00
0.0150 oh Kepala Tukang 154,100.00 2,311.50
0.0150 oh Mandor 159,275.00 2,389.13
Total : 60,590.63 62,552.57 123,143.19

4 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 15 MM


6.2400 kg Semen Portland 2,336.85 14,581.91
0.0240 m3 Pasir Pasang 1,929,620.00 46,310.88
0.3000 oh Pekerja 115,000.00 34,500.00
0.1500 oh Tukang Batu 142,600.00 21,390.00
0.0150 oh Kepala Tukang 154,100.00 2,311.50
0.0150 oh Mandor 159,275.00 2,389.13
Total : 60,590.63 60,892.79 121,483.42

5 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 15 MM


5.1840 kg Semen Portland 2,336.85 12,114.20
0.0260 m3 Pasir Pasang 1,929,620.00 50,170.12
0.3000 oh Pekerja 115,000.00 34,500.00
0.1500 oh Tukang Batu 142,600.00 21,390.00
0.0150 oh Kepala Tukang 154,100.00 2,311.50
0.0150 oh Mandor 159,275.00 2,389.13
Total : 60,590.63 62,284.32 122,874.95

6 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 15 MM


4.4160 kg Semen Portland 2,336.85 10,319.51
0.0270 m3 Pasir Pasang 1,929,620.00 52,099.74
0.3000 oh Pekerja 115,000.00 34,500.00
0.1500 oh Tukang Batu 142,600.00 21,390.00
0.0150 oh Kepala Tukang 154,100.00 2,311.50
0.0150 oh Mandor 159,275.00 2,389.13
Total : 60,590.63 62,419.25 123,009.87

7 1 M2 PLESTERAN CAMP. 1 PC : 8 PS TEBAL 15 MM


3.4560 kg Semen Portland 2,336.85 8,076.14
0.0290 m3 Pasir Pasang 1,929,620.00 55,958.98
0.3000 oh Pekerja 115,000.00 34,500.00
0.1500 oh Tukang Batu 142,600.00 21,390.00
0.0150 oh Kepala Tukang 154,100.00 2,311.50
0.0150 oh Mandor 159,275.00 2,389.13
Total : 60,590.63 64,035.12 124,625.74

8 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 20 MM


13.6320 kg Semen Portland 2,336.85 31,855.87
0.0270 m3 Pasir Pasang 1,929,620.00 52,099.74
0.4000 oh Pekerja 115,000.00 46,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0220 oh Mandor 159,275.00 3,504.05
Total : 81,106.05 83,955.61 165,061.66

9 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 20 MM


10.3680 kg Semen Portland 2,336.85 24,228.41
0.0310 m3 Pasir Pasang 1,929,620.00 59,818.22
0.4000 oh Pekerja 115,000.00 46,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0220 oh Mandor 159,275.00 3,504.05
Total : 81,106.05 84,046.63 165,152.68

10 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 20 MM


8.3200 kg Semen Portland 2,336.85 19,442.55
0.0320 m3 Pasir Pasang 1,929,620.00 61,747.84
0.4000 oh Pekerja 115,000.00 46,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0220 oh Mandor 159,275.00 3,504.05
Total : 81,106.05 81,190.39 162,296.44
11 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 20 MM
6.9120 kg Semen Portland 2,336.85 16,152.27
0.0350 m3 Pasir Pasang 1,929,620.00 67,536.70
0.4000 oh Pekerja 115,000.00 46,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0220 oh Mandor 159,275.00 3,504.05
Total : 81,106.05 83,688.97 164,795.02
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

12 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 20 MM


5.8880 kg Semen Portland 2,336.85 13,759.34
0.0360 m3 Pasir Pasang 1,929,620.00 69,466.32
0.4000 oh Pekerja 115,000.00 46,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0220 oh Mandor 159,275.00 3,504.05
Total : 81,106.05 83,225.66 164,331.71

13 1 M2 PLESTERAN SKONING 1 PC : 2 PS, TEBAL 10 MM


0.5000 kg Semen Portland 2,336.85 1,168.42
0.0130 m3 Pasir Pasang 1,929,620.00 25,085.06
0.0800 oh Pekerja 115,000.00 9,200.00
0.4000 oh Tukang Batu 142,600.00 57,040.00
0.0400 oh Kepala Tukang 154,100.00 6,164.00
0.0040 oh Mandor 159,275.00 637.10
Total : 73,041.10 26,253.48 99,294.58

14 1 M2 PLESTERAN CIPRAT 1 PC : 2 PS
4.3200 kg Semen Portland 2,336.85 10,095.17
0.0060 m3 Pasir Pasang 1,929,620.00 11,577.72
0.3000 oh Pekerja 115,000.00 34,500.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0150 oh Mandor 159,275.00 2,389.13
Total : 52,690.13 21,672.89 74,363.02

15 1 M2 FINISHING SIAR PASANGAN DINDING BATU TELA (=20 M')


3.1080 kg Semen Portland 2,336.85 7,262.91
0.1500 oh Pekerja 115,000.00 17,250.00
0.0750 oh Tukang Batu 142,600.00 10,695.00
0.0080 oh Kepala Tukang 154,100.00 1,232.80
0.0080 oh Mandor 159,275.00 1,274.20
Total : 30,452.00 7,262.91 37,714.91

16 1 M2 FINISHING SIAR PASANGAN DINDING CONBLOCK


EKSPOSE (= 8 M')
1.6000 kg Semen Portland 2,336.85 3,738.95
0.0700 oh Pekerja 115,000.00 8,050.00
0.0350 oh Tukang Batu 142,600.00 4,991.00
0.0040 oh Kepala Tukang 154,100.00 616.40
0.0040 oh Mandor 159,275.00 637.10
Total : 14,294.50 3,738.95 18,033.45

17 1 M2 FINISHING SIAR PASANGAN BATUKALI/BELAH ADUKAN 1PC


: 2 PS
6.3400 kg Semen Portland 2,336.85 14,815.60
0.0120 m3 Pasir Pasang 1,929,620.00 23,155.44
0.3000 oh Pekerja 115,000.00 34,500.00
0.1500 oh Tukang Batu 142,600.00 21,390.00
0.0150 oh Kepala Tukang 154,100.00 2,311.50
0.0150 oh Mandor 159,275.00 2,389.13
Total : 60,590.63 37,971.04 98,561.66

18 1 M2 PEKERJAAN ACIAN
3.2500 zak Semen Portland 50 Kg 2,336.85 7,594.75
0.2000 oh Pekerja 115,000.00 23,000.00
0.1000 oh Tukang Labur/Cat 148,350.00 14,835.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0100 oh Mandor 159,275.00 1,592.75
Total : 40,968.75 7,594.75 48,563.50
VI PEKERJAAN KAYU (SNI 3434 : 2008)
1 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA
KAYU KELAS I (KAYU BESI)
1.1000 m3 Balok Kayu Besi 5,190,427.20 5,709,469.92
1.2500 Kg Paku 10 Cm 30,322.60 37,903.25
1.0000 Kg Lem Kayu 47,614.00 47,614.00
7.0000 oh Pekerja 115,000.00 805,000.00
21.0000 oh Tukang Kayu 148,350.00 3,115,350.00
2.1000 oh Kepala Tukang 154,100.00 323,610.00
0.3500 oh Mandor 159,275.00 55,746.25
Total : 4,299,706.25 5,794,987.17 10,094,693.42
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

2 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA


KAYU KELAS II/III (KAYU MATOA)
1.2000 m3 Balok Kayu Matoa 2,654,355.20 3,185,226.24
1.2500 Kg Paku 10 Cm 30,322.60 37,903.25
1.0000 Kg Lem Kayu 47,614.00 47,614.00
6.0000 oh Pekerja 115,000.00 690,000.00
18.0000 oh Tukang Kayu 148,350.00 2,670,300.00
1.8000 oh Kepala Tukang 154,100.00 277,380.00
0.3000 oh Mandor 159,275.00 47,782.50
Total : 3,685,462.50 3,270,743.49 6,956,205.99

3 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP STANDAR KAYU


KELAS II (KAYU MATOA)
0.0400 m3 Papan Kayu Matoa 2,884,907.20 115,396.29
0.0500 Kg Paku 5-7 Cm 30,322.60 1,516.13
0.3500 oh Pekerja 115,000.00 40,250.00
1.0500 oh Tukang Kayu 148,350.00 155,767.50
0.1050 oh Kepala Tukang 154,100.00 16,180.50
0.0180 oh Mandor 159,275.00 2,866.95
Total : 215,064.95 116,912.42 331,977.37

4 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP SEDERHANA


KAYU KELAS III (KAYU PUTIH)
0.0400 m3 Papan Kayu Putih 2,654,355.20 106,174.21
0.0500 Kg Paku 5-7 Cm 30,322.60 1,516.13
0.3500 oh Pekerja 115,000.00 40,250.00
1.0500 oh Tukang Kayu 148,350.00 155,767.50
0.1050 oh Kepala Tukang 154,100.00 16,180.50
0.0180 oh Mandor 159,275.00 2,866.95
Total : 215,064.95 107,690.34 322,755.29

5 MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU


KELAS I/II (KAYU BESI)
0.0400 m3 Papan Kayu Besi 4,037,667.20 161,506.69
0.5000 Kg Lem Kayu 47,614.00 23,807.00
1.0000 oh Pekerja 115,000.00 115,000.00
3.0000 oh Tukang Kayu 148,350.00 445,050.00
0.3000 oh Kepala Tukang 154,100.00 46,230.00
0.0500 oh Mandor 159,275.00 7,963.75
Total : 614,243.75 185,313.69 799,557.44

6 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA,


KAYU KELAS I/II (KAYU BESI)
0.0240 m3 Papan Kayu Besi 4,037,667.20 96,904.01
1.0000 m2 Kaca rayben 5 mm 233,093.12 233,093.12
0.3000 Kg Lem Kayu 47,614.00 14,284.20
0.8000 oh Pekerja 115,000.00 92,000.00
2.4000 oh Tukang Kayu 148,350.00 356,040.00
0.2400 oh Kepala Tukang 154,100.00 36,984.00
0.0400 oh Mandor 159,275.00 6,371.00
Total : 491,395.00 344,281.33 835,676.33

7 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA JALUSI,


KAYU KELAS I/II (KAYU BESI)
0.0640 m3 Papan Kayu Besi 4,037,667.20 258,410.70
0.5000 Kg Lem Kayu 47,614.00 23,807.00
1.0000 oh Pekerja 115,000.00 115,000.00
3.0000 oh Tukang Kayu 148,350.00 445,050.00
0.3000 oh Kepala Tukang 154,100.00 46,230.00
0.0500 oh Mandor 159,275.00 7,963.75
Total : 614,243.75 282,217.70 896,461.45

8 MEMBUAT 1 M2 DAUN PINTU TEAKWOOD RANGKAP RANGKA


TERTUTUP, KAYU KELAS II (Lebar Sampai 90 Cm)
0.0250 m3 Papan Kayu Matoa 2,884,907.20 72,122.68
0.0300 Kg Paku 1-2,5 Cm 36,086.40 1,082.59
0.5000 Kg Lem Kayu 47,614.00 23,807.00
1.0000 Lbr Taekwood 4 mm 115,977.68 115,977.68
1.0000 oh Pekerja 115,000.00 115,000.00
3.0000 oh Tukang Kayu 148,350.00 445,050.00
0.3000 oh Kepala Tukang 154,100.00 46,230.00
0.0500 oh Mandor 159,275.00 7,963.75
Total : 614,243.75 212,989.95 827,233.70
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

9 MEMBUAT 1 M2 DAUN PINTU TEAKWOOD RANGKAP RANGKA


EXPOSE, KAYU KELAS I/II
0.0256 m3 Papan Kayu Besi 4,037,667.20 103,364.28
0.0300 Kg Paku 1-2,5 Cm 36,086.40 1,082.59
0.5000 Kg Lem Kayu 47,614.00 23,807.00
1.0000 Lbr Teakwood 4 mm 115,977.68 115,977.68
0.8000 oh Pekerja 115,000.00 92,000.00
2.4000 oh Tukang Kayu 148,350.00 356,040.00
0.2400 oh Kepala Tukang 154,100.00 36,984.00
0.0400 oh Mandor 159,275.00 6,371.00
Total : 491,395.00 244,231.55 735,626.55

10 MEMASANG 1 M2 JALUSI KUSEN, KAYU KELAS I/II


0.0600 m3 Papan Kayu Besi 4,037,667.20 242,260.03
0.1500 Kg Paku 1-2,5 Cm 36,086.40 5,412.96
0.6700 oh Pekerja 115,000.00 77,050.00
2.0000 oh Tukang Kayu 148,350.00 296,700.00
0.2000 oh Kepala Tukang 154,100.00 30,820.00
0.3350 oh Mandor 159,275.00 53,357.13
Total : 457,927.13 247,672.99 705,600.12

11 MEMBUAT 1 M2 TEAKWOOD RANGKAP RANGKA EXPOSE, KAYU


KELAS I
0.0256 m3 Papan Kayu Besi 4,037,667.20 103,364.28
0.0300 Kg Paku 1-2,5 Cm 36,086.40 1,082.59
0.5000 Kg Lem Kayu 47,614.00 23,807.00
1.0000 Lbr Teakwood 4 mm uk 90x220 cm 115,977.68 115,977.68
0.8000 oh Pekerja 115,000.00 92,000.00
2.4000 oh Tukang Kayu 148,350.00 356,040.00
0.2400 oh Kepala Tukang 154,100.00 36,984.00
0.0400 oh Mandor 159,275.00 6,371.00
Total : 491,395.00 244,231.55 735,626.55

12 MEMBUAT 1 M2 TEAKWOOD RANGKAP LAPIS FORMIKA RANGKA


EXPOSE, KAYU KELAS II
0.0250 m3 Papan Kayu Matoa 2,884,907.20 72,122.68
0.0300 Kg Paku 1-2,5 Cm 36,086.40 1,082.59
0.8000 Kg Lem Kayu 47,614.00 38,091.20
1.0000 Lbr Teakwood 4 mm uk 90x220 cm 115,977.68 115,977.68
0.5000 Lbr Formika 111,015.80 55,507.90
0.8000 oh Pekerja 115,000.00 92,000.00
2.4000 oh Tukang Kayu 148,350.00 356,040.00
0.2400 oh Kepala Tukang 154,100.00 36,984.00
0.0400 oh Mandor 159,275.00 6,371.00
Total : 491,395.00 282,782.05 774,177.05

13 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL,


KAYU KELAS I,II,III Bentang 6 M'
1.1000 m3 Balok Kayu Besi 5,190,427.20 5,709,469.92
15.0000 Kg Besi Strip Tebal 5 cm 9,872.64 148,089.56
5.6000 Kg Paku 12 Cm 30,322.60 169,806.56
4.0000 oh Pekerja 115,000.00 460,000.00
12.0000 oh Tukang Kayu 148,350.00 1,780,200.00
1.2000 oh Kepala Tukang 154,100.00 184,920.00
0.2000 oh Mandor 159,275.00 31,855.00
Total : 2,456,975.00 6,027,366.04 8,484,341.04

14 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA EXPOSE, KAYU


KELAS I
1.2000 m3 Balok Kayu Besi 5,190,427.20 6,228,512.64
15.0000 Kg Besi Strip Tebal 5 cm 9,872.64 148,089.56
5.6000 Kg Paku 12 Cm 30,322.60 169,806.56
6.7000 oh Pekerja 115,000.00 770,500.00
20.1000 oh Tukang Kayu 148,350.00 2,981,835.00
2.0100 oh Kepala Tukang 154,100.00 309,741.00
0.3350 oh Mandor 159,275.00 53,357.13
Total : 4,115,433.13 6,546,408.76 10,661,841.89

15 MEMASANG 1 M3 KONSTRUKSI GORDENG, KAYU KELAS II


1.1000 m3 Balok Kayu Matoa 2,654,355.20 2,919,790.72
15.0000 Kg Besi Strip Tebal 5 cm 9,872.64 148,089.56
3.0000 Kg Paku 12 Cm 30,322.60 90,967.80
2.4000 oh Pekerja 115,000.00 276,000.00
7.2000 oh Tukang Kayu 148,350.00 1,068,120.00
0.7200 oh Kepala Tukang 154,100.00 110,952.00
0.1200 oh Mandor 159,275.00 19,113.00
Total : 1,474,185.00 3,158,848.08 4,633,033.08
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

16 MEMASANG 1 M2 RANGKA ATAP GENTENG KERAMIK, KAYU


KELAS II
0.0140 m3 Kaso-Kaso ( 5 x 7 ) Cm 2,884,907.20 40,388.70
0.0036 m3 Reng ( 2 x 3 ) Cm 2,884,907.20 10,385.67
0.2500 Kg Paku 5 Cm dan 10 Cm 30,322.60 7,580.65
0.1000 oh Pekerja 115,000.00 11,500.00
0.1000 oh Tukang Kayu 148,350.00 14,835.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0050 oh Mandor 159,275.00 796.38
Total : 28,672.38 58,355.02 87,027.39

17 MEMASANG 1 M2 RANGKA ATAP GENTENG BETON, KAYU KELAS


II
0.0140 m3 Kaso-Kaso ( 5 x 7 ) Cm 2,884,907.20 40,388.70
0.0072 m3 Reng ( 2 x 3 ) Cm 2,884,907.20 20,771.33
0.2500 Kg Paku 5 Cm dan 10 Cm 30,322.60 7,580.65
0.1000 oh Pekerja 115,000.00 11,500.00
0.1000 oh Tukang Kayu 148,350.00 14,835.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0050 oh Mandor 159,275.00 796.38
Total : 28,672.38 68,740.68 97,413.06

18 MEMASANG 1 M2 RANGKA ATAP SIRAP, KAYU KELAS II


0.1650 m3 Balok Kayu Matoa 2,884,907.20 476,009.69
0.2000 Kg Paku 5 Cm dan 10 Cm 30,322.60 6,064.52
0.1200 oh Pekerja 115,000.00 13,800.00
0.1200 oh Tukang Kayu 148,350.00 17,802.00
0.0120 oh Kepala Tukang 154,100.00 1,849.20
0.0060 oh Mandor 159,275.00 955.65
Total : 34,406.85 482,074.21 516,481.06

19 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (50 X 100), KAYU


KELAS II/III
0.0154 m3 Kaso-Kaso ( 5 x 7 ) Cm 2,884,907.20 44,427.57
0.2000 Kg Paku 7 Cm dan 10 Cm 30,322.60 6,064.52
0.1500 oh Pekerja 115,000.00 17,250.00
0.3000 oh Tukang Kayu 148,350.00 44,505.00
0.0300 oh Kepala Tukang 154,100.00 4,623.00
0.0750 oh Mandor 159,275.00 11,945.63
Total : 78,323.63 50,492.09 128,815.72

20 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (60 X 60) CM, KAYU


KELAS II/III
0.0163 m3 Kaso-Kaso ( 5 x 7 ) Cm 2,884,907.20 47,023.99
0.2500 Kg Paku 7 Cm dan 10 Cm 30,322.60 7,580.65
0.2000 oh Pekerja 115,000.00 23,000.00
0.3000 oh Tukang Kayu 148,350.00 44,505.00
0.0300 oh Kepala Tukang 154,100.00 4,623.00
0.0100 oh Mandor 159,275.00 1,592.75
Total : 73,720.75 54,604.64 128,325.39

21 MEMASANG 1 M' LISPLANK UKURAN (3 X 20) CM, KAYU KELAS


I/II
0.0108 m3 Papan Kayu Besi 4,037,667.20 43,606.81
0.1000 Kg Paku 5 Cm dan 7 Cm 30,322.60 3,032.26
0.1000 oh Pekerja 115,000.00 11,500.00
0.2000 oh Tukang Kayu 148,350.00 29,670.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0050 oh Mandor 159,275.00 796.38
Total : 45,048.38 46,639.07 91,687.44

22 MEMASANG 1 M' LISPLANK UKURAN (3 X 30) CM, KAYU KELAS


I/II
0.0110 m3 Papan Kayu Besi 4,037,667.20 44,414.34
0.0500 Kg Paku 5 Cm dan 7 Cm 30,322.60 1,516.13
0.1000 oh Pekerja 115,000.00 11,500.00
0.2000 oh Tukang Kayu 148,350.00 29,670.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0050 oh Mandor 159,275.00 796.38
Total : 45,048.38 45,930.47 90,978.84
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

23 MEMASANG 1 M2 RANGKA DINDING PEMISAH (60 X 120) CM,


KAYU KELAS II/III
0.0280 m3 Balok Kayu Matoa 2,654,355.20 74,321.95
0.1500 Kg Paku 5 Cm dan 7 Cm 30,322.60 4,548.39
0.1500 oh Pekerja 115,000.00 17,250.00
0.4500 oh Tukang Kayu 148,350.00 66,757.50
0.0450 oh Kepala Tukang 154,100.00 6,934.50
0.0080 oh Mandor 159,275.00 1,274.20
Total : 92,216.20 78,870.34 171,086.54

24 MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD


RANGKAP, RANGKA KAYU KELAS II
0.0280 m3 Balok Kayu Matoa 2,654,355.20 74,321.95
0.1500 Kg Paku 5 Cm dan 7 Cm 30,322.60 4,548.39
0.8600 Lbr Teakwood 4 mm uk 90x220 cm 115,977.68 99,740.80
0.5600 Kg Lem Kayu 47,614.00 26,663.84
0.1500 oh Pekerja 115,000.00 17,250.00
0.4500 oh Tukang Kayu 148,350.00 66,757.50
0.0450 oh Kepala Tukang 154,100.00 6,934.50
0.0080 oh Mandor 159,275.00 1,274.20
Total : 92,216.20 205,274.98 297,491.18

25 MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD


RANGKAP, RANGKA KAYU KELAS II
0.0280 m3 Balok Kayu Matoa 2,654,355.20 74,321.95
0.1500 Kg Paku 5 Cm dan 7 Cm 30,322.60 4,548.39
0.8600 Lbr Plywood tebal 4 mm uk 120 x 240 cm 93,724.40 80,602.98
0.5600 Kg Lem Kayu 47,614.00 26,663.84
0.2000 oh Pekerja 115,000.00 23,000.00
0.6000 oh Tukang Kayu 148,350.00 89,010.00
0.0600 oh Kepala Tukang 154,100.00 9,246.00
0.0100 oh Mandor 159,275.00 1,592.75
Total : 122,848.75 186,137.16 308,985.91

26 MEMASANG 1 M2 LAMBRIZIRING DARI PAPAN KAYU KELAS I

0.0070 m3 Papan Kayu Besi 4,037,667.20 28,263.67


0.1000 Kg Paku 5 Cm dan 10 Cm 30,322.60 3,032.26
0.1500 Kg Paku Skrup 10 cm - -
0.6000 oh Pekerja 115,000.00 69,000.00
1.8000 oh Tukang Kayu 148,350.00 267,030.00
0.1800 oh Kepala Tukang 154,100.00 27,738.00
0.0300 oh Mandor 159,275.00 4,778.25
Total : 368,546.25 31,295.93 399,842.18

27 MEMASANG 1 M2 LAMBRIZIRING DARI PLYWOOD UKURAN (120


X 240) CM
0.4000 Lbr Plywood tebal 4 mm uk 120 x 240 cm 96,606.30 38,642.52
0.0500 Kg Paku 1 Cm dan 2.5 Cm 30,322.60 1,516.13
0.0250 oh Pekerja 115,000.00 2,875.00
0.0750 oh Tukang Kayu 148,350.00 11,126.25
0.0080 oh Kepala Tukang 154,100.00 1,232.80
0.0010 oh Mandor 159,275.00 159.28
Total : 15,393.33 40,158.65 55,551.98

VII PEKERJAAN BETON ( SNI 7394:2008)


1 1 M3 MEMBUAT BETON 1 PC : 3 PS : 5 KR
218.0000 kg Semen Portland 2,336.85 509,432.21
0.5200 m3 Pasir Beton 1,929,620.00 1,003,402.40
0.8700 m3 Koral Beton 1,426,289.90 1,240,872.21
1.6500 oh Pekerja 115,000.00 189,750.00
0.2500 oh Tukang Batu 142,600.00 35,650.00
0.0250 oh Kepala Tukang 154,100.00 3,852.50
0.0800 oh Mandor 159,275.00 12,742.00
Total : 241,994.50 2,753,706.82 2,995,701.32

2 1 M3 MEMBUAT BETON 1 PC : 2 PS : 4 KR
232.0000 kg Semen Portland 2,336.85 542,148.04
0.5200 m3 Pasir Beton 1,929,620.00 1,003,402.40
0.7800 m3 Koral Beton 1,426,289.90 1,112,506.12
1.6500 oh Pekerja 115,000.00 189,750.00
0.2500 oh Tukang Batu 142,600.00 35,650.00
0.0250 oh Kepala Tukang 154,100.00 3,852.50
0.0800 oh Mandor 159,275.00 12,742.00
Total : 241,994.50 2,658,056.56 2,900,051.06
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

3 1 M3 MEMBUAT BETON 1 PC : 2 PS : 3 KR
280.0000 kg Semen Portland 2,336.85 654,316.60
0.4500 m3 Pasir Beton 1,929,620.00 868,329.00
0.9000 m3 Koral Beton 1,426,289.90 1,283,660.91
1.6500 oh Pekerja 115,000.00 189,750.00
0.2500 oh Tukang Batu 142,600.00 35,650.00
0.0250 oh Kepala Tukang 154,100.00 3,852.50
0.0800 oh Mandor 159,275.00 12,742.00
Total : 241,994.50 2,806,306.51 3,048,301.01

4 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR


10.5000 kg Besi Beton (Polos/ Ulir) 19,417.41 203,882.76
0.1500 kg Kawat Beton 35,835.80 5,375.37
0.0700 oh Pekerja 115,000.00 8,050.00
0.0700 oh Tukang Besi 148,350.00 10,384.50
0.0070 oh Kepala Tukang 154,100.00 1,078.70
0.0040 oh Mandor 159,275.00 637.10
Total : 20,150.30 209,258.13 229,408.43

5 1 M2 PASANG BEKISTING UNTUK PONDASI


0.0400 m3 Kayu Bekisting 2,884,907.20 115,396.29
0.3000 kg Paku Biasa 5' - 10' 30,322.60 9,096.78
0.1000 ltr Minyak Bekisting 18,795.00 1,879.50
0.5200 oh Pekerja 115,000.00 59,800.00
0.2600 oh Tukang Kayu 148,350.00 38,571.00
0.0260 oh Kepala Tukang 154,100.00 4,006.60
0.0260 oh Mandor 159,275.00 4,141.15
Total : 106,518.75 126,372.57 232,891.32

6 1 M2 PASANG BEKISTING UNTUK SLOOF


0.0400 m3 Kayu Bekisting 2,884,907.20 115,396.29
0.3000 kg Paku Biasa 5' - 10' 30,322.60 9,096.78
0.1000 ltr Minyak Bekisting 18,795.00 1,879.50
0.5200 oh Pekerja 115,000.00 59,800.00
0.2600 oh Tukang Kayu 148,350.00 38,571.00
0.0260 oh Kepala Tukang 154,100.00 4,006.60
0.0260 oh Mandor 159,275.00 4,141.15
Total : 106,518.75 126,372.57 232,891.32

7 1 M2 PASANG BEKISTING UNTUK KOLOM


0.0400 m3 Kayu Bekisting 2,884,907.20 115,396.29
0.4000 kg Paku Biasa 5' - 12' 30,322.60 12,129.04
0.2000 ltr Minyak Bekisting 18,795.00 3,759.00
0.0150 m3 Kayu Usuk 4/6 2,884,907.20 43,273.61
0.3500 lbr Plywood 9 mm 185,945.20 65,080.82
2.0000 btg Dolken Kayu 8" - 10"/4 m 43,002.96 86,005.92
0.6600 oh Pekerja 115,000.00 75,900.00
0.3300 oh Tukang Kayu 148,350.00 48,955.50
0.0330 oh Kepala Tukang 154,100.00 5,085.30
0.0330 oh Mandor 159,275.00 5,256.08
Total : 135,196.88 325,644.68 460,841.55

8 1 M2 PASANG BEKISTING UNTUK BALOK


0.0400 m3 Kayu Bekisting 2,884,907.20 115,396.29
0.4000 kg Paku Biasa 5' - 12' 30,322.60 12,129.04
0.2000 ltr Minyak Bekisting 18,795.00 3,759.00
0.0180 m3 Kayu Usuk 4/6 2,884,907.20 51,928.33
0.3500 lbr Plywood 9 mm 185,945.20 65,080.82
2.0000 btg Dolken Kayu 8" - 10"/4m 43,002.96 86,005.92
0.6600 oh Pekerja 115,000.00 75,900.00
0.3300 oh Tukang Kayu 148,350.00 48,955.50
0.0330 oh Kepala Tukang 154,100.00 5,085.30
0.0330 oh Mandor 159,275.00 5,256.08
Total : 135,196.88 334,299.40 469,496.27

9 1 M2 PASANG BEKISTING UNTUK LANTAI


0.0400 m3 Kayu Bekisting 2,884,907.20 115,396.29
0.4000 kg Paku Biasa 5' - 12' 30,322.60 12,129.04
0.2000 ltr Minyak Bekisting 18,795.00 3,759.00
0.0150 m3 Kayu Usuk 4/6 2,884,907.20 43,273.61
0.3500 lbr Plywood 9 mm 185,945.20 65,080.82
6.0000 btg Dolken Kayu 8" - 10"/4m 43,002.96 258,017.76
0.6600 oh Pekerja 115,000.00 75,900.00
0.3300 oh Tukang Kayu 148,350.00 48,955.50
0.0330 oh Kepala Tukang 154,100.00 5,085.30
0.0330 oh Mandor 159,275.00 5,256.08
Total : 135,196.88 497,656.52 632,853.39
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

10 1 M2 PASANG BEKISTING UNTUK DINDING


0.0300 M3 Kayu Bekisting 2,884,907.20 86,547.22
0.4000 Kg Paku Biasa 5' - 12' 30,322.60 12,129.04
0.2000 Ltr Minyak Bekisting 18,795.00 3,759.00
0.0200 M3 Kayu Usuk 4/6 2,884,907.20 57,698.14
0.3500 Lbr Plywood 9 mm 185,945.20 65,080.82
3.0000 Btng Dolken Kayu 8" - 10"/4m 43,002.96 129,008.88
4.0000 Bh Formite/penjaga jarak bekisting/spacer - -
0.6600 Oh Pekerja 115,000.00 75,900.00
0.3300 Oh Tukang Kayu 148,350.00 48,955.50
0.0330 Oh Kepala Tukang 154,100.00 5,085.30
0.0330 Oh Mandor 159,275.00 5,256.08
Total : 135,196.88 354,223.10 489,419.98

