Anda di halaman 1dari 92

SPESIFIKASI MATERIAL

PEKERJAAN : PEMBANGUNAN GEDUNG OLAHRAGA IPDN JAKARTA


LOKASI : Jl. Ampera Raya No.1, RT.1/RW.6, Cilandak Tim., Kec. Ps. Minggu, Kota Jakarta Selatan
TAHUN ANGGA : 2021

NO. RENCANA MATERIAL DIPAKAI Spesifikasi yang Di Rencanakan

1 2 3

1 Pasir ex. lokal


2 Batu Gunung / Kali ex. lokal
3 Batu Bata Merah ex. lokal
4 Batu Bata Blok pc ex. lokal
EX. Tiga Roda, Tonasa, Gresik, Holcym, Semen
5 Semen PC / 50 kg
Indonesia, Bosowa
6 Cat Air Dalam/ Interior Ex. Jotun Jotaplash
7 Cat Air Luar/ Exterior / Anti Lumut Ex. Jotun Jotashield
8 Cat Minyak Ex. Avian
9 Kayu Ex. lokal
Ex. Jaya Board, Elephant, Knauf , Eka Board /
10 Plafond Gipsum
Standar
11 Plafond PVC Ex. Sunda Plafond
12 GRC Ex. Ekaboard, Nusa Board
13 Besi Beton Ex. SNI
14 Baja Profil Ex. SNI
15 Pipa galvanized Ex. SNI
16 Besi Pipa Hollow Persegi Tebal Minimal 1 mm ( Pagar ) Ex. SNI
17 Besi Baut Ex. SNI
18 Atap Metal ex. Sakura Roof / Azoka Setara
19 Bubungan Atap Metal Ex. Bubungan Zincalium Sakura Roof / Asoka
20 Plywood / Kayu Lapis Ex. Standar
21 HPL / Hot Panel Laminating Ex. TACO Maspion
22 Keramik Ex. Asia Tile, Ikad, Mulia
23 Keramik Granit / Homogeneus Tile 60 x 60 cm Polished Ex. Indo Grass, Golf, Sejat, Happy, Standar
24 Kunci & Aksesoris Ex. Vintage
25 Grendel Pintu Dan Jendela Ex. Vintage
26 Hak Angin Dan Handle Jendela Ex. Vintage
27 Engsel Pintu dan Jendela Ex. Vintage
28 Kaca Ex. Standar
29 Pipa PVC Ex. Wavin, Maspion, Rucika
30 Kabel NYM ex Externa / Eterna
31 Kabel NYA ex Externa / Eterna
Sakla
32 Panasonic
rStop
33 Konta Panasonic
k
34 Imbodooos Dinding Panasonic
NO. RENCANA MATERIAL DIPAKAI Spesifikasi yang Di Rencanakan

Tee
35 Clypsal
Doos
36 Pipa Conduite Cabel Standar
37 Box MCB MK, Panasonic
38 Mcb Sirim, Snaiderh
39 Lampu Penerangan Downlight 13 Wat LED Philips
40 Exchaust Fan D 30 cm + Acc PANASONIC, KDK
Alat
41 Sanit
asi
Monoblok Closet Duduk CW 421 (termasuk aksesories) Ex. TOTO
Kran Doble Shower 1/2" Ex. Onda
Kran Biasa 1/2" Ex. Onda
Kran Cucian Piring Ex. Onda
Kran Air Jet Shower Ex. Onda
Floor Drain Ex. Onda
SPESIFIKASI MATERIAL

Spesifikasi yang ditawarkan

ex. lokal
ex. lokal
ex. lokal
ex. lokal
EX. Tiga Roda, Tonasa, Gresik,
Holcym, Semen Indonesia,
Bosowa
Ex. Jotun Jotaplash
Ex. Jotun Jotashield
Ex. Avian
Ex. lokal
Ex. Jaya Board, Elephant, Knauf ,
Eka Board / Standar
Ex. Sunda Plafond
Ex. Ekaboard, Nusa Board
Ex. SNI
Ex. SNI
Ex. SNI
Ex. SNI
Ex. SNI
ex. Sakura Roof / Azoka Setara
Ex. Bubungan Zincalium Sakura
Roof / Asoka
Ex. Standar
Ex. TACO Maspion
Ex. Asia Tile, Ikad, Mulia
Ex. Indo Grass, Golf, Sejat,
Happy, Standar
Ex. Vintage
Ex. Vintage
Ex. Vintage
Ex. Vintage
Ex. Standar
Ex. Wavin, Maspion, Rucika
ex Externa / Eterna
ex Externa / Eterna
Panasonic
Panasonic
Panasonic
Spesifikasi yang ditawarkan

Clypsal
Standar
MK, Panasonic
Sirim, Snaiderh
Philips
PANASONIC, KDK

Ex. TOTO
Ex. Onda
Ex. Onda
Ex. Onda
Ex. Onda
Ex. Onda
HARGA PERKIRAAN SENDIRI (HPS)
RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN GEDUNG OLAHRAGA IPDN JAKARTA


LOKASI : Jl. Ampera Raya No.1, RT.1/RW.6, Cilandak Tim., Kec. Ps. Minggu, Kota Jakarta Selatan
Daerah Khusus Ibukota Jakarta 12561
TAHUN ANGGARAN : 2021

PERATURAN MENTERI PEKERJAAN UMUM DAN PERUMAHAN RAKYAT NOMOR 22/PRT/M/2018


TENTANG PEDOMAN PEMBANGUNAN BANGUNAN GEDUNG NEGARA

Biaya
Biaya Pengelolaan
Biaya Konstruksi Perencanaan Biaya Manajemen Total Biaya
NO. Kegiatan
Fisik Konstruksi Konstruksi Pembangunan
Konstruksi
1 2 Konstruksi
3 4 5 6
1 3,002,915,000.00 380,280,000.00 283,620,000.00 142,500,000.00 3,809,315,000.00

Jakarta, 01 Maret 2021


HARGA PERKIRAAN SENDIRI (HPS)
REKAPITULASI

PEKERJAAN : PEMBANGUNAN GEDUNG OLAHRAGA IPDN JAKARTA


LOKASI : Jl. Ampera Raya No.1, RT.1/RW.6, Cilandak Tim., Kec. Ps. Minggu, Kota Jakarta Selatan
Daerah Khusus Ibukota Jakarta 12561
TAHUN ANGGA: 2021

NO. URAIAN PEKERJAAN JUMLAH

PEMBANGUNAN RUMAH DINAS

A PEKERJAAN PERSIAPAN Rp. 190,171,936.00


B PEKERJAAN STRUKTUR DAN PASANGAN
I PEKERJAAN PONDASI Rp. 654,168,209.51
II PEKERJAAN BETON Rp. 857,915,020.99
III PEKERJAAN PASANGAN DAN PLESTERAN Rp. 234,531,322.00
IV PEKERJAAN ATAP DAN PLAFOND Rp. 461,120,027.04
V PEKERJAAN PENGECATAN Rp. 118,352,734.28
VI PEKERJAAN LANTAI DAN DINDING Rp. 48,013,673.23
VII PEKERJAAN PINTU, JENDELA DAN PENGGANTUNGNYA Rp. 52,634,426.63
VIII PEKERJAAN PERALATAN SANITASI Rp. 11,959,723.68
IX PEKERJAAN MEKANIKAL DAN ELEKTRIKAL Rp. 38,874,200.00
X PEKERJAAAN HALAMAN DAN SARANA LAINYA Rp. 62,182,021.82

TOTAL Rp. 2,729,923,295.16


PPN 10% Rp. 272,992,329.52
JUMLAH + PPN 10% Rp. 3,002,915,624.68
JUMLAH DIBULATKAN Rp. 3,002,915,000.00

TERBILANG : …………………………………………………………………………………………….

Jakarta, 01 Maret 2021


HARGA PERKIRAAN SENDIRI (HPS)
RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN GEDUNG OLAHRAGA IPDN JAKARTA


LOKASI : Jl. Ampera Raya No.1, RT.1/RW.6, Cilandak Tim., Kec. Ps. Minggu, Kota Jakarta Selatan
Daerah Khusus Ibukota Jakarta 12561
TAHUN ANGGARAN : 2021

HARGA SATUAN (
NO. URAIAN PEKERJAAN SATUAN VOLUME
Rp. )

A PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Lokasi M2 1,152.000 18,590.00
2 Pek. Pengupasan lantai Beton dan Pembersihanya M2 1,152.000 27,582.50
3 Pek. Pemasangan Bowplank Dan Pengukuran M' 1,152.000 44,445.50
4 Pek. Pemenuhan SMK3 Konstruksi
a Penyiapan RK3K terdiri atas :
Pembuatan Kartu Identitas ( KIP ) Bh 10.000 150,000.00
b Sosialisasi dan Promosi K3 terdiri atas:
Spanduk / Barner Himbauan Untuk Keselamataan Ls 1.000 730,000.00
c Alat Pelindung Kerja terdiri atas
Topi Pelindung (safety Helmet) BH 10.000 175,000.00
Pelindung Pernapasan dan mulut (Masker) Bh 20.000 175,000.00
Sarung Tangan (safety Gloves) Psg 20.000 145,000.00
Sepatu Keselamatan (Safety Shoes) Psg 10.000 250,000.00
Rompi Keselamatan (Safety Vest) Psg 10.000 130,000.00
d Alat Pelindung Kerja terdiri atas:
Barikade / Pita Pengaman ( Do Not Cross ) Roll 2.000 500,000.00
e Asuransi Dan Perijinan terdiri atas :
BPJS Ketenaga Kerjaan ( Ansuransi Tenaga kerja Selama Berlangsun Ls 1.000 50,000,000.00
f Personil K3 terdiri atas :
Petugas P3K; OB 5.000 3,500,000.00
g Fasilitas sarana kesehatan:
Peralatan P3K ( Obat Luka, Perban, Dll, Serta Kotak P3K ) Ls 1.000 2,500,000.00
h Rambu-rambu terdiri atas :
Rambu Peringatan BH 4.000 150,000.00
JUMLAH ( A )
B PEKERJAAN STRUKTUR DAN PASANGAN
I PEKERJAAN PONDASI
1 Pek. Galian Tanah Pondasi M3 87.480 73,975.00
2 Pek. Urugan Kembali Galian Tanah Pondasi M3 29.160 33,000.00
3 Pek. Urugan Pasir Bawah Pondasi Dan Lantai M3 66.348 296,725.00
4 Pek. Pondasi Menerus Kali , Spesi 1pc : 4ps M3 489.600 1,238,634.98
5 Pek. Rollag Pasangan Bata 1 Batu Untuk Pondasi KM/WC Dan Teras M2 72.000 286,275.00
HARGA SATUAN (
NO. URAIAN PEKERJAAN SATUAN VOLUME
Rp. )

II PEKERJAAN BETON
1 Pekerjaan Pondasi Plat Setempat
Beton Plat Setempat 1,8 m x 1,8 m x 30 cm M3 26.244 1,303,860.40
Bekisting 2 x Pakai M2 58.320 152,121.75
Besi Penulangan Kg 3,280.500 19,449.65
2 Pekerjaan Sloof 15/25
Beton Kolom 15 x 25 x 300 cm M3 43.200 1,303,860.40
Bekisting 1 x Pakai M2 86.400 59,499.00
Besi Penulangan Kg 5,184.000 19,449.65
3 Pek. Pasangan Kolom 400 cm x 400 cm
Beton Kolom 10 x 15 cm M3 34.560 1,303,860.40
Bekistink 2 x Pakai M2 345.600 29,749.50
Besi Penulangan Kg 4,147.200 19,449.65
4 Pek. Beton Kolom Praktis 10/15
Beton Baalok Latei 10 x 20 cm M3 3.645 1,303,860.40
Bekisting 1 x Pakai M2 97.200 399,503.50
Besi Penulangan Kg 437.400 19,449.65
5 Pek. Beton Ring Balok 15/20
Beton Baalok Latei 12 x 20 cm M3 34.560 1,303,860.40
Bekistink 2 x Pakai M2 20.100 199,751.75
Besi Penulangan Kg 4,147.200 19,449.65
6 Pek. Plat Lantai Dan Kanopy Teras
Beton Plat Tebal 12 cm Dan Kanopy M3 88.200 1,303,860.40
Bekisting 1 x Pakai M2 5.400 277,755.50
Besi Penulangan Kg 7,938.000 19,449.65
HARGA SATUAN (
NO. URAIAN PEKERJAAN SATUAN VOLUME
Rp. )

III PEKERJAAN PASANGAN DAN PLESTERAN


1 Pek. Pasangan Batu Bata 1pc : 4ps Untuk Dinding Dapur Dan Pena M2 600.000 143,137.50
2 Pek. Kusen Aluminium Dan Daun Pintu Unit 40.000 501,710.55
3 Pek. Kusen Aluminium Dan Daun Pintu Utama Unit 1.000 25,000,000.00
4 Pek. Kusen Aluminium Dan Daun Jendela Unit 40.000 205,920.00
5 Pek. Plesteran Dinding 1pc : 4ps Termasuk Kanopy, Plat Dan kolom, M2 1,200.000 45,380.50
6 Pek. Acian Dinding Plesteran Semua Bagian Luar Dan Dalam Dengan M2 1,200.000 34,072.50

NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN ( Rp. )

IV PEKERJAAN ATAP DAN PLAFOND


1 Pek. Rangka Baja M2 576.000 200,219.80
2 Pas. Listplank Kayu Klas II 1.8 x 18 cm M' 1,152.000 72,567.00
3 Pas. Penutup Genteng Atap metal M2 576.000 84,617.50
4 Pek. Bubungan Genteng Atap Metal M' 50.000 87,371.16
5 Pek. Pasangan Plafond Rangka Metal Furing Dan Gifsum 9 mm M2 576.000 186,455.50
6 Pek. Pasangan Plafond PVC / Sunda Plafond 1 x 20 cm ( Motif Kayu ) M2 576.000 176,544.50

V PEKERJAAN PENGECATAN
1 Pek. Cat tembok Dinding Luar ( Wall Sealler, Cat Dasar, + Cat tembok M2 1,200.000 29,346.90
2 Pek. Cat tembok Dinding Dalam ( Plamir, Cat Dasar, + Cat tembok ) M2 1,200.000 44,719.40
3 Pek. Cat Plafond M2 576.000 41,097.10
4 Pek. Cat Kayu ( Pintu, Lisplank, Jendela ) M2 124.120 46,739.00

VI PEKERJAAN LANTAI DAN DINDING


1 Pek. Tiang Rangka Partisi Dinding Dari baja Ringan M2 63.750 200,219.80
2 Pek. Pasangan Dinding Dari Papan GRC 5 mm Untuk Dinding Dapur Si M2 27.360 81,346.10
3 Pek. Pasangan Dinding Dari Papan Gifsum 9 mm Untuk Dinding Dapur M2 27.360 68,744.50
4 Pek. Urugan Tanah M3 9.110 191,125.00
5 Pekerjaan Rabat Lantai Dapur tebal 7.5 cm M3 2.270 1,281,608.98
6 Pek. Urugan pasir bawah lantai 5 cm M3 0.720 296,725.00
7 Pek. Lantai Keramik Polished 40 x 40 cm M2 78.750 88,027.50
8 Pek. Lantai Keramik Un Polished 40 x 40 cm Untuk Tritisan belakang M2 13.680 88,027.50
9 Pek. Pasangan Lantai Keramik Kamar mandi / Wc Un Polished 25 x 2 M2 5.710 79,975.50
10 Pek. Pasangan Keramik Dinding Km/Wc Dan Dinding Dapur Polished M2 61.440 143,693.00
11 Pek. Pasangan Keramik Granit Homogeneus 60 x 60 cm Untuk Meja M2 8.775 244,612.50
12 Pek. Pasangan Tempat Sabun Tanam Dari Keramik Panjang 20 cm Bh 3.000 45,000.00
13 Pek. Pasangan meja beton Untuk dapur M3 0.850 1,303,860.40
Bekistink M2 9.520 277,755.50
Besi Penulangan Kg 45.110 19,449.65
Pas. Bata 1pc : 4ps M2 1.510 143,137.50
Plestran M2 3.840 45,380.50
Acian Plesteran M2 3.840 34,072.50
14 Pek. Pasangan Bak Cucian Piring 1 Lobang Unit 3.000 475,000.00
HARGA SATUAN (
NO. URAIAN PEKERJAAN SATUAN VOLUME
Rp. )

