CANDIDATE / RANK: T
LONGITUDE: 132.91065
LATITUDE: -5.80358
SITE ADDRESS: Jl.Desa, Desa Ohoi Larat,
Kec.Kei Besar Selatan
Kab Maluku Tenggara
Prop.Maluku
REGION: PUMA
SURVEYOR: Syahril Rachmad
NICK NAME : Syahril
PROJECT: B2S
PHASE: 2020
-1-
1. INFORMASI SITE
INFORMASI SITE
Titik Nominal (NOM)
Site ID : TUL147 Site ID Operator :
Nama site : LARAT Nama site Operator :
Alamat Site: Jl. desa, Desa Ohoi Larat Kec Kei Besar Selatan Kab Maluku Tenggara. Prov. Maluku
Koordinat Latitude: -5.804726 Koordinat Longitude: 132.909232
BTS Macro MCP BTS Hotel
Tipe Site :
MCP Semi Macro Lainnya : MINI MACRO
SAR (Search Area
200 m Arah SAR (Search Area Radius) : 0-3600
Radius):
Kandidat P :
Alamat site : Jl. desa, Desa Ohoi Larat Kec Kei Besar Selatan Kab Maluku Tenggara. Prov. Maluku
Koordinat latitude: -5.80358 Koordinat longitude: 132.91065
Pribadi
Jarak kandidat dari Kepemilikan lahan dan Private
200 m
titik NOM: luas lahan : Coorporate
Luas : 400 M2
Pengajuan harga oleh
Rp. /thn Perkiraan masa sewa : 11 tahun
pemilik lahan:
No. telepon pemilik
Nama pemilik lahan : AHMAD RAHAYAAN 082197582811
lahan:
Alamat pemilik lahan : Jl. desa, Desa Ohoi Larat Kec Kei Besar Selatan Kab Maluku Tenggara. Prov. Maluku
Airport : .............................................. Rumah Sakit : ...........................................
Pelabuhan : ........................................ Perumahan : .............................................
POI (Point Of
Stasiun Kereta : .................................. Mall : .........................................................
Interest) / Kawasan
Terminal Bis : ..................................... Sekolah / Kampus : ...................................
ramai di sekitar site:
Perkantoran : Kantor Desa Ohoi Ngursid Pasar Tradisional : toko
Kawasan Industri : ............................. Lainnya : ...................................................
Tipe area sekitar site : DenseUrban Urban SubUrban Rural
Tipe Site : Green Field Rooftop Inbuilding
Rekomendasi tipe
SST ( 62.m)
tower / pole:
Ya Gambarkan kondisi akses ke site : Akses ke site :
Tidak Dari Tual Ke Kec Kei Besar Selatan menggunakan Kapal Menggunakan roda 4
Adakah akses menuju
Setelah di Larat menggunakan Kendaraan Roda
site?
2.angkutan umum roda 4 Tidak ada.
Tipe Site : Green Field Rooftop
Site terdekat dengan Operator / Tower Provider :
kandidat (<700 m):
Jarak :
Longitude : Latitude :
Informasi penting lainnya lainnya :
……………………………………………………………………………………………………………………………………..
KETERSEDIAAN PLN
Jarak terdekat dari tiang PLN ke Jarak terdekat dari transformator
20 m 210 m
kandidat site : ke kandidat site :
Informasi penting lainnya / kebutuhan lainnya :
LISTRIK DARI PLN HANYA BEROPERASI 18 Jam dan Padam dari Jam 12.00 – 18.00.Trafo hanya 1 Unit dalam Desa.Material
semuanya diangkut dari Tual menggunakan Kapal Laut atau Longboat.tidak ada material di Lokasi
-2-
CAPTURED GOOGLE EARTH
Lokasi Site Google Earth Kandidat T
-3-
2. STREET MAP / SITE LOCATION SKETCH
UTARA
S
TRAFO
PELABUHAN
-4-
CANDIDATE PHOTOS
-5-
3. PRELIMINARY CME AND SITAC SURVEY REPORT
General Site Condition
Building Name - Owner Name -
Jl. Desa,Desa Ohoi Larat ,Kec.Kei Besar Selatan Telephone -
Street Address
,Kab Maluku Tenggara. Prov Maluku Mobile Phone -
Contact Person Name AHMAD RAHAYAAN
Contact Person
Jl. Desa,Desa Ohoi Larat ,Kec.Kei Besar Selatan ,Kab Maluku Tenggara. Prov Maluku
Address
Telephone 082197582811 Mobile Phone 082197582811
Access Hour 24 hour Work Hour 24 hour
