STRENGTH CALCULATION

OF
CCTV FOUNDATION
SAP2000 10/24/19 11:15:27

SAP2000 v14.2.2 - File:pondasi cctv - Axial Force Diagram (COMB2) - Kgf, m, C Units
SAP2000 10/24/19 11:17:36

SAP2000 v14.2.2 - File:pondasi cctv - Joint Reactions (COMB2) - Kgf, m, C Units


SAP2000 10/24/19 11:14:37

SAP2000 v14.2.2 - File:pondasi cctv - Moment 3-3 Diagram (COMB2) - Kgf, m, C Units
PENULANGAN KOLOM K1 (30x30)

Beban Aksial P = 852,45 kg


Beban Moment M = 307,06 kg.m
Tinggi Kolom lk = 110 cm

Lebar Penampang b = 30 cm
Tinggi Penampang ht = 30 cm

M 307,06
eo1 = = = 0,36 = 36,02 cm
P 852,45

1 30
eo2 = ht = = 1 cm
30 30

eo = eo1 + eo2 = 37,02 cm

eo 37,02
= = 1,23403 cm
ht 30

C2 = 7,7 7,7

C1 = 1 (1 kolom segi empat, 1.15 kolom bulat)

e1 = C1 C2 ( lk / 100.ht )2 . ht

2
= 1 7,7 ( 110 / 100 30 ) 30
= 0,311 cm

e2 = 0.15 ht = 4,50 cm

eu = eo + e1 + e2
= 37,02 + 0,311 + 4,5 = 41,83 cm

eau = eu + ( 1/2 ht )
= 41,83 + 15,0
= 56,83 cm

P . eau = 852,45 x 56,83 = 48.445,97 kg.cm


= 484,46 kg.m

PT ASUKA E I HAL. A-14 PT SHELL GRESIK - INDONESIA


Pembesian kolom :
- lebar kolom (b) = 300 mm
- beton decking (ds) = 25 mm
- tebal efektif d = 275 mm
- Mutu beton fc' = 22 MPa
- Mutu baja fy = 390 MPa

m = fc / (0,85 .fy)
= 390 / (0.85 . 22)
= 20,86

2
Rn = M / (φ b d )
= 4.844.597/(0.85.300.275,275)
= 0,251

ρ = (1/m) * (1 - ( 1 - ((2 Rn m)/fy)) )

= (1/20,86)*(1- ( 1 - ((2 . 0,251.20,86)/390)))

= 0,00065

Aperlu = ρ .b .d = 0,00065 300 275 = 53,50 mm2

Dipasang tulangan 8 d - 19 (A
4 act = D 13 ( Aact = 531 mm2) Ok

Pembesian begel :
Dsengkang D8 - 200 mm

S1 = 48x8 = 384 mm (48 x Diameter tulangan Sengkang)


S2 = 16x13 = 208 mm (16 x Diameter tulangan Longitudinal)
S3 = 300 mm (Sisi terpendek penampang)
Smin = 208 mm (Dipilih terpendek)
Spakai = 200 mm (Dibulatkan ke bawah)

4 D13
D8 - 200

D8
200

300

300

Detail Penulangan Kolom

PT ASUKA E I HAL. A-15 PT SHELL GRESIK - INDONESIA


PERHITUNGAN FONDASI FOOTPLAT
BENTUK EMPAT PERSEGI PANJANG

A. DATA FONDASI FOOT PLAT

DATA TANAH
Kedalaman fondasi, Df = 1,00 m
Berat volume tanah, γ= 17,60 kN/m3
Sudut gesek dalam, φ= 34,00 
Kohesi, c= 0,00 kPa
Tahanan konus rata-rata (hasil pengujian sondir), qc = 95,00 kg/cm2
DIMENSI FONDASI
Lebar fondasi arah x, Bx = 0,90 m
Lebar fondasi arah y, By = 0,90 m
Tebal fondasi, h= 0,25 m
Lebar kolom arah x, bx = 0,30 m
Lebar kolom arah y, by = 0,30 m
Posisi kolom (dalam = 40, tepi = 30, sudut = 20) αs = 40

