PT. REKADAYA ELEKTRIKA PT. PEMBANGKITAN JAWA BALI

ERECTION METHOD STATEMENT


DOME STEEL STRUCTURE

PROJECT : PENGADAAN PEMBUATAN DOME


SHELTER COAL YARD PLTU TANJUNG
AWAR-AWAR

CLIENT : PT PEMBANGKITAN JAWA BALI

LOCATION : COAL YARD PLTU TANJUNG AWAR-AWAR

DOCUMENT NO. : 0014-C0-CP-513-R

JOB NO : 179014

1 ISSUE FOR CONSTRUCTION 19-07-2019 MN BES ISF


0 ISSUE FOR CONSTRUCTION 30-04-2019 KOS MZR ISF
REV DESCRIPTION DATE PREPARED CHECKED APVD

P.T. R E K A D A Y A E L E K T R I K A
JOB NO. : 179014 REV
ERECTION METHOD STATEMENT
DOC. NO. : 0014-C0-CP-513-R 1
DOME STEEL STRUCTURE
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
19 -07-2019 MN BES ISF

DAFTAR ISI

No DESKRIPSI HAL

DAFTAR ISI 2.

LEMBAR REVISI 3.

1. GAMBARAN UMUM 4.

2. TAHAPAN KONSTRUKSI 4.

3. KONDISI PELAKSANAAN PEKERJAAN 4.

4. DAFTAR PERALATAN 5.

5. DAFTAR TENAGA KERJA 6.

6. PERSYARATAN MATERIAL 6.

7. CONSTRUCTION METHOD 7.

8. HSE CONTROL 18.

9. QUALITY ASSURANCE 18.

10. LAMPIRAN 18.

2
JOB NO. : 179014 REV
ERECTION METHOD STATEMENT
DOC. NO. : 0014-C0-CP-513-R 1
DOME STEEL STRUCTURE
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
19 -07-2019 MN BES ISF

REVISION HISTORICAL SHEET

REV. DATE DESCRIPTION

0 30-04-2019 ISSUE FOR CONSTRUCTION


1 19-07-2019 ISSUE FOR CONSTRUCTION

3
JOB NO. : 179014 REV
ERECTION METHOD STATEMENT
DOC. NO. : 0014-C0-CP-513-R 1
DOME STEEL STRUCTURE
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
19 -07-2019 MN BES ISF

1. GAMBARAN UMUM
Dokumen ini mencakup metode konstruksi untuk Erection Steel Structure. Tujuan dari
metode ini adalah untuk menjeleaskan tahapan konstruksi, kondisi pelaksanaan
pekerjaan, daftar peralatan, daftar tenaga kerja, persyaratan material, metode konstruksi,
HSE control, dan Quality Assurance pekerjaan. Seluruh pekerjaan ini harus dilakukan
dalam kondisi terkendali. Kontraktor dapat merekomendasikan pernyataan lebih baik atau
mengubah metode ini sehingga pekerjaan dapat diselesaikan.

2. TAHAPAN KONSTRUKSI
Tahapan pekerjaan dalam metode ini dimulai dari Line B-C Grid 1 hingga Grid 14,
kemudian dilanjutkan ke Line A-B Grid 1 hingga Grid 14 sebagai berikut :

FOUNDATION PREPARATION I PREPARATION II FIRST FULL


ERECTION (LINE B-C) (LINE B-C) ERECTION

DISMANTLING
FULL ERECTION FULL ERECTION SUPPORT &
SUPPORTING
GRID 3, 4, 5, 6 GRID 2 PLUMBNESS
MATERIAL

FULL ERECTION PREPARATION CONTINUED


GRID 7-14 (LINE A-B) SEQUENCE

Metode ini harus dipersiapkan dengan baik sehingga dapat diaplikasikan pada pekerjaan
ini.

3. KONDISI PELAKSANAAN PEKERJAAN


3.1 WORK PERMIT (IJIN KERJA)
Untuk melaksanakan pekerjaan ini, terdapat beberapa work permits (ijin kerja) yang harus
diperoleh sesuai ketentuan dari PT. PJB sebagai berikut :
a. Susunan Personil yang sah dengan disertai Foto Kopi KTP, Surat Penugasan,
Surat Ijin / Sertifikat yang masuk berlaku.