11 1 M2 PASANG BEKISTING UNTUK TANGGA


0.0300 m3 Kayu Bekisting 2,884,907.20 86,547.22
0.4000 kg Paku Biasa 5' - 12' 30,322.60 12,129.04
0.1500 ltr Minyak Bekisting 18,795.00 2,819.25
0.0150 m3 Kayu Usuk 4/6 2,884,907.20 43,273.61
0.3500 lbr Plywood 9 mm 185,945.20 65,080.82
2.0000 btg Dolken Kayu 8" - 10"/4m 43,002.96 86,005.92
0.6600 oh Pekerja 115,000.00 75,900.00
0.3300 oh Tukang Kayu 148,350.00 48,955.50
0.0330 oh Kepala Tukang 154,100.00 5,085.30
0.0330 oh Mandor 159,275.00 5,256.08
Total : 135,196.88 295,855.85 431,052.73

12 1 M2 PASANG JEMBATAN UNTUK PENGECORAN BETON


0.0264 m3 Kayu Kelas III (Papan Kayu putih) 2,884,907.20 76,161.55
0.6000 kg Paku Biasa 5' - 12' 30,322.60 18,193.56
0.5000 btg Dolken Kayu 8" - 10"/4m 43,002.96 21,501.48
0.1500 oh Pekerja 115,000.00 17,250.00
0.0500 oh Tukang Kayu 148,350.00 7,417.50
0.0050 oh Kepala Tukang 154,100.00 770.50
0.0080 oh Mandor 159,275.00 1,274.20
Total : 26,712.20 115,856.59 142,568.79

13 1 M3 MEMBUAT PONDASI BETON BERTULANG (150 KG BESI + BEKISTING)


0.2000 m3 Kayu Bekisting 2,884,907.20 576,981.44
1.5000 kg Paku Biasa 5' - 12' 30,322.60 45,483.90
0.4000 ltr Minyak Bekisting 18,795.00 7,518.00
157.0000 kg Besi Beton 19,417.41 3,048,532.67
2.2500 kg Kawat Beton 35,835.80 80,630.55
336.0000 kg Semen Portland 2,336.85 785,179.92
0.5400 m3 Pasir Beton 1,929,620.00 1,041,994.80
0.8100 m3 Koral Beton 1,426,289.90 1,155,294.82
5.3000 oh Pekerja 115,000.00 609,500.00
0.2750 oh Tukang Batu 142,600.00 39,215.00
1.3000 oh Tukang Kayu 148,350.00 192,855.00
1.0500 oh Tukang Besi 148,350.00 155,767.50
0.2620 oh Kepala Tukang 154,100.00 40,374.20
0.2650 oh Mandor 159,275.00 42,207.88
Total : 1,079,919.58 6,741,616.10 7,821,535.67

14 1 M3 MEMBUAT SLOOF BETON BERTULANG (200 KG + BEKISTING)


0.2700 m3 Kayu Bekisting 2,884,907.20 778,924.94
2.0000 kg Paku Biasa 5' - 12' 30,322.60 60,645.20
0.6000 ltr Minyak Bekisting 18,795.00 11,277.00
210.0000 kg Besi Beton 19,417.41 4,077,655.16
3.0000 kg Kawat Beton 35,835.80 107,507.40
336.0000 kg Semen Portland 2,336.85 785,179.92
0.5400 m3 Pasir Beton 1,929,620.00 1,041,994.80
0.8100 m3 Koral Beton 1,426,289.90 1,155,294.82
5.6500 oh Pekerja 115,000.00 649,750.00
0.2750 oh Tukang Batu 142,600.00 39,215.00
1.5600 oh Tukang Kayu 148,350.00 231,426.00
1.4000 oh Tukang Besi 148,350.00 207,690.00
0.3230 oh Kepala Tukang 154,100.00 49,774.30
0.2830 oh Mandor 159,275.00 45,074.83
Total : 1,222,930.13 8,018,479.24 9,241,409.37
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

15 1 M3 MEMBUAT KOLOM BETON BERTULANG (300 KG BESI +


BEKISTING)
0.4000 m3 Kayu Bekisting 2,884,907.20 1,153,962.88
4.0000 kg Paku Biasa 5' - 12' 30,322.60 121,290.40
2.0000 ltr Minyak Bekisting 18,795.00 37,590.00
315.0000 kg Besi Beton 19,417.41 6,116,482.74
4.5000 kg Kawat Beton 35,835.80 161,261.10
336.0000 kg Semen Portland 2,336.85 785,179.92
0.5400 m3 Pasir Beton 1,929,620.00 1,041,994.80
0.8100 m3 Koral Beton 1,426,289.90 1,155,294.82
0.1500 m3 Kayu Kelas II balok 2,654,355.20 398,153.28
3.5000 lbr Plywood 9 mm 185,945.20 650,808.20
20.0000 btg Dolken Kayu 8" /4 m 43,002.96 860,059.20
7.0500 oh Pekerja 115,000.00 810,750.00
0.2750 oh Tukang Batu 142,600.00 39,215.00
1.6500 oh Tukang Kayu 148,350.00 244,777.50
2.1000 oh Tukang Besi 148,350.00 311,535.00
0.4030 oh Kepala Tukang 154,100.00 62,102.30
0.3530 oh Mandor 159,275.00 56,224.08
Total : 1,524,603.88 12,482,077.34 14,006,681.21

16 1 M3 MEMBUAT BALOK BETON BERTULANG (200 KG BESI +


BEKISTING)
0.3200 m3 Kayu Bekisting 2,884,907.20 923,170.30
3.2000 kg Paku Biasa 5' - 12' 30,322.60 97,032.32
1.6000 ltr Minyak Bekisting 18,795.00 30,072.00
210.0000 kg Besi Beton 19,417.41 4,077,655.16
3.0000 kg Kawat Beton 35,835.80 107,507.40
336.0000 kg Semen Portland 2,336.85 785,179.92
0.5400 m3 Pasir Beton 1,929,620.00 1,041,994.80
0.8100 m3 Koral Beton 1,426,289.90 1,155,294.82
0.1400 m3 Kayu Kelas II balok 2,654,355.20 371,609.73
2.8000 lbr Plywood 9 mm 185,945.20 520,646.56
16.0000 btg Dolken Kayu 8" /4 m 43,002.96 688,047.36
6.3500 oh Pekerja 115,000.00 730,250.00
0.2750 oh Tukang Batu 142,600.00 39,215.00
1.6500 oh Tukang Kayu 148,350.00 244,777.50
1.4000 oh Tukang Besi 148,350.00 207,690.00
0.3330 oh Kepala Tukang 154,100.00 51,315.30
0.3180 oh Mandor 159,275.00 50,649.45
Total : 1,323,897.25 9,798,210.37 11,122,107.62
17 1 M3 MEMBUAT PLAT BETON BERTULANG (150 KG BESI +
BEKISTING
0.3200 m3 Kayu Bekisting 2,884,907.20 923,170.30
3.2000 kg Paku Biasa 5' - 12' 30,322.60 97,032.32
1.6000 ltr Minyak Bekisting 18,795.00 30,072.00
157.5000 kg Besi Beton 19,417.41 3,058,241.37
2.2500 kg Kawat Beton 35,835.80 80,630.55
336.0000 kg Semen Portland 2,336.85 785,179.92
0.5400 m3 Pasir Beton 1,929,620.00 1,041,994.80
0.8100 m3 Koral Beton 1,426,289.90 1,155,294.82
0.1200 m3 Kayu Kelas II balok 2,654,355.20 318,522.62
2.8000 lbr Plywood 9 mm 185,945.20 520,646.56
32.0000 btg Dolken Kayu 8" /4 m 43,002.96 1,376,094.72
5.3000 oh Pekerja 115,000.00 609,500.00
0.2750 oh Tukang Batu 142,600.00 39,215.00
1.3000 oh Tukang Kayu 148,350.00 192,855.00
1.0500 oh Tukang Besi 148,350.00 155,767.50
0.2650 oh Kepala Tukang 154,100.00 40,836.50
0.2650 oh Mandor 159,275.00 42,207.88
Total : 1,080,381.88 9,386,879.99 10,467,261.86
18 1 M3 MEMBUAT DINDING BETON BERTULANG (150 KG BESI +
BEKISTING)
0.2400 m3 Kayu Bekisting 2,884,907.20 692,377.73
3.2000 kg Paku Biasa 5' - 12' 30,322.60 97,032.32
1.6000 ltr Minyak Bekisting 18,795.00 30,072.00
157.0000 kg Besi Beton 19,417.41 3,048,532.67
2.2500 kg Kawat Beton 35,835.80 80,630.55
336.0000 kg Semen Portland 2,336.85 785,179.92
0.5400 m3 Pasir Beton 1,929,620.00 1,041,994.80
0.8100 m3 Koral Beton 1,426,289.90 1,155,294.82
0.1600 m3 Kayu Kelas II balok 2,654,355.20 424,696.83
2.8000 lbr Plywood 9 mm 185,945.20 520,646.56
24.0000 btg Dolken Kayu 8" /4 m 43,002.96 1,032,071.04
5.3000 oh Pekerja 115,000.00 609,500.00
0.2750 oh Tukang Batu 142,600.00 39,215.00
1.3000 oh Tukang Kayu 148,350.00 192,855.00
1.0500 oh Tukang Besi 148,350.00 155,767.50
0.2620 oh Kepala Tukang 154,100.00 40,374.20
0.2650 oh Mandor 159,275.00 42,207.88
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
Total : 1,079,919.58 8,908,529.24 9,988,448.81
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
19 1 M3 MEMBUAT DINDING BETON BERTULANG (200 KG BESI +
BEKISTING)
0.2500 m3 Kayu Bekisting 2,884,907.20 721,226.80
3.0000 kg Paku Biasa 5' - 12' 30,322.60 90,967.80
1.2000 ltr Minyak Bekisting 18,795.00 22,554.00
210.0000 kg Besi Beton 19,417.41 4,077,655.16
3.0000 kg Kawat Beton 35,835.80 107,507.40
336.0000 kg Semen Portland 2,336.85 785,179.92
0.5400 m3 Pasir Beton 1,929,620.00 1,041,994.80
0.8100 m3 Koral Beton 1,426,289.90 1,155,294.82
0.1050 m3 Kayu Kelas II balok 2,654,355.20 278,707.30
2.5000 lbr Plywood 9 mm 185,945.20 464,863.00
14.0000 btg Dolken Kayu 8" /4 m 43,002.96 602,041.44
5.6500 oh Pekerja 115,000.00 649,750.00
0.2750 oh Tukang Batu 142,600.00 39,215.00
1.5600 oh Tukang Kayu 148,350.00 231,426.00
1.4000 oh Tukang Besi 148,350.00 207,690.00
0.3230 oh Kepala Tukang 154,100.00 49,774.30
0.2830 oh Mandor 159,275.00 45,074.83
Total : 1,222,930.13 9,347,992.43 10,570,922.56

20 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (11 X 11


CM)
0.0020 m3 Kayu Bekisting 2,884,907.20 5,769.81
0.0100 kg Paku Biasa 5' - 12' 30,322.60 303.23
3.0000 kg Besi Beton 19,417.41 58,252.22
0.0450 kg Kawat Beton 35,835.80 1,612.61
4.0000 kg Semen Portland 2,336.85 9,347.38
0.0060 m3 Pasir Beton 1,929,620.00 11,577.72
0.0090 m3 Koral Beton 1,426,289.90 12,836.61
0.1800 oh Pekerja 115,000.00 20,700.00
0.0200 oh Tukang Batu 142,600.00 2,852.00
0.0200 oh Tukang Kayu 148,350.00 2,967.00
0.0200 oh Tukang Besi 148,350.00 2,967.00
0.0060 oh Kepala Tukang 154,100.00 924.60
0.0090 oh Mandor 159,275.00 1,433.48
Total : 31,844.08 99,699.58 131,543.65
21 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (10 X 15
CM)
0.0030 m3 Kayu Bekisting 2,884,907.20 8,654.72
0.0200 kg Paku Biasa 5' - 12' 30,322.60 606.45
3.6000 kg Besi Beton 19,417.41 69,902.66
0.0500 kg Kawat Beton 35,835.80 1,791.79
5.5000 kg Semen Portland 2,336.85 12,852.65
0.0090 m3 Pasir Beton 1,929,620.00 17,366.58
0.0150 m3 Koral Beton 1,426,289.90 21,394.35
0.2970 oh Pekerja 115,000.00 34,155.00
0.0330 oh Tukang Batu 142,600.00 4,705.80
0.0330 oh Tukang Kayu 148,350.00 4,895.55
0.0330 oh Tukang Besi 148,350.00 4,895.55
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0150 oh Mandor 159,275.00 2,389.13
Total : 52,582.03 132,569.20 185,151.22

VIII PEKERJAAN PENUTUP ATAP (SNI 03-3436-2002)


1 1 M2 PEKERJAAN ATAP GENTENG PLENTONG
25.0000 bh Genteng Plentong 3,301.91 82,547.64
0.1500 oh Pekerja 115,000.00 17,250.00
0.0600 oh Tukang Kayu 148,350.00 8,901.00
0.0060 oh Kepala Tukang 154,100.00 924.60
0.0080 oh Mandor 159,275.00 1,274.20
Total : 28,349.80 82,547.64 110,897.44

2 1 M2 PEKERJAAN ATAP GENTENG PLENTONG DI CAT


25.0000 bh Genteng Plentong Dicat 3,094.41 77,360.22
0.1500 oh Pekerja 115,000.00 17,250.00
0.0600 oh Tukang Kayu 148,350.00 8,901.00
0.0060 oh Kepala Tukang 154,100.00 924.60
0.0080 oh Mandor 159,275.00 1,274.20
Total : 28,349.80 77,360.22 105,710.02

3 1 M1 PASANG BUBUNGAN GENTENG PLENTONG


5.0000 bh Bubungan Plentong 9,803.47
8.0000 kg Semen Portland 2,336.85 18,694.76
0.0320 m3 Pasir Pasang 1,353,240.00 43,303.68
0.4000 oh Pekerja 115,000.00 46,000.00
0.2000 oh Tukang Kayu 148,350.00 29,670.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0020 oh Mandor 159,275.00 318.55
Total : 79,070.55 61,998.44 141,068.99
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
4 1 M2 PASANG ATAP GENTENG ASBES GELOMBANG 1.8 M X 0.92 M X 5 MM
0.7500 lbr Asbes Gelombang 1.8 mx0.92mx5mm 40,236.34 30,177.25
0.1200 kg Paku Pancing 60 x 230 23,117.85 2,774.14
0.1400 oh Pekerja 115,000.00 16,100.00
0.0700 oh Tukang Kayu 148,350.00 10,384.50
0.0070 oh Kepala Tukang Kayu 154,100.00 1,078.70
0.0070 oh Mandor 159,275.00 1,114.93
Total : 28,678.13 32,951.39 61,629.52

5 1 M1 PASANG BUBUNGAN STEL GELOMBANG 0.92 M


2.4000 lbr Bubungan Stel Gelombang 29,169.84 70,007.62
6.0000 Bh Paku Skrup 3,5" 196,119.56 1,176,717.36
0.0840 oh Pekerja 115,000.00 9,660.00
0.1250 oh Tukang Kayu 148,350.00 18,543.75
0.0130 oh Kepala Tukang 154,100.00 2,003.30
0.0040 oh Mandor 159,275.00 637.10
Total : 30,844.15 1,246,724.98 1,277,569.13
6 1 M2 PEKERJAAN ATAP SIRAP
60.0000 bh Genteng Sirap 13,261.75 795,705.12
0.2000 kg Paku Biasa 1/2" - 1" 36,086.40 7,217.28
0.1660 oh Pekerja 115,000.00 19,090.00
0.2500 oh Tukang Kayu 148,350.00 37,087.50
0.0250 oh Kepala Tukang 154,100.00 3,852.50
0.0080 oh Mandor 159,275.00 1,274.20
Total : 61,304.20 802,922.40 864,226.60

7 1 M2 PEKERJAAN ATAP NOK SIRAP


0.4000 lbr Seng plat 3" x 6" BJLS 28 26,864.32 10,745.73
0.0600 kg Paku biasa 1/2" - 1" 36,086.40 2,165.18
0.0500 kg Paku biasa 2" - 5" 30,322.60 1,516.13
0.0040 m3 Kayu papan 3 cm 4,037,667.20 16,150.67
0.1250 oh Pekerja 115,000.00 14,375.00
0.2500 oh Tukang kayu 148,350.00 37,087.50
0.0250 oh Kepala Tukang 154,100.00 3,852.50
0.0080 oh Mandor 159,275.00 1,274.20
Total : 56,589.20 30,577.71 87,166.91

8 1 M2 PASANG ATAP ALANG-ALANG 3 M1


6.5000 lbr Alang - alang - -
0.5000 glg Tali pengikat 53,377.80 26,688.90
0.2000 oh Pekerja 115,000.00 23,000.00
0.0100 oh Mandor 159,275.00 1,592.75
Total : 24,592.75 26,688.90 51,281.65

9 1 M2 PEKERJAAN ATAP SENG GELOMBANG


0.7000 lbr Seng Gelombang 3" x 6" BJLS 32 93,724.40 65,607.08
0.0200 kg Paku Biasa 1/2" - 1" 56,836.08 1,136.72
0.1200 oh Pekerja 115,000.00 13,800.00
0.0600 oh Tukang Kayu 148,350.00 8,901.00
0.0060 oh Kepala Tukang 154,100.00 924.60
0.0060 oh Mandor 159,275.00 955.65
Total : 24,581.25 66,743.80 91,325.05

10 1 M2 PASANGAN LAPISANG ALUMINIUM FOIL


1.0500 m2 Aluminium Foil 34,933.64 36,680.32
0.1500 oh Pekerja 115,000.00 17,250.00
0.0500 oh Tukang Kayu 148,350.00 7,417.50
0.0050 oh Kepala Tukang 154,100.00 770.50
0.0080 oh Mandor 159,275.00 1,274.20
Total : 26,712.20 36,680.32 63,392.52

11 1 M1 PASANG NOK SENG GELOMBANG


0.3000 lbr Seng Plat 3" x 6" BJLS 28 26,864.32 8,059.30
0.0400 kg Paku biasa 1/2" - 1" 56,836.08 2,273.44
0.1500 oh Pekerja 115,000.00 17,250.00
0.0700 oh Tukang Kayu 148,350.00 10,384.50
0.0080 oh Kepala Tukang 154,100.00 1,232.80
0.0060 oh Mandor 159,275.00 955.65
Total : 29,822.95 10,332.74 40,155.69
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

12 1 M2 MEMASANG ATAP MULTIROOF


1.0200 lbr Multiroof 105,252.00 107,357.04
0.2000 kg Paku 24,558.80 4,911.76
0.2000 oh Pekerja 115,000.00 23,000.00
0.1000 oh Tukang Kayu 148,350.00 14,835.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0100 oh Mandor 159,275.00 1,592.75
Total : 40,968.75 112,268.80 153,237.55

13 1 M1 MEMASANG BUBUNGAN MULTIROOF


5.0000 bh Bubungan Multiroof 64,905.40 324,527.00
0.8000 kg Semen Portland 2,336.85 1,869.48
0.0320 m3 Pasir Pasang 1,929,620.00 61,747.84
0.4000 oh Pekerja 115,000.00 46,000.00
0.2000 oh Tukang Kayu 148,350.00 29,670.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0020 oh Mandor 159,275.00 318.55
Total : 79,070.55 388,144.32 467,214.87

IX PEKERJAAN LANGIT - LANGIT (SNI 2839-2008)


1 MEMASANG 1 M2 LANGIT-LANGIT ETERNIT, TEBAL 4 MM, 5 MM
DAN 6 MM
1.1000 lbr Eternit 55,683.32 61,251.65
0.0100 kg Paku Biasa 1/2" - 1" 28,969.36 289.69
0.0300 oh Pekerja 115,000.00 3,450.00
0.0700 oh Tukang Kayu 148,350.00 10,384.50
0.0070 oh Kepala Tukang 154,100.00 1,078.70
0.0040 oh Mandor 159,275.00 637.10
Total : 15,550.30 61,541.35 77,091.65

2 1 M2 PASANG LANGIT-LANGIT TRIPLEKS 120X240 CM/4MM


0.3750 lbr Tripleks 4 mm 128,307.20 48,115.20
0.0300 kg Paku Biasa 1/2" - 1" 28,969.36 869.08
0.1000 oh Pekerja 115,000.00 11,500.00
0.1000 oh Tukang Kayu 148,350.00 14,835.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0050 oh Mandor 159,275.00 796.38
Total : 28,672.38 48,984.28 77,656.66

3 1 M2 PASANG LANGIT-LANGIT LAMBRIZIRING


0.0150 m3 Kayu Papan 4,037,667.20 60,565.01
0.0100 kg Paku Biasa 1/2" - 1" 28,969.36 289.69
0.8000 oh Pekerja 115,000.00 92,000.00
0.8000 oh Tukang Kayu 148,350.00 118,680.00
0.0800 oh Kepala Tukang 154,100.00 12,328.00
0.0400 oh Mandor 159,275.00 6,371.00
Total : 229,379.00 60,854.70 290,233.70

4 1 M1 PASANG LIST LANGIT-LANGIT KAYU PROFIL


1.0500 m1 List Kayu Profil 13,031.20 13,682.76
0.1000 kg Paku list SQ 30,322.60 3,032.26
0.0500 oh Pekerja 115,000.00 5,750.00
0.0500 oh Tukang Kayu 148,350.00 7,417.50
0.0050 oh Kepala Tukang 154,100.00 770.50
0.0030 oh Mandor 159,275.00 477.83
Total : 14,415.83 16,715.02 31,130.85
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

5 1 M2 PASANG LANGIT-LANGIT ASBES + RANGKA


0.0120 m3 Matoa Usuk 4/6 cm 2,884,907.20 34,618.89
0.0600 kg Paku Biasa 2" - 5" 30,322.60 1,819.36
1.1000 lbr Asbes 55,683.32 61,251.65
0.1800 oh Pekerja 115,000.00 20,700.00
0.3200 oh Tukang Kayu 148,350.00 47,472.00
0.0320 oh Kepala Tukang 154,100.00 4,931.20
0.0090 oh Mandor 159,275.00 1,433.48
Total : 74,536.68 97,689.89 172,226.57

6 1 M2 PASANG LANGIT-LANGIT GYPSUM BOARD UKURAN (1200X2400X9) MM


0.1100 kg Paku Sekrup 139,834.80 15,381.83
0.3640 lbr Gypsum Board (120x240x9) - -
0.1000 oh Pekerja 115,000.00 11,500.00
0.0500 oh Tukang Kayu 148,350.00 7,417.50
0.0050 oh Kepala Tukang 154,100.00 770.50
0.0050 oh Mandor 159,275.00 796.38
Total : 20,484.38 15,381.83 35,866.20

7 1 M2 PASANG LANGIT-LANGIT KALSIBOARD 4.5 MM


0.1100 kg Paku Sekrup 139,834.80 15,381.83
0.3640 lbr Kalsiboard 4.5 mm - -
0.1000 oh Pekerja 115,000.00 11,500.00
0.0500 oh Tukang Kayu 148,350.00 7,417.50
0.0050 oh Kepala Tukang 154,100.00 770.50
0.0050 oh Mandor 159,275.00 796.38
Total : 20,484.38 15,381.83 35,866.20

X PEKERJAAN SANITASI ( SNI 2002 )


1 MEMASANG 1 BUAH KLOSET DUDUK/MONOBLOK
1.0000 bh Kloset duduk/ monoblok 2,773,640.80 2,773,640.80
6% x harga kloset Perlengkapan 166,418.45
3.3000 oh Pekerja 115,000.00 379,500.00
1.1000 oh Tukang batu 142,600.00 156,860.00
0.0010 oh Kepala Tukang 154,100.00 154.10
0.1600 oh Mandor 159,275.00 25,484.00
Total : 561,998.10 2,940,059.25 3,502,057.35

2 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN


1.0000 bh Kloset jongkok porselen 525,758.80 525,758.80
6.0000 kg Semen Portland 2,336.85 14,021.07
0.0100 m3 Pasir Pasang 1,353,240.00 13,532.40
1.0000 oh Pekerja 115,000.00 115,000.00
1.5000 oh Tukang batu 142,600.00 213,900.00
1.5000 oh Kepala Tukang 154,100.00 231,150.00
0.1600 oh Mandor 159,275.00 25,484.00
Total : 585,534.00 553,312.27 1,138,846.27

3 MEMASANG 1 BUAH URINOIR


1.0000 bh Urinoir 1,214,207.12 1,214,207.12
6% x harga Urin Perlengkapan 72,852.43
6.0000 kg Semen Portland 2,336.85 14,021.07
0.0100 m3 Pasir Pasang 1,353,240.00 13,532.40
1.0000 oh Pekerja 115,000.00 115,000.00
1.0000 oh Tukang batu 142,600.00 142,600.00
0.1000 oh Kepala Tukang 154,100.00 15,410.00
0.1000 oh Mandor 159,275.00 15,927.50
Total : 288,937.50 1,314,613.02 1,603,550.52

4 MEMASANG 1 BUAH WASHTAFEL KIA


1.0000 bh Washtafel 687,395.80 687,395.80
12% x harga wast Perlengkapan 82,487.50
6.0000 kg Semen Portland 2,336.85 14,021.07
0.0100 m3 Pasir Pasang 1,353,240.00 13,532.40
1.2000 oh Pekerja 115,000.00 138,000.00
1.4500 oh Tukang batu 142,600.00 206,770.00
0.1500 oh Kepala Tukang 154,100.00 23,115.00
0.1000 oh Mandor 159,275.00 15,927.50
Total : 383,812.50 797,436.77 1,181,249.27
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

5 MEMASANG 1 BUAH BAK MANDI FIBREGLASS, VOLUME 0,30 M3


1.0000 bh Bak Fibreglass 410,482.80 410,482.80
18% x harga wast Perlengkapan 73,886.90
1.8000 oh Pekerja 115,000.00 207,000.00
2.7000 oh Tukang batu 142,600.00 385,020.00
0.5400 oh Kepala Tukang 154,100.00 83,214.00
0.1100 oh Mandor 159,275.00 17,520.25
Total : 692,754.25 484,369.70 1,177,123.95

6 MEMASANG 1 M1 PIPA GALVANIS f 0,5" - 1 "


1.2000 m1 Pipa galvanis - -
35% x harga pipa Perlengkapan -
0.0540 oh Pekerja 115,000.00 6,210.00
0.0900 oh Tukang Pipa 148,350.00 13,351.50
0.0090 oh Kepala Tukang 154,100.00 1,386.90
0.0270 oh Mandor 159,275.00 4,300.43
Total : 25,248.83 - 25,248.83

7 MEMASANG 1 M1 PIPA GALVANIS f 1,5" - 3"


1.2000 M' Pipa galvanis 132,776.23 159,331.48
35% x harga pipa Perlengkapan 46,471.68
0.1080 Oh Pekerja 115,000.00 12,420.00
0.1800 Oh Tukang Pipa 148,350.00 26,703.00
0.0180 Oh Kepala Tukang 154,100.00 2,773.80
0.0054 Oh Mandor 159,275.00 860.09
Total : 42,756.89 205,803.16 248,560.05

8 MEMASANG 1 M1 PIPA PVC TYPE AW f 0,5" - 1,5"


1.2000 m1 Pipa PVC 27,691.30 33,229.56
35% x harga pipa Perlengkapan 9,691.96
0.0360 oh Pekerja 115,000.00 4,140.00
0.0600 oh Tukang Pipa 148,350.00 8,901.00
0.0060 oh Kepala Tukang 154,100.00 924.60
0.0018 oh Mandor 159,275.00 286.70
Total : 14,252.30 42,921.52 57,173.81

9 MEMASANG 1 M1 PIPA PVC TYPE AW f 2"


1.2000 m1 Pipa PVC - -
35% x harga pipa Perlengkapan -
0.0540 oh Pekerja 115,000.00 6,210.00
0.0900 oh Tukang Pipa 148,350.00 13,351.50
0.0090 oh Kepala Tukang 154,100.00 1,386.90
0.0027 oh Mandor 159,275.00 430.04
Total : 21,378.44 - 21,378.44

10 MEMASANG 1 M1 PIPA PVC TYPE AW f 3" - 4"


1.2000 m1 Pipa PVC - -
35% x harga pipa Perlengkapan -
0.0810 oh Pekerja 115,000.00 9,315.00
0.1350 oh Tukang Pipa 148,350.00 20,027.25
0.0135 oh Kepala Tukang 154,100.00 2,080.35
0.0041 oh Mandor 159,275.00 653.03
Total : 32,075.63 - 32,075.63
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

11 MEMASANG 1 BUAH KRAN f 0,75" ATAU 0,5"


1.0000 bh Kran air 58,891.00 58,891.00
0.0250 bh Seal tape 18,795.00 469.88
0.0100 oh Pekerja 115,000.00 1,150.00
0.1000 oh Tukang Pipa 148,350.00 14,835.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0050 oh Mandor 159,275.00 796.38
Total : 18,322.38 59,360.88 77,683.25

XI PEKERJAAN BESI DAN ALUMINIUM


(SNI 7393:2008)
1 1 KG PASANG RANGKA ATAP BAJA
1.1500 kg Besi Profil WF 20,524.14 23,602.76
0.0060 oh Pekerja 115,000.00 690.00
0.0600 oh Tukang besi 148,350.00 8,901.00
0.0060 oh Kepala Tukang 154,100.00 924.60
0.0003 oh Mandor 159,275.00 47.78
Total : 10,563.38 23,602.76 34,166.14