PT ASUKA E I HAL B-1 PT SHELL GRESIK - INDONESIA


BAHAN KONSTRUKSI
Kuat tekan beton, fc' = 22,0 MPa
Kuat leleh baja tulangan, fy = 390 MPa
Berat beton bertulang, γc = 24 kN/m3
BEBAN RENCANA FONDASI
Gaya aksial akibat beban terfaktor, Pu = 8,360 kN
Momen arah x akibat beban terfaktor, Mux = 3,011 kNm
Momen arah y akibat beban terfaktor, Muy = 0,000 kNm

B. KAPASITAS DUKUNG TANAH

1. MENURUT TERZAGHI DAN PECK (1943)

Kapasitas dukung ultimit tanah menurut Terzaghi dan Peck (1943) :


qu = c * Nc * (1 + 0.3 * B / L) + D f * γ * Nq + 0.5 * B * N γ * (1 - 0.2 * B / L)

c= kohesi tanah (kN/m 2) c= 0,00 


Df = Kedalaman fondasi (m) Df = 1,00 m
γ= berat volume tanah (kN/m 3) γ= 17,60 kN/m3
B= lebar fondasi (m) B = By = 0,90 m
L= panjang fondasi (m) L = By = 0,90 m
Sudut gesek dalam, φ= 34,00 
φ = φ / 180 * π = 0,5934119 rad
φ/2)*tan φ
a = e(3*π / 4 - = 4,011409
Kpγ = 3 * tan [ 45 + 1/2*( φ + 33) ] = 72,476306
2

Faktor kapasitas dukung tanah menurut Terzaghi :


Nc = 1/ tan φ * [ a2 / (2 * cos 2 (45 + φ/2) - 1 ] = 52,637
Nq = a2 / [ (2 * cos 2 (45 + φ/2) ] = Nc * tan φ + 1 = 36,504
Nγ = 1/2 * tan φ * [ Kpγ / cos2 φ - 1 ] = 35,226
Kapasitas dukung ultimit tanah menurut Terzaghi :
qu = c*Nc*(1+0.3*B/L) + Df*γ*Nq + 0.5*B*Nγ*(1-0.2*B/L) = 655,16 kN/m2
Kapasitas dukung tanah, qa = qu / 3 = 218,39 kN/m2

PT ASUKA E I HAL B-2 PT SHELL GRESIK - INDONESIA


2. MENURUT MEYERHOF (1956)

Kapasitas dukung tanah menurut Meyerhof (1956) :


qa = qc / 33 * [ ( B + 0.3 ) / B ]2 * Kd ( dalam kg/cm2)
dengan, Kd = 1 + 0.33 * Df / B harus  1.33

2
qc = tahanan konus rata-rata hasil sondir pada dasar fondasi ( kg/cm )
B = lebar fondasi (m) B = By = 0,90 m
Df = Kedalaman fondasi (m) Df = 1,00 m
Kd = 1 + 0.33 * Df / B = 1,3666667 > 1.33
 diambil, Kd = 1,33
Tahanan konus rata-rata hasil sondir pada dasar fondasi, qc = 95,00 kg/cm2
qa = qc / 33 * [ ( B + 0.3 ) / B ]2 * Kd = 6,807 kg/cm2
2
Kapasitas dukung ijin tanah, qa = 680,67 kN/m

3. KAPASITAS DUKUNG TANAH YANG DIPAKAI

Kapasitas dukung tanah menurut Terzaghi dan Peck : qa = 218,39 kN/m2


Kapasitas dukung tanah tanah menurut Meyerhof : qa = 680,67 kN/m2
Kapasitas dukung tanah yang dipakai : qa = 218,39 kN/m2