Ground Elevation / Tower Height Planning / AGL Antenna Height Planning /
22 m 62 60/60/60
ASL (m) (m) AGL (m)
Site Type Green Field Rooftop Building Height / AGL (m)
Land Condition Very Good Good OK Bad Very Bad
Type of Soil Rocky √ Hard Other :
Roof Condition Very Good Good OK Bad Very Bad
Very
Access Road Condition √ Good OK Bad Very Bad
Good
Can Heavy Truck Access the Yes No Access Road : 10 x 3 M
Location
Electric Suplier PT PLN SWASTA Other :
Acquisition and Permit Information
Land/Rooftop Area Length x Width 12 x 10 m2 Area 120 m2
Lease 11 Years (Min) Yes
Acquisition Type Can Be Extended
Buy No
Girik / Persil No
Sertifikat No
Land Ownership SPPT / PBB No
Documents
Akte Jual-Beli No
√ Lain-Lain
Is the site located within 15 km from the Airport: √ Yes No , if yes 10 Km
Tata Kota
RT/RW IMB
(RUTR)
Kelurahan Bapeda Community
Kecamatan Hub Tel Socialisation
Permits Required
Ijin
Ijin Warga Ijin Prinsip
Dephub/Bandara
Ijin HO Ijin Lokasi
Lain-lain :
Government Permits OK NOT OK
Permit Possibilities
Community Permits OK NOT OK
-6-
Additional CME Work
No Item Information
1 Retaining Wall for Site Access No m3
2 Retaining Wall for Site No m3
3 Bridge/Small Bridge/Plat Decker No m2
4 Import Soil No m3
5 Cut and Fill (Leveling) No
YES.Transportasi Laut dari Tual Ke Kei Besar Selatan.Tidak ada Material CME diSekitar
6 Additional Transportation to site
Site.sehingga harus di datangkan dari Tual
7 Distance from Nearest Trafo 210 M
8 Distance from Nearest 3phase Pole 20 M
9 Site Extreme No
10 Flood Area (Daerah Banjir) No
11 Ketinggian Banjir Maksimum No M
12 PLN or PLTD Exist Yes,Pemadaman dari Jam 12.00 – 18.000
13 Power Supply from Company No
14 Power Supply Issue and Comments Proposed Tower SST 62 m, Perlu Penambahan Trafo karena hanya ada 1 Trafo di
Desa.dan atau Request Genset
-7-
Foto Panoramik 360 Degree
Kandidat T
0° 30°
60° 90°
120° 150°
-8-
180° 210°
240° 270°
300° 330°
Surveyor : Syahril
Tanggal survey: : 9 Maret 2020
-9-
Akses Jalan utamaKandidat T Akses Jalan Kandidat T
Lokasi Tower / Pole Kandidat T (Foto Lahan) Lokasi Tower/Pole Kandidat T (Tampak Jauh)
Surveyor :Syahril
Tanggal survey: 9 Maret 2020
- 10 -
Area Sekitar / POI Kandidat T (add) Area Sekitar / POI Kandidat T (add)
Surveyor :Syahril
Tanggal survey: 9 Maret 2020
- 11 -
Tower/pole Kompetitor site 1 (< 700 m) GPS Kompetitor site 1 (< 700 m)
LONG : LAT :
Surveyor :Syahril
Tanggal survey: 9 Maret 2020
- 12 -
KWH BOXKompetitor 1 KWH BOXKompetitor 1
Surveyor : Syahril
Tanggal survey: 9 Maret 2020
- 13 -
Tower/pole Kompetitor site 2 (< 700 m) GPS Kompetitor site 2 (< 700 m)
LONG : LAT :
Surveyor : Syahril
Tanggal survey: 9 Maret 2020
- 14 -
KWH BOXKompetitor 2 KWH BOXKompetitor 2
Surveyor : Syahril
Tanggal survey: 9 Maret 2020
- 15 -
SKETSA SITE
Utara
10 M
12 M
6M
Surveyor : Syahril
Tanggal survey: 9 Maret 2020
- 16 -
KESIMPULAN HASIL SURVEY
Hasil Survey:
Layak Dibangun Tidak Layak dibangun
Ok /
Internal Catatan Tanda Tangan PIC Tanggal
Tidak Ok
...............................................................
Civil and Mechanical Engineering ...............................................................
..............................................................
.............................................................. Nama :
...............................................................
...............................................................
Project Manager Regional
..............................................................
Nama :
..............................................................
- 17 -