Rab Subsidi
Rab Subsidi
Rp 180,000,000
Rp 2,731,248,000
Rp 70,800,000
Rp 2,982,048,000
RAB PERUMAHAN SUBSIDI TYPE 36
SPES
No JENIS PEKERJAAN
Volume Satuan
l PEKERJAAN PERSIAPAN
2 Listrik dan Air Kerja 1 LS
3 Bowplang 30 M
ll GALIAN DAN PONDASI
1 Galian batu kali Uk. 0,60 x 0,60 x 30 m 7.2 M3
2 Pasangan Btu kali uk 0,60 x 0,60 x 30 M 7.2 M3
3 Slop Beton Uk 0,13 x 0,20 x 30M 0.78 M3
lll. KOLOM DAN BALOK BETON
1 Kolom Beton K1 / Uk. 0,15 x 0,25 x 3,80 M x 1 titik 0.684 M3
2 Kolom Beton KP / Uk 0,13 x 0,13 x 3,80 M x 17 titik 1.091 M3
3 Ring Balok RB / 0,13 x 0,20 x 30 M 0.78 M3
lV PEKERJAAN DINDING PLESTER DAN ACI
1 Pasangan Bata Merah 80 M2
2 Plaster Aci 140 M2
V PEKERJAAN LANTAI
1 Plur Lantai dan Pemandatan dengan Tebal 0,10 cm x 36 M 3.6 M3
2 Keramik Lantaii uk. 40 x 40 / ARWANA / Setara 33 M2
3 Keramik lantai Kmar Mandi uk. 20 x 20 / KIA / Setara 1.5 M2
4 Keramik Dinding Kamar Mandi Uk. 20 x 40 / kia / Setara 5 M2
5 Plen Keramik 50 M
Vl PEKERJAAN ATAP
1 Rangka Atap baja Ringan 42 M2
2 Genteng Morando 42 M2
3 Nok Genteng 8 M
4 Lis Plang GRC 14 M
Vll PEKERJAAN SANITASI AIR BERSIH DAN KOTOR
1 Pipa PVC Aw 3/4 " Wavin / Setara 28 M
2 Pipa PVC Aw 1/2 " Wavin / Setara 4 M
3 Pipa PVC D 4 " Wavin / Setara 10.5 M
5 Septitenk Rembesan dan Pemasangan 1 LS
Vlll INSTALASI LISTRIK
1 Instalasi Lampu + Aksesoris 9 Titik
2 Instalasi stop kontak + Aksosoris 5 Titik
3 Instalasi MCB + Aksesoris 3 Grop
4 Gronding + Asesoris dan Pertanahan 1 LS
lX PEKERJAAN PLAFON
1 Rangka Hollo Gipsum 9 mm 36 M2
2 Lis Gipsum 50 M
X KUSEN PINTU DAN JENDELA
1 TYPE PJ / Komplit 1 BH
2 TYPE J1 / Komplit 2 BH
3 TYPE T / Komplit 1 BH
5 TYPE P2 / Komplit 1 BH
6 TYPE P3 / Komplit 1 BH
7 TYPE J2 / Komplit 1 BH
8 TYPE P/ Komplit 1 BH
Xl SANITERY
1 Kloset Jongkok Toto / Setara 1 BH
2 Kran Onda / Setara 3 BH
Xll Pekerjaan Cat
1 Cat dinding Dalam Vinilek / Setara 38 BH
2 Cat Dinding Luar Dulux / Setara 38 BH
Xlll Pekerjaan Lain-lain
1 Plur Carport 2.4 M3
2 Pompa Air 250 Watt / Sumur Bor 1 BH
4 Dinding Pembatas 20 M2
5 Sumur Bor 30 M
SPESIFIKASI
Haga Satuan Jumlah Total Biaya
Rp 300,000 Rp 300,000
Rp 10,000 Rp 300,000 Rp 600,000
Rp 50,000 Rp 360,000
Rp 210,000 Rp 1,512,000
Rp 1,000,000 Rp 780,000 Rp 2,652,000
