B. LANTAI 2
I Pekerjaan Struktur Beton dan Baja 26.606903 6.65173 6.65173 6.65173 6.65173
II. Pekerjaan Konstruksi Atap 15.695426 7.84771 7.84771
B SITE DEVELOPMENT
I Pekerjaan Jalan Masuk 1.0092028 0.5046 0.5046
II Pekerjaan Lapangan Parkir 10.521452 3.50715 3.50715 3.50715
III Pekerjaan Pagar BRC 1.3168787 0.65844 0.65844
IV Pekerjaan Pengecatan
BOBOT RENCANA 0 0.5046 3.31224 3.31224 3.31224 4.57554 4.57554 11.2273 8.07513 19.0865 20.3005 8.42473 3.86419 3.50715 4.67019 0.65844
AKUMULASI BOBOT RENCANA 0 0.5046 3.81684 7.12908 10.4413 15.0169 19.5924 30.8197 38.8948 57.9813 78.2818 86.7065 90.5707 94.0778 98.748 100
BOBOT PELAKSANAAN 0.12 1.33 8 5.5 2.03 3.8 2.78 9.38 7.08 18.65 21.45 5.85 4.88 4.7 2.29 2.16
AKUMULASI BOBOT PELAKSANAAN 0.12 1.45 9.45 14.95 16.98 20.78 23.56 32.94 40.02 58.67 80.12 85.97 90.85 95.55 97.84 100
----------- = Rencana
----------- = Realisasi