2 1 M2 PASANG JENDELA NAKO


1.1000 m2 Rangka + Kaca Nako 30,322.60 33,354.86
10.0000 bh Paku biasa 1 cm - 2,5 cm 17,441.76 174,417.60
7.0000 m' Besi strip 9,872.64 69,108.46
0.2000 oh Pekerja 115,000.00 23,000.00
0.2000 oh Tukang besi 148,350.00 29,670.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0010 oh Mandor 159,275.00 159.28
Total : 55,911.28 276,880.92 332,792.20

3 1 M1 PASANG TALANG DATAR, SENG BJLS 28


1.0500 lbr Seng plat 26,864.32 28,207.54
0.0150 kg Paku biasa 0,5" - 1" 36,086.40 541.30
0.0190 m3 Kayu papan matoa 2,884,907.20 54,813.24
0.1500 oh Pekerja 115,000.00 17,250.00
0.4000 oh Tukang besi 148,350.00 59,340.00
0.0250 oh Kepala Tukang 154,100.00 3,852.50
0.0013 oh Mandor 159,275.00 207.06
Total : 80,649.56 83,562.07 164,211.63

XII PEKERJAAN KUNCI DAN KACA (SNI 2002)


1 1 BH PASANG KUNCI TANAM BIASA
1.0000 bh Kunci tanam biasa 203,236.60 203,236.60
0.0100 oh Pekerja 115,000.00 1,150.00
0.5000 oh Tukang besi 148,350.00 74,175.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0050 oh Mandor 159,275.00 796.38
Total : 77,662.38 203,236.60 280,898.98

2 1 PS PASANG ENGSEL PINTU


1.0000 ps Engsel pintu 24,558.80 24,558.80
0.0150 oh Pekerja 115,000.00 1,725.00
0.1500 oh Tukang besi 148,350.00 22,252.50
0.0150 oh Kepala Tukang 154,100.00 2,311.50
0.0008 oh Mandor 159,275.00 127.42
Total : 26,416.42 24,558.80 50,975.22

3 1 PS PASANG ENGSEL JENDELA KUPU-KUPU


1.0000 ps Engsel jendela 41,850.20 41,850.20
0.0100 oh Pekerja 115,000.00 1,150.00
0.1000 oh Tukang besi 148,350.00 14,835.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.0005 oh Mandor 159,275.00 79.64
Total : 17,605.64 41,850.20 59,455.84

4 1 BH PASANG KAIT ANGIN


1.0000 ps Kait angin 24,558.80 24,558.80
0.0150 oh Pekerja 115,000.00 1,725.00
0.1500 oh Tukang besi 148,350.00 22,252.50
0.0150 oh Kepala Tukang 154,100.00 2,311.50
0.0008 oh Mandor 159,275.00 127.42
Total : 26,416.42 24,558.80 50,975.22

5 1 BH PASANG KUNCI SLOT


1.0000 bh Kunci slot 33,780.88 33,780.88
0.0200 oh Pekerja 115,000.00 2,300.00
0.2000 oh Tukang besi 148,350.00 29,670.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0010 oh Mandor 159,275.00 159.28
Total : 35,211.28 33,780.88 68,992.16
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

6 1 M2 PASANG KACA, TEBAL 3 - 5 MM


1.1000 m2 Kaca 217,653.82 239,419.20
0.0150 oh Pekerja 115,000.00 1,725.00
0.1500 oh Tukang besi 148,350.00 22,252.50
0.0150 oh Kepala Tukang 154,100.00 2,311.50
0.0008 oh Mandor 159,275.00 127.42
Total : 26,416.42 239,419.20 265,835.62

XIII PEK. PENUTUP LANTAI DAN DINDING


(SNI 7395:2008)

1 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM


11.8700 bh Keramik 30 x 30 cm - -
10.0000 kg Semen Portland 2,336.85 23,368.45
0.0450 m3 Pasir Pasang 1,353,240.00 60,895.80
1.5000 kg Semen warna/semen grouting 16,489.48 24,734.22
0.7000 oh Pekerja 115,000.00 80,500.00
0.3500 oh Tukang batu 142,600.00 49,910.00
0.0350 oh Kepala Tukang 154,100.00 5,393.50
0.0350 oh Mandor 159,275.00 5,574.63
Total : 141,378.13 108,998.47 250,376.60

2 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM


26.5000 bh Keramik 20 x 20 cm 2,933.02 77,725.09
10.4000 kg Semen Portland 2,336.85 24,303.19
0.0450 m3 Pasir Pasang 1,353,240.00 60,895.80
1.6200 kg Semen warna/semen grouting 16,489.48 26,712.96
0.7000 oh Pekerja 115,000.00 80,500.00
0.3500 oh Tukang batu 142,600.00 49,910.00
0.0350 oh Kepala Tukang 154,100.00 5,393.50
0.0350 oh Mandor 159,275.00 5,574.63
Total : 141,378.13 189,637.04 331,015.16

3 1 M1 PASANG PLIN KERAMIK 10 X 30 CM


3.3300 bh Keramik 30 x 30 cm - -
1.1400 kg Semen Portland 2,336.85 2,664.00
0.0030 m3 Pasir Pasang 1,353,240.00 4,059.72
0.1000 kg Semen warna/semen grouting 16,489.48 1,648.95
0.0900 oh Pekerja 115,000.00 10,350.00
0.0900 oh Tukang batu 142,600.00 12,834.00
0.0090 oh Kepala Tukang 154,100.00 1,386.90
0.0050 oh Mandor 159,275.00 796.38
Total : 25,367.28 8,372.67 33,739.95
4 1 M2 PASANG DINDING KERAMIK 20 X 20 CM
26.5000 bh Keramik 20 x 20 cm 2,933.02 77,725.09
9.3000 kg Semen Portland 2,336.85 21,732.66
0.0180 m3 Pasir Pasang 1,353,240.00 24,358.32
1.9400 kg Semen warna/semen grouting 16,489.48 31,989.59
0.9000 oh Pekerja 115,000.00 103,500.00
0.4500 oh Tukang batu 142,600.00 64,170.00
0.0450 oh Kepala Tukang 154,100.00 6,934.50
0.0450 oh Mandor 159,275.00 7,167.38
Total : 181,771.88 155,805.66 337,577.54

5 1 M1 PASANG PLIN KAYU 2 X 10 CM


0.0030 m3 Papan Kayu Matoa 2,884,907.20 8,654.72
0.0500 kg Paku sekrup 3,5' 196,119.56 9,805.98
0.1200 oh Pekerja 115,000.00 13,800.00
0.1200 oh Tukang kayu 148,350.00 17,802.00
0.0120 oh Kepala Tukang 154,100.00 1,849.20
0.0060 oh Mandor 159,275.00 955.65
Total : 34,406.85 18,460.70 52,867.55

XIV PEKERJAAN PENGECATAN (SNI 2002)


1 1 M2 PENGECATAN BIDANG KAYU BARU (1 LAPIS PLAMIR,
1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
0.2000 kg Cat meni 70,669.20 14,133.84
0.1500 kg Dempul 60,645.20 9,096.78
0.1700 kg Cat dasar 80,755.85 13,728.49
0.2600 kg Cat Penutup 2x 73,551.10 19,123.29
0.0700 oh Pekerja 115,000.00 8,050.00
0.0090 oh Tukang cat 148,350.00 1,335.15
0.0060 oh Kepala Tukang 154,100.00 924.60
0.0025 oh Mandor 159,275.00 398.19
Total : 10,707.94 56,082.40 66,790.34
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

2 1 M2 PENGECATAN BIDANG KAYU DENGAN VERNIS


0.1500 kg Vernis 95,228.00 14,284.20
0.0500 kg Dempul 60,645.20 3,032.26
0.1000 lbr Amplas 10,725.68 1,072.57
0.0100 bh Kuas 37,590.00 375.90
0.1600 oh Pekerja 115,000.00 18,400.00
0.1600 oh Tukang cat 148,350.00 23,736.00
0.0160 oh Kepala Tukang 154,100.00 2,465.60
0.0025 oh Mandor 159,275.00 398.19
Total : 44,999.79 18,764.93 63,764.72
3 1 M2 PENGECATAN TEMBOK BARU (1 LAPIS PLAMIR,
1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
0.1000 kg Plamir 15,687.56 1,568.76
0.1000 kg Cat dasar 80,755.85 8,075.59
0.2600 kg Cat Penutup 2x 30,673.44 7,975.09
0.0200 oh Pekerja 115,000.00 2,300.00
0.0630 oh Tukang cat 148,350.00 9,346.05
0.0063 oh Kepala Tukang 154,100.00 970.83
0.0025 oh Mandor 159,275.00 398.19
Total : 13,015.07 17,619.44 30,634.50

4 1 M2 PENGECATAN TEMBOK LAMA (1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)


0.1200 kg Cat dasar 80,755.85 9,690.70
0.1800 kg Cat Penutup 2x 30,673.44 5,521.22
0.0280 oh Pekerja 115,000.00 3,220.00
0.0420 oh Tukang cat 148,350.00 6,230.70
0.0042 oh Kepala Tukang 154,100.00 647.22
0.0025 oh Mandor 159,275.00 398.19
Total : 10,496.11 15,211.92 25,708.03

5 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI


0.1000 kg Meni besi 30,322.60 3,032.26
0.0100 lbr Kuas 37,590.00 375.90
0.0200 oh Pekerja 115,000.00 2,300.00
0.2000 oh Tukang cat 148,350.00 29,670.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0100 oh Mandor 159,275.00 1,592.75
Total : 36,644.75 3,408.16 40,052.91

6 1 M2 PENGECATAN PERMUKAAN BAJA, 1 LAPIS DENGAN CAT BESI


0.3000 kg Cat besi 99,488.20 29,846.46
0.0060 oh Pekerja 115,000.00 690.00
0.0600 oh Tukang cat 148,350.00 8,901.00
0.0120 oh Kepala Tukang 154,100.00 1,849.20
0.0060 oh Mandor 159,275.00 955.65
Total : 12,395.85 29,846.46 42,242.31

7 1 M2 PELABURAN BIDANG KAYU DENGAN POLITUR


0.5220 ltr Politur 54,881.40 28,648.09
2.0000 lbr Amplas 10,725.68 21,451.36
0.0600 oh Pekerja 115,000.00 6,900.00
0.0600 oh Tukang cat 148,350.00 8,901.00
0.0160 oh Kepala Tukang 154,100.00 2,465.60
0.0025 oh Mandor 159,275.00 398.19

Total : 18,664.79 50,099.45 68,764.24

XV PEKERJAAN TETEMPELAN STYLE BALI

1 1 M2 PASANGAN BATA GOSOK 2 MUKA


110.0000 bh Bata Gosok 59,848.11 6,583,292.19
8.4000 kg Semen Portland 2,336.85 19,629.50
Upah Kerja ( Lumpsum) 359,074.00 359,074.00
Total : 359,074.00 6,602,921.69 6,961,995.69

2 1 M2 PASANGAN PARAS KEROBOKAN 1 MUKA


13.7500 bh Paras Kerobokan - -
8.4000 kg Semen Portland 2,336.85 19,629.50
Upah Kerja ( Lumpsum) 192,836.00 192,836.00
Total : 192,836.00 19,629.50 212,465.50

3 1 M2 PASANGAN BATA GOSOK 1 MUKA


55.0000 bh Bata Gosok 59,848.11 3,291,646.10
4.2000 kg Semen Portland 2,336.85 9,814.75
Upah Kerja ( Lumpsum) 192,836.00 192,836.00
Total : 192,836.00 3,301,460.85 3,494,296.85
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

4 1 M2 PASANGAN PARAS 1 MUKA


18.3333 bh Batu paras - -
4.2000 kg Semen Portland 2,336.85 9,814.75
Upah Kerja ( Lumpsum) 192,836.00 192,836.00
Total : 192,836.00 9,814.75 202,650.75

5 1 M2 PASANGAN PARAS + BATA GOSOK 1 MUKA


55.0000 bh Bata gosok 59,848.11 3,291,646.10
4.4917 bh Batu paras - -
5.2500 kg Semen Portland 2,336.85 12,268.44
Upah Kerja ( Lumpsum) 192,836.00 192,836.00
Total : 192,836.00 3,303,914.53 3,496,750.53

6 1 M2 PASANGAN BATA GOSOK DIUKIR


55.0000 bh Bata gosok 59,848.11 3,291,646.10
4.2000 kg Semen Portland 2,336.85 9,814.75
Upah Kerja ( Lumpsum) 383,674.00 383,674.00
Total : 383,674.00 3,301,460.85 3,685,134.85

7 1 M2 PASANGAN PARAS DIUKIR


18.3333 bh Batu paras - -
4.2000 kg Semen Portland 2,336.85 9,814.75
Upah Kerja ( Lumpsum) 383,674.00 383,674.00
Total : 383,674.00 9,814.75 393,488.75

8 1 M2 PASANGAN PARAS + BATA GOSOK DIUKIR


55.0000 bh Bata gosok 59,848.11 3,291,646.10
4.4917 bh Batu paras - -
5.2500 kg Semen 50 Kg 2,336.85 12,268.44
Upah Kerja ( Lumpsum) 383,674.00 383,674.00
Total : 383,674.00 3,303,914.53 3,687,588.53

XVI PEKERJAAN LANDSCAPE

1 1 M2 PASANGAN PAVING BETON 10/20 CM TEBAL 6 CM K 225


1.0000 m2 Paving 10 x 20 cm tebal 6 cm K225 - -
0.2500 oh Tukang Batu 142,600.00 35,650.00
0.0250 oh Kepala Tukang 154,100.00 3,852.50
0.5000 oh Pekerja 115,000.00 57,500.00
0.0250 oh Mandor 159,275.00 3,981.88
Total : 100,984.38 - 100,984.38
2 Paving 10 x 20 cm tebal 6 cm K350 - 100,984.38 - 100,984.38
4 Paving 10 x 20 cm tebal 8 cm K225 - 100,984.38 - 100,984.38
5 Paving 10 x 20 cm tebal 8 cm K350 - 100,984.38 - 100,984.38
5 Paving 10 x 20 cm tebal 8 cm K425 - 100,984.38 - 100,984.38
7 Paving 20 x 20 cm tebal 6 cm K225 - 100,984.38 - 100,984.38
8 Paving 20 x 20 cm tebal 6 cm K350 - 100,984.38 - 100,984.38
10 Paving 20 x 20 cm tebal 8 cm K225 - 100,984.38 - 100,984.38
11 Paving 20 x 20 cm tebal 8 cm K350 - 100,984.38 - 100,984.38
12 Paving 20 x 20 cm tebal 8 cm K425 - 100,984.38 - 100,984.38
14 Paving 20 x 20 cm tebal 10 cm K225 - 100,984.38 - 100,984.38
15 Paving 20 x 20 cm tebal 10 cm K350 - 100,984.38 - 100,984.38
16 Paving 20 x 20 cm tebal 10 cm K425 - 100,984.38 - 100,984.38
18 Paving Tiga Berlian tebal 6 cm K225 - 100,984.38 - 100,984.38

20 1 M2 PASANGAN GRASS BLOCK


1.0000 m2 Grass Block 264,884.20 264,884.20
0.0690 m3 Pasir Urug 1,353,240.00 93,373.56
0.5000 oh Tukang Batu 142,600.00 71,300.00
0.0500 oh Kepala Tukang 154,100.00 7,705.00
1.0000 oh Pekerja 115,000.00 115,000.00
0.0500 oh Mandor 159,275.00 7,963.75
Total : 201,968.75 358,257.76 560,226.51

21 1 M2 PASANGAN KORAL SIKAT


1.2000 zak Koral Sikat - -
9.2800 zak Semen 2,336.85 21,685.92
0.2000 m3 Pasir pasang 1,353,240.00 270,648.00
0.2500 oh Tukang Batu 142,600.00 35,650.00
0.0100 oh Kepala Tukang 154,100.00 1,541.00
0.6250 oh Pekerja 115,000.00 71,875.00
0.0310 oh Mandor 159,275.00 4,937.53
Total : 114,003.53 292,333.92 406,337.45
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
22 1 M1 KANSTEIN BULAT (50 x 30 x 10 ) CM K225
1.0000 m1 Kanstein Bulat(P:50,T:30,La:10,Lb:16 cm K225 - -
0.4500 zak Semen 50 Kg 2,336.85 1,051.58
0.0023 m3 Pasir Pasang 1,353,240.00 3,112.45
0.3500 oh Tukang Batu 142,600.00 49,910.00
0.0350 oh Kepala Tukang 154,100.00 5,393.50
0.9500 oh Pekerja 115,000.00 109,250.00
0.0950 oh Mandor 159,275.00 15,131.13
Total : 179,684.63 4,164.03 183,848.66
23 Kanstein Jumbo (P:50,L:15,T:30 cm K225) - 179,684.63 292,333.92 472,018.55
24 Kanstein Segi Lima Jumbo (P:50,L:15, T:40 cm K225) - 179,684.63 292,333.92 472,018.55

25 1 M2 PENGECATAN KANSTEIN
0.2840 kg Cat 99,488.20 28,254.65
0.0710 kg Thiner 49,117.60 3,487.35
0.0300 oh Tukang Cat 148,350.00 4,450.50
0.0030 oh Kep. Tukang 154,100.00 462.30
0.1500 oh Pekerja 115,000.00 17,250.00
0.0150 oh Mandor 159,275.00 2,389.13
Total : 24,551.93 31,742.00 56,293.92

XVII PEKERJAAN ELEKTRIKAL

1 1 TITIK INSTALASI STOP KONTAK, LAMPU, EXHAUST FAN DAN CEILING FAN
8.0000 m1 Kabel NYM 3 x 2.5 mm ex. Supreme 24,558.80 196,470.40
3.0000 bt Pipa Clipsal 20 mm hitam 30,322.60 90,967.80
2.0000 bh Tee dos clipsal 20 mm hitam 13,031.20 26,062.40
15.0000 bj Klem clipsal 20 mm hitam 7,267.40 109,011.00
3.0000 bj Sock clipsal 20 mm hitam 6,114.64 18,343.92
1.0000 bj Inbow dos plastik clipsal E 157 P 16,489.48 16,489.48
1.0000 ttk Biaya pasang 50,000.00 50,000.00
Total : 50,000.00 457,345.00 507,345.00

2 1 TITIK INSTALASI AC
10.0000 m1 Kabel NYM 3 x 2.5 mm ex. Supreme 24,558.80 245,588.00
3.0000 bt Pipa Clipsal 20 mm hitam 30,322.60 90,967.80
1.0000 bh Tee dos clipsal 20 mm hitam 13,031.20 13,031.20
15.0000 bj Klem clipsal 20 mm hitam 7,267.40 109,011.00
4.0000 bj Sock clipsal 20 mm hitam 6,114.64 24,458.56
1.0000 bj Inbow dos plastik clipsal E 157 P 16,489.48 16,489.48
1.0000 m1 Pipa flexible clipsal 20 mm hitam 47,614.00 47,614.00
1.0000 ttk Biaya pasang 50,000.00 50,000.00 50,000.00
Total : 50,000.00 597,160.04 647,160.04

3 1 TITIK INSTALASI TELEPHONE


25.0000 m1 Kabel telephone 7,267.40 181,685.00
8.0000 bt Pipa Clipsal 20 mm putih 30,322.60 242,580.80
1.0000 bh Tee dos clipsal 20 mm putih 13,031.20 13,031.20
25.0000 bj Klem clipsal 20 mm putih 7,267.40 181,685.00
5.0000 bj Sock clipsal 20 mm putih 6,114.64 30,573.20
1.0000 bj Inbow dos plastik clipsal E 157 P 16,489.48 16,489.48
1.0000 ttk Biaya pasang 50,000.00 50,000.00
Total : 50,000.00 666,044.68 716,044.68

4 1 TITIK INSTALASI MATV


20.0000 m1 Coaxial cable 5C-75 ohm commscof 8,074.33 161,486.64
6.0000 bt Pipa Clipsal 20 mm putih 30,322.60 181,935.60
2.0000 bh Tee dos clipsal 20 mm putih 13,031.20 26,062.40
20.0000 bj Klem clipsal 20 mm putih 7,267.40 145,348.00
6.0000 bj Sock clipsal 20 mm putih 6,114.64 36,687.84
1.0000 bj Inbow dos plastik clipsal E 157 P 16,489.48 16,489.48
1.0000 ttk Biaya pasang 50,000.00 50,000.00
Total : 50,000.00 568,009.96 618,009.96

ANALISA PASANGAN BATA RINGAN (PENDEKATAN)


1 1 M2 PASANGAN BATU RINGAN CAMP. 1 PC : 2 PS
8.0000 bh Bata ringan 60x20x10 cm 22,959.79 183,678.33
43.5000 kg Semen Portland 2,336.85 101,652.76
0.0800 m3 Pasir Pasang 1,353,240.00 108,259.20
0.6000 oh Pekerja 115,000.00 69,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0300 oh Mandor 159,275.00 4,778.25
Total : 105,380.25 393,590.28 498,970.53

2 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 3 PS


8.0000 bh Bata ringan 60x20x10 cm 22,959.79 183,678.33
32.9500 kg Semen Portland 2,336.85 76,999.04
0.0910 m3 Pasir Pasang 1,353,240.00 123,144.84
0.6000 oh Pekerja 115,000.00 69,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0300 oh Mandor 159,275.00 4,778.25
Total : 105,380.25 383,822.21 489,202.46

3 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 4 PS


8.0000 bh Bata ringan 60x20x10 cm 22,959.79 183,678.33
26.5500 kg Semen Portland 2,336.85 62,043.23
0.0930 m3 Pasir Pasang 1,353,240.00 125,851.32
0.6000 oh Pekerja 115,000.00 69,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0300 oh Mandor 159,275.00 4,778.25
Total : 105,380.25 371,572.88 476,953.13

4 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 5 PS


8.0000 bh Bata ringan 60x20x10 cm 22,959.79 183,678.33
22.2000 kg Semen Portland 2,336.85 51,877.96
0.1020 m3 Pasir Pasang 1,353,240.00 138,030.48
0.6000 oh Pekerja 115,000.00 69,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0300 oh Mandor 159,275.00 4,778.25
Total : 105,380.25 373,586.77 478,967.02

5 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 6 PS


8.0000 bh Bata ringan 60x20x10 cm 22,959.79 183,678.33
18.5000 kg Semen Portland 2,336.85 43,231.63
0.1220 m3 Pasir Pasang 1,353,240.00 165,095.28
0.6000 oh Pekerja 115,000.00 69,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
0.0200 oh Kepala Tukang 154,100.00 3,082.00
0.0300 oh Mandor 159,275.00 4,778.25
Total : 105,380.25 392,005.24 497,385.49
REKAPITULASI DAFTAR HARGA SATUAN PEKERJAAN
TAHUN 2018

NO URAIAN PEKERJAAN HARGA


1 2 3
I PEKERJAAN PERSIAPAN (SNI 03-2835-2002)
1 1 M1 PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 METER Rp. 469,751.02
2 1 M1 PENGUKURAN DAN PEMASANGAN BOWPLANK Rp. 80,172.68
3 1 M2 PEMBUATAN KANTOR SEMENTARA, DENGAN LANTAI PLESTERAN Rp. 2,437,989.03
4 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT Rp. 1,319,065.23
5 1 M2 PEMBUATAN RUMAH JAGA/KONSTRUKSI KAYU Rp. 1,297,500.77
6 1 M2 MEMBERSIHKAN LAPANGAN DAN PERATAAN Rp. 19,463.75
7 1 M2 PEMBUATAN BEDENG BURUH Rp. 1,437,644.01
8 1 M2 PEMBUATAN BAK ADUKAN UKURAN (40X50X20) CM Rp. 172,036.68
9 1 M2 PEMBUATAN STEGGER DARI BAMBU Rp. 62,142.53
10 1 M2 PEMBUATAN JALAN SEMENTARA Rp. 375,057.33
11 1 M3 BONGKARAN BETON BERTULANG Rp. 819,743.58
12 1 M3 BONGKARAN DINDING TEMBOK BATU TELA Rp. 771,961.08

II PEKERJAAN TANAH (SNI 2835 : 2008)


1 1 M3 GALIAN TANAH BIASA DALAM 1 METER Rp. 90,231.88
2 1 M3 GALIAN TANAH BIASA DALAM 2 METER Rp. 110,667.38
3 1 M3 GALIAN TANAH BIASA DALAM 3 METER Rp. 131,421.43
4 1 M3 GALIAN TANAH KERAS DALAM 1METER Rp. 120,096.80
5 1 M3 GALIAN TANAH CADAS DALAM 1 METER Rp. 182,056.50
6 1 M3 GALIAN TANAH LUMPUR DALAM 1 METER Rp. 145,167.38
7 1 M2 PEKERJAAN STRIPPING SETINGGI 1 METER Rp. 6,546.38
8 1 M3 PEMBUANGAN TANAH SEJAUH 15 METER Rp. 39,542.75
9 1 M3 URUGAN KEMBALI Rp. -
10 1 M3 PEMADATAN TANAH ( Per 20 Cm ) Rp. 65,463.75
11 1 M3 URUGAN PASIR Rp. 1,659,980.75
12 1 M3 PEMASANGAN LAPISAN IJUK TEBAL 10 CM Rp. 166,991.93
13 1 M3 URUGAN SIRTU PADAT Untuk Peninggian Lantai Bangunan Rp. 619,135.88
14 1 M3 URUGAN TANAH PILIHAN DIPADATKAN Rp. 513,536.55
15 1 M3 URUGAN LIMESTONE PADAT Rp. 383,792.40

III PEKERJAAN PONDASI (SNI 2836 : 2008)


1 1 M3 BATU KALI CAMP. 1 PC : 3 PS Rp. 2,364,752.10
2 1 M3 BATU KALI CAMP. 1 PC : 4 PS Rp. 2,320,978.54
3 1 M3 BATU KALI CAMP. 1 PC : 5 PS Rp. 2,290,361.49
4 1 M3 BATU KALI CAMP. 1 PC : 6 PS Rp. 2,268,966.51
5 1 M3 BATU KALI CAMP. 1 PC : 8 PS Rp. 2,239,333.06
6 1 M3 PASANGAN PONDASI SIKLOP, 40% BATU KALI Rp. 5,159,749.78
7 1 M3 PASANGAN PONDASI SUMURAN DIAMETER 1 M Rp. 2,494,292.85
8 1 M3 PASANGAN BATU KOSONG Rp. 1,675,570.19
NO URAIAN PEKERJAAN HARGA
1 2 3
IV PEKERJAAN DINDING (SNI 6897 : 2008)
1 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 2 PS Rp. 1,915,798.93
2 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 3 PS Rp. 1,906,030.85
3 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 4 PS Rp. 1,893,781.52
4 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 5 PS Rp. 1,895,795.41
5 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 6 PS Rp. 1,914,213.88
6 1 M2 PASANGAN BATU TELA TEBAL 1/2 TELA CAMP. 1 PC : 2 PS Rp. 948,649.82
7 1 M2 PASANGAN BATU TELA TEBAL 1/2 TELA CAMP. 1 PC : 3 PS Rp. 940,653.55
8 1 M2 PASANGAN BATU TELA TEBAL 1/2 TELA CAMP. 1 PC : 4 PS Rp. 938,006.52
9 1 M2 PASANGAN BATU TELA TEBAL 1/2 TELA CAMP. 1 PC : 5 PS Rp. 936,459.94
10 1 M2 PASANGAN BATU TELA TEBAL 1/2 TELA CAMP. 1 PC : 6 PS Rp. 938,694.79
11 1 M2 PASANGAN BATU TELA TEBAL 1/2 TELA CAMP. 1 PC : 8 PS Rp. 935,794.98
12 1 M2 PASANGAN DINDING HOLLOWBLOCK (HB. 10) Rp. 520,372.27
13 1 M2 PASANGAN DINDING HOLLOWBLOCK (HB. 10) TANPA BESI Rp. 482,508.33
14 1 M2 PASANGAN DINDING Terawang/Roster (12 x 11 x 24) CM Rp. 9,109,768.82
15 1 M2 PASANGAN DINDING BEDEG, RANGKA KAYU Rp. 103,992.63

V PEKERJAAN PLESTERAN (SNI 2837 : 2008)