C. KONTROL TEGANGAN TANAH

PT ASUKA E I HAL B-3 PT SHELL GRESIK - INDONESIA


Luas dasar foot plat, A = B x * By = 0,8100 m2
Tahanan momen arah x, Wx = 1/6 * By * Bx2 = 0,1215 m3
Tahanan momen arah y, Wy = 1/6 * Bx * By2 = 0,1215 m3
Tinggi tanah di atas foot plat, z = Df - h = 0,75 m
Tekanan akibat berat foot plat dan tanah, q = h * γc + z * γ = 19,200 kN/m2
Eksentrisitas pada fondasi :
ex = Mux / Pu = 0,3602 m > Bx / 6 = 0,1500 m (NG)
ey = Muy / Pu = 0,0000 m < By / 6 = 0,1500 m (OK)
Tegangan tanah maksimum yang terjadi pada dasar fondasi :
qmax = Pu / A + Mux / Wx + Muy / Wy + q = 54,304 kN/m2
qmax < qa  AMAN (OK)
Tegangan tanah minimum yang terjadi pada dasar fondasi :
2
qmin = Pu / A - Mux / Wx - Muy / Wy + q = 4,737 kN/m
qmin > 0  tak terjadi teg.tarik (OK)

D. GAYA GESER PADA FOOT PLAT

1. TINJAUAN GESER ARAH X

Jarak pusat tulangan terhadap sisi luar beton, d' = 0,075 m


Tebal efektif foot plat, d = h - d' = 0,175 m
Jarak bid. kritis terhadap sisi luar foot plat, ax = ( Bx - bx - d ) / 2 = 0,213 m
Tegangan tanah pada bidang kritis geser arah x,
qx = qmin + (Bx - ax) / Bx * (qmax - qmin) = 42,601 kN/m2
Gaya geser arah x, Vux = [ qx + ( qmax - qx ) / 2 - q ] * ax * By = 5,595 kN

PT ASUKA E I HAL B-4 PT SHELL GRESIK - INDONESIA


Lebar bidang geser untuk tinjauan arah x, b = By = 900 mm
Tebal efektif footplat, d= 175 mm
Rasio sisi panjang thd. sisi pendek kolom, βc = bx / by = 1,0000
Kuat geser foot plat arah x, diambil nilai terkecil dari V c yang diperoleh dari pers.sbb. :
Vc = [ 1 + 2 / βc ] * √ fc' * b * d / 6 * 10-3 = 369,370 kN
Vc = [ αs * d / b + 2 ] * √ fc' * b * d / 12 * 10-3 = 601,937 kN
Vc = 1 / 3 * √ fc' * b * d * 10-3 = 246,247 kN
Diambil, kuat geser foot plat,  Vc = 246,247 kN
Faktor reduksi kekuatan geser, φ = 0,75
Kuat geser foot plat, φ ∗Vc = 184,685 kN
Syarat yang harus dipenuhi,
φ ∗Vc ≥ Vux
184,685 > 5,595  AMAN (OK)

2. TINJAUAN GESER ARAH Y

Jarak pusat tulangan terhadap sisi luar beton, d' = 0,085 m


Tebal efektif foot plat, d = h - d' = 0,165 m
Jarak bid. kritis terhadap sisi luar foot plat, ay = ( By - by - d ) / 2 = 0,218 m
Tegangan tanah pada bidang kritis geser arah y,
qy = qmin + (By - ay) / By * (qmax - qmin) = 42,326 kN/m2
Gaya geser arah y, Vuy = [ qy + ( qmax - qy ) / 2 - q ] * ay * Bx = 5,699 kN
Lebar bidang geser untuk tinjauan arah y, b = Bx = 900 mm
Tebal efektif footplat, d= 165 mm
Rasio sisi panjang thd. sisi pendek kolom, βc = bx / by = 1,0000