VII PEKERJAAN PINTU, JENDELA DAN PENGGANTUNGNYA


1 Pek. Pasang Daun Pintu Rangka Kayu Klas II Isi Panil Kayu Klas III Bh 15.000 790,281.25
2 Pek. Kusen Pintu Aluminium 4" Untuk Km/Wc M' 15.000 107,562.13
3 Pek. Daun Pintu Aluminium Panil Spandril Aluminium Untuk Km/Wc Bh 3.000 110,385.00
4 Pek. Daun Jendela Kayu Klas II Panil kaca 5 mm Bh 21.000 366,916.00
5 Pek. Pemasangan Engsel pintu 4" (1 pintu Di Pasang 3 buah Engsel / Psg 27.000 213,785.00
6 Pek. Pemasangan Kunci tanam 2 x Putar / Slaag Bh 15.000 89,457.50
7 Pek. Grendel Pintu Bh 15.000 175,202.50
8 Pek, Handel Jendela Bh 21.000 263,202.50
9 Pek. Engsel Jendela 3" Psg 21.000 142,752.50
10 Pek. Grendel Jendela 3" Bh 42.000 158,633.75
11 Pek. Hak Angin Jendela Bh 42.000 147,633.75

XIII PEKERJAAN PERALATAN SANITASI


1 Pek. Pasangan Kloset Duduk Standar Type Tabung CW 421 Bh 3.000 1,579,132.50
2 Pek. Pasangan Floor Drain Lantai Dari Steinlist Bh 3.000 95,452.50
3 Pek. Stop Kran Tee Stainless Untuk Kloset Duduk Bh 3.000 48,152.50
4 Pek. Pasangan Kran Air Dobel Shower Bh 3.000 103,152.50
5 Pek. Pasangan Kran Air Biasa Bh 3.000 61,902.50
6 Pek. Pasangan Kran Air Cucian Piring Bh 3.000 70,152.50
7 Pek. Pasangan Kran Hand Jet Shower Bh 3.000 105,352.50
8 Pek. Pasangan Gantungan Handuk Stainless di Pintu Bh 3.000 147,152.50
9 Pekerjaan Pipa Talang Pvc Aw 4" Di Belah Dan Penggantungnya Untu M' 67.900 65,073.25
10 Pek. Pasangan Knee Pvc AW 4" Untuk Talang Bh 27.000 27,500.00
11 Pek. PasanganTee Pvc AW 4" Untuk Talang Bh 6.000 27,900.00

NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN ( Rp. )

IX PEKERJAAN MEKANIKAL DAN ELEKTRIKAL


1 Pek. Instalasi Titik lampu + Instalasi Ttk 25.000 396,137.50
2 Pek. Instalasi Titik Stop Kontak Ttk 15.000 396,137.50
3 Pek. Pasang Saklar Ganda Dan Tunggal Bh 18.000 225,000.00
4 Pek. Pasang Stop Kontak Bh 15.000 225,000.00
5 Pek. Pasang Box Sekring 6 Group Dan Pemindahan KWH Listrik Bh 3.000 3,107,362.50
6 Pek. Lampu Downlight / DL 13 Wat LED Bh 25.000 190,000.00
7 Pek. Pasangan Exchaust Fan D 30 cm + Insatalansi Unit 3.000 510,537.50
HARGA SATUAN (
NO. URAIAN PEKERJAAN SATUAN VOLUME
Rp. )

X PEKERJAAAN HALAMAN DAN SARANA LAINYA


1 Pek. Galian Tanah Untuk untuk pemerataan Di Lokasi Rumdis 3 M3 7.000 73,975.00
2 Pek. Saluran Dari Pipa Pvc D 6" M' 82.930 111,586.75
3 Pek. Pasangan Bak Kontrol untuk Saluran Bh 10.000 372,627.18
4 Pek. Pembongkaran Dan Pemasangan Kembali Paving Blok M' 20.770 48,675.00
5 Pek. Penggantian Dan Pemasangan Pagar Besi Baru Dengan Model Baru M2 37.550 721,233.33
6 Pek. Pembersihan Dan Lumut Dinding pagar Untuk Pengecatan M2 145.150 10,862.50
7 Pek. Pengecatan Dinding Pagar Dengan Cat Anti Lumut M2 145.150 29,346.90
8 Pek. Pasangan kanstin Beton 1pc : 3psr : 6btpc M3 2.450 1,281,608.98
9 Pek. Plesteran Dinding kanstin 1pc : 2ps M2 35.000 45,380.50
10 Pek. Urugan tanah Subur Untuk Tanaman M3 25.200 191,125.00
11
### Pek. Rabat Beton 1pc : 3psr : 6btpc tebal 7,5 cm M3 4.065 1,281,608.98

JUMLAH

PPN 10%

JUMLAH + PPN 10 %

JUMLAH DIBULATKAN
A PERKIRAAN SENDIRI (HPS)
NCANA ANGGARAN BIAYA

Halaman 01

JUMLAH HARGA ( Rp.


)

21,415,680.00
31,775,040.00
51,201,216.00

1,500,000.00

730,000.00

1,750,000.00
3,500,000.00
2,900,000.00
2,500,000.00
1,300,000.00

1,000,000.00

50,000,000.00

17,500,000.00

2,500,000.00

600,000.00
190,171,936.00

6,471,333.00
962,280.00
19,687,110.30
606,435,686.21
20,611,800.00
654,168,209.51
JUMLAH HARGA ( Rp.
)

34,218,512.42
8,871,740.46
63,804,576.83

56,326,769.42
5,140,713.60
100,826,985.60

45,061,415.54
10,281,427.20
80,661,588.48

4,752,571.17
38,831,740.20
8,507,276.91

45,061,415.54
4,015,010.18
80,661,588.48

115,000,487.57
1,499,879.70
154,391,321.70
857,915,020.99
JUMLAH HARGA ( Rp.
)

85,882,500.00
20,068,422.00
25,000,000.00
8,236,800.00
54,456,600.00
40,887,000.00
234,531,322.00

Halaman 02

JUMLAH HARGA ( Rp. )

115,326,604.80
83,597,184.00
48,739,680.00
4,368,558.24
107,398,368.00
101,689,632.00

461,120,027.04

35,216,280.00
53,663,280.00
23,671,929.60
5,801,244.68

118,352,734.28

12,764,012.25
2,225,629.30
1,880,849.52
1,741,148.75
2,909,252.38
213,642.00
6,932,165.58
1,204,216.19
456,660.09
8,828,497.92
2,146,474.69
135,000.00
1,108,281.34
2,644,232.36
877,373.71
216,137.63
174,261.12
130,838.40
1,425,000.00

48,013,673.23
JUMLAH HARGA ( Rp.
)

11,854,218.75
1,613,431.88
331,155.00
7,705,236.00
5,772,195.00
1,341,862.50
2,628,037.50
5,527,252.50
2,997,802.50
6,662,617.50
6,200,617.50

52,634,426.63

4,737,397.50
286,357.50
144,457.50
309,457.50
185,707.50
210,457.50
316,057.50
441,457.50
4,418,473.68
742,500.00
167,400.00

11,959,723.68

Halaman 03

JUMLAH HARGA ( Rp. )

9,903,437.50
5,942,062.50
4,050,000.00
3,375,000.00
9,322,087.50
4,750,000.00
1,531,612.50

38,874,200.00
JUMLAH HARGA ( Rp.
)

517,825.00
9,253,889.18
3,726,271.82
1,010,979.75
27,082,311.67
1,576,691.88
4,259,702.54
3,139,942.00
1,588,317.50
4,816,350.00
5,209,740.50

62,182,021.82

2,729,923,295.16

272,992,329.52

3,002,915,624.68

3,002,915,000.00
DAFTAR ANALISA HARGA SATUAN

PEKERJAAN : PEMBANGUNAN GEDUNG OLAHRAGA IPDN JAKARTA


LOKASI : Jl. Ampera Raya No.1, RT.1/RW.6, Cilandak Tim., Kec. Ps. Minggu, Kota Jakarta Selatan
: Daerah Khusus Ibukota Jakarta 12561
TAHUN ANGGARAN : 2021

Harga Satuan Harga Upah Harga Bahan Jumlah Harga


No. Uraian Pekerjaan
( Rp ) ( Rp ) ( Rp ) ( Rp )

1 1 m1 Memasang Bowplank

A BAHAN

0.005 m3 Kayu 5/7 3,990,000.00 19,950.00

0.020 Kg Paku 20,000.00 400.00

0.002 m3 Papan 3,990,000.00 7,980.00

28,330.00

B TENAGA

0.050 Hr Tukang 120,000.00 6,000.00

0.050 Hr Pekerja 95,000.00 4,750.00

0.010 Hr Kepala Tukang 120,000.00 1,200.00

0.001 Hr Mandor 125,000.00 125.00

12,075.00

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 40,405.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 4,040.50

HARGA SATUAN PEKERJAAN 1 M' 44,445.50

2 1 m3 Galian Tanah Biasa

A BAHAN

B TENAGA

0.675 Hr Pekerja 95,000.00 64,125.00

0.025 Hr Mandor 125,000.00 3,125.00

67,250.00 67,250.00

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 67,250.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 6,725.00

HARGA SATUAN PEKERJAAN 1 M3 73,975.00

3 1 m Urugan Tanah Kembali 1/4 Galian


3

A BAHAN

B TENAGA

0.250 Hr Pekerja 95,000.00 23,750.00

0.050 Hr Mandor 125,000.00 6,250.00


30,000.00 30,000.00

C PERALATAN

- -

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 30,000.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 3,000.00

HARGA SATUAN PEKERJAAN 1 M3 33,000.00


4 1 m3 Timbunan Pasir/ Pasangan Kembali

A BAHAN

1.200 m3 Pasir Timbunan 200,000.00 240,000.00

240,000.00 240,000.00

B TENAGA

0.300 Hr Pekerja 95,000.00 28,500.00

0.010 Hr Mandor 125,000.00 1,250.00

29,750.00 29,750.00

C PERALATAN

- -

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 269,750.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 26,975.00

HARGA SATUAN PEKERJAAN 1 M3 296,725.00

5 1 m Timbunan Tanah Dan Pemadatan Dengan Alat bantu


3

BAHAN

1.200 m' Timbunan Tanah 120,000.00 144,000.00

TENAGA 144,000.00 144,000.00

0.300 Hr Pekerja 95,000.00 28,500.00

0.010 Hr Mandor 125,000.00 1,250.00

0.000 Hr 10,000.00 -

29,750.00 29,750.00

PERALATAN

- - -

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 173,750.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 17,375.00

HARGA SATUAN PEKERJAAN 1 M3 191,125.00

6 1 m Pasangan Pondasi Gunung ( 1 Pc : 4 Ps )


3

A BAHAN

1.200 m3 Batu Gunung 385,714.00 462,856.80

3.260 Zak Semen 85,000.00 277,100.00

0.520 m3 Pasir Pasangan 260,000.00 135,200.00

1 875,156.80 875,156.80

B TENAGA

0.750 Hr Tukang Batu 120,000.00 90,000.00

0.075 Hr Kepala Tukang 120,000.00 9,000.00

1.500 Hr Pekerja 95,000.00 142,500.00

0.075 Hr Mandor 125,000.00 9,375.00

250,875.00 250,875.00

C PERALATAN

- -
D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 1,126,031.80

JUMLAH OVER HEAD + PROFITE 15% D X 10% 112,603.18

HARGA SATUAN PEKERJAAN 1 M3 1,238,634.98


7 1 m2 Pasangan Dinding Bata ( 1 Pc : 4 Ps )

A BAHAN

55.000 Bh Batako 1,200.00 66,000.00

0.180 Zak Semen 85,000.00 15,300.00

0.020 m Pasir Pasangan


3
260,000.00 5,200.00

86,500.00 86,500.00

B TENAGA

0.050 Hr Tukang Batu 120,000.00 6,000.00

0.250 Hr Pekerja 95,000.00 23,750.00

0.015 Hr mandor 125,000.00 1,875.00

0.100 Hr Kepala Tukang 120,000.00 12,000.00

43,625.00 43,625.00

C PERALATAN

- -

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 130,125.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 13,012.50

HARGA SATUAN PEKERJAAN 1 M2 143,137.50

8 1 m2 Pasangan Dinding Bata ( 1 Pc : 2 Ps )

A BAHAN

55.000 Bh Bata 1,200.00 66,000.00

0.230 Zak Semen 85,000.00 19,550.00

0.015 m3 Pasir Pasang 260,000.00 3,900.00

89,450.00 89,450.00

B TENAGA

0.050 Hr Tukang Batu 120,000.00 6,000.00

0.250 Hr Pekerja 95,000.00 23,750.00

0.015 Hr Mandor 125,000.00 1,875.00

0.100 Hr Kepala Tukang 120,000.00 12,000.00

43,625.00 43,625.00

C PERALATAN

- -

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 133,075.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 13,307.50

HARGA SATUAN PEKERJAAN 1 M2 146,382.50


9 1 m2 Plesteran Biasa ( 1 Pc : 4 Ps )

A BAHAN

0.124 Zak Semen 85,000.00 10,540.00

0.024 m3 Pasir Pasang 260,000.00 6,240.00

16,780.00 16,780.00

B TENAGA

0.015 Hr Tukang Batu 120,000.00 1,800.00

0.015 Hr Kepala Tukang 120,000.00 1,800.00

0.200 Hr Pekerja 95,000.00 19,000.00

0.015 Hr Mandor 125,000.00 1,875.00

24,475.00 24,475.00

C PERALATAN

- -

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 41,255.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 4,125.50

HARGA SATUAN PEKERJAAN 1 M3 45,380.50

10 1 M2 Pasangan Tegel Porselin/ Keramik 25 X 40 CM

A BAHAN

10.000 Lbr Tegel Keramik 25 x 40 5,200.00 52,000.00

0.208 Zak Semen 85,000.00 17,680.00

0.045 m3 Pasir Pasang 260,000.00 11,700.00

0.013 Zak Semen Warna 94,000.00 1,175.00

82,555.00 82,555.00

B TENAGA

0.250 Hr Tukang Batu 120,000.00 30,000.00

0.100 Hr Pekerja 95,000.00 9,500.00

0.035 Hr Mandor 125,000.00 4,375.00

0.035 Hr Kepala Tukang 120,000.00 4,200.00

48,075.00 - 48,075.00

C PERALATAN

- -

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 130,630.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 13,063.00

HARGA SATUAN PEKERJAAN 1 M3 143,693.00

11 1 M Pasangan Tegel Porselin/ Keramik 40 X 40 CM


2

A BAHAN

0.250 Lbr Tegel Keramik 40 x 40 10,833.33 2,708.33

0.200 Zak Semen 85,000.00 17,000.00

0.045 m Pasir Pasang


3
260,000.00 11,700.00

0.013 Zak Semen Warna 43,333.29 541.67

31,950.00 31,950.00

B TENAGA

0.250 Hr Tukang Batu 120,000.00 30,000.00


0.100 Hr Pekerja 95,000.00 9,500.00

0.035 Hr Mandor 125,000.00 4,375.00

0.035 Hr Kepala Tukang 120,000.00 4,200.00

48,075.00 - 48,075.00

C PERALATAN

- -

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 80,025.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 8,002.50