4
JOB NO. : 179014 REV
ERECTION METHOD STATEMENT
DOC. NO. : 0014-C0-CP-513-R 1
DOME STEEL STRUCTURE
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
19 -07-2019 MN BES ISF

b. Jadwal Kerja
c. Waktu Rencana akan dimulainya Pekerjaan
d. Jam Kerja Pelaksanaan Pekerjaan
e. Peralatan Transportasi & Peralatan Kerja yang akan digunakan.

3.2 KONDISI KERJA


Metode ini dapat diaplikasi hanya pada kondisi sebagai berikut :
a. Safety Permit sesuai dengan ketentuan dari PT. PJB.
b. Wind Speed Limit (Batas Kecepatan Angin) sesuai dengan ketentuan dari PT. PJB
PLTU Tanjung Awar-Awar adalah 12 knot.
c. Suhu Udara pada area kerja antara 32 s/d 33 0C.
d. Kondisi Cuaca berada dalam kondisi cerah hingga berawan, apabila kondisi cuaca
hujan maka seluruh pekerjaan harus dihentikan.

4. DAFTAR PERALATAN
Peralatan-Peralatan yang akan digunakan sebagai berikut :
No Equipment Unit
1 Crane 55 Ton Type Crawler 1
2 Crane 80 Ton Type Crawler 1
3 Crane 50 Ton Type Crawler 1
4 Crane 50 Ton Type Telescopic 1
5 Crane 25 Ton Type Telescopic 1
6 Manlift 2
7 Truck Mobile Crane 1
8 Excavator PC 320 1
9 Forklift 5 Ton 1
10 Strengthen Tools 1 package
11 Genset 60 kVA dan 27 kVA 2

5
JOB NO. : 179014 REV
ERECTION METHOD STATEMENT
DOC. NO. : 0014-C0-CP-513-R 1
DOME STEEL STRUCTURE
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
19 -07-2019 MN BES ISF

5. DAFTAR TENAGA KERJA


Daftar Tenaga Kerja pada tabel di bawah ini :
No Manpower Qtty
1 Site Manager 1
2 Supervisor 4
3 Rigger 3
4 Operator Alat Berat 14
5 Foreman 16
6 Helper 15

6. PERSYARATAN MATERIAL
Material yang digunakan pada konstruksi ini harus dilaksanakan sesuai dengan AISC
(American Institute of Steel Construction) atau sesuai dengan standar operasional
prosedur sesuai ketentuan dari PT. PJB atau peraturan-peraturan lain yang disebutkan
secara spesifik di dalam kontrak.
Berikut ini adalah Data Teknis untuk Material Utama yang akan diinstalasi pada Dome
Shelter :
 Rafter Bagian (1) = Segmen 3, 4, 5, 6, 7, 8 ------------------------ Beban +/- 13,25 Ton
 Rafter Bagian (2) = Segmen 9, 10, 11 ------------------------------- Beban +/- 6,07 Ton
 Purlin = Type Z Purlin -- Panjang : 1,3 meter ~ 12 meter -------- Beban : 6 kg ~ 106 kg
 Tie Beam ------------------ Panjang : 12 meter ----------------------- Beban : 682 kg
 Sag Arrestor -------------- Panjang : +/- 1.5 meter ----------------- Beban : 1 kg
 Cable Bracing ------------ Panjang 14 meter ~ 17 meter -----------Beban : 21 ~ 24 kg
 Bolts and Nuts ------------------------------------------------------------- Beban : 1,26 kg
Berikut ini adalah Data Teknis untuk Supporting Material :
 Plate Baja untuk Dudukan Crane --- Dimensi 1500 x 6000 mm --- thickness 12 & 16 mm
 Plate Baja untuk Dudukan Temporary Tower --- Dimensi 1200 x 2400 mm –
----- thickness 12mm
 Temporary Tower ---- Panjang 27 meter dan 26 Meter -------- Beban +/- 1,7 Ton
 Temporary Tie Beam ---- Panjang 4 meter ------------------------ Beban +/- 50 kg
 Temporary Wire Sling -------- Panjang rata2 50 – 100 meter
 Material Lifting Gear ------------------------------------------------------ Beban +/- 1,5 Ton

6
JOB NO. : 179014 REV
ERECTION METHOD STATEMENT
DOC. NO. : 0014-C0-CP-513-R 1
DOME STEEL STRUCTURE
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
19 -07-2019 MN BES ISF

