TOTAL A Rp 204.521.340
1/1
BQ RENCANA ANGGARAN BIAYA
PROYEK : REHAB GEDUNG PANCASILA ( EX. RUANG TU & BIDANG )
LOKASI : JL. RAYA PARUNG - CIPUTAT KM. 19 DEPOK - JAWA BARAT
B. PEKERJAAN : INTERIOR DAN BUILD IN FURNITURE
> Tipe Coating ex. Sika Top/Fosroc + serat fiber + screeding termasuk test rendam 3x24 jam
Sub. Total Rp 33.583.832
3 Pekerjaan Beton
1 Pekerjaan Beton Kolom Praktis 15x15cm
Beton Site Mix, Pengering + sewa alat & upah, sertara K. 225 m³ 0,54 Rp 1.016.715 Rp 549.026
Besi polos 4 D 10 kg 59,20 Rp 9.781 Rp 579.016
Besi polos Ø 8 - 200 kg 23,70 Rp 9.781 Rp 231.802
Pekerjaan Bekisting m² 24,00 Rp 287.278 Rp 6.894.666
1/7
BQ RENCANA ANGGARAN BIAYA
PROYEK : REHAB GEDUNG PANCASILA ( EX. RUANG TU & BIDANG )
LOKASI : JL. RAYA PARUNG - CIPUTAT KM. 19 DEPOK - JAWA BARAT
B. PEKERJAAN : INTERIOR DAN BUILD IN FURNITURE
2/7
BQ RENCANA ANGGARAN BIAYA
PROYEK : REHAB GEDUNG PANCASILA ( EX. RUANG TU & BIDANG )
LOKASI : JL. RAYA PARUNG - CIPUTAT KM. 19 DEPOK - JAWA BARAT
B. PEKERJAAN : INTERIOR DAN BUILD IN FURNITURE
- alumunium shopfront 4" finish powder coating hitam merk setara YKK
> kaca polos 6mm ( existing )
> sticker sandblas
3/7
BQ RENCANA ANGGARAN BIAYA
PROYEK : REHAB GEDUNG PANCASILA ( EX. RUANG TU & BIDANG )
LOKASI : JL. RAYA PARUNG - CIPUTAT KM. 19 DEPOK - JAWA BARAT
B. PEKERJAAN : INTERIOR DAN BUILD IN FURNITURE
TOTAL I Rp 583.016.773
II PEKERJAAN INTERIOR LANTAI BASEMENT
1 Pekerjaan Pembongkaran
- Bongkar lantai keramik existing termasuk adukan m² 18,20 Rp 22.660 Rp 412.412
- Bongkar dinding bata existing m² 94,20 Rp 21.609 Rp 2.035.594
- Bongkar dinding keramik existing m² 35,20 Rp 22.660 Rp 797.632
- Bongkar partisi gypsum 2 muka existing m² 65,70 Rp 12.267 Rp 805.955
- Bongkar partisi gypsum 1 muka existing m² 41,20 Rp 12.267 Rp 505.409
- Bongkar panel kayu existing ( termasuk plint dan list/ban) m² 38,60 Rp 12.267 Rp 473.514
- Bongkar plafond existing (termasuk rangka) m² 297,90 Rp 22.725 Rp 6.769.813
- Bongkar pintu double (kusen, daun pintu dan asesories) bh 4,00 Rp 35.000 Rp 140.000
- Bongkar pintu single (kusen, daun pintu dan asesories) bh 6,00 Rp 35.000 Rp 210.000
- Bongkar jendela (kusen, daun jendela dan asesories) bh 4,00 Rp 35.000 Rp 140.000
- Bongkar vertikal blind/curtain existing m² 21,10 Rp 12.267 Rp 258.838
- bongkar closet existing set 1,00 Rp 450.000 Rp 450.000
- bongkar shower existing set 1,00 Rp 300.000 Rp 300.000
- bongkar keran existing set 1,00 Rp 120.000 Rp 120.000
- bongkar floordrain existing set 1,00 Rp 120.000 Rp 120.000
- bongkar wastafel + meja existing set 1,00 Rp 450.000 Rp 450.000