HARGA SATUAN PEKERJAAN 1 M3 88,027.50


12 1 M2 Pasangan Tegel Porselin/ Keramik 25 X 25 CM

A BAHAN

16.000 Lbr Tegel Keramik Kasar 25 x25 1,593.75 25,500.00

0.208 Zak Semen 85,000.00 17,680.00

0.045 m Pasir Pasang


3
43,333.29 1,950.00

0.013 Zak Semen Warna - -

45,130.00 45,130.00

B TENAGA

0.250 Hr Tukang Batu 120,000.00 30,000.00

0.200 Hr Pekerja 95,000.00 19,000.00

0.035 Hr Mandor 125,000.00 4,375.00

0.035 Hr Kepala Tukang 120,000.00 4,200.00

27,575.00 - 27,575.00

C PERALATAN

- -

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 72,705.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 7,270.50

HARGA SATUAN PEKERJAAN 1 M3 79,975.50


### 1 m2 Pasangan Keramik Granit / Homogeneus Tile 60 x 60 cm Polished

A BAHAN

3.000 Lbr Keramik Granit / Homogeneus T 45,250.00 135,750.00

0.250 Zak Semen 85,000.00 21,250.00

0.030 m Pasir Pasang


3
260,000.00 7,800.00

164,800.00 164,800.00

B TENAGA

0.250 Hr Tukang Batu 120,000.00 30,000.00

0.200 Hr Pekerja 95,000.00 19,000.00

0.035 Hr Mandor 125,000.00 4,375.00

0.035 Hr Kepala Tukang 120,000.00 4,200.00

Jumlah 57,575.00 57,575.00

C PERALATAN

- -

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 222,375.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 22,237.50

HARGA SATUAN PEKERJAAN 1 M3 244,612.50

14 1 m Pekerjaan Saluran Terbuka Pasangan Bata


1

A BAHAN

0.160 m3 Galian 67,250.00 10,760.00

1.000 m2 Pas. Batu Bata 133,075.00 133,075.00

1.600 m2 Plesteran 1 : 3 80,691.80 129,106.88

0.023 m3 Cor Rabat 1,165,099.07 26,797.28

1.600 m2 Acian Plesteran 28,350.00 45,360.00

345,099.16

B TENAGA

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 345,099.16

JUMLAH OVER HEAD + PROFITE 15% D X 10% 34,509.92

HARGA SATUAN PEKERJAAN 1 M3 379,609.07

15 1 M' Pekerjaan Saluran Dari Pipa Pvc D 6"

A BAHAN

0.250 M3 Galian 67,250.00 16,812.50

0.023 M3 Pasir Pasang Urugan Pipa 260,000.00 5,980.00

1.100 M' Pipa Pvc C Dia. 6" 71,500.00 78,650.00

101,442.50 101,442.50

B TENAGA
- -

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 101,442.50

JUMLAH OVER HEAD + PROFITE 15% D X 10% 10,144.25

HARGA SATUAN PEKERJAAN 1 M3 111,586.75


16 1 BH BAK KONTROL SALULAN UNTUK PIPA

A BAHAN

0.180 m3 Galian 67,250.00 12,105.00

1.000 m2 Pas. Batu Bata 133,075.00 133,075.00

1.500 m Plesteran 1 : 3
2
80,691.80 121,037.70

0.018 m Cor Rabat


3
1,165,099.07 20,971.78

1.500 m Acian Plesteran


2
34,375.00 51,562.50

338,751.98

B TENAGA

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 338,751.98

JUMLAH OVER HEAD + PROFITE 15% D X 10% 33,875.20

HARGA SATUAN PEKERJAAN 1 M' 372,627.18

17 1 M' Saluran Dari Beton Camp. 1pc : 3ps : 5btpc

A BAHAN

0.180 m3 Galian 67,250.00 12,105.00

0.400 M2 Papan Belistink Plywood 9 mm 107,865.00 43,146.00

1.000 m2 Beton Camp. 1pc : 3ps : 5btpc 1,165,099.07 1,165,099.07

1.500 m2 Plesteran 1 : 3 80,691.80 121,037.70

0.018 m3 Beton Camp. 1pc : 3ps : 5btpc 1,165,099.07 20,971.78

1.500 m Acian Plesteran


2
34,375.00 51,562.50

1,413,922.05

B TENAGA

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 1,413,922.05

JUMLAH OVER HEAD + PROFITE 15% D X 10% 141,392.21

HARGA SATUAN PEKERJAAN 1 M' 1,555,314.26

16 1 m Pekerjaan List Beton


1

BAHAM

0.560 M2 Plesteran 1 : 3 80,691.80 45,187

0.560 M' Acian Plesteran Untuk List 34,375.00 19,250

64,437 64,437.41

TENAGA
PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 64,437.41

JUMLAH OVER HEAD + PROFITE 15% D X 10% 6,443.74

HARGA SATUAN PEKERJAAN 1 M3 70,881.15


17 1 M' Pekerjaan Pot Bunga/ Kanstin Tinggi 40 cm

A BAHAN

0.040 M3 Galian Tanah 67,250.00 2,690

0.400 m2 Pas. Batu Bata 1pc : 2ps 133,075.00 53,230

0.600 m2 Plesteran 1 : 3 80,691.80 48,415

0.600 m Acian Plesteran


2
34,375.00 20,625

124,960 124,960.08

B TENAGA

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 124,960.08

JUMLAH OVER HEAD + PROFITE 15% D X 10% 12,496.01

HARGA SATUAN PEKERJAAN 1 M3 137,456.09

18 1 M3 BETON UNTUK RABAT CAMPURAN 1PC : 3PS : 6BTPC ( Takaran Dari Ember Cat 20 Liter )

A BAHAN

0.750 m3 Batu Pecah 385,714.00 289,142.64

5.520 Zak Semen 85,000.00 469,200.00

0.591 m3 Pasir Pasang 260,000.00 153,771.43

215.000 Ltr Air Tawar 100.00 21,500.00

933,614.07 933,614.07

B TENAGA

0.275 Hr Tukang batu 120,000.00 33,000.00

0.028 Hr Kepala Tukang 120,000.00 3,360.00

1.650 Hr Pekerja 95,000.00 156,750.00

0.083 Hr Mandor 125,000.00 10,375.00

203,485.00 203,485.00

C PERALATAN

0.350 Jam Mesin Pengaduk / Molen 80,000.00 28,000.00

28,000.00 28,000.00

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 1,165,099.07

JUMLAH OVER HEAD + PROFITE 15% D X 10% 116,509.91

HARGA SATUAN PEKERJAAN 1 M3 1,281,608.98

19 1 M3 BETON UNTUK RABAT CAMPURAN 1PC : 2PS : 4BTPC ( Takaran Dari Ember Cat 20 Liter )

A BAHAN

0.762 m3 batu Pecah 385,714.00 293,999.78

6.520 Zak Semen 85,000.00 554,200.00

0.543 m Pasir Kasar


3
260,000.00 141,142.86

215.000 Ltr Air Tawar 100.00 21,500.00

1,010,842.64 1,010,842.64

B TENAGA

0.275 Hr Tukang Batu 120,000.00 33,000.00

0.028 Hr Kepala Tukang 120,000.00 3,360.00


1.050 Hr Pekerja 95,000.00 99,750.00

0.083 Hr mandor 125,000.00 10,375.00

146,485.00 146,485.00

C PERALATAN

0.350 Jam Beton Molen 80,000.00 28,000.00

28,000.00 28,000.00

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 1,185,327.64

JUMLAH OVER HEAD + PROFITE 15% D X 10% 118,532.76

HARGA SATUAN PEKERJAAN 1 M3 1,303,860.40


### 1 M3 BETON UNTUK RABAT CAMPURAN 1PC : 2PS : 3BTPC ( Takaran Dari Ember Cat 20 Liter )'

A BAHAN

0.776 m3 Batu Pecah 385,714.00 299,142.64

0.499 m3 Pasir Pasang 260,000.00 129,628.57

7.420 Kg Semen 85,000.00 630,700.00

215.000 Ltr Air Tawar 100.00 21,500.00

1,080,971.21 1,080,971.21

B TENAGA

0.500 Hr Tukang Batu 120,000.00 60,000.00

0.035 Hr Kepala Tukang batu 120,000.00 4,200.00

2.000 Hr Pekerja 95,000.00 190,000.00

1.000 Hr Mandor 125,000.00 125,000.00

379,200.00 379,200.00

C PERALATAN

0.350 Jam Molen 80,000.00 28,000.00

0.350 Jam Vibrator 80,000.00 28,000.00

56,000.00 56,000.00

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 1,516,171.21

JUMLAH OVER HEAD + PROFITE 15% D X 10% 151,617.12

HARGA SATUAN PEKERJAAN 1 M3 1,667,788.33

### Pekerjaan Penulangan/ Pembesian Untuk Tulangan Polos Dalam 10 Kg

A BAHAN

10.500 Kg Besi Tulangan 15,000.00 157,500.00

0.150 Kg kawat Beton 22,000.00 3,300.00

160,800.00 160,800.00

B TENAGA

0.070 Hr Tukang Besi 120,000.00 8,400.00

0.070 Hr Pekerja 95,000.00 6,650.00

0.001 Hr Mandor 125,000.00 125.00

0.007 Hr Kepala Tukang 120,000.00 840.00

16,015.00 16,015.00

C PERALATAN

Untuk Penulangan 1 Kg Besi Beton x 1/10 176,815.00

Untuk Penulangan 1 Kg Besi Beton x 1/10 17,681.50

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 17,681.50

JUMLAH OVER HEAD + PROFITE 15% D X 10% 1,768.15

HARGA SATUAN PEKERJAAN 1 KG 19,449.65


### Pekerjaan Penulangan/ Pembesian Untuk Tulangan Polos Ulir / Deformand 10 Kg

A BAHAN

10.500 Kg Besi Tulangan 15,000.00 157,500.00

0.150 Kg kawat Beton 22,000.00 3,300.00

160,800.00 160,800.00

B TENAGA

0.070 Hr Tukang Besi 120,000.00 8,400.00

0.070 Hr Pekerja 95,000.00 6,650.00

0.001 Hr Mandor 125,000.00 125.00

0.007 Hr Kepala Tukang 120,000.00 840.00

16,015.00 16,015.00

C PERALATAN

Untuk Penulangan 1 Kg Besi Beton x 1/10 176,815.00

Untuk Penulangan 1 Kg Besi Beton x 1/10 17,681.50

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 17,681.50

JUMLAH OVER HEAD + PROFITE 15% D X 10% 1,768.15

HARGA SATUAN PEKERJAAN 1 Kg 19,449.65

E 1 m2 Cetakan Bekesting

Bekisting Kolom, Dan Balok Prakatis

A BAHAN

0.010 Kg Paku 20,000.00 200.00

0.002 m3 Balok Kayu 3,990,000.00 7,980.00

0.360 Lbr Plywood 9 mm 72,000.00 25,920.00

0.000 Btg Dolken kayu Galam 8/10 30,000.00 -

34,100.00 34,100.00

B TENAGA

0.020 Hr Tukang Kayu 120,000.00 2,400.00

0.180 Hr Pekerja 95,000.00 17,100.00

0.002 Hr Mandor 125,000.00 250.00

0.002 Hr Kepala Tukang 120,000.00 240.00

19,990.00 19,990.00

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 54,090.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 5,409.00

HARGA SATUAN PEKERJAAN 1 M2 59,499.00


Bekisting Plat, Dan Kanopy Dan Tangga

A BAHAN

0.400 Kg Paku 20,000.00 8,000.00

0.030 m3 Balok Kayu 3,990,000.00 119,700.00

0.360 Lbr Plywood 9 mm 72,000.00 25,920.00

2.000 Btg Dolken kayu Galam 8/10 30,000.00 60,000.00

213,620.00 213,620.00

B TENAGA

0.130 Hr Tukang Kayu 120,000.00 15,600.00

0.160 Hr Pekerja 95,000.00 15,200.00

0.033 Hr Mandor 125,000.00 4,125.00

0.033 Hr Kepala Tukang 120,000.00 3,960.00

38,885.00 38,885.00

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 252,505.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 25,250.50

HARGA SATUAN PEKERJAAN 1 M2 277,755.50

G Bekisting Pondasi Plat

A BAHAN

0.300 Kg Paku 20,000.00 6,000.00

0.040 m3 Balok Kayu 3,990,000.00 159,600.00

0.360 Lbr Plywood 9 mm 72,000.00 25,920.00

0.000 Btg Dolken kayu Galam 8/10 30,000.00 -

191,520.00 191,520.00

B TENAGA

0.260 Hr Tukang Kayu 120,000.00 31,200.00

0.520 Hr Pekerja 95,000.00 49,400.00

0.026 Hr Mandor 125,000.00 3,250.00

0.026 Hr Kepala Tukang 120,000.00 3,120.00

86,970.00 86,970.00

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 278,490.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 27,849.00

HARGA SATUAN PEKERJAAN 1 M2 306,339.00


H Bekisting Sloof ( Papan Multiplek 9 mm ) 2 x pemakaian

A BAHAN

0.150 Kg Paku 20,000.00 3,000.00

0.020 m3 Kayu Bekisting 3,990,000.00 79,800.00

0.360 Lbr Papan Multiplek 9mm 72,000.00 25,920.00

2.000 Btg Dolken kayu Galam 8/10 30,000.00 60,000.00

168,720.00 168,720.00

B TENAGA

0.500 Hr Tukang kayu 120,000.00 60,000.00

0.500 Hr Pekerja 95,000.00 47,500.00

0.001 Hr Mandor 125,000.00 125.00

0.002 Hr Kepala Tukang 120,000.00 240.00

107,865.00 107,865.00

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 276,585.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 27,658.50

HARGA SATUAN PEKERJAAN 1 M2 304,243.50

I 1 M 2 Bekisting Kolom ( Papan Multiplek 9 mm ) 2 x pemakaian

A BAHAN

0.400 Kg Paku 20,000.00 8,000.00

0.040 m3 Kayu Terentang 3,990,000.00 159,600.00

0.350 Lbr Plywood 9 mm 72,000.00 25,200.00

2.000 Btg Dolken kayu Galam 5-9/5m' 30,000.00 60,000.00

252,800.00 252,800.00

B TENAGA

0.330 Hr Tukang Kayu 120,000.00 39,600.00

0.660 Hr Pekerja 95,000.00 62,700.00

0.033 Hr Mandor 125,000.00 4,125.00

0.033 Hr Kepala Tukang 120,000.00 3,960.00

110,385.00 110,385.00

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 363,185.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 36,318.50

HARGA SATUAN PEKERJAAN 1 M2 399,503.50

J 1 m2 Bekisting Balok ( Papan Multiplek 9 mm )

BAHAN

0.400 Kg Paku 20,000.00 8,000.00

0.040 m Balok Kayu Bekisting Bekisting


3
3,990,000.00 159,600.00

0.350 Lbr Plywood 9 mm 72,000.00 25,200.00

2.000 Btg Dolken kayu Galam 5-9/5m' 30,000.00 60,000.00

252,800.00 252,800.00

B TENAGA
0.330 Hr Tukang Kayu 120,000.00 39,600.00

0.660 Hr Pekerja 95,000.00 62,700.00

0.033 Hr Mandor 125,000.00 4,125.00

0.033 Hr Kepala Tukang 120,000.00 3,960.00

110,385.00 110,385.00

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 363,185.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 36,318.50