7. CONSTRUCTION METHOD
A. FOUNDATION ERECTION
a. Persiapan Area Kerja dan Mobilisasi Alat Berat Crane 55 Ton Type Crawler
dan Manlift ke sisi Kolom Line A.
b. Langsir Material Rafter Segmen 1 dan Segmen 2 Grid 1~14 menggunakan
Truck Mobile Crane dari Laydwon ke sisi kolom.
c. Langsir Material Purlin dan Tie Beam Segmen 1 dan Segmen 2 Grid 1~14
menggunakan Truck Mobile Crane dari Laydwon ke sisi kolom Line A.
d. Leveling Anchor Bolt dan Baseplate Kolom Grid 1-14.
e. Erection Rafter Segmen 1 Grid 1~14 & Jointing Connection ke Anchor Bolt tiap
Grid sesuai dengan Gambar Kerja.
f. Erection Rafter Segmen 2 Grid 1~14 & Jointing Connection ke Segmen 1 tiap
Grid sesuai dengan Gambar Kerja.
g. Erection Tie Beam Segmen 1 & Segmen 2 Grid 1~14 & Jointing Connection
tiap Grid sesuai dengan Gambar Kerja.
h. Erection Purlin Segmen 1 & Segmen 2 Grid 1~14 & Jointing Connection tiap
Grid sesuai dengan Gambar Kerja.
i. Persiapan Area Kerja & Mobilisasi Alat Berat Crane 55 Ton Type Crawler dan
Manlift ke sisi Kolom Line C.
j. Melakukan tahapan ulang point A.b s/d A.i
k. Persiapan Area Kerja & Mobilisasi Alat Berat Crane 55 Ton Type Crawler dan
Manlift ke dalam Coal Yard 2 Kolom Line B.
l. Langsir Material Rafter Segmen Column dan Segmen Y Grid 1~14
menggunakan Truck Mobile Crane dari Laydwon ke dalam Coal Yard 2.
m. Langsir Material Purlin dan Tie Beam Segmen 12 Grid 1~14 menggunakan
Truck Mobile Crane dari Laydwon ke sisi kolom Line B.
n. Jointing Connection Rafter Segmen Column dan Segmen Y.
o. Erection Rafter Segmen Y& C Grid 1~14 & Jointing Connection ke Anchor Bolt
tiap Grid sesuai dengan Gambar Kerja.
p. Erection Tie Beam Segmen 12 Grid 1~14 & Jointing Connection tiap Grid
sesuai dengan Gambar Kerja.

7
JOB NO. : 179014 REV
ERECTION METHOD STATEMENT
DOC. NO. : 0014-C0-CP-513-R 1
DOME STEEL STRUCTURE
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
19 -07-2019 MN BES ISF

q. Erection Purlin Segmen 12 Grid 1~14 & Jointing Connection tiap Grid sesuai
dengan Gambar Kerja.
r. Finish Foundation Erection.

Gambar 1. Persiapan Area Kerja dan Mobilisasi Alat Berat

B. PREPARATION I (LINE B-C)


a. Perataan dan Pemadatan Area Kerja Erection di CY 1 dan CY 2.
Pekerjaan ini menggunakan Dozer untuk perataan batu bara di Line B-C Grid
1-6 dan Excavator untuk pemadatan batu bara di Area Kerja. Pekerjaan ini
dapat menggunakan alat berat lainnya yang mampu berfungsi sebagai
perataan dan pemadatan batu bara.
b. Perataan dan Pemadatan Akses Jalan di CY 1 dan CY 2..
Diperlukan adanya perataan dan pemadatan akses jalan untuk mobilisasi alat
berat dan material ke dalam Coal Yard. Hal ini perlu kesepakatan bersama
dalam rapat Koordinasi Mingguan antara PT. PJB dan PT. RE.

8
JOB NO. : 179014 REV
ERECTION METHOD STATEMENT
DOC. NO. : 0014-C0-CP-513-R 1
DOME STEEL STRUCTURE
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
19 -07-2019 MN BES ISF