1 1 M2 PLESTERAN CAMP. 1 PC : 1 PS TEBAL 15 MM Rp. 127,694.99
2 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 15 MM Rp. 123,074.93
3 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 15 MM Rp. 123,143.19
4 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 15 MM Rp. 121,483.42
5 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 15 MM Rp. 122,874.95
6 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 15 MM Rp. 123,009.87
7 1 M2 PLESTERAN CAMP. 1 PC : 8 PS TEBAL 15 MM Rp. 124,625.74
8 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 20 MM Rp. 165,061.66
9 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 20 MM Rp. 165,152.68
10 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 20 MM Rp. 162,296.44
11 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 20 MM Rp. 164,795.02
12 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 20 MM Rp. 164,331.71
13 1 M2 PLESTERAN SKONING 1 PC : 2 PS, TEBAL 10 MM Rp. 99,294.58
14 1 M2 PLESTERAN CIPRAT 1 PC : 2 PS Rp. 74,363.02
15 1 M2 FINISHING SIAR PASANGAN DINDING BATU TELA (=20 M') Rp. 37,714.91
16 1 M2 FINISHING SIAR PASANGAN DINDING CONBLOCK EKSPOSE (= 8 M') Rp. 18,033.45
17 1 M2 FINISHING SIAR PASANGAN BATUKALI/BELAH ADUKAN 1PC : 2 PS Rp. 98,561.66
18 1 M2 PEKERJAAN ACIAN Rp. 48,563.50
NO URAIAN PEKERJAAN HARGA
1 2 3
VI PEKERJAAN KAYU (SNI 3434 : 2008)
1 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS I (KA Rp. 10,094,693.42
2 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS II/III Rp. 6,956,205.99
3 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP STANDAR KAYU KELAS II (KAYU Rp. 331,977.37
4 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP SEDERHANA KAYU KELAS III (KA Rp. 322,755.29
5 MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU KELAS I/II (KAYU BESRp. 799,557.44
6 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA, KAYU KELAS I/II (K Rp. 835,676.33
7 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA JALUSI, KAYU KELAS I/II ( Rp. 896,461.45
8 MEMBUAT 1 M2 DAUN PINTU TEAKWOOD RANGKAP RANGKA TERTUTUP, KAYU
KELAS II (Lebar Sampai 90 Cm) Rp. 827,233.70
9 MEMBUAT 1 M2 DAUN PINTU TEAKWOOD RANGKAP RANGKA EXPOSE, KAYU
KELAS I/II Rp. 735,626.55
10 MEMASANG 1 M2 JALUSI KUSEN, KAYU KELAS I/II Rp. 705,600.12
11 MEMBUAT 1 M2 TEAKWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS I Rp. 735,626.55
12 MEMBUAT 1 M2 TEAKWOOD RANGKAP LAPIS FORMIKA RANGKA EXPOSE,
KAYU KELAS II Rp. 774,177.05
13 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KELAS
I,II,III Bentang 6 M' Rp. 8,484,341.04
14 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA EXPOSE, KAYU KELAS I Rp. 10,661,841.89
15 MEMASANG 1 M3 KONSTRUKSI GORDENG, KAYU KELAS II Rp. 4,633,033.08
16 MEMASANG 1 M2 RANGKA ATAP GENTENG KERAMIK, KAYU KELAS II Rp. 87,027.39
17 MEMASANG 1 M2 RANGKA ATAP GENTENG BETON, KAYU KELAS II Rp. 97,413.06
18 MEMASANG 1 M2 RANGKA ATAP SIRAP, KAYU KELAS II Rp. 516,481.06
19 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (50 X 100), KAYU KELAS II/III Rp. 128,815.72
20 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (60 X 60) CM, KAYU KELAS II/III Rp. 128,325.39
21 MEMASANG 1 M' LISPLANK UKURAN (3 X 20) CM, KAYU KELAS I/II Rp. 91,687.44
22 MEMASANG 1 M' LISPLANK UKURAN (3 X 30) CM, KAYU KELAS I/II Rp. 90,978.84
23 MEMASANG 1 M2 RANGKA DINDING PEMISAH (60 X 120) CM, KAYU KELAS II/III Rp. 171,086.54
MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA
24 KAYU KELAS II Rp. 297,491.18
MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD RANGKAP, RANGKA
25 KAYU KELAS II Rp. 308,985.91
26 MEMASANG 1 M2 LAMBRIZIRING DARI PAPAN KAYU KELAS I Rp. 399,842.18
27 MEMASANG 1 M2 LAMBRIZIRING DARI PLYWOOD UKURAN (120 X 240) CM Rp. 55,551.98
NO URAIAN PEKERJAAN HARGA
1 2 3
VII PEKERJAAN BETON ( SNI 7394:2008)
1 1 M3 MEMBUAT BETON 1 PC : 3 PS : 5 KR Rp. 2,995,701.32
2 1 M3 MEMBUAT BETON 1 PC : 2 PS : 4 KR Rp. 2,900,051.06
3 1 M3 MEMBUAT BETON 1 PC : 2 PS : 3 KR Rp. 3,048,301.01
4 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR Rp. 229,408.43
5 1 M2 PASANG BEKISTING UNTUK PONDASI Rp. 232,891.32
6 1 M2 PASANG BEKISTING UNTUK SLOOF Rp. 232,891.32
7 1 M2 PASANG BEKISTING UNTUK KOLOM Rp. 460,841.55
8 1 M2 PASANG BEKISTING UNTUK BALOK Rp. 469,496.27
9 1 M2 PASANG BEKISTING UNTUK LANTAI Rp. 632,853.39
10 1 M2 PASANG BEKISTING UNTUK DINDING Rp. 489,419.98
11 1 M2 PASANG BEKISTING UNTUK TANGGA Rp. 431,052.73
12 1 M2 PASANG JEMBATAN UNTUK PENGECORAN BETON Rp. 142,568.79
13 1 M3 MEMBUAT PONDASI BETON BERTULANG (150 KG BESI + BEKISTING) Rp. 7,821,535.67
14 1 M3 MEMBUAT SLOOF BETON BERTULANG (200 KG + BEKISTING) Rp. 9,241,409.37
15 1 M3 MEMBUAT KOLOM BETON BERTULANG (300 KG BESI + BEKISTING) Rp. 14,006,681.21
16 1 M3 MEMBUAT BALOK BETON BERTULANG (200 KG BESI + BEKISTING) Rp. 11,122,107.62
17 1 M3 MEMBUAT PLAT BETON BERTULANG (150 KG BESI + BEKISTING Rp. 10,467,261.86
18 1 M3 MEMBUAT DINDING BETON BERTULANG (150 KG BESI + BEKISTING) Rp. 9,988,448.81
19 1 M3 MEMBUAT DINDING BETON BERTULANG (200 KG BESI + BEKISTING) Rp. 10,570,922.56
20 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (11 X 11 CM) Rp. 131,543.65
21 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (10 X 15 CM) Rp. 185,151.22

VIII PEKERJAAN PENUTUP ATAP (SNI 03-3436-2002)


1 1 M2 PEKERJAAN ATAP GENTENG PLENTONG Rp. 110,897.44
2 1 M2 PEKERJAAN ATAP GENTENG PLENTONG DI CAT Rp. 105,710.02
3 1 M1 PASANG BUBUNGAN GENTENG PLENTONG Rp. 141,068.99
4 1 M2 PASANG ATAP GENTENG ASBES GELOMBANG 1.8 M X 0.92 M X 5 MM Rp. 61,629.52
5 1 M1 PASANG BUBUNGAN STEL GELOMBANG 0.92 M Rp. 1,277,569.13
6 1 M2 PEKERJAAN ATAP SIRAP Rp. 864,226.60
7 1 M2 PEKERJAAN ATAP NOK SIRAP Rp. 87,166.91
8 1 M2 PASANG ATAP ALANG-ALANG 3 M1 Rp. 51,281.65
9 1 M2 PEKERJAAN ATAP SENG GELOMBANG Rp. 91,325.05
10 1 M2 PASANGAN LAPISANG ALUMINIUM FOIL Rp. 63,392.52
11 1 M1 PASANG NOK SENG GELOMBANG Rp. 40,155.69

IX PEKERJAAN LANGIT - LANGIT (SNI 2839-2008)


1 MEMASANG 1 M2 LANGIT-LANGIT ETERNIT, TEBAL 4 MM, 5 MM DAN 6 MM Rp. 77,091.65
2 1 M2 PASANG LANGIT-LANGIT TRIPLEKS 120X240 CM/4MM Rp. 77,656.66
3 1 M2 PASANG LANGIT-LANGIT LAMBRIZIRING Rp. 290,233.70
4 1 M1 PASANG LIST LANGIT-LANGIT KAYU PROFIL Rp. 31,130.85
5 1 M2 PASANG LANGIT-LANGIT ASBES + RANGKA Rp. 172,226.57
6 1 M2 PASANG LANGIT-LANGIT GYPSUM BOARD UKURAN (1200X2400X9) MM Rp. 35,866.20
7 1 M2 PASANG LANGIT-LANGIT KALSIBOARD 4.5 MM Rp. 35,866.20
NO URAIAN PEKERJAAN HARGA
1 2 3
X PEKERJAAN SANITASI ( SNI 2002 )
1 MEMASANG 1 BUAH KLOSET DUDUK/MONOBLOK Rp. 3,502,057.35
2 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN Rp. 1,138,846.27
3 MEMASANG 1 BUAH URINOIR Rp. 1,603,550.52
4 MEMASANG 1 BUAH WASHTAFEL KIA Rp. 1,181,249.27
5 MEMASANG 1 BUAH BAK MANDI FIBREGLASS, VOLUME 0,30 M3 Rp. 1,177,123.95
6 MEMASANG 1 M1 PIPA GALVANIS f 0,5" - 1 " Rp. 25,248.83
7 MEMASANG 1 M1 PIPA GALVANIS f 1,5" - 3" Rp. 248,560.05
8 MEMASANG 1 M1 PIPA PVC TYPE AW f 0,5" - 1,5" Rp. 57,173.81
9 MEMASANG 1 M1 PIPA PVC TYPE AW f 2" Rp. 21,378.44
10 MEMASANG 1 M1 PIPA PVC TYPE AW f 3" - 4" Rp. 32,075.63
11 MEMASANG 1 BUAH KRAN f 0,75" ATAU 0,5" Rp. 77,683.25

XI PEKERJAAN BESI DAN ALUMINIUM (SNI 7393:2008)


1 1 KG PASANG RANGKA ATAP BAJA Rp. 34,166.14
2 1 M2 PASANG JENDELA NAKO Rp. 332,792.20
3 1 M1 PASANG TALANG DATAR, SENG BJLS 28 Rp. 164,211.63

XII PEKERJAAN KUNCI DAN KACA (SNI 2002)


1 1 BH PASANG KUNCI TANAM BIASA Rp. 280,898.98
2 1 PS PASANG ENGSEL PINTU Rp. 50,975.22
3 1 PS PASANG ENGSEL JENDELA KUPU-KUPU Rp. 59,455.84
4 1 BH PASANG KAIT ANGIN Rp. 50,975.22
5 1 BH PASANG KUNCI SLOT Rp. 68,992.16
6 1 M2 PASANG KACA, TEBAL 3 - 5 MM Rp. 265,835.62

XIII PEK. PENUTUP LANTAI DAN DINDING (SNI 7395:2008)


1 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM Rp. 250,376.60
2 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM Rp. 331,015.16
3 1 M1 PASANG PLIN KERAMIK 10 X 30 CM Rp. 33,739.95
4 1 M2 PASANG DINDING KERAMIK 20 X 20 CM Rp. 337,577.54
5 1 M1 PASANG PLIN KAYU 2 X 10 CM Rp. 52,867.55

XIV PEKERJAAN PENGECATAN (SNI 2002)


1 1 M2 PENGECATAN BIDANG KAYU BARU (1 LAPIS PLAMIR, Rp. 66,790.34
1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
2 1 M2 PENGECATAN BIDANG KAYU DENGAN VERNIS Rp. 63,764.72
3 1 M2 PENGECATAN TEMBOK BARU (1 LAPIS PLAMIR, Rp. 30,634.50
1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
4 1 M2 PENGECATAN TEMBOK LAMA (1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) Rp. 25,708.03
5 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI Rp. 40,052.91
6 1 M2 PENGECATAN PERMUKAAN BAJA, 1 LAPIS DENGAN CAT BESI Rp. 42,242.31
7 1 M2 PELABURAN BIDANG KAYU DENGAN POLITUR Rp. 68,764.24
NO URAIAN PEKERJAAN HARGA
1 2 3
XV PEKERJAAN TETEMPELAN STYLE BALI
1 1 M2 PASANGAN BATA GOSOK 2 MUKA Rp. 6,961,995.69
2 1 M2 PASANGAN PARAS KEROBOKAN 1 MUKA Rp. 212,465.50
3 1 M2 PASANGAN BATA GOSOK 1 MUKA Rp. 3,494,296.85
4 1 M2 PASANGAN PARAS 1 MUKA Rp. 202,650.75
5 1 M2 PASANGAN PARAS + BATA GOSOK 1 MUKA Rp. 3,496,750.53
6 1 M2 PASANGAN BATA GOSOK DIUKIR Rp. 3,685,134.85
7 1 M2 PASANGAN PARAS DIUKIR Rp. 393,488.75
8 1 M2 PASANGAN PARAS + BATA GOSOK DIUKIR Rp. 3,687,588.53

XVI PEKERJAAN LANDSCAPE


1 1 M2 PASANGAN PAVING BETON 10/20 CM TEBAL 6 CM K 225 Rp. 100,984.38
2 Paving 10 x 20 cm tebal 6 cm K350 Rp. 100,984.38
3 Paving 10 x 20 cm tebal 8 cm K225 Rp. 100,984.38
4 Paving 10 x 20 cm tebal 8 cm K350 Rp. 100,984.38
5 Paving 20 x 20 cm tebal 6 cm K225 Rp. 100,984.38
6 Paving 20 x 20 cm tebal 6 cm K350 Rp. 100,984.38
7 Paving 20 x 20 cm tebal 8 cm K225 Rp. 100,984.38
8 Paving 20 x 20 cm tebal 8 cm K350 Rp. 100,984.38
9 Paving 20 x 20 cm tebal 8 cm K425 Rp. 100,984.38
10 Paving 20 x 20 cm tebal 10 cm K225 Rp. 100,984.38
11 Paving 20 x 20 cm tebal 10 cm K350 Rp. 100,984.38
12 Paving 20 x 20 cm tebal 10 cm K425 Rp. 100,984.38
13 Paving Tiga Berlian tebal 6 cm K225 Rp. 100,984.38
14 1 M2 PASANGAN GRASS BLOCK Rp. 560,226.51
15 1 M2 PASANGAN KORAL SIKAT Rp. 406,337.45
16 1 M1 KANSTEIN BULAT (50 x 30 x 10 ) CM K225 Rp. 183,848.66
17 Kanstein Jumbo (P:50,L:15,T:30 cm K225) Rp. 472,018.55
18 Kanstein Segi Lima Jumbo (P:50,L:15, T:40 cm K225) Rp. 472,018.55
19 1 M2 PENGECATAN KANSTEIN Rp. 56,293.92

XVII PEKERJAAN ELEKTRIKAL


1 1 TITIK INSTALASI STOP KONTAK, LAMPU, EXHAUST FAN DAN CEILING FAN Rp. 507,345.00
2 1 TITIK INSTALASI AC Rp. 647,160.04
3 1 TITIK INSTALASI TELEPHONE Rp. 716,044.68
4 1 TITIK INSTALASI MATV Rp. 618,009.96

Fakfak, 16 Agustus 2012


Panitia Penyusunan Standard Harga Satuan
Tahun 2013
Ketua,
Sekretaris,

Ir. ARIEF HARTADI, MT


LIZA NEIRASARI, ST NIP. 19640121 199403 1 004
NIP. 19751016 200111 2 001

Mengetahui,
Kepala Dinas Pekerjaan Umum
Kabupaten Fakfak ,

SAMAUN DAHLAN, S.Sos, MAP


NIP. 19681005 199108 1 002
R A B
PEMBANGUNAN RUMAH T.70
Lokasi : Kampung Homorkokma Distrik Kramamongga

Harga Satuan Jumlah Harga


No Uraian pekerjaan Sat Volume
(Rp) (Rp)
I. Pekerjaan Pendahuluan
1 Pengukuran/pas.bouwplak M' 49.00 80,172.68 3,928,461.31
2 Papan nama proyek Bh 1.00 1,000,000.00 1,000,000.00
3 Pembersihan lokasi M2 100.00 19,463.75 1,946,375.00
4 Barak Kerja M2 12.00 1,437,644.01 17,251,728.15
24,126,564.46
II. Pekerjaan Tanah
1 Galian tanah/batu pondasi M3 32.63 120,096.80 3,918,758.58
2 Urugan tanah kembali M3 10.88 40,032.27 435,417.62
3 Timbunan tanah bawah lantai M3 31.20 513,536.55 16,022,340.36
4 Urugan pasir bawah lantai t=7 cm M3 3.90 1,659,980.75 6,473,924.93
26,850,441.49
III. Pekerjaan Pasangan
1 Pas. Batu kosong M3 8.70 1,675,570.19 14,577,460.61
2 Pasang pondasi batu belah 1:4 M3 38.32 2,320,978.54 88,948,717.37
3 Sloef beton tanpa tulang 1:2:3, 20/25 M3 3.55 3,048,301.01 10,816,896.13
4 Pas. Dinding coor 1:4 M3 13.79 938,006.52 12,935,109.93
5 Plester dinding 1:4 M2 275.80 121,483.42 33,505,126.63
6 Coor lantai beton tumbuk 1:3:5, t=7 cm di- M3 7.80 2,995,701.32 23,366,470.32
plester 1:3 dan difloor -
7 Keramik lantai 30x30 M2 78.00 250,376.60 19,529,374.41
8 Coor bak air 75x50x50 Bh 1.00 1,177,123.95 1,177,123.95
9 Closet jongkok porcelen Bh 1.00 1,138,846.27 1,138,846.27
10 Coor beton tulang plat dapur M3 0.02 10,467,261.86 209,345.24
11 Septictank + rembesan Bh 1.00 9,469,302.09 9,469,302.09
215,673,772.96
IV. Pekerjaan Kayu
1 Tiang ky. Besi 10/10 M3 0.63 4,768,150.00 3,003,934.50
2 Mirplat ky. Besi 10/10 M3 0.70 4,768,150.00 3,337,705.00
3 Kosen pintu/jendela/regel ky. Besi 5/10 M3 0.90 10,094,693.42 9,085,224.08
4 Kuda -kuda + pengapit + skoor ky. Besi 5/10 M3 0.88 8,484,341.04 7,466,220.12
5 Gording ky. Matoa 5/10 M3 1.14 4,633,033.08 5,281,657.72
6 Plafond tripleks 4 mm + rangka M2 109.09 128,815.72 14,052,506.45
7 Jalusi datar papan kayu besi M2 5.94 705,600.12 4,191,264.69
8 Listplank papan ky. Besi 2,5/30 M1 105.60 91,687.44 9,682,193.74
9 Papan gewel kayu matoa M2 18.31 171,086.54 3,132,594.47
10 Pintu panil kayu besi M2 9.45 799,557.44 7,555,817.79
11 Pintu double tripleks kayu besi lapis seng plat M2 1.68 774,177.05 1,300,617.45
12 Jendela split M2 0.32 835,676.33 267,416.43
13 Jendela kaca mati (1,2x0,4) M2 0.48 835,676.33 401,124.64
14 Jendela kaca mati (1,9x0,4) M2 0.76 835,676.33 635,114.01
15 Jendela kaca jungkit (1,9x0,7) M2 2.66 835,676.33 2,222,899.05
16 Jendela nako 8 klips Zet 12.00 483,098.00 5,797,176.00
77,413,466.13
V. Pekerjaan Atap
1 Atap seng gelombang Bjls 0,30 M2 126.50 91,325.05 11,552,619.03
2 Bubungan seng plat Bjls 0,30 M' 16.00 40,155.69 642,491.03
12,195,110.05
VI. Pekerjaan Pengecatan
1 Cat kilap kayu M2 61.60 66,790.34 4,114,284.82
2 Sigmatex plafond baru 3x M2 109.09 30,634.50 3,341,917.92
3 Sigmatex dinding baru 3x M2 275.97 30,634.50 8,454,203.77
15,910,406.51
1 2 3 4 5 6
VII. Pekerjaan Instalasi
1 Pasang lampu TL 40 Watt Bh 6.00 554,959.00 3,329,754.00
2 Pasang lampu pijar 25 Watt Bh 3.00 550,347.96 1,651,043.88
3 Zekering kast 1 group otomatis Bh 1.00 531,903.80 531,903.80
4 Pasang saklar tunggal Bh 5.00 524,987.24 2,624,936.20
5 Pasang saklar ganda Bh 2.00 524,987.24 1,049,974.48
6 Pasang stop kontak Bh 6.00 522,681.72 3,136,090.32
7 Penyambungan listrik Ls 1.00 2,500,000.00 2,500,000.00
8 Instalasi air Ls 1.00 2,000,000.00 2,000,000.00
9 Dokumentasi (0%,50%,100%) Ls 1.00 1,000,000.00 1,000,000.00
17,823,702.68

REKAPITULASI

I Pekerjaan Pendahuluan ………………… Rp 24,126,564.46


II Pekerjaan Tanah ………………… Rp 26,850,441.49
III Pekerjaan Pasangan ………………… Rp 215,673,772.96
IV Pekerjaan Kayu ………………… Rp 77,413,466.13
V Pekerjaan Atap ………………… Rp 12,195,110.05
VI Pekerjaan Pengecatan ………………… Rp 15,910,406.51
VII Pekerjaan Instalasi ………………… Rp 17,823,702.68
Real Cost Rp 389,993,464.28
Di Bulatkan Rp 389,993,000.00
Harga Bangunan per M2 Kons. Rangka Kayu Besi Rp 5,571,328.57
R A B
PEMBANGUNAN RUMAH T.70
Lokasi : Kampung Homorkokma Distrik Kramamongga

Harga Satuan
No Uraian pekerjaan Sat Volume
(Rp)
I. Pekerjaan Pendahuluan
1 Pengukuran/pas.bouwplak M' 49.00 80,172.68
2 Papan nama proyek Bh 1.00 1,000,000.00
3 Pembersihan lokasi M2 100.00 19,463.75
4 Barak Kerja M2 12.00 1,437,644.01

II. Pekerjaan Tanah


1 Galian tanah/batu pondasi M3 32.63 120,096.80
2 Urugan tanah kembali M3 10.88 40,032.27
3 Timbunan tanah bawah lantai M3 31.20 513,536.55
4 Urugan pasir bawah lantai t=7 cm M3 3.90 1,659,980.75

III.Pekerjaan Pasangan
1 Pas. Batu kosong M3 8.70 1,675,570.19
2 Pasang pondasi batu belah 1:4 M3 38.32 2,320,978.54
3 Sloef beton tulang 1:2:3, 20/25 M3 3.55 9,241,409.37
4 Pas. Dinding coor 1:4 M3 13.79 938,006.52
5 Plester dinding 1:4 M2 275.80 121,483.42
6 Coor lantai beton tumbuk 1:3:5, t=7 cm di- M3 7.80 2,995,701.32
plester 1:3 dan difloor
7 Keramik lantai 30x30 M2 78.00 250,376.60
8 Coor bak air 75x50x50 Bh 1.00 1,177,123.95
9 Closet jongkok porcelen Bh 1.00 1,138,846.27
10 Coor beton tulang plat dapur M3 0.02 10,467,261.86
11 Septictank + rembesan Bh 1.00 9,469,302.09

IV. Pekerjaan Kayu


1 Kolom beton tulang 10/10 M3 0.63 14,006,681.21
2 Ringbalk beton tulang 10/10 M3 0.70 11,122,107.62
3 Kosen pintu/jendela/regel ky. Besi 5/10 M3 0.90 10,094,693.42
4 Kuda -kuda + pengapit + skoor ky. Besi 5/10 M3 0.88 8,484,341.04
5 Gording ky. Matoa 5/10 M3 1.14 4,633,033.08
6 Plafond tripleks 4 mm + rangka M2 109.09 128,815.72
7 Jalusi datar papan kayu besi M2 5.94 705,600.12
8 Listplank papan ky. Besi 2,5/30 M1 105.60 91,687.44
9 Papan gewel kayu matoa M2 18.31 171,086.54
10 Pintu panil kayu besi M2 9.45 799,557.44
11 Pintu double tripleks kayu besi lapis seng plat M2 1.68 774,177.05
12 Jendela split M2 0.32 835,676.33
13 Jendela kaca mati (1,2x0,4) M2 0.48 835,676.33
14 Jendela kaca mati (1,9x0,4) M2 0.76 835,676.33
15 Jendela kaca jungkit (1,9x0,7) M2 2.66 835,676.33
16 Jendela nako 8 klips Zet 12.00 483,098.00

V. Pekerjaan Atap
1 Atap seng gelombang Bjls 0,30 M2 126.50 91,325.05
2 Bubungan seng plat Bjls 0,30 M' 16.00 40,155.69

VI. Pekerjaan Pengecatan


1 Cat kilap kayu M2 61.60 66,790.34
2 Sigmatex plafond baru 3x M2 109.09 30,634.50
3 Sigmatex dinding baru 3x M2 275.97 30,634.50

1 2 3 4 5
VII. Pekerjaan Instalasi
1 Pasang lampu TL 40 Watt Bh 6.00 554,959.00
2 Pasang lampu pijar 25 Watt Bh 3.00 550,347.96
3 Zekering kast 1 group otomatis Bh 1.00 531,903.80
4 Pasang saklar tunggal Bh 5.00 524,987.24
5 Pasang saklar ganda Bh 2.00 524,987.24
6 Pasang stop kontak Bh 6.00 522,681.72
7 Penyambungan listrik Ls 1.00 2,500,000.00
8 Instalasi air Ls 1.00 2,000,000.00
9 Dokumentasi (0%,50%,100%) Ls 1.00 1,000,000.00

REKAPITULASI

I Pekerjaan Pendahuluan ………………… Rp


II Pekerjaan Tanah ………………… Rp
III Pekerjaan Pasangan ………………… Rp
IV Pekerjaan Kayu ………………… Rp
V Pekerjaan Atap ………………… Rp
VI Pekerjaan Pengecatan ………………… Rp
VII Pekerjaan Instalasi ………………… Rp
Real Cost Rp
Di Bulatkan Rp
Harga Bangunan per M2 Kons. Beton Bertulang Rp
ga

Jumlah Harga
(Rp)

3,928,461.31
1,000,000.00
1,946,375.00
17,251,728.15
24,126,564.46

3,918,758.58
435,417.62
16,022,340.36
6,473,924.93
26,850,441.49

14,577,460.61
88,948,717.37
32,793,141.14
12,935,109.93
33,505,126.63
23,366,470.32
-
19,529,374.41
1,177,123.95
1,138,846.27
209,345.24
9,469,302.09
237,650,017.96

8,824,209.16
7,785,475.33
9,085,224.08
7,466,220.12
5,281,657.72
14,052,506.45
4,191,264.69
9,682,193.74
3,132,594.47
7,555,817.79
1,300,617.45
267,416.43
401,124.64
635,114.01
2,222,899.05
5,797,176.00
87,681,511.13

11,552,619.03
642,491.03
12,195,110.05

4,114,284.82
3,341,917.92
8,454,203.77
15,910,406.51

3,329,754.00
1,651,043.88
531,903.80
2,624,936.20
1,049,974.48
3,136,090.32
2,500,000.00
2,000,000.00
1,000,000.00
17,823,702.68

24,126,564.46
26,850,441.49
237,650,017.96
87,681,511.13
12,195,110.05
15,910,406.51
17,823,702.68
422,237,754.28
422,237,000.00
6,031,957.14
44.04

275.80
37.6
6.8
4.42 275.80
6.15
5.7
2.15
3.15
5
70.97 4.435625
0.9
10.08
RAB
PEMBANGUNAN PASAR EKS KIOS LAMA THUMBURUNI
KONSTRUKSI BETON TULANG BERLANTAI
LOKASI : FAKFAK KOTA
Harga Satuan Jumlah Harga
No URAIAN KEGIATAN Sat Volume
(Rp) (Rp)
1 2 3 4 5 6
I. PEKERJAAN PENDAHULUAN
1 Dokumentasi 0%,50%,100% LS 1.00 1,000,000.00 1,000,000.00
2 Pasang bouwplank M' 128.00 80,172.68 10,262,103.01
3 Papan nama proyek Bh 1.00 1,000,000.00 1,000,000.00
4 Barak Kerja M2 12.00 1,437,644.01 17,251,728.15
29,513,831.16
II. PEKERJAAN TANAH
1 Galian pondasi berbatu M3 150.21 120,096.80 18,039,740.33
2 Urugan tanah kembali M3 50.07 40,032.27 2,004,415.59
3 Timbunan tanah bawah lantai M3 123.20 513,536.55 63,267,702.96
4 Urugan pasir M3 15.40 1,659,980.75 25,563,703.55
108,875,562.43
III. Pekerjaan Pasangan
1 Pasang pondasi batu belah 1:4 M3 98.80 2,320,978.54 229,312,679.75
2 Pasang talud batu belah 1:4 M3 24.00 2,320,978.54 55,703,484.96
3 Pasang batu saluran 1:4 M3 9.00 2,320,978.54 20,888,806.86
4 Cor lantai kerja t=10 cm M3 6.22 2,995,701.32 18,633,262.23
5 Pasang poer beton tulang 1:2:3 (1x1x0.4) M3 14.40 7,821,535.67 112,630,113.65
6 Sloof beton tulang 1:2:3, 20/30 (arah X) M3 4.44 9,241,409.37 41,031,857.59
7 Sloof beton tulang 1:2:3, 20/30 (arah Y) M3 5.33 9,241,409.37 49,256,711.93
8 Sloof beton tulang 1:2:3,15/20 (arah X) M3 1.03 9,241,409.37 9,518,651.65
9 Sloof beton tulang 1:2:3,15/20 (arah Y) M3 2.28 9,241,409.37 21,070,413.36
10 Kolom beton tulang 1:2:3, 30/30 ( X,Y) M3 28.84 14,006,681.21 403,952,686.16
11 Kolom beton tulang 1:2:3, 20/20 (Teras Lt 1) M3 3.60 14,006,681.21 50,424,052.36
12 Kolom beton tulang 1:2:3, 20/20 (Teras Lt 2) M3 1.70 14,006,681.21 23,811,358.06
13 Balok beton tulang 1:2:3, 25/35 (Arah X)LT 2 M3 4.63 11,122,107.62 51,495,358.28
14 Balok beton tulang 1:2:3, 25/35 (Arah Y)LT 2 M3 5.55 11,122,107.62 61,727,697.29
15 Balok beton tulang 1:2:3, 15/25 (Arah X)LT 2 M3 0.84 11,122,107.62 9,342,570.40
16 Balok beton tulang 1:2:3, 15/25 (Arah Y)LT 2 M3 2.05 11,122,107.62 22,800,320.62
17 Ringbalk plat atap beton tulang 1:2:3, 15/20 (Arah X) M3 0.44 11,122,107.62 4,893,727.35
18 Ringbalk plat atap beton tulang 1:2:3, 15/20 (Arah Y) M3 0.66 11,122,107.62 7,340,591.03
19 Cor lantai beton tulang 1:2:3, T=10CM (LT 2) M3 47.16 10,467,261.86 493,636,069.37
20 Kolom praktis beton tulang 1:2:3, 10/10 (LT 2) M3 1.60 14,006,681.21 22,410,689.94
21 Cor plat atap beton tulang 1:2:3, T=9 cm M3 8.03 10,467,261.86 84,052,112.74
22 Listplankbeton plat atap t=10 cm M3 2.40 10,467,261.86 25,121,428.47
23 Kuda -kuda beton tulang 10/10 M3 1.12 10,467,261.86 11,723,333.28
24 Talang beton T= 10CM ( depan dan belakang) M3 6.00 10,467,261.86 62,803,571.17
25 Canopi beton atap (depan + belakang) t= 10 cm M3 1.73 10,467,261.86 18,108,363.02
26 Canopi ventilasi depan t= 10 cm M3 2.10 10,467,261.86 21,981,249.91
27 Canopi jendela t 5 mm M3 0.79 10,467,261.86 8,269,136.87
28 Kolom pagar beton bertulang 15/15 M3 0.41 14,006,681.21 5,742,739.30
29 Sloofpagar beton bertulang 15/20 M3 0.55 9,241,409.37 5,082,775.15
30 Coor lantai tumbuk 1:3:6, t=7 cm M3 30.80 2,995,701.32 92,267,600.75
31 Keramik lantai 30/30 M2 778.00 250,376.60 194,792,990.91
32 Pasang kaca blok M2 10.00 9,109,768.82 91,097,688.20
33 Pas batu cetak 1:4 LT1 M3 35.57 938,006.52 33,364,891.97
34 Pas batu cetak 1:4 LT2 M3 38.46 938,006.52 36,075,730.82
35 Plester dinding 1:4 M2 2,000.64 121,483.42 243,044,584.99
36 Plester dinding 1:2 M2 225.64 123,074.93 27,770,626.82
37 Acian dinding M2 2,226.28 48,563.50 108,115,940.43
2,779,295,867.63
1 2 3 4 5 6
IV. Pekerjaan KAYU/ALUMINIUM/PAGAR
1 Kusen Kayu besi 5/10 M3 1.07 10,094,693.42 10,760,943.19
2 Kusen kayu besi 5/10 M3 0.42 10,094,693.42 4,239,771.24
3 Gording kayu matoa 5/10 M3 2.00 4,633,033.08 9,266,066.17
4 Kasau 5/5 M3 0.80 4,633,033.08 3,706,426.47
5 Reng 2/3 M3 0.67 4,633,033.08 3,104,132.17
6 Plafond tripleks 3 mm M2 840.00 128,815.72 108,205,201.34
7 Jendela kaca riben M2 46.30 835,676.33 38,691,814.26
8 Jendela panil kaca riben (1,2x0,7) M2 16.80 835,676.33 14,039,362.41
9 Pintu toko (lipat dan besi) M2 175.00 1,100,000.00 192,500,000.00
10 Pagar BRC t= 1,2 m' Panil 26.00 554,808.35 14,425,017.15
11 Tiang BRC Bh 27.00 180,578.48 4,875,618.90
403,814,353.28
V. Pekerjaan Atap
1 Atap multiroof M2 344.00 153,237.55 52,713,717.20
2 Bubungan multiroof M' 40.00 467,214.87 18,688,594.64
71,402,311.84
VI. Pekerjaan Pengecatan
1 Sigmatex dinding baru 3x M2 2,226.28 30,634.50 68,200,981.12
2 Cat plafond M2 840.00 66,790.34 56,103,883.92
124,304,865.04
VII Pekerjaan Instalasi
1 Penyambungan listrik 900 watt Pkt 20.00 1,000,000.00 20,000,000.00
2 Pipa air hujan 3" M' 139.20 32,075.63 4,464,927.35
3 Pasang lampu XL 8 Watt Ttk 80.00 554,959.00 44,396,720.00
4 Pas. Saklar ganda Ttk 40.00 524,987.24 20,999,489.60
5 Pas. Stop kontak Ttk 40.00 522,681.72 20,907,268.80
6 Pas. Sekring kast Group 20.00 531,903.80 10,638,076.00
121,406,481.75