HARGA SATUAN PEKERJAAN 1 M2 399,503.50


23 1 M2 Beton Cor Lantai Kerja Tebal 7.5 cm

A BAHAN

0.075 M3 1 m2 Beton Cor Lantai Kerja Tebal 7.5


1,165,099.07
cm 87,382.43

B TENAGA

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 87,382.43

JUMLAH OVER HEAD + PROFITE 15% D X 10% 8,738.24

HARGA SATUAN PEKERJAAN 1 M2 96,120.67

### 1 m2 Pemasangan Rangka Atap Baja Ringan

A BAHAN

5.000 m' TRUSS C-75-75 31,742.00 158,710.00

3.000 m V Reng 5,000.00 15,000.00

28.000 Bh Skrup 1,500.00 42,000.00

2.000 bh Dynabolt 1,500.00 3,000.00

218,710.00 218,710.00

B TENAGA

0.450 Hr Tukang 120,000.00 54,000.00

0.200 Hr Pekerja 95,000.00 19,000.00

0.050 Hr mandor 125,000.00 6,250.00

0.010 Hr Kepala Tukang 120,000.00 1,200.00

80,450.00 80,450.00

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 299,160.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 29,916.00

HARGA SATUAN PEKERJAAN 1 M2 329,076.00

25 1 m Memasang Bubungan Atap Sakura Roof


1

A BAHAN

1.100 Lbr Nok Genteng Metal Sakura Roo 39,500.00 43,450.00

2.000 m' Reng Baja Ringan 5,000.00 10,000.00

0.040 Kg Skrup Baja Hitam 1 1/4" 43,333.29 1,733.33

55,183.33 55,183.33

B TENAGA
0.070 Hr Tukang Kayu 120,000.00 8,400.00

0.150 Hr Pekerja 95,000.00 14,250.00

0.007 Hr Mandor 125,000.00 875.00

0.006 Hr Kepala Tukang 120,000.00 720.00

24,245.00 24,245.00

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 79,428.33

JUMLAH OVER HEAD + PROFITE 15% D X 10% 7,942.83

HARGA SATUAN PEKERJAAN 1 M2 87,371.16


### 1 m1 Mengerjakan Papan Listplank Calcyboard 100 cm x 20 cm x 1 Lapis

A BAHAN

1.2000 M' Papan Listplank Calcyboard 1 23,250.00 27,900.00

5.000 Bh Skrup Atap 1,500.00 7,500.00

35,400.00 35,400.00

B TENAGA

0.100 Hr Tukang Kayu 120,000.00 12,000.00

0.050 Hr Pekerja 95,000.00 4,750.00

0.010 Hr Mandor 125,000.00 1,250.00

0.010 Hr Kepala Tukang 120,000.00 1,200.00

19,200.00 19,200.00

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 54,600.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 5,460.00

HARGA SATUAN PEKERJAAN 1 M' 60,060.00

27 1 m Memasang Atap Zincalum Colour


2
1.26

A BAHAN

1.000 Lbr Zincalum Colour ( 0.70 x 1.80 ) 48,000.00 48,000.00

5.000 Bh Mur Baut 1,000.00 5,000.00

53,000.00 53,000.00

B TENAGA

0.100 Hr Pekerja 95,000.00 9,500.00

0.005 Hr Mandor 125,000.00 625.00

0.100 Hr Tukang kayu 120,000.00 12,000.00

0.015 Hr Kep. Tukang kayu 120,000.00 1,800.00

23,925.00 - 23,925.00

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 76,925.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 7,692.50

HARGA SATUAN PEKERJAAN 1 M2 84,617.50

28 1 m1 Mengerjakan Listplank / kayu Kelas II Ukuran ( 2 x 18 x 100 ) cm

A BAHAN

0.0055 m3 Papan kayu Kelas II 4,990,000.00 27,445.00

0.100 Kg Paku 20,000.00 2,000.00

29,445.00 29,445.00

B TENAGA
0.200 Hr Tukang Kayu 120,000.00 24,000.00

0.100 Hr Pekerja 95,000.00 9,500.00

0.005 Hr Mandor 125,000.00 625.00

0.020 Hr Kepala Tukang 120,000.00 2,400.00

36,525.00 36,525.00

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 65,970.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 6,597.00

HARGA SATUAN PEKERJAAN 1 M2 72,567.00


29 1 m2 rangka/ Gantungan Plafond Kayu Klas III

BAHAN

0.015 m3 Kayu Kelas III 3,990,000.00 61,446.00

0.200 Kg paku 20,000.00 4,000.00

65,446.00 65,446.00

TENAGA

0.300 Hr Tukang kayu 120,000.00 36,000.00

0.030 Hr Kepala Tukang 120,000.00 3,600.00

0.150 Hr Pekerja 95,000.00 14,250.00

0.075 Hr Mandor 125,000.00 9,375.00

63,225.00 63,225.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 128,671.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 12,867.10

HARGA SATUAN PEKERJAAN 1 M2 141,538.10


30 1 m3 Mengerjakan Kozen Kayu Bengkirai

BAHAN

1.200 m3 kayu Bengkirai 4,990,000.00 5,988,000.00

4.750 Kg Paku

5,988,000.00 5,988,000.00

TENAGA

18.000 Hr Tukang Kayu 120,000.00 2,160,000.00

6.000 Hr Pekerja 95,000.00 570,000.00

0.300 Hr Mandor 125,000.00 37,500.00

2.000 Hr Kepala Tukang 120,000.00 240,000.00

3,007,500.00 3,007,500.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 8,995,500.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 899,550.00

HARGA SATUAN PEKERJAAN 1 M' 9,895,050.00

31 1 Lobang Mengerjakan Kozen Kayu Bengkirai Untuk Jendela / Pintu

BAHAN

0.046 m3 kayu Bengkirai 4,990,000.00 230,538.00

230,538.00 230,538.00

TENAGA

1.350 Hr Tukang Kayu 120,000.00 162,000.00

0.450 Hr Pekerja 33,834 95,000.00 42,750.00

0.023 Hr Mandor 125,000.00 2,812.50

0.150 Hr Kepala Tukang 120,000.00 18,000.00

225,562.50 225,562.50

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 456,100.50

JUMLAH OVER HEAD + PROFITE 15% D X 10% 45,610.05

HARGA SATUAN PEKERJAAN 1 LOBANG KUSEN 501,710.55

31 1 m2 Mengecat Dinding Tembok Luar Dengan Cat Weatershield 2 x Sapu, Untuk tembokLuar Yang Berlumut Lama Dan Di Cuci Dulu Sebeelum Di Cat D

BAHAN

0.180 Kg Cat Tembok Weathersield 45,000.00 8,100.00

0.120 Kg Cat Dasar/ Wall Sealler 75,000.00 9,000.00

0.200 Lbr Kertas Gosok 5,000.00 1,000.00

18,100.00 18,100.00

TENAGA
0.042 Hr Tukang Cat 120,000.00 5,040.00

0.028 Hr Pekerja 95,000.00 2,660.00

0.003 Hr Mandor 125,000.00 375.00

0.004 Hr Kepala Tukang 120,000.00 504.00

8,579.00 - 8,579.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 26,679.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 2,667.90

HARGA SATUAN PEKERJAAN 1 M2 29,346.90


32 1 m2 Mengecat Dinding Tembok Dalam yang pernah di Cat / Cat Lama, 1 lapis Cat Dasar + 2 Lapis Cat Peutup ( Cat Dalam )

BAHAN

0.180 Kg Cat Tembok Dalam 90,000.00 16,200.00

0.120 Kg Cat Dasar/ Wall Sealler 75,000.00 9,000.00

25,200.00 25,200.00

TENAGA

0.042 Hr Tukang Cat 120,000.00 5,040.00

0.028 Hr Pekerja 95,000.00 2,660.00

0.003 Hr Mandor 125,000.00 375.00

0.004 Hr Kepala Tukang 120,000.00 504.00

8,579.00 - 8,579.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 33,779.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 3,377.90

HARGA SATUAN PEKERJAAN 1 M2 37,156.90

33 1 m2 Mengecat Dinding Tembok Baru Dalam yang Belum pernah di Cat, 1 Lapis Plamur Skim Coat + 1 lapis Cat Dasar + 2 Lapis Cat Peutup ( Cat Dalam

BAHAN

0.260 Kg Cat Tembok Dalam 90,000.00 23,400.00

0.100 Kg Cat Dasar/ Wall Sealler 75,000.00 7,500.00

0.100 Kg Plamir Skim Coat 1,750.00 175.00

0.200 Lbr Kertas Gosok 5,000.00 1,000.00

32,075.00 32,075.00

TENAGA

0.042 Hr Tukang Cat 120,000.00 5,040.00

0.028 Hr Pekerja 95,000.00 2,660.00

0.003 Hr Mandor 125,000.00 375.00

0.004 Hr Kepala Tukang 120,000.00 504.00

8,579.00 - 8,579.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 40,654.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 4,065.40

HARGA SATUAN PEKERJAAN 1 M2 44,719.40


### 1 m2 Mengecat Dinding Tembok Baru 3 x Sapu ( Cat Luar ) Cat Weathersield Anti Lumut ( Cat Luar )

BAHAN

0.260 Kg Cat Tembok Watershield 45,000.00 11,700.00

0.100 Kg Cat Dasar/ Wall Sealler 75,000.00 7,500.00

0.150 Lbr Kertas Gosok 5,000.00 750.00

19,950.00 19,950.00

TENAGA

0.003 Hr Tukang Cat 120,000.00 360.00

0.020 Hr Pekerja 95,000.00 1,900.00

0.003 Hr Mandor 125,000.00 375.00

0.006 Hr Kepala Tukang 120,000.00 756.00

3,391.00 3,391.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 23,341.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 2,334.10

HARGA SATUAN PEKERJAAN 1 M2 25,675.10

35 1 Lobang Mengerjakan Kozen Kayu Ukuran 5 x 12 cm

BAHAN

1.000 Btg Kayu Bengkirai Balok Ukuran 251,388.89 251,388.89

0.075 Kg Paku Biasa 20,000.00 1,500.00

252,888.89 252,888.89

TENAGA

1.000 Hr Tukang Kayu 120,000.00 120,000.00

0.750 Hr Pekerja 95,000.00 71,250.00

0.001 Hr Mandor 125,000.00 125.00

0.010 Hr Kepala Tukang 120,000.00 1,200.00

192,575.00 192,575.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 445,463.89

JUMLAH OVER HEAD + PROFITE 15% D X 10% 44,546.39

HARGA SATUAN PEKERJAAN 1 LOBANG KUSEN 490,010.28


36 1 Lobang Mengerjakan Kozen Kayu Ventilasi 3.5 x 12 cm

BAHAN

0.400 Btg Kayu Bengkirai Balok Ukuran 100,000.00 40,000.00

0.200 M2 Kawat Kasa Aluminium 19,000.00 3,800.00

0.075 Kg Paku Biasa 61,000.00 4,575.00

48,375.00 48,375.00

TENAGA

0.750 Hr Tukang Kayu 120,000.00 90,000.00

0.500 Hr Pekerja 95,000.00 47,500.00

0.001 Hr Mandor 125,000.00 125.00

0.010 Hr Kepala Tukang 120,000.00 1,200.00

138,825.00 138,825.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 187,200.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 18,720.00

HARGA SATUAN PEKERJAAN 1 LOBANG KUSEN 205,920.00

### 1 Bh Membuat Pintu Rangka Kayu Klas II Dan Isi Panil Kayu Klas III

BAHAN

1.750 Btg Kayu Bengkirai, Jarum Jaru, B 100,000.00 175,000.00

1.000 Kg Lem Kayu PVAC 15,000.00 15,000.00

0.350 Kg Lem Minyak 25,000.00 8,750.00

1.700 Btg Papan Pengisi Untuk Panil, Kay 115,000.00 195,500.00

394,250.00 394,250.00

TENAGA

1.650 Hr Tukang Kayu 120,000.00 198,000.00

0.550 Hr Pekerja 95,000.00 52,250.00

0.088 Hr Mandor 125,000.00 10,937.50

0.525 Hr Kepala Tukang 120,000.00 63,000.00

324,187.50 324,187.50

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 718,437.50

JUMLAH OVER HEAD + PROFITE 15% D X 10% 71,843.75

HARGA SATUAN PEKERJAAN 1 PINTU KAYU ISI PANIL KAYU PAPAN 790,281.25

### 1 M2 Membuat Daun Pintu Rangka Kayu Klas II Dan Isi Panil Kayu

BAHAN
Kayu Bengkirai, Jarum Jaru,
Barsolok Balok Ukuran 5/14
0.060 Btg cm Panjang 400 cm 4,990,000.00 299,400.00
( Termasuk barang
Terbuang )
1.000 Kg Lem Kayu PVAC 15,000.00 15,000.00

0.350 Kg Lem Minyak 25,000.00 8,750.00


323,150.00 323,150.00

TENAGA

2.000 Hr Tukang Kayu 95,000.00 190,000.00

0.750 Hr Pekerja 125,000.00 93,750.00

0.050 Hr Mandor 120,000.00 6,000.00

0.300 Hr Kepala Tukang 120,000.00 36,000.00

325,750.00 325,750.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 648,900.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 64,890.00

HARGA SATUAN PEKERJAAN 1 PINTU KAYU ISI PANIL KAYU PAPAN 713,790.00
### 1 M2 Membuat Daun Pintu Rangka Kayu Klas II Dan Isi Panil Kayu

BAHAN
Kayu Bengkirai, Jarum Jaru,
Barsolok Balok Ukuran 5/14
0.050 Btg cm Panjang 400 cm 4,990,000.00 249,500.00
( Termasuk barang
Terbuang )
0.500 Kg Lem Kayu PVAC 15,000.00 7,500.00

0.200 Kg Lem Minyak 25,000.00 5,000.00

262,000.00 262,000.00

TENAGA

2.500 Hr Tukang Kayu 120,000.00 300,000.00

1.000 Hr Pekerja 95,000.00 95,000.00

0.050 Hr Mandor 125,000.00 6,250.00

0.250 Hr Kepala Tukang 120,000.00 30,000.00

431,250.00 431,250.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 693,250.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 69,325.00

HARGA SATUAN PEKERJAAN 1 PINTU KAYU ISI PANIL KAYU PAPAN 762,575.00

### 1 Bh Membuat Pintu Rangka Kayu Klas II Dan Isi Panil Kayu Klas III Sisi Dalam Di lapis Aluminiumm Kulit Jeruk

A BAHAN

2.000 Btg Kayu Bengkirai, Jarum Jaru, B 100,000.00 200,000.00

0.150 Kg Paku Biasa 20,000.00 3,000.00

1.000 Kg Lem Kayu PVAC 15,000.00 15,000.00

0.350 Kg Lem Minyak 25,000.00 8,750.00

2.000 Btg Papan Pengisi Untuk Panil, Kay 115,000.00 230,000.00

1.700 Lbr Plyawood Lapis Aluminium Moti 160,000.00 272,000.00

728,750.00 728,750.00

B TENAGA

6.000 Hr Tukang Kayu 120,000.00 720,000.00

2.000 Hr Pekerja 95,000.00 190,000.00

0.100 Hr Mandor 125,000.00 12,500.00

0.600 Hr Kepala Tukang 120,000.00 72,000.00

922,500.00 922,500.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 1,651,250.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 165,125.00