- bongkar cermin existing set 1,00 Rp 120.000 Rp 120.000
- kerok cat existing m² 245,80 Rp 12.535 Rp 3.081.034
> sampai terlihat acian dinding existing
Sub. Total Rp 17.190.201
2 Pekerjaan finishing lantai
L1 - Pengadaan dan pemasangan parquete m² 22,50 Rp 146.126 Rp 3.287.832
> material parquete merk. Setara GBU Floring tipe Ufloor W18RC
L2 - Pengadaan dan pemasangan karpet tile m² 32,50 Rp 337.946 Rp 10.983.258
> material kapet tile 50x50 cm merk. Setara SMJ tipe City Blocks SQ (CYA17402SKY ACCENT)
L3 - Pengadaan dan pemasangan homogeneous tile 60x60 cm m² 12,70 Rp 239.997 Rp 3.047.967
> material homogeneous tile 60x60 cm merk. Setara Sandimas tipe Calvin ( matt )
L5 - Pengadaan dan pemasangan ubin teraso sesuai existing (perbaikan lantai akibat bongkaran) m² 14,10 Rp 247.049 Rp 3.483.394
L6 - Pengadaan dan pemasangan ubin teraso hitam ( border ) uk. 20x20cm m² 6,40 Rp 200.026 Rp 1.280.164
- Pengadaan dan pemasangan assesories kayu/list ( adaptasi, transisi ) m' 5,60 Rp 70.576 Rp 395.226
> material PVCex. GBU Flooring
- Pengadaan dan pemasangan waterproofing m² 13,97 Rp 133.670 Rp 1.867.373
> Tipe Coating ex. Sika Top/Fosroc + serat fiber + screeding termasuk test rendam 3x24 jam
Sub. Total Rp 24.345.213
3 Pekerjaan Beton
Pekerjaan Beton Kolom Praktis 15x15cm
Beton Site Mix, Pengering + sewa alat & upah m³ 0,27 Rp 1.016.715 Rp 274.513
4/7
BQ RENCANA ANGGARAN BIAYA
PROYEK : REHAB GEDUNG PANCASILA ( EX. RUANG TU & BIDANG )
LOKASI : JL. RAYA PARUNG - CIPUTAT KM. 19 DEPOK - JAWA BARAT
B. PEKERJAAN : INTERIOR DAN BUILD IN FURNITURE
5/7
BQ RENCANA ANGGARAN BIAYA
PROYEK : REHAB GEDUNG PANCASILA ( EX. RUANG TU & BIDANG )
LOKASI : JL. RAYA PARUNG - CIPUTAT KM. 19 DEPOK - JAWA BARAT
B. PEKERJAAN : INTERIOR DAN BUILD IN FURNITURE
a. Kusen
- alumunium shopfront 4" finish powder coating hitam merk setara YKK
b. Daun pintu (double)
- Rangka kayu solid
- Plywood 4mm
- Finish HPL merk. Splendor
- Edging PVC
- Rockwool
c. Hardware dan asesories
> Handle Dekkson LHTR 0003 SSS
> Mortise Lock Dekkson MTS IL DL8585 SSS
> Cylinder Dekkson CYL DC DL60MM SN
> Hinge Dekkson ESS DL 4X3X3MM 2BB SSS
> Door Closer Dekkson DCL 300 NHO NA
6/7
BQ RENCANA ANGGARAN BIAYA
PROYEK : REHAB GEDUNG PANCASILA ( EX. RUANG TU & BIDANG )
LOKASI : JL. RAYA PARUNG - CIPUTAT KM. 19 DEPOK - JAWA BARAT
B. PEKERJAAN : INTERIOR DAN BUILD IN FURNITURE
TOTAL II Rp 345.758.677
TOTAL B = I + II Rp 928.775.450
7/7
BQ RENCANA ANGGARAN BIAYA
PROYEK : REHAB GEDUNG PANCASILA ( EX. RUANG TU & BIDANG )
LOKASI : JL. RAYA PARUNG - CIPUTAT KM. 19 DEPOK - JAWA BARAT