REKAPITULASI
I PEKERJAAN PENDAHULUAN Rp. 29,513,831.16
II PEKERJAAN TANAH Rp. 108,875,562.43
III Pekerjaan Pasangan Rp. 2,779,295,867.63
IV Pekerjaan KAYU/ALUMINIUM/PAGAR Rp. 403,814,353.28
V Pekerjaan Atap Rp. 71,402,311.84
VI Pekerjaan Pengecatan Rp. 124,304,865.04
VII Pekerjaan Instalasi Rp. 121,406,481.75
JUMLAH Rp 3,638,613,273.13
DIBULATKAN Rp 3,638,613,000.00

Harga Bangunan per M2 Kons. Beton tulang berlantai Rp 5,906,839.29


TYPE 640 M2 Rp 5,906,000.00
PEMERINTAH KABUPATEN FAKFAK
DINAS PU, PENATAAN RUANG, PERUMAHAN RAKYAT
DAN KAWASAN PERMUKIMAN
Jl. Achmad Yani No. 08 Fakfak, Telp. (0956) 22320 - 22709

HARGA SATUAN PER M2


PEMBANGUNAN BANGUNAN GEDUNG DAN RUMAH NEGARA
TAHUN ANGGARAN 2018 DI DISTRIK FAKFAK KABUPATEN FAKFAK

Untuk Tahun Anggaran 2018 Triwulan ke - I, Dinas Pekerjaan Umum menetapkan harga satuan
per meter persegi untuk pembangunan gedung dan rumah dinas sebagai berikut:

1 Bang. Gedung/Rumah Konstruksi Rangka Beton Bertulang Rp 6,031,957.14


2 Bang. Gedung/Rumah Konstruksi Rangka Beton Bertulang Rp 5,906,000.00
Bertingkat
2 Bang. Gedung/Rumah Konstruksi Rangka Rp 5,571,328.57
Kayu Besi

Dengan dasar perhitungan =

I Harga material didapat dari beberapa toko material di Fakfak, ditambahkan dengan
biaya pikul, biaya transport, dan keuntungan/overhead ( 15% )
II Upah tenaga berdasarkan UMP Prop. Papua Barat Sektor Konstruksi = Rp.2.875.000,- per bulan.
dan hasil survey/wawancara bersama pekerja di lokasi proyek.
III Analisa harga satuan pekerjaan menggunakan analisa SNI, kecuali untuk yang tidak ada dalam
SNI masih mengacu pada BOW
IV Analisa/asumsi bangunan sebagai berikut
- Pondasi tinggi rata2 1,00 m s/d 1.50 m
- Timbunan menggunakan tanah+batu
- Galian tanah berbatu
- Rangka bangunan dengan kayu besi dan beton bertulang
- Lantai beton tumbuk

Fakfak, 12 Februari 2018


PANITIA PENYUSUNAN STANDARD HARGA SATUAN TAHUN 2018

Sekretaris, Ketua,

RIZAL MINGGELE, ST LIZA NEIRASARI, ST


NIP. 19820701 200909 1 001 NIP. 19751016 200111 2 001

Mengetahui,
Kepala Dinas PU, Penataan Ruang, Perumahan Rakyat
dan Kawasan Permukiman
Kabupaten Fakfak ,

TTD

SAMAUN DAHLAN S.Sos, MAP


NIP. 19681005 199108 1 002
DAFTAR ANALISA PEKERJAAN SWAKLOLA
TAHUN 2018
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN (SNI 03-2835-2002)
1 1 M1 PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2
METER
1.2500 btg Bambu Sedang 15,000.00 18,750.00
2.5000 kg Semen Portland 1,875.00 4,687.50
1.2000 lbr Seng gelombang 3" - 5" 65,000.00 78,000.00
0.0050 m3 Pasir Beton 1,500,000.00 7,500.00
0.0090 m3 Koral beton 1,062,500.00 9,562.50
0.0720 m3 Kayu Meranti Usuk 5/7 - -
0.0600 kg Paku biasa 2" - 5" 20,000.00 1,200.00
0.4500 kg Meni Besi 25,000.00 11,250.00
0.2000 oh Tukang Kayu 148,350.00 29,670.00
0.4000 oh Pekerja 115,000.00 46,000.00
Total : 75,670.00 130,950.00 206,620.00

2 1 M1 PENGUKURAN DAN PEMASANGAN BOWPLANK


0.0120 m3 Kayu Usuk Meranti 5/7 - -
0.0200 kg Paku Biasa 2" - 5" 20,000.00 400.00
0.0070 m3 Kayu Papan Meranti 3/20 - -
0.1000 oh Tukang Kayu 148,350.00 14,835.00
0.1000 oh Pekerja 115,000.00 11,500.00
Total : 26,335.00 400.00 26,735.00

3 1 M2 PEMBUATAN KANTOR SEMENTARA, DENGAN LANTAI


PLESTERAN
1.2500 btg Dolken Kayu Ø 8 - 10/4m 36,000.00 45,000.00
0.1800 m3 Kayu Meranti - -
0.8500 kg Paku Biasa 2" - 5" 20,000.00 17,000.00
1.1000 kg Besi Strip 7,260.00 7,986.00
35.0000 kg Semen Portland 1,875.00 65,625.00
0.1500 m3 Pasir Pasang 1,000,000.00 150,000.00
0.1000 m3 Pasir Beton 1,500,000.00 150,000.00
0.1500 m3 Koral Beton 1,062,500.00 159,375.00
30.0000 bh Bata Merah 8,000.00 240,000.00
0.2500 lbr Seng Plat 22,000.00 5,500.00
2.0000 bh Jendela Nako 21,000.00 42,000.00
0.0800 m2 Kaca Polos 187,506.70 15,000.54
0.1500 bh Kunci Tanam 175,000.00 26,250.00
0.0600 lbr Plywood 4 mm 225,000.00 13,500.00
2.0000 oh Tukang Kayu 148,350.00 296,700.00
1.0000 oh Tukang Batu 142,600.00 142,600.00
2.0000 oh Pekerja 115,000.00 230,000.00
Total : 669,300.00 937,236.54 1,606,536.54

4 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT


1.7000 btg Bambu Sedang 15,000.00 25,500.00
0.2100 m3 Kayu Meranti - -
0.3000 kg Paku Biasa 2" - 5" 20,000.00 6,000.00
10.5000 kg Semen Portland 1,875.00 19,687.50
0.0300 m3 Pasir Beton 1,500,000.00 45,000.00
0.0500 m3 Koral Beton 1,062,500.00 53,125.00
1.5000 lbr Seng gelombang BJLS 28 - -
2.0000 oh Tukang Kayu 148,350.00 296,700.00
1.0000 oh Pekerja 115,000.00 115,000.00
Total : 411,700.00 149,312.50 561,012.50

5 1 M2 PEMBUATAN RUMAH JAGA/KONSTRUKSI KAYU


3.0000 btg Bambu Sedang 15,000.00 45,000.00
0.2760 m3 Kayu Meranti - -
0.7000 kg Paku biasa 2" - 5" 20,000.00 14,000.00
1.5000 lbr Seng gelombang BJLS 28 - -
1.5000 oh Tukang Kayu 148,350.00 222,525.00
1.0000 oh Pekerja 115,000.00 115,000.00
Total : 337,525.00 59,000.00 396,525.00

6 1 M2 MEMBERSIHKAN LAPANGAN DAN PERATAAN


0.1000 oh Pekerja 115,000.00 11,500.00
Total : 11,500.00 11,500.00

7 1 M2 PEMBUATAN BEDENG BURUH


1.2500 btg Bambu Sedang 15,000.00 18,750.00
0.1860 m3 Kayu Meranti - -
0.3000 kg Paku Biasa 2" - 5" 20,000.00 6,000.00
18.0000 kg Semen Portland 1,875.00 33,750.00
0.0300 m3 Pasir Beton 1,500,000.00 45,000.00
0.0500 m3 Koral Beton 1,062,500.00 53,125.00
1.5000 lbr Seng gelombang BJLS 28 - -
1.3500 lbr Plywood 4 mm 225,000.00 303,750.00
2.0000 oh Tukang Kayu 148,350.00 296,700.00
1.0000 oh Pekerja 115,000.00 115,000.00
Total : 411,700.00 460,375.00 872,075.00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

8 1 M2 PEMBUATAN BAK ADUKAN UKURAN (40X50X20) CM


0.0360 m3 Kayu Terentang - -
0.0800 kg Paku Biasa 2" - 5" 20,000.00 1,600.00
1.0000 btg Kaso 5/7 - -
0.3000 oh Tukang kayu 148,350.00 44,505.00
Total : 44,505.00 1,600.00 46,105.00

9 1 M2 PEMBUATAN STEGGER DARI BAMBU


1.0000 btg Bambu 10,000.00 10,000.00
0.2500 kg Tali Ijuk 47,000.00 11,750.00
0.0170 oh Tukang Kayu 148,350.00 2,521.95
0.0020 oh Pekerja 115,000.00 230.00
2,751.95 21,750.00 24,501.95

10 1 M2 PEMBUATAN JALAN SEMENTARA


0.1500 m3 Batu Kali / Batu Bulat 15/20 500,000.00 75,000.00
0.0900 m3 Batu Pecah 5 - 7 #REF! #REF!
0.0100 m3 Pasir Pasang 1,000,000.00 10,000.00
1.0000 oh Pekerja 115,000.00 115,000.00
Total : 115,000.00 #REF! #REF!

11 1 M3 BONGKARAN BETON BERTULANG


6.6670 oh Pekerja 115,000.00 766,705.00
Total : 766,705.00 766,705.00

12 1 M3 BONGKARAN DINDING TEMBOK BATA MERAH


6.6670 oh Pekerja 115,000.00 766,705.00
Total : 766,705.00 766,705.00

II PEKERJAAN TANAH (SNI 2835 : 2008)

1 1 M3 GALIAN TANAH BIASA DALAM 1 METER


0.7500 oh Pekerja 115,000.00 86,250.00
Total : 86,250.00 86,250.00
2 1 M3 GALIAN TANAH BIASA DALAM 2 METER
0.9000 oh Pekerja 115,000.00 103,500.00
Total : 103,500.00 103,500.00

3 1 M3 GALIAN TANAH BIASA DALAM 3 METER


1.0500 oh Pekerja 115,000.00 120,750.00
Total : 120,750.00 120,750.00

4 1 M3 GALIAN TANAH KERAS DALAM 1METER


1.0000 oh Pekerja 115,000.00 115,000.00
Total : 115,000.00 115,000.00

5 1 M3 GALIAN TANAH CADAS DALAM 1 METER


1.5000 oh Pekerja 115,000.00 172,500.00
Total : 172,500.00 172,500.00

6 1 M3 GALIAN TANAH LUMPUR DALAM 1 METER


1.2000 oh Pekerja 115,000.00 138,000.00
Total : 138,000.00 138,000.00

7 1 M2 PEKERJAAN STRIPPING SETINGGI 1 METER


0.0500 oh Pekerja 115,000.00 5,750.00
Total : 5,750.00 5,750.00

8 1 M3 PEMBUANGAN TANAH SEJAUH 15 METER


0.3300 oh Pekerja 115,000.00 37,950.00
Total : 37,950.00 37,950.00

9 1 M3 URUGAN KEMBALI
Mengurug Kembali 1 m3 galian dihitung dari 1/3 kali dari indeks pekerjaan galian

10 1 M3 PEMADATAN TANAH ( Per 20 Cm )


0.5000 oh Pekerja 115,000.00 57,500.00
Total : 57,500.00 57,500.00

11 1 M3 URUGAN PASIR
1.2000 m3 Pasir Urug 500,000.00 600,000.00
0.3000 oh Pekerja 115,000.00 34,500.00
Total : 34,500.00 600,000.00 634,500.00

12 1 M3 PEMASANGAN LAPISAN IJUK TEBAL 10 CM


6.0000 m3 Ijuk 20,000.00 120,000.00
0.1500 oh Pekerja 115,000.00 17,250.00
Total : 17,250.00 120,000.00 137,250.00

13 1 M3 URUGAN SIRTU PADAT Untuk Peninggian Lantai Bangunan


1.2000 m3 Sirtu 250,000.00 300,000.00
0.2500 oh Pekerja 115,000.00 28,750.00
Total : 28,750.00 300,000.00 328,750.00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
14 1 M3 URUGAN TANAH PILIHAN DIPADATKAN
1.2000 m3 Tanah Urug 150,000.00 180,000.00
0.5000 oh Pekerja 115,000.00 57,500.00
Total : 57,500.00 180,000.00 237,500.00

14 1 M3 URUGAN LIMESTONE PADAT


1.2000 m3 Limestone 79,000.00 94,800.00
0.2500 oh Pekerja 115,000.00 28,750.00
Total : 28,750.00 94,800.00 123,550.00

III PEKERJAAN PONDASI (SNI 2836 : 2008)

1 1 M3 BATU KALI CAMP. 1 PC : 3 PS


1.2000 m3 Batu Kali / Batu Bulat 15/20 500,000.00 600,000.00
202.0000 kg Semen Portland 1,875.00 378,750.00
0.4850 m3 Pasir Pasang 1,000,000.00 485,000.00
1.5000 oh Pekerja 115,000.00 172,500.00
0.7500 oh Tukang Batu 142,600.00 106,950.00
Total : 279,450.00 1,463,750.00 1,743,200.00

2 1 M3 BATU KALI CAMP. 1 PC : 4 PS


1.2000 m3 Batu Kali / Batu Bulat 15/20 500,000.00 600,000.00
163.0000 kg Semen Portland 1,875.00 305,625.00
0.5200 m3 Pasir Pasang 1,000,000.00 520,000.00
1.5000 oh Pekerja 115,000.00 172,500.00
0.7500 oh Tukang Batu 142,600.00 106,950.00
Total : 279,450.00 1,425,625.00 1,705,075.00

3 1 M3 BATU KALI CAMP. 1 PC : 5 PS


1.2000 m3 Batu Kali / Batu Bulat 15/20 500,000.00 600,000.00
136.0000 kg Semen Portland 1,875.00 255,000.00
0.5440 m3 Pasir Pasang 1,000,000.00 544,000.00
1.5000 oh Pekerja 115,000.00 172,500.00
0.7500 oh Tukang Batu 142,600.00 106,950.00
Total : 279,450.00 1,399,000.00 1,678,450.00

4 1 M3 BATU KALI CAMP. 1 PC : 6 PS


1.2000 m3 Batu Kali / Batu Bulat 15/20 500,000.00 600,000.00
117.0000 kg Semen Portland 1,875.00 219,375.00
0.5610 m3 Pasir Pasang 1,000,000.00 561,000.00
1.5000 oh Pekerja 115,000.00 172,500.00
0.7500 oh Tukang Batu 142,600.00 106,950.00
Total : 279,450.00 1,380,375.00 1,659,825.00

5 1 M3 BATU KALI CAMP. 1 PC : 8 PS


1.2000 m3 Batu Kali / Batu Bulat 15/20 500,000.00 600,000.00
91.0000 kg Semen Portland 1,875.00 170,625.00
0.5840 m3 Pasir Pasang 1,000,000.00 584,000.00
1.5000 oh Pekerja 115,000.00 172,500.00
0.7500 oh Tukang Batu 142,600.00 106,950.00
Total : 279,450.00 1,354,625.00 1,634,075.00

6 1 M3 PASANGAN PONDASI SIKLOP, 40% BATU KALI


0.4800 m3 Batu Kali / Batu Bulat 15/20 500,000.00 240,000.00
194.0000 kg Semen Portland 1,875.00 363,750.00
0.3120 m3 Pasir Beton 1,500,000.00 468,000.00
0.4680 m3 Koral Beton 1,062,500.00 497,250.00
126.0000 kg Besi Beton 12,395.43 1,561,823.55
1.8000 kg Kawat Beton 25,000.00 45,000.00
3.4000 oh Pekerja 115,000.00 391,000.00
0.8500 oh Tukang Batu 142,600.00 121,210.00
512,210.00 3,175,823.55 3,688,033.55

7 1 M3 PASANGAN PONDASI SUMURAN DIAMETER 1 M


0.4500 m3 Batu Kali / Batu Bulat 15/20 500,000.00 225,000.00
194.0000 kg Semen Portland 1,875.00 363,750.00
0.3120 m3 Pasir Beton 1,500,000.00 468,000.00
0.4680 m3 Koral Beton 1,062,500.00 497,250.00
2.4000 oh Pekerja 115,000.00 276,000.00
0.8000 oh Tukang Batu 142,600.00 114,080.00
Total : 390,080.00 1,554,000.00 1,944,080.00

8 1 M3 PASANGAN BATU KOSONG


1.2000 m3 Batu Kali / Batu Bulat 15/20 15/20 500,000.00 600,000.00
0.4320 m3 Pasir Urug 1,500,000.00 648,000.00
0.7800 oh Pekerja 115,000.00 89,700.00
0.3900 oh Tukang Batu 142,600.00 55,614.00
Total : 145,314.00 1,248,000.00 1,393,314.00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

IV PEKERJAAN DINDING (SNI 6897 : 2008)

1
1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 2 PS
140.0000 bh Bata Merah 5 x 11 x 22 cm 8,000.00 1,120,000.00
43.5000 kg Semen Portland 1,875.00 81,562.50
0.0800 m3 Pasir Pasang 1,000,000.00 80,000.00
0.6000 oh Pekerja 115,000.00 69,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
97,520.00 1,281,562.50 1,379,082.50

2 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 3 PS


140.0000 bh Bata Merah 5 x 11 x 22 cm 8,000.00 1,120,000.00
32.9500 kg Semen Portland 1,875.00 61,781.25
0.0910 m3 Pasir Pasang 1,000,000.00 91,000.00
0.6000 oh Pekerja 115,000.00 69,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
97,520.00 1,272,781.25 1,370,301.25

3 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 4 PS


140.0000 bh Bata Merah 5 x 11 x 22 cm 8,000.00 1,120,000.00
26.5500 kg Semen Portland 1,875.00 49,781.25
0.0930 m3 Pasir Pasang 1,000,000.00 93,000.00
0.6000 oh Pekerja 115,000.00 69,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
97,520.00 1,262,781.25 1,360,301.25

4 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 5 PS


140.0000 bh Bata Merah 5 x 11 x 22 cm 8,000.00 1,120,000.00
22.2000 kg Semen Portland 1,875.00 41,625.00
0.1020 m3 Pasir Pasang 1,000,000.00 102,000.00
0.6000 oh Pekerja 115,000.00 69,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
97,520.00 1,263,625.00 1,361,145.00

5 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 6 PS


140.0000 bh Bata Merah 5 x 11 x 22 cm 8,000.00 1,120,000.00
18.5000 kg Semen Portland 1,875.00 34,687.50
0.1220 m3 Pasir Pasang 1,000,000.00 122,000.00
0.6000 oh Pekerja 115,000.00 69,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
97,520.00 1,276,687.50 1,374,207.50

6 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 2 PS


70.0000 bh Bata Merah 5 x 11 x 22 cm 8,000.00 560,000.00
18.9500 kg Semen Portland 1,875.00 35,531.25
0.0380 m3 Pasir Pasang 1,000,000.00 38,000.00
0.3000 oh Pekerja 115,000.00 34,500.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
48,760.00 633,531.25 682,291.25

7 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 3 PS


70.0000 bh Bata Merah 5 x 11 x 22 cm 8,000.00 560,000.00
14.3700 kg Semen Portland 1,875.00 26,943.75
0.0400 m3 Pasir Pasang 1,000,000.00 40,000.00
0.3000 oh Pekerja 115,000.00 34,500.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
Total : 48,760.00 626,943.75 675,703.75

8 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 4 PS


70.0000 bh Bata Merah 5 x 11 x 22 cm 8,000.00 560,000.00
11.5000 kg Semen Portland 1,875.00 21,562.50
0.0430 m3 Pasir Pasang 1,000,000.00 43,000.00
0.3000 oh Pekerja 115,000.00 34,500.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
Total : 48,760.00 624,562.50 673,322.50

9 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 5 PS


70.0000 bh Bata Merah 5 x 11 x 22 cm 8,000.00 560,000.00
9.6800 kg Semen Portland 1,875.00 18,150.00
0.0450 m3 Pasir Pasang 1,000,000.00 45,000.00
0.3000 oh Pekerja 115,000.00 34,500.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
Total : 48,760.00 623,150.00 671,910.00
10 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 6 PS
70.0000 bh Bata Merah 5 x 11 x 22 cm 8,000.00 560,000.00
8.3200 kg Semen Portland 1,875.00 15,600.00
0.0490 m3 Pasir Pasang 1,000,000.00 49,000.00
0.3000 oh Pekerja 115,000.00 34,500.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
Total : 48,760.00 624,600.00 673,360.00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

11 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 8 PS


70.0000 bh Bata Merah 5 x 11 x 22 cm 8,000.00 560,000.00
6.5000 kg Semen Portland 1,875.00 12,187.50
0.0500 m3 Pasir Pasang 1,000,000.00 50,000.00
0.3000 oh Pekerja 115,000.00 34,500.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
Total : 48,760.00 622,187.50 670,947.50

12 1 M2 PASANGAN DINDING HOLLOWBLOCK (HB. 10)


12.5000 bh Batako 8,000.00 100,000.00
7.5000 kg Semen Portland 1,875.00 14,062.50
0.0270 m3 Pasir Pasang 1,000,000.00 27,000.00
1.9500 kg Besi Beton 8 mm 12,395.43 24,171.08
0.3200 oh Pekerja 115,000.00 36,800.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
Total : 51,060.00 165,233.58 216,293.58

13 1 M2 PASANGAN DINDING HOLLOWBLOCK (HB. 10) TANPA BESI


12.5000 bh Batako 8,000.00 100,000.00
7.5000 kg Semen Portland 1,875.00 14,062.50
0.0270 m3 Pasir Pasang 1,000,000.00 27,000.00
0.3200 oh Pekerja 115,000.00 36,800.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
Total : 51,060.00 141,062.50 192,122.50

14 1 M2 PASANGAN DINDING Terawang/Roster (12 x 11 x 24) CM


30.0000 bh Roster Keramik 85,000.00 2,550,000.00
11.0000 kg Semen Portland 1,875.00 20,625.00
0.0350 m3 Pasir Pasang 1,000,000.00 35,000.00
0.3000 oh Pekerja 115,000.00 34,500.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
Total : 48,760.00 2,605,625.00 2,654,385.00

15 1 M2 PASANGAN DINDING BEDEG, RANGKA KAYU


1.5000 m2 Bedeg/Bilik Bambu Kelas I 21,000.00 31,500.00
0.0140 m3 Kayu kamper usuk/reng - -
0.0120 kg Paku Biasa 20,000.00 240.00
0.0030 m3 List Kayu 2/4 - -
0.1000 oh Pekerja 115,000.00 11,500.00
0.0500 oh Tukang Kayu 148,350.00 7,417.50
Total : 18,917.50 31,740.00 50,657.50

V PEKERJAAN PLESTERAN (SNI 2837 : 2008)

1 1 M2 PLESTERAN CAMP. 1 PC : 1 PS TEBAL 15 MM


15.5040 kg Semen Portland 1,875.00 29,070.00
0.0160 m3 Pasir Pasang 1,000,000.00 16,000.00
0.3000 oh Pekerja 115,000.00 34,500.00
0.1500 oh Tukang Batu 142,600.00 21,390.00
Total : 55,890.00 45,070.00 100,960.00
2 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 15 MM
10.2240 kg Semen Portland 1,875.00 19,170.00
0.0200 m3 Pasir Pasang 1,000,000.00 20,000.00
0.3000 oh Pekerja 115,000.00 34,500.00
0.1500 oh Tukang Batu 142,600.00 21,390.00
Total : 55,890.00 39,170.00 95,060.00

3 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 15 MM


7.7760 kg Semen Portland 1,875.00 14,580.00
0.0230 m3 Pasir Pasang 1,000,000.00 23,000.00
0.3000 oh Pekerja 115,000.00 34,500.00
0.1500 oh Tukang Batu 142,600.00 21,390.00
Total : 55,890.00 37,580.00 93,470.00

4 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 15 MM


6.2400 kg Semen Portland 1,875.00 11,700.00
0.0240 m3 Pasir Pasang 1,000,000.00 24,000.00
0.3000 oh Pekerja 115,000.00 34,500.00
0.1500 oh Tukang Batu 142,600.00 21,390.00
Total : 55,890.00 35,700.00 91,590.00

5 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 15 MM


5.1840 kg Semen Portland 1,875.00 9,720.00
0.0260 m3 Pasir Pasang 1,000,000.00 26,000.00
0.3000 oh Pekerja 115,000.00 34,500.00
0.1500 oh Tukang Batu 142,600.00 21,390.00
Total : 55,890.00 35,720.00 91,610.00

6 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 15 MM


4.4160 kg Semen Portland 1,875.00 8,280.00
0.0270 m3 Pasir Pasang 1,000,000.00 27,000.00
0.3000 oh Pekerja 115,000.00 34,500.00
0.1500 oh Tukang Batu 142,600.00 21,390.00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
Total : 55,890.00 35,280.00 91,170.00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

7 1 M2 PLESTERAN CAMP. 1 PC : 8 PS TEBAL 15 MM


3.4560 kg Semen Portland 1,875.00 6,480.00
0.0290 m3 Pasir Pasang 1,000,000.00 29,000.00
0.3000 oh Pekerja 115,000.00 34,500.00
0.1500 oh Tukang Batu 142,600.00 21,390.00
Total : 55,890.00 35,480.00 91,370.00

8 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 20 MM


13.6320 kg Semen Portland 1,875.00 25,560.00
0.0270 m3 Pasir Pasang 1,000,000.00 27,000.00
0.4000 oh Pekerja 115,000.00 46,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
Total : 74,520.00 52,560.00 127,080.00

9 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 20 MM


10.3680 kg Semen Portland 1,875.00 19,440.00
0.0310 m3 Pasir Pasang 1,000,000.00 31,000.00
0.4000 oh Pekerja 115,000.00 46,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
Total : 74,520.00 50,440.00 124,960.00

10 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 20 MM


8.3200 kg Semen Portland 1,875.00 15,600.00
0.0320 m3 Pasir Pasang 1,000,000.00 32,000.00
0.4000 oh Pekerja 115,000.00 46,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
Total : 74,520.00 47,600.00 122,120.00
11 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 20 MM
6.9120 kg Semen Portland 1,875.00 12,960.00
0.0350 m3 Pasir Pasang 1,000,000.00 35,000.00
0.4000 oh Pekerja 115,000.00 46,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
Total : 74,520.00 47,960.00 122,480.00

12 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 20 MM


5.8880 kg Semen Portland 1,875.00 11,040.00
0.0360 m3 Pasir Pasang 1,000,000.00 36,000.00
0.4000 oh Pekerja 115,000.00 46,000.00
0.2000 oh Tukang Batu 142,600.00 28,520.00
Total : 74,520.00 47,040.00 121,560.00

13 1 M2 PLESTERAN SKONING 1 PC : 2 PS, TEBAL 10 MM


0.5000 kg Semen Portland 1,875.00 937.50
0.0130 m3 Pasir Pasang 1,000,000.00 13,000.00
0.0800 oh Pekerja 115,000.00 9,200.00
0.4000 oh Tukang Batu 142,600.00 57,040.00
Total : 66,240.00 13,937.50 80,177.50