HARGA SATUAN PEKERJAAN 1 PINTU KAYU ISI PANIL KAYU PAPAN 1,816,375.00

1 Bh Membuat Daun Jendela Rangka Kayu Panil Kaca Ryben 5 mm Ukuran ( 1.15 x 0.70 ) m - ( 1.40 x 0.65 ) m

BAHAN

0.019 Btg Kayu Bengkirai, Jarum Jaru, B 4,990,000.00 94,810.00

0.300 Kg Lem Kayu PVAC 20,000.00 6,000.00

0.580 M2 Kaca Ryben 5 mm 62,500.00 36,250.00


137,060.00 137,060.00

TENAGA

1.050 Hr Tukang Kayu 120,000.00 126,000.00

0.500 Hr Pekerja 95,000.00 47,500.00

0.040 Hr Mandor 125,000.00 5,000.00

0.150 Hr Kepala Tukang 120,000.00 18,000.00

196,500.00 196,500.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 333,560.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 33,356.00

HARGA SATUAN PEKERJAAN 1 BH DAUN JENDELA 366,916.00


### 1 m2 Mengecat Dinding Kayu Dengan Cat Air 3 x Sapu ( untuk dinding kayu )

BAHAN

0.280 Kg Cat Tembok Standar 90,000.00 25,200.00

0.750 Lbr Kertas Gosok 5,000.00 3,750.00

28,950.00 28,950.00

TENAGA

0.0420 Hr Tukang Cat 120,000.00 5,040.00

0.0280 Hr Pekerja 95,000.00 2,660.00

0.0030 Hr Mandor 125,000.00 375.00

0.0028 Hr Kepala Tukang 120,000.00 336.00

8,411.00 8,411.00

PERALATA

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 37,361.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 3,736.10

HARGA SATUAN PEKERJAAN 1 BH DAUN JENDELA 41,097.10

42 1 m Mengecat Kozen, Daun Pintu/ Jendela dll 3x Sapu


2

BAHAN

0.200 Kg Cat manie 78,000.00 15,600.00

0.260 Kg cat Minyak 50,000.00 13,000.00

0.030 Kg Thenner 10,000.00 300.00

0.150 Kg Dempul 25,000.00 3,750.00

0.200 Lbr Amplas 5,000.00 1,000.00

33,650.00 33,650.00

TENAGA

0.009 Hr Tukang Cat 120,000.00 1,080.00

0.070 Hr Pekerja 95,000.00 6,650.00

0.006 Hr Mandor 125,000.00 750.00

0.003 Hr Kepala Tukang 120,000.00 360.00

1 m2 cat Mnegkilat 8,840.00 8,840.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 42,490.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 4,249.00

HARGA SATUAN PEKERJAAN 1 M2 46,739.00

43 1 m Pekerjaan Pemasangan Kaca


2

BAHAN

1.100 m2 Kaca 5 mm Ryben 275,000.00 302,500.00

302,500.00 302,500.00

TENAGA

0.150 Hr Tukang Kaca 120,000.00 18,000.00


0.015 Hr Pekerja 95,000.00 1,425.00

0.0008 Hr Mandor 125,000.00 100.00

0.015 Hr Kepala Tukang 120,000.00 1,800.00

21,325.00 21,325.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 323,825.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 32,382.50

HARGA SATUAN PEKERJAAN 1 M2 356,207.50


44 Pemasangan Kunci Tanam ( 2 x Putar / Slaag )

BAHAN

1.000 Psg Kunci Tanam 60,000.00 60,000.00

60,000.00 60,000.00

TENAGA

0.150 Hr Tukang 120,000.00 18,000.00

0.015 Hr Kepala Tukang 120,000.00 1,800.00

0.0008 Hr Mandor 125,000.00 100.00

0.015 Hr Pekerja 95,000.00 1,425.00

21,325.00 21,325.00

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 81,325.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 8,132.50

HARGA SATUAN PEKERJAAN 1 BH 89,457.50

45 Pemasangan Engsel Pintu 4" Sepasang

BAHAN

1.000 Psg Engsel Pintu 4" 151,700.00 151,700.00

151,700.00 151,700.00

TENAGA

0.300 Hr Tukang 120,000.00 36,000.00

0.030 Hr Kepala Tukang 120,000.00 3,600.00

0.002 Hr Mandor 125,000.00 200.00

0.030 Hr Pekerja 95,000.00 2,850.00

( PEMASANGAN 1 PASANG ENGSEL / 2 BH ENGSEL ) 42,650.00 42,650.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 194,350.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 19,435.00

HARGA SATUAN PEKERJAAN 1 PASANG 213,785.00

### Pemasangan Engsel Jendela 3"

BAHAN

1.000 Psg Engsel Jendela 3" 115,000.00 115,000.00

115,000.00 115,000.00

TENAGA

0.100 Hr Tukang 120,000.00 12,000.00

0.010 Hr Kepala Tukang 120,000.00 1,200.00

0.005 Hr Mandor 125,000.00 625.00

0.010 Hr Pekerja 95,000.00 950.00


( PEMASANGAN 1 PASANG ENGSEL / 2 BH ENGSEL ) 14,775.00 14,775.00

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 129,775.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 12,977.50

HARGA SATUAN PEKERJAAN 1 PASANG 142,752.50


47 Pemasangan Grendel Pintu 5"

BAHAN

1.000 Psg Grendel Pintu 5" 145,000.00 145,000.00

145,000.00 145,000.00

TENAGA

0.100 Hr Tukang 120,000.00 12,000.00

0.010 Hr Kepala Tukang 120,000.00 1,200.00

0.001 Hr Mandor 125,000.00 125.00

0.010 Hr Pekerja 95,000.00 950.00

14,275.00 14,275.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 159,275.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 15,927.50

HARGA SATUAN PEKERJAAN 1 PASANG 175,202.50

### Pemasangan Grendel Jendela 3"

BAHAN

1.000 Bh Grendel Jendela 3" 130,000.00 130,000.00

130,000.00 130,000.00

TENAGA

0.100 Hr Tukang 120,000.00 12,000.00

0.010 Hr Kepala Tukang 120,000.00 1,200.00

0.001 Hr Mandor 125,000.00 62.50

0.010 Hr Pekerja 95,000.00 950.00

14,212.50 14,212.50

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 144,212.50

JUMLAH OVER HEAD + PROFITE 15% D X 10% 14,421.25

HARGA SATUAN PEKERJAAN 1 PASANG 158,633.75


DAFTAR ANALISA

Harga Satuan Harga Upah Harga Bahan Jumlah Harga


No. Uraian Pekerjaan
( Rp ) ( Rp ) ( Rp ) ( Rp )

49 Pemasangan Hak Angin Sepasang

BAHAN

1.000 Psg Hak Angin. 120,000.00 120,000.00

120,000.00 120,000.00

TENAGA

0.100 Hr Tukang 120,000.00 12,000.00

0.010 Hr Kepala Tukang 120,000.00 1,200.00

0.0005 Hr Mandor 125,000.00 62.50

0.010 Hr Pekerja 95,000.00 950.00

14,212.50 - 14,212.50

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 134,212.50

JUMLAH OVER HEAD + PROFITE 15% D X 10% 13,421.25

HARGA SATUAN PEKERJAAN 1 PASANG 147,633.75

50 Pemasangan Handle Jendela

BAHAN

1.000 Psg Handle Jendela 225,000.00 225,000.00

225,000.00 225,000.00

TENAGA

0.100 Hr Tukang 120,000.00 12,000.00

0.010 Hr Kepala Tukang 120,000.00 1,200.00

0.001 Hr Mandor 125,000.00 125.00

0.010 Hr Pekerja 95,000.00 950.00

14,275.00 14,275.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 239,275.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 23,927.50

HARGA SATUAN PEKERJAAN 1 PASANG 263,202.50

51 Pemasangan Kloset Jongkok

BAHAN

1.000 Bh Kloset Jongkok Toto 456,000.00 456,000.00

0.120 Zak Semen 85,000.00 10,200.00

0.010 m3 Pasir Pasang 260,000.00 2,600.00

7.000 Bh Batu Bata 1,200.00 8,400.00

477,200.00 477,200.00
TENAGA

0.75000 Hr Tukang 120,000.00 90,000.00

0.075 Hr Kepala Tukang 120,000.00 9,000.00

0.001 Hr Mandor 125,000.00 125.00

0.150 Hr Pekerja 95,000.00 14,250.00

113,375.00 113,375.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 590,575.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 59,057.50

HARGA SATUAN PEKERJAAN 1 BUAH 649,632.50


52 Pemasangan Floor Drain

BAHAN

1.000 Bh Floor Drain 72,000.00 72,000.00

72,000.00 72,000.00

TENAGA

0.100 Hr Tukang 120,000.00 12,000.00

0.010 Hr Kepala Tukang 120,000.00 1,200.00

0.005 Hr Mandor 125,000.00 625.00

0.010 Hr Pekerja 95,000.00 950.00

14,775.00 14,775.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 86,775.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 8,677.50

HARGA SATUAN PEKERJAAN 1 BUAH 95,452.50

53 1 m Pemasangan Pipa PVC 4" AW


2

BAHAN

1.200 m1 Pipa PVC Aw 4" 22,500.00 27,000.00

1.000 Ls Perlengkapan 25 % dari Harga 5,625.00 5,625.00

32,625.00 32,625.00

TENAGA

0.135 Hr Tukang 120,000.00 16,200.00

0.0135 Hr Kepala Tukang 120,000.00 1,620.00

0.0041 Hr Mandor 125,000.00 512.50

0.081 Hr Pekerja 95,000.00 7,695.00

26,027.50 26,027.50

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 58,652.50

JUMLAH OVER HEAD + PROFITE 15% D X 10% 5,865.25

HARGA SATUAN PEKERJAAN 1 BUAH 64,517.75


54 1 M' Pemasangan Talang Pipa PVC 4" AW ( Tiap Meter Di Pasang Penggantung Plat 2 Buah )

BAHAN

1.100 m1 Pipa PVC Aw 4" 22,500.00 24,750.00

1.000 Ls Perlengkapan 25 % dari Harga 5,625.00 5,625.00

1.000 M' Plat Streep 30 x 2 mm 9,500.00 9,500.00

6.000 Bh Skrup Roofing Baja Ringan 1,500.00 9,000.00

39,875.00 39,875.00

TENAGA

0.135 Hr Tukang 120,000.00 16,200.00

0.0135 Hr Kepala Tukang 120,000.00 1,620.00

0.0041 Hr Mandor 125,000.00 512.50

0.010 Hr Pekerja 95,000.00 950.00

19,282.50 19,282.50

PERALATAN

- -

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 59,157.50

JUMLAH OVER HEAD + PROFITE 15% D X 10% 5,915.75

HARGA SATUAN PEKERJAAN 1 BUAH 65,073.25

55 Pemasangan 1 bak mandi Volume = 0.30 m 3

BAHAN

200.000 Bh batu Bata 1,200.00 240,000.00

2.400 Zak Semen 85,000.00 204,000.00

0.300 M3 Pasir Pasang 260,000.00 78,000.00

522,000.00 522,000.00

TENAGA

1.150 Hr Tukang 120,000.00 138,000.00

0.300 Hr Kepala Tukang 120,000.00 36,000.00

0.300 Hr Mandor 125,000.00 37,500.00

2.000 Hr Pekerja 95,000.00 190,000.00

401,500.00 401,500.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 923,500.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 92,350.00

HARGA SATUAN PEKERJAAN 1 BUAH 1,015,850.00


56 1 m' Pemasangan Pipa PVC AW 2 1/2"

BAHAN

1.200 m1 Pipa PVC Aw 2 1/2" 11,700.00 14,040.00

1.000 Ls Perlengkapan 25 % dari Harga 2,925.00 2,925.00

16,965.00 16,965.00

TENAGA

0.135 Hr Tukang 120,000.00 16,200.00

0.0135 Hr Kepala Tukang 120,000.00 1,620.00

0.0040 Hr Mandor 125,000.00 500.00

0.081 Hr Pekerja 95,000.00 7,695.00

26,015.00 26,015.00

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 42,980.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 4,298.00

HARGA SATUAN PEKERJAAN 1 M' 47,278.00

57 1 m Pemasangan Pipa PVC 1"


'

BAHAN

1.100 m1 Pipa PVC 1" 37,250.00 40,975.00

1.000 Ls Perlengkapan 25 % dari Harga 9,312.50 9,312.50

50,287.50 50,287.50

TENAGA

0.0600 Hr Tukang 120,000.00 7,200.00

0.0060 Hr Kepala Tukang 120,000.00 720.00

0.0002 Hr Mandor 125,000.00 25.00

0.0260 Hr Pekerja 95,000.00 2,470.00

10,415.00 10,415.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 60,702.50

JUMLAH OVER HEAD + PROFITE 15% D X 10% 6,070.25

HARGA SATUAN PEKERJAAN 1 M' 66,772.75


DAFTAR ANALISA

Harga Satuan Harga Upah Harga Bahan Jumlah Harga


No. Uraian Pekerjaan
( Rp ) ( Rp ) ( Rp ) ( Rp )

58 1 m' Pemasangan Pipa PVC 1/2"

BAHAN

1.100 m1 Pipa PVC 1/2" 3,250.00 3,575.00

1.000 Ls Perlengkapan 25 % dari Harga 812.50 812.50

4,387.50 4,387.50

TENAGA

0.0200 Hr Tukang 120,000.00 2,400.00

0.0060 Hr Kepala Tukang 120,000.00 720.00

0.0002 Hr Mandor 125,000.00 25.00

0.0360 Hr Pekerja 95,000.00 3,420.00

6,565.00 8,775.00 15,340.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 19,727.50

JUMLAH OVER HEAD + PROFITE 15% D X 10% 1,972.75

HARGA SATUAN PEKERJAAN 1 M' 21,700.25

58 1 m2 Pasangan Plafond Lumbersiring Kayu Meranti 1 x 9 cm

BAHAN

2.750 Lbr Limbersiring 300,000.00 825,000.00

0.150 Kg Paku 20,000.00 3,000.00

0.010 m2 rangka Plafond 2,900,000.00 29,000.00

857,000.00 857,000.00

TENAGA

1.250 Hr Tukang 120,000.00 150,000.00

0.180 Hr Kepala Tukang 120,000.00 21,600.00

0.600 Hr Pekerja 125,000.00 75,000.00

0.003 Hr Mandor 95,000.00 285.00

246,885.00 246,885.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 1,103,885.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 110,388.50

HARGA SATUAN PEKERJAAN 1 M' 1,214,273.50

59 1 m Pasangan Plafond PVC / Sunda Plafond 1 x 20 cm ( Motif Kayu )


2

BAHAN

1.150 Lbr Penutup Plafon Bahan PVC uk. 60,000.00 69,000.00

0.300 Btg Penutup List Samping PVC 15,400.00 4,620.00

0.150 Kg Skrup Plafon 5,000.00 750.00

1.000 Btg Rangka Plafond Metal Furing 2 40,000.00 40,000.00

114,370.00 114,370.00

TENAGA
0.125 oh Pekerja 95,000.00 11,875.00

0.250 oh Tukang 120,000.00 30,000.00

0.025 oh Kepala tukang 120,000.00 3,000.00

0.010 oh Mandor 125,000.00 1,250.00

46,125.00 46,125.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 160,495.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 16,049.50

HARGA SATUAN PEKERJAAN 1 M' 176,544.50


60 1 m2 Mengecat Plitur Kayu/ lumbersiring 2x Sapu Dengan Plytur Jadi

BAHAN

0.372 Kg Plitur 15,000.00 5,580.00

2.000 Lbr Kertas Gosok 5,000.00 10,000.00

15,580.00 15,580.00

TENAGA

0.060 Hr Tukang Cat 120,000.00 7,200.00

0.040 Hr Pekerja 125,000.00 5,000.00

0.003 Hr Mandor 95,000.00 285.00

0.016 Hr Kepala Tukang 120,000.00 1,920.00

14,405.00 14,405.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 29,985.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 2,998.50

HARGA SATUAN PEKERJAAN 1 M' 32,983.50

61 1 m Acian Tembok dengan semen Mortar Acian Putih ( Mortar Siap Pakai / MSP )
2

