PEKERJAAN : PEKERJAAN PAVING BLOCK (K-300)

SATUAN UKURAN: M2

NO. URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH HARGA


(Rp) (Rp)

A TENAGA
Pekerja hari/org 0.071 Rp 90,000.00 Rp 6,390.00
Tukang batu Paving hari/org 0.071 Rp 120,000.00 Rp 8,520.00
Mandor hari/org 0.004 Rp 135,000.00 Rp 540.00
total Rp 15,450.00
B MATERIAL
Paving block K.300 m2 1 Rp 80,000.00 Rp 80,000.00
Pasir Urug m3 0.15 Rp 250,000.00 Rp 37,500.00

total Rp 117,500.00
C ALAT
Stamper hr 0.0010 Rp 650,000.00 Rp 650.00
total Rp 650.00
JUMLAH HARGA TENAGA , MATERIAL , DAN PERALATAN (A + B + Rp 133,600.00
D Overhead + Profit 5% x (A+B+C) Rp 6,680.00
Rp 140,280.00