14 1 M2 PLESTERAN CIPRAT 1 PC : 2 PS
4.3200 kg Semen Portland 1,875.00 8,100.00
0.0060 m3 Pasir Pasang 1,000,000.00 6,000.00
0.3000 oh Pekerja 115,000.00 34,500.00
0.1000 oh Tukang Batu 142,600.00 14,260.00
Total : 48,760.00 14,100.00 62,860.00

15
1 M2 FINISHING SIAR PASANGAN DINDING BATA MERAH (=20 M')
3.1080 kg Semen Portland 1,875.00 5,827.50
0.1500 oh Pekerja 115,000.00 17,250.00
0.0750 oh Tukang Batu 142,600.00 10,695.00
Total : 27,945.00 5,827.50 33,772.50

16 1 M2 FINISHING SIAR PASANGAN DINDING CONBLOCK


EKSPOSE (= 8 M')
1.6000 kg Semen Portland 1,875.00 3,000.00
0.0700 oh Pekerja 115,000.00 8,050.00
0.0350 oh Tukang Batu 142,600.00 4,991.00
Total : 13,041.00 3,000.00 16,041.00

17
1 M2 FINISHING SIAR PASANGAN BATU KALI ADUKAN 1PC : 2 PS
6.3400 kg Semen Portland 1,875.00 11,887.50
0.0120 m3 Pasir Pasang 1,000,000.00 12,000.00
0.3000 oh Pekerja 115,000.00 34,500.00
0.1500 oh Tukang Batu 142,600.00 21,390.00
Total : 55,890.00 23,887.50 79,777.50

18 1 M2 PEKERJAAN ACIAN
3.2500 zak Semen Portland 50 Kg 1,875.00 6,093.75
0.2000 oh Pekerja 115,000.00 23,000.00
0.1000 oh Tukang Labur/Cat 148,350.00 14,835.00
Total : 14,835.00 6,093.75 20,928.75
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
VI PEKERJAAN KAYU (SNI 3434 : 2008)

1 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA


KAYU KELAS I
1.1000 m3 Balok Kayu Kamper - -
1.2500 Kg Paku 10 Cm 30,000.00 37,500.00
1.0000 Kg Lem Kayu 40,000.00 40,000.00
7.0000 oh Pekerja 115,000.00 805,000.00
21.0000 oh Tukang Kayu 148,350.00 3,115,350.00
Total : 3,920,350.00 77,500.00 3,997,850.00

2 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA


KAYU KELAS II/III
1.2000 m3 Balok Kayu kruing - -
1.2500 Kg Paku 10 Cm 30,000.00 37,500.00
1.0000 Kg Lem Kayu 40,000.00 40,000.00
6.0000 oh Pekerja 115,000.00 690,000.00
18.0000 oh Tukang Kayu 148,350.00 2,670,300.00
Total : 3,360,300.00 77,500.00 3,437,800.00

3 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP STANDAR KAYU


KELAS II
0.0400 m3 Papan Kayu Kamper - -
0.0500 Kg Paku 5-7 Cm 30,000.00 1,500.00
0.3500 oh Pekerja 115,000.00 40,250.00
1.0500 oh Tukang Kayu 148,350.00 155,767.50
Total : 196,017.50 1,500.00 197,517.50

4 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP SEDERHANA


KAYU KELAS III
0.0400 m3 Papan Kayu Kruing - -
0.0500 Kg Paku 5-7 Cm 30,000.00 1,500.00
0.3500 oh Pekerja 115,000.00 40,250.00
1.0500 oh Tukang Kayu 148,350.00 155,767.50
Total : 196,017.50 1,500.00 197,517.50

5 MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU


KELAS I/II
0.0400 m3 Papan Kayu Kamper - -
0.5000 Kg Lem Kayu 40,000.00 20,000.00
1.0000 oh Pekerja 115,000.00 115,000.00
3.0000 oh Tukang Kayu 148,350.00 445,050.00
Total : 560,050.00 20,000.00 580,050.00

6 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA,


KAYU KELAS I/II
0.0240 m3 Papan Kayu Kamper - -
0.3000 Kg Lem Kayu 40,000.00 12,000.00
0.8000 oh Pekerja 115,000.00 92,000.00
2.4000 oh Tukang Kayu 148,350.00 356,040.00
Total : 448,040.00 12,000.00 460,040.00

7 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA JALUSI,


KAYU KELAS I/II
0.0640 m3 Papan Kayu Kamper - -
0.5000 Kg Lem Kayu 40,000.00 20,000.00
1.0000 oh Pekerja 115,000.00 115,000.00
3.0000 oh Tukang Kayu 148,350.00 445,050.00
Total : 560,050.00 20,000.00 580,050.00

8 MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA


TERTUTUP, KAYU KELAS II (Lebar Sampai 90 Cm)
0.0250 m3 Papan Kayu Kamper - -
0.0300 Kg Paku 1-2,5 Cm 30,000.00 900.00
0.5000 Kg Lem Kayu 40,000.00 20,000.00
1.0000 Lbr Plywood 4 mm 225,000.00 225,000.00
1.0000 oh Pekerja 115,000.00 115,000.00
3.0000 oh Tukang Kayu 148,350.00 445,050.00
Total : 560,050.00 245,900.00 805,950.00

9 MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA


EXPOSE, KAYU KELAS I/II
0.0256 m3 Papan Kayu Kamper - -
0.0300 Kg Paku 1-2,5 Cm 30,000.00 900.00
0.5000 Kg Lem Kayu 40,000.00 20,000.00
1.0000 Lbr Plywood 4 mm 225,000.00 225,000.00
0.8000 oh Pekerja 115,000.00 92,000.00
2.4000 oh Tukang Kayu 148,350.00 356,040.00
Total : 448,040.00 245,900.00 693,940.00

10 MEMASANG 1 M2 JALUSI KUSEN, KAYU KELAS I/II


0.0600 m3 Papan Kayu Kamper - -
0.1500 Kg Paku 1-2,5 Cm 30,000.00 4,500.00
0.6700 oh Pekerja 115,000.00 77,050.00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
2.0000 oh Tukang Kayu 148,350.00 296,700.00
Total : 373,750.00 4,500.00 378,250.00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

11 MEMBUAT 1 M2 TEAKWOOD RANGKAP RANGKA EXPOSE, KAYU


KELAS I
0.0256 m3 Papan Kayu Kamper - -
0.0300 Kg Paku 1-2,5 Cm 30,000.00 900.00
0.5000 Kg Lem Kayu 40,000.00 20,000.00
1.0000 Lbr Teakwood 4 mm uk 90x220 cm 98,000.00 98,000.00
0.8000 oh Pekerja 115,000.00 92,000.00
2.4000 oh Tukang Kayu 148,350.00 356,040.00
Total : 448,040.00 118,900.00 566,940.00

12 MEMBUAT 1 M2 TEAKWOOD RANGKAP LAPIS FORMIKA RANGKA


EXPOSE, KAYU KELAS II
0.0250 m3 Papan Kayu Kamper - -
0.0300 Kg Paku 1-2,5 Cm 30,000.00 900.00
0.8000 Kg Lem Kayu 40,000.00 32,000.00
1.0000 Lbr Teakwood 4 mm uk 90x220 cm 98,000.00 98,000.00
0.5000 Lbr Formika 95,000.00 47,500.00
0.8000 oh Pekerja 115,000.00 92,000.00
2.4000 oh Tukang Kayu 148,350.00 356,040.00
Total : 448,040.00 178,400.00 626,440.00

13 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL,


KAYU KELAS I,II,III Bentang 6 M'
1.1000 m3 Balok Kayu Kamper - -
15.0000 Kg Besi Strip Tebal 5 cm 7,260.00 108,900.00
5.6000 Kg Paku 12 Cm 30,000.00 168,000.00
4.0000 oh Pekerja 115,000.00 460,000.00
12.0000 oh Tukang Kayu 148,350.00 1,780,200.00
Total : 2,240,200.00 276,900.00 2,517,100.00

14 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA EXPOSE, KAYU


KELAS I
1.2000 m3 Balok Kayu Kamper - -
15.0000 Kg Besi Strip Tebal 5 cm 7,260.00 108,900.00
5.6000 Kg Paku 12 Cm 30,000.00 168,000.00
6.7000 oh Pekerja 115,000.00 770,500.00
20.1000 oh Tukang Kayu 148,350.00 2,981,835.00
Total : 3,752,335.00 276,900.00 4,029,235.00

15 MEMASANG 1 M3 KONSTRUKSI GORDENG, KAYU KELAS II

1.1000 m3 Balok Kayu Kamper - -


15.0000 Kg Besi Strip Tebal 5 cm 7,260.00 108,900.00
3.0000 Kg Paku 12 Cm 30,000.00 90,000.00
2.4000 oh Pekerja 115,000.00 276,000.00
7.2000 oh Tukang Kayu 148,350.00 1,068,120.00
Total : 1,344,120.00 198,900.00 1,543,020.00

16 MEMASANG 1 M2 RANGKA ATAP GENTENG KERAMIK, KAYU


KELAS II
0.0140 m3 Kaso-Kaso ( 5 x 7 ) Cm - -
0.0036 m3 Reng ( 2 x 3 ) Cm - -
0.2500 Kg Paku 5 Cm dan 10 Cm 30,000.00 7,500.00
0.1000 oh Pekerja 115,000.00 11,500.00
0.1000 oh Tukang Kayu 148,350.00 14,835.00
Total : 26,335.00 7,500.00 33,835.00

17 MEMASANG 1 M2 RANGKA ATAP GENTENG BETON, KAYU KELAS


II
0.0140 m3 Kaso-Kaso ( 5 x 7 ) Cm - -
0.0072 m3 Reng ( 2 x 3 ) Cm - -
0.2500 Kg Paku 5 Cm dan 10 Cm 30,000.00 7,500.00
0.1000 oh Pekerja 115,000.00 11,500.00
0.1000 oh Tukang Kayu 148,350.00 14,835.00
Total : 26,335.00 7,500.00 33,835.00

18 MEMASANG 1 M2 RANGKA ATAP SIRAP, KAYU KELAS II

0.1650 m3 Balok Kayu Kamper - -


0.2000 Kg Paku 5 Cm dan 10 Cm 30,000.00 6,000.00
0.1200 oh Pekerja 115,000.00 13,800.00
0.1200 oh Tukang Kayu 148,350.00 17,802.00
Total : 31,602.00 6,000.00 37,602.00

19 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (50 X 100), KAYU


KELAS II/III
0.0154 m3 Kaso-Kaso ( 5 x 7 ) Cm - -
0.2000 Kg Paku 7 Cm dan 10 Cm 30,000.00 6,000.00
0.1500 oh Pekerja 115,000.00 17,250.00
0.3000 oh Tukang Kayu 148,350.00 44,505.00
Total : 61,755.00 6,000.00 67,755.00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

20 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (60 X 60) CM, KAYU


KELAS II/III
0.0163 m3 Kaso-Kaso ( 5 x 7 ) Cm - -
0.2500 Kg Paku 7 Cm dan 10 Cm 30,000.00 7,500.00
0.2000 oh Pekerja 115,000.00 23,000.00
0.3000 oh Tukang Kayu 148,350.00 44,505.00
Total : 67,505.00 7,500.00 75,005.00

21 MEMASANG 1 M' LISPLANK UKURAN (3 X 20) CM, KAYU KELAS


I/II
0.0108 m3 Papan Kayu Kamper - -
0.1000 Kg Paku 5 Cm dan 7 Cm 30,000.00 3,000.00
0.1000 oh Pekerja 115,000.00 11,500.00
0.2000 oh Tukang Kayu 148,350.00 29,670.00
Total : 41,170.00 3,000.00 44,170.00

22 MEMASANG 1 M' LISPLANK UKURAN (3 X 30) CM, KAYU KELAS


I/II
0.0110 m3 Papan Kayu Kamper - -
0.0500 Kg Paku 5 Cm dan 7 Cm 30,000.00 1,500.00
0.1000 oh Pekerja 115,000.00 11,500.00
0.2000 oh Tukang Kayu 148,350.00 29,670.00
Total : 41,170.00 1,500.00 42,670.00

23 MEMASANG 1 M2 RANGKA DINDING PEMISAH (60 X 120) CM,


KAYU KELAS II/III
0.0280 m3 Balok Kayu Kamper - -
0.1500 Kg Paku 5 Cm dan 7 Cm 30,000.00 4,500.00
0.1500 oh Pekerja 115,000.00 17,250.00
0.4500 oh Tukang Kayu 148,350.00 66,757.50
Total : 84,007.50 4,500.00 88,507.50

24 MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD


RANGKAP, RANGKA KAYU KELAS II
0.0280 m3 Balok Kayu Kamper - -
0.1500 Kg Paku 5 Cm dan 7 Cm 30,000.00 4,500.00
0.8600 Lbr Teakwood 4 mm uk 90x220 cm 98,000.00 84,280.00
0.5600 Kg Lem Kayu 40,000.00 22,400.00
0.1500 oh Pekerja 115,000.00 17,250.00
0.4500 oh Tukang Kayu 148,350.00 66,757.50
Total : 84,007.50 111,180.00 195,187.50

25 MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD


RANGKAP, RANGKA KAYU KELAS II
0.0280 m3 Balok Kayu Kamper - -
0.1500 Kg Paku 5 Cm dan 7 Cm 30,000.00 4,500.00
0.8600 Lbr Plywood tebal 4 mm uk 120 x 240 cm 225,000.00 193,500.00
0.5600 Kg Lem Kayu 40,000.00 22,400.00
0.2000 oh Pekerja 115,000.00 23,000.00
0.6000 oh Tukang Kayu 148,350.00 89,010.00
Total : 112,010.00 220,400.00 332,410.00

26 MEMASANG 1 M2 LAMBRIZIRING DARI PAPAN KAYU KELAS I

0.0070 m3 Papan Kayu Kamper - -


0.1000 Kg Paku 5 Cm dan 10 Cm 30,000.00 3,000.00
0.1500 Kg Paku Skrup 10 cm - -
0.6000 oh Pekerja 115,000.00 69,000.00
1.8000 oh Tukang Kayu 148,350.00 267,030.00
Total : 336,030.00 3,000.00 339,030.00

27 MEMASANG 1 M2 LAMBRIZIRING DARI PLYWOOD UKURAN (120


X 240) CM
0.4000 Lbr Plywood tebal 4 mm uk 120 x 240 cm 225,000.00 90,000.00
0.0500 Kg Paku 1 Cm dan 2.5 Cm 30,000.00 1,500.00
0.0250 oh Pekerja 115,000.00 2,875.00
0.0750 oh Tukang Kayu 148,350.00 11,126.25
Total : 14,001.25 91,500.00 105,501.25

VII PEKERJAAN BETON ( SNI 7394:2008)


1 1 M3 MEMBUAT BETON 1 PC : 3 PS : 5 KR
218.0000 kg Semen Portland 1,875.00 408,750.00
0.5200 m3 Pasir Beton 1,500,000.00 780,000.00
0.8700 m3 Koral Beton 1,062,500.00 924,375.00
1.6500 oh Pekerja 115,000.00 189,750.00
0.2500 oh Tukang Batu 142,600.00 35,650.00
225,400.00 2,113,125.00 2,338,525.00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

2 1 M3 MEMBUAT BETON 1 PC : 2 PS : 4 KR
232.0000 kg Semen Portland 1,875.00 435,000.00
0.5200 m3 Pasir Beton 1,500,000.00 780,000.00
0.7800 m3 Koral Beton 1,062,500.00 828,750.00
1.6500 oh Pekerja 115,000.00 189,750.00
0.2500 oh Tukang Batu 142,600.00 35,650.00
Total : 225,400.00 2,043,750.00 2,269,150.00

3 1 M3 MEMBUAT BETON 1 PC : 2 PS : 3 KR
280.0000 kg Semen Portland 1,875.00 525,000.00
0.4500 m3 Pasir Beton 1,500,000.00 675,000.00
0.9000 m3 Koral Beton 1,062,500.00 956,250.00
1.6500 oh Pekerja 115,000.00 189,750.00
0.2500 oh Tukang Batu 142,600.00 35,650.00
Total : 225,400.00 2,156,250.00 2,381,650.00

4 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR


10.5000 kg Besi Beton (Polos/ Ulir) 12,395.43 130,151.96
0.1500 kg Kawat Beton 25,000.00 3,750.00
0.0700 oh Pekerja 115,000.00 8,050.00
0.0700 oh Tukang Besi 148,350.00 10,384.50
Total : 18,434.50 133,901.96 152,336.46

5 1 M2 PASANG BEKISTING UNTUK PONDASI


0.0400 m3 Kayu Kelas III - -
0.3000 kg Paku Biasa 5' - 10' 20,000.00 6,000.00
0.1000 ltr Minyak Bekisting 15,000.00 1,500.00
0.5200 oh Pekerja 115,000.00 59,800.00
0.2600 oh Tukang Kayu 148,350.00 38,571.00
Total : 98,371.00 7,500.00 105,871.00

6 1 M2 PASANG BEKISTING UNTUK SLOOF


0.0400 m3 Kayu Kelas III - -
0.3000 kg Paku Biasa 5' - 10' 20,000.00 6,000.00
0.1000 ltr Minyak Bekisting 15,000.00 1,500.00
0.5200 oh Pekerja 115,000.00 59,800.00
0.2600 oh Tukang Kayu 148,350.00 38,571.00
Total : 98,371.00 7,500.00 105,871.00

7 1 M2 PASANG BEKISTING UNTUK KOLOM


0.0400 m3 Kayu Kelas III - -
0.4000 kg Paku Biasa 5' - 12' 20,000.00 8,000.00
0.2000 ltr Minyak Bekisting 15,000.00 3,000.00
0.0150 m3 Kayu Usuk 4/6 - -
0.3500 lbr Plywood 9 mm 290,000.00 101,500.00
2.0000 btg Dolken Kayu 8" - 10"/4 m 36,000.00 72,000.00
0.6600 oh Pekerja 115,000.00 75,900.00
0.3300 oh Tukang Kayu 148,350.00 48,955.50
Total : 124,855.50 184,500.00 309,355.50

8 1 M2 PASANG BEKISTING UNTUK BALOK


0.0400 m3 Kayu Kelas III - -
0.4000 kg Paku Biasa 5' - 12' 20,000.00 8,000.00
0.2000 ltr Minyak Bekisting 15,000.00 3,000.00
0.0180 m3 Kayu Usuk 4/6 - -
0.3500 lbr Plywood 9 mm 290,000.00 101,500.00
2.0000 btg Dolken Kayu 8" - 10"/4m 36,000.00 72,000.00
0.6600 oh Pekerja 115,000.00 75,900.00
0.3300 oh Tukang Kayu 148,350.00 48,955.50
Total : 124,855.50 184,500.00 309,355.50

9 1 M2 PASANG BEKISTING UNTUK LANTAI


0.0400 m3 Kayu Kelas III - -
0.4000 kg Paku Biasa 5' - 12' 20,000.00 8,000.00
0.2000 ltr Minyak Bekisting 15,000.00 3,000.00
0.0150 m3 Kayu Usuk 4/6 - -
0.3500 lbr Plywood 9 mm 290,000.00 101,500.00
6.0000 btg Dolken Kayu 8" - 10"/4m 36,000.00 216,000.00
0.6600 oh Pekerja 115,000.00 75,900.00
0.3300 oh Tukang Kayu 148,350.00 48,955.50
Total : 124,855.50 328,500.00 453,355.50

10 1 M2 PASANG BEKISTING UNTUK DINDING


0.0300 M3 Kayu Kelas III - -
0.4000 Kg Paku Biasa 5' - 12' 20,000.00 8,000.00
0.2000 Ltr Minyak Bekisting 15,000.00 3,000.00
0.0200 M3 Kayu Usuk 4/6 - -
0.3500 Lbr Plywood 9 mm 290,000.00 101,500.00
3.0000 Btng Dolken Kayu 8" - 10"/4m 36,000.00 108,000.00
4.0000 Bh Formite/penjaga jarak bekisting/spacer 2,000.00 8,000.00
0.6600 Oh Pekerja 115,000.00 75,900.00
0.3300 Oh Tukang Kayu 148,350.00 48,955.50
124,855.50 228,500.00 353,355.50
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

11 1 M2 PASANG BEKISTING UNTUK TANGGA


0.0300 m3 Kayu Kelas III - -
0.4000 kg Paku Biasa 5' - 12' 20,000.00 8,000.00
0.1500 ltr Minyak Bekisting 15,000.00 2,250.00
0.0150 m3 Kayu Usuk 4/6 - -
0.3500 lbr Plywood 9 mm 290,000.00 101,500.00
2.0000 btg Dolken Kayu 8" - 10"/4m 36,000.00 72,000.00
0.6600 oh Pekerja 115,000.00 75,900.00
0.3300 oh Tukang Kayu 148,350.00 48,955.50
Total : 124,855.50 183,750.00 308,605.50

12 1 M2 PASANG JEMBATAN UNTUK PENGECORAN BETON


0.0264 m3 Kayu Kelas III (Papan) - -
0.6000 kg Paku Biasa 5' - 12' 20,000.00 12,000.00
0.5000 btg Dolken Kayu 8" - 10"/4m 36,000.00 18,000.00
0.1500 oh Pekerja 115,000.00 17,250.00
0.0500 oh Tukang Kayu 148,350.00 7,417.50
Total : 24,667.50 30,000.00 54,667.50

13 1 M3 MEMBUAT PONDASI BETON BERTULANG (150 KG BESI + BEKISTING)


0.2000 m3 Kayu Kelas III - -
1.5000 kg Paku Biasa 5' - 12' 20,000.00 30,000.00
0.4000 ltr Minyak Bekisting 15,000.00 6,000.00
157.0000 kg Besi Beton 12,395.43 1,946,081.73
2.2500 kg Kawat Beton 25,000.00 56,250.00
336.0000 kg Semen Portland 1,875.00 630,000.00
0.5400 m3 Pasir Beton 1,500,000.00 810,000.00
0.8100 m3 Koral Beton 1,062,500.00 860,625.00
5.3000 oh Pekerja 115,000.00 609,500.00
0.2750 oh Tukang Batu 142,600.00 39,215.00
1.3000 oh Tukang Kayu 148,350.00 192,855.00
1.0500 oh Tukang Besi 148,350.00 155,767.50
Total : 997,337.50 4,338,956.73 5,336,294.23

14 1 M3 MEMBUAT SLOOF BETON BERTULANG (200 KG + BEKISTING)


0.2700 m3 Kayu Kelas III - -
2.0000 kg Paku Biasa 5' - 12' 20,000.00 40,000.00
0.6000 ltr Minyak Bekisting 15,000.00 9,000.00
210.0000 kg Besi Beton 12,395.43 2,603,039.26
3.0000 kg Kawat Beton 25,000.00 75,000.00
336.0000 kg Semen Portland 1,875.00 630,000.00
0.5400 m3 Pasir Beton 1,500,000.00 810,000.00
0.8100 m3 Koral Beton 1,062,500.00 860,625.00
5.6500 oh Pekerja 115,000.00 649,750.00
0.2750 oh Tukang Batu 142,600.00 39,215.00
1.5600 oh Tukang Kayu 148,350.00 231,426.00
1.4000 oh Tukang Besi 148,350.00 207,690.00
Total : 1,128,081.00 5,027,664.26 6,155,745.26

15 1 M3 MEMBUAT KOLOM BETON BERTULANG (300 KG BESI +


BEKISTING)
0.4000 m3 Kayu Kelas III - -
4.0000 kg Paku Biasa 5' - 12' 20,000.00 80,000.00
2.0000 ltr Minyak Bekisting 15,000.00 30,000.00
315.0000 kg Besi Beton 12,395.43 3,904,558.88
4.5000 kg Kawat Beton 25,000.00 112,500.00
336.0000 kg Semen Portland 1,875.00 630,000.00
0.5400 m3 Pasir Beton 1,500,000.00 810,000.00
0.8100 m3 Koral Beton 1,062,500.00 860,625.00
0.1500 m3 Kayu Kelas II balok - -
3.5000 lbr Plywood 9 mm 290,000.00 1,015,000.00
20.0000 btg Dolken Kayu 8" /4 m 36,000.00 720,000.00
7.0500 oh Pekerja 115,000.00 810,750.00
0.2750 oh Tukang Batu 142,600.00 39,215.00
1.6500 oh Tukang Kayu 148,350.00 244,777.50
2.1000 oh Tukang Besi 148,350.00 311,535.00
Total : 1,406,277.50 8,162,683.88 9,568,961.38

16 1 M3 MEMBUAT BALOK BETON BERTULANG (200 KG BESI +


BEKISTING)
0.3200 m3 Kayu Kelas III - -
3.2000 kg Paku Biasa 5' - 12' 20,000.00 64,000.00
1.6000 ltr Minyak Bekisting 15,000.00 24,000.00
210.0000 kg Besi Beton 12,395.43 2,603,039.26
3.0000 kg Kawat Beton 25,000.00 75,000.00
336.0000 kg Semen Portland 1,875.00 630,000.00
0.5400 m3 Pasir Beton 1,500,000.00 810,000.00
0.8100 m3 Koral Beton 1,062,500.00 860,625.00
0.1400 m3 Kayu Kelas II balok - -
2.8000 lbr Plywood 9 mm 290,000.00 812,000.00
16.0000 btg Dolken Kayu 8" /4 m 36,000.00 576,000.00
6.3500 oh Pekerja 115,000.00 730,250.00
0.2750 oh Tukang Batu 142,600.00 39,215.00
1.6500 oh Tukang Kayu 148,350.00 244,777.50
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
1.4000 oh Tukang Besi 148,350.00 207,690.00
Total : 1,221,932.50 6,454,664.26 7,676,596.76
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6
17 1 M3 MEMBUAT PLAT BETON BERTULANG (150 KG BESI +
BEKISTING
0.3200 m3 Kayu Kelas III - -
3.2000 kg Paku Biasa 5' - 12' 20,000.00 64,000.00
1.6000 ltr Minyak Bekisting 15,000.00 24,000.00
157.5000 kg Besi Beton 12,395.43 1,952,279.44
2.2500 kg Kawat Beton 25,000.00 56,250.00
336.0000 kg Semen Portland 1,875.00 630,000.00
0.5400 m3 Pasir Beton 1,500,000.00 810,000.00
0.8100 m3 Koral Beton 1,062,500.00 860,625.00
0.1200 m3 Kayu Kelas II balok - -
2.8000 lbr Plywood 9 mm 290,000.00 812,000.00
32.0000 btg Dolken Kayu 8" /4 m 36,000.00 1,152,000.00
5.3000 oh Pekerja 115,000.00 609,500.00
0.2750 oh Tukang Batu 142,600.00 39,215.00
1.3000 oh Tukang Kayu 148,350.00 192,855.00
1.0500 oh Tukang Besi 148,350.00 155,767.50
997,337.50 6,361,154.44 7,358,491.94
18 1 M3 MEMBUAT DINDING BETON BERTULANG (150 KG BESI +
BEKISTING)
0.2400 m3 Kayu Kelas III - -
3.2000 kg Paku Biasa 5' - 12' 20,000.00 64,000.00
1.6000 ltr Minyak Bekisting 15,000.00 24,000.00
157.0000 kg Besi Beton 12,395.43 1,946,081.73
2.2500 kg Kawat Beton 25,000.00 56,250.00
336.0000 kg Semen Portland 1,875.00 630,000.00
0.5400 m3 Pasir Beton 1,500,000.00 810,000.00
0.8100 m3 Koral Beton 1,062,500.00 860,625.00
0.1600 m3 Kayu Kelas II balok - -
2.8000 lbr Plywood 9 mm 290,000.00 812,000.00
24.0000 btg Dolken Kayu 8" /4 m 36,000.00 864,000.00
5.3000 oh Pekerja 115,000.00 609,500.00
0.2750 oh Tukang Batu 142,600.00 39,215.00
1.3000 oh Tukang Kayu 148,350.00 192,855.00
1.0500 oh Tukang Besi 148,350.00 155,767.50
997,337.50 6,066,956.73 7,064,294.23
19 1 M3 MEMBUAT DINDING BETON BERTULANG (200 KG BESI +
BEKISTING)
0.2500 m3 Kayu Kelas III - -
3.0000 kg Paku Biasa 5' - 12' 20,000.00 60,000.00
1.2000 ltr Minyak Bekisting 15,000.00 18,000.00
210.0000 kg Besi Beton 12,395.43 2,603,039.26
3.0000 kg Kawat Beton 25,000.00 75,000.00
336.0000 kg Semen Portland 1,875.00 630,000.00
0.5400 m3 Pasir Beton 1,500,000.00 810,000.00
0.8100 m3 Koral Beton 1,062,500.00 860,625.00
0.1050 m3 Kayu Kelas II balok - -
2.5000 lbr Plywood 9 mm 290,000.00 725,000.00
14.0000 btg Dolken Kayu 8" /4 m 36,000.00 504,000.00
5.6500 oh Pekerja 115,000.00 649,750.00
0.2750 oh Tukang Batu 142,600.00 39,215.00
1.5600 oh Tukang Kayu 148,350.00 231,426.00
1.4000 oh Tukang Besi 148,350.00 207,690.00
1,128,081.00 6,285,664.26 7,413,745.26

20 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (11 X 11


CM)
0.0020 m3 Kayu Kelas III - -
0.0100 kg Paku Biasa 5' - 12' 20,000.00 200.00
3.0000 kg Besi Beton 12,395.43 37,186.28
0.0450 kg Kawat Beton 25,000.00 1,125.00
4.0000 kg Semen Portland 1,875.00 7,500.00
0.0060 m3 Pasir Beton 1,500,000.00 9,000.00
0.0090 m3 Koral Beton 1,062,500.00 9,562.50
0.1800 oh Pekerja 115,000.00 20,700.00
0.0200 oh Tukang Batu 142,600.00 2,852.00
0.0200 oh Tukang Kayu 148,350.00 2,967.00
0.0200 oh Tukang Besi 148,350.00 2,967.00
Total : 29,486.00 64,573.78 94,059.78
21 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (10 X 15
CM)
0.0030 m3 Kayu Kelas III - -
0.0200 kg Paku Biasa 5' - 12' 20,000.00 400.00
3.6000 kg Besi Beton 12,395.43 44,623.53
0.0500 kg Kawat Beton 25,000.00 1,250.00
5.5000 kg Semen Portland 1,875.00 10,312.50
0.0090 m3 Pasir Beton 1,500,000.00 13,500.00
0.0150 m3 Koral Beton 1,062,500.00 15,937.50
0.2970 oh Pekerja 115,000.00 34,155.00
0.0330 oh Tukang Batu 142,600.00 4,705.80
0.0330 oh Tukang Kayu 148,350.00 4,895.55
0.0330 oh Tukang Besi 148,350.00 4,895.55
Total : 48,651.90 86,023.53 134,675.43
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

VIII PEKERJAAN PENUTUP ATAP (SNI 03-3436-2002)


1 1 M2 PEKERJAAN ATAP GENTENG PLENTONG
25.0000 bh Genteng Plentong #REF! #REF!
0.1500 oh Pekerja 115,000.00 17,250.00
0.0600 oh Tukang Kayu 148,350.00 8,901.00
Total : 26,151.00 #REF! #REF!