Gambar 2. Persiapan Area Kerja dan Mobilisasi Material & Alat Berat untuk
Full Erection Grid 1-6

c. Mobilisasi Alat Berat Crane 55 ton, 80 ton, dan 50 ton ke dalam Coal Yard.
d. Langsir Supporting Material : Plate Baja untuk landasan Crane, Dudukan
Assembly Rafter, dan supporting material lainnya.
e. Langsir Material Rafter Grid 1-6 Segmen 3 s/d Segmen 8 di Coal Yard 1.
f. Langsir Material Rafter Grid 1-6 Segmen 9 s/d Segmen 11 di Coal Yard 2.
g. Fabrikasi Purlin, Sag Arrestor, dan aksesoris lainnya di Laydown.
h. Langsir Material Purlin yang sudah di-assembly dan Tie Beam ke dalam Coal
Yard.
i. Setting dan Assembly Rafter :
Setiap Rafter akan di-jointing terlebih dahulu di area Assembly menjadi bagian
sebagai berikut :
 Setting dan Assembly Bagian 1 Grid 1-6 (Rafter Segmen 3, 4 dan 5).
 Setting dan Assembly Bagian 2 Grid 1-6 (Rafter Segmen 6, 7, dan 8).
 Setting dan Assembly Bagian 3 Grid 1-6 (Rafter Segmen 9, 10, dan 11).

9
JOB NO. : 179014 REV
ERECTION METHOD STATEMENT
DOC. NO. : 0014-C0-CP-513-R 1
DOME STEEL STRUCTURE
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
19 -07-2019 MN BES ISF

Gambar 3. Pekerjaan Assembly Rafter di Area Assembly (Coal Yard)


j. Finish Preparation (Line B-C).

C. PREPARATION II (LINE B-C)


a. Langsir Supporting Material ke dalam Coal Yard: Temporary Tower,
Temporary Wire Sling, Temporary Tie Beam to Existing.
b. Assembly Temporary Tower.
c. Persiapan Rafter Bagian 1 dan Bagian 2, Supporting Material sesuai posisi
pada Rigging Plan masing-masing Crane.
d. Persiapan Posisi Crane sesuai posisi pada Gambar 4.
Posisi Crane 55 Ton di Coal Yard 1 dekat dengan Line C, Posisi Crane 80 Ton
di Coal Yard 1, Posisi Crane 50 Ton di Coal Yard 2.
Crane 50 Ton type Telescopic berfungsi sebagai perbantuan awal Erection
Bagian 2 di Coal Yard 2, setelah itu akan mobilisasi ke Coal Yard 1 untuk
pemasangan Tie Beam.
e. Persiapan Posisi Manlift di Coal Yard 1 dan Coal Yard 2.
f. Persiapan Posisi Temporary Tower sesuai posisi pada Gambar 5.
Temporary Tower berfungsi sebagai Supporting Rafter untuk penahan beban
secara vertikal.
g. Persiapan Posisi Temporary Tie Beam sesuai posisi pada Gambar 6.
Temporary Tie Beam berfungsi sebagai Supporting Rafter untuk menahan
beban secara horizontal.

10
JOB NO. : 179014 REV
ERECTION METHOD STATEMENT
DOC. NO. : 0014-C0-CP-513-R 1
DOME STEEL STRUCTURE
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
19 -07-2019 MN BES ISF

h. Persiapan Posisi Temporary Wire Sling sesuai posisi pada Gambar 7.


Temporary Wire Sling membantu Temporary Tie Beam untuk penahan beban
beban secara horizontal.

Gambar 4. Fix Position of Crane

Gambar 5. Fix Position of Temporary Tower

11
JOB NO. : 179014 REV
ERECTION METHOD STATEMENT
DOC. NO. : 0014-C0-CP-513-R 1
DOME STEEL STRUCTURE
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
19 -07-2019 MN BES ISF

Gambar 6. Fix Position of Temporary Tie Beam

Gambar 7. Fix Position of Temporary Wire Sling

i. Inspeksi Kondisi Material dan Peralatan.


Diharuskan pengecekan kondisi Material dan Peralatan yang akan digunakan
selama proses Erection pertama dan dicatat pada Form Inspection Record.

12
JOB NO. : 179014 REV
ERECTION METHOD STATEMENT
DOC. NO. : 0014-C0-CP-513-R 1
DOME STEEL STRUCTURE
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
19 -07-2019 MN BES ISF

j. Trial Lifting
Dipastikan kembali bahwa landasan Crane sudah padat diberi Plate Baja,
kemudian Pengangkatan dilakukan uji coba secara perlahan-lahan hingga
mencapai top level dome shelter. Kemudian setelah itu diturunkan secara
perlahan. Kegiatan ini harus di-record sesuai dengan Rigging Plan.
k. Finish Preparation II

D. FIRST FULL ERECTION GRID 1 (LINE B-C)

Gambar 8. First Full Erection Grid 1

a. Erection Bagian 1
 Pastikan kembali Material Rafter Bagian 1 sudah selesai diinspeksi.
 Crane 55 Ton dan Crane 80 Ton sudah fix Position di Line C (Coal Yard 1).
 Webbling Sling pada masing-masing Crane menggunakan 2 Lengan Sling
yang diikat (chocked) ke Rafter Bagian 1.
 Penempatan posisi Webbing Sling pada Rafter bagian 1 sesuai Rigging Plan
dan Standar Operational Prosedur Lifting.
 Material Rafter diangkat secara perlahan, apabila sudah mendekati Segmen
2 maka Manlift sudah beroperasi untuk persiapan Connection dan
Strengthen Tightening Bolt.