C. PEKERJAAN : MEKANIKAL DAN ELEKTRIKAL
A PEKERJAAN LANTAI 1
A.1 PEKERJAAN BONGKARAN
1 Pembongkaran armarture lampu, saklar, stop kontak dan armarture lain 1 ls Rp 416.667 Rp 416.667
2 Pembongkaran armarture elektronik ( Speaker, Fire alarm, Router, CCTV ) 1 ls Rp 416.667 Rp 416.667
3 Pembongkaran panel-panel listrik dan elektronik 1 ls Rp 416.667 Rp 416.667
4 Pembongkaran jalur instalasi titik lampu, data, telepon dll 1 ls Rp 416.667 Rp 416.667
5 Pembongkaran jalur instalasi kabel feeder 1 ls Rp 416.667 Rp 416.667
6 Pembongkaran unit AC dan instalasinya 1 ls Rp 416.667 Rp 416.667
1 Instalasi titik lampu penerangan (ex. Kabel 4 besar dalam pipa conduit hight impact) 176 titik Rp 90.351 Rp 15.901.839
3 Saklar Multi 4 Gang White Neo Vertical + Komplit dgn Aksesories ex. Schneider/ setara 5 bh Rp 166.584 Rp 832.920
1/3
BQ RENCANA ANGGARAN BIAYA
PROYEK : REHAB GEDUNG PANCASILA ( EX. RUANG TU & BIDANG )
LOKASI : JL. RAYA PARUNG - CIPUTAT KM. 19 DEPOK - JAWA BARAT
C. PEKERJAAN : MEKANIKAL DAN ELEKTRIKAL
Instalasi pemipaan AC
Instalasi pemipaan refrigerant unit AC Split Wall 3/4 - 1 pk lengkap dgn isolasi dan
1 168 m' Rp 56.468 Rp 9.486.597
fittingnya
Instalasi pemipaan refrigerant unit AC Ceilling Cassette 2 - 3 pk lengkap dgn isolasi dan
2 184 m' Rp 56.468 Rp 10.390.083
fittingnya
3 Instalasi pemipaan drain AC pipa PVC AW lengkap dgn isolasi dan fittingnya 84 m' Rp 56.468 Rp 4.743.299
4 Instalasi kabel power dan kontrol indoor unit 9 titik Rp 86.328 Rp 776.952
5 Material bantu 1 lot Rp 153.439 Rp 153.439
2/3
BQ RENCANA ANGGARAN BIAYA
PROYEK : REHAB GEDUNG PANCASILA ( EX. RUANG TU & BIDANG )
LOKASI : JL. RAYA PARUNG - CIPUTAT KM. 19 DEPOK - JAWA BARAT
C. PEKERJAAN : MEKANIKAL DAN ELEKTRIKAL
Instalasi titik lampu penerangan, kabel NYM 3x2,5mm ex. Kabelindo, Kabel Metal,
1 82 titik Rp 90.351 Rp 7.408.812
Supreme
2 Material bantu 1 lot Rp 54.211 Rp 54.211
3 Saklar Multi 4 Gang White Neo Vertical + Komplit dgn Aksesories ex. Schneider/ setara 1 bh Rp 166.584 Rp 166.584
b Instalasi pemipaan AC
Instalasi pemipaan refrigerant unit AC Split Wall 3/4 - 1 pk lengkap dgn isolasi dan
1 144 m' Rp 56.468 Rp 8.131.369
fittingnya
Instalasi pemipaan refrigerant unit AC Ceilling Cassette 2 - 3 pk lengkap dgn isolasi dan
2 42 m' Rp 56.468 Rp 2.371.649
fittingnya
3 Instalasi pemipaan drain AC pipa PVC AW lengkap dgn isolasi dan fittingnya 174 m' Rp 56.468 Rp 9.825.404
4 Instalasi kabel power dan kontrol indoor unit 16 titik Rp 86.328 Rp 1.381.248
5 Material bantu 1 lot Rp 153.439 Rp 153.439
TOTAL C Rp 497.868.113
3/3