2 1 M2 PEKERJAAN ATAP GENTENG PLENTONG DI CAT


25.0000 bh Genteng Plentong Dicat #REF! #REF!
0.1500 oh Pekerja 115,000.00 17,250.00
0.0600 oh Tukang Kayu 148,350.00 8,901.00
Total : 26,151.00 #REF! #REF!

3 1 M1 PASANG BUBUNGAN GENTENG PLENTONG


5.0000 bh Bubungan Plentong #REF! #REF!
8.0000 kg Semen Portland 1,875.00 15,000.00
0.0320 m3 Pasir Pasang 1,000,000.00 32,000.00
0.4000 oh Pekerja 115,000.00 46,000.00
0.2000 oh Tukang Kayu 148,350.00 29,670.00
Total : 75,670.00 #REF! #REF!
4 1 M2 PASANG ATAP GENTENG ASBES GELOMBANG 1.8 M X 0.92 M X 5 MM
0.7500 lbr Asbes Gelombang 1.8 mx0.92mx5mm 33,600.00 25,200.00
0.1200 kg Paku Pancing 60 x 230 18,750.00 2,250.00
0.1400 oh Pekerja 115,000.00 16,100.00
0.0700 oh Tukang Kayu 148,350.00 10,384.50
Total : 26,484.50 27,450.00 53,934.50

5 1 M1 PASANG BUBUNGAN STEL GELOMBANG 0.92 M


2.4000 lbr Bubungan Stel Gelombang 24,000.00 57,600.00
6.0000 kg Paku Skrup 3,5" 170,000.00 1,020,000.00
0.0840 oh Pekerja 115,000.00 9,660.00
0.1250 oh Tukang Kayu 148,350.00 18,543.75
Total : 28,203.75 1,077,600.00 1,105,803.75
6 1 M2 PEKERJAAN ATAP SIRAP
60.0000 bh Genteng Sirap 10,200.00 612,000.00
0.2000 kg Paku Biasa 1/2" - 1" 30,000.00 6,000.00
0.1660 oh Pekerja 115,000.00 19,090.00
0.2500 oh Tukang Kayu 148,350.00 37,087.50
Total : 56,177.50 618,000.00 674,177.50

7 1 M2 PEKERJAAN ATAP NOK SIRAP


0.4000 lbr Seng plat 3" x 6" BJLS 28 22,000.00 8,800.00
0.0600 kg Paku biasa 1/2" - 1" 30,000.00 1,800.00
0.0500 kg Paku biasa 2" - 5" 20,000.00 1,000.00
0.0040 m3 Kayu papan 3 cm - -
0.1250 oh Pekerja 115,000.00 14,375.00
0.2500 oh Tukang kayu 148,350.00 37,087.50
Total : 51,462.50 11,600.00 63,062.50

8 1 M2 PASANG ATAP ALANG-ALANG 3 M1


6.5000 lbr Alang - alang - -
0.5000 glg Tali pengikat 45,000.00 22,500.00
0.2000 oh Pekerja 115,000.00 23,000.00
Total : 23,000.00 22,500.00 45,500.00

9 1 M2 PEKERJAAN ATAP SENG GELOMBANG


0.7000 lbr Seng Gelombang 3" x 6" BJLS 28 - -
0.0200 kg Paku Biasa 1/2" - 1" 30,000.00 600.00
0.1200 oh Pekerja 115,000.00 13,800.00
0.0600 oh Tukang Kayu 148,350.00 8,901.00
Total : 22,701.00 600.00 23,301.00

10 1 M2 PASANGAN LAPISANG ALUMINIUM FOIL


1.0500 m2 Aluminium Foil 29,000.00 30,450.00
0.1500 oh Pekerja 115,000.00 17,250.00
0.0500 oh Tukang Kayu 148,350.00 7,417.50
Total : 24,667.50 30,450.00 55,117.50

11 1 M1 PASANG NOK SENG GELOMBANG


0.3000 lbr Seng Plat 3" x 6" BJLS 28 22,000.00 6,600.00
0.0400 kg Paku biasa 1/2" - 1" 30,000.00 1,200.00
0.1500 oh Pekerja 115,000.00 17,250.00
0.0700 oh Tukang Kayu 148,350.00 10,384.50
Total : 27,634.50 7,800.00 35,434.50

IX PEKERJAAN LANGIT - LANGIT (SNI 2839-2008)


1 MEMASANG 1 M2 LANGIT-LANGIT ASBES SEMEN, TEBAL 4 MM,
5 MM DAN 6 MM
1.1000 lbr Asbes semen 47,000.00 51,700.00
0.0100 kg Paku Biasa 1/2" - 1" 30,000.00 300.00
0.0300 oh Pekerja 115,000.00 3,450.00
0.0700 oh Tukang Kayu 148,350.00 10,384.50
Total : 13,834.50 52,000.00 65,834.50
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

2 1 M2 PASANG LANGIT-LANGIT TRIPLEKS 120X240 CM/6MM


0.3750 lbr TRIPLEKS 225,000.00 84,375.00
0.0300 kg Paku Biasa 1/2" - 1" 30,000.00 900.00
0.1000 oh Pekerja 115,000.00 11,500.00
0.1000 oh Tukang Kayu 148,350.00 14,835.00
Total : 26,335.00 85,275.00 111,610.00

3 1 M2 PASANG LANGIT-LANGIT LAMBRIZIRING


0.0150 m3 Kayu Papan - -
0.0100 kg Paku Biasa 1/2" - 1" 30,000.00 300.00
0.8000 oh Pekerja 115,000.00 92,000.00
0.8000 oh Tukang Kayu 148,350.00 118,680.00
Total : 210,680.00 300.00 210,980.00

4 1 M1 PASANG LIST LANGIT-LANGIT KAYU PROFIL


1.0500 m1 List Kayu Profil 10,000.00 10,500.00
0.1000 kg Paku list SQ 15,840.00 1,584.00
0.0500 oh Pekerja 115,000.00 5,750.00
0.0500 oh Tukang Kayu 148,350.00 7,417.50
Total : 13,167.50 12,084.00 25,251.50

5 1 M2 PASANG LANGIT-LANGIT ASBES + RANGKA


0.0120 m3 Kamper Usuk 4/6 cm - -
0.0600 kg Paku Biasa 2" - 5" 15,840.00 950.40
1.1000 lbr Asbes 47,000.00 51,700.00
0.1800 oh Pekerja 115,000.00 20,700.00
0.3200 oh Tukang Kayu 148,350.00 47,472.00
Total : 68,172.00 52,650.40 120,822.40

6 1 M2 PASANG LANGIT-LANGIT GYPSUM BOARD UKURAN (1200X2400X9) MM


0.1100 kg Paku Sekrup 120,000.00 13,200.00
0.3640 lbr Gypsum Board (120x240x9) - -
0.1000 oh Pekerja 115,000.00 11,500.00
0.0500 oh Tukang Kayu 148,350.00 7,417.50
Total : 18,917.50 13,200.00 32,117.50

7 1 M2 PASANG LANGIT-LANGIT KALSIBOARD 4.5 MM


0.1100 kg Paku Sekrup 120,000.00 13,200.00
0.3640 lbr Kalsiboard 4.5 mm - -
0.1000 oh Pekerja 115,000.00 11,500.00
0.0500 oh Tukang Kayu 148,350.00 7,417.50
Total : 18,917.50 13,200.00 32,117.50

X PEKERJAAN SANITASI ( SNI 2002 )


1 MEMASANG 1 BUAH KLOSET DUDUK/MONOBLOK
1.0000 bh Kloset duduk/ monoblok 2,575,000.00 2,575,000.00
6% x harga kloset Perlengkapan 154,500.00
3.3000 oh Pekerja 115,000.00 379,500.00
1.1000 oh Tukang batu 142,600.00 156,860.00
Total : 536,360.00 2,729,500.00 3,265,860.00

2 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN


1.0000 bh Kloset jongkok porselen 450,000.00 450,000.00
6.0000 kg Semen Portland 1,875.00 11,250.00
0.0100 m3 Pasir Pasang 1,000,000.00 10,000.00
1.0000 oh Pekerja 115,000.00 115,000.00
1.5000 oh Tukang batu 142,600.00 213,900.00
Total : 328,900.00 471,250.00 800,150.00

3 MEMASANG 1 BUAH URINOIR


1.0000 bh Urinoir 1,052,000.00 1,052,000.00
6% x harga Urin Perlengkapan 63,120.00
6.0000 kg Semen Portland 1,875.00 11,250.00
0.0100 m3 Pasir Pasang 1,000,000.00 10,000.00
1.0000 oh Pekerja 115,000.00 115,000.00
1.0000 oh Tukang batu 142,600.00 142,600.00
Total : 257,600.00 1,136,370.00 1,393,970.00

4 MEMASANG 1 BUAH WASHTAFEL KIA


1.0000 bh Washtafel 595,000.00 595,000.00
12% x harga wast Perlengkapan 71,400.00
6.0000 kg Semen Portland 1,875.00 11,250.00
0.0100 m3 Pasir Pasang 1,000,000.00 10,000.00
1.2000 oh Pekerja 115,000.00 138,000.00
1.4500 oh Tukang batu 142,600.00 206,770.00
Total : 344,770.00 687,650.00 1,032,420.00

5 MEMASANG 1 BUAH BAK MANDI FIBREGLASS, VOLUME 0,30 M3


1.0000 bh Bak Fibreglass 350,000.00 350,000.00
18% x harga wast Perlengkapan 63,000.00
1.8000 oh Pekerja 115,000.00 207,000.00
2.7000 oh Tukang batu 142,600.00 385,020.00
Total : 592,020.00 413,000.00 1,005,020.00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

6 MEMASANG 1 M1 PIPA GALVANIS f 0,5" - 1 "


1.2000 m1 Pipa galvanis - -
35% x harga pipa Perlengkapan -
0.0540 oh Pekerja 115,000.00 6,210.00
0.0900 oh Tukang Pipa 148,350.00 13,351.50
Total : 19,561.50 - 19,561.50

7 MEMASANG 1 M1 PIPA GALVANIS f 1,5" - 3"


1.2000 M' Pipa galvanis 137,500.00 165,000.00
35% x harga pipa Perlengkapan 48,125.00
0.1080 Oh Pekerja 115,000.00 12,420.00
0.1800 Oh Tukang Pipa 148,350.00 26,703.00
Total : 39,123.00 213,125.00 252,248.00

8 MEMASANG 1 M1 PIPA PVC TYPE AW f 0,5" - 1,5"


1.2000 m1 Pipa PVC - -
35% x harga pipa Perlengkapan -
0.0360 oh Pekerja 115,000.00 4,140.00
0.0600 oh Tukang Pipa 148,350.00 8,901.00
Total : 13,041.00 - 13,041.00

9 MEMASANG 1 M1 PIPA PVC TYPE AW f 2"


1.2000 m1 Pipa PVC - -
35% x harga pipa Perlengkapan -
0.0540 oh Pekerja 115,000.00 6,210.00
0.0900 oh Tukang Pipa 148,350.00 13,351.50
Total : 19,561.50 - 19,561.50

10 MEMASANG 1 M1 PIPA PVC TYPE AW f 3" - 4"


1.2000 m1 Pipa PVC - -
35% x harga pipa Perlengkapan -
0.0810 oh Pekerja 115,000.00 9,315.00
0.1350 oh Tukang Pipa 148,350.00 20,027.25
Total : 29,342.25 - 29,342.25

11 MEMASANG 1 BUAH KRAN f 0,75" ATAU 0,5"


1.0000 bh Kran air 45,000.00 45,000.00
0.0250 bh Seal tape 15,000.00 375.00
0.0100 oh Pekerja 115,000.00 1,150.00
0.1000 oh Tukang Pipa 148,350.00 14,835.00
Total : 15,985.00 45,375.00 61,360.00

XI PEKERJAAN BESI DAN ALUMINIUM


(SNI 7393:2008)
1 1 KG PASANG RANGKA ATAP BAJA
1.1500 kg Besi Profil WF 16,500.00 18,975.00
0.0060 oh Pekerja 115,000.00 690.00
0.0600 oh Tukang besi 148,350.00 8,901.00
Total : 9,591.00 18,975.00 28,566.00

2 1 M2 PASANG JENDELA NAKO


1.1000 m2 Rangka + Kaca Nako 25,000.00 27,500.00
10.0000 bh Paku biasa 1 cm - 2,5 cm 120,000.00 1,200,000.00
7.0000 m' Besi strip 7,260.00 50,820.00
0.2000 oh Pekerja 115,000.00 23,000.00
0.2000 oh Tukang besi 148,350.00 29,670.00
Total : 52,670.00 1,278,320.00 1,330,990.00

3 1 M1 PASANG TALANG DATAR, SENG BJLS 28


1.0500 lbr Seng plat 22,000.00 23,100.00
0.0150 kg Paku biasa 0,5" - 1" 120,000.00 1,800.00
0.0190 m3 Kayu papan kelas II/III - -
0.1500 oh Pekerja 115,000.00 17,250.00
0.4000 oh Tukang besi 148,350.00 59,340.00
Total : 76,590.00 24,900.00 101,490.00

XII PEKERJAAN KUNCI DAN KACA (SNI 2002)


1 1 BH PASANG KUNCI TANAM BIASA
1.0000 bh Kunci tanam biasa 175,000.00 175,000.00
0.0100 oh Pekerja 115,000.00 1,150.00
0.5000 oh Tukang besi 148,350.00 74,175.00
Total : 75,325.00 175,000.00 250,325.00

2 1 PS PASANG ENGSEL PINTU


1.0000 ps Engsel pintu 20,000.00 20,000.00
0.0150 oh Pekerja 115,000.00 1,725.00
0.1500 oh Tukang besi 148,350.00 22,252.50
Total : 23,977.50 20,000.00 43,977.50
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

3 1 PS PASANG ENGSEL JENDELA KUPU-KUPU


1.0000 ps Engsel jendela 35,000.00 35,000.00
0.0100 oh Pekerja 115,000.00 1,150.00
0.1000 oh Tukang besi 148,350.00 14,835.00
Total : 15,985.00 35,000.00 50,985.00

4 1 BH PASANG KAIT ANGIN


1.0000 ps Kait angin 20,000.00 20,000.00
0.0150 oh Pekerja 115,000.00 1,725.00
0.1500 oh Tukang besi 148,350.00 22,252.50
Total : 23,977.50 20,000.00 43,977.50

5 1 BH PASANG KUNCI SLOT


1.0000 bh Kunci slot 28,000.00 28,000.00
0.0200 oh Pekerja 115,000.00 2,300.00
0.2000 oh Tukang besi 148,350.00 29,670.00
Total : 31,970.00 28,000.00 59,970.00

6 1 M2 PASANG KACA, TEBAL 3 - 5 MM


1.1000 bh Kaca 187,506.70 206,257.37
0.0150 oh Pekerja 115,000.00 1,725.00
0.1500 oh Tukang besi 148,350.00 22,252.50
Total : 23,977.50 206,257.37 230,234.87

XIII PEK. PENUTUP LANTAI DAN DINDING


(SNI 7395:2008)

1 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM


11.8700 bh Keramik 30 x 30 cm - -
10.0000 kg Semen Portland 1,875.00 18,750.00
0.0450 m3 Pasir Pasang 1,000,000.00 45,000.00
1.5000 kg Semen warna/semen grouting 13,000.00 19,500.00
0.7000 oh Pekerja 115,000.00 80,500.00
0.3500 oh Tukang batu 142,600.00 49,910.00
Total : 130,410.00 83,250.00 213,660.00

2 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM


26.5000 bh Keramik 20 x 20 cm 2,440.00 64,660.00
10.4000 kg Semen Portland 1,875.00 19,500.00
0.0450 m3 Pasir Pasang 1,000,000.00 45,000.00
1.6200 kg Semen warna/semen grouting 13,000.00 21,060.00
0.7000 oh Pekerja 115,000.00 80,500.00
0.3500 oh Tukang batu 142,600.00 49,910.00
Total : 130,410.00 150,220.00 280,630.00

3 1 M1 PASANG PLIN KERAMIK 10 X 30 CM


3.3300 bh Keramik 30 x 30 cm - -
1.1400 kg Semen Portland 1,875.00 2,137.50
0.0030 m3 Pasir Pasang 1,000,000.00 3,000.00
0.1000 kg Semen warna/semen grouting 13,000.00 1,300.00
0.0900 oh Pekerja 115,000.00 10,350.00
0.0900 oh Tukang batu 142,600.00 12,834.00
Total : 23,184.00 6,437.50 29,621.50
4 1 M2 PASANG DINDING KERAMIK 20 X 20 CM
26.5000 bh Keramik 20 x 20 cm 2,440.00 64,660.00
9.3000 kg Semen Portland 1,875.00 17,437.50
0.0180 m3 Pasir Pasang 1,000,000.00 18,000.00
1.9400 kg Semen warna/semen grouting 13,000.00 25,220.00
0.9000 oh Pekerja 115,000.00 103,500.00
0.4500 oh Tukang batu 142,600.00 64,170.00
Total : 167,670.00 125,317.50 292,987.50

5 1 M1 PASANG PLIN KAYU 2 X 10 CM


0.0030 m3 Papan Kayu Kelas II - -
0.0500 kg Paku sekrup 3,5' 170,000.00 8,500.00
0.1200 oh Pekerja 115,000.00 13,800.00
0.1200 oh Tukang kayu 148,350.00 17,802.00
Total : 31,602.00 8,500.00 40,102.00

XIV PEKERJAAN PENGECATAN (SNI 2002)


1 1 M2 PENGECATAN BIDANG KAYU BARU (1 LAPIS PLAMIR,
1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
0.2000 kg Cat meni 60,000.00 12,000.00
0.1500 kg Dempul 50,000.00 7,500.00
0.1700 kg Cat dasar 68,750.00 11,687.50
0.2600 kg Cat Penutup 2x 65,000.00 16,900.00
0.0700 oh Pekerja 115,000.00 8,050.00
0.0090 oh Tukang cat 148,350.00 1,335.15
Total : 9,385.15 48,087.50 57,472.65
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

2 1 M2 PENGECATAN BIDANG KAYU DENGAN VERNIS


0.1500 kg Vernis 80,000.00 12,000.00
0.0500 kg Dempul 50,000.00 2,500.00
0.1000 lbr Amplas 8,000.00 800.00
0.0100 bh Kuas 30,000.00 300.00
0.1600 oh Pekerja 115,000.00 18,400.00
0.1600 oh Tukang cat 148,350.00 23,736.00
Total : 42,136.00 15,600.00 57,736.00
3 1 M2 PENGECATAN TEMBOK BARU (1 LAPIS PLAMIR,
1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
0.1000 kg Plamir 11,000.00 1,100.00
0.1000 kg Cat dasar 68,750.00 6,875.00
0.2600 kg Cat Penutup 2x 24,000.00 6,240.00
0.0200 oh Pekerja 115,000.00 2,300.00
0.0630 oh Tukang cat 148,350.00 9,346.05
Total : 11,646.05 14,215.00 25,861.05

4 1 M2 PENGECATAN TEMBOK LAMA (1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)


0.1200 kg Cat dasar 68,750.00 8,250.00
0.1800 kg Cat Penutup 2x 24,000.00 4,320.00
0.0280 oh Pekerja 115,000.00 3,220.00
0.0420 oh Tukang cat 148,350.00 6,230.70
Total : 9,450.70 12,570.00 22,020.70

5 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI


0.1000 kg Meni besi 25,000.00 2,500.00
0.0100 lbr Kuas 30,000.00 300.00
0.0200 oh Pekerja 115,000.00 2,300.00
0.2000 oh Tukang cat 148,350.00 29,670.00
Total : 31,970.00 2,800.00 34,770.00

6 1 M2 PENGECATAN PERMUKAAN BAJA, 1 LAPIS DENGAN CAT BESI


0.3000 kg Cat besi 85,000.00 25,500.00
0.0060 oh Pekerja 115,000.00 690.00
0.0600 oh Tukang cat 148,350.00 8,901.00
Total : 9,591.00 25,500.00 35,091.00

7 1 M2 PELABURAN BIDANG KAYU DENGAN POLITUR


0.5220 ltr Politur 45,000.00 23,490.00
2.0000 lbr Amplas 8,000.00 16,000.00
0.0600 oh Pekerja 115,000.00 6,900.00
0.0600 oh Tukang cat 148,350.00 8,901.00

Total : 15,801.00 39,490.00 55,291.00

XV PEKERJAAN TETEMPELAN STYLE BALI

1 1 M2 PASANGAN BATA GOSOK 2 MUKA


110.0000 bh Bata Gosok 50,000.00 5,500,000.00
8.4000 kg Semen 50 Kg 1,875.00 15,750.00
Upah Kerja ( Lumpsum) 359,074.00 359,074.00
Total : 359,074.00 5,515,750.00 5,874,824.00

2 1 M2 PASANGAN PARAS KEROBOKAN 1 MUKA


13.7500 bh Paras Kerobokan - -
8.4000 kg Semen 50 Kg 1,875.00 15,750.00
Upah Kerja ( Lumpsum) 192,836.00 192,836.00
Total : 192,836.00 15,750.00 208,586.00

3 1 M2 PASANGAN BATA GOSOK 1 MUKA


55.0000 bh Paras Kerobokan 50,000.00 2,750,000.00
4.2000 kg Semen 50 Kg 1,875.00 7,875.00
Upah Kerja ( Lumpsum) 192,836.00 192,836.00
Total : 192,836.00 2,757,875.00 2,950,711.00

4 1 M2 PASANGAN PARAS 1 MUKA


18.3333 bh Batu paras - -
4.2000 kg Semen 50 Kg 1,875.00 7,875.00
Upah Kerja ( Lumpsum) 192,836.00 192,836.00
Total : 192,836.00 7,875.00 200,711.00

5 1 M2 PASANGAN PARAS + BATA GOSOK 1 MUKA


55.0000 bh Bata gosok 50,000.00 2,750,000.00
4.4917 bh Batu paras - -
5.2500 kg Semen 50 Kg 1,875.00 9,843.75
Upah Kerja ( Lumpsum) 192,836.00 192,836.00
Total : 192,836.00 2,759,843.75 2,952,679.75

6 1 M2 PASANGAN BATA GOSOK DIUKIR


55.0000 bh Bata gosok 50,000.00 2,750,000.00
4.2000 kg Semen 50 Kg 1,875.00 7,875.00
Upah Kerja ( Lumpsum) 383,674.00 383,674.00
Total : 383,674.00 2,757,875.00 3,141,549.00
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

7 1 M2 PASANGAN PARAS DIUKIR


18.3333 bh Batu paras - -
4.2000 kg Semen 50 Kg 1,875.00 7,875.00
Upah Kerja ( Lumpsum) 383,674.00 383,674.00
Total : 383,674.00 7,875.00 391,549.00

8 1 M2 PASANGAN PARAS + BATA GOSOK DIUKIR


55.0000 bh Bata gosok 50,000.00 2,750,000.00
4.4917 bh Batu paras - -
5.2500 kg Semen 50 Kg 1,875.00 9,843.75
Upah Kerja ( Lumpsum) 280,000.00 280,000.00
Total : 280,000.00 2,759,843.75 3,039,843.75

XVI PEKERJAAN LANDSCAPE

1 1 M2 PASANGAN PAVING BETON 10/20 CM TEBAL 6 CM K 225


1.0000 m2 Paving 10 x 20 cm tebal 8 cm K225 - -
0.2500 oh Tukang Batu 142,600.00 35,650.00
0.5000 oh Pekerja 115,000.00 57,500.00
Total : 93,150.00 - 93,150.00
2 Paving 10 x 20 cm tebal 6 cm K350 - 93,150.00 - 93,150.00
4 Paving 10 x 20 cm tebal 8 cm K225 - 93,150.00 - 93,150.00
5 Paving 10 x 20 cm tebal 8 cm K350 - 93,150.00 - 93,150.00
7 Paving 20 x 20 cm tebal 6 cm K225 - 93,150.00 - 93,150.00
8 Paving 20 x 20 cm tebal 6 cm K350 - 93,150.00 - 93,150.00
10 Paving 20 x 20 cm tebal 8 cm K225 - 93,150.00 - 93,150.00
11 Paving 20 x 20 cm tebal 8 cm K350 - 93,150.00 - 93,150.00
12 Paving 20 x 20 cm tebal 8 cm K425 - 93,150.00 - 93,150.00
14 Paving 20 x 20 cm tebal 10 cm K225 - 93,150.00 - 93,150.00
15 Paving 20 x 20 cm tebal 10 cm K350 - 93,150.00 - 93,150.00
16 Paving 20 x 20 cm tebal 10 cm K425 - 93,150.00 - 93,150.00
18 Paving Tiga Berlian tebal 6 cm K225 - 93,150.00 - 93,150.00
19 Paving Tiga Berlian tebal 6 cm Standar - 93,150.00 - 93,150.00

20 1 M2 PASANGAN GRASS BLOCK


1.0000 m2 Grass Block - -
0.0690 m3 Pasir Urug 500,000.00 34,500.00
0.5000 oh Tukang Batu 142,600.00 71,300.00
1.0000 oh Pekerja 115,000.00 115,000.00
Total : 186,300.00 34,500.00 220,800.00

21 1 M2 PASANGAN KORAL SIKAT


1.2000 zak Koral Sikat - -
9.2800 zak Semen 1,875.00 17,400.00
0.2000 m3 Pasir pasang 1,000,000.00 200,000.00
0.2500 oh Tukang Batu 142,600.00 35,650.00
0.6250 oh Pekerja 115,000.00 71,875.00
Total : 107,525.00 217,400.00 324,925.00
22 1 M1 KANSTEIN BULAT (50 x 30 x 10 ) CM K225
1.0000 m1 Kanstein Bulat(P:50,T:30,La:10,Lb:16 cm K225 - -
0.4500 zak Semen 50 Kg 1,875.00 843.75
0.0023 m3 Pasir Pasang 1,000,000.00 2,300.00
0.3500 oh Tukang Batu 142,600.00 49,910.00
0.9500 oh Pekerja 115,000.00 109,250.00
Total : 159,160.00 3,143.75 162,303.75
23 Kanstein Jumbo (P:50,L:15,T:30 cm K225) - 159,160.00 217,400.00 376,560.00
24 Kanstein Segi Lima Jumbo (P:50,L:15, T:40 cm K225) - 159,160.00 217,400.00 376,560.00

25 1 M2 PENGECATAN KANSTEIN
0.2840 kg Cat 85,000.00 24,140.00
0.0710 kg Thiner 40,000.00 2,840.00
0.0300 oh Tukang Cat 148,350.00 4,450.50
0.1500 oh Pekerja 115,000.00 17,250.00
Total : 21,700.50 26,980.00 48,680.50
HARGA HARGA HARGA HARGA
NO URAIAN SATUAN UPAH BAHAN JUMLAH
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6

XVII PEKERJAAN ELEKTRIKAL

1 1 TITIK INSTALASI STOP KONTAK, LAMPU, EXHAUST FAN DAN CEILING FAN
8.0000 m1 Kabel NYM 3 x 2.5 mm ex. Supreme 16,000.00 128,000.00
3.0000 bt Pipa Clipsal 20 mm hitam 25,000.00 75,000.00
2.0000 bh Tee dos clipsal 20 mm hitam 10,000.00 20,000.00
15.0000 bj Klem clipsal 20 mm hitam 5,000.00 75,000.00
3.0000 bj Sock clipsal 20 mm hitam 4,000.00 12,000.00
1.0000 bj Inbow dos plastik clipsal E 157 P 13,000.00 13,000.00
1.0000 ttk Biaya pasang 25,000.00 25,000.00
Total : 25,000.00 323,000.00 348,000.00

2 1 TITIK INSTALASI AC
10.0000 m1 Kabel NYM 3 x 2.5 mm ex. Supreme 41,000.00 410,000.00
3.0000 bt Pipa Clipsal 20 mm hitam 25,000.00 75,000.00
1.0000 bh Tee dos clipsal 20 mm hitam 10,000.00 10,000.00
15.0000 bj Klem clipsal 20 mm hitam 5,000.00 75,000.00
4.0000 bj Sock clipsal 20 mm hitam 4,000.00 16,000.00
1.0000 bj Inbow dos plastik clipsal E 157 P 13,000.00 13,000.00
1.0000 m1 Pipa flexible clipsal 20 mm hitam 40,000.00 40,000.00
1.0000 ttk Biaya pasang 25,000.00 25,000.00 25,000.00
Total : 25,000.00 664,000.00 689,000.00

3 1 TITIK INSTALASI TELEPHONE


25.0000 m1 Kabel telephone 5,000.00 125,000.00
8.0000 bt Pipa Clipsal 20 mm putih 25,000.00 200,000.00
1.0000 bh Tee dos clipsal 20 mm putih 10,000.00 10,000.00
25.0000 bj Klem clipsal 20 mm putih 5,000.00 125,000.00
5.0000 bj Sock clipsal 20 mm putih 4,000.00 20,000.00
1.0000 bj Inbow dos plastik clipsal E 157 P 13,000.00 13,000.00
1.0000 ttk Biaya pasang 25,000.00 25,000.00
Total : 25,000.00 493,000.00 518,000.00

4 1 TITIK INSTALASI MATV


20.0000 m1 Coaxial cable 5C-75 ohm commscof 5,700.00 114,000.00
6.0000 bt Pipa Clipsal 20 mm putih 25,000.00 150,000.00
2.0000 bh Tee dos clipsal 20 mm putih 10,000.00 20,000.00
20.0000 bj Klem clipsal 20 mm putih 5,000.00 100,000.00
6.0000 bj Sock clipsal 20 mm putih 4,000.00 24,000.00
1.0000 bj Inbow dos plastik clipsal E 157 P 13,000.00 13,000.00
1.0000 ttk Biaya pasang 25,000.00 25,000.00
Total : 25,000.00 421,000.00 446,000.00