13
JOB NO. : 179014 REV
ERECTION METHOD STATEMENT
DOC. NO. : 0014-C0-CP-513-R 1
DOME STEEL STRUCTURE
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
19 -07-2019 MN BES ISF

 Komunikasi tetap berjalanan untuk penyesuaian posisi Rafter antara


Instalator, Rigger dan Supervisor.
 Setelah dilakukan Connection Bolt dan Strengthen Tightening ke Segmen 2,
Crane 55 Ton dan Crane 80 Ton tetap beroperasi melakukan Hanging.

b. Erection Bagian 2
 Pastikan kembali Material Rafter Bagian 2 sudah selesai diinspeksi.
 Crane 50 Ton Type Telescopic dan Type Crawler sudah fix Position di Line
B (Coal Yard 2).
 Webbling Sling pada masing-masing Crane menggunakan 2 Lengan Sling
yang diikat (chocked) ke Rafter Bagian 2.
 Penempatan posisi Webbing Sling pada Rafter bagian 2 sesuai Rigging Plan
dan Standar Operational Prosedur Lifting.
 Material Rafter diangkat secara perlahan, apabila sudah mendekati Segmen
12 (J3) dan Bagian 1 (J2) maka Manlift sudah beroperasi untuk persiapan
Connection dan Strengthen Tightening Bolt.
 Komunikasi tetap berjalanan untuk penyesuaian posisi Rafter antara
Instalator, Rigger dan Supervisor.
 Setelah dilakukan Connection Bolt dan Strengthen Tightening ke Segmen 2,
Crane 50 Ton Type Crawler tetap beroperasi melakukan Hanging.
 Crane 50 Ton Type Telescopic melepas Hanging.

c. Finish Erection
 Kondisi Crane 55 Ton Type Crawler di Coal Yard 1 tetap Hanging
 Kondisi Crane 80 Ton Type Crawler di Coal Yard 1 tetap Hanging
 Kondisi Crane 50 Topn Type Crawler di Coal Yard 2 tetap Hanging
 Crane 50 Ton Type Telescopic Persiapan Pemasangan Temporary Support
di Coal Yard 1.
 Crane 25 Ton Persiapan Pemasangan Temporary Support di Coal Yard 2.

14
JOB NO. : 179014 REV
ERECTION METHOD STATEMENT
DOC. NO. : 0014-C0-CP-513-R 1
DOME STEEL STRUCTURE
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
19 -07-2019 MN BES ISF

Gambar 9. Erection Rafter Bagian 2

Gambar 10. Erection Rafter Bagian 2

15
JOB NO. : 179014 REV
ERECTION METHOD STATEMENT
DOC. NO. : 0014-C0-CP-513-R 1
DOME STEEL STRUCTURE
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
19 -07-2019 MN BES ISF

E. SUPPORT & PLUMBNESS (LINE B-C)


a. Instalasi Temporary Temporary Tower
b. Instalasi Temporary Tie Beam
c. Instalasi Temporary Wire Sling
d. Plumbness Test
e. Unloading Sling & Mobilisasi Crane.
f. Finish Erection

F. FULL ERECTION GRID 2 (LINE B-C)


a. Prosedur Erection Rafter sama dengan First Full Erection Grid 1 (Point D)
b. Instalasi Purlin Grid 1 ke Grid 2 sesuai dengan Gambar Kerja menggunakan
Crane 50 Ton Type Telescopic dan Manlift.
c. Instalasi Tie Beam Grid 1 ke Grid 2 sesuai dengan Gambar Kerja
menggunakan Crane 50 Ton Type Telescopic dan Manlift.
d. Instalasi Hot Dip Brace Galvanized Grid 1 ke Grid 2 (Jika terdapat pada
gambar) dan aksesoris lainnya.
e. Melakukan Inspeksi dan Plumbness.
f. Finish Full Erection Grid 2.