BAHAN

1.500 Kg Semen Mortar Accian Putih 1,750.00 2,625.00

2,625.00 2,625.00

TENAGA

0.010 Hr Tukang 120,000.00 1,200.00

0.200 Hr Pekerja 125,000.00 25,000.00

0.010 Hr Kepala Tukang 120,000.00 1,200.00

0.010 Hr Mandor 95,000.00 950.00

1 m Acian Tembok
2
28,350.00 28,350.00

PEARALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 30,975.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 3,097.50

HARGA SATUAN PEKERJAAN 1 M2 34,072.50

62 1 m Pasangan Rangka Dinding Pemisah Dari Kayu Klas III


2

BAHAN

0.0195 m3 Kayu Kals III Ukuran 5/10 3,990,000.00 77,805.00

0.250 Kg Paku 20,000.00 5,000.00

82,805.00 82,805.00

TENAGA

0.600 Hr Tukang 120,000.00 72,000.00

0.060 Hr Kepala Tukang 120,000.00 7,200.00


0.200 Hr Pekerja 95,000.00 19,000.00

0.010 Hr Mandor 125,000.00 1,250.00

99,450.00 99,450.00

PERALATA

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 182,255.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 18,225.50

HARGA SATUAN PEKERJAAN 1 M2 200,480.50


63 1 m2 Pasangan Plywood untuk Dinding Doble Muka Belakang/ Dua Sisi

BAHAN

0.7000 Lbr Plywood 72,000.00 50,400.00

0.075 Kg Paku 20,000.00 1,500.00

51,900.00 51,900.00

TENAGA

0.600 Hr Tukang 120,000.00 72,000.00

0.060 Hr Kepala Tukang 120,000.00 7,200.00

0.200 Hr Pekerja 95,000.00 19,000.00

0.010 Hr Mandor 125,000.00 1,250.00

99,450.00 99,450.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 151,350.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 15,135.00

HARGA SATUAN PEKERJAAN 1 M2 166,485.00

64 KUSEN, DAUN PINTU JENDELA BAHAN ALUMINIUM

BAHAN

1 m1 rangka Kusen Aluminium

1.100 m1 Aluminium Kusen 27,712.50 30,483.75

2.000 bh Angkur 500.00 1,000.00

31,483.75 31,483.75

TENAGA

0.004 Hr Mandor 125,000.00 500.00

0.040 Hr Kepala Tukang 120,000.00 4,800.00

0.350 Hr Tukang 120,000.00 42,000.00

0.200 Hr Pekerja 95,000.00 19,000.00

66,300.00 66,300.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 97,783.75

JUMLAH OVER HEAD + PROFITE 15% D X 10% 9,778.38

HARGA SATUAN PEKERJAAN 1 M' 107,562.13


1 Unit Pintu Aluminium Spandril Untuk Toilet

1.512 m2 Aluminium Kusen 25,000.00 37,800.00

2.000 bh Angkur 500.00 1,000.00

38,800.00 38,800.00

TENAGA

0.004 Hr Mandor 125,000.00 500.00

0.040 Hr Kepala Tukang 120,000.00 4,800.00

0.350 Hr Tukang 120,000.00 42,000.00

0.150 Hr Pekerja 95,000.00 14,250.00

61,550.00 61,550.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 100,350.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 10,035.00

HARGA SATUAN PEKERJAAN 1 M' 110,385.00

### 1 m Pasangan Papan untuk Dinding Ukuran Papan 1.5 x 18 cm Dengan Ketam Manual
2

BAHAN

0.022 m3 kayu Kelas III 3,990,000.00 87,780.00

0.100 Kg Paku 15,000.00 1,500.00

89,280.00 89,280.00

TENAGA

1.800 Hr Tukang 120,000.00 216,000.00

0.180 Hr Kepala Tukang 120,000.00 21,600.00

0.600 Hr Pekerja 95,000.00 57,000.00

0.030 Hr Mandor 125,000.00 3,750.00

298,350.00 298,350.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 387,630.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 38,763.00

HARGA SATUAN PEKERJAAN 1 M' 426,393.00


### 1 m2 Mengerjakan Rangka Partisi Rangka Kuda - kuda Baja Ringan

BAHAN

4.0000 m' Rangka Kuda Kuda Baja 31,742.00 126,968.00

1.5000 m' Rangka Reng Kuda Kuda Baja 5,000.00 7,500.00

12.0000 Bh Skrup 1,500.00 18,000.00

152,468.00 152,468.00

TENAGA

0.2000 Hr Tukang 120,000.00 24,000.00

0.0200 Hr Pekerja 95,000.00 1,900.00

0.0100 Hr mandor 125,000.00 1,250.00

0.0200 Hr Kepala Tukang 120,000.00 2,400.00

29,550.00 29,550.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 182,018.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 18,201.80

HARGA SATUAN PEKERJAAN 1 M2 200,219.80

### 1 M2 RANGKA PLAFOND DAN PENUTUP GIFSUM 9 MM

BAHAN

0.250 Btg Hollow 4/4 Zincromate 50,000.00 12,500.00

2.000 Btg Hollow 2/4 Zincromate 40,000.00 80,000.00

0.364 Lbr Gifsum 9mm 47,000.00 17,108.00

0.750 Kg Compound 50,000.00 37,500.00

0.072 Roll Cotton plaster 8,500.00 612.00

0.110 kg Skrup 3/4" 5,000.00 550.00

148,270.00 148,270.00

TENAGA

0.150 Hr Tukang 120,000.00 18,000.00

0.013 Hr Kepala Tukang 120,000.00 1,560.00

0.015 Hr Pekerja 95,000.00 1,425.00

0.002 Hr Mandor 125,000.00 250.00

21,235.00 21,235.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 169,505.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 16,950.50

HARGA SATUAN PEKERJAAN 1 M2 186,455.50


### 1 M2 PASANG PENUTUP PARTISI GIFSUM 9 MM SELAPIS

BAHAN

0.364 Lbr Gifsum 9mm 47,000.00 17,108.00

0.550 Kg Compound 50,000.00 27,500.00

0.072 Roll Cotton plaster 8,500.00 612.00

0.110 kg Skrup 3/4" 5,000.00 550.00

45,770.00 45,770.00

TENAGA

0.050 Hr Tukang 120,000.00 6,000.00

0.005 Hr Kepala Tukang 120,000.00 600.00

0.100 Hr Pekerja 95,000.00 9,500.00

0.005 Hr Mandor 125,000.00 625.00

16,725.00 16,725.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 62,495.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 6,249.50

HARGA SATUAN PEKERJAAN 1 M2 68,744.50

### 1 M2 PASANG PENUTUP PARTISI PAPAN GRC CALCYBOARD 5 MM SELAPIS

BAHAN

0.364 Lbr Papan GRC Calcyoard 5 mm 51,000.00 18,564.00

0.750 Kg Compound 50,000.00 37,500.00

0.072 Roll Cotton plaster 8,500.00 612.00

0.110 kg Skrup 3/4" 5,000.00 550.00

57,226.00 57,226.00

TENAGA

0.050 Hr Tukang 120,000.00 6,000.00

0.005 Hr Kepala Tukang 120,000.00 600.00

0.100 Hr Pekerja 95,000.00 9,500.00

0.005 Hr Mandor 125,000.00 625.00

16,725.00 16,725.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 73,951.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 7,395.10

HARGA SATUAN PEKERJAAN 1 M2 81,346.10


70 1 m' Pemasangan Pipa PVC 4 Klas C"

BAHAN

1.200 m1 Pipa PVC Aw 4" 33,000.00 39,600.00

1.000 Ls Perlengkapan 25 % dari Harga 8,250.00 8,250.00

47,850.00 47,850.00

TENAGA

0.125 Hr Tukang 120,000.00 15,000.00

0.0035 Hr Kepala Tukang 120,000.00 420.00

0.0041 Hr Mandor 125,000.00 512.50

0.081 Hr Pekerja 95,000.00 7,695.00

23,627.50 95,700.00 119,327.50

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 167,177.50

JUMLAH OVER HEAD + PROFITE 15% D X 10% 16,717.75

HARGA SATUAN PEKERJAAN 1 M2 183,895.25

### 1 m Mengerjakan Tralis Jendela Dari Besi Nako 12 mm


2

BAHAN

23.0000 m' Besi Nako / Besi Kotak 12 mm 12,000.00 276,000.00

4.4000 m' Plat Streep 30 x 2 mm 9,500.00 41,800.00

0.0250 Kg Skrup 5,000.00 125.00

0.5000 Kg Kawat las 30,500.00 15,250.00

0.1750 Kg Cat Meni 78,000.00 13,650.00

0.2000 Kg Cat Bei 50,000.00 10,000.00

0.7500 Jam Mesin Las 50,000.00 37,500.00

1.0000 Jam Alat bantu 10,000.00 10,000.00

404,325.00 404,325.00

TENAGA

0.5000 Hr Tukang 120,000.00 60,000.00

0.1500 Hr Pekerja 95,000.00 14,250.00

0.0250 Hr mandor 125,000.00 3,125.00

0.0030 Hr Kepala Tukang 120,000.00 360.00

77,735.00 77,735.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 482,060.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 48,206.00

HARGA SATUAN PEKERJAAN 1 M2 530,266.00


DAFTAR ANALISA

Harga Satuan Harga Upah Harga Bahan Jumlah Harga


No. Uraian Pekerjaan
( Rp ) ( Rp ) ( Rp ) ( Rp )

### 1 M' Pekerjaan Galian Dan Perbaikan Saluran Di Jalal Gang Depan Rumah Dinas

BAHAN

0.240 m3 Galian Tanah Untuk Pendalam 67,250.00 16,140

0.090 m3 Pek. Beton Dinding, Dan Lantai 1,185,327.64 106,679

0.750 m2 Pek. Plesterann Dinding Salu 80,691.80 60,519

0.750 m2 Pek. Acian Plesteran Dinding S 28,350.00 21,263

- - 204,601

TENAGA

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 21,262.50

JUMLAH OVER HEAD + PROFITE 15% D X 15% 3,189.38

HARGA SATUAN PEKERJAAN 1 M' 24,451.88

### 1 m2 Acian Tembok dengan semen PC

BAHAN

1.500 Kg Semen PC 1,100.00 1,650.00

1,650.00 1,650.00

TENAGA

0.200 Hr Tukang 120,000.00 24,000.00

0.050 Hr Pekerja 95,000.00 4,750.00

0.030 Hr Kepala Tukang 120,000.00 3,600.00

0.003 Hr Mandor 125,000.00 375.00

1 m Acian Tembok
2
32,725.00 32,725.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 34,375.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 3,437.50

HARGA SATUAN PEKERJAAN 1 M' 37,812.50


### 1 Unit Pembuatan Septiktank Dan Peresapan Dari Gorong Gorong Beton D 100 cm Panjang 50 cm Tebal 8 cm

BAHAN

18.840 M3 Cgalian Tanah 67,250.00 1,266,990

0.250 M3 Urugan Pasir samping Gorong 26,975.00 6,744

12.000 Bh Gorong Gorong Beton D 100 x 5 365,000.00 4,380,000

0.250 M3 Urugann Batu Pecah 5/7 cm 385,714.00 96,429

10.000 M' Pasangan Pipa Pvc Aw 4" 119,327.50 1,193,275

5.000 M'' Pasangan Pipa Pvc Aw 2 1/2" 26,015.00 130,075

4.000 M2 Plesteran Adukan Untuk Samb 50,175.00 200,700

0.650 M3 Beton Untuk Tutup Tebal 12 c 146,485.00 95,215

27.900 Kg Besi Beton 17,681.50 493,314

4.000 Bh Sambungan Pipa Pvc Dup Ulir 40,000.00 160,000

8,022,741 8,022,741

TENAGA

1.000 Hr Tukang 120,000.00 120,000.00

2.000 Hr Pekerja 95,000.00 190,000.00

0.050 Hr Kepala Tukang 120,000.00 6,000.00

0.005 Hr Mandor 125,000.00 625.00

316,625.00 316,625.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 8,339,366.35

JUMLAH OVER HEAD + PROFITE 15% D X 10% 833,936.64

HARGA SATUAN PEKERJAAN 1 UNIT 9,173,302.99


### 1 Unit Pembuatan Pondasi Profil Tank Dari Kayu Ulin Untuk 2 Profil Tank Kap 2 x 1125 Ltr

BAHAN

12.000 Btg Kayu Ulin Balok 10 x 10 x 400 200,000.00 2,400,000

13.000 Btg Kayu Ulin Balok 5 x 10 x 400 225,000.00 2,925,000

3.500 Kg Paku Ulin 20,000.00 70,000

0.200 M3 Papan Kayu Klas III 3,990,000.00 798,000

3.000 Kg Baut Dan Mur Dia. 1/2" 10,000.00 30,000

0.750 M3 Galian Tanah 67,250.00 50,438

0.750 M3 Baton K 175 146,485.00 109,864

6,383,301 6,383,301

TENAGA

2.000 Hr Tukang 120,000.00 240,000.00

3.000 Hr Pekerja 95,000.00 285,000.00

0.300 Hr Kepala Tukang 120,000.00 36,000.00

0.030 Hr Mandor 125,000.00 3,750.00

564,750.00 564,750.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 6,948,051.25

JUMLAH OVER HEAD + PROFITE 15% D X 10% 694,805.13

HARGA SATUAN PEKERJAAN 1 UNIT 7,642,856.38

### 1 Bh Memasang Kran Cucian Piring D 1/2"

BAHAN

1.0000 bh Kran Cucian Piring D 1/2" Log 55,000.00 55,000.00

Jumlah 55,000.00 55,000.00

TENAGA

0.0500 org Tukang batu 120,000.00 6,000.00

0.0100 org Kepala tukang batu 120,000.00 1,200.00

0.0100 org Pekerja 95,000.00 950.00

0.0050 org Mandor 125,000.00 625.00

8,775.00 8,775.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 63,775.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 6,377.50

HARGA SATUAN PEKERJAAN 1 BH 70,152.50


### 1 Bh Memasang Kran Air Biasa D 1/2"

BAHAN

1.0000 bh Kran Air Biasa D 1/2" Logam 47,500.00 47,500.00

Jumlah 47,500.00 47,500.00

TENAGA

0.0500 org Tukang batu 120,000.00 6,000.00

0.0100 org Kepala tukang batu 120,000.00 1,200.00

0.0100 org Pekerja 95,000.00 950.00

0.0050 org Mandor 125,000.00 625.00

8,775.00 8,775.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 56,275.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 5,627.50

HARGA SATUAN PEKERJAAN 1 BH 61,902.50

### 1 Bh Memasang Kran Air Doble Shower D 1/2" Steinless

BAHAN

1.0000 bh Kran Air Doble Shower D 1/2" S 85,000.00 85,000.00

Jumlah 85,000.00 85,000.00

TENAGA

0.0500 org Tukang batu 120,000.00 6,000.00

0.0100 org Kepala tukang batu 120,000.00 1,200.00

0.0100 org Pekerja 95,000.00 950.00

0.0050 org Mandor 125,000.00 625.00

8,775.00 8,775.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 93,775.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 9,377.50

HARGA SATUAN PEKERJAAN 1 BH 103,152.50


### 1 Bh Memasang Stop Kran Tee Stainless Untuk Kloset Duduk

BAHAN

1.0000 bh Stop Kran Tee Stainless Untuk 35,000.00 35,000.00

Jumlah 35,000.00 35,000.00

TENAGA

0.0500 org Tukang batu 120,000.00 6,000.00

0.0100 org Kepala tukang batu 120,000.00 1,200.00

0.0100 org Pekerja 95,000.00 950.00

0.0050 org Mandor 125,000.00 625.00

8,775.00 8,775.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 43,775.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 4,377.50

