NO. KONTRAK :
TABEL REVISI
DAFTAR ISI
1. TECHNICAL BID EVALUATION FOR CRUDE OIL TANK (02-T-105) ............................................... 4
TECHINCAL BID EVALUATION FOR CRUDE OIL TANK (02-T-105) BSTJG-10-T2-TE-004
JASA PELAKSANAAN UPGRADING BS II, BS V DAN BS VI FIELD TANJUNG -
TANJUNG WATERFLOOD PROJECT Hal 4 dari 6
RESUME
Dokumen ini dipersiapkan sebagai dasar rangkuman perhitungan internal PT Globalindo Buana atas
pekerjaan Crude Oil Tank (02 – T – 105) di kontrak pekerjaan “Pekerjaan Jasa Pelaksanaan Upgrading
BS II, BS V dan BS VI Field Tanjung – Tanjung Waterflood Project”.
Pelaksanaan kontruksi rencana tangki crude oil (02-T-105) ini akan di kerjakan swa-kelola oleh PT.
Globalindo Buana dengan dasar referensi PT. Globalindo Buana mempunyai SKUP (Surat Kemampuan
Usaha Penunjang) MIGAS dan mempunyai WPS (Welding Specification Specification) dan PQR
(Procedure Qualification Record) dan berpengalaman.
PEKERJAAN JASA PELAKSANAAN UPGRADING BS II, BS V, BS VI FIELD TANJUNG – TANJUNG WATERFLOOD PROJECT
Status
NO. DESCRIPTION REQUIREMENT PT. GLOBALINDO BUANA
1 I - GENERAL
2 Tag No. 02-T-105 02-T-105
3 Quantity 1 (Satu) 1 (Satu)
4 Service Crude Oil Tank Crude Oil Tank
5 Tank Type Silinder Silinder
6 Roof Type Self Supported Cone Roof Self Supported Cone Roof
7 Bottom Type Flat Bottom Flat Bottom
8 II - CONFORMITY (as listed in Requisition)
9 Applicable Code and Standard listed in specification Required Confirmed
10 Compliance with Project Specification Required Confirmed
11 III - SCOPE OF SUPPLY / SERVICES
12 III.1 - Scope of Supply
Detail Design, Material Supply, Fabrication, Painting, Shop Test/Hydrotest, Expediting and Testing, Internal
13 Confirmed
Assembly & Installation, External Attachments, and Documentation of Crude Oil Tank (02-T-105)
One unit
14 Scope of supply as minimum consists of the followings:
15 • One (1) unit of Crude Oil Tank c/w internal pipe, external attachment, nozzle,and gaskets Required Confirmed
16 • Internally Epoxy Lining Required Confirmed
17 • Coating and painting as per project specification PEP-00-N1-SP-0001 Required Confirmed
18 • Pipe Support Clips Required Confirmed
19 • Anchor Bolts Required Confirmed
20 • Anchor Chair Required Confirmed
21 • Vortex Breaker Required Confirmed
22 • Measurement Table Required Confirmed
23 • Deflector Required Confirmed
24 • Foam Chamber Required Confirmed
25 • Earthing Boss Required Confirmed
26 • Lifting Lugs Required Confirmed
27 • Davit Required Confirmed
28 • Name plate & it's bracket Required Confirmed
29 Guarantee for selected material is suitable for process service Required
Confirmed
30 Recommended 2 years operation spare parts lists with itemized price One set Confirmed
Spare parts for precommissioning / commissioning and start-up including bolst&nuts, washer, gaskets,
31 Confirmed
packing, etc. One set
32 Special tools for maintenance and installation (if any) One set Confirmed
33 III.2 - Scope of Services
34 Packing and Shipping Preparation as per Project Specification Required Confirmed
Detail engineering for the Crude Oil Tank including tank datasheet, calculation report (tank & skid support),
35 Confirmed
GA drawing, detail fabrication drawing & other required documentations. Required
36 Warranty and mechanical guarantee Required Confirmed
37 III.2.a - QA Inspection and Test
38 ITP (Inspection Test Plan), Inspection Report, QA/QC Procedure Required Confirmed
39 Material Certification ISO 10474 Confirmed
40 Material Traceability Required Confirmed
41 Non Destructive Testing As Per Code Confirmed
42 Hydrotesting (Full of Water) Required Confirmed
43 Radiography Test Required Confirmed
44 Vacuum Test Required Confirmed
45 Painting + Linning Inspection Procedure PEP-TJG-M-JP-010 Confirmed
46 WPS Required Confirmed
47 PQR PEP-TJG-M-JP-010 Confirmed
48 Welder Test Required Confirmed
49 Dimensions Required Confirmed
50 Inspection and Testing Schedule Required Confirmed
TECHNICAL BID EVALUATION - CRUDE OIL TANK (02-T-105)
Status
NO. DESCRIPTION REQUIREMENT PT. GLOBALINDO BUANA
51 III.2.b - Others
52 All Documents (MDR) required for SI/PLO Required Confirmed
53 IV. OPERATING CONDITION
54 IV.1 - SITE AND INSTALLATION DATA
55 Basic Wind Speed 108 mph 108 mph
56 Seismic Factor Ss=0,283; S1=0,085 Ss=0,283; S1=0,085
57 IV.2 - MECHANICAL DESIGN DATA
58 Liquid Service Crude Oil Crude Oil
59 Design Code API 650 API 650
60 Size: ID x Tinggi ID 8230 x 5490 H ID 8230 x 5490 H
61 Design Pressure: Internal/External Full of Water + 1 psig / - Full of Water + 1 psig / -
62 Design Temperature 160 oF 160 oF
63 Operating Pressure Atm Atm
64 Operating Temperature 110 oF o
110 F
65 Corrosion Allowance 3 mm 3 mm
66 Thickness: Course 1 (mm) 8 mm 8 mm
67 Thickness: Course 2 (mm) 8 mm 8 mm
68 Thickness: Course 3 (mm) 8 mm 8 mm
69 Thickness: Roof (mm) 10 mm 10 mm
70 Thickness: Bottom (mm) 10 mm 10 mm
71 Pumping Rate in / out (bpd) 4500 / 3680 4500 / 3680
72 Material: As Per Datasheet / GA Drawings Confirmed
73 Nozzle Connection (Size/Rating/Type): As Per Datasheet / GA Drawings Confirmed
74 V. WEIGHT and DIMENSIONS
75 Empty (lb) VTA 46786 lbs
76 Operating (lb) VTA 578360 lbs
77 Test Full of Water (lb) VTA 689880 lbs
78 VI. MISCELANEOUS
79 Delivery time Best possible 3 Months
80 Location of Fabrication VTA Site Tanjung Field
81 Design Life 20 years Confirmed
A
REMARKS: (VTA): Vendor To Advise (NAV): No Data Available Yet (C): Compliant (CR): Clarification Required (A): Acceptable (NC): Not Compliant (NA): Not Applicable