PT ASUKA E I HAL B-5 PT SHELL GRESIK - INDONESIA


Kuat geser foot plat arah y, diambil nilai terkecil dari V c yang diperoleh dari pers.sbb. :
Vc = [ 1 + 2 / βc ] * √ fc' * b * d / 6 * 10-3 = 348,263 kN
Vc = [ αs * d / b + 2 ] * √ fc' * b * d / 12 * 10-3 = 541,743 kN
Vc = 1 / 3 * √ fc' * b * d * 10-3 = 232,176 kN
Diambil, kuat geser foot plat,  Vc = 232,176 kN
Faktor reduksi kekuatan geser, φ = 0,75
Kuat geser foot plat, φ ∗Vc = 174,132 kN
Syarat yang harus dipenuhi,
φ ∗Vc ≥ Vux
174,132 > 5,699  AMAN (OK)

3. TINJAUAN GESER DUA ARAH (PONS)

Jarak pusat tulangan terhadap sisi luar beton, d' = 0,085 m


Tebal efektif foot plat, d = h - d' = 0,17 m
Lebar bidang geser pons arah x, c x = bx + 2 * d = 0,465 m
Lebar bidang geser pons arah y, c y = by + 2 * d = 0,465 m
Gaya geser pons yang terjadi,
Vup = ( Bx * By - cx * cy ) * [ ( qmax + qmin ) / 2 - q ] = 6,128 kN
Luas bidang geser pons, Ap = 2 * ( c x + c y ) * d = 0,307 m2
Lebar bidang geser pons, bp = 2 * ( cx + cy ) = 1,860 m
Rasio sisi panjang thd. sisi pendek kolom, βc = bx / by = 1,0000
Tegangan geser pons, diambil nilai terkecil dari fp yang diperoleh dari pers.sbb. :

PT ASUKA E I HAL B-6 PT SHELL GRESIK - INDONESIA


fp = [ 1 + 2 / βc ] * √ fc' / 6 = 2,345 MPa
fp = [ αs * d / bp + 2 ] * √ fc' / 12 = 2,169 MPa
fp = 1 / 3 * √ fc' = 1,563 MPa
Tegangan geser pons yang disyaratkan, fp = 1,563 MPa
Faktor reduksi kekuatan geser pons, φ = 0,75
Kuat geser pons, φ * Vnp = φ * Ap * fp * 10 = 359,87
3
kN
Syarat : φ * Vnp ≥ Vup
359,872 > 6,128  AMAN (OK)
φ * Vnp ≥ Pu
359,872 > 8,360  AMAN (OK)

E. PEMBESIAN FOOTPLAT

1. TULANGAN LENTUR ARAH X

Jarak tepi kolom terhadap sisi luar foot plat, ax = ( Bx - bx ) / 2 = 0,300 m


Tegangan tanah pada tepi kolom,
qx = qmin + (Bx - ax) / Bx * (qmax - qmin) = 37,782 kN/m2
Momen yang terjadi pada plat fondasi akibat tegangan tanah,
Mux = 1/2 * ax2 * [ qx + 2/3 * ( qmax - qx ) - q ] * By = 1,199 kNm
Lebar plat fondasi yang ditinjau, b = By = 900 mm
Tebal plat fondasi, h= 250 mm
Jarak pusat tulangan thd. sisi luar beton, d' = 75 mm
Tebal efektif plat, d = h - d' = 175 mm

PT ASUKA E I HAL B-7 PT SHELL GRESIK - INDONESIA


Kuat tekan beton, fc' = 22 MPa
Kuat leleh baja tulangan, fy = 390 MPa
Modulus elastis baja, Es = 2,00E+05 MPa
Faktor distribusi teg. beton, β1 = 0,85
ρb = β1* 0.85 * fc’/ fy * 600 / ( 600 + fy ) = 0,0247009
Faktor reduksi kekuatan lentur, φ = 0,80
Rmax = 0.75 * ρb * fy * [1-½*0.75* ρb * fy / ( 0.85 * fc’ ) ] = 5,829
Mn = Mux / φ = 1,498 kNm
6 2
Rn = Mn * 10 / ( b * d ) = 0,05436
Rn < Rmax  (OK)
Rasio tulangan yang diperlukan,
ρ = 0.85 * fc’ / fy * [ 1 -  {1 – 2 * Rn / ( 0.85 * fc’ ) } ] = 0,0001
Rasio tulangan minimum, ρmin = 0,0025
Rasio tulangan yang digunakan,  ρ = 0,0025
Luas tulangan yang diperlukan, As = ρ * b * d = 393,75 mm2
Diameter tulangan yang digunakan, D 13 mm
Jarak tulangan yang diperlukan, s = π / 4 * D * b / As =
2
303 mm
Jarak tulangan maksimum, smax = 200 mm
Jarak tulangan yang digunakan,  s= 200 mm
Digunakan tulangan, D 13 - 200
Luas tulangan terpakai, As = π / 4 * D * b / s = 597,30
2
mm2

