JADWAL PELAKSANAAN

KEGIATAN : Perencanaan Rekonstruksi Rumah Negara Type E Pada KPP Pratama Kisaran
LOKASI : Kisaran
TAHUN ANGGARAN : 2021

BULAN I BULAN II BULAN III BULAN IV BULAN V


NO URAIAN PEKERJAAN Bobot KET
M1 M2 M3 M4 M5 M6 M7 M8 M9 M 10 M 11 M 12 M 13 M 14 M 15 M 16 M 17 KET
1 2 8 9 7 14 21 28 35 42 49 56 63 70 77 84 91 98 105 112 120
M
I PEKERJAAN PERSIAPAN 4,79% RENCANA 1,198% 1,198% 1,198% 1,198% A
REALISASI S
II PEKERJAAN PONDASI DAN BETON 24,38% RENCANA 4,064% 4,064% 4,064% 4,064% 4,064% 4,064% A
REALISASI
III PEKERJAAN PASANGAN DAN PLESTERAN 27,58% RENCANA 3,939% 3,939% 3,939% 3,939% 3,939% 3,939% 3,939% P
REALISASI E
IV PEKERJAAN LANTAI DAN DINDING 3,98% RENCANA 0,995% 0,995% 0,995% 0,995% M
REALISASI E
V PEKERJAAN ATAP 12,85% RENCANA 2,570% 2,570% 2,570% 2,570% 2,570% L
REALISASI I
VI PEKERJAAN PLAFOND 1,93% RENCANA 0,322% 0,322% 0,322% 0,322% 0,322% 0,322% H
REALISASI A
VII PEKERJAAN KOSEN, PINTU, DAN JENDELA 8,36% RENCANA 1,393% 1,393% 1,393% 1,393% 1,393% 1,393% R
REALISASI A
VIII PEKERJAAN SANITAIR 1,74% RENCANA 0,581% 0,581% 0,581% A
REALISASI N
IX INSTALASI AIR BERSIH, AIR BEKAS DAN AIR KOTOR 4,63% RENCANA 1,543% 1,543% 1,543%
REALISASI

(
X INSTALASI AIR BERSIH, AIR BEKAS DAN AIR KOTOR 3,39% RENCANA 1,129% 1,129% 1,129% 1
REALISASI 8
XI PEKERJAAN PENGECATAN 5,00% RENCANA 1,249% 1,249% 1,249% 1,249% 0
REALISASI
XII PEKERJAAN LAIN-LAIN 1,37% RENCANA 0,686% 0,686% H
REALISASI A
REALISASI R
JUMLAH 100,00% I
RENCANA KEMAJUAN FISIK / MINGGUAN 1,88% 5,95% 7,65% 7,65% 9,02% 13,28% 12,29% 8,22% 6,83% 4,26% 4,26% 3,94% 3,25% 4,50% 4,50% 1,25% 1,25%
RENCANA KOMULATIF KEMAJUAN FISIK / MINGGUAN 0 1,88% 7,83% 15,48% 23,13% 32,15% 45,44% 57,72% 65,95% 72,78% 77,04% 81,30% 85,24% 88,50% 93,00% 97,50% 98,75% 100,00% K
A
RENCANA KOMULATIF KEMAJUAN FISIK / BULAN 23,13% 65,95% 85,24% 98,75% 100,00%
L
0% 1% 2% 2% 3% 7% 14% 21% 28% 36% 42% 50% 57% E
REALISASI KEMAJUAN FISIK / MINGGUAN N
REALISASI KOMULATIF KEMAJUAN FISIK / MINGGUAN D
REALISASI KOMULATIF KEMAJUAN FISIK / BULAN E
R
DEVIASI +/-

)
Semarang, 21 Juni 2021