METODA PELAKSANAAN
Nama Pekerjaan : Pemeliharaan Beerkala Jembatan Kapuas I
Tahun 2016
JL. Tj Raya I
JL. Tritura
Jl. Pahlawan Jl. Perintis Kemerdekaan Jl. Perintis Kemerdekaan KE SEI. PINYUH
JL. Imam Bonjol
JL. Tj Raya II
KE TAYAN
Tampak bentang jembatan Tampak bentang jembatan Tampak Pilar Jembatan Tampak Bawah Lantai jembatan Tampak Bawah Lantai jembatan
INFORMASI UMUM :
1. Nama Paket = Pemeliharaan Berkala Jembatan Kapuas I
2. Sumber Dana = APBN TA. 2016
3. Jenis Kontrak = Tahunan
4. Target = 430 meter
5. Eksisting = - Jembatan Rangka Baja
- Panjang : 430 meter
- Lebar : 7,50 meter
- Bentang : 7
PROJECT DIRECTOR
Hadi Prawira
GENERAL SUPERINTENDENT
Muliawan, ST.
Pelaksana Pekerjaan
Gudang & Stock Opname
Perkuatan Jembatan
Bulan
DIVISI URAIAN PEKERJAAN Bobot (%)
1 2 3 4 5 6
7.489
1 Umum 1.25 1.25 1.25 1.25 1.25 1.25
2 Jalan Pendekat -
Rencana Bobot Bulanan 100.000 3.28 4.45 14.23 37.56 35.03 5.45
589 Mpa
1 Pekerjaan Umum
1. Pembuatan Kantor Lapangan
2. Pengadaan Perlengkapan Pengamanan & Pengaturan Lalu Lintas
3. Test Material
4. Pengadaan Peralatan Kerja
II Pekerjaan Struktur
1. Pemasangan Perancah / Lantai Kerja
2. Pekerjaan Perkuatan Struktur dengan Fiber Composit jenis karbon untuk
aplikasi daerah kering 589 MPa
I.1. PEMBUATAN KANTOR LAPANGAN/KONTRAK RUMAH SIAP HUNI
LOKASI
KANTOR
LAPANGAN
Pemasangan Spanduk
Pemasangan Rambu
Flagman
I.4. TEST MATERIAL
Test Material FRP
PERALATAN : 1. Genset
3. Hand Mixer
4. Gerinda tangan
5. Scrape/Cape, Sikat Kawat, Sikat Ijuk, dan alat bantu lainnya.
Pembersihan Perataan permukaan beton Priming
Plat Beton Yang akan di pasang Material Estowrap Di aduk dengan
Estowrap Elektric Hand MixerProses dilaburkannya
material yg telah di aduk
Aplikasi Resin Ke permukaan beton yang sdah di ratakan
Mix semua komponen Estowrap Resin dan bersih
Base Agent dan Hardrner dengan
mixer selama 3 mnt
Aplikasikan ke permukaan
dengan roll atau kuas dengan rata Aplikasi Polyurethane Paint
Setelah pelapisan selesai lanjutkan
Aplikasi Serat Karbon dengan Acrylic polymer sebagai tahap
Retakkan FRP Carbon diatas akhir pekerjaan dengan tujuan
permukaan Est Resin dan tekan memerikan perlindungan terhadap
dengan roll hingga melekat sempurna cuacadan paparan Ultra Violet
Ratakan resin yang menembus
anyaman sert dengan spatula
(tidak disarankan menggukana Pembersihan
material berbahan metal) Bersihkan semua sisa material dan
sampah kotoran pekerjaan di lokasi
kerja, dan dibuang di tempet yg sudah
SELESAI di tentukan
1. Marking Keretakan 2. Pasang Injektor 3. Pasang Bahan Penutup (Sealant)
Primer
Resin
Installation Flow
Surface Preparation
& Surface Repair
Primer Application
Finish Coating
Surface Preparation
◆ Objective
- Strong Surface
- Smooth Surface
◆ Procedure
- Remove the deteriorated surface of the concrete
- Make a smooth surface : Surface differentiation < 1mm
R
Surface Preparation
• Chipping the Deteriorated Concrete
Surface Preparation
• Surface Grinding by Hand Grinder
Surface Preparation
- Grind a sharp corner : Radius > 10mm
◆ Procedure
- Confirm the condition : RH < 85%, Temperature > 5℃
- Mix the primer using an electric hand mixer (Resin:Hardener = 2:1)
- Apply the primer uniformly : 250g/m2
- Curing
Primer Application
• Weighing ; Resin:Hardener = 2:1
Primer Application
• Mix the primer by an electric hand mixer
Primer Application
• Coating Amount : 250g/m2
Primer Application
Primer Application
• Checking of Curing State
Application of Carbon Sheet
• Preparation
- Confirm the condition : RH < 85%, Temperature > 5℃
- Mark the application surface
Application of Carbon Sheet
• Preparation
- Cut the carbon fiber sheet : Usually in 3∼4m
Application of Carbon Sheet
• Undercoat
- Mixing (Resin:Hardener = 2:1)
Application of Carbon Sheet
• Undercoat
Application of Carbon Sheet
- Apply the pre-cut carbon sheet by a rubber or plastic scraper
Application of Carbon Sheet
• Impregnation ; Impregnate the carbon sheet with applied
undercoat resin by an impregnation roller
Application of Carbon Sheet
• Impregnation
SHEET
Impregnation Direction
SHEET
SHEET
Application of Carbon Sheet
- Overlap in excess of 10cm on top and bottom edges (longitudinally)
- Overlap is not required on the sides
Finish Coating
• Curing
- Complete cure times of resins are as follows ;
Estowrap Encapsulation Resin : 30℃ = 7 days
• Finish Coating
- Finish surface with urethane or fluorine paint
after curing of resins
SASARAN : TEPAT MUTU – TEPAT WAKTU – TEPAT BIAYA
Pengajuan Sampel
Material : No
- Sertifikat pabrik
- Brosur Spesifikasi
Evaluasi Oleh
KONSULTAN
Yes
Test Laboratorium
No Material On Site
Evaluasi oleh
KONSULTAN
No
Yes Evaluasi oleh
PURCHASING ORDER KONSULTAN
Yes
Transport ke Site
Material Siap
Digunakan
Persiapan & Pengecekan
Peralatan di Gudang
No
Yes
Yes
No
Diperiksa oleh
KONSULTAN
Yes
PENGAJUAN REQUEST
Tidak
OKE
Ya
PEKERJAAN DILAKSANAKAN DGN DIAWASI
KONSULTAN
DITERIMA
Tidak
Ya Catan & Masukkan
ke Sistem
Verifikasi (NK-13) Dokumentasi File
untuk Back Up
Laporan Data MC
END
1. Menjaga Keselamatan Kerja dan Kesehatan Lingkungan Kerja
2. Menjamin Produktifitas Kerja Tidak Terganggu
3. Menuju Kondisi Nol Kecelakaan Fatal ( Zero Accident )
SHE PLAN TARGET : PEKERJA BARU SETIAP KAMIS -SHE PATROL SETIAP - DASAR2 K3 - LINGKUNGAN 3 BULAN
ZERO - PERUSAHAAN JAM 08.00 WIB SETIAP HARI SELASA -P3K KERJA BERSIH, SEKALI
ACCIDENT - SUBKON -INSPEKSI K3 JAM 09.00 - PMADAMAN API RAPI & SEHAT.
- MANDOR SETIAP KAMIS WIB - TANGGAP - PEMBERSIHAN
( MINGGUAN) DARURAT MASAL SETIAP
JUM’AT ( RUTIN )