2. TULANGAN LENTUR ARAH Y

PT ASUKA E I HAL B-8 PT SHELL GRESIK - INDONESIA


Jarak tepi kolom terhadap sisi luar foot plat, ay = ( By - by ) / 2 = 0,300 m
Tegangan tanah pada tepi kolom,
qy = qmin + (By - ay) / By * (qmax - qmin) = 37,782 kN/m2
Momen yang terjadi pada plat fondasi akibat tegangan tanah,
Muy = 1/2 * ay2 * [ qy + 2/3 * ( q max - qy ) - q ] * B x = 1,199 kNm
Lebar plat fondasi yang ditinjau, b = Bx = 900 mm
Tebal plat fondasi, h= 250 mm
Jarak pusat tulangan thd. sisi luar beton, d' = 85 mm
Tebal efektif plat, d = h - d' = 165 mm
Kuat tekan beton, fc' = 22 MPa
Kuat leleh baja tulangan, fy = 390 MPa
Modulus elastis baja, Es = 2,00E+05 MPa
Faktor distribusi teg. beton, β1 = 0,85
ρb = β1* 0.85 * f c’/ fy * 600 / ( 600 + f y ) = 0,0247009
Faktor reduksi kekuatan lentur, φ = 0,80
Rmax = 0.75 * ρb * fy * [1-½*0.75* ρb * fy / ( 0.85 * f c’ ) ] = 5,829
Mn = Muy / φ = 1,498 kNm
6 2
Rn = Mn * 10 / ( b * d ) = 0,06115
Rn < Rmax  (OK)
Rasio tulangan yang diperlukan,
ρ = 0.85 * f c’ / fy * [ 1 -  {1 – 2 * Rn / ( 0.85 * f c’ ) } ] = 0,0002
Rasio tulangan minimum, ρmin = 0,0025
Rasio tulangan yang digunakan,  ρ = 0,0025
Luas tulangan yang diperlukan, As = ρ * b * d = 371,25 mm2
Diameter tulangan yang digunakan, D 13 mm
Jarak tulangan yang diperlukan, s = π / 4 * D * b / As =
2
322 mm
Jarak tulangan maksimum, smax = 200 mm
Jarak tulangan yang digunakan,  s= 200 mm
Digunakan tulangan, D 13 - 200
Luas tulangan terpakai, As = π / 4 * D * b / s = 597,30
2
mm2

PT ASUKA E I HAL B-9 PT SHELL GRESIK - INDONESIA


3. TULANGAN SUSUT

Rasio tulangan susut minimum, ρsmin = 0,0014


Luas tulangan susut arah x, Asx = ρsmin* d * Bx = 220,500 mm2
Luas tulangan susut arah y, Asy = ρsmin* d * By = 207,900 mm2
Diameter tulangan yang digunakan,  13 mm

Jarak tulangan susut arah x, sx = π / 4 * 2 * By / Asx = 542 mm


Jarak tulangan susut maksimum arah x, sx,max = 200 mm
Jarak tulangan susut arah x yang digunakan,  sx = 200 mm
Jarak tulangan susut arah y, sy = π / 4 *  * Bx / Asy =
2
575 mm
Jarak tulangan susut maksimum arah y, sy,max = 200 mm
Jarak tulangan susut arah y yang digunakan,  sy = 200 mm
Digunakan tulangan susut arah x,  13 - 200
Digunakan tulangan susut arah y,  13 - 200