Rp 1,200,000 Rp 410,400
Rp 1,200,000 Rp 1,309,200
Rp 1,200,000 Rp 936,000 Rp 2,655,600
Rp 75,000 Rp 6,000,000
Rp 40,000 Rp 5,600,000 Rp 11,600,000
Rp 300,000 Rp 1,080,000
Rp 60,000 Rp 1,980,000
Rp 50,000 Rp 75,000
Rp 65,000 Rp 325,000
Rp 20,000 Rp 1,000,000 Rp 4,460,000
Rp 130,000 5460000
Rp 45,000 Rp 1,890,000
Rp 45,000 Rp 360,000
Rp 35,000 Rp 607,500 Rp 8,317,500
Rp 9,000 Rp 252,000
Rp 7,000 Rp 28,000
Rp 35,000 Rp 367,500
Rp 1,750,000 Rp 1,750,000 Rp 2,397,500
Rp 180,000 Rp 1,620,000
Rp 180,000 Rp 900,000
Rp 180,000 Rp 540,000
Rp 250,000 Rp 250,000 Rp 3,310,000
Rp 110,000 Rp 3,960,000
Rp 14,000 Rp 700,000 Rp 4,660,000
Rp 1,100,000 Rp 1,100,000
Rp 750,000 Rp 1,500,000
Rp 900,000 Rp 900,000
Rp 900,000 Rp 900,000
Rp 220,000 Rp 220,000
Rp 570,000 Rp 570,000
Rp 780,000 Rp 780,000 Rp 5,970,000
Rp 170,000 Rp 170,000
Rp 25,000 Rp 75,000 Rp 245,000
Rp 18,000 Rp 684,000
Rp 20,000 Rp 760,000 Rp 1,444,000
Rp 300,000 Rp 720,000
Rp 500,000 Rp 500,000
Rp 80,000 Rp 1,600,000
Rp 145,000 Rp 4,350,000 Rp 7,170,000
Total Biaya Rp 55,481,600
ARUS KAS
AKTIVA
Aug-18 Penerimaan Pinjaman Rp 2,982,048,000
Penjualan Bulan Pertama (4 unit36+ 1unit 45) Rp 642,500,000
Jumlah Rp 3,624,548,000
Jumlah Rp 1,117,596,571
Jumlah Rp 1,269,685,143
Jumlah Rp 1,406,573,714
Jumlah Rp 1,543,462,286
Jumlah Rp 1,680,350,857
Jumlah Rp 1,817,239,429
Jumlah Rp 1,954,128,000
Jumlah Rp 2,091,016,571
Jumlah Rp 2,227,905,143
Jumlah Rp 2,372,293,714
Jul-19 Kas Awal
Penjualan Bulan Keduabelas (5 unit type 36) Rp 1,866,682,286
Rp 650,000,000
Jumlah Rp 2,516,682,286
Aug-19 Kas Awal Rp 2,011,070,857
Penjualan Bulan Ketigabelas (5 unit type 36) Rp 650,000,000
Jumlah Rp 2,661,070,857
Sep-19 Kas Awal Rp 2,155,459,429
Penjualan Bulan Keempat belas (5 unit type 36) Rp 650,000,000
Jumlah Rp 2,805,459,429
Kas Awal Rp 2,299,848,000
Penjualan Bulan Keempat belas (5 unit type 36) Rp 650,000,000
Jumlah Rp 2,949,848,000
PASIVA SELISIH KAS
Pembangunan Infrastruktrur dan 5 Unit Awal Rp 2,936,448,000
Dana Ditempatkan Rp 213,003,429
Jumlah Rp 3,149,451,429 Rp 475,096,571
Rp 49,610,000
Rp 180,400,000
Rp 1,058,347
Rp 116,899,200
Rp 1,081,318
Rp 67,650,000
Rp 157,850,000
Rp 926,053
Rp 94,349,200
Rp 872,730
Rp 992,200
Rp 161,999,200
Rp 720,878
Rp 2,000,000