Mengetahui
Kepala Dinas Cipta Karya
Kabupaten Badung

Ir. Ni Luh Putu Dessy Dharmayanty, M.T


Pembina
NIP. 196110101994032001
REKAPITULASI DAFTAR HARGA SATUAN PEKERJAAN SWAKLOLA
TAHUN 2018

NO URAIAN PEKERJAAN HARGA


1 2 3
I PEKERJAAN PERSIAPAN (SNI 03-2835-2002)
1 1 M1 PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 METER Rp. 206,620.00
2 1 M1 PENGUKURAN DAN PEMASANGAN BOWPLANK Rp. 26,735.00
3 1 M2 PEMBUATAN KANTOR SEMENTARA, DENGAN LANTAI PLESTERAN Rp. 1,606,536.54
4 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT Rp. 561,012.50
5 1 M2 PEMBUATAN RUMAH JAGA/KONSTRUKSI KAYU Rp. 396,525.00
6 1 M2 MEMBERSIHKAN LAPANGAN DAN PERATAAN Rp. 11,500.00
7 1 M2 PEMBUATAN BEDENG BURUH Rp. 872,075.00
8 1 M2 PEMBUATAN BAK ADUKAN UKURAN (40X50X20) CM Rp. 46,105.00
9 1 M2 PEMBUATAN STEGGER DARI BAMBU Rp. 24,501.95
10 1 M2 PEMBUATAN JALAN SEMENTARA Rp. #REF!
11 1 M3 BONGKARAN BETON BERTULANG Rp. 766,705.00
12 1 M3 BONGKARAN DINDING TEMBOK BATU TELA Rp. 766,705.00

II PEKERJAAN TANAH (SNI 2835 : 2008)


1 1 M3 GALIAN TANAH BIASA DALAM 1 METER Rp. 86,250.00
2 1 M3 GALIAN TANAH BIASA DALAM 2 METER Rp. 103,500.00
3 1 M3 GALIAN TANAH BIASA DALAM 3 METER Rp. 120,750.00
4 1 M3 GALIAN TANAH KERAS DALAM 1METER Rp. 115,000.00
5 1 M3 GALIAN TANAH CADAS DALAM 1 METER Rp. 172,500.00
6 1 M3 GALIAN TANAH LUMPUR DALAM 1 METER Rp. 138,000.00
7 1 M2 PEKERJAAN STRIPPING SETINGGI 1 METER Rp. 5,750.00
8 1 M3 PEMBUANGAN TANAH SEJAUH 15 METER Rp. 37,950.00
9 1 M3 URUGAN KEMBALI Rp. -
10 1 M3 PEMADATAN TANAH ( Per 20 Cm ) Rp. 634,500.00
11 1 M3 URUGAN PASIR Rp. 634,500.00
12 1 M3 PEMASANGAN LAPISAN IJUK TEBAL 10 CM Rp. 137,250.00
13 1 M3 URUGAN SIRTU PADAT Untuk Peninggian Lantai Bangunan Rp. 328,750.00
14 1 M3 URUGAN TANAH PILIHAN DIPADATKAN Rp. 237,500.00
15 1 M3 URUGAN LIMESTONE PADAT Rp. 123,550.00

III PEKERJAAN PONDASI (SNI 2836 : 2008)


1 1 M3 BATU KALI CAMP. 1 PC : 3 PS Rp. 1,743,200.00
2 1 M3 BATU KALI CAMP. 1 PC : 4 PS Rp. 1,705,075.00
3 1 M3 BATU KALI CAMP. 1 PC : 5 PS Rp. 1,678,450.00
4 1 M3 BATU KALI CAMP. 1 PC : 6 PS Rp. 1,659,825.00
5 1 M3 BATU KALI CAMP. 1 PC : 8 PS Rp. 1,634,075.00
6 1 M3 PASANGAN PONDASI SIKLOP, 40% BATU KALI Rp. 3,688,033.55
7 1 M3 PASANGAN PONDASI SUMURAN DIAMETER 1 M Rp. 1,944,080.00
8 1 M3 PASANGAN BATU KOSONG Rp. 1,393,314.00

IV PEKERJAAN DINDING (SNI 6897 : 2008)


1 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 2 PS Rp. 1,379,082.50
2 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 3 PS Rp. 1,370,301.25
3 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 4 PS Rp. 1,360,301.25
4 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 5 PS Rp. 1,361,145.00
NO URAIAN PEKERJAAN HARGA
1 2 3
5 1 M2 PASANGAN BATU TELA TEBAL 1 TELA CAMP. 1 PC : 6 PS Rp. 1,374,207.50
6 1 M2 PASANGAN BATU TELA TEBAL 1/2 TELA CAMP. 1 PC : 2 PS Rp. 682,291.25
7 1 M2 PASANGAN BATU TELA TEBAL 1/2 TELA CAMP. 1 PC : 3 PS Rp. 675,703.75
8 1 M2 PASANGAN BATU TELA TEBAL 1/2 TELA CAMP. 1 PC : 4 PS Rp. 673,322.50
9 1 M2 PASANGAN BATU TELA TEBAL 1/2 TELA CAMP. 1 PC : 5 PS Rp. 671,910.00
10 1 M2 PASANGAN BATU TELA TEBAL 1/2 TELA CAMP. 1 PC : 6 PS Rp. 673,360.00
11 1 M2 PASANGAN BATU TELA TEBAL 1/2 TELA CAMP. 1 PC : 8 PS Rp. 670,947.50
12 1 M2 PASANGAN DINDING HOLLOWBLOCK (HB. 10) Rp. 216,293.58
13 1 M2 PASANGAN DINDING HOLLOWBLOCK (HB. 10) TANPA BESI Rp. 192,122.50
14 1 M2 PASANGAN DINDING Terawang/Roster (12 x 11 x 24) CM Rp. 2,654,385.00
15 1 M2 PASANGAN DINDING BEDEG, RANGKA KAYU Rp. 50,657.50

V PEKERJAAN PLESTERAN (SNI 2837 : 2008)


1 1 M2 PLESTERAN CAMP. 1 PC : 1 PS TEBAL 15 MM Rp. 100,960.00
2 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 15 MM Rp. 95,060.00
3 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 15 MM Rp. 93,470.00
4 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 15 MM Rp. 91,590.00
5 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 15 MM Rp. 91,610.00
6 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 15 MM Rp. 91,170.00
7 1 M2 PLESTERAN CAMP. 1 PC : 8 PS TEBAL 15 MM Rp. 91,370.00
8 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 20 MM Rp. 127,080.00
9 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 20 MM Rp. 124,960.00
10 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 20 MM Rp. 122,120.00
11 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 20 MM Rp. 122,480.00
12 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 20 MM Rp. 121,560.00
13 1 M2 PLESTERAN SKONING 1 PC : 2 PS, TEBAL 10 MM Rp. 80,177.50
14 1 M2 PLESTERAN CIPRAT 1 PC : 2 PS Rp. 62,860.00
15 1 M2 FINISHING SIAR PASANGAN DINDING BATU TELA (=20 M') Rp. 33,772.50
16 1 M2 FINISHING SIAR PASANGAN DINDING CONBLOCK EKSPOSE (= 8 M') Rp. 16,041.00
17 1 M2 FINISHING SIAR PASANGAN BATUKALI/BELAH ADUKAN 1PC : 2 PS Rp. 79,777.50
18 1 M2 PEKERJAAN ACIAN Rp. 20,928.75

VI PEKERJAAN KAYU (SNI 3434 : 2008)


1 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS I (KA Rp. 3,997,850.00
2 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS II/III Rp. 3,437,800.00
3 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP STANDAR KAYU KELAS II (KAYU Rp. 197,517.50
4 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP SEDERHANA KAYU KELAS III (KA Rp. 197,517.50
5 MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU KELAS I/II (KAYU BESRp. 580,050.00
6 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA, KAYU KELAS I/II (K Rp. 460,040.00
7 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA JALUSI, KAYU KELAS I/II ( Rp. 580,050.00
8 MEMBUAT 1 M2 DAUN PINTU TEAKWOOD RANGKAP RANGKA TERTUTUP, KAYU
KELAS II (Lebar Sampai 90 Cm) Rp. 805,950.00
9 MEMBUAT 1 M2 DAUN PINTU TEAKWOOD RANGKAP RANGKA EXPOSE, KAYU
KELAS I/II Rp. 693,940.00
10 MEMASANG 1 M2 JALUSI KUSEN, KAYU KELAS I/II Rp. 378,250.00
11 MEMBUAT 1 M2 TEAKWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS I Rp. 566,940.00
12 MEMBUAT 1 M2 TEAKWOOD RANGKAP LAPIS FORMIKA RANGKA EXPOSE,
KAYU KELAS II Rp. 626,440.00
13 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KELAS
I,II,III Bentang 6 M' Rp. 2,517,100.00
NO URAIAN PEKERJAAN HARGA
1 2 3
14 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA EXPOSE, KAYU KELAS I Rp. 4,029,235.00
15 MEMASANG 1 M3 KONSTRUKSI GORDENG, KAYU KELAS II Rp. 1,543,020.00
16 MEMASANG 1 M2 RANGKA ATAP GENTENG KERAMIK, KAYU KELAS II Rp. 33,835.00
17 MEMASANG 1 M2 RANGKA ATAP GENTENG BETON, KAYU KELAS II Rp. 33,835.00
18 MEMASANG 1 M2 RANGKA ATAP SIRAP, KAYU KELAS II Rp. 37,602.00
19 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (50 X 100), KAYU KELAS II/III Rp. 67,755.00
20 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (60 X 60) CM, KAYU KELAS II/III Rp. 75,005.00
21 MEMASANG 1 M' LISPLANK UKURAN (3 X 20) CM, KAYU KELAS I/II Rp. 44,170.00
22 MEMASANG 1 M' LISPLANK UKURAN (3 X 30) CM, KAYU KELAS I/II Rp. 42,670.00
23 MEMASANG 1 M2 RANGKA DINDING PEMISAH (60 X 120) CM, KAYU KELAS II/III Rp. 88,507.50
MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA
24 KAYU KELAS II Rp. 195,187.50
MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD RANGKAP, RANGKA
25 KAYU KELAS II Rp. 332,410.00
26 MEMASANG 1 M2 LAMBRIZIRING DARI PAPAN KAYU KELAS I Rp. 339,030.00
27 MEMASANG 1 M2 LAMBRIZIRING DARI PLYWOOD UKURAN (120 X 240) CM Rp. 105,501.25

VII PEKERJAAN BETON ( SNI 7394:2008)


1 1 M3 MEMBUAT BETON 1 PC : 3 PS : 5 KR Rp. 2,338,525.00
2 1 M3 MEMBUAT BETON 1 PC : 2 PS : 4 KR Rp. 2,269,150.00
3 1 M3 MEMBUAT BETON 1 PC : 2 PS : 3 KR Rp. 2,381,650.00
4 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR Rp. 152,336.46
5 1 M2 PASANG BEKISTING UNTUK PONDASI Rp. 105,871.00
6 1 M2 PASANG BEKISTING UNTUK SLOOF Rp. 105,871.00
7 1 M2 PASANG BEKISTING UNTUK KOLOM Rp. 309,355.50
8 1 M2 PASANG BEKISTING UNTUK BALOK Rp. 309,355.50
9 1 M2 PASANG BEKISTING UNTUK LANTAI Rp. 453,355.50
10 1 M2 PASANG BEKISTING UNTUK DINDING Rp. 353,355.50
11 1 M2 PASANG BEKISTING UNTUK TANGGA Rp. 308,605.50
12 1 M2 PASANG JEMBATAN UNTUK PENGECORAN BETON Rp. 54,667.50
13 1 M3 MEMBUAT PONDASI BETON BERTULANG (150 KG BESI + BEKISTING) Rp. 5,336,294.23
14 1 M3 MEMBUAT SLOOF BETON BERTULANG (200 KG + BEKISTING) Rp. 6,155,745.26
15 1 M3 MEMBUAT KOLOM BETON BERTULANG (300 KG BESI + BEKISTING) Rp. 9,568,961.38
16 1 M3 MEMBUAT BALOK BETON BERTULANG (200 KG BESI + BEKISTING) Rp. 7,676,596.76
17 1 M3 MEMBUAT PLAT BETON BERTULANG (150 KG BESI + BEKISTING Rp. 7,358,491.94
18 1 M3 MEMBUAT DINDING BETON BERTULANG (150 KG BESI + BEKISTING) Rp. 7,064,294.23
19 1 M3 MEMBUAT DINDING BETON BERTULANG (200 KG BESI + BEKISTING) Rp. 7,413,745.26
20 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (11 X 11 CM) Rp. 94,059.78
21 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (10 X 15 CM) Rp. 134,675.43

VIII PEKERJAAN PENUTUP ATAP (SNI 03-3436-2002)


1 1 M2 PEKERJAAN ATAP GENTENG PLENTONG Rp. #REF!
2 1 M2 PEKERJAAN ATAP GENTENG PLENTONG DI CAT Rp. #REF!
3 1 M1 PASANG BUBUNGAN GENTENG PLENTONG Rp. #REF!
4 1 M2 PASANG ATAP GENTENG ASBES GELOMBANG 1.8 M X 0.92 M X 5 MM Rp. 53,934.50
5 1 M1 PASANG BUBUNGAN STEL GELOMBANG 0.92 M Rp. 1,105,803.75
6 1 M2 PEKERJAAN ATAP SIRAP Rp. 674,177.50
7 1 M2 PEKERJAAN ATAP NOK SIRAP Rp. 63,062.50
8 1 M2 PASANG ATAP ALANG-ALANG 3 M1 Rp. 45,500.00
9 1 M2 PEKERJAAN ATAP SENG GELOMBANG Rp. 23,301.00
NO URAIAN PEKERJAAN HARGA
1 2 3
10 1 M2 PASANGAN LAPISANG ALUMINIUM FOIL Rp. 55,117.50
11 1 M1 PASANG NOK SENG GELOMBANG Rp. 35,434.50

IX PEKERJAAN LANGIT - LANGIT (SNI 2839-2008)


1 MEMASANG 1 M2 LANGIT-LANGIT ETERNIT, TEBAL 4 MM, 5 MM DAN 6 MM Rp. 65,834.50
2 1 M2 PASANG LANGIT-LANGIT TRIPLEKS 120X240 CM/4MM Rp. 111,610.00
3 1 M2 PASANG LANGIT-LANGIT LAMBRIZIRING Rp. 210,980.00
4 1 M1 PASANG LIST LANGIT-LANGIT KAYU PROFIL Rp. 25,251.50
5 1 M2 PASANG LANGIT-LANGIT ASBES + RANGKA Rp. 120,822.40
6 1 M2 PASANG LANGIT-LANGIT GYPSUM BOARD UKURAN (1200X2400X9) MM Rp. 32,117.50
7 1 M2 PASANG LANGIT-LANGIT KALSIBOARD 4.5 MM Rp. 32,117.50

X PEKERJAAN SANITASI ( SNI 2002 )


1 MEMASANG 1 BUAH KLOSET DUDUK/MONOBLOK Rp. 3,265,860.00
2 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN Rp. 800,150.00
3 MEMASANG 1 BUAH URINOIR Rp. 1,393,970.00
4 MEMASANG 1 BUAH WASHTAFEL KIA Rp. 1,032,420.00
5 MEMASANG 1 BUAH BAK MANDI FIBREGLASS, VOLUME 0,30 M3 Rp. 1,005,020.00
6 MEMASANG 1 M1 PIPA GALVANIS f 0,5" - 1 " Rp. 19,561.50
7 MEMASANG 1 M1 PIPA GALVANIS f 1,5" - 3" Rp. 252,248.00
8 MEMASANG 1 M1 PIPA PVC TYPE AW f 0,5" - 1,5" Rp. 13,041.00
9 MEMASANG 1 M1 PIPA PVC TYPE AW f 2" Rp. 19,561.50
10 MEMASANG 1 M1 PIPA PVC TYPE AW f 3" - 4" Rp. 29,342.25
11 MEMASANG 1 BUAH KRAN f 0,75" ATAU 0,5" Rp. 61,360.00

XI PEKERJAAN BESI DAN ALUMINIUM (SNI 7393:2008)


1 1 KG PASANG RANGKA ATAP BAJA Rp. 28,566.00
2 1 M2 PASANG JENDELA NAKO Rp. 1,330,990.00
3 1 M1 PASANG TALANG DATAR, SENG BJLS 28 Rp. 101,490.00

XII PEKERJAAN KUNCI DAN KACA (SNI 2002)


1 1 BH PASANG KUNCI TANAM BIASA Rp. 250,325.00
2 1 PS PASANG ENGSEL PINTU Rp. 43,977.50
3 1 PS PASANG ENGSEL JENDELA KUPU-KUPU Rp. 50,985.00
4 1 BH PASANG KAIT ANGIN Rp. 43,977.50
5 1 BH PASANG KUNCI SLOT Rp. 59,970.00
6 1 M2 PASANG KACA, TEBAL 3 - 5 MM Rp. 230,234.87

XIII PEK. PENUTUP LANTAI DAN DINDING (SNI 7395:2008)


1 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM Rp. 213,660.00
2 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM Rp. 280,630.00
3 1 M1 PASANG PLIN KERAMIK 10 X 30 CM Rp. 29,621.50
4 1 M2 PASANG DINDING KERAMIK 20 X 20 CM Rp. 292,987.50
5 1 M1 PASANG PLIN KAYU 2 X 10 CM Rp. 40,102.00

XIV PEKERJAAN PENGECATAN (SNI 2002)


1 1 M2 PENGECATAN BIDANG KAYU BARU (1 LAPIS PLAMIR, Rp. 57,472.65
1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
2 1 M2 PENGECATAN BIDANG KAYU DENGAN VERNIS Rp. 57,736.00
NO URAIAN PEKERJAAN HARGA
1 2 3
3 1 M2 PENGECATAN TEMBOK BARU (1 LAPIS PLAMIR, Rp. 25,861.05
1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
4 1 M2 PENGECATAN TEMBOK LAMA (1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) Rp. 22,020.70
5 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI Rp. 34,770.00
6 1 M2 PENGECATAN PERMUKAAN BAJA, 1 LAPIS DENGAN CAT BESI Rp. 35,091.00
7 1 M2 PELABURAN BIDANG KAYU DENGAN POLITUR Rp. 55,291.00

XV PEKERJAAN TETEMPELAN STYLE BALI


1 1 M2 PASANGAN BATA GOSOK 2 MUKA Rp. 5,874,824.00
2 1 M2 PASANGAN PARAS KEROBOKAN 1 MUKA Rp. 208,586.00
3 1 M2 PASANGAN BATA GOSOK 1 MUKA Rp. 2,950,711.00
4 1 M2 PASANGAN PARAS 1 MUKA Rp. 200,711.00
5 1 M2 PASANGAN PARAS + BATA GOSOK 1 MUKA Rp. 2,952,679.75
6 1 M2 PASANGAN BATA GOSOK DIUKIR Rp. 3,141,549.00
7 1 M2 PASANGAN PARAS DIUKIR Rp. 391,549.00
8 1 M2 PASANGAN PARAS + BATA GOSOK DIUKIR Rp. 3,039,843.75

XVI PEKERJAAN LANDSCAPE


1 1 M2 PASANGAN PAVING BETON 10/20 CM TEBAL 6 CM K 225 Rp. 93,150.00
2 Paving 10 x 20 cm tebal 6 cm K350 Rp. 93,150.00
3 Paving 10 x 20 cm tebal 8 cm K225 Rp. 93,150.00
4 Paving 10 x 20 cm tebal 8 cm K350 Rp. 93,150.00
5 Paving 20 x 20 cm tebal 6 cm K225 Rp. 93,150.00
6 Paving 20 x 20 cm tebal 6 cm K350 Rp. 93,150.00
7 Paving 20 x 20 cm tebal 8 cm K225 Rp. 93,150.00
8 Paving 20 x 20 cm tebal 8 cm K350 Rp. 93,150.00
9 Paving 20 x 20 cm tebal 8 cm K425 Rp. 93,150.00
10 Paving 20 x 20 cm tebal 10 cm K225 Rp. 93,150.00
11 Paving 20 x 20 cm tebal 10 cm K350 Rp. 93,150.00
12 Paving 20 x 20 cm tebal 10 cm K425 Rp. 93,150.00
13 Paving Tiga Berlian tebal 6 cm K225 Rp. 93,150.00
14 1 M2 PASANGAN GRASS BLOCK Rp. 220,800.00
15 1 M2 PASANGAN KORAL SIKAT Rp. 324,925.00
16 1 M1 KANSTEIN BULAT (50 x 30 x 10 ) CM K225 Rp. 162,303.75
17 Kanstein Jumbo (P:50,L:15,T:30 cm K225) Rp. 376,560.00
18 Kanstein Segi Lima Jumbo (P:50,L:15, T:40 cm K225) Rp. 376,560.00
19 1 M2 PENGECATAN KANSTEIN Rp. 48,680.50

XVII PEKERJAAN ELEKTRIKAL


1 1 TITIK INSTALASI STOP KONTAK, LAMPU, EXHAUST FAN DAN CEILING FAN Rp. 348,000.00
2 1 TITIK INSTALASI AC Rp. 689,000.00
3 1 TITIK INSTALASI TELEPHONE Rp. 518,000.00
4 1 TITIK INSTALASI MATV Rp. 446,000.00

Kepala Dinas Cipta Karya


Kabupaten Badung
NO URAIAN PEKERJAAN HARGA
1 2 3
Ir. Ni Luh Putu Dessy Dharmayanty, M.T
Pembina
NIP. 196110101994032001
DAFTAR HARGA SATUAN BAHAN TAMBAHAN
BULAN APRIL TAHUN 2010
A. Harga Satuan Bahan

NO NAMA BARANG SATUAN HARGA SATUAN


1 2 3 4

BATU
Batu Candi
1 20x20x2 m2 78,000.00
2 15x30x2 m2 78,000.00
3 20x30x2 m2 78,000.00
4 20x40x2 m2 80,000.00
5 30x30x2 m2 80,000.00
6 40x40x2 m2 105,000.00
7 30x60x2 m2 115,000.00
8 20x40x3 m2 135,000.00
9 30x30x3 m2 135,000.00
10 30x30x5 m2 165,000.00
11 40x40x5 m2 185,000.00

Palimanan putih
1 20x20x2 m2 65,000.00
2 20x30x2 m2 67,000.00
3 20x40x2 m2 68,000.00
4 20x40x3 m2 110,000.00
5 30x30x3 m2 110,000.00

Palimanan Serat Kuning


1 20x30 m2 75,000.00
2 20x40 m2 75,000.00
3 15x30 m2 75,000.00

Palimanan Cirebon
1 15x30x2 m2 72,000.00
2 20x30x2 m2 73,000.00
3 20x40x2 m2 75,000.00
4 30x30x2 m2 80,000.00

Alur Bali Green Lurus


1 20x30 m2 105,000.00
2 20x40 m2 105,000.00

Alur Bali Green Cukil


1 20x30 m2 105,000.00
2 20x40 m2 105,000.00
3 20x20 m2 105,000.00

Batu Bali Green


1 15x30 m2 75,000.00
2 20x30 m2 75,000.00
3 20x40 m2 75,000.00
4 40x40 m2 80,000.00

PARAS
Paras Kerobokan
1 20x40x3 Bj 6,000.00
2 20x40x5 Bj 8,000.00

Paras Kelating
1 20x40x3 Bj 6,000.00
2 20x40x5 Bj 8,000.00

Alur Andesit Lurus


1 20x40 m3 135,000.00
2 30x60 m3 140,000.00

Alur and cukil


1 20x40 m2 135,000.00
2 15x30 m2 135,000.00

Harga Barang dan Upah Hal. 148


NO NAMA BARANG SATUAN HARGA SATUAN
1 2 3 4
Alur And Gelombang m2 140,000.00
Alur And Gelombang lurus m2 140,000.00

Random Singaraja m2 25,000.00


Random Cirebon m2 65,000.00
Random Jember m2 45,000.00

Harga Barang dan Upah Hal. 149


LAMPIRAN
SUMBER DATA
NO KABUPATEN SUMBER DATA ALAMAT
1 Badung Utara - UD. Ubud Sari Jaya Jl. Raya Sangeh Petang
- UD. Surya Br. Plakan Sibang Kaja
- Dwi Putri Jl. Darmasaba - Lukluk

2 Badung Tengah - UD. Ron Anyar Jl. Raya Canggu, Kerobokan


- Mitra 10 Jl. Gatsu Barat
- PT. Budi Aluh Jl. Raya Kapal
- CV. Mertanadi Br. Perang Sempidi
- Karya Indah Jl. Raya Kapal

3 Badung Selatan - Indah Jaya Jl. Bay Pass Nusa Dua No. 69
- Dewa Brata Jl. Raya Kuta
- Mekar Abadi Bangunan Jl. Bay Pass Nusa Dua
DAFTAR HARGA SATUAN UPAH
TAHUN 2016
HARGA
NO NAMA BARANG SPESIFIKASI SATUAN
(Rp.)
1 2 3 4 5

1 Mandor Hari 156,960.00


2 Kepala Tukang Hari 143,880.00
3 Tukang Politur Hari 130,800.00
4 Tukang Batu Hari 117,720.00
5 Tukang kayu Hari 130,800.00
6 Tukang Besi Hari 130,800.00
7 Tukang cat Hari 130,800.00
8 Tukang gali/buruh/ pekerja Hari 98,100.00
9 Tukang Listrik Hari 130,800.00
10 Tukang Pipa/ Tukang Ledeng Hari 130,800.00
11 Tukang Aspal Hari 130,800.00
12 Tukang masak Aspal/pekerja Hari 98,100.00
13 Pekerja Hari 98,100.00
14 Tukang Ukir Hari 130,800.00
15 Operator Hari 130,800.00
16 Pembantu Operator Hari 98,100.00
17 Mekanik Hari 130,800.00
18 Pembantu Mekanik Hari 98,100.00
19 Pasang Atap Alang-Alang Hari 130,800.00
20 Pasang Bata Gosok Dua Muka M2 388,477.08
21 Pasang Bata Gosok Satu Muka M2 208,626.54
22 Pasang Batu Paras Diukir M2 415,165.80
23 Pasang Patu Paras Siap Diukir M2 359,701.08
24 Tukang Bongkar Begesting Hari 98,100.00

Catatan :

Harga - harga hanya sebagai pedoman / pendukung


dalam perhitungan konstruksi ( tidak mengikat ).
UMP PROV. PAPUA BARAT 2016 2,237,000.00
SEKTOR PERTAMBANGAN MINYAK DAN GAS BUMI 2,943,000.00
SEKTOR PERTAMBANGAN KECUALI GALIAN C 2,507,000.00
SEKTOR KEHUTANAN, PERKEBUNAN, DAN
PERIKANAN 2,343,500.00
SEKTOR JASA KONSTRUKSI 2,452,500.00
Undang -undang no. 13 tahun 2003 tentang "ketenagakerjaan"
Jika dalam 1 hari bekerja selama 8 jam (5 hari kerja/ senin s/d jumat) maka dalam 1 bulan bekerja selama 21 hari
Jika dalam 1 hari bekerja selama 7 jam (6 hari kerja/ senin s/d sabtu) maka dalam 1 bulan bekerja selama 25 hari

Fakfak, 25 April 2016

PANITIA PENYUSUNAN STANDART HARGA SATUAN


TAHUN 2016

Sekretaris, Ketua,

RIZAL MINGGELE, ST LIZA NEIRASARI, ST


NIP. 19820701 200909 1 001 NIP. 19751016 200111 2 001

Mengetahui,
Plh. Kepala Dinas Pekerjaan Umum
Kabupaten Fakfak ,

ANTHON UBRA, SE
NIP. 19580726 197807 1 001
DAFTAR HARGA SATUAN BAHAN BANGUNAN
TAHUN 2009

NO NAMA BARANG SATUAN HARGA


1 2 4 5
1 Gedeg Klas I m2
2 Genteng Beton bj
3 Genteng Bubungan Lokal bj
4 Genteng Bubungan Beton bj
5 Genteng Bubungan Karang Pilang bj
6 Genteng Bubungan Plentong bj
7 Genteng Kaca bj
8 Genteng Kodok bj
9 Genteng Lokal bj
10 Genteng Plentong bj
11 Genteng Plentong Dicat bj
12 Batu Bata Pasangan Kelas I bh
13 Batu Belah 15-30 cm m3
14 Batu Karang m3
15 Batu Lahar Merah Singaraja m3
16 Batu Padas bh
17 Batu Pipih Singaraja m3
18 Batu Pecah 0.5 - 1 cm m3
19 Batu Pecah 1 - 2 cm m3
20 Batu Pecah 2 - 3 cm (Manual, Mesin) m3
21 Batu Pecah 3 - 5 cm (Manual, Mesin) m3
22 Batu Pecah 5 - 7 cm (Manual) m3
23 Batu Pecah 7 - 10 cm m3
24 Besi Beton kg
25 Kayu Albesia Balok m3
26 Kayu Albesia Papan / Usuk m3
27 Kayu Bingkirai Balok m3
28 Kayu Bingkirai Papan / Usuk / Reng m3
29 Kayu Dolken (Pekerjaan Sementara) btg
30 Kayu Jati Balok m3
31 Kayu Jati Papan m3
32 Kayu Kamper Balok m3
33 Kayu Kamper Papan/ Usuk / Reng m3
34 Kayu Kruing Balok m3
35 Kayu Kruing Papan / Usuk / Reng m3
36 Kayu Meranti Balok m3
37 Kayu Meranti Papan / Usuk / Reng m3
38 Kayu Merbau Balok m3
39 Kayu Merbau Papan m3
40 Kayu Perancah / Begesting m3
41 Kayu Profil m1
42 Pasir Beton m3
43 Pasir Pasang m3
44 Pasir Urug m3
45 Semen PC 40 Kg kg
46 Semen PC 50 Kg kg
47 Semen warna/semen grouting kg
1481900
5400000
28000000
399400
1890000
534000

37,705,300

5400