HARGA SATUAN PEKERJAAN 1 BH 48,152.50

### 1 Bh Memasang Kran Air Jet Shower D 1/2"

BAHAN

1.0000 bh Kran Air Jet Shower D 1/2" 87,000.00 87,000.00

87,000.00 87,000.00

TENAGA

0.0500 org Tukang batu 120,000.00 6,000.00

0.0100 org Kepala tukang batu 120,000.00 1,200.00

0.0100 org Pekerja 95,000.00 950.00

0.0050 org Mandor 125,000.00 625.00

8,775.00 8,775.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 95,775.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 9,577.50

HARGA SATUAN PEKERJAAN 1 BH 105,352.50


### 1 Bh Memasang Gantungan Baju Di Pintu Toiet Stainless

BAHAN

1.0000 bh Gantungan Baju Di Pintu Toiet 125,000.00 125,000.00

Jumlah 125,000.00 125,000.00

TENAGA

0.0500 org Tukang batu 120,000.00 6,000.00

0.0100 org Kepala tukang batu 120,000.00 1,200.00

0.0100 org Pekerja 95,000.00 950.00

0.0050 org Mandor 125,000.00 625.00

8,775.00 8,775.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 133,775.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 13,377.50

HARGA SATUAN PEKERJAAN 1 BH 147,152.50

### 1 Unit Memasang Kloset Duduk Toto CW 420/421

BAHAN

1.0000 bh Kloset Duduk Standar Type T 1,350,000.00 1,350,000.00

Jumlah 1,350,000.00 1,350,000.00

TENAGA

0.5000 org Tukang batu 120,000.00 60,000.00

0.0100 org Kepala tukang batu 120,000.00 1,200.00

0.2500 org Pekerja 95,000.00 23,750.00

0.0050 org Mandor 125,000.00 625.00

85,575.00 85,575.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 1,435,575.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 143,557.50

HARGA SATUAN PEKERJAAN 1 BH 1,579,132.50


ANALISAA PEKERJAAN PEMBONGKARAN

### 1 M2 PEKERJAAN PEMBONGKARAN ATAP, PLAFOND, DAN RANGKA KUDA KUDA ( DI KUMPUL & DI BERSIHKAN ) ( Di Hitung Rata Sesuai Luasan Ba

A BAHAN

Jumlah - -

B TENAGA

0.0200 org Tukang batu 120,000.00 2,400.00

0.1500 org Pekerja 95,000.00 14,250.00

0.0020 org Mandor 125,000.00 250.00

16,900.00 16,900.00

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 16,900.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 1,690.00

HARGA SATUAN PEKERJAAN 1 M2 18,590.00

1 M2 PEKERJAAN PEMBONGKARAN, MENGUPAS KERAMIK DINDING DAN LANTAI


###
( DI KUMPUL & DI BERSIHKAN ) ( Di Hitung Sesuai Luasan Keramik Yang Di Bongkar )

A BAHAN

Jumlah - -

B TENAGA

0.0100 org Tukang batu 120,000.00 1,200.00

0.2500 org Pekerja 95,000.00 23,750.00

0.0010 org Mandor 125,000.00 125.00

25,075.00 25,075.00

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 25,075.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 2,507.50

HARGA SATUAN PEKERJAAN 1 M2 27,582.50

### 1 M2 PEKERJAAN MENGUPAS DAN MEMBERSIHKAN LUMUT DAN KERAK PADA DINDING PAGAR DAN DI CUCI

A BAHAN

Jumlah - -

B TENAGA

0.1000 org Pekerja 95,000.00 9,500.00

0.0030 org Mandor 125,000.00 375.00

9,875.00 9,875.00
C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 9,875.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 987.50

HARGA SATUAN PEKERJAAN 1 M2 10,862.50


### 1 M2 PEKERJAAN MEMBONGKAR DAN MEMASANG KEMBALI PAVING BLOK HALAMAN

A BAHAN

Jumlah - -

B TENAGA

0.1500 org Tukang batu 120,000.00 18,000.00

0.2500 org Pekerja 95,000.00 23,750.00

0.0200 org Mandor 125,000.00 2,500.00

44,250.00 44,250.00

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 44,250.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 4,425.00

HARGA SATUAN PEKERJAAN 1 M2 48,675.00

### 1 M' PEKERJAAN MENGGALI DAN MEMBONGKAR PONDASI BATU GUNUNG DAN PASANG KEMBALI

A BAHAN

Jumlah - -

B TENAGA

0.0500 org Tukang batu 120,000.00 6,000.00

0.2500 org Pekerja 95,000.00 23,750.00

0.0200 org Mandor 125,000.00 2,500.00

32,250.00 32,250.00

C PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 32,250.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 3,225.00

HARGA SATUAN PEKERJAAN 1 BH 35,475.00


86 1 m2 Mengecat Ulang Tralis Besi Pagar Terpasang

BAHAN

0.125 Kg cat Minyak 50,000.00 6,250.00

0.080 Kg Thenner 10,000.00 800.00

0.150 Lbr Amplas 5,000.00 750.00

0.125 Ltr Remove Paint 25,000.00 3,125.00

10,925.00 10,925.00

TENAGA

0.025 Hr Tukang Cat 120,000.00 3,000.00

0.012 Hr Pekerja 95,000.00 1,140.00

0.001 Hr Mandor 125,000.00 125.00

0.001 Hr Kepala Tukang - -

1 m2 cat Mnegkilat 4,265.00 4,265.00

PERALATAN

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 15,190.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 1,519.00

HARGA SATUAN PEKERJAAN 1 M2 16,709.00

### 1 M2 Pekerjaan Pemasangan Tralis Pagar

BAHAN

2.000 m' Pipa Galvanised 1 1/2" 53,250.00 106,500.00

9.468 Kg Besi Beton D 16 mm 15,000.00 142,020.00

2.000 bh Dyna Bolt 10' 1,500.00 3,000.00

2.144 Kg Plat Besi 2 mm 20,000.00 42,875.00

0.500 Kg Kawat Las 30,500.00 15,250.00

0.225 ltr Meni besi 78,000.00 17,550.00

0.400 ltr Cat besi 50,000.00 20,000.00

347,195.00 347,195.00

TENAGA

0.250 oh Pekerja 95,000.00 23,750.00

0.750 oh Tukang 120,000.00 90,000.00

0.020 oh Kepala Tukang 120,000.00 2,400.00

0.001 oh Mandor 125,000.00 125.00

116,275.00 116,275.00

PERALATAN

1.000 Jam Mesin Las 50,000.00 50,000.00

1.000 Ls Alat Bantu 10,000.00 10,000.00

60,000.00 60,000.00

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 523,470.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 52,347.00

HARGA SATUAN PEKERJAAN 1 M2 575,817.00


### 1 M2 Pekerjaan Pembuatan Dan Pemasangan Tralis Pagar Dari Besi Hollow

BAHAN

4.000 M' Pipa Hollow 4 x 4 cm 39,000.00 156,000.00

10.000 M' Pipa Hollow 1.5 x 3 cm 30,166.67 301,666.67

2.000 bh Dyna Bolt 10' 1,500.00 3,000.00

2.144 Kg Plat Besi 2 mm 20,000.00 42,875.00

0.500 Kg Kawat Las 30,500.00 15,250.00

0.150 Kg Dempul Plastik Untuk Cat 25,000.00 3,750.00

0.225 ltr Meni besi 78,000.00 17,550.00

0.400 ltr Cat besi 50,000.00 20,000.00

560,091.67 560,091.67

TENAGA

0.150 oh Pekerja 95,000.00 14,250.00

0.250 oh Tukang 120,000.00 30,000.00

0.010 oh Kepala Tukang 120,000.00 1,200.00

0.001 oh Mandor 125,000.00 125.00

45,575.00 45,575.00

PERALATAN

1.000 Jam Mesin Las 50,000.00 50,000.00

1.000 Ls Alat Bantu - -

50,000.00 50,000.00

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 655,666.67

JUMLAH OVER HEAD + PROFITE 15% D X 10% 65,566.67

HARGA SATUAN PEKERJAAN 1 M2 721,233.33

### 1 TITIK PEMASANGAN INSTALASI LAMPU PENERANGAN / STOP KONTAK DAYA

BAHAN

3.000 Btg Pipa Listrik Pvc 5/8" 21,000.00 63,000.00

10.000 M' Kabel NYM 2 x 2.5 mm 11,200.00 112,000.00

2.000 bh Tee Dos Pvc 7,500.00 15,000.00

4.000 bh L Bow Pvc 5/8" 21,000.00 84,000.00

1.000 bh Imbowdose Pvc 2,000.00 2,000.00

10.000 bh Cla Pipa Pvc/ Kabel Tis 5,000.00 50,000.00

326,000.00 326,000.00

TENAGA

0.150 oh Pekerja 95,000.00 14,250.00

0.150 oh Tukang Listrik 120,000.00 18,000.00

0.015 oh Mandor Listrik 125,000.00 1,875.00

34,125.00 34,125.00

PERALATAN

1.000 Ls Alat Bantu - -


- -

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 360,125.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 36,012.50

HARGA SATUAN PEKERJAAN 1 TITIK 396,137.50


### 1 TITIK PEMASANGAN INSTALASI STOP KONTAK DAYA UNTUK AC 16 A

BAHAN

5.000 Btg Pipa Listrik Pvc 5/8" 21,000.00 105,000.00

15.000 M' Kabel NYM 3 x 4 mm 32,000.00 480,000.00

2.000 bh Tee Dos Pvc 7,500.00 15,000.00

4.000 bh L Bow Pvc 5/8" 21,000.00 84,000.00

1.000 bh Imboodoss Tembok Pvc Panaso 2,500.00 2,500.00

10.000 bh Clam Pipa Pvc/ Kabel Tis 5,000.00 50,000.00

736,500.00 736,500.00

TENAGA

0.150 oh Pekerja 95,000.00 14,250.00

0.150 oh Tukang Listrik 120,000.00 18,000.00

0.015 oh Mandor Listrik 125,000.00 1,875.00

34,125.00 34,125.00

PERALATAN

1.000 Ls Alat Bantu - -

- -

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 770,625.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 77,062.50

HARGA SATUAN PEKERJAAN 1 TITIK 847,687.50


### 1 UNIT PEMASANGAN BOX MCB LENGKAP DAN DAN INSTALASI KABEL GROUP

BAHAN

6.000 Btg Pipa Listrik Pvc 5/8" 21,000.00 126,000.00

1.250 M' Kabel Tanduk NYM 3 x 6 mm 29,000.00 36,250.00

15.000 M' Kabel NYM 2 x 2.5 mm 11,200.00 168,000.00

2.000 bh Tee Dos Pvc 7,500.00 15,000.00

4.000 bh L Bow Pvc 5/8" 21,000.00 84,000.00

1.000 bh Box MCB Plastik Di Tanam Tem 1,500,000.00 1,500,000.00

10.000 bh Clam Pipa Pvc/ Kabel Tis 5,000.00 50,000.00

6.000 Bh MCB 6 Amp. 127,500.00 765,000.00

2,744,250.00 2,744,250.00

TENAGA

0.500 oh Pekerja 95,000.00 47,500.00

0.250 oh Tukang Listrik 120,000.00 30,000.00

0.025 oh Mandor Listrik 125,000.00 3,125.00

80,625.00 80,625.00

PERALATAN

1.000 Ls Alat Bantu - -

- -

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 2,824,875.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 282,487.50

HARGA SATUAN PEKERJAAN 1 UNIT 3,107,362.50

### 1 TITIK PEMASANGAN INSTALASI KABEL ANTENA TV

BAHAN

5.000 Btg Pipa Listrik Pvc 5/8" 21,000.00 105,000.00

15.000 M' Kabel TV Coaxial 2,500.00 37,500.00

2.000 bh Tee Dos Pvc 7,500.00 15,000.00

4.000 bh L Bow Pvc 5/8" 21,000.00 84,000.00

1.000 bh Imboodoss Tembok Pvc Panason 2,000.00 2,000.00

10.000 bh Clam Pipa Pvc/ Kabel Tis 5,000.00 50,000.00

293,500.00 293,500.00

TENAGA

0.250 oh Pekerja 95,000.00 23,750.00

0.150 oh Tukang Listrik 120,000.00 18,000.00

0.015 oh Mandor Listrik 125,000.00 1,875.00

43,625.00 43,625.00

PERALATAN

1.000 Ls Alat Bantu - -

- -

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 337,125.00


JUMLAH OVER HEAD + PROFITE 15% D X 10% 33,712.50

HARGA SATUAN PEKERJAAN 1 TITIK 370,837.50


### 1 UNIT PEMASANGAN EXHAUSFAN D 30 CM

BAHAN

0.500 Btg Pipa Listrik Pvc 5/8" 21,000.00 10,500.00

2.500 M' Kabel NYM 2 x 2.5 mm 11,200.00 28,000.00

2.000 bh L Bow Pvc 5/8" 21,000.00 42,000.00

1.000 bh Exchaust Fan D 30 cm + Acc 335,000.00 335,000.00

1.000 bh Clam Pipa Pvc/ Kabel Tis 5,000.00 5,000.00

420,500.00 420,500.00

TENAGA

0.250 oh Pekerja 95,000.00 23,750.00

0.150 oh Tukang Listrik 120,000.00 18,000.00

0.015 oh Mandor Listrik 125,000.00 1,875.00

43,625.00 43,625.00

PERALATAN

1.000 Ls Alat Bantu - -

- -

D JUMLAH BAHAN, TENAGA, DAN PERALATAN D = ( A + B + C ) 464,125.00

JUMLAH OVER HEAD + PROFITE 15% D X 10% 46,412.50

HARGA SATUAN PEKERJAAN 1 TITIK 510,537.50


DAFTAR HARGA BAHAN DAN UPAH

PEKERJAAN : PEMBANGUNAN GEDUNG OLAHRAGA IPDN JAKARTA


LOKASI : Jl. Ampera Raya No.1, RT.1/RW.6, Cilandak Tim., Kec. Ps. Minggu, Kota Jakarta Selatan
: Daerah Khusus Ibukota Jakarta 12561
TAHUN ANGGARAN : 2021