G. FULL ERECTION GRID 3 – 6 (LINE B-C)


a. Prosedur Erection Rafter sama dengan Full Erection Grid 2 (Point F)
b. Prosedur Instalasi Purlin, Tie Beam, Bracing, & aksesoris lainnya sama
dengan Full Erection Grid 2 (Point F).
c. Melakukan Inspeksi dan Plumbness.
d. Finish Full Erection Grid 3 - 6

H. DISMANTLING SUPPORTING MATERIAL


a. Setelah mencapai Grid 6, Temporary Material sudah dapat dilepas sehingga
SR 1 dapat melakukan Stacking dan Reclaiming Batu Bara di Area Grid 1-6
Line B-C.
b. Pekerjaan ini menggunakan Crane 50 Ton type Telescopic dan Manlift untuk
pelaksanaannya.

16
JOB NO. : 179014 REV
ERECTION METHOD STATEMENT
DOC. NO. : 0014-C0-CP-513-R 1
DOME STEEL STRUCTURE
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
19 -07-2019 MN BES ISF

c. Proses Dismantling dilakukan secara bertahap, dimulai dari Dismantling


Temporary Wire Sling -> Temporary Tie Beam -> Temporary Tower.
d. Prosedur Dismantling mengikuti standar operasional yang berlaku untuk lifting.

I. FULL ERECTION GRID 7-14 (LINE B-C)


a. Preparation I dilakukan di area Grid 7 – 14. Prosedur Preparation I di Grid 7-
14 Line B-C sama dengan Point B.
b. Prosedur Erection Rafter sama dengan Full Erection Grid 3-6 (Point G)
c. Prosedur Instalasi Purlin, Tie Beam, Bracing, & aksesoris lainnya sama
dengan Full Erection Grid 3-6 (Point G)
d. Finish Full Erection Grid 7-14.
e. Melakukan Inspeksi dan Plumbness.
f. Progress Pekerjaan Rafter Baja 50 %.

J. PREPARATION (LINE A-B)


a. Mobilisasi Alat Berat ke Line A-B.
b. Prosedur Preparation I di Line A-B sama dengan Point B.
c. Prosedur Preparation II di Line A-B sama dengan Point C.

K. CONTINUED SEQUENCE LINE A-B (Point D ~ S/D Point I)


a. Prosedur First Full Erection Grid 1 di Line A-B sama dengan Point D.
b. Prosedur Support & Plumbness sama dengan Point E.
c. Prosedur Full Erection Grid 2 di Line A-B sama dengan Point F.
d. Prosedur Full Erection Grid 3-6 di Line A-B sama dengan Point G.
e. Prosedur Dismantling Supporting Material sama dengan Point H.
f. Prosedur Full Erection Grid 7-14 di Line A-B sama Point I.
g. Progress Pekerjaan Rafter Baja 100 %.

17
JOB NO. : 179014 REV
ERECTION METHOD STATEMENT
DOC. NO. : 0014-C0-CP-513-R 1
DOME STEEL STRUCTURE
PT. REKADAYA ELEKTRIKA DATE BY CHKD APVD
19 -07-2019 MN BES ISF

8. HSE CONTROL
a. Seluruh personil yang terlibat di dalam pekerjaan ini ini harus menggunakan Alat
Pelindung Diri diantaranya Sepatu Safety, Helm Proyek, Sarung Tangan, Body
Harness, Masker dan sebagainya sesuai dengan ketentuan dari PT. PJB dan PT. RE.
b. Seluruh personil yang terlibat di dalam pekerjaan ini harus berpengalaman dan ahli
sesuai dengan bidangnya, pada posisi tertentu harus memiliki sertifikat sesuai dengan
ketentuan dari PT. PJB dan PT. RE.
c. Semua Peralatan dan Perlengkapan harus diinspeksi terlebih dahulu oleh PT. RE dan
disetujui oleh PT. PJB.
d. Prosedur lainnya secara spesifik disebutkan di dalam Standar Operasional Prosedur
Erection Steel Structure yang telah disepakati bersama oleh PT. PJB dan PT. RE.

9. QUALITY ASSURANCE
Kualitas material dan hasil pekerjaan akan dipastikan dari Project Team PT. Rekadaya
Elektrika yang terdiri dari Project Manager, Project Engineer, Site Manager, Quality
Control, dan Supervisor.

10. ATTACHMENTS
Work method for :
1. Rigging Plan

18