Anda di halaman 1dari 9

RAB

(RENCANA ANGGARAN BIAYA)


ALOKASI DANA DESA (ADD)
TAHUN 2019

PENGURUGAN TEMPAT PARKIR


DUSUN MANGSULAN DESA JAMBON
DETAIL ENGINERING DESIGN DESA : JAMBON
KECAMATAN : PULOKULON
KABUPATEN : GROBOGAN
PEKERJAAN PENGURUGAN TEMPAT PARKIR LOKASI : DSN. MANGSULAN DS. JAMBON
PK :

DESIGN

DASTU 0,15 M KANSTEN PAS. BATA 10/20 CM

STA

P 30.00
L 26.00

PERHITUNGAN VOLUME

b. Dastu = PXLXT = 117.00 M³


c. Pas Bata = (0.2 X P X 2) + (0.2 X L X 2) = 22.40 M³
d. Plester = ((0.1 + 0.2) X 2 X P) + ((0.1 + 0.2) X 2 X L) = 33.60 M²
e. Galian Tanah = 2*((0.15 X 0.2 X P) + (0.15 X 0.2 X L)) = 3.36 M³

KEBUTUHAN BAHAN, ALAT DAN TENAGA KERJA

BAHAN Dibulatkan
Batu Bata = 1,568.00 = 1,568.00 bh
Pasir Pasang = 2.18 = 2.00 M³
Semen (PC) 40kg = 11.23 = 11.00 Zak
Dastu = 118.17 = 118.00 M³

ALAT

TENAGA KERJA
Pekerja = 51.93 = 52.00 HOK
Tukang = 8.96 = 9.00 HOK
ANALISA HARGA SATUAN PEKERJAAN

Volume
NO URAIAN PEKERJAAN KOEF SAT

1 2 3 4 5
A.2.3.1.1 Menggali 1 m³ tanah biasa sedalam 0,2 meter
B. Tenaga
Pekerja 0.750 OH 3.36
O.007 Mengurug 1 m³ Dastu
Bahan
Dastu 1.010 M³ 117.00
Tenaga
Pekerja 0.250 OH 117.00
A.4.4.1.10 Memasang 1 m² Batu Bata 1 PC : 5 PP
A. Bahan
Bata Merah 70.000 buah 22.40
Portland Cement (PC) 9.680 kg 22.40
Pasir Pasang (PP) 0.045 M³ 22.40
B. Tenaga
Pekerja 0.300 OH 22.40
Tukang Batu 0.100 OH 22.40
A.44.2.16 Memasang 1 m² plesteran 1 PC : 5 PP; tebal 20 mm (SUDAH ACIAN)
A. Bahan
Portland Cement (PC) 6.912 kg 33.60
Pasir Pasang (Ps) 0.035 M³ 33.60
B. Tenaga
Pekerja 0.400 OH 33.60
Tukang Batu 0.200 OH 33.60
KERJAAN RENCANA ANGGARAN BIAYA
DESA JAMBON KECAMATAN PULOKULON KABUPATEN
JUMLAH TAHUN ANGGARAN 2019

6=(3x5) BIDANG : PEMBANGUNAN SARANA PRASARANA


PEKERJAAN : PENGURUGAN TEMPAT PARKIR
VOLUME : P 30M X L 26M
2.52 LOKASI : DSN. MANGSULAN DS. JAMBON
SUMBER DANA : ALOKASI DANA DESA BHPBP

118.17 URAIAN VOLUME SATUAN


1 2 3
29.25 I BAHAN
1 Batu Bata 1,568.00 bh
2 Pasir Pasang 2.00 M³
1,568.00 3 Semen (PC) 40kg 11.00 Zak
216.83 4 Dastu 118.00 M³
1.01

6.72 II ALAT
2.24 1 Cangkul 4 bh
2 Ekrak 4 bh
3 Angkong 1 bh
232.24 4 Benang proyek 1 bh
1.18

13.44 III UPAH


6.72 1 Pekerja 52.00 HOK
2 Tukang 9.00 HOK

JUMLAH
Biaya Operasional
TOT

Menyetujui,
Kepala Desa Jambon

HARDI, S.Pd
RENCANA ANGGARAN BIAYA
DESA JAMBON KECAMATAN PULOKULON KABUPATEN GROBOGAN
TAHUN ANGGARAN 2019

HARGA SATUAN (Rp) JUMLAH BIAYA (Rp)


4 5 (2x4)

900.00 1,411,200.00
350,000.00 700,000.00
50,000.00 550,000.00
105,000.00 12,390,000.00

SUB TOTAL I 15,051,200.00

40,000.00 160,000.00
45,000.00 180,000.00
450,000.00 450,000.00
32,400.00 32,400.00

SUB TOTAL II 822,400.00

70,000.00 3,640,000.00
90,000.00 810,000.00
SUB TOTAL III 4,450,000.00
JUMLAH : (I+II+III) 20,323,600.00
Biaya Operasional Kegiatan 1,069,700.00
TOTAL BIAYA 21,393,300.00

Jambon, 7 Oktober 2019

Dibuat Oleh:
TPK Desa Jambon

MANSUR
DENAH LOKASI PENGURUGAN TEMPAT PARKIR DSN. MANGSULAN DE

BALAI
LOKASI
KEGIATAN
DESA

G B PASAR JAMBON
COR
BETO
1:2:3

REL KERETA API


DETAIL PENGURUGAN TEMPAT PARKIR

PROVINSI

JAWA TENGAH

KABUPATEN

GROBOGAN
TANAH URUG 0,1 KANSTEN PAS. BATA
M 10/20 CM

KECAMATAN

TANAH URUG 0,1 KANSTEN PAS. BATA


M 10/20 CM PULOKULON

DESA
COR
BETON JAMBON
1:2:3
PEKERJAAN

URUGAN DASTU

LOKASI

DSN MANGSULAN

DIBUAT OLEH
TPK

MANSUR
DIFASILITASI OLEH
PENDAMPING DESA

PUJI PRIYANTO
DISETUJUI OLEH
KEPALA DESA

HARDI, S.Pd