No. Bahan - Bahan Harga ( Rp ) Satuan

1 Pasir Timbunan 200,000.00 m3


2 Tanah Timbunan 120,000.00 m3
3 Pasir Pasangan 260,000.00 m3
4 Batu Gunung 285,714.00 m3
5 Batu Pecah 385,714.00 m3
6 Batu Sungai 385,714.00 m3
7 Bata 1,200.00 Bh
8 Bata Holllow 10 x 18 x 36 cm 20,000.00 Bh
9 Semen @ 50 kg 85,000.00 Zak
10 Semen PC 1 Kg 1,100.00 Kg
11 Semen Warna / Semen Putih @ 40 kg 94,000.00 Zak
12 Semen Warna / Semen Putih @ 40 kg 2,350.00 Kg
13 Besi Tulangan Beton Polos 15,000.00 Kg
14 Besi Tulangan Beton Ulir / Deformand 15,000.00 Kg
15 Kawat Beton 22,000.00 Kg
16 Paku Besi Ukuran 20,000.00 Kg
17 Paku Seng 25,000.00 Kg
18 Paku Ulin Ukuran 30,000.00 Kg
19 Besi Beugel dia. 1/2" 10,000.00 Kg
20 Mur Baut 59,800.00 Kg
21 Besi Klam U 15,000.00 Kg
22 Besi Plat/ Besi Profil 20,000.00 Kg
23 Kaca Bening 3 mm 80,000.00 m2
24 Kaca Bening 5 mm 275,000.00 m2
25 Kaca Riben 3 mm 65,000.00 m2
26 Kaca Riben 5 mm 62,500.00 m2
27 Genteng Metal Sakura Roof 61,000.00 Bh
28 Nok Genteng Sakura Roof 39,500.00 Bh
29 Nok Genteng Multi Roof 39,500.00 Bh
30 Skrup Atap Metal 1 1/4" 43,333.29 Kg
31 Atap Seng Colour Asoka 80 x 180 cm 48,000.00 Lbr
32 Rangka Kuda Kuda Baja 31,742.00 M'
33 Rangka Reng Kuda Kuda Baja Ringan 3/4 Taso 5,000.00 M'
34 Paku Skrup Baja Ringan 1,500.00 Bh
35 Skrup Atap Metal Zincalium D 2" Dan Karet 1,000.00 Bh
36 Baut Skrup Dynabolt 1,500.00 Bh
37 Papan GRC Calcyoard 5 mm 51,000.00 Lbr
38 Plywood 9 mm 72,000.00 Lbr
39 Plywood 3 mm 43,000.00 Lbr
40 Plywood 4 mm 54,000.00 Lbr
41 Seng Plat Bjls 30 48,000.00 m1
42 Seng Gelombang Bjls 30 60,000.00 Lbr
43 Tegel Keramik 25 x 40 5,200.00 Bh
44 Tegel Keramik 25 x 25 1,593.75 Bh
45 Tegel Keramik 40x40 10,833.33 Bh
46 Keramik Granit / Homogeneus Tile 60 x 60 cm Polished 45,250.00 Bh
47 Keramik Granit / Homogeneus Tile 60 x 60 cm Un Polished 45,250.00 Bh
No. Bahan - Bahan Harga ( Rp ) Satuan
48 Tegel plint 10 x 25 cm Bh
49 Batu Alam Andesit 20 x 40 / Batu Bilah 110,000.00 m2
50 Pipa Baja Gip 1.5 53,250.00 m1
51 Pipa Baja Gip 3.0 78,333.33 m1
52 Pipa Hollow 50 x 50 tebal 1 mm 39,000.00 m1
53 Pipa Hollow 15 x 30 tebal 1 mm 30,166.67 m1
54 Pipa Hollow 40 x 40 tebal 1 mm 51,333.33 m1
55 Kunci Tanam 2 Slaag 60,000.00 Psg
56 Engsel Pintu Steinlist / RRT 4" 151,700.00 Psg
57 Grendel Pintu 4" 140,000.00 Bh
58 Grendel Pintu 6" 145,000.00 Bh
59 Grendel Jendela 3" 130,000.00 Bh
60 Hak Angin 120,000.00 Psg
61 Handle Jendela 225,000.00 Bh
62 Handle Jendela 125,000.00 Bh
63 Engsel Jendela Steinlist / RRT 3" 115,000.00 Psg
64 Kayu Ulin 13,000,000.00 M3
65 Kayu Ulin Balok 5 x 10 x 400 cm 225,000.00 Btg
66 Kayu Ulin Balok 10 x 10 x 400 cm 200,000.00 Btg
67 Kayu Meranti Balok 3,990,000.00 m3
68 Kayu Bengkirai Balok 4,990,000.00 m3
69 Kayu Bengkirai Balok Ukuran 6/15 cm Panjang 400 cm 251,388.89 Btg
70 Kayu Bengkirai Balok Ukuran 4/15 cm Panjang 400 cm 100,000.00 Btg
71 Kayu Bengkirai Balok Ukuran 4/12 cm Panjang 400 cm 135,000.00 Btg
72 Kayu Papan Klas III 5 x 25 cm 115,000.00 Btg
73 Kayu Perancah/ Bouwplank 2,900,000.00 m3
74 Lis Kayu 3 x 3 Panjang 4 m' 20,000.00 Btg
75 Lis Kayu 2 x 10 cm Panjang 4 m' 15,000.00 Btg
76 Kayu Ulin 10 / 10 - 4m' 250,000.00 Btg
77 Kayu laut Merah Unttuk Pancang D 10 - 12 cm Panjaang 3.5 m' 280,000.00 Btg
78 Dolken kayu Galam 8/10 30,000.00 Btg
79 Cat kayu Dan Besi 50,000.00 Kg
80 Cat Atap 40,500.00 Kg
81 Dempul Cat Kayu 25,000.00 Kg
82 Cat Tembok Untuk Plafond 75,000.00 Kg
83 Cat Menie 78,000.00 Kg
84 Cat Tembok Dalam 90,000.00 Kg
85 Cat Tembok Luar Standart 85,000.00 Kg
86 Cat Teembok Watershield 45,000.00 Kg
87 Cat Dasar Untuk Tembok/ Wall Sealler 75,000.00 Kg
88 Acian Mortar Putih Untuk Plamur Tembok 1,750.00 Kg
89 Kertas Gosok 5,000.00 Lbr
90 Remove Paint ( Cairan Peluntur Cat ) 25,000.00 Ltr
91 Thenner 10,000.00 Ltr
No.Bahan - Bahan Harga ( Rp ) Satuan
92 Kabel NYM 2 x 2.5 mm 11,200.00 M'
93 Kabel NYM 3 x 2.5 mm 46,520.00 M'
94 Kabel NYM 3 x 4 mm 32,000.00 M'
95 Kabel NYM 3 x 6 mm 29,000.00 M'
96 Kabel NYA 2.5 mm 7,450.00 M'
97 Kabel Coaxial Untuk Antena TV 2,500.00 M'
98 Imboodoss Tembok Pvc Panasonic untuk Stop Kontak/ Saklar 2,000.00 Bh
99 Imboodoss Tembok Pvc Panasonic untuk Stop Kontak AC 2,500.00 Bh
100 Tee Dus Pvc Putih Setara Clysap 7,500.00 Bh
101 Pipa Listrik Pvc 5/8" Setara Clysal 21,000.00 Btg
102 Clam Pipa Pvc 5/8" atau kabel tiis 5,000.00 Bh
103 L Bow Pvc 5/8" Setara Clypsal 21,000.00 Bh
104 Box MCB Plastik Di Tanam Tembok Untuk Isi 6 Group 1,107,000.00 Bh
105 MCB 6 Amp. 127,500.00 BH
106 Lampu TL 20 Watt ( Type bambu ) 278,750.00 Bh
107 Lampu Downlight / DL 13 Wat LED 190,000.00 Bh
108 Lampu SL 14 Watt 246,900.00 Bh
109 Stop Kontak Putih 15,000.00 Bh
110 Saklar Tunggal Putih 120,000.00 Bh
111 Saklar Ganda Putih 225,000.00 Bh
112 Pasangan Instalasi Titik Cahaya lampu / Stop Kontak Daya 350,000.00 Ttk
113 Pek. Instalasi Stop Kontak AC 250,000.00 Ttk
114 Pek. Instalasi Antena TV 235,000.00 Ttk
115 Pek. Pasang Box Sekring 6 Group + MCB 6Amp. Dan Arde 224,500.00 Unit
116 Exchaust Fan D 30 cm + Acc 335,000.00 Unit
117 Roster Beton 12,000.00 Bh
118 Pemasangan Rostter Beton Dalam 1 M2 300,000.00 M2
119 Kloset Jongkok toto 456,000.00 Bh
120 Kloset Jongkok Ing/ Standar 245,000.00 Bh
121 Floor Drain 72,000.00 Bh
122 Karet Pelapis 7,500.00 m1
123 Kitchen Zink Bcp 475,000.00 Bh
124 Kitchen Zink 2 Lb 1,980,000.00 Bh
125 Kitchen Zink 870,000.00 Bh
126 Pipa Pvc AW Dia. 4" 22,500.00 m1
127 Pipa Pvc AW Dia. 2 1/2" 11,700.00 m1
128 Pipa Pvc AW Dia. 3" 14,500.00 m1
129 Pipa Dia. 1/2" 3,250.00 m1
130 Pipa Pvc Klas C Dia. 4" 33,000.00 m1
131 Pipa Pvc Klas C Dia. 6" 71,500.00 M'
132 Sambungan Pipa Pvc Dup Ulir 4 Dalam/ Clean Out Pvc 4" 40,000.00 Bh
No. Bahan - Bahan Harga ( Rp ) Satuan
133 Pipa Dia. 1" 37,250.00 m1
134 Knee Pvc AW 2 1/2" 15,000.00 Bh
135 Knee Pvc AW 4" 27,500.00 Bh
136 Tee Pvc AW 4" 27,900.00 Bh
137 Tempat Sabun Tanam Dari Keramik Panjang 20 cm 45,000.00 Bh
138 Paku Ulin 30,000.00 Kg
139 Alat Bantu 15,000.00 Unit
140 Skrup Dan Fixer 4"' 500.00 Bh
141 Plitur 15,000.00 Kg
142 Lambersiring 300,000.00 Lbr
143 Kusen Aluminium 4" 27,712.50 M'
144 Daun Pintu Spandri Aluminium Untuk Toilet 25,000.00 M2
145 Les pinggir / profil Kayu 15,000.00 M'
146 Hollow 40/40 mm Zincromate 50,000.00 Btg
147 Hollow 20/44 mm Zincromate 40,000.00 Btg
148 Skrup 3/4" 5,000.00 Kg
149 Lem Minyak 25,000.00 Kg
150 Lem Putih PVAC 15,000.00 Bks
151 Plyawood Lapis Aluminium Motif Kulit Jeruk 3.2 mm 160,000.00 Lbr
152 Gifsum Board 9 mm 47,000.00 Lbr
153 Gifsum Board 9 mm 47,000.00 Lbr
154 Calcyboard 3.2 mm 59,000.00 Lbr
155 Compound 50,000.00 Kg
156 Cotton plaster 8,500.00 Roll
157 Les pinggir / profil Dari Gifsum 7 - 12 cm Dan Pemasanganya 25,000.00 M'
158 Papan Listplank Calyboard 1.2 x 20 cm 93,000.00 Btg
159 Papan Listplank Calyboard 1.2 x 20 cm 15,500.00 M'
160 List Sudut Plafond PVC 15,400.00 Btg
161 Papan Plafon PVC 0.8 x 20 x 400 cm 60,000.00 Lbr
162 AirTawar 100.00 Ltr
163 Besi Wiremesh M8 100,000.00 M2
164 Besi Nako/ Besi Kotak 12 mm Panjang 4 m' 48,000.00 Btg
165 Besi Nako/ Besi Kotak 12 mm 12,000.00 M'
166 Kawat Kasa Aluminium 19,000.00 M2
167 Plat Streep 30 x 2 mm Panjang 6 m' 57,000.00 Btg
168 Plat Streep 30 x 2 mm 9,500.00 M;'
169 Kawat Las RD 30,500.00 Kg
170 Gorong Gorong Beton Diameter 100 cm Panjang 50 cm 365,000.00 Bh
171 Stop Kran Tee Stainless Untuk Kloset Duduk 35,000.00 Bh
172 Kran Air Dobel Shower 85,000.00 Bh
173 Kran Air Biasa 47,500.00 Bh
174 Kran Air Cucian Piring 55,000.00 Bh
175 Kran Hand Jet Shower 87,000.00 Bh
176 Gantungan Handuk Dari Bahan Stainless di Pintu 125,000.00 Bh
177 Kloset Duduk Standar Type Tabung CW 421 1,350,000.00 Unit
178 Profil Tank 1200 Ltr 1,424,000.00 Unit
179 Topi Pelindung (safety Helmet) 175,000.00 BH
180 Pelindung Pernapasan dan mulut (Masker) 175,000.00 Bh
181 Sarung Tangan (safety Gloves) 145,000.00 Psg
182 Sepatu Keselamatan (Safety Shoes) 250,000.00 Psg
183 Rompi Keselamatan (Safety Vest) 130,000.00 Psg
184 Kartu Identitas Pekerja ( KIP ) 150,000.00 Bh
185 Spanduk / Barner Himbauan Untuk Keselamataan 730,000.00 Roll
186 Rambu Peringatan 150,000.00 BH
187 BPJS Ketenaga Kerjaan ( Ansuransi Tenaga kerja Selama Berlangsung 50,000,000.00 Ls
188 Barikade / Pita Pengaman ( Do Not Cross ) 500,000.00 Bh
189 Peralatan P3K ( Obat Luka, Perban, Dll, Serta Kotak P3K ) 2,500,000.00 Ls
190 Petugas K3 3,500,000.00 Bl
UPAH KERJA

No. PEKERJA HARGA ( RP)

1 Pekerja Agak Terampil 95,000.00


2 Tukang Batu, Kayu, Besi 120,000.00
3 Kepala Tukang 120,000.00
4 Mandor 125,000.00
5 Operator 110,000.00
6 Mesin Las 50,000.00
7 Mesin Molen 80,000.00
8 Mesin Vibrator 110,000.00
9 Alat Bantu 10,000.00
TIME SCHEDULE

PEKERJAAN : REHABILITASI 3 UNIT RUMAH DIN


LOKASI : Jl. Ujang Dewa,Sedadap, Nunukan Se
TAHUN ANGGARA: 2021 M
A
S
BULAN I BULAN II BULAN III BULAN IV BULAN V BULAN VI A
No Uraian Pekerjaan Bobot KET
M1 M2 M3 M4 M5 M6 M7 M8 M9 M 10 M 11 M 12 M 13 M 14 M 15 M 16 M 17 M 18 M 19 M 20 M 21 M 22 KET
1 2 5 6 7 14 21 28 35 42 49 56 63 70 77 84 91 98 105 112 119 126 133 140 147 150
P
E
A PEKERJAAN PERSIAPAN Err:509 RENCANA Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
M
REALISASI
B PEKERJAAN STRUKTUR DAN PASANGAN
E
L
1 PEKERJAAN PONDASI Err:509 RENCANA Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 I
REALISASI H
2 PEKERJAAN BETON Err:509 RENCANA Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 A
REALISASI R
3 PEKERJAAN PASANGAN DAN PLESTERAN Err:509 RENCANA Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 A
REALISASI A
4 PEKERJAAN ATAP DAN PLAFOND Err:509 RENCANA Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
N
REALISASI
5 PEKERJAAN PENGECATAN Err:509 RENCANA Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
REALISASI
1
6 PEKERJAAN LANTAI DAN DINDING Err:509 RENCANA Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 8
REALISASI 0
7 PEKERJAAN PINTU, JENDELA DAN PENGGANTUNGNYA Err:509 RENCANA Err:509 Err:509
REALISASI H
8 PEKERJAAN PERALATAN SANITASI Err:509 RENCANA Err:509 Err:509 A
REALISASI R
9 PEKERJAAN MEKANIKAL DAN ELEKTRIKAL Err:509 RENCANA I
REALISASI Err:509 Err:509 Err:509 Err:509
10 PEKERJAAAN HALAMAN DAN SARANA LAINYA Err:509 RENCANA Err:509 Err:509 Err:509 Err:509
REALISASI
K
11 Err:509 Err:509 RENCANA Err:509 Err:509 Err:509 Err:509 A
Err:509 REALISASI L
RENCANA KEMAJUAN FISIK / MINGGUAN Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 E
RENCANA KOMULATIF KEMAJUAN FISIK / MINGGUAN 0 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 N
RENCANA KOMULATIF KEMAJUAN FISIK / BULAN Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 D
0% 1% 2% 2% 3% 7% 14% 21% 28% 36% 42% 50% 57% 64% 36% 42% 50% 57% 64% 57% 64% 57% 64% E
REALISASI KEMAJUAN FISIK / MINGGUAN R
REALISASI KOMULATIF KEMAJUAN FISIK / MINGGUAN
REALISASI KOMULATIF KEMAJUAN FISIK / BULAN

DEVIASI +/-

Jakarta, 15 Februari 2021

Penawar:
PT. PRATAMA CITRA KREASI

PT. PRATAMA CITRA KREASI


Direktur

Anda mungkin juga menyukai